M&E - DAILY SITE ACTIVITIES

Project: Building Works at Tampines Neighnourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date: 8/21/2013

No. of
S/N BLK LOCATION ACTIVITY Worker
UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC'S AND PIPES
1 870A 5
(AF~AE)-(A5) BETWEEN IC-13A TO 14A

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date: 8/22/2013

No. of
S/N BLK LOCATION ACTIVITY Worker
UNDERGROUND / INSTALLATION ,PRESSURE TESTING AND HAUNCING OF IC-14A
1 870A (AF~AE)-(A5) AND IC-13A AND ITS ASSOCIATED PIPES
6
UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC'S 12A AND 11A
1 870A (AG~AE)-(A9) AND ITS ASSOCIATED PIPES.

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date: 8/23/2013

No. of
S/N BLK LOCATION ACTIVITY Worker
UNDERGROUND / EXCAVATION , BAKAU AND BASE CASTING FOR IC'S 10A, 11A &
1 870A 5
(AG~AE)-(A9-) 12A AND ITS ASSOCIATED PIPES.

INSPECTION EXPECTED AROUND 14.00 P.M

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date: 8/24/2013

No. of
S/N BLK LOCATION ACTIVITY Worker
UNDERGROUND / INSTALLATION OF IC'S 10A, 11A & 12A .
1 870A (AG~AE)-(A9-)
5
WATER TIGHTNESSS TESTING AND HAUNCING OF PIPES
ASSOCIATED TO IC'S 10A, 11A & 12A.

INSPECTION EXPECTED AROUND 11.30 P.M

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date: 8/27/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY
UNDERGROUND / (AB)- INSTALLATION,WATER TIGHTNESSS TESTING AND HAUNCING OF
1 870A (A3 ~ A8) PIPES BETWEEN IC-9A TO IC-7A.

INSPECTION EXPECTED AROUND 11.00 A.M

UNDERGROUND / (AG)- EXCAVATION ,BAKAU AND BASE CASTING FOR PIPES BETWEEN
2 870A (A5~ A9) IC-12A TO IC-14A

INSPECTION EXPECTED AROUND 16.00 HRS

ELECTRICAL
UNDERGROUND / (AY7)- EXCAVATION ,PIPE LAYING AND HAUNCHING OF TELECOM PIPE
3 870 (AX1~ AX2) FOR BLK-870A TELECOM ROOM
5
INSPECTION EXPECTED AROUND 16.00 HRS

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date: 8/28/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY
UNDERGROUND / (AG)- INSTALLATION,WATER TIGHTNESSS TESTING AND HAUNCING OF
1 870A (A5~ A9) PIPES BETWEEN IC-12A TO IC-14A

INSPECTION EXPECTED AROUND 15.00 HRS

UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC'S -1A,2A & 3A
2 870A (AX3~AX1)-(AY7~ AY6) AND ITS ASSOCIATED PIPES

INSPECTION EXPECTED AROUND 16.00 HRS

ELECTRICAL
UNDERGROUND / (AY7)- SOIL BACKFILLING OF HAUNCHED TELECOM PIPE FOR BLK-870A
3 870 5
(AX1~ AX2) TELECOM ROOM

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date: 8/29/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY
UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC'S -1A,2A ,3A &
1 870A (AX3~AX1)-(AY7~ AY6) 4A AND ITS ASSOCIATED PIPES
5
INSPECTION EXPECTED AROUND 16.00 HRS

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date: 8/30/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY
INSTALLATION OF IC'S -1A,2A ,3A & 4A AND INSTALLATION
UNDERGROUND /
1 870A ,WATER TIGHTNESSS TESTING AND HAUNCING OF PIPES
(AX3~AX1)-(AY7~ AY6) ASSOCIATED TO IC'S -1A,2A ,3A & 4A 5

INSPECTION EXPECTED AROUND 16.00 HRS

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date: 8/31/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY
INSTALLATION OF IC'S -1A, 2A & 3A AND INSTALLATION ,WATER
UNDERGROUND /
1 870A TIGHTNESSS TESTING AND HAUNCING OF PIPES ASSOCIATED TO
(AX3~AX1)-(AY7~ AY6) IC'S -1A, 2A & 3A

INSPECTION EXPECTED AROUND 10.30 HRS


5

UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC -11A'S


1 870A (AX3~AX1)-(AY7~ AY6) ASSOCIATED PIPES

INSPECTION EXPECTED AROUND 11.00 HRS

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date: 9/2/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

UNDERGROUND / INSTALLATION ,WATER TIGHTNESSS TESTING AND HAUNCING


1 870A (AX3~AX1)-(AY7~ AY6) OF PIPES ASSOCIATED TO IC -4A,

INSPECTION EXPECTED AROUND 16.00 HRS


5

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date: 9/3/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC'S -6A & 7A AND
1 870A (AC~AA)-(A8) ITS ASSOCIATED PIPES.

INSPECTION EXPECTED AROUND 15.00 HRS


5

UNDERGROUND / (A9)- EXCAVATION ,BAKAU AND BASE CASTING FOR IC-11A AND ITS
870 A (AF~AE) ASSOCIATED PIPES.

INSPECTION EXPECTED AROUND 15.00 HRS

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
04/09/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY
INSTALLATION OF IC 5A, 6A & 7A AND INSTALLATION ,WATER
UNDERGROUND /
1 870A TIGHTNESS TESTING AND HAUNCING OF PIPES ASSOCIATED TO
(AC~AA)-(A8) IC'S 5A, 6A & 7A.

INSPECTION EXPECTED AROUND 16.00 HRS


6

UNDERGROUND / (A9)- INSTALLATION ,WATER TIGHTNESSS TESTING AND HAUNCING


870 A (AF~AE) OF PIPES ASSOCIATED TO ICA-11A

INSPECTION EXPECTED AROUND 16.00 HRS

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
05/09/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

UNDERGROUND / INSTALLATION OF IC 5A AND INSTALLATION ,WATER TIGHTNESS


1 870A (AC~AA)-(A8~A9) TESTING AND HAUNCING OF PIPES ASSOCIATED TO IC-5A.

INSPECTION EXPECTED AROUND 16.00 HRS

INSTALLATION OF IC 11A AND INSTALLATION ,WATER


UNDERGROUND /
870 A TIGHTNESSS TESTING AND HAUNCING OF PIPES ASSOCIATED TO
(A8~A9)-(AF~AE) IC-11A

INSPECTION EXPECTED AROUND 16.00 HRS

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
06/09/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY
INSTALLATION OF IC 3A, 4A, 5A AND 7A AND INSTALLATION
UNDERGROUND /
1 870A ,WATER TIGHTNESS TESTING AND HAUNCING OF PIPES
(AX1~AX2)-(A8~A9) ASSOCIATED TO IC-3A, 4A, 5A AND 7A.

INSPECTION EXPECTED AROUND 16.00 HRS


6

UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC-18A AND 19A
870A (A1)-(AA~AC) AND ITS ASSOCIATED PIPES.

INSPECTION EXPECTED AROUND 16.00 HRS

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
07/09/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY
INSTALLATION OF IC 18A AND 19A AND INSTALLATION, WATER
UNDERGROUND /
1 870A TIGHTNESS TESTING AND HAUNCHING OF PIPES ASSOCIATED
(A1)-(AA~AC) TO 18A AND 19A.

INSPECTION EXPECTED AROUND 11.45 HRS


6

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
09/09/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC-5C AND ITS
1 871C (CA~CB)-(C3~C5) ASSOCIATED PIPES.

INSPECTION EXPECTED AROUND 16.00 HRS


7

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
10/09/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

UNDERGROUND / INSTALLATION OF IC 5C AND INSTALLATION AND HAUNCHING


1 871C (CA~CB)-(C3~C5) OF PIPES ASSOCIATED TO 5C.

INSPECTION EXPECTED AROUND 16.30 HRS


6

2 870A ZONE-3 INSTALLATION OF RAINWATER DOWNPIPE FOR ZONE-3

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
11/09/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC-11C & IC-12C
1 871 C (CC~CD)-(C6) AND ITS ASSOCIATED PIPES.

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
12/09/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC-11C & IC-12C
1 871 C (CC~CD)-(C6) AND ITS ASSOCIATED PIPES.

INSPECTION EXPECTED AROUND 16.30 HRS


7

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
13/09/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

UNDERGROUND / INSTALLATION OF IC 11C AND INSTALLATION, WATER TIGHTNESS


1 871 C (CC~CD)-(C6) TESTING AND HAUNCHING OF PIPES ASSOCIATED TO 11C.

INSPECTION EXPECTED AROUND 15.00 HRS


7

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
14/09/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC-12C AND ITS
1 871 C (CD)-(C1~C6) ASSOCIATED PIPES.

INSPECTION EXPECTED AROUND 11.45 HRS


7

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
16/09/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

UNDERGROUND / INSTALLATION OF IC 12C AND INSTALLATION AND HAUNCHING


1 871 C (CD)-(C1~C6) OF PIPES ASSOCIATED TO 12C.

INSPECTION EXPECTED AROUND 11.30 HRS


7

UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC-10C AND ITS
2 871 C (CB)-(C8) ASSOCIATED PIPES.

INSPECTION EXPECTED AROUND 16.00 HRS

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
17/09/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC-7C AND ITS
1 871 C (CA~CB)-(C7) ASSOCIATED PIPES.

INSPECTION EXPECTED AROUND 16.00 HRS


7

UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC-1C & IC-2C
2 871 C (CXA~CXC)-(C12~C13) AND ITS ASSOCIATED PIPES.

INSPECTION EXPECTED AROUND 16.30 HRS

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
18/09/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

UNDERGROUND / INSTALLATION OF IC 7C AND INSTALLATION, WATER TIGHTNESS


1 871 C (CA~CB)-(C7) TESTING AND HAUNCHING OF PIPES ASSOCIATED TO 7C.

INSPECTION EXPECTED AROUND 15.30 HRS

UNDERGROUND / INSTALLATION OF IC 10C AND INSTALLATION, WATER TIGHTNESS


2 871 C (CB)-(C8) TESTING AND HAUNCHING OF PIPES ASSOCIATED TO 10C. 7

INSPECTION EXPECTED AROUND 16.00 HRS

UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC-1C & IC-2C
3 871 C (CXA~CXC)-(C12~C13) AND ITS ASSOCIATED PIPES.

INSPECTION EXPECTED AROUND 16.30 HRS

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
19/09/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

INSTALLATION OF IC 1C & 2C AND INSTALLATION, WATER


UNDERGROUND /
1 871 C TIGHTNESS TESTING AND HAUNCHING OF PIPES ASSOCIATED
(CA~CB)-(C12~C13) TO IC 1C & 2C.

INSPECTION EXPECTED AROUND 16.00 HRS

7
UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC-3C AND ITS
2 871 C (CA)-(C12~C13) ASSOCIATED PIPES.

UNDERGROUND /
3 871 C INSTALLATION OF WATER PIPES.
(CD)-(C4~C11)

ELECTRICAL

INSTALLATION OF LIGHTNING CONDUITS AT BLK 870A PART B


1 870 A (A4~A9)-(AA~AF) 2
COLUMNS.

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
20/09/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC-14A & IC-15A
1 870 A (A1~A5)-(AF) AND ITS ASSOCIATED PIPES.
7

INSPECTION EXPECTED AROUND 16.00 HRS

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
21/09/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC-14A & IC-15A
1 870 A (A1~A5)-(AF) AND ITS ASSOCIATED PIPES.

INSPECTION EXPECTED AROUND 10.30 HRS

UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC-13C & IC-15C
1 871 C (CC~CD)-(C1~C4) AND ITS ASSOCIATED PIPES.

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
23/09/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY
INSTALLATION OF IC-14A & IC-15A AND INSTALLATION, WATER
UNDERGROUND /
1 870 A TIGHTNESS TESTING AND HAUNCHING OF PIPES ASSOCIATED
(A1~A5)-(AF) TO IC-14A & IC-15A..

INSPECTION EXPECTED AROUND 10.30 HRS

UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC-13C, IC-14C &
1 871 C (CC~CD)-(C1~C4) IC-15C AND ITS ASSOCIATED PIPES.

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
24/09/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

INSTALLATION OF IC-12C, IC-13C & IC-15C AND INSTALLATION,


UNDERGROUND /
1 871 C WATER TIGHTNESS TESTING AND HAUNCHING OF PIPES
(C1~C6)-(CC~CD) ASSOCIATED TO IC-12C, IC-13C & IC-15C.

INSPECTION EXPECTED AROUND 16.00 HRS


8

UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC-15C, IC-16C &
1 871 C (CA~CD)-(C1~C4) IC-17C AND ITS ASSOCIATED PIPES.

INSPECTION EXPECTED AROUND 16.00 HRS

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
25/09/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY
UNDERGROUND /
1 871 C INSTALLATION OF RAINWATER DOWNPIPE.
(CXA~CXB)-(C9~C12)

8
UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC-15C, IC-16C &
2 871 C (CA~CD)-(C1~C4) IC-17C AND ITS ASSOCIATED PIPES.

INSPECTION EXPECTED AROUND 16.00 HRS

ELECTRICAL

1 871 C (CA~CD)-(C1~C13) INSTALLATION OF LIGHTNING CONDUITS AT BLK 871C. 2

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
26/09/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY
UNDERGROUND /
1 871 C INSTALLATION OF RAINWATER DOWNPIPE.
(CXA~CXB)-(C9~C12)

8
UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC-15C, IC-16C &
2 871 C (CA~CD)-(C1~C4) IC-17C AND ITS ASSOCIATED PIPES.

INSPECTION EXPECTED AROUND 16.00 HRS

ELECTRICAL

1 871 C (CA~CD)-(C1~C13) INSTALLATION OF LIGHTNING CONDUITS AT BLK 871C. 3

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
27/09/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY
UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC-16C & IC-17C
1 871 C (CA~CC)-(C1~C4) AND ITS ASSOCIATED PIPES.
8
INSPECTION EXPECTED AROUND 16.00 HRS

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
28/09/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

INSTALLATION OF IC-16C & IC-17C AND INSTALLATION, WATER


UNDERGROUND /
1 871 C TIGHTNESS TESTING AND HAUNCHING OF PIPES ASSOCIATED TO
(CA~CC)-(C1~C4) IC-16C & IC-17C. 8

INSPECTION EXPECTED AROUND 15.30 HRS

ELECTRICAL

1 871 C (CA~CD)-(C1~C13) INSTALLATION OF LIGHTNING CONDUITS AT BLK 871C. 2

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
30/09/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

INSTALLATION OF IC-16C & IC-17C AND INSTALLATION, WATER


UNDERGROUND /
1 871 C TIGHTNESS TESTING AND HAUNCHING OF PIPES ASSOCIATED TO
(CA~CC)-(C1~C4) IC-16C & IC-17C. 8

INSPECTION EXPECTED AROUND 16.00 HRS

ELECTRICAL

1 871 C (CA~CD)-(C1~C13) INSTALLATION OF LIGHTNING CONDUITS AT BLK 871C.

2 870 A (AA~AF)-(A1~A5) INSTALLATION OF LIGHTING CONDUITS AT BLK 870A.

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
01/10/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC-18C AND ITS
1 871 C (CA~CB)-(C1) ASSOCIATED PIPES.
8

INSPECTION EXPECTED AROUND 16.00 HRS

ELECTRICAL

1 871 C (CA~CD)-(C1~C13) INSTALLATION OF LIGHTNING CONDUITS AT BLK 871C.

2 870 A (AA~AF)-(A1~A5) INSTALLATION OF LIGHTING CONDUITS AT BLK 870A.

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
02/10/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

UNDERGROUND / INSTALLATION OF IC-18C AND INSTALLATION, WATER TIGHTNESS


1 871 C (CA~CB)-(C1) TESTING AND HAUNCHING OF PIPES ASSOCIATED TO IC-18C.
8

INSPECTION EXPECTED AROUND 16.00 HRS

ELECTRICAL

INSTALLATION OF LIGHTING & POWERPOINT CONDUITS AT BLK


1 870 A (AA~AF)-(A1~A5) 5
870A.

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
03/10/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC-2C, IC-3C, IC-7C
1 871 C (CXA~CXB)-(C7~C12) & IC-8C AND ITS ASSOCIATED PIPES.
8

INSPECTION EXPECTED AROUND 16.00 HRS

ELECTRICAL

INSTALLATION OF LIGHTING & POWERPOINT CONDUITS AT BLK


1 870 A (AA~AF)-(A1~A5) 5
870A.

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
04/10/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

INSTALLATION OF IC-7C, IC-8C, IC-2C & IC-3C AND


UNDERGROUND /
1 871 C INSTALLATION, WATER TIGHTNESS TESTING AND HAUNCHING
(CXA~CXB)-(C7~C12) OF PIPES ASSOCIATED TO IC-7C, IC-8C, IC-2C & IC-3C.

INSPECTION EXPECTED AROUND 16.00 HRS

8
UNDERGROUND / (B1)- EXCAVATION ,BAKAU AND BASE CASTING FOR IC-1B & IC-2B
2 871 B (BA~BF) AND ITS ASSOCIATED PIPES.

INSPECTION EXPECTED AROUND 16.00 HRS

2nd Storey / (AA~AF)-


3 870 A INSTALLATION OF SANITARY PIPES FOR DWELLING UNITS.
(A1~A5)

ELECTRICAL

2nd Storey / (AA~AF)- INSTALLATION OF LIGHTING & POWERPOINT CONDUITS AT BLK


1 870 A 5
(A1~A5) 870A.

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
05/10/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

UNDERGROUND / (B1)- INSTALLATION OF IC-1B AND INSTALLATION AND HAUNCHING


1 871 B (BA~BF) OF PIPES ASSOCIATED TO IC-1B.

INSPECTION EXPECTED AROUND 11.30 HRS 8

2nd Storey / (AA~AF)-


2 870 A INSTALLATION OF SANITARY PIPES FOR DWELLING UNITS.
(A1~A5)

ELECTRICAL
2nd Storey / (AA~AF)- INSTALLATION OF LIGHTING & POWERPOINT CONDUITS AT BLK
1 870 A 5
(A1~A9) 870A.

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
07/10/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

UNDERGROUND / (B1)- EXCAVATION ,BAKAU AND BASE CASTING FOR IC-2B & IC-3B
1 871 B (BA~BE) AND ITS ASSOCIATED PIPES.

INSPECTION EXPECTED AROUND 17.00 HRS 8

2nd Storey / (AA~AF)-


2 870 A INSTALLATION OF SANITARY PIPES FOR DWELLING UNITS.
(A1~A5)

ELECTRICAL
2nd Storey / (AA~AF)- INSTALLATION OF LIGHTING & POWERPOINT CONDUITS AT BLK
1 870 A 5
(A4~A9) 870A.

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
08/10/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

UNDERGROUND / (B1)- INSTALLATION OF IC-2B & IC-3B AND INSTALLATION, WATER


1 871 B TIGHTNESS TESTING AND HAUNCHING OF PIPES ASSOCIATED TO
(BA~BE) IC-2B & IC-3B.

INSPECTION EXPECTED AROUND 16.30 HRS 8

2nd Storey / (AA~AF)-


2 870 A INSTALLATION OF SANITARY PIPES FOR DWELLING UNITS.
(A1~A5)

ELECTRICAL
2nd Storey / (AA~AF)- INSTALLATION OF LIGHTING & POWERPOINT CONDUITS AT BLK
1 870 A 5
(A4~A9) 870A.

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
09/10/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC-4B, IC-5B & IC-
1 871 B (B1~B4)-(BA~BD) 6B AND ITS ASSOCIATED PIPES.

INSPECTION EXPECTED AROUND 16.00 HRS

2nd Storey / (AA~AF)-


2 870 A INSTALLATION OF SANITARY PIPES FOR DWELLING UNITS.
(A4~A9)

2nd Storey / (AA~AF)-


3 870 A INSTALLATION OF RAINWATER DOWN PIPES.
(A4~A9)

ELECTRICAL
2nd Storey / (AA~AF)- INSTALLATION OF LIGHTING & POWERPOINT CONDUITS AT BLK
1 870 A 5
(A4~A9) 870A.

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
10/10/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

INSTALLATION OF IC-4B & IC-5B AND INSTALLATION, WATER


UNDERGROUND /
1 871 B TIGHTNESS TESTING AND HAUNCHING OF PIPES ASSOCIATED TO
(B1~B4)-(BA~BD) IC-4B & IC-5B.

INSPECTION EXPECTED AROUND 16.00 HRS

10

2nd Storey / (AA~AF)- INSTALLATION OF CAST-IN SLEEVES & SOCKETS FOR SANITARY
2 870 A (A4~A9) PIPES.

3 - UNDERGROUND EXCAVATION AND LEAN CONCRETE FOR MANHOLE 2.

ELECTRICAL
2nd Storey / (AA~AF)- INSTALLATION OF LIGHTING & POWERPOINT CONDUITS AT BLK
1 870 A 5
(A4~A9) 870A.

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
11/10/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC-3C & IC-4C
1 871 C (C7~C12)-(CXA) AND ITS ASSOCIATED PIPES.

INSPECTION EXPECTED AROUND 16.00 HRS

10

2nd Storey / (AA~AF)- INSTALLATION OF CAST-IN SLEEVES & SOCKETS FOR SANITARY
2 870 A (A4~A9) PIPES.

3 - UNDERGROUND EXCAVATION AND LEAN CONCRETE FOR MANHOLE 2.

ELECTRICAL
2nd Storey / (AA~AF)- INSTALLATION OF LIGHTING & POWERPOINT CONDUITS AT BLK
1 870 A 5
(A4~A9) 870A.

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
12/10/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC-6B AND ITS
1 871 B (B1~B4)-(BA~BC) ASSOCIATED PIPES.

INSPECTION EXPECTED AROUND 11.30 HRS

UNDERGROUND / INSTALLATION OF IC-3C AND INSTALLATION, WATER TIGHTNESS


2 871 C (C7~C12)-(CXA) TESTING AND HAUNCHING OF PIPES ASSOCIATED TO IC-3C.
10

INSPECTION EXPECTED AROUND 11.30 HRS

2nd Storey / (AA~AF)- INSTALLATION OF CAST-IN SLEEVES & SOCKETS FOR SANITARY
3 870 A (A4~A9) PIPES.

4 - UNDERGROUND EXCAVATION AND LEAN CONCRETE FOR MANHOLE 2.

ELECTRICAL
2nd Storey / (AY1~AY8)- INSTALLATION OF LIGHTING & POWERPOINT CONDUITS AT BLK
1 870 A 5
(AX1~AX4) 870A (Part C).

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
14/10/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

UNDERGROUND / INSTALLATION OF IC-6B AND INSTALLATION, WATER TIGHTNESS


1 871 C (C7~C12)-(CXA) TESTING AND HAUNCHING OF PIPES ASSOCIATED TO IC-6B.

INSPECTION EXPECTED AROUND 16.30 HRS

13
2nd Storey / (AY1~AY8)- INSTALLATION OF CAST-IN SLEEVES & SOCKETS FOR SANITARY
2 870 A (AX1~AX4) PIPES (Part C).

3 - UNDERGROUND EXCAVATION, BAKAU AND BASE CASTING FOR MANHOLE 2.

INSPECTION EXPECTED AROUND 16.30 HRS

ELECTRICAL

2nd Storey / (AY1~AY8)- INSTALLATION OF LIGHTING & POWERPOINT CONDUITS AT BLK


1 870 A 5
(AX1~AX4) 870A (Part C).

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
16/10/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

INSTALLATION OF CAST-IN SLEEVES & SOCKETS FOR PLUMBING


1 871 B (B3) - (BA) PIPES (Part A).

2nd Storey / (AY1~AY8)- INSTALLATION OF CAST-IN SLEEVES & SOCKETS FOR SANITARY
2 870 A 13
(AX1~AX4) PIPES (Part C).

3 - UNDERGROUND EXCAVATION, BAKAU AND BASE CASTING FOR MANHOLE 2.

INSPECTION EXPECTED AROUND 16.30 HRS

ELECTRICAL

2nd Storey / (AY1~AY8)- INSTALLATION OF LIGHTING & POWERPOINT CONDUITS AT BLK


1 870 A 5
(AX1~AX4) 870A (Part C).

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
17/10/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC-12B AND ITS
1 871 B (B4~B6) - (BE~BF) ASSOCIATED PIPES.

INSPECTION EXPECTED AROUND 16.00 HRS

2nd Storey / (AY1~AY8)- INSTALLATION OF CAST-IN SLEEVES & SOCKETS FOR SANITARY 13
2 870 A (AX1~AX4) PIPES (Part C).

3 - UNDERGROUND EXCAVATION, BAKAU AND BASE CASTING FOR MANHOLE 2.

INSPECTION EXPECTED AROUND 16.00 HRS

ELECTRICAL

2nd Storey / (AY1~AY8)- INSTALLATION OF LIGHTING & POWERPOINT CONDUITS AT BLK


1 870 A 5
(AX1~AX4) 870A (Part C).

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
18/10/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

INSTALLATION OF IC-12B AND INSTALLATION, WATER


UNDERGROUND /
1 871 B TIGHTNESS TESTING AND HAUNCHING OF PIPES ASSOCIATED TO
(B4~B6) - (BE~BF) IC-12B.

INSPECTION EXPECTED AROUND 16.30 HRS

UNDERGROUND / (CA) - EXCAVATION ,BAKAU AND BASE CASTING FOR IC-8C & IC-18C
2 871 C (C2~C5) AND ITS ASSOCIATED PIPES.

INSPECTION EXPECTED AROUND 16.30 HRS 13

2nd Storey / (AY1~AY8)- INSTALLATION OF CAST-IN SLEEVES & SOCKETS FOR SANITARY
3 870 A (AX1~AX4) PIPES (Part C).

4 - UNDERGROUND EXCAVATION, BAKAU AND BASE CASTING FOR MANHOLE 2.

INSPECTION EXPECTED AROUND 16.00 HRS

ELECTRICAL

2nd Storey / (AY1~AY8)- INSTALLATION OF LIGHTING & POWERPOINT CONDUITS AT BLK


1 870 A 5
(AX1~AX4) 870A (Part C).

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
19/10/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

UNDERGROUND / (CA) - INSTALLATION OF IC-8C AND INSTALLATION, WATER TIGHTNESS


1 871 C (C3~C7) TESTING AND HAUNCHING OF PIPES ASSOCIATED TO IC-8C.

INSPECTION EXPECTED AROUND 11.30 HRS

UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC-13B AND ITS
2 871 B (B5~B7) - (BE~BF) ASSOCIATED PIPES.

INSPECTION EXPECTED AROUND 11.30 HRS 13

2nd Storey / (C7~C13)- INSTALLATION OF CAST-IN SLEEVES & SOCKETS FOR SANITARY
3 871 C (CXA~CXD) PIPES AT BLK 871 C (Part B).

4 - UNDERGROUND EXCAVATION, BAKAU AND BASE CASTING FOR MANHOLE 2.

INSPECTION EXPECTED AROUND 11.30 HRS

ELECTRICAL

2nd Storey / (C7~C13)- INSTALLATION OF LIGHTING & POWERPOINT CONDUITS AT BLK


1 871 C 5
(CXA~CXD) 871 C (Part B).

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
21/10/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

UNDERGROUND / (CA) - EXCAVATION ,BAKAU AND BASE CASTING FOR IC-18C AND ITS
1 871 C (C2~C3) ASSOCIATED PIPES.

INSPECTION EXPECTED AROUND 16.30 HRS

INSTALLATION OF IC-13B AND INSTALLATION, WATER


UNDERGROUND /
2 871 B TIGHTNESS TESTING AND HAUNCHING OF PIPES ASSOCIATED TO
(B5~B7) - (BE~BF) IC-13B.

INSPECTION EXPECTED AROUND 16.30 HRS 13

2nd Storey / (C7~C13)- INSTALLATION OF CAST-IN SLEEVES & SOCKETS FOR SANITARY
3 871 C (CXA~CXD) PIPES AT BLK 871 C (Part B).

INSTALLATION OF MANHOLE 2 AND INSTALLATION AND


4 - UNDERGROUND HAUNCHING OF PIPES ASSOCIATED TO MANHOLE 2.

INSPECTION EXPECTED AROUND 16.30 HRS

ELECTRICAL

2nd Storey / (C7~C13)- INSTALLATION OF LIGHTING & POWERPOINT CONDUITS AT BLK


1 871 C 5
(CXA~CXD) 871 C (Part B).
Signature of M&E Engineer
M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
22/10/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC-15B AND ITS
1 871 B (B5~B8) - (BF) ASSOCIATED PIPES.

INSPECTION EXPECTED AROUND 16.30 HRS

UNDERGROUND / EXCAVATION ,BAKAU AND BASE CASTING FOR IC-8B AND ITS
2 871 B (B4~B8) - (BA) ASSOCIATED PIPES.

INSPECTION EXPECTED AROUND 16.30 HRS 13

2nd Storey / (C7~C13)- INSTALLATION OF CAST-IN SLEEVES & SOCKETS FOR SANITARY
3 871 C (CXA~CXD) PIPES AT BLK 871 C (Part B).

EXCAVATION, BAKAU AND BASE CASTING FOR MANHOLE 2 AND


4 - UNDERGROUND ITS ASSOCIATED PIPES..

INSPECTION EXPECTED AROUND 16.30 HRS

ELECTRICAL

2nd Storey / (C7~C13)- INSTALLATION OF LIGHTING & POWERPOINT CONDUITS AT BLK


1 871 C 6
(CXA~CXD) 871 C (Part B).
Signature of M&E Engineer
M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
23/10/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

INSTALLATION OF IC-15B AND INSTALLATION, WATER


UNDERGROUND /
1 871 B TIGHTNESS TESTING AND HAUNCHING OF PIPES ASSOCIATED TO
(B5~B8) - (BF) IC-15B.

INSPECTION EXPECTED AROUND 16.30 HRS

UNDERGROUND / INSTALLATION OF IC-8B AND INSTALLATION, WATER TIGHTNESS


2 871 B (B4~B8) - (BA) TESTING AND HAUNCHING OF PIPES ASSOCIATED TO IC-8B.

INSPECTION EXPECTED AROUND 16.30 HRS 13

2nd Storey / (C7~C13)- INSTALLATION OF CAST-IN SLEEVES & SOCKETS FOR SANITARY
3 871 C (CXA~CXD) PIPES AT BLK 871 C (Part B).

EXCAVATION, BAKAU AND BASE CASTING FOR MANHOLE 2 AND


4 - UNDERGROUND ITS ASSOCIATED PIPES..

INSPECTION EXPECTED AROUND 16.30 HRS

ELECTRICAL

2nd Storey / (C7~C13)- INSTALLATION OF LIGHTING & POWERPOINT CONDUITS AT BLK


1 871 C 6
(CXA~CXD) 871 C (Part B).
Signature of M&E Engineer
M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
24/10/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

2nd Storey / (C1~C6)- INSTALLATION OF CAST-IN SLEEVES & SOCKETS FOR SANITARY
1 871 C (CA~CD) PIPES AT BLK 871 C (Part A).

13
EXCAVATION, BAKAU AND BASE CASTING FOR MANHOLE 2 AND
2 - UNDERGROUND ITS ASSOCIATED PIPES..

INSPECTION EXPECTED AROUND 16.30 HRS

ELECTRICAL
2nd Storey / (C1~C6)- INSTALLATION OF LIGHTING & POWERPOINT CONDUITS AT BLK
1 871 C 6
(CA~CD) 871 C (Part A).

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
25/10/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

2nd Storey / (C1~C6)- INSTALLATION OF CAST-IN SLEEVES & SOCKETS FOR SANITARY
1 871 C (CA~CD) PIPES AT BLK 871 C (Part A).

INSTALLATION OF MANHOLE 2 AND INSTALLATION AND


2 - UNDERGROUND HAUNCHING OF PIPES ASSOCIATED TO MANHOLE 2. 13

INSPECTION EXPECTED AROUND 16.30 HRS

1st Storey / (BA~BF) -


3 871 B INSTALLATION OF CAST-IN RAINWATER DOWNPIPES.
(B1~B5)

ELECTRICAL

2nd Storey / (C1~C6)- INSTALLATION OF LIGHTING & POWERPOINT CONDUITS AT BLK


1 871 C (CA~CD) 871 C (Part A).

1st Storey / (BA~BF) -


2 871 B INSTALLATION OF LIGHTNING CONDUITS AT BLK 871 B (Part A).
(B1~B5)

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
26/10/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

2nd Storey / (C1~C6)- INSTALLATION OF CAST-IN SLEEVES & SOCKETS FOR SANITARY
1 871 C (CA~CD) PIPES AT BLK 871 C (Part A).

INSTALLATION OF MANHOLE 2 AND INSTALLATION AND


2 - UNDERGROUND HAUNCHING OF PIPES ASSOCIATED TO MANHOLE 2. 13

INSPECTION EXPECTED AROUND 16.30 HRS

1st Storey / (M1~M3) -


3 870 B INSTALLATION OF RAINWATER SUMP AT MSCP.
(MD~MG)

ELECTRICAL

2nd Storey / (C1~C6)- INSTALLATION OF LIGHTING & POWERPOINT CONDUITS AT BLK


1 871 C (CA~CD) 871 C (Part A). 6

Signature of M&E Engineer


M&E - DAILY SITE ACTIVITIES
Project: Building Works at Tampines Neighbourhood 8 Contract 30 (Total 380 Dwelling Units)
& Contingency Works
Date:
28/10/2013

No. of
S/N BLK LOCATION ACTIVITY Worker

SANITARY

2nd Storey / (C1~C6)- INSTALLATION OF CAST-IN SLEEVES & SOCKETS FOR SANITARY
1 871 C (CA~CD) PIPES AT BLK 871 C (Part A).

INSTALLATION OF MANHOLE 2 AND INSTALLATION AND


2 - UNDERGROUND HAUNCHING OF PIPES ASSOCIATED TO MANHOLE 2.
14
INSPECTION EXPECTED AROUND 16.30 HRS

UNDERGROUND / EXCAVATION, BAKAU AND BASE CASTING FOR RAINWATER


3 870 B (M1~M3) - (MD~MG) SUMP AND ITS ASSOCIATED PIPES.

ELECTRICAL
2nd Storey / (C1~C6)- INSTALLATION OF LIGHTING & POWERPOINT CONDUITS AT BLK
1 871 C 6
(CA~CD) 871 C (Part A).

Signature of M&E Engineer


1500 150 10.5 2362500 78.75
100 300 30000

111.423
TBM 1.89 113.313
IC-12 2.265 111.048 110.888
1C-11 2.178 111.135 110.975
1C-10 2.125 111.188 111.028

112.1
TBM 1.129 113.229
IC-9A 3.245 109.984 109.824
1C-7A 2.945 110.284 110.124
1C-10 2.125 111.104 110.944

112.1
TBM 1.208 113.308
IC-12A 2.325 110.983 110.823 length
1C-14A 2.499 110.809 110.649 differ level
gradient

110.86 length
110.64 differ level
gradient

111.42
TBM 1.859 113.279
IC-1A 2.529 110.75 110.59
1C-1A 2.7 110.579 110.419
1C-2A 2.719 110.56 110.4
1C-3A 2.845 110.434 110.274
18
0.174
103.4483

18
0.22
81.81818
INCOME 3000
OUT 1000
OUT 106
OUT 46.8
OUT 5477.27
3000 3630.07
6630.07 6000 630.07

You might also like