4 - Installation

1007051a

W1 W1 Filling flange
1 1 Gas cylinder
2 2 Pressure reducer regulating valve
3 (0 9.0 bar) 3 Pressure gauge (0 up to 9.0 bar)
4 4 Safety valve
31 Fig. 31 Gas filling device connected

+20 SF6 At an ambient temperature other than +20°C, the SF 6


1 filling pressure must be taken from the diagram (Fig.
1).
When filling is completed, unscrew the hose of the fill-
4 Nm ing device and close the filling flange. Screw on the
union nut by hand (4 Nm). Ensure that all parts are
clean.

4.7.2 4.7.2 Leakage Test after Installation

SF6 After successful assembly of the circuit-breaker and


filling with SF6 gas, the tube connections should be
checked for leakages.
A leak detector must be used.
If a leak is detected:

WARNING
Release the SF6-pressure before working
SF6 on the screw connections of the gas
chamber.
If a leak is discovered, undo the leaking connection
and check the sealing surface for damage or foreign
bodies. Then fit a new seal, remake the connection
and repeat the leak test.