OTAWAY GLOBAL RESOURCES

PROJECT TITLE: PIPING MODIFICATION FOR BARGING JUMPER


LINE-UPS

DOCUMENT TITLE: WORK SCHEDULE


DOCUMENT NUMBER N/A
ID Task Task Name Duration Start Finish Feb 18, '19 Feb 25, '19 Mar 4, '19
Mode M T W T F S S M T W T F S S M T W T F
1 Piping Modification 10.25 days? Wed Wed 3/6/19
for Barging Jumper 2/20/19
Line-UPS
2 Preliminary Activities
1.75 days Wed 2/20/19Thu 2/21/19
3 Review of 4 hrs Wed Wed
Contract 2/20/19 2/20/19
4 Documents of 6 hrs
Procurement Wed Thu 2/21/19
Materials 2/20/19
5 Inspection of Materials
1 hr Thu 2/21/19 Thu 2/21/19
6 Premobilization 3 hrs Thu 2/21/19 Thu 2/21/19
of Personnel
and Equipment
7 Job Execution 5 days Thu 2/21/19 Thu 2/28/19
8 Onshore Activities5 days Thu 2/21/19 Thu 2/28/19
9 Fabrication of 3 days Thu 2/21/19 Tue 2/26/19
Spools/Radigraphy
10 Hydro Testing 1 day Tue 2/26/19 Wed
of 2/27/19
11 Pipes/Spools 4 hrs
Media Wed Thu 2/28/19
Blasting of 2/27/19
12 The
Painting 4 hrs Thu 2/28/19 Thu 2/28/19
13 Offshore Activities 2.5 days Thu 2/28/19 Tue 3/5/19

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: OTAWAY GLOBAL RESO
Summary Manual Summary Rollup Progress
Date: Thu 2/21/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Task Name Duration Start Finish Feb 18, '19 Feb 25, '19 Mar 4, '19
Mode M T W T F S S M T W T F S S M T W T F
14 Mobilization of 3 hrs Thu 2/28/19 Fri 3/1/19
Equipment,
Personnel and
Materials to
15 Offshore
HSE Site
Induction/ 1 hr Fri 3/1/19 Fri 3/1/19
Raising of Work
16 Permit
Installation of 1 day Fri 3/1/19 Mon 3/4/19
the Fabricated
17 Spools
Excavation for 4 hrs Mon 3/4/19 Mon 3/4/19
Pipe support
18 Base of Pipe 4 hrs
Casting Mon 3/4/19 Tue 3/5/19
Support Base
19 Installation of 1 day Fri 3/1/19 Mon 3/4/19
Golden Weld
20 Joint Out Activities
Closing 1 day Tue 3/5/19 Wed 3/6/19
21 Signing of Job 2 hrs Tue 3/5/19 Tue 3/5/19
Completion
22 Certificate
House Keeping 3 hrs Tue 3/5/19 Tue 3/5/19
23 Demobilization 3 hrs Tue 3/5/19 Wed 3/6/19

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: OTAWAY GLOBAL RESO
Summary Manual Summary Rollup Progress
Date: Thu 2/21/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only