Material Delivery Inspection Register

Project: Sibiyu 132/33 kV Substation Project


Owner: Sarawak Energy Berhad Updated
(as of): 25/03/2019
Contract No.: PLS-150129
CONTRACTOR Pestech Sdn Bhd

Delivery Inspection Description of


No. D/O No. Supplier Manufacturer Quantity Delivered Inspection Status Remarks
Date Date Material / Product

Chiew Brothers
MDI/001 3/18/2019 3/19/2019 27511 Hoarding Material/ GI Purlin C10025 Lysaght 85 Pass
Hardware

Chiew Brothers
MDI/002 3/23/2019 3/23/2019 27529 Hoarding Material/ Lysaght Trimdeck Lysaght 100 Pass
Hardware

RC Pile 200x200x6m (8T10) X-shoe and RC Pile 200x200x6m FJ Concrete & Piles FJ Concrete & Piles 4 nos x Starter Piles
MDI/003 3/24/2019 4/23/2019 D60077 8 Pass
(8T10) Extension Sdn Bhd Sdn Bhd 4 nos x Extension Piles

Ultrapower Industrial
MDI/004 3/30/2019 4/30/2019 544 Nippon Zinc Chromate Primer Nippon Paint 1 Pass
Supplies S/B
RC Pile 200x200x6m (8T10) X-shoe and RC Pile 200x200x6m FJ Concrete & Piles FJ Concrete & Piles 1 nos x Starter Piles
MDI/005 5/17/2019 5/18/2019 2 Pass
14264 (8T10) Extension Sdn Bhd Sdn Bhd 1 nos x Extension Piles

Page 1 of 2
Form. No.: 017-F024-2667
Request for Inspection Notice (RFIN) Register - SUMMARY STATUS Revision: :1
Date: 19-Jun-15
Provision of Procurement and Construction for the Proposed New LNG Jetty (Berth 4) at Bintulu Port, Sarawak
Project:
Updated (as
of): 27/06/2019
Owner: PETRONAS LNG 9 Sdn Bhd
CONTRACTOR SYS-MCD Joint Venture

2015 2016

RFIN Previous January February March April May June July August September October November December TOTAL

ISSUED 86 14 23 62 11
196

CLOSED 86 14 23 62 10
195
OPEN 0 0 0 0 1 1

Page 2 of 2