TASK 52-73-12-000-001-A
Removal of the Cabin-Pressure Detection Pressure-Switch
WARNING: PUT THE SAFETY DEVICES AND THE WARNING NOTICES IN POSITION BEFORE YOU
START A TASK ON OR NEAR:
- THE FLIGHT CONTROLS
- THE FLIGHT CONTROL SURFACES
- THE LANDING GEAR AND THE RELATED DOORS
- COMPONENTS THAT MOVE.
MOVEMENT OF COMPONENTS CAN KILL OR CAUSE INJURY TO PERSONS AND/OR CAN
CAUSE DAMAGE TO THE EQUIPMENT.
FIN : 14WN
1. Reason for the Job
Self explanatory
2 Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
C. Referenced Information
REFERENCE DESIGNATION
(Ref. 24-42-00-861-001-A). Energize the Ground Service Network from the External Power
Cabin Pressure Detection Pressure Switch - (14WN) SHEET 1
14WN
FR2
DOOR 811
FR1 A 8
7
3
2
1
2
4
3
N_MM_527312_4_AAM0_01_00
Figure 52-73-12-991-00100-00-A / SHEET 1/1 - Cabin Pressure Detection Pressure Switch - (14WN)
** ON A/C ALL
3. Job Set-up
Subtask 52-73-12-860-050-A
A. Aircraft Maintenance Configuration
(1) Energize the ground service network
(Ref. AMM TASK 24-42-00-861-001)
Subtask 52-73-12-865-050-A
B. Open, safety and tag this(these) circuit breaker(s):
TASK 52-73-12-400-001-A
Installation of the Cabin-Pressure Detection Pressure-Switch
FIN : 14WN
1. Reason for the Job
Self explanatory
2 Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
C. Expendable Parts
D. Referenced Information
REFERENCE DESIGNATION
(Ref. 24-42-00-861-001-A). Energize the Ground Service Network from the External Power
(Ref. 24-42-00-862-001-A). De-energize the Ground Service Network Supplied from the External
Power
(Ref. 34-22-25-790-001-A). Low range Leak Test of the Standby Pneumatic circuits
(Ref. 52-73-00-720-003-A). Operational Test of the Residual Cabin Pressure Warning System
and In-Situ Functional Test of the Cabin Pressure Detection Pres-
sure-Switch
Cabin Pressure Detection Pressure Switch - (14WN) SHEET 1
3. Job Set-up
Subtask 52-73-12-860-051-A
A. Aircraft Maintenance Configuration
(1) Make sure that the access door 811 is open, and that the access platform is in position.
(2) Make sure that the ground service network is energized (Ref. AMM TASK 24-42-00-861-001) .
Subtask 52-73-12-865-051-A
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
(2) Install the IPC -CSN (52-73-01-02-030) O-ring (6) or IPC -CSN (52-73-81-02-030) O-ring (6) on the
restrictor (7).
(3) Install the restrictor (7) on the pressure switch (5) and tighten it.
(4) TORQUE the restrictor (7) to between 0.36 and 0.40 m.daN (31.86 and 35.40 lbf.in).
(5) Remove the PLUG - BLANKING from the calibrated plug hole (1).
(6) Install the calibrated plug (1) on the pressure switch (5) and tighten it.
(7) Put the pressure switch (5) in position on its support.
(8) Install the bolts (3) and the washers (2) and tighten the bolts.
(9) Install the line (8) on the restrictor (7).
(10) TORQUE the line (8).
CAUTION: USE A SECOND WRENCH TO HOLD THE MATING PARTS WHEN YOU LOOSEN
OR TIGHTEN THE TUBE OR HOSE NUTS. IF YOU DO NOT OBEY THIS CAUTION,
YOU CAN TWIST OR CAUSE DAMAGE TO THE TUBES OR HOSES.
(a) TORQUE the line (8) to between 0.695 and 0.705 m.daN (61.50 and 62.39 lbf.in).
(11) Remove the CAP - BLANKING from the electrical connector (4).
(12) Connect the electrical connector (4) to the pressure switch (5).
Subtask 52-73-12-720-050-B
B. Functional Test
(1) Do the in-situ functional test of the pressure switch (14WN) (Ref. AMM TASK 52-73-00-720-003) .
(2) Do the low range leak test of standby pneumatic circuits (Ref. AMM TASK 34-22-25-790-001) .
5. Close-up
Subtask 52-73-12-865-052-A
A. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):