Environmental

Engineering
Lydia
Pre-treatment
1. SEPARATE 2. AVOID DAMAGE
Separate contaminants. Contaminants will damage
other equipment.
*pumps
*valves

2
Screening

3
Assumptions
Approach velocity, Inclination Peak Factor
va
60˚ 2.5
0.6 m/s

Manually Cleaned Efficient D:W Ratio Source


Screen
1.5
Elbeshbishy, 2016
Zaher. nd

4
Design
Area available for D W
flow
0.51 m 0.34 m
0.15 m2
S=3 cm

Anet=0.15 m2
No of bars in the
screen, n

8
Tbar= 1 cm
5
Grit Chamber

6
Assumptions

Horizontal flow Flow through Settling velocity, vt


velocity, vh
grit chamber
0.02 m/s
0.3 m/s

Ratio Source
Depth is 1.5 times Christian, 2006
the width Zaher. nd

7
Design
Area Dimensions Volume

0.35 m2 L = 10.8 m V=3.73 m3


D = 0.72 m
W = 0.48 m
Detention time, td
36 s