Professional Documents
Culture Documents
Nyamagasani 1 Design Review (Detailed Design) - GEOTECHNICS - Rev - E
Nyamagasani 1 Design Review (Detailed Design) - GEOTECHNICS - Rev - E
Nyamagasani 1 Design Review (Detailed Design) - GEOTECHNICS - Rev - E
Page 1 of 16
Nyamagasani 1 Hydropower Project, Uganda, 2208521A
Detailed Design Review GEOTECHNICS Rev E 20-Jun-2019
Page 2 of 16
Nyamagasani 1 Hydropower Project, Uganda, 2208521A
Detailed Design Review GEOTECHNICS Rev E 20-Jun-2019
Page 3 of 16
Nyamagasani 1 Hydropower Project, Uganda, 2208521A
Detailed Design Review GEOTECHNICS Rev E 20-Jun-2019
SS5 Slope Stability Drained and undrained parameters 22/04/17 2 Response A :23-05-2017
Analysis Report Undrained parameters are the same as drained for Layer 03 soil parameters are taken from the
Table 6 the inferred parameters of Layer 1 and 3. literatures. We couldn’t find the different
parameters for both drained and undrained
DRS Revision B comment: 29/05/17 conditions. Hence, we used same parameters for
The parameters should be reviewed when further both cases.
test data is available. However, when these results For layer 01, Same parameters (drained
are available, we expect to see a difference parameter) were used due to the lag of
between the drained (lower) and undrained shear geotechnical investigation results. But drained
strength (higher). parameters are lesser than the undrained
parameters. Hence, the design is safer.
DRS Revision C comment:
OPEN
As per Rev B comment. Consider adopting drained 13/07/17 Response B: 02-06-2017
parameters from shear box test results as opposed The parameters will be reviewed when additional
to undrained parameters. Groundwater conditions investigation parameters are available.
currently assumed already provides a conservative
assessment. Response C: 23-02-2018
Revised slope stability analysis report (R1) was
DRS Revision D comment: 26/02/18 submitted on Nov 2017 and same report is
Slope stability: Lower headrace (Ch+400 to Forebay attached herewith.
tank) The results from the (R1) slope stability report
derives parameters from shear box test from Teclab Response C: 12-03-2018
report (Oct 2017). These results are significantly To be provided.
higher than the original report from CaCl (Jan,
Page 5 of 16
Nyamagasani 1 Hydropower Project, Uganda, 2208521A
Detailed Design Review GEOTECHNICS Rev E 20-Jun-2019
14/03/18
Page 6 of 16
Nyamagasani 1 Hydropower Project, Uganda, 2208521A
Detailed Design Review GEOTECHNICS Rev E 20-Jun-2019
SS7 Slope Stability Additional slope analysis scope 22/04/17 2 Response A : 23-05-2017
Analysis Report The slope stability analysis is limited to the HRC up We will identify the critical sections in penstock
General to the forebay tank. What are the intentions about line & roads and do the analysis. This report can
addressing other areas requiring stability be submitted before construction of them.
assessment (e.g. access roads and penstock)?
Response B: 02-06-2017
DRS Revision B comment: 29/05/17 Reassessment will be provided when additional
Reissue of slope stability assessment report investigation parameters are available.
pending
13/07/17 Response C: 23-02-2018
DRS Revision C comment: Some information requested from the site.
As per Rev B comment To be submitted.
26/02/18
DRS Revision D comment: Response C: 12-03-2018
Stability assessment from forebay to PH pending To be provided.
Page 7 of 16
Nyamagasani 1 Hydropower Project, Uganda, 2208521A
Detailed Design Review GEOTECHNICS Rev E 20-Jun-2019
requirements can be satisfied for all the joint required to take lateral deflection in
temporary stages; this alternative may addition to axial extension was urged. Details
prove to be more expedient and cost of a new expansion joint of below type which
effective can take 20mm of lateral deflection was
The ground profile in the model doesn’t submitted. Evidence of use of proposed
look to match the design drawings bellow type joint in similar situation required
by OE. Enclosed in this submission is a list
The arbitrary RL datum adopted makes it
of projects provided by the expansion joint
difficult to compare with the design supplier.
The report provides no discussion about
the settlement analysis; are the computed
settlement values acceptable?
Does the total settlement include the
settlement prior to the application of the
footing loads?
There are some unusual peaks in the
settlement plot that look anomalous (see
below); these should be checked
Stability of Structures
Page 9 of 16
Nyamagasani 1 Hydropower Project, Uganda, 2208521A
Detailed Design Review GEOTECHNICS Rev E 20-Jun-2019
Page 10 of 16
Nyamagasani 1 Hydropower Project, Uganda, 2208521A
Detailed Design Review GEOTECHNICS Rev E 20-Jun-2019
Page 11 of 16
Nyamagasani 1 Hydropower Project, Uganda, 2208521A
Detailed Design Review GEOTECHNICS Rev E 20-Jun-2019
Closed
Page 12 of 16
Nyamagasani 1 Hydropower Project, Uganda, 2208521A
Detailed Design Review GEOTECHNICS Rev E 20-Jun-2019
01/05/18
DD DRS Revision B comment: Further comments
A detailed set of PH drawings review comments Please refer to the separate excel sheet provided
provided in attached document. Refer
“N1_PHdwg_OEcomments_010518.pdf”
Page 14 of 16
Nyamagasani 1 Hydropower Project, Uganda, 2208521A
Detailed Design Review GEOTECHNICS Rev E 20-Jun-2019
Risk Assessment for The risk assessment (RA) makes no reference to the 09/04/18
Construction of staged excavation process and geologist
Page 15 of 16
Nyamagasani 1 Hydropower Project, Uganda, 2208521A
Detailed Design Review GEOTECHNICS Rev E 20-Jun-2019
Page 16 of 16