The document outlines a project plan and schedule with 15 activities including planning, feasibility analysis, requirements capture, design, coding, testing, training and review. Activity A of planning the project occurs first with a duration of 4 days. Subsequent activities like feasibility analysis, questionnaires, interviews and requirements capture depend on preceding tasks in the schedule.
The document outlines a project plan and schedule with 15 activities including planning, feasibility analysis, requirements capture, design, coding, testing, training and review. Activity A of planning the project occurs first with a duration of 4 days. Subsequent activities like feasibility analysis, questionnaires, interviews and requirements capture depend on preceding tasks in the schedule.
The document outlines a project plan and schedule with 15 activities including planning, feasibility analysis, requirements capture, design, coding, testing, training and review. Activity A of planning the project occurs first with a duration of 4 days. Subsequent activities like feasibility analysis, questionnaires, interviews and requirements capture depend on preceding tasks in the schedule.
No Activities Name Duration(day) Preceding Activities
A Plan Project 4 - B Feasibility Analysis 6 A C Questionnaire 4 B D Interview 4 B E System Requirement Capture 6 C,D F Input and Output Design 10 E G Interface Design 5 E H File Design 8 E I Coding 30 F,G,H J Install system 3 I K Integration 5 J L File Conversion 4 J M System Testing 6 K,L N User Training 5 M O Review 5 N 5.2 PERT Chart