Responsibility Matrix for Design and Construction Projects

Campus Finance/Facilities

Construction Contractor
Director of Construction

Program Manager (SO)

Specialty Consultants
Chancellor, Facilities

C/U Project Manager


Associate Vice

C/U President

Owner's Rep
Delegated
Officer
(OOC)

(SO)

A/E
Notes/Comments

Project Initiation and A/E Selection


Delegation Letter A I L Approved by Vice Chancellor-Chief Financial Officer
Program Schedule A A R/R I I L
Program Budget A A R/R I I L
A/E RFP I I R/R I L
A/E Selection A I L I I
A/E Contract A I R/R I L A
Owner's Representative Selection
OR RFP A R/R R/R I A
OR Selection A A A R/R I A
OR Contract A A A R/R I A A

Schematic Design Phase


Design Kickoff Meeting I R/R L I I I I
Project Schedule I R/R A L R/R Deviations need approval
Project Budget I R/R R/R L, A I I Deviations need approval
Code Approvals I L I Approval at either the state or local county/city office
Surveys (Hazardous, Geotechnical, etc.) I L I I I
Schematic Design options I A L I I
FF&E I L, A I I I
Value Engineering/Constructability Review I R/R L I I
Schematic Design Phase Reporting R/R R/R A L I I Including required B3 reporting
Schematic Design Submittal A R/R R/R R/R R/R L I I Approved by Vice Chancellor-Chief Financial Officer
Schematic Design Review R/R R/R R/R R/R L

Design Development Phase


Project Schedule I R/R I A L I Deviations need approval
Project Budget I R/R R/R I L, A I I Deviations need approval
Design Development Phase Reporting I R/R A L I I
Design Development Phase Submittal R/R R/R L I I
Design Development Review R/R R/R R/R A I R/R I

Construction Documents Phase


Project Schedule A R/R I A L I Deviations need approval
Project Budget A R/R R/R A I I Deviations need approval
Construction Documents Phase Reporting A I L I I I
Construction Documents Phase Submittal R/R R/R L I I
Construction Document Review R/R R/R R/R R/R L R/R I

Rev. 5/7/2012 Page 1 of 2


Responsibility Matrix for Design and Construction Projects

Campus Finance/Facilities

Construction Contractor
Director of Construction

Program Manager (SO)

Specialty Consultants
Chancellor, Facilities

C/U Project Manager


Associate Vice

C/U President

Owner's Rep
Delegated
Officer
(OOC)

(SO)

A/E
Notes/Comments

Bidding and Award Phase


Advertisement for Bid I A L I
Respond to Questions I I L I
Review of Bids/Recommend Award I R/R L I
Bidding and Award Phase Reporting R/R A L I
Contract Award R/R I A R/R I A

Construction
Pre-Construction Meeting I I A L I I I
Construction Schedule I A R/R I I L Deviations need approval
Construction Progress Meetings I I L I I I
Construction Observation I L I I I
Construction Phase Reporting R/R R/R L I I I Architects' field reports
Pay Requests I A R/R R/R L
Change Orders I A L R/R I
Commissioning I I I A I I Specialty consultant is commissioning agent
Substantial Completion I A R/R I R/R L

Closeout
Punchlist Items I I A I R/R L
Final Completion I A R/R I R/R L
Close Out I A R/R I R/R L
Warrantee/Guarantee Management I L I I I I

Post Occupancy Evaluation


Post Occupancy Evaluations A I R/R L I R/R R/R R/R R/R As required by system office

A = Approval Authority
L = Lead Responsible party
R/R = Review & Recommend
I = Provides Input

Rev. 5/7/2012 Page 2 of 2