Professional Documents
Culture Documents
Alman Hukukunda Prolongation Cost PDF
Alman Hukukunda Prolongation Cost PDF
PROLONGATION COSTS
UNDER GERMAN LAW
Dr Wolfgang Breyer
August 2012
D138
www.scl.org.uk
CLAIMING AND DETERMINING
PROLONGATION COSTS
UNDER GERMAN LAW
Dr Wolfgang Breyer
Introduction
This is a paper about claims: the requirements that claims for additional
monies need to fulfill if those monies are claimed due to delays or disruptions
in the execution of the works. The paper, drawing on Costain v Haswell,1 will
attempt to sketch the conditions that appear to be imposed by English courts in
order to approve such claims; and then, drawing on a German landmark
decision BGH VII ZR 225/03,2 compare these with the requirements German
courts lay down. The paper will then attempt to discuss the conclusions, if
any, that might be drawn from this comparison, and also point out some
further fields where further legal comparative research might be of benefit to
all involved.
This leads to the conclusion that a contractor must prove, to the usual civil
standard of the balance of probabilities, that:
1 Costain Ltd v Charles Haswell & Partners Ltd [2009] EWHC 3140 (TCC), [2010]
TCLR 1, 128 Con LR 154.
2 BGH VII ZR 225/03, published in BauR 2005, 861. [Note to English readers: German
court decisions tend to be published in legal journals, each covering a specialised legal
field. The leading German journal on construction law is ‘Baurecht’, abbreviated to
‘BauR’. The citation states the court, the journal, followed by the year of publication
and the page number. There are also registers of official decisions, but these are not
organised according to subject matter.]
3 Costain v Haswell, note 1, para [184].
1
o the disruption or delay event in fact led to a delay;
o the said event impacted on the activities on the site; and
o to what extent exactly, and how, the delay or disruption did impact
on all activities on the site.
Dr Ronan Champion, in his SCL paper Prolongation Costs: Where now after
Costain v Haswell? discusses at length the implications of this ruling.4 He
establishes that prolongation costs can be classified into various types of cost,
and narrows the term down to ‘site running costs’ and ‘winter working costs’
in order to discuss Costain v Haswell. He goes on to show that the Time
Impact Analysis, as performed by the experts in the case, failed to show the
causal link between the delay undoubtedly suffered by the claimant at that
time and the impact of that delay on the completion of the Works as a whole.
Thus, the claim, first and foremost, failed on the facts.5 From this, however,
Champion concludes:
‘… claimants proving delays may be put to the burden of proving the
impact of every subsequent delay event, merely to confirm that the
earlier delay in issue in fact crystallized. This could result in a
disproportionate burden that was never intended, and which is
unsupported by authority elsewhere.’6
According to Costain v Haswell, a claimant must prove that all activities being
carried out on site were affected by the delay in question. This requirement is
challenged on the basis that it was arrived at without reference to authority or
to established principles of valuation based on time-based resources alone.8
Phrased differently: the judge in Costain v Haswell required that a link be
proven between time-related losses and other activities underway at the time
of the losses; arguably, such a link should not have been required.9
4 Dr Ronan Champion, Prolongation Costs: Where now after Costain v Haswell? SCL
Paper 170 (September 2011), downloadable from www.scl.org.uk, pages 2-3.
5 Champion, note 4, page 10.
6 Champion, note 4, page 10.
7 Champion, note 4, page 11.
8 Champion, note 4, page 14.
9 Champion, note 4, page 14.
2
Comparison with the situation in German law and the decision
BGH VII ZR 225/03
The purpose of this paper is not to discuss Costain v Haswell in yet more
detail, but to compare it with German principles. In Germany, there exists a
rather large number of judicial decisions that have examined and discussed in
quite some detail the requirements that the contractor needs to satisfy in order
to be able to successfully claim monies resulting from an extension of the time
required for executing the works.
As German law, however, does not follow the principal of stare decisis, the
law can and does develop differently in different districts of the various high
courts, depending on the stance of those courts on the subject matter.
Ultimately, the legal community will turn to the Federal Court of Justice
(Bundesgerichtshof, abbreviated in Germany to BGH) for a final authoritative
ruling on how to interpret the law. Despite the absence of stare decisis, such
decisions usually shape the interpretation of the law for years to come.
The Federal Court of Justice has had the opportunity to discuss at length and
lay down the requirements that a contractor’s claim for monies due to an
extension of time needs to fulfill in order to succeed in the case BGH VII ZR
225/03.10 The facts of the case: a general contractor entered into a turnkey
contract, under which it was to construct a residential park. The employer was
responsible for providing the design. The employer was, amongst other
things, late in providing the design.
The contractor claimed for ‘damages’ arising out of the delayed date for
completion, based on circumstances which were attributable to the employer,
like delayed delivery of the drawings, delays in the employer making
decisions and the like. Hence, the contractor claimed for ‘compensation for
prolongation costs’ which had been caused, at least according to the facts
established by the courts, for reasons other than variations (this will become
important later on). In its statement of claim, the contractor relied, and
primarily referred to, the report of an expert, which was attached to the
statement of claim as an exhibit.
The contractor failed at both first and second instances, both the regional court
and the high court holding that the contractor’s claim was not substantiated
enough, ie the contractor had failed to sufficiently show why it was entitled to
the monies it claimed. Both courts held that:
o mere reference to expert opinion is not sufficient to provide
particulars for supporting the claim; and
o the claimant had failed to provide evidence of causation – that the
circumstances attributable to the employer were the cause for the
whole of the delay that had arisen; and
o had also failed to show the impact that such ‘employer delay’ did
have on the date for completion.
3
In its ruling, the Federal Court of Justice (BGH) set the judgment aside and
made two findings. First, reference to an expert opinion, even if only annexed
to a statement of claim, can be sufficient and can be considered to be part of
the statement of claim, provided however that the essential facts which form
the basis of the claim are included in the statement of claim itself.
Secondly, the court held that there is a need for the claimant to prove the
concrete actual period of delay arising out of each single delay event. The
question of whether or not the contractor had met this criteria remained
unanswered, as the courts of first and second instance had not dealt with that
matter, as they had dismissed the claims due to the allegedly improper
reference to the expert opinion.
In a second step to this part of the ruling, the BGH also provided guidance on:
o how the contractor might prove the concrete period of delay
arising out of each single delay event, and how such delay affected
the date for completion; and
o what requirements the contractor had to satisfy to prove the
additional costs that arose out of the whole of the delay.
The court stated that it is sufficient to show in a reasonable way, for example
by using a chart reflecting a delay analysis, the impact on the completion
date.11 The cause and effect relationship between a ‘delay event’ and actual
‘delay’ or ‘prolongation’ needs to be clear. However, there is no need to
prove the total actual impact on the date of completion by analysing and then
summarising all single events together. Rather, the exact amount of additional
time that was or is required is subject to para 287 of the German Code of Civil
Procedure, which allows the court, under certain conditions, to estimate the
damage.
The BGH ruled that it is sufficient to provide a plausible basis for such an
estimation. Single mistakes, ambiguities and other small discrepancies are, by
themselves, not reasons to dismiss a claim, provided that the court can ‘fill the
gaps’ with such an estimation.12 Nevertheless, the contractor has to present
his claim in as detailed a way as possible. This also holds true for the
damages arising out of the delay. Such damages may be estimated in
accordance with para 287 of the German Code of Civil procedure, provided
that a plausible basis for such estimation is provided by the contractor.
11 When the court is asking for a ‘proof of concrete delay arising out of each single delay
event’, it is in fact demanding what is known in English terminology as a ‘Time Impact
Analysis’. Other types of delay analysis will usually not meet the standards of the BGH.
12 It appears that the court acknowledges the weaknesses of ‘Time Impact Analysis’ in
estimating such a total impact, its willingness to make an estimate in effect providing a
workaround.
4
In Costain v Haswell, the court held that Costain had failed to show that the
delays had actually delayed the completion of the works by 12 weeks, or at
all.13 The court expressly required such proof, as previously shown. Would
the BGH have replaced any such lack of evidence with an estimation, in the
light of the above?
This means that, even though basically, according to German law, proof of
delay is demanded, proving the extent of the delay is made easier because this
impact can be estimated. In other words: the BGH still requires proof that a
‘delay event’ did in fact delay the works in question, but the extent of the
delay, that is the ‘size of the footprint’, may be estimated.16 This estimation,
however, requires a plausible basis.
So, even though the ‘theory’ might be different, the requirements for ‘proof’
will not be all that dissimilar. It does mean, however, that, once causation has
been proved, the consequences of a delay will not need to be presented in
excruciating detail, as these can be estimated once they have been made
plausible.
5
obtain an award in Germany. That a delay occurred because of a delay
event must be proven,19 even if its extent need not.20
2. Costain v Haswell appears to suggest that the contractor must show what
losses were generated as a result of the delaying event.21 This
requirement is, in fact, quite similar to the German requirements: The
contractor must prove that losses were incurred as a result of the delay
event in front of a German court too.
Regarding the ‘costs’ of time, the usual approach of German law is to provide
for an evaluation, basically a variation which is supposed to be based on the
original calculation of the contract prices (in a BoQ or otherwise). This
especially holds true if the parties agreed to utilize the VOB/B, the German
standard terms and conditions for construction works, which are similar to
those provided in France (AFNOR), Switzerland (SIA), Austria (ÖNORM B
2110) or the JCT23 and ICE24 forms.
This means that the basis for a claim has to be individually determined for
each delay event. In theory, paragraph 2 sub-paragraphs 5 or 6 VOB/B rely on
the calculations of the contractor, whereas paragraph 6 looks to the actual
costs. In practice, it is almost impossible to keep the impact of ‘paragraph 2
events’ distinguished and separate from the impact of ‘paragraph 6 events’.
6
This leads to a conflict: should the cost impact of the additional time now be
evaluated according to additional cost, or according to the descriptions which
underpin the calculations of the contractor? This entire principle within the
VOB/B has come under fire for being too unwieldy and failing to meet the
needs of practitioners, so it is currently being hotly debated.25
So there arises a conflict: ‘calculated time’ versus ‘actual time’. For example,
assume that, after commencement of the works, the employer instructs a first
variation which will have an impact on the critical path, leading to two weeks’
delay to the date for completion, according to the calculations and the
programme of the contractor. In reality, due to generous padding of the
programme, perfect staff or whatever reason, the varied works are carried out
within one week.
After the first week, within the (calculated) second ‘prolonged’ week, a
disturbance occurs on the site, for example delayed drawings related to the
works which follow the variation works. The contractor is ready to continue
the works, but for lack of drawings, he cannot. So, real progress on the site is
hampered by the disruption event. At the beginning of the third week, the
employer submits the drawings required, and the contractor can progress the
works once more.
At the present time, it seems impossible to predict how the BGH would
decide: whether it will follow the ‘theoretical’ approach with regard to time
arising out of a variation, or if the BGH is of the opinion – as are others in the
German legal community – that both circumstances have to be handled the
same way, by evaluation based on the time actually required on site.26
This problem also arises with regard to costs which stem from additional time
caused by a variation. Should these costs be determined upon the original
calculation, based on the original prices of the contractor, or should they be
evaluated based on the real costs incurred by the contractor?
On the one hand, it seems unfair to ask the employer to grant the contractor an
additional extension of time, as the contractor was not actually hindered.
25 Compare with Oberhauser, BauR 2011, 1547-1562; Schottke, BauR 2011, 1881-1896.
26 There is a tendency of the high courts to demand that costs shall be recovered only as
incurred, cf OLG Munich IBR 2012, 11; OLG Frankfurt IBR 2008, 1054; not decided
yet by the BGH. There is no established authority yet as to the handling of time.
7
After all, compared with the revised programme, progress after the second
disruption will be exactly on schedule.
Christopher Ennis has, to some extent, discussed some of the issues that arise
from each of the above points, but the focus of the discussion seems to be
different.27 He points out the differences between the various methods of
quantifying what he terms ‘disruption costs’, and considers the pros and cons
of each method of measuring the effects of disruption.
The discussion in Germany, on the other hand, centres around the fact that the
standard form of contract actually prescribes what method of ‘quantum
measurement’ to utilise in which circumstances, but that this ‘differentiation’
has proven nearly impossible to sustain in practice, with the effect that the
courts will, to some extent, invoke paragraph 287 of the Code of Civil
Procedure and allow for an estimation of the extent of the losses suffered,
which however must have a ‘plausible basis’.
So, even though the BGH allows for estimates of the impact of delay events
on the project with regard to time or money, the basis of those calculations
depends on the type of claim being pursued: is it a claim based on a variation,
or based on a disruption? As either event can generate delays, handling them
according to these different requirements can get tricky in practice.
The SCL Delay and Disruption Protocol, on the other hand, refers to ‘work
actually done’ on the site, ‘expenses actually incurred’ etc, but it also
recommends that, in cases where prolongation is caused by a variation, the
prolongation should be included in the evaluation of the variation.28
What then is supposed to happen if the parties fail to agree on such a variation
that includes prolongation, or simply forget to address the prolongation issue?
The issues remain unresolved at this time.
8
Conclusions
This paper has highlighted the different requirements of English and German
courts with regard to contractors’ claims for prolongation costs. It appears
that the English courts, at least after Costain v Haswell, have more stringent
requirements with regard to the impact of events on total delay, and that, in
theory at least, the German courts, by accepting estimates as to the impact of
delays, make it easier for contractors to obtain awards. In practice, however,
the requirements are not so different, as the estimates need to be made on a
‘plausible basis’, which the contractor must provide.
English contract forms appear to handle this issue in a more uniform way, but
there is no consistency across different contract forms on how to determine
prolongation costs: by referring to the contractor’s calculations, or by utilising
the actual costs incurred? The matter seems to be discussed along different
lines than in Germany, with the key item in the English discussion being
‘entitlement to reasonable cost’, and how to prove what costs are reasonable.29
Whereas in Germany, the discussion centers on ‘when may the contractor
claim additional costs based on the original contract price calculations’, as
opposed to ‘when may he claim additional actual costs?’ The methods for
determining the extent of such an adjustment, on either basis, is currently not
the focus of the German discussion.
The question appears to be in need of further research, and may benefit from
the English discussion about various methods of determining costs.
The views expressed by the author in this paper are his alone, and do not necessarily
represent the views of the Society of Construction Law or the editors. Neither the
author, the Society, nor the editors can accept any liability in respect of any use to
which this paper or any information or views expressed in it may be put, whether
arising through negligence or otherwise.
9
‘The object of the Society
is to promote the study and understanding of
construction law amongst all those involved
in the construction industry’
MEMBERSHIP/ADMINISTRATION ENQUIRIES
Jill Ward
The Cottage, Bullfurlong Lane
Burbage, Leics LE10 2HQ
tel: 07730 474074
e-mail: admin@scl. org. uk
10