Appendix G: Lpu Package (6Mw + 3Mw)
Appendix G: Lpu Package (6Mw + 3Mw)
11kV
SPARE SPARE
0.4/11.5kV
0.4/11.5kV 0.4/11.5kV xx MVA
xx MVA xx MVA (Optional)
11kV LEGEND
Firm Scope
630A VCB (TYP)
Optional Scope
2X3CX185sq.mm XLPE cable (Note‐2)
LPU SCOPE
BATTERY LIMIT
11kV Switchboard in WMS‐5 OTHERS' SCOPE
Notes:
1 The generator configuration is only for information. CONTRACTOR may propose alternative schemes
2 Distance between LPU location and WMS substation is approximately 100m. CONTRACTOR to verify and
confirm the same during site visit and include cables accordingly in the scope.
3 11kV switchboard shall be designed (Continous and short time ratings) to include the optional 3MW power to
CONCEPTUAL SINGLE LINE DIAGRAM FOR LPU be added in future.
4 CONTRACTOR to submit the details of the proposed generation scheme including the provision for future
optional scope.
5 Earthing and lightning protection system for the LPU shall be included in CONTRACTOR scope including the
main grounding grid.
6 All cabling works within the package and cabling to PURCHASER's load including terminations at both ends shall
b eincluded in CONTRACTOR scope.
7 CONTRACTOR to remove existing cable from 11kV switchboard in WMS‐5 and reterminate the same at WMS‐5
soft starter prior to connecting the LPU cable to he 11kV Switchboard.