Schedule Electrical Work (Amber Electrotech.Ltd.

A) Target action plan


Hospital Block Medical College
S.no Floor Light&,Fan Light&,Fan
Conduting Wiring Conduting Wiring
installation installation
22/06/2019 30/06/2019 7/7/2019 N.A N.A N.A
1) Basement
2) Ground Floor 19/06/2019 28/06/2019 30/06/2019 17/06/2019 28/06/2019 30/06/2019
3) First Floor 20/06/2019 28/06/2019 30/06/2019 16/06/2019 27/06/2019 30/06/2019
4) Second Floor 26/06/2019 6/7/2019 10/7/2019 20/06/2019 28/06/2019 30/06/2019
5) Third Floor 3/7/2019 13/07/2019 15/07/2019
6) Fourth Floor 11/7/2019 13/07/2019 15/07/2019

B) Major Electrical Item procured


M.V Items L.V Items
1) Light Fixture 1) CCTV Camera
2) Distribution Board 2) Cat 5A Cable
3) M.C.B 3) Power & Control Cables
4)IDigital Video Management System
C) Major Electrical Item to be procured
M.V Items L.V Items
1) Wires 1)19 inck rack mount console unit
2) Fans
3) M.V Panel
4) Earthing Materials
5) Cables
6) Switches & Sockets
7) Lightning Arrester
8) Light fixtures for service area &Toilets.