Títle: WEST COURAGEOUS Rig Move Report R001

Reference: LA0089/R1/2018-02-20

Issue: Issue for client


LION-ALFA Marine Consultants WEST COURAGEOUS Rig Move Report R001
LA0089/R0/2018-02-20

Table of content

1. INTRODUCTION 1

1.1 Instructions received ................................................................................................... 1


1.2 Attendance .................................................................................................................. 1
1.3 Scope of report ............................................................................................................ 1

2. RIG MOVE 2

2.1 General ........................................................................................................................ 2


2.2 Personnel in attendance ............................................................................................. 2
2.3 Details of the unit ........................................................................................................ 3
2.4 Departure location ...................................................................................................... 4
2.5 Arrival location ............................................................................................................ 4
2.6 Recommendations from MWS .................................................................................... 5
2.7 Weather window ......................................................................................................... 6
2.8 Vessels in attendance .................................................................................................. 7
2.9 Conduction of the move ............................................................................................ 11

• APPENDICES 14

o Logbook ........................................................................................................................ 14
o Minute of Pre-move meeting ....................................................................................... 14
o LION-ALFA Positioning Report ...................................................................................... 14
o OCEANEERING Delivery Letter ..................................................................................... 14

i
LION-ALFA Marine Consultants WEST COURAGEOUS Rig Move Report R001
LA0089/R0/2018-02-20

1.1.1 On 15th January 2018 this office received a request from Mr David Castelan Valero rig
manager of MODU West Courageous of Seadrill Mexico for carrying out a Rig Move service
(the service) for her mobilization from KAX-1 to MAY-1 in the PEMEX Platform field at Bay of
Campeche, Mexico.

1.2.1 As per instructed by Mr. Castelan, on 17th January 2018, undersigned mobilized from
Tampico to Dos Bocas, Tabasco for attending a What If? Meeting at PEMEX offices on next
day. What if? Meeting was held on 18th January 2018 from 11:00 to 19:00 hours
1.2.2 For attending the Rig move service, undersigned travelled from Dos Bocas to Ciudad del
Carmen, Campeche on evening of Thursday 18th January 2018. Mobilization to West
Courageous was done by helicopter on Friday 19th January 2018 at 16:00 hours.
1.2.3 Attendance aboard West Intrepid was performed from 19th January to 07th February 2018.
Demobilization to Tampico was on 08th February 2018.

1.3.1 This report describes our work on the conduction of the rig mover service aboard MODU
West Courageous during her mobilization from KAX-1 to MAY-1. Documentation produced
and gathered during the course of service has been appended to this report.

1
LION-ALFA Marine Consultants WEST COURAGEOUS Rig Move Report R001
LA0089/R0/2018-02-20

2.1.1 Since at KAX-1, the rig’s legs reached large penetrations of 115 feet, the rig move was
planned to be performed within an ample weather window of 15 days for releasing the
spudcans in addition to 3-day of suitable weather for carrying out the move indeed. However
since during winter season, cold fronts regularly affect the Bay of Campeche; weather
windows are not of long period. Thus, it was decided to work the soil by reducing the legs’s
penetration by 20-foot on first opportunity during a weather window 20th to 22nd February
2018; then jack up to 20 feet air gap to wait for another weather window.
2.1.2 Another suitable weather window was forecasted from 02nd to 7th February 2018, so the rig’s
legs were released without delays and the rig move was performed in one single event
during Sunday 04-Feb-18 to Wednesday 07-Feb-18.

2.2.1 The following list indicates the personnel in attendance during rig move:

Rank Name
Offshore Installation Manager Paul Panko
Marine Safety Leader Herman McLendon
Rig Manager David Castelan Valero
Marine Superintendent Peter Allerup
Rig Mover Luis Orozco Velazquez
Marine Warranty Surveyor Matthew Formel
PEMEX Contract Supervisor Daniel Santos Ayala
PEMEX Superintendent Miguel A. Medina Cayetano
PEMEX Pipeline Supervisor Humberto Berzunza Baeza
PEMEX Toolpusher Marco Molina Sánchez
PEMEX Well Engineer Tania Ivette Collado Sánchez
Oceaneering surveyor Vicente Cabrera Antonio
Oceaneering surveyor Jesús A. Cárdenas Aguilar
Oceaneering surveyor Hilario Ham Cabrera
Oceaneering surveyor Alfredo Ojeda Rodríguez

2
LION-ALFA Marine Consultants WEST COURAGEOUS Rig Move Report R001
LA0089/R0/2018-02-20

2.3.1 The following table shows the particulars of the unit.

Particulars

Official name West Courageous
Design LeTorneau Super 116
Call sign 9V2541
Operator Seadrill
Flag / Registry Singapore
Hull Length (LBP) 243.08 ft
Breadth 206.0 ft
Depth 26.0 ft
Tonnage GT: 7079 NT: 2123
Length of legs 477.47 ft
Diameter of spudcan 46 ft
Height of spudcan 24 ft
Footing Area (one can) 1555 ft2
Volume (one can) 13520 ft3
Longitudinal leg spacing 129.0 ft
Transverse leg spacing 142.0 ft
Aft leg centres to transom 54.08 ft
Maximum draft 15.55 ft
Maximum displacement 25,028 kips
Maximum reaction allowed 14,015 kips
Variable load (afloat) 4,432.1 kips
Variable load (elevating & preloading) 3,661.0 kips
Variable (drilling) 7,011.0 kips
Variable load (severe storm) 3,511.0 kips

3
LION-ALFA Marine Consultants WEST COURAGEOUS Rig Move Report R001
LA0089/R0/2018-02-20

2.4.1 The following table indicates the departure location particulars:


Designation: KAX-1
Area: Bay of Campeche, Mexico
Latitude: 19º - 08’ – 03.827”N
Longitude: 092º – 29’ 15.034” W
Rig heading: 000.8º
Water depth: 165 ft
Seabed type: Very soft clay
Penetration achieved: 115 feet average
Platform riser or open location: Three legged platform
Operator: PEMEX

2.5.1 The following table indicates the destination location particulars:


Designation: MAY-1
Area: Bay of Campeche, Mexico
Latitude: 18º - 43’ 22.29”N
Longitude: 092º - 35’ 49.35” W
Rig heading: 323.3º
Water depth: 49 ft
Seabed type: Very soft clay
Penetration reached (initials): Bow: 55.3 ft, Starboard: 56.0 ft, Port: 54.8 ft
Platform riser or open location: Sea-Pony platform
Operator: PEMEX

4
LION-ALFA Marine Consultants WEST COURAGEOUS Rig Move Report R001
LA0089/R0/2018-02-20

2.6.1 The Marine Warranty Surveyor Messer’s. Aqualis Offshore produced the following
recommendations, which were attended during the course of West Courageous move and
positioning at MAY-1.

RECOMMENDATIONS:

Approval of the location is subject to the following observations and recommendations being
implemented:

i. Data from the Compania Mexicana Aerofoto report shows that the seabed slopes gently towards the NW and that
there no natural obstructions which could damage the unit. A seabed survey of the approach area should be
conducted to show any anomalies such as spud can holes from previous units, drag marks possibly created by the
dragging of a previous rig’s spud cans and any man made infrastructure, such as pipelines and debris which may be
present.
ii. Any debris within 100 m of the platform rig approach face should be removed. The fresh survey may be conducted
using Mesotech equipment installed on the jackup to detect any debris and to confirm the position of the pipeline to
MAY-A to SE of platform.
iii. Good weather conditions and a favourable forecast should be received prior to departure covering the tow route,
positioning phases and throughout the pre-loading operations.
iv. Given the soft seabed and the report that other rig designs have been deployed previously at this location, the
WEST COURAGEOUS should be placed on a heading which allows for careful positioning of the unit in the same
old spud can holes generated by the other rigs. From Mesotech and sonar reports, a heading of approx. 328oT will
be required.
v. It is recommended that preloading should take place adopting a leg-by-leg approach and rotating from leg to leg to
try and keep leg penetrations even.
vi. Based on the soil boring reports and leg penetration analysis undertaken, rapid settlement may occur during
jacking and preloading operations. Operators should adopt cautious and careful procedures in line with the
recommendations of the Operating Manual. The preload procedure requires preloading operations to proceed with
the hull in the water to mitigate the risk of any rapid settlement.
vii. At all times actual leg penetrations achieved should be monitored against expectations as contained in the leg
penetration analysis. If clear deviations are identified, then operations should be temporarily halted and advice
sought from owners and this office advised. The full pre-load should be held on each leg for the minimum period
stated in the Operations Manual, without additional settlement being noted, and in no circumstances less than 1
hour.
viii. This review considers the minimum required air gap requirement and does not take into consideration the
required leg length for operations and platform air gaps which maybe greater.
ix. All operations are to be undertaken in accordance with the recommendations stipulated within the approved
operating manual.
x. As per the Marine Operations Manual, maximum wave height should be less than 5 feet when pulling legs, going
off and on location and during preloading. This limit can be adjusted depending on the movement of the rig and will
be at the discretion of the OIM, MWS and Rig Mover in order to avoid any damages to the jacking system.
xi. Departure from and approach to platform should only commence in daylight hours.
xii. Destination platform to be shut down unless the rig mover and attending surveyor agree otherwise. The platform
must be ready for shutdown and adequate personnel should be available to effect the shutdown operation before
commencement of rig move operations in the vicinity of the platform.
xiii. Any other recommendations made on site by the attending surveyor.

5
LION-ALFA Marine Consultants WEST COURAGEOUS Rig Move Report R001
LA0089/R0/2018-02-20

2.7.1 For purposes of assessing the sea and wind conditions, to comply with allowed weather
criteria indicated in the West Courageous operating manual and Marine Warranty Surveyor;
undersigned was provided with a forecast bulletins produced by the Wilkens Weather and
WeatherOps agencies twice a day that; in turn indicated suitable conditions for working
releasing the spudcans and conducting the rig move; starting on Thursday 1st to Wednesday
07th February 2018.
2.7.2 After having assessed the forecasted weather conditions, Undersigned rig mover, OIM, Barge
MSL, Marine and Warranty Surveyor agreed in proceeding with the rig move since; the
forecasted conditions were to be within limits to allow the operation to be completed.

6
LION-ALFA Marine Consultants WEST COURAGEOUS Rig Move Report R001
LA0089/R0/2018-02-20

2.8.1 The following table indicates the tugs in attendance during the rig move from KAX-1 area to
MAY-1:

Tug Bollard Pull


LEIBE TIDE Lead Tug 80.11 tonnes
SAAM CITLALI (starboard side) 90.26 tonnes
SAAM QUETZAL (port side) 90.80 tonnes


2.8.2 The tugs above mentioned were duly inspected by undersigned along with marine warranty
surveyor and found suitable and in satisfactory operational condition for the projected rig
move.
2.8.3 The following tables show the particulars of tugs used during the rig move.

Particulars
Name LEIBE TIDE
Official number 9513397
Year of built 2008
Operator Tidewater de México S. de R.L. de C.V.
Flag / Registry Mexican / Isla del Carmen
Dimensions LOA: 57.59 m, B: 15.00 m, D: 6.10 m
Tonnage 1815.0
Main engines 2x MAK Maschinebau GMBH 2,640 KW each
Horsepower 7190 HP
Thrusters Yes, Bow thruster
Rudder Yes, compensated type
Propellers & Nozzles Yes, Kort nozzles
Bollard pull 80.11 tonnes
Towline 6x36 IWRC EEIPS, 1000m 64 mm diam. Proof
load: 120.4 ton
Stretcher 1x doubled, with thimble in each end, 15”
circular plaited nylon rope 30 meter, MBL:
230.4 tonnes
Pennant wire 6x26 IWRC RHRL, 27.5mts, 2.0” diam. BS: 137.5

7
LION-ALFA Marine Consultants WEST COURAGEOUS Rig Move Report R001
LA0089/R0/2018-02-20

tm
Shackles Bolt type 3”, SWL 85 tonnes
Towline anti-chaffing Yes
Shark jaws Karm fork
Towing Pins Yes
Gog wire Yes
Stern roller Yes
Tugger 2x
Operational / Actual draft 6.00m / 5.50m
Bunkers D.O. 133,791 USG, F.W. 91 m3, L.O. 597 USG
Daily consumption D.O. 2400 USG and 3,000 towing, F.W. 1m3,
L.O. -
Master name Raul Pérez Gómez
Master experience 22 years in tugs

8
LION-ALFA Marine Consultants WEST COURAGEOUS Rig Move Report R001
LA0089/R0/2018-02-20

Particulars
Name SAAM CITLALI
Official number 9680384
Year of built 2013
Operator SAAM Remolques S.A. de C.V.
Flag / Registry Mexican / Veracruz
Dimensions LOA: 230.39 m, B: 12.50 m, D: 5.80 m
Tonnage 496
Main engines 2x Caterpillar C-280-8
Horsepower 6,598 hp
Thrusters Yes
Rudder Z-drive propellers
Propellers & Nozzles Yes, Kort nozzles
Bollard pull 90.26 tonnes
Towline 6x36 IWRC WS Galvanized EEIPS, RHRL, 5,000
ft, 2” diam, Strength: 441,137 Lbs
Stretcher 1x doubled, with thimble in each end, 6” diam
plaited nylon rope, mbl: 308.629 tf
Pennant wire 6x36 IWRC RHRL, 12 mts, 2.0” diam, BS: 167.85
tm
Shackles Crosby Bolt type Anchor Shackle 3” Maxtough,
WLL 85 tm, Proof Load: 170 tonnes
Towline anti-chaffing No
Shark jaws No
Towing Pins No
Gog wire No
Stern roller Yes
Tugger 1x drum
Operational / Actual draft 6.00m
Bunkers D.O. 50,200 USG, F.W. 50 m3, L.O. 1,350 Liters
Daily consumption D.O. 1,200 USG, F.W. 1m3, L.O. -
Master name Celestino Delgado Baizabal
Master experience 17 years in tugs towing rigs

9
LION-ALFA Marine Consultants WEST COURAGEOUS Rig Move Report R001
LA0089/R0/2018-02-20

Particulars
Name SAAM QUETZAL
Official number 9680396
Year of built 2013
Operator SAAM Remolques S.A. de C.V.
Flag / Registry Mexican / Dos Bocas
Dimensions LOA: 32.60 m, B: 12.50 m, D: 5.8 m
Tonnage 496
Main engines 2x Caterpillar C-280-8
Horsepower 2x 4,920 kw @ 1,000 rpm
Thrusters Yes
Rudder Z-drive propellers
Propellers & Nozzles Yes, Kort nozzles
Bollard pull 90.80 tonnes
Towline 6x36 IWRC RHRL, 750 meter 2.5” diam,
Strength: 274.52 tonnes
Stretcher 1x doubled, with thimble in each end, 6” diam
ProSet Nylon, 8-Strand, Square Braid
mbl: 780,000 Lbs
Pennant wire 6x36 IWRC Bright import, 12 mts, 2.0” diam,
BS: 185.0 tm
Shackles Crosby Bolt type Anchor Shackle 3” Maxtough,
WLL 85 tm, Proof Load: 170 tonnes
Towline anti-chaffing No
Shark jaws No
Towing Pins No
Gog wire No
Stern roller Yes
Tugger 1x drum
Operational / Actual draft 6.00m
Bunkers D.O. 34,600 USG, F.W. 61 m3, L.O. 2,846 Liters
Daily consumption D.O. 1,200 USG, F.W. 1m3, L.O. -
Master name Pascual Hernández Navarro
Master experience 28 years in tugs

10
LION-ALFA Marine Consultants WEST COURAGEOUS Rig Move Report R001
LA0089/R0/2018-02-20

2.9.1 The rig move was planned for carrying out on first opportunity during the operational
weather window of Sunday 04th to Wednesday 07th February 2018 and all preparations were
carried out to do so.

2.9.2 During Sunday 01, tugs were notified and Captains were called to attend the pre-move
meeting aboard West Courageous. After the meeting the tug LEIBE TIDE was connected to
bow main tow bridle in preparation for conducting the move-off manoeuver.

2.9.3 Leg releasing work was performed from Thursday 01st to evening of Saturday 03rd February
01, when legs were moving freely and ready to start the move.
2.9.4 Move-off manoeuver was conducted from 10:35 hours on Monday 5th February 2018 using
the LEIBE TIDE connected to main tow bridle, SAAM CITLALI connected to smit-bitt on
starboard-aft and SAAM QUETZAL connected to smit-bitt on port-aft. The manoeuver
commenced by pulling the rig in a slow and controlled manner to the heading North during
the first 100 meters, while dragging slightly the legs about 4 feet and after that, the rig
started to slowly turn to follow the drafted route bound to MAY-1. During the move-off
manoeuver the legs were jacked up simultaneously, having the bowleg in a upper position by
5 feet. Thereafter, the legs were picked up to tow position 2 feet below base line.
2.9.5 After moving the rig away, at about 1 nm Northeast of KAX-1 area, the three tugs were
reduced in power and their towlines were lengthening to 200-220 meters and then power
was increased for arriving MAY-1 area the soonest to be prepared and wait for Pemex
production personnel to arrive at MAY-1 to shut in the wells.

2.9.6 The navigation to MAY-1 was conducted with good coordination between the tugs’ Captains
and Rig Mover. During the route the tow did crossed over eight pipelines. Average tow speed
was 2.83 knots
2.9.7 On next day Tuesday 06th February at 02:22 hours, the tow arrived to 235 -meter standoff
position to wait for daylight to assess weather conditions and wait for Pemex production
personnel to shut-in the wells at MAY-1 and proceed to final position.

2.9.8 At 06:50 hours, the rig was moved to 150-meter position to deploy the first mesotech sonar
and verify the seabed condition and shutting in the oil wells. Once completed the seabed
scan, the rig was moved to 75-meter to run another sonar scan of seabed. PEMEX pipeline
supervisor, marine warranty surveyor and undersigned witnessed the seabed scans.
2.9.9 As the images obtained from Mesotech sonar scan did not show the previous footprints at
MAY-1, decision was made to stop at 50-meter standoff position and to deploy Mesotech
and run another seabed scan.

11
LION-ALFA Marine Consultants WEST COURAGEOUS Rig Move Report R001
LA0089/R0/2018-02-20

2.9.10 The approaching manoeuver to final position was conducted using the three tugs keeping
good control and orientation so that the velocity was well controlled during the approach
until reaching the final position aiming to get aligned the rig’s center line with conductors C1-
C2 getting 44-foot stand-off distance to jack the legs down into the previous can holes left by
other rigs. Final position was verified by OIM, Pemex positioning supervisors, PEMEX contract
supervisor and Company man who gave their acceptance of position at 17:10 hours 06-Feb-
18.
2.9.11 Thereafter undersigned instructed the jacking control console operator, to jack down legs to
make hard pinning and jacking hull up to secure the rig’s position while keeping the tension
on tugs, however noted that rig slid about 2.5 meters away from MAY-1 installation and
turned slightly to port side.
2.9.12 After positioning manoeuver and penetration of legs to get hard pinning the rig’s position
was re-assessed and noted in the load chart that cantilever had suitable capacity to perform
the envisaged operations; then hull was jacked up by steps until reaching zero draft and
started preparations for preloading.

2.9.13 Preload operation is not addressed in present report, as undersigned was demobilized to
Ciudad del Carmen the day after positioning at MAY-1.
2.9.14 Full detail of events is included in the appended logbook.

Leg Initial
Penetration
feet
Bow 55.30
Starboard 56.00
Port 54.80

12
LION-ALFA Marine Consultants WEST COURAGEOUS Rig Move Report R001
LA0089/R0/2018-02-20


This report is based on activities performed during the course of the rig move service and
documentation gathered and is prepared in good faith and without prejudice to any or all
parties concerned.

For and on behalf of Lion-Alfa S de RL de CV




Capt. Luis Orozco / Rig Mover

13
LION-ALFA Marine Consultants WEST COURAGEOUS Rig Move Report R001
LA0089/R0/2018-02-20

14
LION-ALFA MARINE CONSULTANTS


LOGBOOK
WEST COURAGEOUS RIG MOVE

Job: 0089 MODU WEST COURAGEOUS Rig Mover: Luis Orozco


Project: Rig Move from: KAX-1 to MAY-1 Start: 18 Jan 18
Site: Bay of Campeche, Mexico End: 08 Feb 18

Reason: Rig Mover service



Date / Time Description
Wed Jan 17 Rig Mover Luis Orozco (LO) mobilization from Tampico to Villahermosa to attend for attending
1200 – 1820 What If? Meeting at PEMEX offices at Dos Bocas
1830 – 1920 Mobilization from Villahermosa to Dos Bocas for attending What If? Meeting
Thu Jan 18 Attending What If? Meeting at Pemex offices and demobilization from Dos Bocas to Ciudad del
0900 – 1900 Carmen after attending What If? Meeting for WCO rig move at Pemex offices
Fri Jan 19 Rig mover mobilization from Ciudad del Carmen to West Courageous by helicopter
1530 - 1700
1700 - 2000 Meetings with OIM, MSL, Pemex contract supervisor, Pemex positioning supervisor and Pemex
superintendent to get familiar with current operations and organize next ones
Personnel attending rig move:
1. David Castelan Rig manager
2. Peter Allerup Marine superintendent
3. Clint Coker OIM
4. McLendon MSL
5. Luis Orozco Rig Mover
6. Matthew Formel AQUALIS MWS
7. Mauricio Baizabal Hdz PEMEX contract supervisor
8. Sergio Oviedo PEMEX positioning supervisor
9. Hugo Ruiz Landin PEMEX superintendent
2255 SAAM CITLALI reported available on location
2320 - 2400 Rig mover, PEMEX positioning supervisor and MWS carry out inspection to tug SAAM CITLALI with
satisfactory result. The only remark informed by tug captain is next crew change at Dos Bocas next
Monday
1. Pascual Hernández Navarro Tug Captain
2. Miguel Aarón Trejo Pérez Tug Chief engineer
Bunkers:
D.O.: 25,200 usg
L.O.: 1,350 liters
F.W.: 50 m3
Sat Jan 20 Checked jacking system console and e-stop
0440
0455 Jacking meeting with crew
0518 Crew allocated at legs and ready for jacking
0519 Hull jacked up 1 foot
0520 Hull stop at 26 feet air gap for mooring ropes removal
Legs marks:
Stbd: 366.8 ft Bow: 362.7 ft Port: 363.5 ft
0645 - 1000 25,000 usg of diesel oil received from LEIDE TIDE
0700 – 0730 Review of weather forecast and email:
Sat 20-jan-18: 0800 – 2400 Window

pág. 1 of 16
LION-ALFA MARINE CONSULTANTS


LOGBOOK
WEST COURAGEOUS RIG MOVE

Sun 21-jan-18: 0000 – 2400 Window


Mon 22-jan-18: 0000 – 2400 Window
Tue 23-jan-18: 0000 – 1800 Window
Tue 23-jan-18: 1800 – 2400 No window
Wed 24-jan-18: 0000 – 2400 No window
Thu 25-jan-18: 0000 – 0600 No window

0800 - 1100 Rig mover works on preparation of manoeuvring procedure
1100 - 1200 Attending daily conference with PEMEX office and Seadrill personnel. Topics addressed:
• Buoy installation
• DGPS and Mesotech arrival
• Weather forecast – Operational weather window
• Current operations
• Tug SAAM CITLALI crew change status
1100 – 1330 Crew working removing mooring ropes from bow and port legs
1130 Pre-jacking meeting with crew
1345 Pre-jack meeting with crew
1402 All legs ready to jack
1403 Hull jacking in all legs down to the sea
1412 Hull in the water
1420 All stopped at 10 feet draft
Legs marks:
Stbd: 330.6 ft Bow: 326.7 ft Port: 327.3 ft
1421 - 1430 Start watertight integrity check
1433 SAAM CITLALI called in for connecting to main tow bridle
1450 SAAM CITLALI connected
1454 WTI checked and ok
1520 Hull jacking down to 16 feet draft
1530 Hull jacked down to 16 feet draft
Legs marks:
Stbd: 324.8 ft Bow: 320.9 ft Port: 321.5 ft
1532 Pulling starboard leg to 0.5 meters over floating draft
1535 All stop at 18 feet draft on starboard leg checking for movement
1608 Level rig to a6 feet draft to connect jetting hose
1640 Jetting hoses connected to starboard leg, preparing to start jetting on starboard leg at floating draft
1650 Start jetting in starboard leg with low pressure 75 psi
1850 No movement observed. Stopped low pressure jetting on the starboard leg and swap to high
pressure
1920 Start high pressure jetting on starboard leg 5spm 40psi
1923 All stop. Connector leaking bleed off pressure to tighten connector
1953 Jetting with high pressure on starboard leg 10spm 130psi
2020 Jetting with high pressure on starboard leg 20spm 80psi
2030 Jetting with high pressure on starboard leg 60spm 170psi
2040 Jetting with high pressure on starboard leg 85spm 260psi
2050 Jetting with high pressure on starboard leg 90spm 290psi
2100 Jetting with high pressure on starboard leg keeping WTI

pág. 2 of 16
LION-ALFA MARINE CONSULTANTS


LOGBOOK
WEST COURAGEOUS RIG MOVE

2110 Jetting with high pressure on starboard leg 123spm 500psi


2111 Pulling down on starboard leg 0.5 meters
2113 All stop, no pressure increase, pulling hull down a total of 1 meter over floating draft
2120 Draft at starboard leg 19 feet
2130 Jetting with high pressure on starboard leg 145spm 680psi
2133 Draft at starboard leg 18 feet, back to 19 feet draft
2140 Jetting with high pressure on starboard leg 150spm 680psi
2155 Draft at starboard leg 18 feet pulling hull down back to 19 feet draft leg mark: 320.3
2210 Draft at starboard leg 18.5 feet pulling hull down back to leg mark: 319.5
2216 Draft at starboard leg 18.5 feet pulling hull down back to leg mark: 319.0
2230 Draft at starboard leg 18.5 feet pulling hull down back to 19 ft leg mark: 318.5
2235 Draft at starboard leg 18.5 feet pulling hull down back to 19 ft leg mark: 317.8
2255 Draft at starboard leg 18.0 feet pulling hull down back to 19 ft leg mark: 316.7
2310 Draft at starboard leg 18.5 feet pulling hull down back to 19 ft leg mark: 316.0
2350 Draft at starboard leg 17.5 feet pulling hull down back to 19 ft leg mark: 314.6
Jetting with high pressure on starboard leg 148spm 700psi
2355 Jetting with high pressure on starboard leg 150spm 710psi
2359 Draft at starboard leg 18.0 feet pulling hull down back to 19 ft leg mark: 313.5
Sun Jan 21 Draft at starboard leg 18.0 feet pulling hull down back to 19 ft leg mark: 312.0
0030
0100 Mud pumps off to prepare for jetting hose connection on bow and port legs
0200 Hull up on all legs
0205 All stop, connecting hoses on bow and port legs
0220 Hull jacking to 16 feet draft
0240 Jetting with low pressure on bow, port and starboard legs at floating draft
0440 No movement observed, stopped low pressure jetting on bow leg and swapping over high pressure
0500 Hoses connected on bow leg to high pressure, start staging mud pumps to jet
0510 Jetting with high pressure on bow leg 40spm 180psi
0520 Jetting with high pressure on bow leg 160spm 260psi, keeping WTI
0530 Pulling bow leg to 0.5 meters over floating draft
0532 All stop no pressure increase, pulling bow leg 1 meter in total over floating draft
0550 Jetting with high pressure on bow leg 160spm 220psi
0554 Draft at bow leg 18.5 feet pulling hull down back to 19 ft leg mark: 316.0
0607 Draft at bow leg 18.5 feet pulling hull down back to 19 ft leg mark: 315.5
0620 Draft at bow leg 18.5 feet pulling hull down back to 19 ft leg mark: 314.3, jetting with 160spm
220psi
0640 Draft at bow leg 18.0 feet pulling hull down back to 19 ft leg mark: 313.5
0653 Draft at bow leg 18.0 feet pulling hull down back to 19 ft leg mark: 312.3
0700 - 0730 Review of weather forecast and email:
Sun 21-jan-18: 0000 – 2400 Window
Mon 22-jan-18: 0000 – 2400 Window
Tue 23-jan-18: 0000 – 1800 Window
Tue 23-jan-18: 1800 – 2400 No window
Wed 24-jan-18: 0000 – 2400 No window
Thu 25-jan-18: 0000 – 2400 No window
Fri 26-jan-18: 0000 – 0600 No window

pág. 3 of 16
LION-ALFA MARINE CONSULTANTS


LOGBOOK
WEST COURAGEOUS RIG MOVE

0710 Draft at bow leg 18.0 feet pulling hull down back to 19 ft leg mark: 311.3
0730 Draft at bow leg 18.0 feet pulling hull down back to 19 ft leg mark: 310.0
0752 Draft at bow leg 17.5 feet pulling hull down back to 18.5 ft leg mark: 308.8
0810 Stop high pressure jetting on bow leg t swap to low pressure jet connection
Jetting with high pressure on port leg and Jetting with low pressure on bow and starboard legs
0840 Jetting with high pressure on port leg 160spm 250psi and with low pressure on bow and starboard
legs
0850 Draft at port leg 15.0 feet pulling hull down back to 17.5 ft leg mark: 318.9 0.5 meter over floating
draft
0900 Draft at port leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 318.5
0905 Draft at port leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 318.0
0920 Draft at port leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 317.6
0947 Draft at port leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 317.1 160spm 240psi
0952 Draft at port leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 316.1
1002 Draft at port leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 315.6
1013 Draft at port leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 315.1 160spm 250psi
1025 Draft at port leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 314.0
1050 Draft at port leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 313.5
1057 Draft at port leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 313.0
1105 Draft at port leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 312.5
1115 Draft at port leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 312.0 160spm 250 psi
1125 Draft at port leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 311.5
1133 Draft at port leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 311.0
1150 Draft at port leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 310.5
1205 Draft at port leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 310.0
1213 Jetting hose leaking on bow leg, stop low pressure pumps to fix leaking
1225 Draft at port leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 309.5
1234 Draft at port leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 309.0
1250 Draft at port leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 308.0
1255 Stop low pressure pumps on starboard leg to change to high pressure
1300 Hoses connected to high pressure pumping on starboard leg
1308 Jetting with low pressure on bow leg
1818 Stop high pressure jetting on port leg to change to low pressure
1325 High pressure jetting on starboard leg, low pressure on bow and port legs
1330 Draft at starboard leg 16.5 feet pulling hull down back to 17.5 ft leg mark: 316.9
Legs marks:
Stbd: 316.9 ft Bow: 308.8 ft Port: 308.0 ft
1342 Draft at starboard leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 316.2
1346 150spm 680psi
1355 Draft at starboard leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 315.5
1406 Draft at starboard leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 314.8
1410 - 1420 Abandon drill carried out
1425 Draft at starboard leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 314.0
1444 Draft at starboard leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 313.5
1512 Draft at starboard leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 313.0
1530 Draft at starboard leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 312.5

pág. 4 of 16
LION-ALFA MARINE CONSULTANTS


LOGBOOK
WEST COURAGEOUS RIG MOVE

1545 Draft at starboard leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 312.0
1606 Draft at starboard leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 311.5
1615 Draft at starboard leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 311.0
1625 Draft at starboard leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 310.5
1640 Draft at starboard leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 310.0
1652 Draft at starboard leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 309.5
1704 Draft at starboard leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 309.0
1715 Draft at starboard leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 308.5
1730 Draft at starboard leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 308.0
1730 Review of weather forecast and email:
Sun 21-jan-18: 1800 – 2400 Window
Mon 22-jan-18: 0000 – 2400 Window
Tue 23-jan-18: 0000 – 1800 Window
Tue 23-jan-18: 1800 – 2400 No window
Wed 24-jan-18: 0000 – 2400 No window
Thu 25-jan-18: 0000 – 2400 No window
Fri 26-jan-18: 0000 – 0600 No window
1735 Draft at starboard leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 307.5
1757 Draft at starboard leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 307.0
1805 Draft at starboard leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 306.5
1823 Draft at starboard leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 306.0
1827 Draft at starboard leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 305.5
1850 Draft at starboard leg 17.0 feet pulling hull down back to 17.5 ft leg mark: 305.0
2000 Tide changed, now draft is 18 in bow and port
2030 Draft at starboard leg 19.5 feet pulling hull down back to 20.0 ft leg mark: 305.5
2100 Draft at starboard leg 19.5 feet pulling hull down back to 20.0 ft leg mark: 303.0
2138 Draft at starboard leg 19.5 feet pulling hull down back to 20.0 ft leg mark: 302.5
2205 Draft at starboard leg 19.5 feet pulling hull down back to 20.0 ft leg mark: 302.0
2235 Draft at starboard leg 19.5 feet pulling hull down back to 20.0 ft leg mark: 301.5
2245 Draft at starboard leg 19.5 feet pulling hull down back to 20.0 ft leg mark: 301.0
2310 Draft at starboard leg 19.5 feet pulling hull down back to 20.0 ft leg mark: 300.0
Mud pumps shut down, changed jetting to bow leg
2315 Mud pumps staging up high pressure pumping in bow leg
2326 80spm 80psi
2340 Hull elevated to 16 feet draft
Legs marks:
Stbd: 302.6 ft Bow: 307.6 ft Port: 310.2 ft
2345 Draft at bow leg 18.0 feet pulling hull down back to 19.0 ft leg mark: 306.7
Mon Jan 22 Draft at bow leg 18.0 feet pulling hull down back to 19.0 ft leg mark: 305.5
0015
0020 Jetting at 160spm 220psi
0020 Draft at bow leg 18.5 feet pulling hull down back to 19.0 ft leg mark: 305.0
0025 Draft at bow leg 18.5 feet pulling hull down back to 19.0 ft leg mark: 304.5
0030 Draft at bow leg 18.5 feet pulling hull down back to 19.0 ft leg mark: 304.0
0040 Draft at bow leg 18.5 feet pulling hull down back to 19.0 ft leg mark: 303.5
0048 Draft at bow leg 18.5 feet pulling hull down back to 19.0 ft leg mark: 303.0
0054 Draft at bow leg 18.5 feet pulling hull down back to 19.0 ft leg mark: 302.5

pág. 5 of 16
LION-ALFA MARINE CONSULTANTS


LOGBOOK
WEST COURAGEOUS RIG MOVE

0105 Draft at bow leg 18.5 feet pulling hull down back to 19.0 ft leg mark: 302.0
0120 Draft at bow leg 18.5 feet pulling hull down back to 19.0 ft leg mark: 301.0
0125 Draft at bow leg 18.5 feet pulling hull down back to 19.0 ft leg mark: 300.5
0130 Draft at bow leg 18.5 feet pulling hull down back to 19.0 ft leg mark: 300.0
0135 Mud pumps shut down changing over to port leg to jet with high pressure
0145 Hoses on port leg connected to high pressure lines staging up mud pumps
0150 Hull elevated to 16 feet draft
0208 Draft at pot leg 18.5 feet pulling hull down back to 19.0 ft leg mark: 308.5
0230 Draft at port leg 18.5 feet pulling hull down back to 19.0 ft leg mark: 308.0
0250 Draft at port leg 18.0 feet pulling hull down back to 19.0 ft leg mark: 307.0
0310 Draft at port leg 18.5 feet pulling hull down back to 19.0 ft leg mark: 306.5
0325 Draft at port leg 18.5 feet pulling hull down back to 19.0 ft leg mark: 306.0
0415 Mud pumps working at 160spm 230psi
0455 Draft at port leg 19.0 feet pulling hull down back to 19.5 ft leg mark: 305.5
0520 Draft at port leg 19.0 feet pulling hull down back to 19.5 ft leg mark: 304.5
0600 Draft at port leg 19.0 feet pulling hull down back to 19.5 ft leg mark: 304.5
0630 Jetting with high pressure on port leg 160spm 210psi
0700 Keeping WTI, Jetting with high pressure on port leg 160spm 230psi
0730 Keeping WTI, Jetting with high pressure on port leg 160spm 230psi
0800 Jetting with high pressure on port leg 160spm 230psi
0815 Keeping WTI, Jetting with high pressure on port leg 160spm 230psi
0830 Keeping WTI, Jetting with high pressure on port leg 160spm 230psi, no movement observed on port
leg
0900 Hull up to 18.5 on port leg
0920 Hull down to 19.5 on port leg
0930 Keeping WTI, Jetting with high pressure on port leg 160spm 230psi, 19.5 feet draft on port leg
1000 Keeping WTI, Jetting with high pressure on port leg 160spm 230psi, 19.5 feet draft on port leg
1015 Draft at port leg 19.0 feet pulling hull down back to 19.5 ft leg mark: 304.3
1030 Draft at port leg 19.0 feet, Jetting with high pressure 160spm 230psi
1045 Port leg 19.5 feet pulling hull down, Jetting with high pressure 160spm 230psi
1125 Draft at port leg 19.0 feet pulling hull down back to 19.5 ft leg mark: 304.0
1130 Mud pumps working at 160spm 220psi
1200 Mud pumps working at 160spm 230psi
1230 Keeping WTI, Jetting with high pressure on port leg 160spm 230psi,
1300 Keeping WTI, Jetting with high pressure on port leg 160spm 220psi,
1330 Keeping WTI, Jetting with high pressure on port leg 160spm 220psi,
1400 Draft at port leg 19.0 feet pulling hull down back to 19.5 ft leg mark: 303.5
1412 Draft at port leg 19.0 feet pulling hull down back to 19.5 ft leg mark: 303.3
1450 Draft at port leg 19.0 feet pulling hull down back to 19.5 ft leg mark: 303.0
1530 Mud pumps working at 160spm 220psi
Draft at stbd: 17.5 ft draft on bow: 16.5 ft Draft on port: 19.5 ft
1600 Mud pumps working at 160spm 200psi, keeping WTI
1630 Level the rig up for PEMEX crew change by boat
1700 Hull pulling down to 19.5 feet on port leg leg mark: 303.0 ft
1755 Hull down to 19.5 ft on port leg leg mark: 302.5 ft
1810 Draft at port leg 19.0 feet pulling hull down back to 19.5 ft leg mark: 302.0

pág. 6 of 16
LION-ALFA MARINE CONSULTANTS


LOGBOOK
WEST COURAGEOUS RIG MOVE

1820 Draft at port leg 19.0 feet pulling hull down back to 19.5 ft leg mark: 301.5
1845 Draft at port leg 19.0 feet pulling hull down back to 19.5 ft leg mark: 301.0 jetting with high
pressure 160spm 200psi
1915 Draft at port leg 19.0 feet pulling hull down back to 19.5 ft leg mark: 300.5
2018 Draft at port leg 19.0 feet pulling hull down back to 19.5 ft leg mark: 300.0
2025 Shutting down mud pumps, all personnel called to prejack meeting
2050 Prejack meeting complete, all personnel to jacking stations and preparing to disconnect hoses
2055 Jacking hull up
2103 All stop for disconnect hoses on bow leg
2113 Jacking hull up
2117 All stop for disconnect hoses on starboard leg
2120 Jacking hull up
2125 All stop for disconnect hoses on port leg
2125 SAAM CITLALI called in for disconnection
2135 SAAM CITLALI disconnected from main tow bridle
2230 SAAM CITLALI received instruction from PEMEX
2250 Jacking hull up to zero air gap
2303 All stop
Legs marks:
Stbd: 339.5 ft Bow: 335.6 ft Port: 334.7 ft
2305 Hull jacking to 20 feet air gap
All stop at 20 feet air gap
Legs marks:
Stbd: 359.5 ft Bow: 355.9 ft Port: 355.6 ft
2320 Monitoring weather conditions
Tue Jan 23
0001
0700 - 0715 Review of weather forecast and email:
Tue 23-jan-18: 0000 – 1800 Window
Tue 23-jan-18: 1800 – 2400 No window
Wed 24-jan-18: 0000 – 2400 No window
Thu 25-jan-18: 0000 – 2400 No window
Fri 26-jan-18: 0000 – 0600 No window
Sat 27-jan-18: 0600 – 2400 Window
Sun 28-jan-18: 0600 – 2400 No window
Wed Jan 24 Review of weather forecast and email:
0700 - 0730 Wed 24-jan-18: 0000 – 2400 No window
Thu 25-jan-18: 0000 – 2400 No window
Fri 26-jan-18: 0000 – 0600 No window
Sat 27-jan-18: 0600 – 2400 Window
Sun 28-jan-18: 0600 – 2400 No window
Mon 29-jan-18: 0000 – 2400 No window
Tue 30-jan-18: 0000 – 0600 No window
Wed Jan 31 Oceaneering personnel boarded the rig.
2335 • Jesus A. Cárdenas Aguilar
• Hilario Ham Cabrera
• Vicente Cabrera Antonio

pág. 7 of 16
LION-ALFA MARINE CONSULTANTS


LOGBOOK
WEST COURAGEOUS RIG MOVE

• Alfredo Ojeda Rodríguez


Thu Feb 01 SAAM QUETZAL arrive to worksite and report available for towing
0142
0206 SAAM CITLALI arrive to worksite and report available for towing
0730 - 0800 SAAM CITLALI inspected and found in satisfactory condition, however; the Captain informed that
the remain on board of Diesel is about 25% of her capacity and this was informed to Pemex
contract supervisor
0814 - 0842 SAAM QUETZAL inspected and found in satisfactory condition, however; her Captain informed that
crew shall be changed, lack of fresh water, low quantity of lube oil and lack of food provision
1015 - 1030 Prejack meeting with crew
1034 Hull jacking up 1 ft
1035 All stop
1036 Resume jacking down hull to 10 feet draft for WTI
1038 All stop to check a grease hose
1042 Resume jacking down hull
1048 Hull at sea level
Legs marks:
Stbd: 339.5 ft Bow: 335.6 ft Port: 334.7 ft
1052 Hull at 7 feet draft
1054 Hull at 10 feet draft, start checking WTI
1133 - 1535 Oceaneering personnel aboard SAAM CITLALI to install DGPS system
1200 - 1430 WTI checked and maintained
1500 - 1515 Jetting hoses in Bow and port leg connected to 100%
1538 - 1555 SAAM CITLALI connected in bow tow bridle
1622 - 1852 Oceaneering personnel aboard SAAM QUETZAL to install DGPS system
1630 Hull jacked down to connect jetting lines
1637 All stop to connect jetting lines
1644 Jetting lines connected to starboard leg, hull down to floating draft
1647 All stop at 16 feet draft
1652 Jetting with low pressure in port leg with 55 psi
1656 Jetting with low pressure in stbd leg with 70 psi
1800 Hull down to 16 feet draft
1811 Changing over to high pressure in port leg
1849 High pressure lines connected to port leg system staging up mud pumps 10spm 70 psi
1900 LEIBE TIDE reported onsite available for towing and for supplying liquids to SAAM CITLALI and
SAAM QUETZAL
1910 71 spm 70 psi jetting in port leg with mud pump and low pressure jetting on starboard
1920 – 2035 LEIBE TIDE inspection carried out with satisfactory result
1930 130spm 100psi
2035 Oceaneering personnel aboard LEIBE TIDE to install DGPS system
2035 Jetting with high pressure in port leg 150spm 130psi
Legs marks:
Stbd: 16.0 ft Bow: 16.0 ft Port: 17.5 ft
Stbd: 324.5 ft Bow: 321.1 ft Port: 318.7 ft
2100 Jetting with high pressure in port leg 150spm 130psi keeping WTI
2115 Port leg at 17 ft draft, hull down to 17.5 ft leg mark: 318.2 ft

pág. 8 of 16
LION-ALFA MARINE CONSULTANTS


LOGBOOK
WEST COURAGEOUS RIG MOVE

2135 Port leg at 17.25 ft draft, hull down to 17.5 ft leg mark: 317.9 ft
2200 Jetting with high pressure in port leg and low pressure in bow and starboard legs. Keeping WTI
2210 Port leg at 17 ft draft, hull down to 17.5 ft leg mark: 317.3 ft
2230 Legs marks:
Stbd: 16.0 ft Bow: 16.0 ft Port: 17.5 ft
Stbd: 323.6 ft Bow: 321.1 ft Port: 317.3 ft
2300 Port leg at 17 ft draft, hull down to 17.5 ft. LEIBE TIDE completed fuel transfer to SAAM QUETZAL,
SAAM CITLALI informed to disconnect and SAAM QUETZAL to connect in main tow bridle
2306 SAAM CITLALI disconnected from main tow bridle
2336 SAAM QUETZAL connected to main tow bridle
2350 Port leg at 17 ft draft, hull down to 17.5 ft leg mark: 316.0 ft, keeping WTI
Fri Feb 02 LEIBE TIDE on starboard side to transfer oceaneering personnel back
0050
0100 Legs marks:
Stbd: 17.0 ft Bow: 17.0 ft Port: 18.5 ft
Stbd: 321.5 ft Bow: 319.0 ft Port: 315.0 ft
0145 Legs marks:
Stbd: 16.0 ft Bow: 17.0 ft Port: 19.0 ft
Stbd: 321.5 ft Bow: 319.0 ft Port: 314.5 ft
Jetting with high pressure in port leg 150spm 130 psi and low pressure in bow and starboard legs.
Keeping WTI
0200 Port leg at 18.5 ft draft, hull down to 19.0 ft
Legs marks:
Stbd: 16.5 ft Bow: 16.0 ft Port: 19.0 ft
Stbd: 321.5 ft Bow: 318.5 ft Port: 314.0 ft
0300 Legs marks:
Stbd: 16.0 ft Bow: 16.0 ft Port: 19.0 ft
Stbd: 321.0 ft Bow: 318.0 ft Port: 313.0 ft
0330 Port leg at 18.5 ft draft, hull down to 19.0 ft, leg mark 312.5 ft
0400 Port leg at 18.5 ft draft, hull down to 19.0 ft, leg mark 312.0 ft
0430 LEIBE TIDE informed that transfer of liquids to SAAM CITLALI is completed
0435 Port leg at 18.5 ft draft, hull down to 19.0 ft, Port leg mark 311.5 ft
0438 Bow leg at 15.5 ft draft, hull down to 16.0 ft, Bow leg mark 317.5 ft
0450 Jetting with high pressure in port leg 150 spm 130 psi and low pressure in bow and starboard legs.
Keeping WTI
Legs marks:
Stbd: 16.0 ft Bow: 16.0 ft Port: 19.0 ft
Stbd: 321.0 ft Bow: 317.5 ft Port: 311.5 ft
0455 Port leg at 18.5 ft draft, hull down to 19.0 ft, leg mark 311.0 ft
0520 Port leg at 18.5 ft draft, hull down to 19.0 ft, leg mark 310.5 ft
0600 Jetting with high pressure in port leg 160 spm 110 psi
0630 Jetting with high pressure in port leg 160 spm 110 psi
0700 Jetting with high pressure in port leg 160 spm 110 psi
0741 Port leg at 18.5 ft draft, hull down to 19.0 ft, leg mark 309.9 ft
0800 Jetting with high pressure in port leg 160 spm 110 psi
0900 Jetting with high pressure in port leg 160 spm 110 psi
0907 Port leg at 18.5 ft draft, hull down to 19.0 ft, leg mark 319.5 ft

pág. 9 of 16
LION-ALFA MARINE CONSULTANTS


LOGBOOK
WEST COURAGEOUS RIG MOVE

0930 Jetting with high pressure in port leg 160 spm 110 psi
1000 Maintaining WTI
1030 Jetting with high pressure in port leg 160 spm 110 psi
1105 Stbd leg at 15.5 ft draft, hull down to 16.0 ft
1130 Jetting with high pressure in port leg 160 spm 110 psi
1200 Jetting with high pressure in port leg 160 spm 70 psi, keeping WTI
1320 Tide raising
Legs marks:
Stbd: 16.5 ft Bow: 16.5 ft Port: 19.5 ft
Keeping WTI, Jetting with high pressure in port leg 160 spm 90 psi
1330 Jetting with high pressure in port leg 160 spm 90 psi
1406 Mesotech deployed on port bow, Keeping WTI, Jetting with high pressure in port leg 160 spm 90 psi
1435 Mesotech completed, seabed clear of debris
1510 SAAM CITLALI on side for Oceaneering personnel transfer
1533 Oceaneering personnel on SAAM CITLALI for remove DGPS equipment
1546 Keeping WTI, Jetting with high pressure in port leg 160 spm 80 psi
1620 Oceaneering personnel back on rig
1627 SAAM CITLALI released from West Courageous
1634 Legs marks:
Stbd: 17.0 ft Bow: 17.0 ft Port: 19.5 ft
Stbd: 320.2 ft Bow: 317.5 ft Port: 309.5 ft
Keeping WTI, Jetting with high pressure in port leg 160 spm 80 psi
1830 Legs marks:
Stbd: 16.5 ft Bow: 16.75 ft Port: 19.0 ft
Stbd: 320.2 ft Bow: 317.5 ft Port: 309.5 ft
Keeping WTI, Jetting with high pressure in port leg 150 spm 80 psi
1900 Keeping WTI, Jetting with high pressure in port leg 150 spm 80 psi
1930 Keeping WTI, Jetting with high pressure in port leg 150 spm 80 psi
2000 Keeping WTI, Jetting with high pressure in port leg 150 spm 80 psi, no movement observed
2100 Keeping WTI, Jetting with high pressure in port leg 150 spm 80 psi, no movement observed
2130 Port leg at 18.5 ft draft, hull down to 19.0 ft, continue Jetting with high pressure in port leg 150
spm 80 psi
Legs marks:
Stbd: 16.0 ft Bow: 16.0 ft Port: 19.0 ft
Stbd: 320.0 ft Bow: 317.5 ft Port: 309.0 ft
2200 Port leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 308.0 ft, continue Jetting with high pressure
in port leg 150 spm 80 psi, keeping WTI

2230 Port leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 307.5 ft
2300 Port leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 307.0 ft
2315 Port leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 306.5 ft
2330 Port leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 306.0 ft
2350 Port leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 305.5 ft
Sat Feb 03 Port leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 305.0 ft
0010
0100 Port leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 304.5 ft
0110 Port leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 304.0 ft

pág. 10 of 16
LION-ALFA MARINE CONSULTANTS


LOGBOOK
WEST COURAGEOUS RIG MOVE

0115 Port leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 303.5 ft
0125 Port leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 303.0 ft
0145 Rig levelled to 16.5 ft draft in all legs
0200 Stbd leg at 19.0 ft draft, Leg mark: 317.5 ft, still jetting with low pressure on starboard, observing
during 0.5 hours
0230 Stbd leg at 18.0 ft draft, hull down to 19.0 ft, Leg mark: 316.5 ft, still jetting with low pressure on
starboard, observing during 0.5 hours
0250 Stbd leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 316.0 ft, still jetting with low pressure on
starboard
0300 Stop high pressure jetting on port leg changing to low pressure lines, jetting with low pressure on
starboard
Legs marks:
Stbd: 19.0 ft Bow: 16.5 ft Port: 16.5 ft
Stbd: 316.0 ft Bow: 317.5 ft Port: 307.0 ft
0305 Stbd leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 315.5 ft
0310 Port leg jetting lines connected to low pressure, all three legs with low pressure
0320 Stbd leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 315.0 ft
0335 Stbd leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 314.5 ft
0350 Stbd leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 314.0 ft
0355 Stbd leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 313.5 ft
0405 Stbd leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 313.0 ft
0415 Stbd leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 312.5 ft
0425 Stbd leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 311.5 ft
0430 Stbd leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 310.5 ft
0435 Stbd leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 309.5 ft
0440 Stbd leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 308.5 ft
0445 Stbd leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 307.5 ft
0450 Stbd leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 306.5 ft
0455 Stbd leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 305.5 ft
0505 Stbd leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 304.5 ft
0510 Stbd leg at 18.0 ft draft
0515 Stbd leg at 17.5 ft draft, level rig to 17 feet
0525 Hull down bow to 19.0 ft, jetting all legs with low pressure
0530 Bow leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 314.0 ft
0545 Bow leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 313.5 ft
0600 Bow leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 313.0 ft
0610 Bow leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 312.0 ft
0616 Bow leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 311.0 ft
0620 Bow leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 310.5 ft
0625 Bow leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 310.0 ft
0630 Bow leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 309.0 ft
0633 Bow leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 308.5 ft
0638 Bow leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 308.0 ft
0640 Bow leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 307.5 ft
0645 Bow leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 306.5 ft
0650 Bow leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 305.5 ft

pág. 11 of 16
LION-ALFA MARINE CONSULTANTS


LOGBOOK
WEST COURAGEOUS RIG MOVE

0700 Bow leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 304.5 ft
0710 Shut down low pressure pumping on blow leg for changing of connection point on same bow leg
0800 Bow leg at 18.0 ft draft, hull down to 19.0 ft, Leg mark: 299.5 ft
0852 Bow leg at 18.0 ft draft, hull down to 19.0 ft, Leg mark: 291.5 ft
0920 Bow leg 17.5 ft draft, level the rig up
0947 Rig at 16.5 ft draft, hull down on port leg to 19.0 ft
1000 Port leg at 18.0 ft draft, hull down to 19.0 ft, Leg mark: 303.5 ft
1010 Stop jetting low pressure on port leg to reconnect on next connection point
1025 Jetting port leg with low pressure at 45psi
1030 Port leg at 18.0 ft draft, hull down to 19.0 ft, Leg mark: 302.5 ft
1255 Port leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 296.0 ft
1430 Port leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 290.5 ft
1512 Port leg at 17.5 ft draft, hull levelled to 17.0 ft draft
1516 Stbd leg at 16.5 ft draft, hull down to 18.5 ft, Leg mark: 303.0 ft
1518 Stop jetting low pressure on stbd leg to reconnect on next connection point
Legs marks:
Stbd: 18.5 ft Bow: 16.0 ft Port: 17.5 ft
Stbd: 303.0 ft Bow: 290.5 ft Port: 290.5 ft
1542 Jetting hoses connected on stbd leg. Stbd leg 18.0 ft draft, hull down to 19.0 ft, Leg mark: 302.0 ft
1548 Stbd leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 301.5 ft
1725 Stbd leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 294.0 ft
1945 Stbd leg at 18.5 ft draft, hull down to 19.0 ft, Leg mark: 281.0 ft
2000 Stop jetting low pressure on stbd leg to reconnect on next connection point
2030 Bow leg hull down to 19.0 ft, Leg mark: 287.5 ft
2105 Bow leg at 18.0 ft draft, hull down to 19.0 ft, Leg mark: 281.0 ft
2130 Jetting in all legs with low pressure
2135 Bow leg at 18.0 ft draft, hull down to 19.0 ft, Leg mark: 277.0 ft
2145 Bow leg at 18.0 ft draft Leg mark: 275.0 ft
2155 Port leg at 18.0 ft draft, hull down to 19.0 ft, Leg mark: 285.0 ft
2200 Legs marks:
Stbd: 17.0 ft Bow: 17.0 ft Port: 19.0 ft
Stbd: 282.0 ft Bow: 275.0 ft Port: 284.0 ft
2205 Port leg at 18.0 ft draft, hull down to 19.0 ft, Leg mark: 283.0 ft
2250 Port leg at 18.0 ft draft, hull down to 19.0 ft, Leg mark: 275.0 ft
2300 Pulling all legs at same time
Legs marks:
Stbd: 16.0 ft Bow: 17.5 ft Port: 18.5 ft
Stbd: 270.0 ft Bow: 270.0 ft Port: 270.0 ft
2340 Pulling all legs at same time
Legs marks:
Stbd: 16.0 ft Bow: 16.0 ft Port: 18.5 ft
Stbd: 263.0 ft Bow: 263.0 ft Port: 263.0 ft
2355 All legs noted moving freely
Legs marks:
Stbd: 16.0 ft Bow: 16.0 ft Port: 17.0 ft
Stbd: 258.5 ft Bow: 259.5 ft Port: 259.5 ft
Sun Feb 04 Disconnect jetting hoses from all legs

pág. 12 of 16
LION-ALFA MARINE CONSULTANTS


LOGBOOK
WEST COURAGEOUS RIG MOVE

0001 – 0025
0025 Monitoring drafts, sea condition and tide; keeping WTI checks
0120 Penetration in all legs 50 feet
0330 Monitoring drafts, sea condition and tide; keeping WTI checks
Legs marks:
Stbd: 16.0 ft Bow: 15.0 ft Port: 16.0 ft
Stbd: 257.0 ft Bow: 258.0 ft Port: 257.0 ft
Keeping penetration in all legs 50 feet
0600 Monitoring drafts, sea condition and tide; keeping WTI checks
1200 Monitoring drafts, sea condition and tide; keeping WTI checks
1330 Monitoring drafts, sea condition and tide; keeping WTI checks
Legs marks:
Stbd: 15.5 ft Bow: 15.0 ft Port: 15.5 ft
Stbd: 257.0 ft Bow: 258.0 ft Port: 257.0 ft
Keeping penetration in all legs 50 feet
1428 - 1442 Emergency and fire drill carried out
1530 Monitoring drafts, sea condition and tide; keeping WTI checks
Legs marks:
Stbd: 15.5 ft Bow: 15.0 ft Port: 15.5 ft
Stbd: 257.0 ft Bow: 258.0 ft Port: 257.0 ft
Keeping penetration in all legs 50 feet
1616 SAAM CITLALI reported available on site in 20 more minutes
1635 JSA Meeting
1643 SAAM CITLALI onsite
1726 - 1737 SAAM CITLALI general inspection and interview with captain
1800 Monitoring drafts, sea condition and tide; keeping WTI checks
Legs marks:
Stbd: 15.5 ft Bow: 14.0 ft Port: 15.5 ft
Stbd: 257.0 ft Bow: 258.0 ft Port: 257.0 ft
Keeping penetration in all legs 50 feet
1835 - 2005 Captain of tugs boarded the rig for pre-move meeting
1945 SAAM QUETZAL disconnected from main tow bridle
2015 - 2115 Pre-move meeting carried out with Pemex personnel, MSL, MWS, IMO, Rig Mover
2055 - 2210 Tugs’ captains disembarked
2225 LEIBE TIDE connected to main tow bridle
2230 Monitoring drafts, sea condition and tide; keeping WTI checks
Legs marks:
Stbd: 15.5 ft Bow: 14.5 ft Port: 15.5 ft
Stbd: 257.0 ft Bow: 258.0 ft Port: 257.0 ft
Keeping penetration in all legs 50 feet
2400 Monitoring drafts, sea condition and tide; keeping WTI checks
Legs marks:
Stbd: 15.5 ft Bow: 14.5 ft Port: 15.5 ft
Stbd: 257.0 ft Bow: 258.0 ft Port: 257.0 ft
Keeping penetration in all legs 50 feet
Mon Feb 05 Monitoring drafts, sea condition and tide; keeping WTI checks
0100 Legs marks:
Stbd: 15.5 ft Bow: 14.5 ft Port: 15.5 ft

pág. 13 of 16
LION-ALFA MARINE CONSULTANTS


LOGBOOK
WEST COURAGEOUS RIG MOVE

Stbd: 257.0 ft Bow: 258.0 ft Port: 257.0 ft


Keeping penetration in all legs 50 feet
0100 - 0325 Bow leg deepwell pump shut down and retrieved
0210 - 0125 M/V MONFORTE DE LEMUS alongside for personnel transfer
0330 - 0600 Hull jacked down for retrieving legs
0610 SAAM QUETZAL called in to be connected in port aft
0618 SAAM QUETZAL connection delayed due Pemex Company man instructions. Pipeline 264 marker
buoys were not installed yet
0621 Pemex contract supervisor confirmed that buoys were not installed.
OIM comments that this issue will be commented with Seadrill’s office for further instructions
0625 Daybreak
0645 Wind speed 12 – 13 knots ENE, waves 3-4 ft ENE
0745 Wind speed 11 – 12 knots ENE, waves 3-4 ft ENE
0825 - 0846 OIM, Rig mover and Pemex personnel called to Company man’s office for conference call. OIM and
Company man will call office to get instructions
0945 Wind speed 14 – 15 knots ENE, waves 2-3 ft ENE
0945 SAAM QUETZAL called in to be connected in port aft
0950 SAAM QUETZAL connected in port aft
0955 SAAM CITLALI connected in starboard aft
1017 All crew reported at jacking stations ready for departure
1030 Hull jacked down for retrieving legs to 25 feet penetration
1035 Pemex Marine Control informed about commencement of departure manoeuver from KAX-1
1036 - 1045 Picking up legs during departure manoeuver
1046 Movement noted away from KAX-1
1047 - 1125 Picking up legs during departure manoeuver.
1130 Rig at 150 meters away from KAX-1
1142 Legs at 30 feet off bottom
1153 Legs at 50 feet off bottom
1207 Legs at 75 feet off bottom
1220 - 1230 Power adjusted in all three tugs, towlines lengthened to 220 meters and power increased to
commence towing to next location. Tow control passed to Leader tug LEIBE TIDE
1225 All stop in three legs to wash out mud on spudcans and bracings
1300 Rig underway to MAY-1 in coordinates Lat.= 19° 07.58’ N; Lon.= 092° 27.44’ W
Course= 125°
Average speed: 2.4 knots
Distance travelled: 2.4 nm
Distance to go: 31.11 nm
Wind: 5 knots E knots
Seas: 2-3 ft Period 6 Secs ESE
ETA: 01:30 Hours
Keeping WTI, monitoring weather conditions and waves
1500 Rig underway to MAY-1 in coordinates Lat.= 19° 03.80’ N; Lon.= 092° 24.0’ W
Course= 125°
Average speed: 2.4 knots
Distance travelled: 6.81 nm
Distance to go: 26.3 nm
Wind: 15 knots ENE knots

pág. 14 of 16
LION-ALFA MARINE CONSULTANTS


LOGBOOK
WEST COURAGEOUS RIG MOVE

Seas: 2-3 ft Period 6 Secs E


ETA: 02:00 Hours
Keeping WTI, monitoring weather conditions and waves
1700 Rig underway to MAY-1 in coordinates Lat.= 18° 58.74’ N; Lon.= 092° 25.66’ W
Course= 125°
Average speed: 2.4 knots
Distance travelled: 12.82 nm
Distance to go: 20.51 nm
Wind: 15 knots N knots
Seas: 2-3 ft Period 6 Secs NE
ETA: 23:00 Hours
Keeping WTI, monitoring weather conditions and waves
1900 Rig underway to MAY-1 in coordinates Lat.= 18° 52.89’ N; Lon.= 092° 30.02’ W
Course= 215°
Average speed: 3.7 knots
Distance travelled: 19.82 nm
Distance to go: 13.52 nm
Wind: 15 knots NE knots
Seas: 2-3 ft Period 6 Secs NE
ETA: 23:00 Hours
Keeping WTI, monitoring weather conditions and waves
1942 Company man informed that marker buoys are installed on pipeline 264
2100 Rig underway to MAY-1 in coordinates Lat.= 18° 48.30’ N; Lon.= 092° 34.71’ W
Course= 247°
Average speed: 3.3 knots
Distance travelled: 26.51 nm
Distance to go: 6.83 nm
Wind: 15 knots NE knots
Seas: 1-2 ft Period 6 Secs NE
ETA: 23:00 Hours
Keeping WTI, monitoring weather conditions and waves
2300 Rig underway to MAY-1 in coordinates Lat.= 18° 44.78’ N; Lon.= 092° 36.75’ W
Course= 165°
Average speed: 2.6 knots
Distance travelled: 31.84 nm
Distance to go: 1.5 nm
Wind: 10 knots NNE knots
Seas: 1-2 ft Period 6 Secs NE
ETA: 23:30 Hours
Keeping WTI, monitoring weather conditions and waves
2315 Rig at 1 nm from final position, started approaching manoeuver
Tue Feb 06 Rig at 1000 meters from final position, continues approaching manoeuver
0045 All legs ready to jack, confirmed spudcans are full
0100 Jacking down legs 10 feet
0110 Jacking down 10 more feet
0115 Jacking down 1 more foot
0120 Jacking down 5 more feet
0122 Approaching to 200 meters stand off position for soft pin

pág. 15 of 16
LION-ALFA MARINE CONSULTANTS


LOGBOOK
WEST COURAGEOUS RIG MOVE

0200 Jacking down 5 more feet, 75 meters to 200-meter position


0218 Jacking down legs to 8 feet penetration
0230 All stop observing if rig moves
0235 Rig at soft pin location, 235 meters WNW from MAY-1 waiting for daylight to proceed to final
position
0641 All personnel ready at jacking stations
0649 Picking up legs to start moving to 150-meter position for first mesotech sonar scan
0650 - 0739 Rig moves from 235 meters to 150 meters
0748 – 0809 Rig at 150 meters. 1st mesotech deployed
0820 MAY-1 production personnel confirmed wells shut in
0837 - 0950 Rig is moved to 75 meters position to deploy second mesotech
0958 - 1023 2nd mesotech deployed. Previous footprints were not seen
1027 - 1058 Rig is moved to 50 meters position to deploy third mesotech
1100 - 1120 3rd mesotech deployed. Previous footprints were not seen
1121 - 1655 Rig is moved to final position
1710 Rigs final position accepted by OIM and Pemex company man, start lowering all legs to make hard
pinning
1716 Hull elevated to 12 feet draft and penetrated legs
2210 Hull at 0 foot draft, getting initial penetrations
Legs marks:
Stbd: 0.0 ft Bow: 0.0 ft Port: 0.0 ft
Stbd: 163.0 ft Bow: 162.3 ft Port: 161.8 ft
Stbd: 56.0 ft Bow: 55.3 ft Port: 54.8 ft

2235 SAAM QUETZAL disconnected from port aft
2240 SAAM CITLALI disconnected from starboard aft
2250 LEIBE TIDE disconnected from main tow bridle
2400 Rig at final position in preparations for preloading operation
Wed Feb 07 Rig mover demobilized from West Courageous to Ciudad del Carmen
1645 - 1720
End of Log

pág. 16 of 16