Professional Documents
Culture Documents
Estimate For Change Oder Hitoma
Estimate For Change Oder Hitoma
Labor : 16 days
construction foreman day 14 380.00 5,320.00
1 skilled laborer day 15 350.00 5,250.00
5 laborers day 64 220.00 14,080.00
Labor Cost 24,650.00
Total Direct Cost 24,650.00
OCM 2,465.00
Profit 2,465.00
Tax 2,958.00
Item Total 32,538.00
XII. EXTENSION OF PROPOSED BHS( re usable const materials were used to the new BHS)
4" CHB pcs 500 11.00 5,500.00
Portland cement bag 45 250.00 11,250.00
Washed sand cu.m 5 500.00 2,500.00
0.40 X 0.40 glazed tiles pc 200 80.00 16,000.00
#16 GI tie wire kg 5 80.00 400.00
Material Cost 35,650.00
Labor Cost 12,477.50
Total Direct Cost 48,127.50
OCM 4,812.75
Profit 4,812.75
Tax 5,973.00
Item Total 63,726.00
prepared by:
SALVE VERA
Munucipal Engineer
X . Repair on existing BHS
ORIGINAL NEW
item No Description QUANTITY UNIT UNIT COST AMOUNT QUANTITY UNIT UNIT COST AMOUNT
I EXCAVATION FOR STRUCTURE LS 5,438.40 LS 5,438.40
II CONCRETE WORKS LS 441,045.00 LS 441,045.00
III MASONRY WORKS LS 166,438.80 LS 166,438.80
IV TILE WORKS LS 124,918.20 LS 124,918.20
V ROOF AND ROOF FRAMING LS 402,963.66 LS 402,963.66
VI PAINTING LS 123,759.90 LS 123,759.90
VII PLUMBING WORKS LS 157,787.19 LS 157,787.19
VIII DOORS AND WINDOWS LS 267,977.16 LS 267,977.16
IX ELECTRICAL WORKS LS 122,191.74 LS 122,191.74
X REPAIR OF EXISTING BHS LS 220,736.34
X CONCRETE GUTTER LS 124,472.70
XI DEMOLITION OF EXISTING BHS LS 32,538.00
XII EXTENSION OF PROPOSED BHS LS 63,726.00
2,033,256.39 2,033,256.75
PREPARED BY: Reviewed by: Submitted By: