2014
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Pragati Mahalakshmi, South block no. 62,
Yeshwantpur, Bangalore 560022
Karnataka
Kind Attn.: Mr. Joseph Kurian – Dy. General Manager
Sub.: 1. Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff
Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01
2. Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-II) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff
Based Competitive Bidding Route
Tender Specification No.: TBCB/765KV/02(N-M)/ERE02
With reference to the subject project(s), we would like to inform you that, we are in receipt of
following two notification of award:
1. Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem Transmission
Line (Part-I) (with Hex Zebra Conductor) associated with Transmission System pertaining
to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff Based Competitive
Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01
2. Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem Transmission
Line (Part-II) (with Hex Zebra Conductor) associated with Transmission System pertaining to
IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff Based Competitive Bidding
Route
Tender Specification No.: TBCB/765KV/02(N-M)/ERE02
GAMMON INDIA LIMITED (T & D Business)
//2//
As per our scope of work, we have to do Route alignment, Detailed Survey, tower spotting,
check survey soil investigation, Foundation, Earthing, Tower Erection, stringing, Testing &
Commissioning of subject line.
In order to start above mentioned activities, we require following documents from PGCIL.
1. Tower Spotting Data & Sag Template Curve
2. Foundation Drawings
3. Structural drawings & Bill of materials for stubs and templates.
4. Structural drawings & Bill of materials for towers and extensions.
5. Tower Accessories (Number Plate, Danger Plate, Phase Plate, Circuit Plate, Bird Guard,
ACD etc.) and Earthing drawings.
Further, we understand from site that the subject line(s) comes under Wind Zone – 2 & wind
zone -4 Terrain category and we have already executed following projects for 765 KV D/C with
Hex Zebra Conductor under for Wind Zone – 2 & Wind Zone - 4 Terrain category. The details
are as under:
Sr. Wind
Name of Project Contract Agreement No.
No. Zone
Tower Package TW03 for II NOA No.: CC-CS/136-
WR1/TW-1023/3/G6/NOA-
1. 765kV D/C Raigarh (Tomnar) -
I&II/3751 & 3752, dtd.15/7/11
Raigarh (Kotra) T/L
Tower Package TW02 for IV
NOA No.: CC-CS/136-WR1/TW-
765kV D/C Champa Pooling
2. 1022/3/G6/NOA-I& II/3753 &
Station–Raipur Pooling Station
3754, dtd.15/7/11
T/L
We request you to kindly confirm if the documents of above referred projects can be used for
the subject project also. If not, then kindly arrange to release the documents as requested
Uday Patil
(Sr. Manager, Contracts-T & D Business)
Cc. 1. Mr. R N Singh, CEO, Powergrid NM Transmission Limited, Bangalore.
2. Mr. G K Sharma, DGM (Engg.), PGCIL, Gurgaon.
3. Mr. Pankaj Pande, CM(Regulatory Cell), PGCIL, Gurgaon.
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Pragati Mahalakshmi, South block no. 62,
Yeshwantpur, Bangalore 560022
Karnataka
Kind Attn.: Mr. Joseph Kurian – Dy. General Manager
Sub.: 1. Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff
Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01
2. Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-II) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff
Based Competitive Bidding Route
Tender Specification No.: TBCB/765KV/02(N-M)/ERE02
2. Supply contract for Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam -
Salem Transmission Line (Part-II) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff Based
Competitive Bidding Route
Tender Specification No.: TBCB/765KV/02(N-M)/ERE02
NOA No. PGNMTL/765 kV/02(N-M)/ERE02/NOA-I/12 & NOA – II/13 dated 16.05.2014
Thanking You,
Yours faithfully,
For Gammon India Limited
Uday Patil
(Sr. Manager, Contracts – T&D Business)
Cc. 1. Mr. S K Mishra, GM (QA&I), PGCIL, Gurgaon
2. Mr. G K Sharma, DGM (Engg.), PGCIL, Gurgaon.
3. Mr. Pankaj Pande, CM(Regulatory Cell), PGCIL, Gurgaon.
Ref: GIL/AL/G-289&290/15949 Date: 28.05.2014
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Pragati Mahalakshmi, South block no. 62,
Yeshwantpur, Bangalore 560022
Karnataka
Kind Attn.: Mr. Joseph Kurian – Dy. General Manager
Sub.: 1. Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff
Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01
2. Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-II) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff
Based Competitive Bidding Route
Tender Specification No.: TBCB/765KV/02(N-M)/ERE02
Ref.: 1. NOA No. PGNMTL/765 kV/02(N-M)/ERE01/NOA-I/10 & NOA-II/11 dated
16.05.2014.
2. NOA No. PGNMTL/765 kV/02(N-M)/ERE02/NOA-I/12 & NOA – II/13 dated
16.05.2014
Dear Sir,
As per clause no. 30.8, Section – III, Page no. 68 of General Conditions of Contract (GCC), we
have to take Storage and Erection insurance of the materials being supplied by Powergrid NM
Transmission Limited, for the subject project.
In this regard, we request you to inform the value of the Owner Supplied Materials (OSM) in
order to get the quotations for insurance from insurance company and submit the same to you
for your approval.
Please arrange to send the details of OSM value at the earliest.
Thanking You,
Yours faithfully,
For Gammon India Limited
Uday Patil
(Sr. Manager, Contracts – T&D Business)
Cc. 1. Mr. R N Singh, CEO, Powergrid NM Transmission Limited, Bangalore.
2. Mr. Pankaj Pande, CM (Regulatory Cell), PGCIL, Gurgaon.
With reference to the subject project(s), please find below our co-ordination team:
Thanking You,
Yours faithfully,
For Gammon India Limited
Uday Patil
(Sr. Manager, Contracts – T&D Business)
With reference to the subject project, we are pleased to inform you that we have established
our Site Office and store at Dharmapuri District & also deputed Mr. Mahesh Kulkarni as a
Project In-charge. Address of Site Office is as under:
SITE OFFICE & STORE :
M/S Gammon India limited,
At post Pillaparthy ,
Taluka-Pappiredipatti,
Dist Dharmapuri 635301
Tamil Nadu
Thanking You,
Yours faithfully,
For Gammon India Limited
D Suryanarayana
(Associate Vice President, Marketting – T&D Business)
Cc. 1. Mr. R N Singh, CEO, Powergrid NM Transmission Limited, Bangalore.
With reference to the subject project, we are pleased to inform you that we have established
our Site Office and store at Villupuram District & also deputed Mr. Mahesh Kulkarni as a
Project In-charge. Address of Site Office is as under:
SITE OFFICE & STORE :
M/S Gammon India limited,
Thalaivasal, S/o Krishanan,
Rayappur Village & Post, Chinna Salem Taluk,
Villupuram District,
Tamil Nadu - 606201
Thanking You,
Yours faithfully,
For Gammon India Limited
D Suryanarayana
(Associate Vice President, Marketting – T&D Business)
With reference to the subject project(s), please find below our co-ordination team:
Thanking You,
Yours faithfully,
For Gammon India Limited
D Suryanarayana
(Associate Vice President, Marketing – T&D Business)
Cc. 1. Mr. R N Singh, CEO, Powergrid NM Transmission Limited, Bangalore.
With reference to the subject project(s), please find below our co-ordination team:
Thanking You,
Yours faithfully,
For Gammon India Limited
D Suryanarayana
(Associate Vice President, Marketing – T&D Business)
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Pragati Mahalakshmi, South block no. 62,
Yeshwantpur, Bangalore 560022
Karnataka
Kind Attn.: Mr. Joseph Kurian – Dy. General Manager
Sub.: 1. Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff
Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01
Dear Sir,
You are kindly aware that above contracts were awarded on 16.05.14 and we are unable to
carry out any meaningful execution since required stubs supply is still awaited. In view of this
we are unable to deploy necessary resources. Immediate supply of stubs is to be ensured to
avoid further delays and execution pressure at a later date which results in deployment of
disproportionate workforce at inordinately high cost.
We want to avoid pressure of execution within original completion on us due to avoidable initial
delays not attributable to us. We also want to ensure safety of our work force which at times
becomes extremely difficult to maintain while executing with un-planned & disproportionate
resources at site.
To avoid further delays in foundation work, we request you to please expedite the supply of
stubs for these contracts which ensures smooth completion of foundation work except for any
ROW issues.
Considering the delays so far in supply of stubs and we may send you the revised bar chart for
your approval as these delays are not attributable to us.
Further the following issues still unattended and request your kind attention for the same and
issue us the necessary approvals
1. As per clause no. 30.8, Section – III, Page no. 68 of General Conditions of Contract
(GCC), we have to take Storage and Erection insurance of the materials being supplied
by Powergrid NM Transmission Limited, for the subject project. In this regard, we
request you to inform the value of the Owner Supplied Materials (OSM) in order to get
the quotations for insurance from insurance company and submit the same to you for
your approval.
2. Engineering documents like Drawings for stubs, Stub setting templates , foundation
drawings , structural drawings, line materials drawings including hardware fittings,
earthing & tower accessories drawings.
3. Source Approval for usage of Cement (including PPC grade) & steel.
Kindly arrange for the needful accordingly at the earliest.
Thanking You,
Yours faithfully,
For Gammon India Limited
D Suryanarayana
(Associate Vice President, Marketting – T&D Business)
Cc.
1. Mr. R N Singh, CEO, Powergrid NM Transmission Limited, Bangalore.
2. Mr. Pankaj Pande, CM (Regulatory Cell), PGCIL, Gurgaon.
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Pragati Mahalakshmi, South block no. 62,
Yeshwantpur, Bangalore 560022
Karnataka
Kind Attn.: Mr. Joseph Kurian – Dy. General Manager
Sub.: 1. Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff
Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01
2. Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-II) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff
Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE02
Ref.: 1. NOA No. PGNMTL/765 kV/02(N-M)/ERE01/NOA-I/10 & NOA-II/11 dated
16.05.2014.
2. NOA No. PGNMTL/765 kV/02(N-M)/ERE02/NOA-I/12 & NOA – II/13 dated
16.05.2014
Dear Sir,
With reference to the subject project, enclosed herewith, please find two sets of Bar-Chart for
your scrutiny and approval.
Kindly accord your approval for the same at the earliest and return one signed and stamped
copy to us.
Thanking You,
Yours faithfully,
For Gammon India Limited
D Suryanarayana
(Associate Vice President – T&D Business)
Cc.
1. Mr. R N Singh, CEO, Powergrid NM Transmission Limited, Bangalore.
2. Mr. Pankaj Pande, CM (Regulatory Cell), PGCIL, Gurgaon.
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Pragati Mahalakshmi, South block no. 62,
Yeshwantpur, Bangalore 560022
Karnataka
Kind Attn.: Mr. Joseph Kurian – Dy. General Manager
Sub.: 1. Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff
Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01
Ref.: 1. NOA No. PGNMTL/765 kV/02(N-M)/ERE01/NOA-I/10 & NOA-II/11 dated
16.05.2014.
Dear Sir,
With reference to the subject project, enclosed herewith, please find three sets of following documents
of M/s UIC Udyog Limited for your scrutiny and approval. The details are as under.
Sr.
Details Drawing No.
No.
Wooden Drum for Galvanized Earthwire UUL/Gammon/PGNMTL/14-
1
Strand 15/05
Guaranteed Technical Particulars of
2 -
7/3.66 mm G S Earthwire
Kindly arrange to regularize by approving the aforementioned drawings & GTP in Category – I and
provide one set duly signed and stamped for our reference and our record.
Thanking you
Yours faithfully,
For GAMMON INDIA LIMITED
Uday Patil
(Sr. Manager, Contracts – T & D Business)
Encl.: as above
With reference to the subject project, we would like to inform you that we have received structural
drawings and bill of material of Stub Setting Template (WZ-4) from PGCIL Guragaon Office.
We have done proto inspection of DA type Stub Setting Template upto +9M (WZ-4) at our Deoli works
on 26.07.2014, enclosed herewith, please find two sets of proto corrected structural drawings and bill of
materials of DA type Stub Setting Template (WZ-4) alongwith proto inspection reports and photographs
for your scrutiny and approval.
Please arrange to regularize by approving the aforementioned drawings and Bill of materials in
Category – I at the earliest.
Thanking you
Yours faithfully,
For GAMMON INDIA LIMITED
Uday Patil
(Sr. Manager, Contracts – T & D Business)
Encl.: as above
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Pragati Mahalakshmi, South block no. 62,
Yeshwantpur, Bangalore 560022
Karnataka
Kind Attn.: Mr. Joseph Kurian – Dy. General Manager
Sub.: 1. Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff
Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01
2. Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-II) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff
Based Competitive Bidding Route
Tender Specification No.: TBCB/765KV/02(N-M)/ERE02
Ref.: 1. NOA No. PGNMTL/765 kV/02(N-M)/ERE01/NOA-I/10 & NOA-II/11 dated
16.05.2014.
2. NOA No. PGNMTL/765 kV/02(N-M)/ERE02/NOA-I/12 & NOA – II/13 dated
16.05.2014
Dear Sir,
With reference to the subject project, we would like to inform you that, we have received
following foundation drawings from PGCIL Guragaon Office.
We are pleased to submit herewith 3 set of same foundation drawings with endorsement of
subject project for your regularization.
Wind
Description Soil Type Drawing No.
Zone
WET PADDY WZ-2 CC:ENGG:TL:7222-61Z-P-2WP 01TBCB
DRY WBC WZ-2 CC:ENGG:TL:7222-61Z-P-5DBC 01TBCB
WET WBC WZ-2 CC:ENGG:TL:7222-61Z-P-5WBC 01TBCB
DB-6.0/-4.5/-3.0/-1.5/0M Extn.
DFR WZ-2 CC:ENGG:TL:7222-61Z-P-6 01 TBCB
WFR WZ-2 CC:ENGG:TL:7222-61Z-P-7 01 TBCB
SFR WZ-2 CC:ENGG:TL:7222-61Z-P-8 01 TBCB
DB+1.5/3.0/4.5/6.0/7.5/9.0M WET PADDY WZ-2 CC:ENGG:TL:7222-61Z-P-2 WP 02 TBCB
Extn. DRY WBC WZ-2 CC:ENGG:TL:7222-61Z-P-5DBC 02 TBCB
WET WBC WZ-2 CC:ENGG:TL:7222-61Z-P-5WBC 02 TBCB
DFR WZ-2 CC:ENGG:TL:7222-61Z-P-6 02 TBCB
WFR WZ-2 CC:ENGG:TL:7222-61Z-P-7 02 TBCB
SFR WZ-2 CC:ENGG:TL:7222-61Z-P-8 02 TBCB
DRY WZ-2 7222-61Z-P-1- 02
WET WZ-2 7222-61Z-P-2 -02
PS WZ-2 7222-61Z-P-3- 02
FS WZ-2 7222-61Z-P-4- 02
WBC WZ-2 7222-61Z-P-6- 02
Dry WZ-4 CC:ENGG:TL:8422-61Z-P-1-5551A
Wet WZ-4 CC:ENGG:TL:8422-61Z-P-2-5551B
PS WZ-4 CC:ENGG:TL:8422-61Z-P-3-5551C
FS WZ-4 CC:ENGG:TL:8422-61Z-P-4-5551D
FS-BC WZ-4 CC:ENGG:TL:8422-61Z-P-5-5551E
DB-6 to +-0M Body Extn. DFR WZ-4 CC:ENGG:TL:8422-61Z-P-6-5551F
WFR WZ-4 CC:ENGG:TL:8422-61Z-P-7-5551G
SFR WZ-4 CC:ENGG:TL:8422-61Z-P-8-5551H
Wet-Paddy WZ-4 CC:ENGG:TL:8422-61Z-P-9-5551I
Dry-BC WZ-4 CC:ENGG:TL:8422-61Z-P-10-5551J
Wet-BC WZ-4 CC:ENGG:TL:8422-61Z-P-11-5551K
DRY WZ-4 CC:ENGG:TL:8422-61Z-P-12-5552A
Wet WZ-4 CC:ENGG:TL:8422-61Z-P-2-5552B
PS WZ-4 CC:ENGG:TL:8322-61Z-P-3-5552C
FS WZ-4 CC:ENGG:TL:8422-61Z-P-4-5552D
FS-BC WZ-4 CC:ENGG:TL:8422-61Z-P-5-5552E
DB+1.5 to 9M Body Extn. DFR WZ-4 CC:ENGG:TL:8422-61Z-P-6-5552F
WFR WZ-4 CC:ENGG:TL:8422-61Z-P-7-5552G
SFR WZ-4 CC:ENGG:TL:8422-61Z-P-8-5552H
Wet-Paddy WZ-4 CC:ENGG:TL:8422-61Z-P-9-5552I
Dry-BC WZ-4 CC:ENGG:TL:8422-61Z-P-10-5552J
Wet-BC WZ-4 CC:ENGG:TL:8422-61Z-P-11-5552K
Dry WZ-4 CC:ENGG:TL:8423-61Z-P-1-1001
Wet WZ-4 CC:ENGG:TL:8423-61Z-P-2-1001
WET Paddy WZ-4 CC:ENGG:TL:8423-61Z-P-2P1001
PS WZ-4 CC:ENGG:TL:8423-61Z-P-3-1001
Wind
Description Soil Type Drawing No.
Zone
DRY WZ-4 CC:ENGG:TL:8423-61Z-P-1-1002
DCM+1.5 to 9m Body Extn.
Wet WZ-4 CC:ENGG:TL:8423-61Z-P-2-1002
DCM+1.5/3.0/4.5/6.0/7.5/9M WET Paddy WZ-4 CC:ENGG:TL:8423-61Z-P-2P1002
PS WZ-4 CC:ENGG:TL:8423-61Z-P-3-1002
FS WZ-4 CC:ENGG:TL:8423-61Z-P-4-1002
Dry BC WZ-4 CC:ENGG:TL:8423-61Z-P-5D-1002
Wet BC WZ-4 CC:ENGG:TL:8423-61Z-P-5W-1002
DCM+1.5 to 9m Body Extn.
DFR WZ-4 CC:ENGG:TL:8422-61Z-P-6-1002
WFR WZ-4 CC:ENGG:TL:8423-61Z-P-7-1002
WBC WZ-4 CC:ENGG:TL:8423-61Z-P-5-1002
SFR WZ-4 CC:ENGG:TL:8423-61Z-P-8-1002
WET PADDY WZ-4 CC:ENGG:TL:7424-61Z-P-2WP 01TBCB
DRY WBC WZ-4 CC:ENGG:TL:7424-61Z-P-5DBC 01TBCB
WET WBC WZ-4 CC:ENGG:TL:7424-61Z-P-5WBC 01TBCB
DD-6.0/-4.5/-3.0/-1.5/0M Extn.
DFR WZ-4 CC:ENGG:TL:7424-61Z-P-6 01 TBCB
WFR WZ-4 CC:ENGG:TL:7424-61Z-P-7 01 TBCB
SFR WZ-4 CC:ENGG:TL:7424-61Z-P-8 01 TBCB
WET PADDY WZ-4 CC:ENGG:TL:7424-61Z-P-2WP 02 TBCB
DRY WBC WZ-4 CC:ENGG:TL:7424-61Z-P-5DBC 02 TBCB
WET WBC WZ-4 CC:ENGG:TL:7424-61Z-P-5WBC 02 TBCB
DFR WZ-4 CC:ENGG:TL:7424-61Z-P-6 02 TBCB
WFR WZ-4 CC:ENGG:TL:7424-61Z-P-7 02 TBCB
DD+1.5/3.0/4.5/6.0/7.5/9.0M SFR WZ-4 CC:ENGG:TL:7424-61Z-P-8 02 TBCB
Extn.
DRY WZ-4 CC:ENGG:TL:842461-ZP-102
WET WZ-4 CC:ENGG:TL:842461-ZP-202
PS WZ-4 CC:ENGG:TL:842461-ZP-302
FS WZ-4 CC:ENGG:TL:842461-ZP-402
WBC WZ-4 CC:ENGG:TL:842461-ZP-502
DRY WZ-4 CC:ENGG:TL:842461-ZP-101
WET WZ-4 CC:ENGG:TL:842461-ZP-201
DD+0/-1.5/-3.0/-4.5 M Extn. PS WZ-4 CC:ENGG:TL:842461-ZP-301
FS WZ-4 CC:ENGG:TL:842461-ZP-401
WBC WZ-4 CC:ENGG:TL:842461-ZP-501
Please arrange to regularize by approving the aforementioned foundation drawings for field
use.
Thanking you
Yours faithfully,
For GAMMON INDIA LIMITED
Uday Patil
(Sr. Manager, Contracts – T & D Business)
Encl.: as above
1. Mr. G K Sharma, DGM (Engg.), PGCIL, Gurgaon.
2. Mr. Pankaj Pande, CM (Regulatory Cell), PGCIL, Gurgaon.
Sub.: Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-II) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff
Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE02
Ref.: 1. NOA No. PGNMTL/765 kV/02(N-M)/ERE02/NOA-I/12 & NOA – II/13 dated
16.05.2014
Dear Sir,
With reference to the subject project, enclosed herewith, please find three sets of following documents
of M/s Bharat wire Ropes Ltd. for your scrutiny and approval. The details are as under.
Sr.
Details Drawing No.
No.
1 Wooden Drum for 7/3.66mm Earthwire BWR/A/00039/REV1
Guaranteed Technical Particulars of
2 -
7/3.66 mm G S Earthwire
Kindly arrange to regularize by approving the aforementioned drawings & GTP in Category – I and
provide one set duly signed and stamped for our reference and our record.
Thanking you
Yours faithfully,
For GAMMON INDIA LIMITED
Uday Patil
(Sr. Manager, Contracts – T & D Business)
Encl.: as above
We are pleased to submit herewith 3 set of same foundation drawings with endorsement of
subject project for your regularization.
Tower Wind
Description Drawing No. BOM No.
Type Zone
Stub for 3M foundation depth 0861_DA4_S3FD
DA Stub for 3.5M foundation depth WZ-4 C:ENGG:TL:8421-61Z-P-1-11 0861_DA4_S35FD
Stub Setting Template 0861_DA4_T0
Stub for 3M foundation depth 226/BOM/STUB/DB-1
WZ-2 C:ENGG:TL:7222-61Z-P-0-02
Stub Setting Template 226/BOM/SST/DB-1
DB Stub for 3M foundation depth C:ENGG:TL:8422-61Z-P-0-108 G252-DBM-BOM-01
Stub for 3.5M foundation depth WZ-4 C:ENGG:TL:8422-61Z-P-0-109 G252-DBM-BOM-01A
Stub Setting Template C:ENGG:TL:8422-61Z-P-0-110 G252-DBM-BOM-02
Stub for 3M foundation depth C:ENGG:TL:8223-61Z-P-02 BOM/LE120522/DC/001
WZ-2
Stub Setting Template C:ENGG:TL:8223-61Z-P-03 BOM/LE120522/DC/002
DC Stub for 3M foundation depth C:ENGG:TL:8423-61Z-P-0-108 G252-DCM-BOM-01
Stub for 3.5M foundation depth WZ-4 C:ENGG:TL:8423-61Z-P-0-109 G252-DCM-BOM-01A
Stub Setting Template C:ENGG:TL:8423-61Z-P-0-110 G252-DC-BOM-02
Tower Wind
Description Drawing No. BOM No.
Type Zone
Stub (-4.5M to +9M) WZ-4 C:ENGG:TL:842461ZP031 196/BOM/STUB/DD-1
Stub Setting Template (-4.5M
WZ-4 C:ENGG:TL:842461ZP035 196/BOM/SST/DD-1
to +9M)
DD
Stub (+18M & +25M) WZ-4 S-3470 BOM/LE110268/DD/010
Stub Setting Template (+18M
WZ-4 196/BOM/SST/DD-2
& +25M)
B) Foundation Drawings:
Wind
Description Soil Type Drawing No.
Zone
WET PADDY WZ-2 CC:ENGG:TL:7222-61Z-P-2WP 01TBCB
DRY WBC WZ-2 CC:ENGG:TL:7222-61Z-P-5DBC 01TBCB
DB-6.0/-4.5/-3.0/-1.5/0M Extn. WET WBC WZ-2 CC:ENGG:TL:7222-61Z-P-5WBC 01TBCB
DFR WZ-2 CC:ENGG:TL:7222-61Z-P-6 01 TBCB
WFR WZ-2 CC:ENGG:TL:7222-61Z-P-7 01 TBCB
SFR WZ-2 CC:ENGG:TL:7222-61Z-P-8 01 TBCB
WET PADDY WZ-2 CC:ENGG:TL:7222-61Z-P-2 WP 02 TBCB
DRY WBC WZ-2 CC:ENGG:TL:7222-61Z-P-5DBC 02 TBCB
WET WBC WZ-2 CC:ENGG:TL:7222-61Z-P-5WBC 02 TBCB
DFR WZ-2 CC:ENGG:TL:7222-61Z-P-6 02 TBCB
WFR WZ-2 CC:ENGG:TL:7222-61Z-P-7 02 TBCB
DB+1.5/3.0/4.5/6.0/7.5/9.0M
Extn. SFR WZ-2 CC:ENGG:TL:7222-61Z-P-8 02 TBCB
DRY WZ-2 7222-61Z-P-1- 02
WET WZ-2 7222-61Z-P-2 -02
PS WZ-2 7222-61Z-P-3- 02
FS WZ-2 7222-61Z-P-4- 02
WBC WZ-2 7222-61Z-P-6- 02
Dry WZ-4 CC:ENGG:TL:8422-61Z-P-1-5551A
Wet WZ-4 CC:ENGG:TL:8422-61Z-P-2-5551B
DB-6 to +-0M Body Extn.
PS WZ-4 CC:ENGG:TL:8422-61Z-P-3-5551C
FS WZ-4 CC:ENGG:TL:8422-61Z-P-4-5551D
FS-BC WZ-4 CC:ENGG:TL:8422-61Z-P-5-5551E
DFR WZ-4 CC:ENGG:TL:8422-61Z-P-6-5551F
WFR WZ-4 CC:ENGG:TL:8422-61Z-P-7-5551G
DB-6 to +-0M Body Extn. SFR WZ-4 CC:ENGG:TL:8422-61Z-P-8-5551H
Wet-Paddy WZ-4 CC:ENGG:TL:8422-61Z-P-9-5551I
Dry-BC WZ-4 CC:ENGG:TL:8422-61Z-P-10-5551J
Wet-BC WZ-4 CC:ENGG:TL:8422-61Z-P-11-5551K
DRY WZ-4 CC:ENGG:TL:8422-61Z-P-12-5552A
Wet WZ-4 CC:ENGG:TL:8422-61Z-P-2-5552B
PS WZ-4 CC:ENGG:TL:8322-61Z-P-3-5552C
FS WZ-4 CC:ENGG:TL:8422-61Z-P-4-5552D
FS-BC WZ-4 CC:ENGG:TL:8422-61Z-P-5-5552E
DB+1.5 to 9M Body Extn. DFR WZ-4 CC:ENGG:TL:8422-61Z-P-6-5552F
WFR WZ-4 CC:ENGG:TL:8422-61Z-P-7-5552G
SFR WZ-4 CC:ENGG:TL:8422-61Z-P-8-5552H
Wet-Paddy WZ-4 CC:ENGG:TL:8422-61Z-P-9-5552I
Dry-BC WZ-4 CC:ENGG:TL:8422-61Z-P-10-5552J
Wet-BC WZ-4 CC:ENGG:TL:8422-61Z-P-11-5552K
Dry WZ-4 CC:ENGG:TL:8423-61Z-P-1-1001
Wet WZ-4 CC:ENGG:TL:8423-61Z-P-2-1001
WET Paddy WZ-4 CC:ENGG:TL:8423-61Z-P-2P1001
PS WZ-4 CC:ENGG:TL:8423-61Z-P-3-1001
DCM -6 to +-0M body Extn.
FS WZ-4 CC:ENGG:TL:8423-61Z-P-4-1001
Dry BC WZ-4 CC:ENGG:TL:8423-61Z-P-5D-1001
Please arrange to regularize by approving the aforementioned documents for field use.
Thanking you
Yours faithfully,
For GAMMON INDIA LIMITED
Uday Patil
(Sr. Manager, Contracts – T & D Business)
Encl.: as above
1. Mr. G K Sharma, DGM (Engg.), PGCIL, Gurgaon.
2. Mr. Pankaj Pande, CM (Regulatory Cell), PGCIL, Gurgaon.
To
The Dy. General Manager (Engg-TL/TBCB)
Powergrid Corporation of India Limited
Saudamini Plot No.-2, Sector-29
Gurgaon -122001, (Haryana)
Fax: 0124-2571760, 2571848
Kind Attn.: Mr. G K Sharma
Sub.: 1. Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff
Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01
2. Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-II) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff
Based Competitive Bidding Route
Tender Specification No.: TBCB/765KV/02(N-M)/ERE02
Ref.: 1. NOA No. PGNMTL/765 kV/02(N-M)/ERE01/NOA-I/10 & NOA-II/11 dated
16.05.2014.
2. NOA No. PGNMTL/765 kV/02(N-M)/ERE02/NOA-I/12 & NOA – II/13 dated
16.05.2014
Dear Sir,
With reference to the subject project, we are pleased to inform you that, we have done proto
inspection of following stub setting template for WZ-IV on 12.10.2014 at our Deoli Works.
Enclosed herewith, please find, three sets of proto corrected structural drawings, bill of
material, inspection report along with photograph`s for your scrutiny and approval.
Thanking you
Yours faithfully,
For GAMMON INDIA LIMITED
Uday Patil
(Chief. Manager, Contracts – T & D Business)
Encl.: as above
To
The Dy. General Manager (Engg-TL/TBCB)
Powergrid Corporation of India Limited
Saudamini Plot No.-2, Sector-29
Gurgaon -122001, (Haryana)
Fax: 0124-2571760, 2571848
Dear Sir,
Cont..2
Thanking you
Yours faithfully,
For GAMMON INDIA LIMITED
Uday Patil
(Chief. Manager, Contracts – T & D Business)
Encl.: as above
With reference to the subject project, we invite your kind attention to the following:
1. GTP & Drum drawing of 7/3.66 mm G S Earthwire, was submitted for approval vide our
letter no. GIL/AL/G-289&G-290/16449 dated 21.08.2014. Same was approved by
PGCIL vide their letter no. CC:ENGG:TL:TBCB:PGNMTL:DDEW/ERE02 dated
21.10.2014 (copy enclosed) in CAT- III.
2. Based on the above remark, enclosed herewith, please find the revised drawing for your
scrutiny and approval in Cat-I.
3. Further, as per PGCIL specifications one type test is valid only for 500 Kms of
Earthwire. M/s Bharatwire, has proposed for supply of Earthwire from their machine no.
EW-02, against which material type tested and is balance for completion of 500 Kms
(Copy enclosed). The details are as under:
Cont..2
In view of the above, we request you to accord commercial manufacturing clearance based on
the above referred type test for the subject project.
Thanking you,
Yours faithfully
For GAMMON INDIA LIMITED
Uday Patil
(Chief Manager, Contracts – T & D Business)
Encl. As above
With reference to the subject project, we invite your kind attention to the following:
1. GTP & Drum drawing of 7/3.66 mm G S Earthwire, was submitted for approval vide our
letter no. GIL/AL/G-289&G-290/16306 dated 28.07.2014. Same was approved by
PGCIL vide their letter no. CC:ENGG:TL:TBCB:PGNMTL:DDEW/ERE01 dated
21.10.2014 (copy enclosed) in CAT- II.
2. Based on the above remark, enclosed herewith, please find the revised drawing for your
scrutiny and approval in Cat-I.
3. Further, as per PGCIL specifications one type test is valid only for 500 Kms of
Earthwire. M/s Uic Udyog Ltd, has proposed for supply of Earthwire from their kalyani
works, against which material type tested and is balance for completion of 500 Kms
(Copy enclosed). The details are as under:
Qty. Proposed to
Sr. be supplied
Name of Contractor LOA No.
no. against this type
test
CA no. CC-CS/111-NR1/TW-
M/s National Construction
1 993/3/G2/NOA-I/3963 & NOA- 71.091 Kms
Company Ltd.
II/3964 dated 03.11.2010
C-47302-L195A-3/LOA-I/2634
2 M/s Jyoti Structure 8.00 Kms
dated 08.09.2007
PGNMTL/765 kV/02(N-
M/s Gammon India Limited M)/ERE02/NOA-I/10 & NOA- 103.00 Kms
II/11 dated 16.05.2014
Cont..2
In view of the above, we request you to accord commercial manufacturing clearance based on
the above referred type test for the subject project.
Thanking you,
Yours faithfully
For GAMMON INDIA LIMITED
Uday Patil
(Chief Manager, Contracts – T & D Business)
Encl. As above
To
Power Grid Corporation of India Limited
Saudamini Plot No.-2, Sector-29
Gurgaon -122001, (Haryana)
Fax: 0124-2571760, 2571848
Contact Person & Number T. K .Sil , GM QA & I 033 2582 0069 / 6332
90079 96575
Subsequently after completion of the test we shall submit the all report to your office for
scrutiny and issuance of approval.
Thanking you and assuring you of our best services at all times.
With regards
FOR GAMMON INDIA LIMITED
Uday Patil
(Chief. Manager Contracts – T&D Business)
With reference to the subject project & your email dated 27.11.2014 you asked for submit the
recent type test report against 7/3.66 mm GS E/W for waiver of said project, as the type test
report was provided by us vide our letter No. GIL/AL/G-290/16886 dated 17.11.14, approved
on 10.09.2012 which is quite old.
So as per your advice here we resubmit the recent type test report was conducted by M/s.
Bharat Wire Rope from their machine no. EW-02 which was approved by PGCIL vide letter No.
CC. ENGG: TL: WR: KETAN: WR-NR-A/TW02 on dated 26.03.2014. Materials utilized against
this test report are as under:
Qty. Proposed to
be supplied
Sr. no. Name of Contractor LOA No.
against this type
test
CA no. CC-CS/402-WR1/TW-
1 M/s Ketan Construction Ltd. 2235/3/G1/NOA-I/4836 & NOA- 152.00 Kms
II/4837 dated 26.11.2013
BALANCE: 348.00 kms
PGNMTL/765 kV/02(N-
M/s Gammon India Limited
M)/ERE02/NOA-I/10 & NOA- 103.00 Kms
(Proposed Qty)
II/11 dated 16.05.2014
In view of the above, we request you to accord commercial manufacturing clearance based on
the above referred type test for the subject project.
Cont..2
Thanking you,
Yours faithfully
For GAMMON INDIA LIMITED
Uday Patil
(Chief Manager, Contracts – T & D Business)
Encl. As above
To
The Chief Executive Officer
M/s. Vizag Transmission Limited
A Wholly owned Subsidiary of Power Grid Corporation of India Ltd.,
Vizag 400 KV Substation, Sector 10,
Visakhapatnam - 530032
Kind Attn.: Mr. S. Ravi, CEO
Sub.: Tower Erection Package - ERE05 for 400 KV D/C Khamman (Existing) - Nagarjuna Sagar
Transmission Line (with Twin Moose Conductor) associated with System Strengthening in Southern
Region for Import of Power From Eastern Region Under Tariff Based Competitive Bidding Route.
With reference to the subject project and your Email dated 23.11.2014 (copy enclosed) regarding
issuance of manufacturing clearance of tower to M/s. Unique Structures & Towers Limited, please find
enclosed here with manufacturing clearance for line material i.e. ACSR Moose Conductor, Disc
Insulator, Hardware fittings and Conductor & E/W accessories ( Details calculation attached in
annexure –I).
We request you to arrange the above materials at the earliest within 15 days advance intimation to us
for providing store destination and also making unloading arrangement.
Further we request you to arrange the clarification / documents on following issues immediately.
i) Details of Hardware, Insulator, Conductor Supplier along with GTP, Drawings etc in order to
receive the material properly at our site store.
ii) Please provide bundle spacer & Rigid spacer placement chart along with jumper drawing.
iii) The insulator calculation based on standard 120 KN & 160 KN disc insulator. If M/s. VTL intent
to use antifog insulator or long rod insulator then same to be intimated along with drawing in
order to revise requirement.
iv) VTL is request to confirm the location of TP tower since foundation work is already under
progress.
v) Please provide GTP & Drum drawing of OPGW and its accessories along with guidelines of
termination of OPGW in order to submit the drum schedule.
Yours faithfully
For GAMMON INDIA LIMITED
Y N Venkateswarulu
Associate Vice President - T & D Business
Encl.: as above
To
The Dy. General Manager (Engg-TL/TBCB)
Powergrid Corporation of India Limited
Saudamini Plot No.-2, Sector-29
Gurgaon -122001, (Haryana)
Fax: 0124-2571760, 2571848
With reference to the subject project, here we attach the Bird Guard Placement drawing for DA
type Tower WZ-IV. Details of the Drawings given below-
Thanking you
Yours faithfully,
For GAMMON INDIA LIMITED
Uday Patil
(Chief. Manager, Contracts – T & D Business)
Encl.: as above
Cc. Mr. Joseph Kurian, DGM (Engg.), PGCIL, Bangalore..
To
The Dy. General Manager (Engg-TL/TBCB)
Powergrid Corporation of India Limited
Saudamini Plot No.-2, Sector-29
Gurgaon -122001, (Haryana)
Fax: 0124-2571760, 2571848
With reference to the subject project & your letter No. Engg
TL:TBCB:PGNMTL:Gammon:ERE01 & ERE02 dated 15.01.15, herewith, please find, one set
of structural drawings and bill of material of DC Tower (WZ-4) for your reference.
The above mentioned approved drawings are circulated at site for further use on material
receive and erection Purpose. This is for your information.
Thanking you
Yours faithfully,
For GAMMON INDIA LIMITED
Uday Patil
(Chief. Manager, Contracts – T & D Business)
To
M/s. Powergrid NM Transmission Limited
(A fully owned subsidiary of Power Grid Corporation of India Limited)
400kV Substation, Konakapadi Post, K.R.Thoppur,
SALEM, TAMIL NADU - 636 502
Sub.: 1. Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem Transmission
Line (Part-I) (with Hex Zebra Conductor) associated with Transmission System pertaining to
IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff Based Competitive Bidding
Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01
Details calculations are available in annexure –I to annexure – III. The calculation has been made
based on actual consumption upto February’2015 and expected classification of balance work, wherein
you will observe that Hard Rock quantity is encountered in some location already and future expected
to come for which unit rate is not available in Contract. We have propose the same to be incorporated
in amendment to the contract with same unit rate as per existing contract under execution (TW03 765
KV D/C (Hexa Zebra) Jharsuguda - Dharamjaygarh T/L,CA No: CC-CS /159-ER2/TW-
2389/3/G7/CA-II/4944 Dated 19.05.2014) copy of reference is enclosed. Also the individual quantities
of most of items are varying and interim quantity amendment is necessary for execution of work /
passing RA Bills.
Therefore we request you to arrange the approval of interim amendment on priority basis.
Thanking You,
Yours faithfully
For GAMMON INDIA LIMITED
Y N Venkateswarulu
Associate Vice President - T & D Business
Encl.: as above
To
M/s. Powergrid NM Transmission Limited
(A fully owned subsidiary of Power Grid Corporation of India Limited)
400kV Substation, Konakapadi Post, K.R.Thoppur,
SALEM, TAMIL NADU - 636 502
Sub.: 1. Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem Transmission
Line (Part-II) (with Hex Zebra Conductor) associated with Transmission System pertaining to
IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff Based Competitive Bidding
Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE02
Therefore we request you to arrange the approval of interim amendment on priority basis.
Thanking You,
Yours faithfully
For GAMMON INDIA LIMITED
Y N Venkateswarulu
Associate Vice President - T & D Business
Encl.: as above
To
M/s. Powergrid NM Transmission Limited
(A fully owned subsidiary of Power Grid Corporation of India Limited)
400kV Substation, Konakapadi Post, K.R.Thoppur,
SALEM, TAMIL NADU - 636 502
Sub.: 1. Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem Transmission
Line (Part-I) (with Hex Zebra Conductor) associated with Transmission System pertaining to
IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff Based Competitive Bidding
Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01
With reference to the subject project we would like to inform you that as per “Contract
agreement Volume –B Clause No 9.5.1 of GCC page No.15”, please find enclose here with the
original copy of Indemnity Bond for M/s. GIL supply material and owner supply material.
Thanking you
Yours faithfully,
For GAMMON INDIA LIMITED
Uday Patil
(Chief. Manager, Contracts – T & D Business)
Encl.: as above
To
M/s. Powergrid NM Transmission Limited
(A fully owned subsidiary of Power Grid Corporation of India Limited)
400kV Substation, Konakapadi Post, K.R.Thoppur,
SALEM, TAMIL NADU - 636 502
Sub.: 1. Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem Transmission
Line (Part-II) (with Hex Zebra Conductor) associated with Transmission System pertaining to
IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff Based Competitive Bidding
Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE02
Thanking you
Yours faithfully,
For GAMMON INDIA LIMITED
Uday Patil
(Chief. Manager, Contracts – T & D Business)
Encl.: as above
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,
Bangalore 560064, Karnataka
Kind Attn.: Mr. R N Singh – CEO
Sub.: 1. Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem Transmission Line
(Part-I) (with Hex Zebra Conductor) associated with Transmission System pertaining to IPPs of
Nagapattinam / Cuddalore Area: Package - A under Tariff Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01
Ref.: 1. NOA No. PGNMTL/765 kV/02(N-M)/ERE01/NOA-I/10 & NOA-II/11 dated 16.05.2014.
Dear Sir,
With reference to the subject project we would like to bring your kind attention on our Erection payment
terms of Clause No.1.1 D where 10% of payment of erection components will be pay progressively after
completion of stringing work of corresponding segment.
Regarding this clause we want to make your kind attention on following matters-
1) As per schedule angle tower stub would be supplied on the month of July’2014 but we have
received angle point stubs on the month of Nov’14 and latter we have casted the gap locations
which effect the efficiency of our foundation progress.
2) We have received first lot DA type tower 60 set on Jan’15 in erectable shape supplied by M/s.
Skipper but extension of the same was supplied on the month of Mar’15 due to this numbers of
gap locations are increases which affect the progress as well as incurred extra cost for gang
shifting.
3) The angle tower supply has been completed on dated 06.04.2015 but till date no spring washer &
Pack washer for 24mm B&N are supplied from M/s. ICOMM, hence our erection at angle points
are yet to be start. Till date we have not received any approved drawing of tower extension for
angle towers.
4) As per approved L2 network we need to be start our stringing activity on the month of Jan’15 and
our foundation activity of section 25/0 to 26/0, 37/0 to 40/0 & 42/0 to 44/0 of 12.99 KM was
completed but we are unable to start our stringing activity due to timely received of towers,
conductor, hardware & insulator.
On the basis of above matters, it is clearly shown that the delay in start of stringing activity is not
beyond the control of M/s. GIL, hence we request to please release our hold 10% amount of Rs.166.92
Lacs upto passed RA bill of Feb’15 (Details attached) against foundation & erection activity as per
Clause No. 1.1.C of Payment terms. This helps us to regularize our cash flow and we are able to
funding our site to expedite the balance activity for completion of line in timely.
Thanking you and assuring you of our best services at all times.
Yours faithfully,
For GAMMON INDIA LIMITED,
Y N Venkateswarulu
Associate Vice President - T & D Business
Cc. 1. Mr. Joseph Kurion, DGM, Powergrid NM Transmission Limited, Bangalore.
2. Mr. Jayprakash J.P, AsstGM, PGNMTL, Salem
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,
Bangalore 560064, Karnataka
Kind Attn.: Mr. R N Singh – CEO
Sub.: 1. Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem Transmission Line
(Part-II) (with Hex Zebra Conductor) associated with Transmission System pertaining to IPPs of
Nagapattinam / Cuddalore Area: Package - A under Tariff Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE02
With reference to the subject project we would like to bring your kind attention on our Erection payment
terms of Clause No.1.1 D where 10% of payment of erection components will be pay progressively after
completion of stringing work of corresponding segment.
Regarding this clause we want to make your kind attention on following matters-
1) As per schedule angle tower stub would be supplied on the month of July’2014 but we have received
angle point stubs on the month of Nov’14 and latter we have casted the gap locations which effect
the efficiency of our foundation progress.
2) We have received first lot DA type tower 60 set on Jan’15 in erectable shape supplied by M/s.
Skipper but extension of the same was supplied on the month of Mar’15 due to this numbers of gap
locations are increases which affect the progress as well as incurred extra cost for gang shifting.
3) Till date no Angle Tower supply has been start for WZ-II section from M/s. ICOMM and DD (WZ-II)
structural drawings are yet to be approved from M/s PGCIL.
4) As per approved L2 network we need to be start our stringing activity on the month of Jan’15
and our foundation activity of section 44/0 to 48/0, 81/0 to 86/0 & 87/0 to 89/0 of 16.10 KM was
completed but we are unable to start our stringing activity due to no receive of angle towers,
hardware & insulator..
On the basis of above matters, it is clearly shown that the delay in start of stringing activity is not beyond the
control of M/s.GIL , hence we request to please release our hold 10% amount of Rs.152.42 Lacs upto
passed RA bill of Feb’15 (Details attached) against foundation & erection activity as per Clause No. 1.1.C of
Payment terms. This helps us to regularize our cash flow and we are able to funding our site to expedite the
balance activity for completion of line in timely.
Thanking you and assuring you of our best services at all times.
Thanking you.
Yours faithfully,
For GAMMON INDIA LIMITED,
Y N Venkateswarulu
Associate Vice President - T & D Business
Cc. 1. Mr. Joseph Kurion, DGM, Powergrid NM Transmission Limited, Bangalore.
2. Mr. Jayprakash J.P, AsstGM, PGNMTL, Salem
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,
Bangalore 560064, Karnataka
Kind Attn.: Mr. R N Singh – CEO
Sub.: 1. Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem Transmission Line
(Part-I) (with Hex Zebra Conductor) associated with Transmission System pertaining to IPPs of
Nagapattinam / Cuddalore Area: Package - A under Tariff Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01
2) 70% of the erection component excluding survey & stringing charges will be paid progressive
monthly basis.
3) 10% of payment of erection components excluding survey & stringing charges will be pay
progressively after completion of stringing work of corresponding segment.
4) 5% after successful- Trial operation & balance 5% after Taking over by the Employer.
With respect to the point No.3, you will observe that 10% payment of tower foundation, Erection &
earthing will get released only after completion of stringing of corresponding section. Enclosed herewith
please find annexure- I. Where in you will observe that Rs.208.66 lacs has been held up for completed
foundation work/tower erection work and for non completion of stringing.
As per approved L2 network stringing activity were planned to commence from Jan’15 and as of
March’15 19 Km is scheduled to be completed however on account of following reasons stringing not
commenced :
1) Delay in supply of stubs and towers commensurate to approve L2. Annexure –II enclosed
wherein you will observe the delay of 3 months for supply of stubs & average 5 months delay in
supply of towers.
2) Delay in supply of all types of towers including tower extension for making stringing stretch
ready. For subject contract DA towers (60 sets) supplied in Jan’15 from M/s. Skipper and Angle
type towers supplied in month of April’15 only & that too without Bolts & Nuts.
3) As on date foundation activity of 12.99 KM section has been completed but due to delay in
receipt of angle type towers stringing could not be commenced.
4) Stringing material such as conductor, insulator & hardware etc. supply commenced in Mar’15
against Schedule of Dec’14.So delay by 3 Months.
Cont..2
Gammon India Limited
:: 2 ::
From above you would agree that stringing has been delayed for the reasons not under control of M/s.
GIL, however our Rs.208.66 lacs of payment has been held up making cash flow to the project
negative.
You will agree that next 3 to 4 months is peak period of working seasons and we need to pull up
resources for make up back log and requirement of funds is very critical for project completion point of
view.
Hence we request you for immediate release of Rs. 208.66 lacs which will be used for completion of
stringing activity and also to amend the payment terms of project as under.
2) 80% of the erection component excluding survey will be paid progressive on monthly basis.
3) 5% after successful- Trial operation & balance 5% after Taking over by the Employer
Your immediate intervention and support is required for release of Rs. 208.66 Lacs to maintain the cash flow
to the project.
Thanking you and assuring you of our best services at all times.
Yours faithfully,
For GAMMON INDIA LIMITED,
Y N Venkateswarulu
Associate Vice President - T & D Business
Encl: As above
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,
Bangalore 560064, Karnataka
Kind Attn.: Mr. R N Singh – CEO
Sub.: 1. Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem Transmission Line
(Part-II) (with Hex Zebra Conductor) associated with Transmission System pertaining to IPPs of
Nagapattinam / Cuddalore Area: Package - A under Tariff Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE02
6) 70% of the erection component excluding survey & stringing charges will be paid progressive
monthly basis.
7) 10% of payment of erection components excluding survey & stringing charges will be pay
progressively after completion of stringing work of corresponding segment.
8) 5% after successful- Trial operation & balance 5% after Taking over by the Employer.
With respect to the point No.3, you will observe that 10% payment of tower foundation, Erection &
earthing will get released only after completion of stringing of corresponding section. Enclosed herewith
please find annexure- I. Wherein you will observe that Rs.198.98 lacs has been held up for completed
foundation work/tower erection work and for non completion of stringing.
As per approved L2 network stringing activity were planned to commence from Jan’15 and as of
March’15 19 Km is scheduled to be completed however on account of following reasons stringing not
commenced :
5) Delay in supply of stubs and towers commensurate to approve L2. Annexure –II enclosed
wherein you will observe the delay of 3 months for supply of stubs & average 5 months delay in
supply of towers.
6) Delay in supply of all types of towers including tower extension for making stringing stretch
ready. For subject contract DA towers (60 sets) supplied in Jan’15 from M/s. Skipper and Angle
type towers are yet to be supplied for WZ-II from M/s. ICOMM.
7) As on date foundation activity of 16.10 KM section has been completed but due to delay in
receipt of angle type towers stringing could not be commenced.
8) Stringing material such as conductor, insulator & hardware etc. supply commenced in Mar’15
against Schedule of Dec’14.So delay by 3 Months.
From above you would agree that stringing has been delayed for the reasons not under control of M/s.
GIL, however our Rs.198.98 lacs of payment has been held up making cash flow to the project
negative.
You will agree that next 3 to 4 months is peak period of working seasons and we need to pull up
resources for make up back log and requirement of funds is very critical for project completion point of
view.
Hence we request you for immediate release of Rs. 198.98 lacs which will be used for completion of
stringing activity and also to amend the payment terms of project as under.
5) 80% of the erection component excluding survey will be paid progressive on monthly basis.
6) 5% after successful- Trial operation & balance 5% after Taking over by the Employer
Your immediate intervention and support is required for release of Rs. 198.98 Lacs to maintain the cash flow
to the project.
Thanking you and assuring you of our best services at all times.
Yours faithfully,
For GAMMON INDIA LIMITED,
Y N Venkateswarulu
Associate Vice President - T & D Business
Encl: As above
To
The Dy. General Manager (Engg-TL/TBCB)
Powergrid Corporation of India Limited
Saudamini Plot No.-2, Sector-29
Gurgaon -122001, (Haryana)
Fax: 0124-2571760, 2571848
With reference to the subject project please find enclosed here with the drawings of
enamel plates, the details of submission are as under:
Thanking you and assuring you of our best services at all times.
Yours faithfully,
For GAMMON INDIA LIMITED,
Uday Patil
(Chief. Manager, Contracts – T & D Business)
Encl.: as above
Cc. Mr. Joseph Kurion, DGM, Powergrid NM Transmission Limited, Bangalore.
To
The Dy. General Manager (Engg-TL/TBCB)
Powergrid Corporation of India Limited
Saudamini Plot No.-2, Sector-29
Gurgaon -122001, (Haryana)
Fax: 0124-2571760, 2571848
With reference to the subject we would like to inform you that, we have received
approval of ACD drawings vide letter No. CC:ENGG:TL:TBCB:PGNMTL:Gammon: ERE01
& ERE02 on dated 13.02.2015, where the barbed wire calculation was done for +3M,
+6M, +9M, +18M & +25M Ext only. But as per our approved survey report -6M Ext to -
1.5M Extn, +1.5M, +4.5M & +7.5M extension are also to be introduce on our line at both
wind zone – II & IV.
Based on the above required extensions, here we submit the barbed wire calculation
for the tower with -6M Ext to -1.5M Extn, +1.5M, +4.5M & +7.5M extension, as details are
given below –
Sl No. Drawing No. Wind zone
01 G-289/G290-ACC-04/WZ-2 2
02 G-289/G290-ACC-04/WZ-4 4
Thanking you and assuring you of our best services at all times.
Yours faithfully,
For GAMMON INDIA LIMITED,
Uday Patil
(Chief. Manager, Contracts – T & D Business)
Encl.: as above
Cc. Mr. Joseph Kurion, DGM, Powergrid NM Transmission Limited, Bangalore
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,
Bangalore 560064, Karnataka
Kind Attn.: Mr. R N Singh – CEO
Sub.: 1. Tower Erection Package – ERE01 & ERE02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I) (with Hex Zebra Conductor) associated with Transmission System
pertaining to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff Based
Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01 & ERE02
In lieu of the clause 9.2.2 of the GCC we shall allow to reduce the amount of bank
guarantees on every six months limited up to 75% of the total amount. Provided
hereunder are some details of adjusted and unadjusted advance details in this
regard:
Cont..2
We would request you to kindly accord the approval for reducing the Advance Bank
Guarantee values to what has been proposed above. This shall enable us to provide
additional BG limits and relief from extra payment of commission charges for extension
of Bank Guarantees.
Encl.: as above
Cc. Mr. Joseph Kurion, DGM, Powergrid NM Transmission Limited, Bangalore
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,
Bangalore 560064, Karnataka
Kind Attn.: Mr. R N Singh – CEO
Sub.: 1. Tower Erection Package – ERE01 & ERE02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I) (with Hex Zebra Conductor) associated with Transmission System
pertaining to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff Based
Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01 & ERE02
Yours faithfully,
For GAMMON INDIA LIMITED,
Y N Venkateswarulu
Associate Vice President - T & D Business
Encl: As above
To
The Dy. General Manager (Engg-TL/TBCB)
Powergrid Corporation of India Limited
Saudamini Plot No.-2, Sector-29
Gurgaon -122001, (Haryana)
Fax: 0124-2571760, 2571848
Kind Attn.: Mr. G K Sharma
Sub.: 1. Tower Erection Package – ERE01 & 02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I &II) (with Hex Zebra Conductor) associated with
Transmission System pertaining to IPPs of Nagapattinam / Cuddalore Area:
Package - A under Tariff Based Competitive Bidding Route.
Tender Specification No.: BCB/765KV/02(N-M)/ERE01 TBCB/765KV/02(N-
M)/ERE02
Sir,
With reference to the subject project we would like to draw your kind attention
regarding the placement of “Single I Suspension Pilot fitting” on DD tower at WZ-IV & II.
Considering the above change we would like to request you to please configure us,
the placement details of Pilot fitting per tower (DD WZ-IV & II), and also request to
please provide us the placement chart of rigid spacer accordingly.
Thanking you
With Regards
For GAMMON INDIA LIMITED,
Uday Patil
(Chief. Manager, Contracts – T & D Business)
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,
Bangalore 560064, Karnataka
Kind Attn.: Mr. Joseph Kurion – DGM
Sub.: 1. Tower Erection Package – ERE01 & 02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I &II) (with Hex Zebra Conductor) associated with
Transmission System pertaining to IPPs of Nagapattinam / Cuddalore Area:
Package - A under Tariff Based Competitive Bidding Route.
Tender Specification No.: BCB/765KV/02(N-M)/ERE01 TBCB/765KV/02(N-
M)/ERE02
Sir,
With reference to the subject contracts we would like to inform you that, survey of the
above lines has been completed and final tower schedule along with tower quantity
was submitted at your site office vide our letter no. GIL/PNMTL/G-289&290/201-15/59
dated 30.05.2015.
Request you to kindly verify the same from your end and arrange to dispatch the
material at our respective stores for plan our stringing activity accordingly.
Thanking you
With Regards
For GAMMON INDIA LIMITED,
Y N Venkateswarulu
Associate Vice President - T & D Business
Cc. 1. Mr. R N Singh, CEO, Powergrid NM Transmission Limited, Bangalore
2. Mr. Jayprakash J.P, AsstGM, PGNMTL, Salem
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,
Bangalore 560064, Karnataka
Kind Attn.: Mr. Joseph Kurion – DGM
Sub.: 1. Tower Erection Package – ERE01 & 02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I &II) (with Hex Zebra Conductor) associated with
Transmission System pertaining to IPPs of Nagapattinam / Cuddalore Area:
Package - A under Tariff Based Competitive Bidding Route.
Tender Specification No.: BCB/765KV/02(N-M)/ERE01 TBCB/765KV/02(N-
M)/ERE02
Sir,
With reference to the subject contract we would like to draw your kind attention on
the following matter-
1) As per Joint measurement certificate upto 31.05.2015 we are completed
excavation of Hard rock of 286.214 cum & 1039.765 cum respectively for Part-I &
Part-II of subject line.
2) In our BOQ, quantity of hard rock is not available and till date we are not able
to claim the same.
3) We have already submitted our amendment proposal vide letter no. GIL/SS/G-
289/17460 & GIL/SS/G-290/17461 on dated 07.03.2015, in which we proposed the
rate of hardrock quantity as per our existing contract no. TW03 765 KV D/C
(Hexa Zebra)Jharsuguda-Dharamjaygarh T/L,CA No: CC-CS /159-ER2/TW-
2389/3/G7/CA-II/4944 Dated 19.05.2014 copy of reference is enclosed.
Considering the above we are request you to please arrange, approval of unit rate of
hard rock and amend the same along with quantity in our BOQ, so that we can claim
approx. Rs.17,90,071/-.
Thanking you
With Regards
For GAMMON INDIA LIMITED,
Uday Patil
(Chief. Manager, Contracts – T & D Business)
Cc. Mr. G P Payasi, CM -TBCB Cell, PGCIL, Gurgaon
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,
Bangalore 560064, Karnataka
Kind Attn.: Mr. R N Singh – CEO
Sub.: 1. Tower Erection Package – ERE01 & 02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I &II) (with Hex Zebra Conductor) associated with
Transmission System pertaining to IPPs of Nagapattinam / Cuddalore Area:
Package - A under Tariff Based Competitive Bidding Route.
Tender Specification No.: BCB/765KV/02(N-M)/ERE01 TBCB/765KV/02(N-
M)/ERE02
Dear Sir,
With reference to the subject contract and further to review meeting held on
11.06.2015 at PGNMTL, Bangalore, we invite your attention on the following –
a. Foundation : From the annexure –A you will observe that for part-I out of
balance 115 locations, 61 locations are on hold and for part-II out of balance
91 locations, 78 locations are on hold due to various reason. Therefore we can
work only on the 54 location on Part-I & 13 locations at Part-II which has been
planned for completion by Aug’15.
Cont..2
b. Erection : From the annexure –II, you will observe that total 232 location
erection balance which foundations has been completed. However we
have only 67 nos erectable tower at store, out of the same 50 nos tower
getting erected in July’15 and only 17 tower will remain for aug’15. Thus there
will be gang idling. As communicated during the meeting the movement of
erection gang from Jharkhand/Malda has been commenced and we
expect arrival of 8 to 10 tower erection gangs in addition to existing 7 gangs.
Therefore immediate supply of towers is required from PGNMTL. We herein
also proposed PGNMTL to supply further towers on tower wise bundling basis
in order to save the time required for sorting and stacking of material at store
and further issuance to erection gang.
In view of the above you would agree that the progress of project is getting suffered
for the reasons beyond control of M/s. GIL and we request your immediate action on
the following matter.
a. Clearance of foundation work on hold location (139 Nos).
b. Supply of towers (103 nos) in July’15 & Aug’15 progressively to ensure erection
program up to sept’15.
c. Supply of tower instead of mass bundling, on tower wise bundling basis.
d. Immediate release of Rs. 4.07 cr amount hold towards foundation & erection
component.
Thanking you
With Regards
For GAMMON INDIA LIMITED,
Y N Venkateswarulu
Associate Vice President - T & D Business
Cc. 1. Mr. Joseph Kurion, DGM, Powergrid NM Transmission Limited, Bangalore
2. Mr. Jayprakash J.P, AsstGM, PGNMTL, Salem
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,
Bangalore 560064, Karnataka
Kind Attn.: Mr. R N Singh – CEO
Sub.: 1. Tower Erection Package – ERE01 & 02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I &II) (with Hex Zebra Conductor) associated with
Transmission System pertaining to IPPs of Nagapattinam / Cuddalore Area:
Package - A under Tariff Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01,TBCB/765KV/02(N-
M)/ERE02
Ref.:1. NOA No. PGNMTL/765 kV/02(N-M)/ERE01/NOA-I/10 & NOA-II/11 dated
16.05.2014.
2. NOA No. PGNMTL/765 kV/02(N-M)/ERE02/NOA-I/12 & NOA-II/13 dated
16.05.2014.
3. Our Email Dated: 25.08.2015
Dear Sir,
With reference to the subject contract the work status as on 24.08.2015 is as
hereunder-
From above as well as detailed status given in annexure enclosed, you will observe the
following-
2) Only 14 nos erectable towers are available in WZ-2 section (58.110 KM) which
expected to be complete in next 15 to 20 days.
4) From annexure-III, you will observe that further no sections are ready. From
planned stringing sections for 36.309 km (Part-I 17.112 Km & Part-II 19.297 km),
supply of 8 nos tower/ extension and clearance of ROW, tree cutting is critical.
You would agree that the project is lagging very much behind the schedule and
reasons for same are beyond the control of M/s. Gammon.
Therefore, we request your immediate attention to arrange necessary supplies and
clearance of ROW on priority to avoid idling of our resources and loss to time in
demobilization / remobilization of gangs which shall incur extra cost as well as affect
the completion schedule.
Thanking you
With Regards
For GAMMON INDIA LIMITED,
Y N Venkateswarulu
Vice President - T & D Business
Encl.: As above
Cc. 1. Mr. Joseph Kurion, DGM, Powergrid NM Transmission Limited, Bangalore
2. Mr. Jayprakash J.P, AsstGM, PGNMTL, Salem
To
M/s. Powergrid NM Transmission Limited
(A fully owned subsidiary of Power Grid Corporation of India Limited)
400kV Substation, Konakapadi Post, K.R.Thoppur,
SALEM, TAMIL NADU - 636 502
Kind Attn.: Jayaprakash J.P.(Asst.GM)
Sub.: 1. Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem Transmission
Line (Part-II) (with Hex Zebra Conductor) associated with Transmission System pertaining
to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff Based
Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE02,
Dear Sir,
With reference to the subject project, we would like to inform you that we received approved drawings
of Danger Plate, Number, Phase Plate & Circuit plate from your good office PGCIL, Gurgaon vide letter
No. CC: ENGG:TL:TBCB:PGNMTTL:Gammon:ERE01 & ERE02 dated 21.05.2015.
In order to take up the procurement of tower accessories (i.e. Danger Plate, Number Plate, Circuit Plate
& Phase Plates) and request you to confirm the following:-
A) Number plate:
I) Total quantity – 272 Nos.
II) We propose the numbering sequence as 273 to 544 (Continuation with Part-I)
III) We propose line abbreviation NAG - SAL (Represents code for sending end and receiving end
of line respectively)
IV) Owner Name is PGNMTL In Place of Powergrid
B) Danger Plate:
I) Total Quantity – 272 Nos.
II) Local language description to be provided in English/ Hindi/ Tamil for word “DANGER” &
“VOLTS”.
C) Circuit Plate:
I) Total Quantity – 272 Nos (Set of Two)
II) We proposed the Circuit details i.e. CKT-I & CKT-II
D) Phase Plate:
I) Total Quantity – 544 Nos (Set of Three)
Kindly arrange for the confirmation of the above, so that we can able to supply the material at the
earliest.
Thanking you and assuring you of our best services at all times.
Yours faithfully,
For GAMMON INDIA LIMITED
Uday Patil
(Asst General Manager, Contracts – T & D Business)
Encl: Approved drawing Copy
Dear Sir,
With reference to the subject project, we would like to inform you that we received approved drawings
of Danger Plate, Number, Phase Plate & Circuit plate from your good office PGCIL, Gurgaon vide letter
No. CC: ENGG:TL:TBCB:PGNMTTL:Gammon:ERE01 & ERE02 dated 21.05.2015.
In order to take up the procurement of tower accessories (i.e. Danger Plate, Number Plate, Circuit Plate
& Phase Plates) and request you to confirm the following:-
A) Number plate:
I) Total quantity – 272 Nos.
II) We propose the numbering sequence as 001 to 272
III) We propose line abbreviation NAG - SAL (Represents code for sending end and receiving end
of line respectively)
IV) Owner Name is PGNMTL In Place of Powergrid
B) Danger Plate:
I) Total Quantity – 272 Nos.
II) Local language description to be provided in English/ Hindi/ Tamil for word “DANGER” &
“VOLTS”.
C) Circuit Plate:
I) Total Quantity – 272 Nos (Set of Two)
II) We proposed the Circuit details i.e. CKT-I & CKT-II
D) Phase Plate:
I) Total Quantity – 544 Nos (Set of Three)
Kindly arrange for the confirmation of the above, so that we can able to supply the material at the
earliest.
Thanking you and assuring you of our best services at all times.
Yours faithfully,
For GAMMON INDIA LIMITED
Uday Patil
(Asst. General Manager, Contracts – T & D Business)
Encl: Approved drawing Copy
To
M/s. Powergrid NM Transmission Limited
(A fully owned subsidiary of Power Grid Corporation of India Limited)
Attur, TAMIL NADU
Kind Attn.: Mr R Gunasekaran.(CM)
Sub.: 1. Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem Transmission
Line (Part-I) (with Hex Zebra Conductor) associated with Transmission System pertaining
to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff Based
Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01,
Dear Sir,
With reference to the subject contract and our previous letter No.GIL/PNMTL/G-289/2014-15/79
dated 16.09.2015, we would like to thanking you for your recommendation for foundation
drawing vide your email dated 18.09.2015. In addition with we have further required some
foundation drawings to complete the balance foundation activity at site, details are given
below-
Sr No. Loc No. Type of tower Anticipated Classification Drawing required
01 6B/0 DD+0 Wet/Wet Paddy DD -4.5 to ±0 MBE – Wet &
Wet Paddy (3.5 M Depth) for
02 7/0 DD-03 Wet/Wet Paddy WZ-4
DD +1.5 to ±9 MBE – Wet &
03 11B/0 DD+09 Wet/Wet Paddy Wet Paddy (3.5 M Depth) for
WZ-4
Therefore we request you to please give your recommendation for above drawings also and
available us the same at the earliest, so that we can plan to deploy our foundation gangs.
Thanking you and assuring you of our best services at all times.
Yours faithfully,
For GAMMON INDIA LIMITED
Uday Patil
(Asst. General Manager, Contracts – T & D Business)
Encl: as above
To
M/s. Powergrid NM Transmission Limited
(A fully owned subsidiary of Power Grid Corporation of India Limited)
400kV Substation, Konakapadi Post, K.R.Thoppur,
SALEM, TAMIL NADU - 636 502
Kind Attn.: Jayaprakash J.P.(Asst.GM)
Sub.: 1. Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem Transmission
Line (Part-II) (with Hex Zebra Conductor) associated with Transmission System pertaining
to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff Based
Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE02,
Dear Sir,
With reference to the subject contract we would like to inform you that as per approve tower
schedule, we found that foundation drawings of some tower combination (as per anticipated
classification according to site condition) are not available with us to complete the balance
foundation activity, details of required foundation drawings are listed below-
Sr No. Loc No. Type of tower Anticipated Classification Drawing required
01 53/2 DB+0 (6MRC) DRY/DFR DB-4.5 to ±0 MBE (5M&6M
02 58/4 DB-4.5 (5MRC) DRY/DFR RC) – DRY & DFR for WZ-4
Thanking you and assuring you of our best services at all times.
Yours faithfully,
For GAMMON INDIA LIMITED
Uday Patil
(Asst. General Manager, Contracts – T & D Business)
Encl: as above
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,+
Bangalore 560064, Karnataka
Kind Attn.: Mr. R N Singh – CEO
Sub.: 1. Tower Erection Package – ERE01 & 02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I &II) (with Hex Zebra Conductor) associated with
Transmission System pertaining to IPPs of Nagapattinam / Cuddalore Area:
Package - A under Tariff Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01,TBCB/765KV/02(N-
M)/ERE02
Dear Sir,
With reference to the subject contract we would like to bring your kind attention
regarding the supply status of counter poise earthing.
Description Package LOA Qty Supplied Unbilled Qty
Part-I 24 Nos 75 Nos 51 Nos
120 M CP Earthing
Part-II 79 Nos 150 Nos 71 Nos
As per above statement you can found that, already we have unbilled quantity of 122
nos. 120m CP earthing approx. value of 10.07 lacs which is pending from last 6 Months
due to non availability of quantity amendment after our several follow up regarding
the quantity amendment.
Now we would like to inform you that, as per site condition the expected quantity of
the CP earthing is 100 nos & 212 nos respectively for Part-I & Part-II and we need to be
supply further 25 nos & 62 Nos quantity for completion of project, which will be kept
unbilled due to quantity amendment.
Therefore, we request you to please issue the quantity amendment or instruct you
QA&I department to issue the MICC of the previous quantity as well as the quantity
which will be supply now, otherwise we are unable to supply the balance material as
our previous payment to vendor is balance due to non billing of the same.
Thanking you and assuring you of our best services at all times.
Yours faithfully,
For GAMMON INDIA LIMITED
Uday Patil
(Asst. General Manager, Contracts – T & D Business)
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,+
Bangalore 560064, Karnataka
Kind Attn.: Mr. R N Singh – CEO
Sub.: 1. Tower Erection Package – ERE01 & 02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I &II) (with Hex Zebra Conductor) associated with
Transmission System pertaining to IPPs of Nagapattinam / Cuddalore Area:
Package - A under Tariff Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01,TBCB/765KV/02(N-
M)/ERE02
1) The Bolts & Nuts have been supplied along with towers by tower manufacturer
i.e. for suspension tower M/s. Skipper, Kolkata and for all angle type towers M/s.
ICOMM .
2) Till date we have received 326 Nos Towers & extension and its related Bolts &
Nuts for both Wind zone 2 & 4, structure wise details are given in annexure –I.
3) On receipt of Bolts & Nuts for above mentioned towers we made a joint
verification of different size of B&N at our store along with supplier (Joint
inspection report attached), wherein we found that in every 50 kg bag there
have a shortage of approx. 1.5 Kg/bag.
4) On account of above total shortages of 13.58 MT has been observed in Bolts &
Nuts supplied corresponding to supplied towers as on 30.09.2015, i.e. from M/s.
Skipper 9.690 MT against Suspension tower & from M/s. ICOMM 2.908 MT against
angle tower (details structure wise calculation given in annexure-I ).
Considering the above we would like to request you to please kindly instruct the
supplier to replenish the above shortages at the earliest, as well as in future same shall
be take care from their end so that further shortages will not be come on B&N.
In addition to above we also want to draw your kind attention regarding the step bolt
quantity for Basic Body of DC (WZ-4) mentioned in approved BOM. Details given below
–
1) As per approved BOM the total quantity of Step bolts (16 x 175mm) is 84 nos for
per structure.
2) However as per drawing, as well as actual the total quantity is 285 nos for each
structure.
3) For example please consider the drawing no. C.ENGG: TL: 8423-61Z-P-0-111, in
which total 52nos step bolt provision has been given, but the same has been not
incorporate at B&N summary sheet shown at bottom on drawing sheet.
Considering the above, we request you to review the drawings of Basic body of DC
(WZ-4) & accordingly revise the BOM. Kindly also instruct M/s. ICOMM to supply the
differences quantity of 14 set (201x 14= 2814 nos) at the earliest.
In view of the above requested you to kindly review the same and instruct the supplier
to replenish all shortages immediately, so that we will not face any supply shortages
during erection of towers.
Thanking you and assuring you of our best services at all times.
Yours faithfully,
For GAMMON INDIA LIMITED
Uday Patil
(Asst. General Manager, Contracts – T & D Business)
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,+
Bangalore 560064, Karnataka
Kind Attn.: Mr. R N Singh – CEO
Sub.: 1. Tower Erection Package – ERE01 & 02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I &II) (with Hex Zebra Conductor) associated with
Transmission System pertaining to IPPs of Nagapattinam / Cuddalore Area:
Package - A under Tariff Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01,TBCB/765KV/02(N-
M)/ERE02
Dear Sir,
With reference to the subject contract, we invite your kind attention to the following:
1. As per LOA, OPGW stringing is in our scope of work & OPGW is OSM material.
2. We understand that the average length of OPGW drum being supplied by PGNMTL
will
be of approx. 4.5km to 4.8Km.
3. As per tower schedule and considering the length of OPGW in each drum, we will
have to terminate the OPGW laying in suspension tower also. But in suspension tower
which has been supply by M/s. Skipper, there is no provision given for termination of
OPGW on E/W peak on DA type towers.
4. As on date 280 Nos. of DA type towers have been already supplied and 201 towers
erected also.
Therefore, we request you kindly instruct M/s. Skipper to supply the additional mark
number required for termination OPGW on peak at suspension tower, so that we will
not face any problem during the stringing of OPGW, as well as please arrange to give
the approved drum schedule for OPGW stringing.
Thanking you and assuring you of our best services at all times.
Yours faithfully,
For GAMMON INDIA LIMITED
Uday Patil
(Asst. General Manager, Contracts – T & D Business)
Dear Sir,
With reference to the subject contract we acknowledge with thanks receipt of amendment-I
vide letter no. SR-II/C&M/PGNMTL/02/(N-M)/ERE01/AMDT-I(Supply)/1530 and SR-II/C&M/
PGNMTL/02/(N-M)/ERE01/AMDT-I(Serv.)/1531 on dated 23.09.2015 for supply and erection
portion respectively.
However, there is some variation in the received amendment with respect to our
submission. The details of same are as under:
1) Supply Amendment:-
As per Amendment received, Sl No. 1.1 item - Pipe type earthing quantity is 177 Nos and
Counter poise earthing (120mtr) quantity is 95 nos. However as per confirmation given
from PGNMTL, site, the expected quantity of Pipe & CP is 172 nos & 100 nos respectively.
2) Erection Amendment:-
a) Installation of Pipe type and counter poise earthing (120mtr) as detailed above.
b) As per amendment Sl No. 1.0 item Survey, quantity is 100.81 KM in all items related
with survey but as per approved schedule the quantity is 102.624 KM.
c) Amendment Quantity in Sl. No. 9.1 Stringing of 765 KV hexa conductor as per quantity
mentioned in survey above.
We request to note the above changes suitably.
Duplicate copy of amendment dully accepted considering above changes is enclosed here
with for your reference.
Thanking you and assuring of the best service as always.
For GAMMON INDIA LIMITED,
D. Suryanarayana
(Vice President – T & D Business)
Dear Sir,
With reference to the subject contract we acknowledge with thanks receipt of amendment-I
vide letter no. SR-II/C&M/PGNMTL/02/(N-M)/ERE02/AMDT-I(Supply)/1528 and SR-II/C&M/
PGNMTL/02/(N-M)/ERE02/AMDT-I(Serv.)/1529 on dated 23.09.2015 for supply and erection
portion respectively.
However, there is some variation in the received amendment with respect to our
submission. The details of same are as under:
1) Supply Amendment:-
As per Amendment received. Sl No. 1.1 item Pipe type earthing quantity is 48 Nos and
Counter poise earthing (120mtr) quantity is 224 nos. However as per confirmation given
from PGNMTL, site, the expected quantity of Pipe type & CP is 60 nos & 212 nos
respectively.
2) Erection Amendment:-
a) Installation of Pipe type and counter poise earthing at (120mtr) and as detailed
above.
b) As per amendment, Sl No. 1.0 item Survey, where amendment quantity is 98.156 KM
in all items related with survey but in actual as per approved schedule the quantity is
100.312 KM.
c) As per amendment, Sl No. 4.1 item various type excavation soil are not as per our
proposal submitted. After this quantity amendment & foundation casted upto
30.09.2015, wet soil- 709.488 cum, WFR- 228.01 cum & Hard rock – 932.725 (billable value
15.95 lacs), is only available whereas further 70 nos location are balance to cast. This will
restrict us from execution / billing until further amendment is received.
d) Amendment Quantity in Sl. No. 9.1 Stringing of 765 KV hexa conductor as per quantity
mentioned in survey above We request to note the above changes suitably.
Duplicate copy of amendment dully accepted considering above changes is enclosed here
with for your reference.
Thanking you and assuring of the best service as always.
For GAMMON INDIA LIMITED,
D. Suryanarayana
(Vice President – T & D Business)
Cc to. 1. Mr. Joseph Kurion, DGM, Powergrid NM Transmission Limited, Bangalore
Encl: as above
Sub.: 1. Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I &II) (with Hex Zebra Conductor) associated with
Transmission System pertaining to IPPs of Nagapattinam / Cuddalore Area:
Package - A under Tariff Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01,
Dear Sir,
With reference to the subject contract we would like to bring your kind attention on
the following status of the project –
B) Erection Status:
As per L2 Actual
Activity Qty Schedule as on Completed As Balance
Sep’15 on Sep’15
Foundation 272 Nos 272 Nos 207 Nos 65 Nos
Erection 272 Nos 272 Nos 120 Nos 152 Nos
Stringing 103 Km 87 Km 18 Km 69 Km
We invite your kind attention to the following reasons and hold points which were
beyond our control and impact of the same has affected the work progress as well as
schedule plan. Major events of delay are as under:-
I. Survey:
a. As per schedule the check survey should be finalized by Mar’15, but the same has
been received by Sep’15 (section wise details given in annexure-I).
b. Till date we are yet to be get technical clearance from Gantry to 3/0 affecting
2.32
Km & 7 nos Locations, due to bay position finalization at Nagapattinam S/S end.
2. Statutory Involved: In subject line 2 nos Railway crossing & 14 nos Power line crossing
involved. Approvals of railway crossing conclude but out of 14 Power line crossing
we have received clearance of 6 nos, 8 nos are still pending for that 17 Nos
Location & 2.761 Km are affected (Section wise statutory clearance details in
Annexure-IB). The above mentioned statutory clearance (2 nos Rly & 6 nos Power
line) received on Aug’15 and for that 7 nos locations & 1.577 KM section were
affected.
3. Foundation:
a. As per schedule we need to be start foundation activity on the Month of July’14
and for that the first lot of stub should be reached at site by June’14, however
same
has been receipt on Aug’14 and first lot of angle tower stub has been received in
the month of Nov’14.
b. Please refer annexure-II, regarding month wise section clearance received from
PGNMTL for foundation activity and annexure –III regarding month wise s
foundation completion by GIL. Wherein you will observe that upto Jun’15 the
foundation activity is in line with the clearances received from M/s. PGNMTL.
However, subsequently from July’ 15 onwards, backlog has occurred due to ROW
encountered at Cashew nuts garden from section 3/0 to 8/0 wherein 48 locations
were affected and secondly due to delay in approval of statutory clearances
affected 34 nos locations. Further, due to non-finalization of bay position i.e. from
1/0 to 3/0, 7 nos locations were held up.
c. Further 3.5 M foundation has been introduced in the line in Jun’15 i.e. after 13
Months from date of contract. Due to the introduction of above drawings 32
nos locations have been affected and stub for the same are yet to be supplied
from M/s. ICOMM.
5. Stringing:
a. Stringing activity were schedule to start from Jan’15, but due to delay in supply of
angle towers stretches could not be ready to commence the stringing till April 15.
Also the first lot of Line material has been receipt at site on the month of May’15
which was scheduled in Dec’14.
b. After receipt of material and angle towers we have started our stringing activity
from section 38/0 to 39/0 – 1.568 Km. After completion of this section we were
only able to do paying out from 39/0 to 41/0 – 6.732 Km, the final sag was
pending due to non-availability of angle towers with desired extensions and
further no sections was clear for stringing which we repeatedly informed you
through our communication (vide letter no. GIL/AL/G-289/17355 dated 06.02.15,
GIL/PGCIL-NM/G-289&290/2014-15/48 dated 19.05.15,GIL/PGCIL-NM/G-
289&290/2014-15/60 dated 02.06.15, GIL/SS/G-289&290/17883 dated 04.07.15,
GIL/SS/G-289&290/18169 dated 26.08.15 copy enclosed). This has resulted hold
of stringing activity for next two months.
c. Further We have submitted our stringing plan section wise, identifying the
immediate required tower extensions to complete the stringing stretches of
36.309 KM, vide our letter no. GIL/SS/G-289&290/18169 on dated 26.08.15, but
supply of angle tower and its extension not done by PGNMTL and we are unable
to ready the stretches to expedite the stringing activity.
d. Also, as per contract 10% price component of Foundation & erection activity will
be released after completion of corresponding stringing section. However due to
above reasons which are beyond control of GIL, stringing progress has been
delayed and for that total 10% amount of 372.73 Lacs are held up which
affected the cash flow of the project.
From the above, you will observe that the delay occurred on subject line were beyond
our control, and also incurred extra cost resulting in shortages of funds for completion
of project.
Uday Patil
(Asst. General Manager, Contracts – T & D Business)
Encl: As Above
Ref: GIL/SS/G-289&290/18375 Date:
23.10.2015
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,+
Bangalore 560064, Karnataka
Kind Attn.: Mr. Joseph Kurion – DGM
Sub.: 1. Tower Erection Package – ERE01 & 02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I &II) (with Hex Zebra Conductor) associated with
Transmission System pertaining to IPPs of Nagapattinam / Cuddalore Area:
Package - A under Tariff Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01,TBCB/765KV/02(N-
M)/ERE02
Dear Sir,
This is with reference to the subject project; please find enclosed herewith the amedment of
Original Bank Guarantee towards Advance of erection of the above project for your records.
Sr.
Date of Issuing Amount Present
No B. G. No. & Date Remarks
Amend Bank (Rs.) Validity
.
I02G0PG141920003 Erection
1 06.10.15 CANARA 4,23,88,681/- 31.10.16
Dt. 11.07.2014 Advance BG
I02G0PG141920005 Erection
2 06.10.15 CANARA 3,86,14,230/- 31.10.16
Dt. 11.07.2014 Advance BG
Uday Patil
(Asst. General Manager, Contracts – T & D Business)
Encl: As Above
Dear Sir,
With reference to the subject project we want to draw your kind attention on the
following-
1. As per contract Payment terms 10% price component of Foundation and
erection will be released after stringing of the corresponding section.
2. For above clause upto Sep’15 the value of 10% retention amount is 416 lacs and
412 lacs respectively for Part-I & Part-II .
3. Till date we have done 20.725 KM & 3.409 KM stringing respectively at part-I and
Part-II project.
4. Considering the above work done we already raised 10% retention bills of
corresponding section, the bills details are given in below-
Sl No. Package Bill No. Date Amount
01 G-289 (Part-I) 01 12.10.15 49,25,308/-
02 G-289 (Part-I) 02 02.11.15 59,64,166/-
03 G-290 (Part-II) 01 02.11.15 22,86,920
TOTAL AMOUNT 1,31,76,395/-
Request you kindly arrange to release the 131lacs against 10% at the earliest. Also you
agree that stringing progress of subject project has been effected due to non-
availability of tower & desired extension and hence 10% retention amount has been
stuck up which are beyond control of M/s. GIL.
Therefore we request you kindly arrange to release the balance 10% amount, so that
we can able to funding the project for its timely completion.
Thanking you and assuring our best services always.
With Regards
For GAMMON INDIA LIMITED,
Uday Patil
(Asst. General Manager, Contracts – T & D Business)
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,+
Bangalore 560064, Karnataka
Kind Attn.: Mr. Joseph Kurion – DGM
Sub.: 1. Tower Erection Package – ERE01 & 02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I &II) (with Hex Zebra Conductor) associated with
Transmission System pertaining to IPPs of Nagapattinam / Cuddalore Area:
Package - A under Tariff Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01,TBCB/765KV/02(N-
M)/ERE02
Dear Sir,
With reference to the subject project we invite your kind attention on following-
1) Upon completion of survey and finalization of tower quantity, here we submitted
quantity amendment proposal vide letter No. GIL/SS/G-289/17460 & GIL/SS/G-
290/17461 on dated 07.03.2015 respectively for Part-I& Part-II, with estimation of
increasing contract price by 34% for Part-I & 15% for Part-II.
Based on the same enclosed herewith, please find quantity amendment-II proposal,
wherein you observe that quantity are getting exceeded specifically for foundation
and erection work and immediate amendment is required for billing of same.
G-290 (Part-II)
Description LOA Value Amnd-I dated 23.09.15 Proposed Amendment
Uday Patil
(Asst. General Manager, Contracts – T & D Business)
Encl: As above.
To
The Dy. General Manager (Engg-TL/TBCB)
Powergrid Corporation of India Limited
Saudamini Plot No.-2, Sector-29
Gurgaon -122001, (Haryana)
Fax: 0124-2571760, 2571848
With reference to the subject we would like to inform you that, we have received
approval of ACD drawings vide letter No. CC:ENGG:TL:TBCB:PGNMTL:Gammon: ERE01
& ERE02 on dated 13.02.2015. But as per our approved survey report +18M/25M
extension of DB & DC tower of WZ-4 are also introduce on our line.
Based on the above required extensions, here we submit the barbed wire calculation
for the tower with +18M/25M extension of DB &DC tower, as details are given below –
Sl No. Drawing No. Wind zone
01 G-289/G290-ACC-04/WZ-4 4
Thanking you and assuring you of our best services at all times.
Yours faithfully,
For GAMMON INDIA LIMITED,
Uday Patil
(Asst. General Manager, Contracts – T & D Business)
Encl.: as above
Cc. Mr. Joseph Kurion, DGM, Powergrid NM Transmission Limited, Bangalore
Sub.: 1. Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part- II) (with Hex Zebra Conductor) associated with
Transmission System pertaining to IPPs of Nagapattinam / Cuddalore Area:
Package - A under Tariff Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE02,
Dear Sir,
With reference to the subject contract we would like to bring your kind attention on
the following status of the project –
B) Erection Status:
As per L2 Actual
Activity Qty Schedule as on Completed As Balance
Sep’15 on Sep’15
Foundation 272 Nos 272 Nos 207 Nos 65 Nos
Erection 272 Nos 272 Nos 120 Nos 152 Nos
Stringing 103 Km 87 Km 18 Km 69 Km
The above documents are enclosed for your scrutiny and approval.
Approved copy of Tower Spotting Data, Sag Tension Calculation & Check Survey report is also attached
for your ready reference.
Kindly forward one approved copy for our reference & further distribution from our end. Thanking you
assuring the best of our service as always. Thanking you
Yours faithfully
For GAMMON INDIA LIMITED
Uday Patil
(Asst. General Manager, Contracts – T & D Business)
Encl.: as above
Cc. Mr. Joseph Kurian, DGM (Engg.), PGCIL, Bangalore
Ref: GIL/SS/G-290/18611 Date: 28.12.2015
To
The Dy. General Manager (Engg-TL/TBCB)
Powergrid Corporation of India Limited
Saudamini Plot No.-2, Sector-29
Gurgaon -122001, (Haryana)
Fax: 0124-2571760, 2571848
Kind Attn.: Mr. G K Sharma
Sub.: 1. Tower Erection Package – ERE 02 for 765 kV D/C Nagapattinam - Salem Transmission Line
(Part- II) (with Hex Zebra Conductor) associated with Transmission System pertaining to IPPs of
Nagapattinam / Cuddalore Area: Package - A under Tariff Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE02
The above documents are enclosed for your scrutiny and approval.
Approved copy of Tower Spotting Data, Sag Tension Calculation & Check Survey report is also attached
for your ready reference.
Kindly forward one approved copy for our reference & further distribution from our end. Thanking you
assuring the best of our service as always. Thanking you
Yours faithfully
For GAMMON INDIA LIMITED
Uday Patil
(Asst. General Manager, Contracts – T & D Business)
Encl.: as above
Cc. Mr. Joseph Kurian, DGM (Engg.), PGCIL, Bangalore
Sub.: 1. Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I &II) (with Hex Zebra Conductor) associated with
Transmission System pertaining to IPPs of Nagapattinam / Cuddalore Area:
Package - A under Tariff Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01,
Dear Sir,
With reference to the subject contract we would like to bring your kind attention on
our advance bank guarantee status, and amount of advance adjusted are as under:
Sl Bank Guarantee Issuing Present BG Unadjusted Package
No. Details Bank Value Advance
Value
01 102G0PG141920003 CANARA 3,86,14,230/- 69,99,973/- ERE-01
Date: 11.07.2014
Bill wise annexure-I is enclosed herewith
Also we would like to inform you that we have received Amendment –I to contract
were issued vide your letter No. SR-II/C&M/PGNMTL/02/(N-M)/ERE01/AMDT-I (Serv.)/
1531on date 23.09.2015 wherein value of contract has been amended from Rs.
594,593,500/- to Rs. 683,044,358/-. Accordingly as per payment terms 10% advance of
Increase value is payable which is coming to Rs. 88,47,979/-. We herein claim the
same copy of invoice attached herewith.
Further enclosed herewith copy of BG amendment for PBG which value has been
enhanced to Rs. 6,83,82,026/- i.e. 10% of amended value of contract. With respect to
advance BG, we herein like to inform that already 3.20 cr. advance has been
adjusted and as per contract BG can be reduced corresponding to advance
adjusted.
In view of the same, we request you to process the claim of advance payment of Rs.
88,47,999/- on priority. We herein confirm you that PBG already amended (copy
enclosed) & for ABG we will not claim reduction by Rs. 3,16,14,257/-. Thanking you and
assuring the best of our service as always.
Yours faithfully
For GAMMON INDIA LIMITED
Uday Patil
(Asst. General Manager, Contracts – T & D Business)
Encl.: as above
Cc. 1. Mr. R N Singh, CEO, PGCIL Bangalore
2.Mr. Joseph Kurian, DGM (Engg.), PGCIL, Bangalore
Sub.: 1. Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part- II) (with Hex Zebra Conductor) associated with
Transmission System pertaining to IPPs of Nagapattinam / Cuddalore Area:
Package - A under Tariff Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE02,
Dear Sir,
With reference to the subject contract we would like to bring your kind attention on
our advance bank guarantee status, and amount of advance adjusted are as under:
Unadjusted
Sl. Bank Guarantee Issuing Present BG
Advance Package
No. Details Bank Value
Value
102G0PG141920005
01 CANARA 4,23,88,681/- 1,21,13,000/- ERE-02
Date: 11.07.2014
Bill wise annexure-I is enclosed herewith
Also we would like to inform you that we have received Amendment –I to contract
were issued vide your letter No. SR-II/C&M/PGNMTL/02/(N-M)/ERE02/AMDT-I (Serv.)/
1529on date 23.09.2015 wherein value of contract has been amended from Rs.
638,338,799/- to Rs. 736,041,921/-. Accordingly as per payment terms 10% advance of
Increase value is payable which is coming to Rs. 97,70,304/-. We herein claim the same
copy of invoice attached herewith.
Further enclosed herewith copy of BG amendment for PBG which value has been
enhanced to Rs. 7,36,04,192/- i.e. 10% of amended value of contract. With respect to
advance BG, we herein like to inform that already 3.03 cr. advance has been
adjusted and as per contract BG can be reduced corresponding to advance
adjusted.
In view of the same, we request you to process the claim of advance payment of Rs.
97,70,304/- on priority. We herein confirm you that PBG already amended (copy
enclosed) & for ABG we will not claim reduction by Rs. 3,02,75,681/-. Thanking you and
assuring the best of our service as always.
Yours faithfully
For GAMMON INDIA LIMITED
Uday Patil
(Asst. General Manager, Contracts – T & D Business)
Encl.: as above
Cc. 1. Mr. R N Singh, CEO, PGCIL Bangalore
2.Mr. Joseph Kurian, DGM (Engg.), PGCIL, Bangalor
1. All supplies under the scope of GIL completed except tower accessories
(NP/DP/PP/CP), which confirmation of sequence issued by PGNTL on 22.12.2015
vide letter no. PGNMTL/SLM/765 KV N-D TL/Part-I and same are under inspection
and will be supplied within April’16.
2. Towers, B&N, Conductor, Hardware fittings & Accessories, Insulators and OPGW are
under the scope of PGNMTL. As on date 15 sets of towers, 46 sets SIS Pilot fitting
and 3000 Nos 210KN Long rod insulators is balance to be supplied.
II. Construction:
Completed
Final Balanc
Activity UOM upto Remarks
Qty. e
11.04.2016
1. U/P – 9 loc, Clear Loc -2 Nos.
Foundation Nos. 272 237 35 2. ROW-19, Hilly Area- 3 loc.
3. Forest Area -2 Loc
1. U/P – 9 loc, Clear Loc-7 Nos
Tower 2. 35 loc. Foundation Balance
Nos. 272 204 68
Erection 3. Non availability Tower – 7 loc.
4. ROW -8 Loc, Water Log – 2 Loc.
1. Due to balance foundation & erection
34.125Kms.
Stringing Km 100.33 36.24 64.091 2. U/P – 6.686 Kms. Clear Front- 5 Km
3. Tree Cutting Pending at Maximum
balance sections.
e) Delay in clearance of ROW: Huge ROW at section 48B to 49A near village
Pithyakaplayam and between location no. 54 to 55 at village Belur. Till date ROW are
not resolve by M/s. PGNMTL. At AP 63 to AP64 line has been diverted on 28.03.16 due
to ROW which profile was submitted on 04.04.2016, approval of the same is pending.
GAMMON INDIA LIMITED (T & D Business)
//3//
Impact: Delay in taking up Foundation, Erection (18 Nos Loc) & Stringing (6.00 KM),
frequent idling of gangs having severe price implications.
f) Delay in clearance of statutory approvals: The subject line consists of 8 Power line
crossings and 2 railway line crossings. All of these crossings have been cleared in
Aug’15 & Oct’15. Details enclosed in annexure-III (copy enclosed).
Impact: Delay in taking up work at type work could not be taken up for more than 1 year.
g) Delay in clearance of Forest approvals: In this section Total 10 nos locations are in
forest area which clearance we have received in the month of Jan’15. However Loc no.
58/4 are on hold due to non-clearance from social forest.
Impact: Delay in foundation, erection & stringing.
h) Interruption due to intermediate rain:- Due to heavy rainfall since Oct’15 upto Dec’
2015, work at site got hampered and due to same further extra time required for work
completion.
Vide our regular correspondences & MOMs regarding above issue is enclosed for your
reference. From the above you would agree that, the reasons for delay of project were beyond
control of GIL.
However with huge mobilization of resources & your continued support and considering field
constraints, we expect to complete all balance work of line by June’16 and taking over of line in
Aug’16 by PGNMTL.
In view of the above, we appeal to issue -:
Time limit extension up to 31st Aug’2016 without imposition of LD & with
application of Price Variation for the extended period for continuance of balance
work.
Request you to arrange for the needful at the earliest.
Thanking you,
Yours faithfully
For GAMMON INDIA LIMITED
Uday Patil
Above payment are critically required for maintaining the huge resources at site and to
achieve the plan work.
Please Expedite. Thanking you,
Yours faithfully
For GAMMON INDIA LIMITED
Uday Patil
(Asst. General Manager, Contracts – T & D Business)
To
Sub.: 1. Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-II) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package-A under
Tariff Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE02,
Dear Sir,
With reference to the subject contract, we invite your kind attention to the following:
2. As per clause no 9.2.2, page 76, of GCC of subject contract, “ The Advance
payment Security shall be allowed to be reduced every six (06) months after first
running account bill / stage payment under the contract if the validity of the
Bank Guarantee is more than one year. The cumulative amount of reduction at
any point of time shall not exceed seventy five percent (75%) of the advance
corresponding to cumulative value of facilities completed as per a certificate to
be issued by the Project Manager.”
Proposed
Sl. No. BG number BG Amount Reduced By in (%)
BG Value
01 I02GOPG141920003 6,33,54,719/- 1,58,38,680/- 75%
Further, we confirm that this is our second request for Advance payment Bank
Guarantee value reduction against completed erection.
Uday Patil
(Asst. General Manager, Contracts – T & D Business)
Encl.: Details of adjusted advance payment
Cc. 1. Mr. R N Singh, CEO, PGCIL Bangalore
2. Mr. Joseph Kurian, DGM (Engg.), PGCIL, Bangalore
Ref: GIL/RS/G-289/19145 Date:
04.05.2016
To
Sub.: 1. Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package-A under
Tariff Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01,
Dear Sir,
With reference to the subject contract, we invite your kind attention to the following:
4. From above you will observe that the Bank’s obligation is concluded once the
advance is fully adjusted and hence there is no reason to keep the advance Bank
Guarantee and extending its validity.
In view of the above we request you to kindly arrange for release of Bank Guarantee
along with earlier submitted original & Bank Guarantee amendment copies.
Yours faithfully
For GAMMON INDIA LIMITED
Uday Patil
(Asst. General Manager, Contracts – T & D Business)
Encl.: As above
Cc. 1. Mr. R N Singh, CEO, PGCIL Bangalore
2. Mr. Joseph Kurian, DGM (Engg.), PGCIL, Bangalore
Ref: GIL/RS/G-289/…. Date:…..05.2016
To
Sub.: 1. Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package-A under
Tariff Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01,
Ref.: NOA No. PGNMTL/765 kV/02(N-M)/ERE02/NOA-I/10 & NOA-II/11 dated 16.05.2014.
Dear Sir,
With reference to the subject contract, we would like to bring your kind attention to
the following:
3. Accordingly as per payments 10% advance for increased value is payable which is
coming to Rs.71,37,170/-
4. We would like to inform you that, there is no need for enhancing the advance
bank guarantee with respect to the increase in amendment value because
advance adjusted is already more than the revised value of advance bank
guarantee required for claiming the differential value. Detail calculation given in
Annexure-I & II.
Yours faithfully
For GAMMON INDIA LIMITED
Uday Patil
(Asst. General Manager, Contracts – T & D Business)
Encl.: As above
Cc. 1. Mr. Joseph Kurian, DGM (Engg.), PGCIL, Bangalore
To
Sub.: 1. Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-II) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package-A under
Tariff Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE02,
Dear Sir,
With reference to the subject contract, we would like to bring your kind attention to
the following:
3. Accordingly as per payments 10% advance for increased value is payable which is
coming to Rs.78,48,655/-
4. We would like to inform you that, there is no need for enhancing the advance
bank guarantee with respect to the increase in amendment value because
advance adjusted is already more than the revised value of advance bank
guarantee required for claiming the differential value. Detail calculation given in
Annexure-I & II.
GAMMON INDIA LIMITED (T&D BUSINESS)
//2//
Uday Patil
(Asst. General Manager, Contracts – T & D Business)
Encl.: As above
Cc. 1. Mr. Joseph Kurian, DGM (Engg.), PGCIL, Bangalore
Ref: GIL/RS/G-289/19219 Date: 17.05.2016
To
Dear Sir,
With reference to the subject contract we acknowledge with thanks the receipt of Amendment-
II vide letter no. SR-II/C&M/PGNMTL/02(N-M)/ERE01/201, Amendment-II (Supply Contract)
dated 27.04.2016 and SR-II/C&M/PGNMTL/02(N-M)/ERE01/201, Amendment-II
(Service Contract) dated 27.04.2016 for supply and erection portion respectively.
Duplicate copy of amendment dully accepted is enclosed here with for your reference, please.
Thanking you & assuring you our best services at all times.
Yours faithfully
For GAMMON INDIA LIMITED,
D. Suryanarayana
(Vice President, Contracts & Marketing– T & D Business)
Encl.: As above
Cc.: 1. Mr. Joseph Kurion, DGM, Powergrid NM Transmission Limited, Bangalore
2. Mr. R Gunasekaran, CM, Powergrid NM Transmission Limited, Attur
Dear Sir,
With reference to the subject contract we acknowledge with thanks the receipt of
Amendment-II vide letter no. SR-II/C&M/PGNMTL/02(N-M)/ERE02/200, Amendment-II
(Supply Contract) dated 27.04.2016 and SR-II/C&M/PGNMTL/02(N-M)/ERE01/200,
Amendment-II (Service Contract) dated 27.04.2016 for supply and erection portion
respectively.
Duplicate copy of amendment dully accepted is enclosed here with for your reference, please.
Thanking you & assuring you our best services at all times.
Yours faithfully
For GAMMON INDIA LIMITED,
D. Suryanarayana
(Vice President, Contracts & Marketing– T & D Business)
Encl.: As above
Cc.: 1. Mr. Joseph Kurion, DGM, Powergrid NM Transmission Limited, Bangalore
2. Mr. J P Jayaprakash, CM, Powergrid NM Transmission Limited, Salem.
Sub.: 1. Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-II) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package-A under
Tariff Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE02,
Dear Sir,
With reference to subject project we invite your kind attention to the following:
(i) For the subject project angle type towers were supplied by M/s. ICOMM.
(ii) During erection at location no. 101/0(DD+18M) & 124/0(DD+25M)
on 06.05.2016,we observed fabrication mistake in all leg joint plates, cleats,
support plates etc. and also in bracing joint cleats (Mark No. 2536 & 2537R).
(iii) Same was communicated to you vide our mail dated 08/05/16(copy
enclosed), but till date issue is not resolved.
Because of above we are not able to carry out erection work on above two
locations since 06/05/16 and two erection gangs are idle since more than two
week.
Hence we request you to kindly look into the same and arrange to resolve the issue at
the earliest; to resume tower erection work on above locations and avoid gang idling.
Uday Patil
(Asst. General Manager, Contracts – T & D Business)
Encl.: As above
Cc. 1. Mr. Joseph Kurian, DGM (Engg.), PGCIL, Bangalore
3. M/s ICOMM
To
M/s. Power grid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Near RTO Driving test track, Singanayakanahalli,
Yelahanka Hobli, Doddaballapur Road,
Bangalore 560064, Karnataka.
Sub.: Tower Erection Package – ERE01 & ERE02 for 765 kV D/C Nagapattinam - Salem Transmission
Line (Part-I&II) (with Hex Zebra Conductor) associated with Transmission System pertaining to
IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff Based Competitive Bidding
Route.
Ref.: 1. NOA No. PGNMTL/765 kV/02(N-M)/ERE01/NOA-I/10 & NOA-II/11 dated 16.05.2014.
2. NOA No. PGNMTL/765 kV/02(N-M)/ERE01/NOA-I/12 & NOA-II/13 dated 16.05.2014.
Dear Sir,
With reference to the subject project, we would like to inform you that, the bill processing is taking long
time and resulting into delay in getting the payments. Please find below the bill wise details which are
yet to be processed and balance for release of payment:
Further, other than the above Rs8.82Cr, approximately Rs17.46Cr retention amount is also blocked with
PGNMTL. Due to this huge fund blockage we are finding difficult to fund the project.
Hence, we request you to please look into and arrange to release atleast 8.82 Cr. on urgent basis.
Yours faithfully
For GAMMON INDIA LIMITED
D. Suryanarayana
(Vice President, Contracts & Monitoring – T & D Business)
Cc.:1. Mr. Joseph Kurian – DGM, Powergrid NM Transmission Limited, Bangalore.
2. Mr. J P Jayaprakash, CM, PGNMTL, Powergrid NM Transmission Limited, Salem.
3. Mr. R Gunasekaran CM, PGNMTL, Powergrid NM Transmission Limited, Attur.
Sub.: Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem Transmission
Line (Part-I&II) (with Hex Zebra Conductor) associated with Transmission System
pertaining to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff Based
Competitive Bidding Route.
Ref.: NOA No. PGNMTL/765 kV/02(N-M)/ERE02/NOA-I/12 & NOA-II/13, dt.16.05.2014.
Dear Sir,
With reference to the subject contract and from payment abstract dt.04.08.16, we understand
that, from our erection RA bill No.24 dt.04.07.2016 (Bill for the month of June’16), for net
payable amount of Rs.2,79,48,213/-, Powergrid has unilaterally deducted Rs.32,00,000/-
against shortage of tower materials supplied by M/s. ICOMM.
In this regard, kindly note that as per contract, supply of towers in complete shape is in scope
of Powergrid, which is being arranged from M/s. ICOMM & we are not responsible for any
shortages.
We strongly object such deductions & request you to release Rs.32,00,000/- immediately.
Thanking you & assuring you our best services at all times.
Yours faithfully,
For GAMMON INDIA LIMITED ( T&D, Business ),
(K. P. Singh)
Vice President, Project Execution
Sub.: Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem Transmission
Line (Part-I) (with Hex Zebra Conductor) associated with Transmission System
pertaining to IPPs of Nagapattinam / Cuddalore Area: Package-A under Tariff Based
Competitive Bidding Route : Request for Issuance of time limit extension-reg.
Dear Sir,
With reference to the subject contract, we would like to bring the following to your kind notice:
1. As per contract, scheduled completion date of line work was 19.01.2016 and the trial
operation with taking over of line on 19.06.2016.
2. However due to the various reasons as elaborated in our letter ref. cited (3) above,
which were beyond the control of GIL such as (ii) Delay in Supply of stubs & Towers, (ii)
Delay in Supply of line materials, (iii) Introduction of 3.5M depth Foundation, (iv)
Increase in volume of work & Non Availability of Quantity Amendment, (v) Discrete
supply of Tower, (vi) Delay in clearance of locations near Ariyalur PGNMTL Substation,
(vii) Delay in clearing statutory approvals, (viii) ROW (ix) Interruption of work due to
intermediate rain and hence Provisional extension of time for the work under
subject contract had been accorded by you and up to 31.08.2016, vide your letter
reference cited (4), above.
3. Here again we would like to bring your kind attention to the Present status & completion
of balance work:
A. Supply:
(i) Supply of material under the scope of GIL completed in all respect.
(ii) Towers, B&N, Conductor, Hardware fittings & Accessories, Insulators and OPGW are
under the scope of PGNMTL. Last lot of material received in July’16 as against
scheduled in Sept’15 as per approved L2 schedule(month wise supply details is
shown in Annexure-I & II).
B. Physical Progress:
(i) Gantry-AP2A
(1.363Km)-1No FDN &
1No Ere Pending.(ii)
AP6B to AP7
(0.726Km)-, Loc. Ere
Stringing Km 102.6 91.413 5.568 96.981 5.598 U/P, (iii) AP10 to
AP11A (2.8Km),
(iv)AP28 to
AP29(0.709Km)-2Nos
of PLX shutdown is
required to be
arranged.
(i) Foundation: Till 30th April’16 we had completed 267 foundation and only 4locations
(AP15/1, AP2, AP1 & 1/1) were pending in addition to the ROW faced till completion
of 267Foundation. Out of balance four AP15/1 completed on 12 th May’16.Locations
AP2 & AP1 were completed on 31st May’16 and 18th June’16 respectively
immediately after clearance of ROW. But the location no. 1/1 is still under ROW, due
which we are unable to complete the foundation of Part-I. Had these four locations
been cleared before, the entire foundation of Part-I would have been completed
much before.
(ii) Erection: As on 1st May’16, total 23Locations were balance for erection. As the
locations were under ROW, the work could not be taken up simultaneously in all
locations and we have restricted to deploy only 10erection gangs during May’16 and
again we had to demobilize few gang due to unavailability of work front. The tower
erection at Loc. No. 7/0 remain stopped since 18.05.2016 till 16.07.2016 due to
ROW and also due to mismatch of holes and issue in shortage supply, tower
erection at 2A/0 has suffered severely (work remained stopped from 08.06.16 till
25.06.16). On 16.7.2016, after clearance of ROW of Loc. No. 7/0, erection work
taken up and the same is under Progress. Now only one location 1/1 is pending for
erection, which is pending for foundation due ROW, as stated in ante Para.
(iii) Stringing: The progress of stringing suffered due to above reasons. Section AP3 to
AP4 (4.481Km) was under ROW which cleared only during July’16 & Work on
balance sections are under progress.
4. The above issues have dragged the completion of project to the fagend. This has been
discussed to you in every meeting. The copy of our regular correspondence & MOM
regarding the same is enclosed herewith for your ready reference.
5. At this juncture it can stated that the completion of balance work is totally dependent on
clearance of ROW for Loc. No. 1/1, which is beyond the control of GIL.
Gammon India Limited (T & D Business)
//4//
6. Further the commissioning of this Part of the Line is dependent on completion of Part-II.
Considering the clearance of ROW, quantum of balance work in Part-II, we anticipate
the completion of Part-I by Aug’16 and Part-II by Sept’16; and the testing,
commissioning & taking of line by PGNMTL in Dec’16.
In view of above, we appeal you for issuance of “Time limit extension from 01.09.2016 upto
31.12.2016, without imposition of Liquidated Damages & with the application of Price
Variation for extended period” for continuance of work.
Thanking you & assuring you our best services at all times.
Yours faithfully
For GAMMON INDIA LIMITED
(Uday Patil)
Asst. General Manager (Contracts – T & D Business)
Encl.: As above
Cc.: 1. Mr. Joseph Kurian – Dy. General Manager, PGNMTL, Bangalore.
2. Mr. V. Khare, CEO, PGNMTL, Bangalore.
3. Mr. D. Ganeshan, DGM (C&M), PGNMTL, Bangalore.
4. Mr. Surendran, AGM, PGCIL, `Salem.
Sub.:Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem Transmission
Line (Part-II) (with Hex Zebra Conductor) associated with Transmission System
pertaining to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff Based
Competitive Bidding Route : Request for Issuance of time limit extension-reg.
Dear Sir,
With reference to the subject contract, we would like to bring the following to your kind notice:
1. As per contract, scheduled completion date of line work was 19.01.2016 and the trial
operation with taking over of line on 19.06.2016.
2. Vide our letter no. GIL/RP/G-290/19050 dated 13.04.2016; we applied for time limit
extension up to 31st Aug’2016. However, same is still awaited from PGNMTL.
A. Supply:
(i) Supply of material under the scope of GIL completed in all respect.
(ii) Towers, B&N, Conductor, Hardware fittings & Accessories, Insulators and OPGW
are under the scope of PGNMTL. Last lot of material received in July’16 (Excl.
Insulator, still 730Nos of 210KN Long Rod Insulator is balance to supply), as against
scheduled in Sept’15 as per approved L2 schedule.
B. Construction:
i) 13.14Km is
balance for
above detailed
foundation &
Stringing Km 100.331 69.283 8.637 77.92 22.411
erection.
ii) Balance
stringing is under
progress.
4. Further, the construction work of the subject project substantially got delayed from
scheduled completion, due to the following reasons:
a) Delay in supply of Stubs & Towers: As per schedule, supply of stubs and towers were
to start from June’14 & Sept’14 respectively. However actual supply of stubs started in
Aug’14 and supply of angle type stubs was initiated in Dec’14, this has resulted in
foundation of gap locations and non-readiness of complete stretches for tower erection
and stringing. Similarly actual supply of suspension towers commenced in Jan’15 and
Angle type towers supply were started in June’15. However we have received the first
lot of DD type tower (WZ-II) during the month of Sep’2015. Month wise actual supply
statement compared to scheduled supply is enclosed in Annexure-I&II.
Gammon India Limited (T & D Business)
//3//
b) Delay in supply of Line materials: As per schedule, supply of Line materials; such as
Conductors, Insulators, hardware fittings, conductor Accessories & OPGW etc., were to
commence from Sept’14, however actual supply started during Mar’15. Supply of
OPGW was made during Feb’16. Actual supply of line materials (excl. Insulator, still
730Nos of 210KN Long Rod Insulator is balance to supply) completed in July’2016. The
month wise supply details are given in Annexure-I&II.
Impact: Delay in supply of Line materials by 6 months & delay in receipt of OPGW
by 17 months has resulted much delay in commencement and taking up of
stringing work at site.
d) Discrete supply of Tower: The supply of towers & required extensions were not made
either in line with L-2 scheduled or the site requirement. Therefore erection work could
not be carried out several times for want of necessary extensions, even though the
basic body was available. As stated in ante para (B-i) of this letter, inordinate delay in
supply of angle type towers as well stubs, had resulted in gap locations during the
execution of work. Also during the month of May’15 & June’15 no erection were carried
out due to unavailability of towers at site.
Impact: This has delayed the progress of work for around more than 3months.
e) Delay in clearance of ROW: We have faced Severe ROW at section 48B to 49A near
village Pithyakaplayam and between location no. 54 to 55 at village Belur. ROW of
AP54 to AP55 was cleared during 4th week of July’16. At AP 68 to AP69 route has been
diverted on 28.03.16 due to ROW and diverted route has been finalized/ freezed only
during 4th week of June’16. Similarly ROW in the section AP61 to AP64 was cleared
during 1st week of July’16.
f) Delay in getting of statutory approvals: The subject line is having of 8 Power line
crossings and 2 railway line crossings. All of these crossings have been cleared /
approved during Aug’15 & Oct’15 respectively.
Impact: Delay in taking up work at these locations as the type of tower could not
be freezed for more than 1 year.
g) Delay in getting Forest approvals: Total 10 Locations are falling in forest area which
has been cleared progressively only during the year 2016 for foundation. Example Loc.
No. 53/4 during April’16, 53/1 during Mar’16 & 58/4 were cleared during 3rd week of
July’16. Even as on today also, 53/1 is still to clear for taking up erection work.
5. Our regular correspondences & MOMs, regarding the above issues are enclosed for
your reference.
6. From the above you will agree that, the reasons of delay in completion of project stated
above are beyond the control GIL.
7. However with huge mobilization of resources, your continued support and considering
field constraints, we expect to complete all the balance work by September’16,
commissioning and taking over of line by PGNMTL by Dec’16.
In view of above, we appeal you for issuance of “Time limit extension upto 31.12.2016,
without imposition of Liquidated Damages & with the application of Price Variation for
extended period” for continuance of work.
Thanking you & assuring you our best services at all times.
Yours faithfully
For GAMMON INDIA LIMITED
(Uday Patil)
Asst. General Manager (Contracts – T & D Business)
Encl.: As above
To
Sub.: 1.Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package-A under Tariff
Based Competitive Bidding Route : Request for release of Advance bank
Guarantee – Reg.
Dear Sir,
With reference to the subject contract, we invite your kind attention to the following:
1. The details of advance payment Bank guarantee submitted towards advance payment are
as under:
01 68,44,92,432/- 6,56,57,222/-
Cont…
4. Further, as per clause no 9.2.2, page 76, of GCC of subject contract, “ The Advance
payment Security shall be allowed to be reduced every six (06) months after first
running account bill / stage payment under the contract if the validity of the Bank
Guarantee is more than one year. The cumulative amount of reduction at any point
of time shall not exceed seventy five percent (75%) of the advance corresponding to
cumulative value of facilities completed as per a certificate to be issued by the
Project Manager.”
Therefore, we request to issue your confirmation letter addressed to Bank Guarantee issuing
Bank i.e. CANARA BANK, Specialized Prime Corporate Branch, Maker Chambers III, 7 th Floor,
Nariman Point, Mumbai-400021 and having its Head office at 112,J.C.Road,Bangalore – 560
002 with copy to us towards acceptance of reduction in BG value by Rs.2,38,54,855/-, as
detailed above.
Further, we confirm that this is our second request for Advance payment Bank Guarantee
value reduction against completed erection.
Yours faithfully,
For GAMMON INDIA LIMITED
Uday Patil
Asst. General Manager, Contracts – T & D Business
Encl.: As above
Cc. 1. Mr. R N Singh, CEO, PGCIL Bangalore
2. Mr. Joseph Kurian, DGM (Engg.), PGCIL, Bangalore
Ref: GIL/RS/G-290/19642 Date: 26.08.2016
To
Sub.: 1.Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-II) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package-A under Tariff
Based Competitive Bidding Route : Advance payment bank Guarantee reduction
request-Reg.
Dear Sir,
With reference to the subject contract, we invite your kind attention to the following:
1. The details of advance payment Bank guarantee submitted towards advance payment are
as below:-
01 77,25,27,893 /- 7,35,39,369/-
Cont…
4. Further, as per clause no 9.2.2, page 76, of GCC of subject contract, “ The Advance
payment Security shall be allowed to be reduced every six (06) months after first
running account bill / stage payment under the contract if the validity of the Bank
Guarantee is more than one year. The cumulative amount of reduction at any
point of time shall not exceed seventy five percent (75%) of the advance
corresponding to cumulative value of facilities completed as per a certificate to
be issued by the Project Manager.”
5. According to above mentioned clause the BG value can be reduced as under:-
Present BG Proposed
Sl. No. BG number Reduced By in (%)
Value BG Value
01 I02GOPG141920003 4,23,88,681/- 1,58,38,680/- 75%
Therefore, we request to issue your confirmation letter addressed to Bank Guarantee issuing
Bank i.e. CANARA BANK, Specialized Prime Corporate Branch, Maker Chambers III, 7 th Floor,
Nariman Point, Mumbai-400021 and having its Head office at 112,J.C.Road,Bangalore – 560
002 with copy to us towards acceptance of reduction in BG value by Rs.2,65,50,001; as
detailed above.
Further, we confirm that this is our second request for Advance payment Bank Guarantee
value reduction against completed erection.
Uday Patil
Asst. General Manager, Contracts – T & D Business
Encl.: As above
Cc. 1. Mr. R N Singh, CEO, PGCIL Bangalore
2. Mr. Joseph Kurian, DGM (Engg.), PGCIL, Bangalore
Ref: GIL/SS/G-289/19856 Date: 21.10.2016
To
M/s. Powergrid NM Transmission Limited
(A fully owned subsidiary of Power Grid Corporation of India Limited)
Attur, TAMIL NADU
Kind Attn.: Mr R Gunasekaran(CM)
Sub.: 1.Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem Transmission
Line (Part-I) (with Hex Zebra Conductor) associated with Transmission System
pertaining to IPPs of Nagapattinam / Cuddalore Area: Package-A under Tariff Based
Competitive Bidding Route : Request for release of Advance bank Guarantee – Reg.
Dear Sir,
With reference to the subject contract and in continuation to our previous letter no. GIL/RS/G-
289/19145 dated 04.05.2016 & GIL/RS/G-289/19641 dated 26.08.2016 we invite your kind
attention to the following:
2. The details of advance payment Bank guarantee submitted towards advance payment are
as under:
Original BG Value Present BG Valid up to
Sl. No. Bank Guarantee No.
Rs. Value Rs.
102G0PG141920005
01 5,90,37,498/- 3,86,14,230/- 31.10.2016
dated 11.07.2014
Cont…
GAMMON INDIA LIMITED (T & D Business)
//2//
In view of the above and as per provision of contract for reduction of advance payment bank
guarantee (GCC clause No. 9.2.2), we request you to allow ABG reduction as here under-
Therefore, we request to issue your confirmation letter addressed to Bank Guarantee issuing
Bank i.e. CANARA BANK, Specialized Prime Corporate Branch, Maker Chambers III, 7th Floor,
Nariman Point, Mumbai-400021 and having its Head office at 112,J.C.Road,Bangalore – 560
002 with copy to us towards acceptance of reduction in BG value by Rs.2,38,54,855/-, as
detailed above.
Yours faithfully,
For GAMMON INDIA LIMITED
Uday Patil
Asst. General Manager, Contracts – T & D Business
Encl.: As above
Cc. 1. Mr. A K Das, CFO, PGCIL Bangalore
2. Mr. Joseph Kurian, DGM (Engg.), PGCIL, Bangalore
3. Mr. V. Khare, CEO, PGNMTL, Bangalore.
To
M/s. Powergrid NM Transmission Limited
(A fully owned subsidiary of Power Grid Corporation of India Limited)
Salem, TAMIL NADU
Kind Attn.: Mr J P Jayaprakash(CM)
Sub.: 1.Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem Transmission
Line (Part-II) (with Hex Zebra Conductor) associated with Transmission System
pertaining to IPPs of Nagapattinam / Cuddalore Area: Package-A under Tariff Based
Competitive Bidding Route : Request for release of Advance bank Guarantee – Reg.
Dear Sir,
With reference to the subject contract and in continuation to our previous letter no. GIL/RS/G-
290/19139 dated 03.05.2016 & GIL/RS/G-290/19642 dated 26.08.2016 we invite your kind
attention to the following:
Cont…
GAMMON INDIA LIMITED (T & D Business)
//2//
In view of the above and as per provision of contract for reduction of advance payment bank
guarantee (GCC clause No. 9.2.2), we request you to allow ABG reduction as here under-
Therefore, we request to issue your confirmation letter addressed to Bank Guarantee issuing
Bank i.e. CANARA BANK, Specialized Prime Corporate Branch, Maker Chambers III, 7 th Floor,
Nariman Point, Mumbai-400021 and having its Head office at 112,J.C.Road,Bangalore – 560
002 with copy to us towards acceptance of reduction in BG value by Rs. 2,65,50,001/-, as
detailed above.
Yours faithfully,
For GAMMON INDIA LIMITED
Uday Patil
Asst. General Manager, Contracts – T & D Business
Encl.: As above
Cc. 1. Mr. A K Das, CFO, PGCIL Bangalore
2. Mr. Joseph Kurian, DGM (Engg.), PGCIL, Bangalore
3. Mr. V. Khare, CEO, PGNMTL, Bangalore.
Ref: GIL/SS/G-289/19892 Date: 26.10.2016
To
M/s. Powergrid NM Transmission Limited
(A fully owned subsidiary of Power Grid Corporation of India Limited)
Attur, TAMIL NADU
Kind Attn.: Mr R Gunasekaran(CM)
Sub.: 1.Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem Transmission
Line (Part-I) (with Hex Zebra Conductor) associated with Transmission System
pertaining to IPPs of Nagapattinam / Cuddalore Area: Package-A under Tariff Based
Competitive Bidding Route : Request for release of Advance bank Guarantee – Reg.
Dear Sir,
With reference to the subject contract we are pleased to inform that, subject line has
successfully tested and commissioned on 21.10.2016. We congratulate PGNMTL & extend
sincere thanks for support give for completion of work.
Further as per clause no. 1 “Terms of Payment”, sub clause 1.1E “Payment on – Trial Operation”
of subject contract, 5% of the erection component (excluding price component for survey)
shall be paid after successful trial – operation.
In view of the above, we enclosed herewith invoice towards claim of 5% retention bill of
erection component. Details of invoice are given in below –
Uday Patil
Asst. General Manager, Contracts – T & D Business
Encl.: As above
Cc. 1. Mr. A K Das, CFO, PGCIL Bangalore
2. Mr. Joseph Kurian, DGM (Engg.), PGCIL, Bangalore
3. Mr. V. Khare, CEO, PGNMTL, Bangalore.
Ref: GIL/SS/G-290/19893 Date: 26.10.2016
To
M/s. Powergrid NM Transmission Limited
(A fully owned subsidiary of Power Grid Corporation of India Limited)
Salem, TAMIL NADU
Kind Attn.: Mr J P Jayaprakash(CM)
Sub.: 1.Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem Transmission
Line (Part-II) (with Hex Zebra Conductor) associated with Transmission System
pertaining to IPPs of Nagapattinam / Cuddalore Area: Package-A under Tariff Based
Competitive Bidding Route : Request for release of Advance bank Guarantee – Reg.
Dear Sir,
With reference to the subject contract we are pleased to inform that, subject line has
successfully tested and commissioned on 21.10.2016. We congratulate PGNMTL & extend
sincere thanks for support give for completion of work.
Further as per clause no. 1 “Terms of Payment”, sub clause 1.1E “Payment on – Trial Operation”
of subject contract, 5% of the erection component (excluding price component for survey)
shall be paid after successful trial – operation.
In view of the above, we enclosed herewith invoice towards claim of 5% retention bill of
erection component. Details of invoice are given in below –
We request you to arrange the above payment on priority basis, as we have to make
payment to our supplier/sub-contractor .
Thanking you and assuring of our best of service always.
Yours faithfully,
For GAMMON INDIA LIMITED
Uday Patil
Asst. General Manager, Contracts – T & D Business
Encl.: As above
Cc. 1. Mr. A K Das, CFO, PGCIL Bangalore
2. Mr. Joseph Kurian, DGM (Engg.), PGCIL, Bangalore
3. Mr. V. Khare, CEO, PGNMTL, Bangalore.
Ref: GIL/SS/G-289/19894 Date: 26.10.2016
To
M/s. Powergrid NM Transmission Limited
(A fully owned subsidiary of Power Grid Corporation of India Limited)
Attur, TAMIL NADU
Kind Attn.: Mr R Gunasekaran(CM)
Sub.: 1.Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem Transmission
Line (Part-I) (with Hex Zebra Conductor) associated with Transmission System
pertaining to IPPs of Nagapattinam / Cuddalore Area: Package-A under Tariff Based
Competitive Bidding Route : Request for release of Advance bank Guarantee – Reg.
Dear Sir,
With reference to the subject contract we are pleased to inform you that, both circuit of 765
KV D/C Nagapattinam – Salem (Part-I) T/L (102.457 KM) has been successfully commissioned
on 21.10.2016. Details of line commissioned are given in below –
We congratulate PGNMTL for successful completion of line & extend sincere thanks for
immense support extended by our team.
In view of the commissioning of line, we now request you to take over the line and please
arrange to issue the” Tacking Over Certificate” of subject line, so that we can proceed for
contract closure .
Yours faithfully,
For GAMMON INDIA LIMITED
Uday Patil
Asst. General Manager, Contracts – T & D Business
Encl.: As above
Cc. 1. Mr. Joseph Kurian, DGM (Engg.), PGCIL, Bangalore
3. Mr. V. Khare, CEO, PGNMTL, Bangalore.
To
M/s. Powergrid NM Transmission Limited
(A fully owned subsidiary of Power Grid Corporation of India Limited)
Salem, TAMIL NADU
Kind Attn.: Mr J P Jayaprakash(CM)
Sub.: 1.Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem Transmission
Line (Part-II) (with Hex Zebra Conductor) associated with Transmission System
pertaining to IPPs of Nagapattinam / Cuddalore Area: Package-A under Tariff Based
Competitive Bidding Route : Request for release of Advance bank Guarantee – Reg.
Dear Sir
With reference to the subject contract we are pleased to inform you that, both circuit of 765
KV D/C Nagapattinam – Salem (Part-II) T/L (100.331 KM) has been successfully commissioned
on 21.10.2016. Details of line commissioned are given in below –
We congratulate PGNMTL for successful completion of line & extend sincere thanks for
immense support extended by our team.
In view of the commissioning of line, we now request you to take over the line and please
arrange to issue the” Tacking Over Certificate” of subject line, so that we can proceed for
contract closure .
Yours faithfully,
For GAMMON INDIA LIMITED
Uday Patil
Asst. General Manager, Contracts – T & D Business
Encl.: As above
Cc. 1. Mr. Joseph Kurian, DGM (Engg.), PGCIL, Bangalore
3. Mr. V. Khare, CEO, PGNMTL, Bangalore.
To
M/s. Powergrid NM Transmission Limited
(A fully owned subsidiary of Power Grid Corporation of India Limited)
Attur, TAMIL NADU
Kind Attn.: Mr R Gunasekaran(CM)
Sub.: 1.Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem Transmission
Line (Part-I) (with Hex Zebra Conductor) associated with Transmission System
pertaining to IPPs of Nagapattinam / Cuddalore Area: Package-A under Tariff Based
Competitive Bidding Route : Request for release of Advance bank Guarantee – Reg.
Dear Sir,
With reference to the subject contract and in continuation to our previous letter no. GIL/RS/G-
289/19145 dated 04.05.2016 & GIL/RS/G-289/19641 dated 26.08.2016 we invite your kind
attention to the following:
1. The subject line was successfully tested and commissioned on 21.10.2016 and we
congratulate PGNMTL for successful completion of line & extend sincere thanks for immense
support extended by our team
2. The details of advance payment Bank guarantee submitted towards advance payment are
as under:
Original BG Value Present BG Valid up to
Sl. No. Bank Guarantee No.
Rs. Value Rs.
102G0PG141920005
01 5,90,37,498/- 3,86,14,230/- 31.10.2016
dated 11.07.2014
Cont....
In view of the above we Propose our ABG value from 3,86,14,230/- to 45,43,207/-, taking in
account Unadjusted advance value.
Therefore, we request to issue your confirmation letter addressed to Bank Guarantee issuing
Bank i.e. CANARA BANK, Specialized Prime Corporate Branch, Maker Chambers III, 7th Floor,
Nariman Point, Mumbai-400021 and having its Head office at 112,J.C.Road,Bangalore – 560
002 with copy to us towards acceptance of reduction in BG value by Rs.3,40,71,023/-, as
detailed above.
Yours faithfully,
For GAMMON INDIA LIMITED
Uday Patil
Asst. General Manager, Contracts – T & D Business
Encl.: As above
Cc. 1. Mr. A K Das, CFO, PGCIL Bangalore
2. Mr. Joseph Kurian, DGM (Engg.), PGCIL, Bangalore
3. Mr. V. Khare, CEO, PGNMTL, Bangalore.
Ref: GIL/SS/G-289&290/18375 Date: 07.11.2016
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,+
Bangalore 560064, Karnataka
Kind Attn.: Mr. Joseph Kurion – DGM
Sub.: 1. Tower Erection Package – ERE01 & 02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I &II) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff
Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01,TBCB/765KV/02(N-M)/ERE02
Dear Sir,
This is with reference to the subject project; please find enclosed herewith the extension copy
of Bank Guarantee towards Advance of Supply & erection of the above project for your
records. The Bank Guarantees details are here under.
Sr.
Date of Issuing Amount Present
No B. G. No. & Date Remarks
Amend Bank (Rs.) Validity
.
I02G0PG141920002 Supply
1 25.10.16 CANARA 15,73,914/- 30.04.17
Dt. 11.07.2014 Advance BG
I02G0PG141920003 Erection
2 25.10.16 CANARA 4,23,88,681/- 30.04.17
Dt. 11.07.2014 Advance BG
I02G0PG141920001 Supply
3 06.10.15 CANARA 16,78,246/- 30.04.17
Dt. 11.07.2014 Advance BG
I02G0PG141920005 Erection
4 06.10.15 CANARA 3,86,14,230/- 30.04.17
Dt. 11.07.2014 Advance BG
Uday Patil
(Asst. General Manager, Contracts – T & D Business)
Encl: As Above
Ref: GIL/SS/G-289/20050 Date: 30.11.2016
To
Sub.: Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem Transmission
Line (Part-I) (with Hex Zebra Conductor) associated with Transmission System
pertaining to IPPs of Nagapattinam / Cuddalore Area: Package-A under Tariff Based
Competitive Bidding Route : Request for Issuance of time limit extension-reg.
Dear Sir,
With reference to the subject project we invite your kind attention to the following:
1. Schedule completion period of the subject project was as per contractual terms &
condition on 19.05.2016.
2. Based on the various delays beyond control of M/s. GIL, PGNMTL vide their letter no. SR-
II/C&M/PGNMTL/02(N-M)/ERE01/PTE-01/1423, dt.06.09.16, issued provisional time
extension upto 31.12.2016.
3. Construction of the subject line has been completed on 06.10.2016 and line has been
successfully tested & commissioned on 21.10.2016 (Ckt-I at 8.43 PM & Ckt-II at
9.25PM). The line is under commercial utilization by PGNMTL since then.
The Delay in completion of line within schedule time is mainly on account of the following
reasons which were beyond control of GIL, as detailed under:
1. Delay in Supply of Stub:- As per Schedule stub supply should have commenced from
Jun’14, but the first lot receipt at site on the Month of Aug’14. However the stub supply
including Raised Chimney stub has been completed in Feb’16 instead of Jun’15 as per
schedule. Impact 3 Months delay in start of foundation as well as further delay of 8
months in completion of foundation.
2. Delay in Supply of Tower & its B&N:- As per Schedule tower supply should have
commenced from Sep’14, but the first lot receipt at site in Jan’15. As per schedule the
supply was to be completed by M/s. Skipper Ltd for Suspension tower and M/s. ICCOM
for Tension towers by Aug’15 however actual tower supply completed in April’16,
however the 75MT shortages was supplied on 22.07.2016 by M/s. ICOMM.
Impact 5 Months delay in start of Erection activity as well as further delay of 11 months
in completion of erection.
3. Delay in Supply of Line Material:- As per schedule we had to start stringing on the
month of Jan’15, for that the line materials should be available at site before Dec’14,
however the first lot of Conductor & Hardware receipt at site on May’15. As per
schedule all line materials supply should have been completed by Nov’15, but actual
supply completed Hardware By Mar’16, Insulator by Aug’16 & Conductor by June’16.
Impact 6 Months delay in start of Stringing activity as well as further delay of 7 months in
completion of stringing.
II. CONSTRUCTION:
1. Survey:
a. Delay in Approval of Survey & Quantity Finalization:- As per schedule the survey & tower
quantity should be finalized by Feb’15. But at actual we have received final approval of
survey on the Month of Sep’15. However due to non-finalization of bay position at
Nagapattinam S/S end Gantry to AP 3/0 has been hold by PGNMTL for construction
activity and same was cleared for construction by Mar’2016.
Impact: Delay in finalization of route thereby delay in taking up Foundation, erection &
stringing.
b. Delay in Clearance of statutory approval :- The subject line consists of 14 power line
crossings and 2 railway crossings. All of these crossings have been cleared in Aug’15 &
Oct’15. Details enclosed in annexure-I (copy enclosed).
Impact: Delay in taking up construction activity on 34 locations which are mainly tension
towers with higher extension.
2. Foundation:
a. As per schedule we need to be start foundation activity on the Month of July’14
and for that the first lot of stub should be reached at site by June’14, however
same has been receipt on Aug’14 and first lot of angle tower stub has been
received in the month of Nov’14.
b. Please refer annexure-II, regarding month wise section clearance received from
PGNMTL for foundation activity and annexure –III regarding month wise
foundation completion by GIL. Wherein you will observe that upto Jun’15 the
foundation activity is in line with the clearances received from M/s. PGNMTL.
However, subsequently from July’ 15 onwards, backlog has occurred due to ROW
encountered at Cashew nuts garden from section 3/0 to 8/0 wherein 48 locations
were affected and secondly due to delay in approval of statutory clearances
affected 34 nos locations. Further, due to non-finalization of bay position i.e. from
1/0 to 3/0, 7 nos locations were held up.
c. As per GCC clause Section-II, clause 1.1.2.1 employer i.e. PGNMTL is to be
provide structural drawings / BOM / foundation drawings to contractor. In this
regards please note that change of foundation design from 3.0M depth to 3.5M
depth were introduced by PGNMTL in month of May’2015 and design & drawing
were issued in Aug’2015 which has delayed the foundation/ erection / stringing
of said locations (28 Nos Angle type towers)
Although above hurdle, till 30th April’16 we had completed 267 foundation and only
4 locations (AP15/1, AP2, AP1 & 1/1) were pending in addition to the ROW faced till
completion of 267Foundation. Out of balance 4 location Loc No.15/1 completed on
12th May’16. Locations 2/0 & 1/0 were completed on 31st May’16 and 18th June’16
respectively immediately after clearance of ROW. But the location no. 1/1 was
cleared by PGNMTL by 02.09.2016 and foundation of the same has been completed
on very next day i.e. 03.09.2016.
2. Erection:
a. Erection activity scheduled to start from Oct’14 and for that first lot of tower
required to be reach at our site store by Sep’14, however we have received first
lot on the Month on Jan’15. Impact 4 months delay in start of Erection activity.
b. Also we have received first lot of angle towers in April’15 only and on account of
same gap location erection happened till that time & delay in erection of angle
towers. Due to delay in supply of angle towers, as well as non-availability of
desired extensions gap locations are increased which were repeatedly informed
you through our various communications (vide letter no. GIL/AL/G-289/17355
dated 06.02.15, GIL/PGCIL-NM/G-289&290/2014-15/48 dated 19.05.15,GIL/PGCIL-
NM/G-289&290/2014-15/60 dated 02.06.15, GIL/SS/G-289&290/17883 dated
04.07.15, GIL/SS/G-289&290/18169 dated 26.08.15 copy enclosed). This has also
resulted in frequent shifting our gangs which incurred additional cost as well as
affected the progress of erection activity.
Although above hurdle, as on April’16, total 23Locations were balance for erection. As
the locations were under ROW, the work could not be taken up simultaneously in all
locations and we have advised by PGNMTL deploy only 10 erection gangs during
May’16 in view of less work front availability and again we had to demobilize few
gang due to unavailability of work front. The tower erection at Loc. No. 7/0 was
stopped due to ROW from 18.05.2016 to 16.07.2016. Also due to wrong fabrications
tower erection at 2A/0 was stopped from 08.06.16 t0 25.06.16 and also tower erection
was severely affected due to shortages in tower supply approx.75 MT which was
supplied on 22. 07.2016 by M/s. ICCOM.
3. Stringing:
a. Stringing activity were schedule to start from Jan’15, but due to delay in supply of
angle towers stretches could not be ready to commence the stringing till April 15.
Also the first lot of Line material has been receipt at site on the month of May’15
which was scheduled in Dec’14.
b. After receipt of material and angle towers we have started our stringing activity
from section 38/0 to 39/0 – 1.568 Km on June’15. After completion of this section
we were only able to do paying out from 39/0 to 41/0 – 6.732 Km & the final sag
was pending due to non-availability of angle towers with desired extensions and
further no sections was clear for stringing till Aug’15 which we repeatedly
informed you through our communication (vide letter no. GIL/AL/G-289/17355
dated 06.02.15, GIL/PGCIL-NM/G-289&290/2014-15/48 dated 19.05.15,GIL/PGCIL-
NM/G-289&290/2014-15/60 dated 02.06.15, GIL/SS/G-289&290/17883 dated
04.07.15, GIL/SS/G-289&290/18169 dated 26.08.15 copy enclosed).
d. We herein also like to inform you that as advised by PGNMTL, we have deploy 4
nos. TSE along with gang & 4 Nos. manual gangs for expedite the stringing, but
due to severe ROW, tree cutting & delay in supply of angle towers with desired
extension, affected progress severely & also loss of resources.
Above delays have affected schedule completion which informed to you vide our various
communication & also during the review meetings we have communicated all the hurdle as
well as also deployed huge manpower for early completion. The copy of our regular
correspondence & MOM regarding the same is enclosed herewith for your ready reference.
With lots of joint efforts and with your support, we have completed line on 06.10.2016 and
same has been commissioned on 21.10.2016. However after commissioning carried out some
minor work such as ACD fixing, muffing, coping etc. are required to complete as per scope &
as advise by PGNMTL.
In view of above, we appeal you for issuance of “ Time limit extension for testing &
commissioning of line till 21.10.2016 and for minor work completion till 31.12.2016,
without imposition of Liquidated Damages & with athe application of price variation for
extended period.
Kindly arrange to do the above needful on priority, please.
Thanking you & assuring you our best services at all times.
Yours faithfully
For GAMMON INDIA LIMITED
(Uday Patil)
Asst. General Manager (Contracts – T & D Business)
Encl.: As above
Cc.: 1. Mr. Joseph Kurian – Dy. General Manager, PGNMTL, Bangalore.
2. Mr. V. Khare, CEO, PGNMTL, Bangalore.
3. Mr. D. Ganeshan, DGM (C&M), PGNMTL, Bangalore.
Ref: GIL/SS/G-289/20059 Date: 03.12.2016
To
The Chief Manager (Construction)
M/s. Powergrid N M Transmission Limited.
C/o. Powergrid Corporation of India Limited.
Attur, Tamil Nadu.
Kind Attn.: Mr. R Gunasekaran, CM (Construction)
Sub.: Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem Transmission Line
(Part-I) (with Hex Zebra Conductor) associated with Transmission System pertaining to
IPPs of Nagapattinam / Cuddalore Area: Package-A under Tariff Based Competitive
Bidding Route : Request for process of Final Amendment-reg.
Ref.: 1. NOA No. PGNMTL/765 kV/02(N-M)/ERE01/NOA-I/10 & NOA-II/11, dt.16.05.2014.
2. Amnd-1 Issued vide letter No. SR-II/C&M/PGNMTL/02(N-M)/ERE01/1531 dated 23.09.15
3. Amnd-2 Issued vide letter No. SR-II/C&M/PGNMTL/02(N-M)/ERE01/201 dated 27.04.16
Dear Sir,
With reference to the subject contract, based on the actual consumed quantity as per Joint
measurement certificate, please find enclosed here with final quantity amendment proposal
for supply and service contract. Summary of same is as under –
Variance
Proposed
Descripti Amndment-2 Variance Variance with Varianc
LOA Value Final Amnd.
on Value with LOA In (%) Amnd-2 e
Value
In (%)
Supply 10,492,760 10,431,066 10,451,651 (38,109) -0.36% 23,585 0.23%
Details calculations are available in activity wise annexure. The calculation has been made
based on actual consumption.
Therefore we request you to arrange the approval of final amendment on priority basis so that
we can raise our final bill.
Thanking you
Yours faithfully
For GAMMON INDIA LIMITED
Uday Patil
(Asst. General Manager, Contracts – T & D Business)
Encl.: as above
Cc.: 1. Mr. Joseph Kurian – Dy. General Manager, PGNMTL, Bangalore.
2. Mr. V. Khare, CEO, PGNMTL, Bangalore.
Sub.: Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem Transmission
Line (Part-I) (with Hex Zebra Conductor) associated with Transmission System
pertaining to IPPs of Nagapattinam / Cuddalore Area: Package-A under Tariff Based
Competitive Bidding Route : Request for Issuance of time limit extension-reg.
Dear Sir,
With reference to the subject project we invite your kind attention to the following:
The Delay in completion of line within schedule time is mainly on account of the following
reasons which were beyond control of GIL, as detailed under:
1. Delay in Supply of Stub:- As per Schedule stub supply should have commenced from
Jun’14, but the first lot receipt at site on the Month of Aug’14. Also we received the first
lot of DD WZ-II stub in the month of Feb’2015 and all stub supply including Raised
Chimney stubs has been completed in Jan’16 instead of Jun’15 as per schedule.
Impact 3 Months delay in start of foundation as well as further delay of 8 months in
completion of foundation.
2. Delay in Supply of Tower & its B&N:- As per Schedule tower supply should have
commenced from Sep’14, but the first lot receipt at site in Jan’15. As per schedule the
supply was to be completed by M/s. Skipper Ltd for Suspension tower and M/s. ICCOM
for Tension towers by Aug’15. However 1st lot of DD WZ-II tower was supplied in the
month of Sep’2015 i.e only 1 set and 2nd lot of DD tower was supplied in the month of
Nov’15 and In total actual tower supply completed in July’16, however the 75MT
shortages was supplied on 22.07.2016 by M/s. ICOMM.
Impact 5 Months delay in start of Erection activity as well as further delay of 11 months
in completion of erection.
3. Delay in Supply of Line Material:- As per schedule we had to start stringing in the month
of Jan’15, for that the line materials should be available at site before Dec’14, however
the first lot of Conductor & Hardware receipt at site on May’15. As per schedule all line
materials supply should have been completed by Nov’15, but actual supply completed
Hardware By Mar’16, Insulator by Aug’16 & Conductor by June’16. Impact 6 Months
delay in start of Stringing activity as well as further delay of 7 months in completion of
stringing.
4. Discrete supply of Tower: The supply of towers & required extensions were made not in
line with the site requirement therefore many times for want of extension, inspite of
availability of basic tower erection could not be done. Also there is inordinate delay in
supply of angle type towers which resulted in gap locations during project period. Due
to non-availability of tower no tower was erected in the month of May’2015 &
June’2015. Impact: Due to same three months extra time required for work
completion as well as affected completion of tower erection as per planned
stringing section.
II. CONSTRUCTION:
1. Survey:
a. Delay in Approval of Survey & Quantity Finalization:- As per schedule the survey & tower
quantity should be finalized by Feb’15. But at actual we have received final approval of
survey on the Month of Sep’15. However due to technical clearance at Loc No. 68/2,
route has been changed between section 68/0 to 69/0. And same has been approved
on the month of Jul’16.
Impact: Delay in finalization of route thereby delay in taking up Foundation, erection &
stringing.
b. Delay in Clearance of statutory approval :- The subject line consists of 8 power line
crossings and 2 railway crossings. All of these crossings have been cleared in Aug’15 &
Oct’15. Details enclosed in annexure-I (copy enclosed).
Impact: Delay in taking up construction activity on 20 locations which are mainly tension
towers with higher extension.
c. Delay in Clearance of Forest :- The subject line consists forest area at section between
70/1 to 72/0 about 2.583 KM & 5 location and 99/1 to 100/0 about 1.385 km & 2 location.
As per schedule forest clearance should be receipt by Jun’2015. However same has
been received on Feb’2016 except location No. 58/4 which was cleared on 15.07.2016.
Impact: Delay in taking up construction activity on 7 locations which are mainly tension
towers with higher extension
2. Foundation:
a. As per schedule we need to be start foundation activity on the Month of July’14
and for that the first lot of stub should be reached at site by June’14, however
same has been receipt on Aug’14 and first lot of angle tower stub has been
received in the month of Dec’14.
b. Please refer annexure-II, regarding month wise section clearance received from
PGNMTL for foundation activity, wherein you will observe that we have received
all locations was progressively cleared by Sep’2015 instead of Feb’2015 as per
schedule. On that period we have already completed 203 nos locations upto
and 11 locations are in under progress and balance 58 location are hold for
various reason which details are given in annexure –III.
c. As per GCC clause Section-II, clause 1.1.2.1 employer i.e. PGNMTL is to be
provide structural drawings / BOM / foundation drawings to contractor. But due
to non-availability of special structure foundation drawings of raised chimney as
well as stub extender drawings. The same has already been informed to you
vide our letter No. GIL/SS/G-289/18250 dated 18.09.15 and vide email dated on
26.08.15 & 09.10.15 (copy enclosed).
Rather than above we also used Ropeway to transfer the material at loc No.
71/1 & 71/2.
e. We have faced Severe ROW at section 48B to 49A near village Pithyakaplayam
and between location no. 54 to 55 at village Belur. ROW of AP54 to AP55 was
cleared during 4th week of July’16. At AP 68 to AP69 route has been diverted on
28.03.16 due to ROW and diverted route has been finalized/ freezed only during
4th week of June’16. Similarly ROW in the section AP61 to AP64 was cleared
during 1st week of July’16. Impact: Delay in taking up Foundation, Erection (at
18Locations) & Stringing (around 6.00 KM), frequent idling of gangs, incurring
additional cost to company.
3. Erection:
a. Erection activity scheduled to start from Oct’14 and for that first lot of tower
required to be reach at our site store by Sep’14, however we have received first
lot on the Month on Jan’15. Impact 4 months delay in start of Erection activity.
b. Also we have received first lot of angle towers in Jun’15, i.e only DB & DC tower.
The first lot of DD tower was supplied on Sep’15 and on account of same gap
location erection happened till that time & delay in erection of angle towers. Due
to delay in supply of angle towers, as well as non-availability of desired extensions
gap locations are increased which were repeatedly informed you through our
various communications (vide letter no. GIL/AL/G-289/17355 dated 06.02.15,
GIL/PGCIL-NM/G-289&290/2014-15/48 dated 19.05.15,GIL/PGCIL-NM/G-
289&290/2014-15/60 dated 02.06.15, GIL/SS/G-289&290/17883 dated 04.07.15,
GIL/SS/G-289&290/18169 dated 26.08.15 copy enclosed). This has also resulted in
frequent shifting our gangs which incurred additional cost as well as affected the
progress of erection activity.
c. After receipt of first lot of DA tower -48 set on the Month of Jan’15, we are
immediately deployed our erection gang but after 3 month completion of 47 nos
tower erection we were forced to demobilize our erection gang for three months
due to non-supply of further tower.
c. We also want to inform you that upto Feb’2016 we have completed 226 nos
foundations and 181 nos erection but we are only able to complete stringing of
17 km due to non-availability of stringing stretches for non-clearance of
foundation at hold locations & non-availability of desired angle towers &
extension.
d. We herein also like to inform you that as advised by PGNMTL, we have deploy 3
nos. TSE along with gang & 5 Nos. manual gangs for expedite the stringing, but
due to severe ROW, tree cutting & delay in supply of angle towers with desired
extension, affected progress severely & also loss of resources.
e. We also want to inform you that, after deployment of huge resources we are
faced problem of gang idling due to ROW & shutdown problem. Details are as
under –
i) Due to ROW at section 48A to 48B our stringing gang was sitting idle which
informed you vide email dated 12.04.2016.
ii) We were also demobilized our stringing from section 93A/0 to 93A/2 to 94/0
to 95/0 on instruction of PGCIL representative for non-payment of
compensation at loc no. 93A/1 which informed you vide email dated
06.04.2016.
iii) We also faced problem of gang idling due to non availability of shutdown
timely at section 91/0 to 92/0 which informed you vide email dated
23.04.2016.
Above delays have affected schedule completion which informed to you vide our
various communication & also during the review meetings we have communicated all
the hurdle as well as also deployed huge manpower for early completion. The copy of
our regular correspondence & MOM regarding the same is enclosed herewith for your
ready reference.
With lots of joint efforts and with your support, we have completed line on 20.10.2016
and same has been commissioned on 21.10.2016. However after commissioning
carried out, revetment work at 11 nos location were balance to take up in which we
have received approval of 4 locations on 23.09.2016 and balance 7 location approval
are yet to pending from PGCIL which expect to receive by Feb’17 end. We have
already deployed our gangs for revetment work and one location revetment was
completed & 2 are in under progress.
In view of above, we appeal you for issuance of “ Time limit extension for testing &
commissioning of line till 21.10.2016 and for balance revetment & other minor work
completion which does not affect the satisfactory operation of commissioned line, till
31.05.2017, without imposition of Liquidated Damages & with the application of price
variation for extended period.
Kindly arrange to do the above needful on priority, please.
Thanking you & assuring you our best services at all times.
Yours faithfully
For GAMMON INDIA LIMITED
Uday Patil
(Asst. General Manager, Contracts – T & D Business)
Encl.: as above
Cc.: 1. Mr. Ravindra Kumar – General Manager, PGNMTL, Bangalore.
2. Mr. Joseph Kurian – Dy. General Manager, PGNMTL, Bangalore.
Ref: GIL/SS/G-290/20579 Date: 23.02.2017
To
The Asst. General Manager (Construction)
M/s. Powergrid N M Transmission Limited.
C/o. Powergrid Corporation of India Limited.
Attur, Tamil Nadu.
Kind Attn.: Mr. J P Jayapraksh AGM (Construction)
Sub.: Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem Transmission Line
(Part-II) (with Hex Zebra Conductor) associated with Transmission System pertaining to
IPPs of Nagapattinam / Cuddalore Area: Package-A under Tariff Based Competitive
Bidding Route : Request for process of Final Amendment-reg.
Ref.: 1. NOA No. PGNMTL/765 kV/02(N-M)/ERE02/NOA-I/12 & NOA-II/13, dt.16.05.2014.
2. Amnd-1 Issued vide letter No. SR-II/C&M/PGNMTL/02(N-M)/ERE02/1529 dated 23.09.15
3. Amnd-2 Issued vide letter No. SR-II/C&M/PGNMTL/02(N-M)/ERE02/200 dated 27.04.16
Dear Sir,
With reference to the subject contract, based on the actual consumed quantity as per Joint
measurement certificate and as per approved revetment quantity of 4 locations vide letter
no. PNMTL/SLM/GIL/F-217 dated. 23.09.2016 & 7 locations which proposal has been submitted
at Bangalore office, please find enclosed here with final quantity amendment proposal for
supply and service contract. Summary of same is as under –
Proposed Variance
Descripti Amndment-2 Variance Variance with Variance
LOA Value Final Amnd.
on Value with LOA In (%) Amnd-2 In (%)
Value
Supply 11,188,307 10,641,374 10,523,434 (664,873) -5.94% (117,940) -1.11%
Details calculations are available in activity wise annexure. The calculation has been made
based on actual consumption.
Therefore we request you to arrange the approval of final amendment on priority basis so that
we can raise our final bill.
Thanking you
Yours faithfully
For GAMMON INDIA LIMITED
Uday Patil
(Asst. General Manager, Contracts – T & D Business)
Encl.: as above
Cc.: 1. Mr. Rabindra Kumar –General Manager, PGNMTL, Bangalore.
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,+
Bangalore 560064, Karnataka
Kind Attn.: Mr. A K Das – CM (Finanace)
Sub.: 1. Tower Erection Package – ERE01 & 02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I &II) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff
Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01,TBCB/765KV/02(N-M)/ERE02
Dear Sir,
This is with reference to the subject project and your ABG reduction letter issued on dated.
23.01.2017, please find enclosed herewith the Advance Bank Guarantee of revised values for
erection portion of the above project for your records. The Bank Guarantees details are here
under.
Sr.
Date of Issuing Amount Present
No B. G. No. & Date Remarks
Amend Bank (Rs.) Validity
.
I02G0PG141920003 Erection
1 06.02.17 CANARA 2,02,43,400/- 30.04.17
Dt. 11.07.2014 Advance BG
I02G0PG141920005 Erection
2 06.02.17 CANARA 1,87,55,662/- 30.04.17
Dt. 11.07.2014 Advance BG
Uday Patil
(Asst. General Manager, Contracts – T & D Business)
Encl.: as above
Cc.: 1. Mr. Joseph Kurian – Dy. General Manager, PGNMTL, Bangalore.
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,+
Bangalore 560064, Karnataka
Kind Attn.: Mr Rabindra Kumar(GM)
Sub.: 1.Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem Transmission
Line (Part-I) (with Hex Zebra Conductor) associated with Transmission System
pertaining to IPPs of Nagapattinam / Cuddalore Area: Package-A under Tariff Based
Competitive Bidding Route : Reg.- Request for Issuance of TOC
Dear Sir,
IWith reference to the subject contract and continuation to our previous letter No. GIL/SS/G-
289/19894 dated 26.10.2016, we are pleased to inform you that, both circuit of 765 KV D/C
Nagapattinam – Salem (Part-I) T/L (102.457 KM) has been successfully commissioned on
21.10.2016. Details of line commissioned are given in below –
In view of the commissioning of line, we now request you to take over the line and please
arrange to issue the” Tacking Over Certificate” of subject line, so that we can proceed for
contract closure .
Yours faithfully,
For GAMMON INDIA LIMITED
Uday Patil
Asst. General Manager, Contracts – T & D Business
Encl.: As above
Cc. 1. Mr. Joseph Kurian, DGM (Engg.), PGCIL, Bangalore
2. Mr. R. Gunasekaran, CM, PGNMTL, Attur.
Ref: GIL/SS/G-290/20693 Date: 15.03.2017
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,+
Bangalore 560064, Karnataka
Kind Attn.: Mr Rabindra Kumar(GM)
Sub.: 1.Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem Transmission
Line (Part-II) (with Hex Zebra Conductor) associated with Transmission System
pertaining to IPPs of Nagapattinam / Cuddalore Area: Package-A under Tariff Based
Competitive Bidding Route : Reg.- Request for Issuance of TOC
Dear Sir
With reference to the subject contract and in continuation to our previous letter No. GIL/SS/G-
290/19895 dated 26.10.2016, we are pleased to inform you that, both circuit of 765 KV D/C
Nagapattinam – Salem (Part-II) T/L (100.331 KM) has been successfully commissioned on
21.10.2016. Details of line commissioned are given in below –
In view of the commissioning of line, we now request you to take over the line and please
arrange to issue the” Tacking Over Certificate” of subject line, so that we can proceed for
contract closure .
Yours faithfully,
For GAMMON INDIA LIMITED
Uday Patil
Asst. General Manager, Contracts – T & D Business
Encl.: As above
Cc. 1. Mr. Joseph Kurian, DGM (Engg.), PGCIL, Bangalore
2. Mr. J P Jayaprakash, AGM, PGNMTL, Salem.
Dear Sir,
With reference to the subject contract, here we submit the Foundation drawings & accessories
drawing towards final submission for closure of contract. The details of submission are listed
below –
Request you kindly verify the details from your end against final submission.
Thanking you
Yours faithfully,
For GAMMON INDIA LIMITED
Uday Patil
Asst. General Manager, Contracts – T & D Business
Encl.: As above
Cc. 1. Mr. Joseph Kurian, DGM (Engg.), PGCIL, Bangalore
Dear Sir
With reference to the subject project and as per final OSM material reconciliation, we need to
be replenish 90.655 Km ACSR Zebra conductor. Accordingly we have finalized PO with M/s. JSK
Industries Pvt. Ltd which is approved vendor of PGCIL.
In view of the above here we submitting 3 sets of following documents for your reference with
endorsement of subject contract. Details of drum drawings, GTP & type test report are here
under-
Sr.
Details Drawing No.
No.
Drum Drawing for ACSR Zebra
1 JSK/ACSRZ/GIL/PGNMTL/16-17/1603 Rev-0
Conductor
2 Type Test Report of CPRI 43/t/2016-HV14 475lJSrJ'|474 Dated 18.08.16
Guaranteed Technical Particulars of
3 -
ACSR Zebra Conductor
As per requirement by PGNMTL to replenish the same at Mecheri, Tutikorin-Dharmapuri line ,
we are plan to dispatch the material by Mar’17. Therefore we request you Kindly arrange to
regularize by approving the aforementioned drawings & GTP in Category – I and provide one
set duly signed and stamped for our reference and our record.
Thanking you
Yours faithfully,
For GAMMON INDIA LIMITED
Uday Patil
(Asst. General Manager, Contracts – T & D Business)
Encl.: As above
Ref: TLL/SS/G-289 &290/21066 Date: 10.05.2017
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,+
Bangalore 560064, Karnataka
Kind Attn.: Mr. Joseph Kurian, DGM (Engg.)
Sub.: 1.Tower Erection Package – ERE01 & ERE02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-II) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package-A under Tariff
Based Competitive Bidding Route : Reg.- Request for Issuance of TOC
Dear Sir
With reference to the subject contract and as per approved letter no.
CC.ENGG:TL:TBCB: PGNMTL:Gammon:ERE01 & ERE02 dated 04.04.2017 received from
PGCIL Gurgaon (copy attached), regarding commercial clearance for supply of
90.665 KM conductor, we would like to inform you that the said material are ready for
inspection.
As you are aware that the above materials are not in GIL BOQ item, hence we are not
able to raise inspection call in PGCIL IMS system. Therefore we request you to please
arrange the inspection of said material w.r.t. details mentioned in below or
alternatively waiver of Inspection for the above materials. The details of inspection are
given in below –
Description Insulator
Manufacture Name: JSK Industries Pvt. Ltd.
JSK Industries Pvt. Ltd.
126/1-B, Gov. School Road, Rakholi,
Address:
Silvasa – 396 230
U.T. of Dadar & Nagar Haveli
Request you kindly arrange to depute your concern person from silvasa, so that
inspection can carry out and we are able to dispatch the same at the earliest.
Thanking you and assuring of our best of service always.
Yours faithfully,
For TRANSRAIL LIGHTING LIMITED
Uday Patil
Asst. General Manager, Contracts – T & D Business
Encl.: As above
Cc. 1. Mr. Rabindar Kumar, GM, PGCIL, Bangalore
To
M/s. Powergrid NM Transmission Limited
(A fully owned subsidiary of Power Grid Corporation of India Limited)
Attur, TAMIL NADU
Kind Attn.: Mr J P Jayaprakash(CM)
Sub.: 1.Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem Transmission
Line (Part-I) (with Hex Zebra Conductor) associated with Transmission System
pertaining to IPPs of Nagapattinam / Cuddalore Area: Package-A under Tariff Based
Competitive Bidding Route : Request for release of Advance bank Guarantee – Reg.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01,
Dear Sir,
With reference to the subject contract and considering the present status of project we invite
your kind attention to the following:
b) Final amendment & final time extension has been submitted and under process.
2. The details of advance payment Bank guarantee submitted towards advance payment are
as under:
Present BG Valid up to
Sl. No. Bank Guarantee No.
Value Rs.
ID0GOPG162990004
01 1,87,55,662/- 31.10.2017
Dated 25.10.2016
3. The details of adjusted advance payment: Till date all advance has been adjusted and
PGCIL has been deducted additional advance of Rs.73,915/- from our RA Bill , which we
claimed through Bill No. G-289/ERE01/N-S/ERE/ADV/04 dated 09.02.2017.
In view of the above and considering the present status of project, we request you to please
release the above bank guarantee.
Therefore, we request to issue your confirmation letter addressed to Bank Guarantee issuing
Bank i.e. CANARA BANK, Specialized Prime Corporate Branch, Maker Chambers III, 7th Floor,
Nariman Point, Mumbai-400021 and having its Head office at 112,J.C.Road,Bangalore – 560
002 with copy to us towards acceptance of release of BG.
Yours faithfully,
For TRANSRAIL LIGHTING LIMITED
Uday Patil
Asst. General Manager, Contracts – T & D Business
Encl.: As above
Cc. 1. Mr. A K Das, CFO, PGCIL Bangalore
2. Mr. Joseph Kurian, DGM (Engg.), PGCIL, Bangalore
3. Mr. Rabindra Kumar, GM, PGNMTL, Bangalore.
NOTE.: CONTRACT AMENDMENT REQUSET TOWARDS TRANSFER OF BUSINESS FROM
“GAMMON” TO “TRANSRAIL”SUBMITTED TO OGNMTL VIDE LETTER NO. GIL/G-
289&290/SS/20928 dated 26.04.2017
To
M/s. Powergrid NM Transmission Limited
(A fully owned subsidiary of Power Grid Corporation of India Limited)
Attur, TAMIL NADU
Kind Attn.: Mr J P Jayaprakash(CM)
Sub.: 1.Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem Transmission
Line (Part-II) (with Hex Zebra Conductor) associated with Transmission System
pertaining to IPPs of Nagapattinam / Cuddalore Area: Package-A under Tariff Based
Competitive Bidding Route : Request for release of Advance bank Guarantee – Reg.
Dear Sir,
With reference to the subject contract and considering the present status of project we invite
your kind attention to the following:
b) Final amendment & final time extension has been submitted and under process.
2. The details of advance payment Bank guarantee submitted towards advance payment are
as under:
Present BG Valid up to
Sl. No. Bank Guarantee No.
Value Rs.
ID0GOPG162990003
01 2,02,43,400/- 31.10.2017
Dated 25.10.2016
3. The details of adjusted advance payment: Till date all advance has been adjusted and
PGCIL has been deducted additional advance of Rs.1,05,665/- from our RA Bill, which we
claimed through Bill No. G-290/ERE02/N-S/ERE/ADV/04 dated 09.02.2017.
In view of the above and considering the present status of project, we request you to please
release the above bank guarantee.
Therefore, we request to issue your confirmation letter addressed to Bank Guarantee issuing
Bank i.e. CANARA BANK, Specialized Prime Corporate Branch, Maker Chambers III, 7 th Floor,
Nariman Point, Mumbai-400021 and having its Head office at 112,J.C.Road,Bangalore – 560
002 with copy to us towards acceptance of release of BG.
Yours faithfully,
For TRANSRAIL LIGHTING LIMITED
Uday Patil
Asst. General Manager, Contracts – T & D Business
Encl.: As above
Cc. 1. Mr. A K Das, CFO, PGCIL Bangalore
2. Mr. Joseph Kurian, DGM (Engg.), PGCIL, Bangalore
3. Mr. Rabindra Kumar, GM, PGNMTL, Bangalore.
Dear Sir,
This is with reference to the subject project, please find enclosed herewith the extension copy
Advance Bank Guarantee of Supply & erection portion of the above project for your records.
The Bank Guarantees details are here under.
Sr.
Date of Issuing Amount Present
No B. G. No. & Date Remarks
Amend Bank (Rs.) Validity
.
ID0GOPGI62990001 Supply
1 06.02.17 CANARA 16,78,246/- 31.10.17
Dt. 25.10.2016 Advance BG
ID0GOPGI62990002 Supply
2 06.02.17 CANARA 15,73,914/- 31.10.17
Dt. 25.10.2016 Advance BG
ID0GOPGI62990003 Erection
3 06.02.17 CANARA 2,02,43,400/- 31.10.17
Dt. 25.10.2016 Advance BG
ID0GOPGI62990004 Erection
4 06.02.17 CANARA 1,87,55,662/- 31.10.17
Dt. 25.10.2016 Advance BG
Uday Patil
(Asst. General Manager, Contracts – T & D Business)
Encl.: as above
Cc.: 1. Mr. Joseph Kurian – Dy. General Manager, PGNMTL, Bangalore.
Ref: TLL/SS/G-289&290/21221 Date: 01.06.2017
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,+
Bangalore 560064, Karnataka
Kind Attn.: Mr. Rabindra Kumar – GM
Sub.: 1. Tower Erection Package – ERE01 & 02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I &II) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff
Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01,TBCB/765KV/02(N-M)/ERE02
Dear Sir,
With reference to our letter No. GIL/G-289&290/21016 dated 03.05.2017, regarding core
extraction & testing of 16 locations, we have engaged M/s. Civil Aid, Chennai for extraction &
testing of core. M/s. Civil Aid, Chennai is an NABL accredited Laboratory who has facility of
core extraction & testing. Accordingly to perform this job we have done agreement with said
M/s. Civil aid and 12 tower core cutting has been done as advise by PGCIL.
However we are in receipt of your letter no. PNMTL/SLM/Vig/Core dated 29.05.2017, wherein
PGCIL advise to do core testing from National Testing House, Chennai.
In this regards we like to inform you that National Testing House is not having facility of
extraction of core and we have already done agreement with M/s. Civil Aid, Chennai for core
extraction as well as testing.
In view of the above we are arranged testing of the core from civil aid who is an NABL
accredited Laboratory.
K. P. Singh
Vice President (Construction)
Encl.: as above
Cc.: 1. Mr. J P Jayaprakash – Dy. General Manager, PGNMTL, Bangalore.
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,+
Bangalore 560064, Karnataka
Kind Attn.: Mr. Joseph Kurain – DGM
Sub.: 1. Tower Erection Package – ERE01 & 02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I &II) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff
Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01,TBCB/765KV/02(N-M)/ERE02
Dear Sir,
With reference to our letter No. GIL/G-289&290/SS/20928 dated 26.04.2017 we like to inform
you the following regarding transfer of Business from Gammon India Ltd to Transrail Lighting
Ltd.
A) Scheme of Arrangement :
i. Presently under above said contract we (Gammon) are executing Supply & Erection
part for both Package i.e Part-I & Part-II (Details are enclosed in annexure-I).
Considering the transfer of business the same are to be now amended in Transrail name
pursuant to guidelines of National Company Law Tribunal (NCLT). The supply part was
already transferred from Gammon to Transrail from 1st Jan 2016 pursuant to Business
Transfer agreement (BTA).
ii. The details of balance quantities to execute and to be transfer on Transrail name
already worked out with your team and freezed on 13th May 2017.
C) Transfer of Bank Guarantee:
In view of the above we request you for immediate issuance of amendment to the ongoing
contract for transfer of business from Gammon to Transrail to enable us submission of BG
amendment and to execute balance work as well as claim our receivable.
Yours Faithfully,
For Transrail Lighting Ltd.
Uday Patil
Asst. General Manager (Contracts.)
Encl : As above.
Ref : TLL/SS/G-289/21239 Date : 03.06.2017
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,+
Bangalore 560064, Karnataka
Kind Attn.: Mr. Rabindra Kumar – GM
Sub.: 1. Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem Transmission
Line (Part-I) (with Hex Zebra Conductor) associated with Transmission System pertaining
to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff Based
Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01,TBCB/765KV/02(N-M)/ERE02
Ref.: i. NOA No. PGNMTL/765 kV/02(N-M)/ERE01/NOA-I/10 & NOA-II/11 dated 16.05.2014.
Dear Sir
With reference to the subject contract, we like to invite your kind attention on following –
1) The subject line has been commissioned on 21.10.2016 and under commercial
utilization by PGNMTL since then.
2) However we still await the following-
a) Final Quantity Amendment – Proposal Submitted by us vide letter No. GIL/SS/G-
289/20059 dated 03.12.2016 and understand that presently same is in RHQ.
b) Final Time Limit Extension – Our request has been submitted vide our letter No.
GIL/SS/G-289/20050 dated 31.11.2016.
c) Taking Over certificated of the line.
3) On account of the above our total payment of 586.39 lacs is on hold as detailed
under –
a) With Hold payment from Our RA bills – 180.40 Lacs
b) 5% Retention Amount – 402.70 Lacs.
c) Release of ABG – 204.34 Lacs.
From above you would agree that considerable time has lapse, since commission of the
project. However for issuance of required documents, our payment is getting delayed. Also
you would agree that with deployment of lot of resources, we have completed the line.
We request you to your kind intervention for immediate clearance of above point from
PGNMTL.
With Regards
For TRANSRAIL LIGHTING LIMITED,
K. P. Singh
Vice President (Construction)
Cc.: 1. Mr. R K Sing – ED, SR-II
2. Mr. Joseph Kurain – DGM, PGNMTL, Bangalore.
3. Mr. J P Jayaprakash – AGM, PGNMTL, Bangalore.
Ref : TLL/SS/G-290/21240 Date : 03.06.2017
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,+
Bangalore 560064, Karnataka
Kind Attn.: Mr. Rabindra Kumar – GM
Sub.: 1. Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem Transmission
Line (Part-II) (with Hex Zebra Conductor) associated with Transmission System pertaining
to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff Based
Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01,TBCB/765KV/02(N-M)/ERE02
Dear Sir
With reference to the subject contract, we like to invite your kind attention on following –
1) The subject line has been commissioned on 21.10.2016 and under commercial
utilization by PGNMTL since then.
2) However we still await the following-
a) Final Quantity Amendment – Proposal Submitted by us vide letter No. GIL/SS/G-
289/20579 dated 23.02.2017 and understand that presently same is in RHQ.
b) Final Time Limit Extension – Our request has been submitted vide our letter No.
GIL/SS/G-289/20554 dated 18.02.2017.
c) Taking Over certificated of the line.
3) On account of the above our total payment of 904.36 lacs is on hold as detailed
under –
a) With Hold payment from Our RA bills – 106.09 Lacs
b) 5% Retention Amount – 798.27 Lacs.
c) Work done/ unbilled Quantity of Revetment - 62.59 lacs
d) Release of ABG – 218.17 Lacs.
From above you would agree that considerable time has lapse, since commission of the
project. However for issuance of required documents, our payment is getting delayed. Also
you would agree that with deployment of lot of resources, we have completed the line.
We request you to your kind intervention for immediate clearance of above point from
PGNMTL.
With Regards
For TRANSRAIL LIGHTING LIMITED,
K. P. Singh
Vice President (Construction)
Cc.: 1. Mr. R K Sing – ED, SR-II
2. Mr. Joseph Kurain – DGM, PGNMTL, Bangalore.
3. Mr. J P Jayaprakash – AGM, PGNMTL, Bangalore.
Ref: TLL/SS/G-289&290/21497 Date: 15.07.2017
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,+
Bangalore 560064, Karnataka
Kind Attn.: Mr. A K Das – CM (Finanace)
Sub.: 1. Tower Erection Package – ERE01 & 02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I &II) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff
Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01,TBCB/765KV/02(N-M)/ERE02
Dear Sir,
With reference to the subject contract and our letter No. GIL/G-289&290/SS/20928
dated 26.04.2017 regarding transfer of Business from Gammon India Ltd to Transrail
Lighting Ltd, we would like to inform you all outstanding payments against said
contracts to be paid to us in the below mentioned bank account. Details of the bank
are as under -
Request you to please Update the above bank details in your system and remit the
payment in the respective account.
With Regards
For TRANSRAIL LIGHTING LIMITED,
D. Suryanarayana
Vice President (T & D - Business)
Cc.: 1. Mr. R K Sing – ED, SR-II
2. Mr. Joseph Kurain – DGM, PGNMTL, Bangalore.
Ref: TLL/SS/L-290/21750 Date: 18.08.2017
To
The Asst. General Manager (Construction)
M/s. Powergrid N M Transmission Limited.
C/o. Powergrid Corporation of India Limited.
Salem, Tamil Nadu.
Kind Attn.: Mr. J P Jayaprakash, AGM (Construction)
Sub.: Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem Transmission Line
(Part-II) (with Hex Zebra Conductor) associated with Transmission System pertaining to
IPPs of Nagapattinam / Cuddalore Area: Package-A under Tariff Based Competitive
Bidding Route : Submission of Drawings-reg.
Ref.: 1. NOA No. PGNMTL/765 kV/02(N-M)/ERE02/NOA-I/12 & NOA-II/13, dt.16.05.2014.
Dear Sir,
With reference to the subject contract, here we submit the Foundation drawings & accessories
drawing towards final submission for closure of contract. The details of submission are listed
below –
Request you kindly verify the details from your end against final submission.
Thanking you
Yours faithfully,
For Transrail Lighting Limited
Uday Patil
Asst. General Manager, Contracts – T & D Business
Encl.: As above
Cc. 1. Mr. Joseph Kurian, DGM (Engg.), PGCIL, Bangalore
Ref: TLL/SS/G-289&290/22261 Date: 08.11.2017
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,+
Bangalore 560064, Karnataka
Kind Attn.: Mr. A K Das – CM (Finanace)
Sub.: 1. Tower Erection Package – ERE01 & 02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I &II) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff
Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01,TBCB/765KV/02(N-M)/ERE02
Dear Sir,
This is with reference to the subject project and our email dated 04.11.2017, please find
enclosed herewith amendment copy of BG for Name change from “Gammon India Ltd” to
“Transrail Lighting Limited”, along with extension copy of Advance Bank Guarantee of for
Supply and CPBG(S) of for Supply & erection portion of the above project for your records.
The Bank Guarantees details are here under.
Sr.
Date of Issuing Amount Present
No B. G. No. & Date Remarks
Amend Bank (Rs.) Validity
.
ID0GOPGI62990001 Supply
1 27.10.17 CANARA 16,78,246/- 30.04.18
Dt. 25.10.2016 Advance BG
ID0GOPGI62990002 30.04.18 Supply
2 27.10.17 CANARA 15,73,914/-
Dt. 25.10.2016 Advance BG
I02GPGE141920003 30.04.18
3 27.10.17 CANARA 11,22,831/- Supply CPG
Dt. 11.07.2014
I02GPGE141920004 30.04.18
4 27.10.17 CANARA 8,14,61,332/- Erection CPG
Dt. 11.07.2014
I02GPGE141920005 30.04.18
5 27.10.17 CANARA 7,55,27,138/- Erection CPG
Dt. 11.07.2014
I02GPGE141920002 30.04.18
6 27.10.17 CANARA 10,53,276/- Supply CPG
Dt. 11.07.2014
Uday Patil
(Dy. General Manager, Contracts – T & D Business)
Encl.: as above
Cc.: 1. Mr. Joseph Kurian – Dy. General Manager, PGNMTL, Bangalore.
Ref: TLL/SS/G-289&290/22300 Date: 14.11.2017
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,+
Bangalore 560064, Karnataka
Kind Attn.: Mr. Joseph Kurion – DGM
Sub.: 1. Tower Erection Package – ERE01 & 02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I &II) (with Hex Zebra Conductor) associated with Transmission
System pertaining to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff
Based Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01,TBCB/765KV/02(N-M)/ERE02
Dear Sir,
This is with reference to the subject project; we want to inform you that all advance(s) related
to the subject contract are already adjusted from our RA Bill(s) and you have already released
our erection advance BG(s) vide your letter dated 31st July’ 2017. Now we are requesting you
to please arrange to release the following supply advance BG(S).
Sr.
Issuing Amount Present
No B. G. No. & Date Remarks
Bank (Rs.) Validity
.
I02G0PG141920002 Supply
1 CANARA 15,73,914/- 30.04.18
Dt. 11.07.2014 Advance BG
I02G0PG141920001 Supply
2 CANARA 16,78,246/- 30.04.18
Dt. 11.07.2014 Advance BG
We would request you kindly accept the same and release the BG(s).
Uday Patil
(Dy. General Manager, Contracts – T & D Business)
Encl: As Above
Ref: TLL/SS/G-289/Final Bill Date: 12.11.2017
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,+
Bangalore 560064, Karnataka
Kind Attn.: Mr. Joseph Kurion – DGM
Sub.: 1. Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem Transmission Line
(Part-I) (with Hex Zebra Conductor) associated with Transmission System pertaining to IPPs of
Nagapattinam / Cuddalore Area: Package - A under Tariff Based Competitive Bidding
Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01
Dear Sir,
With reference to the above, we are enclosing herewith the following invoice toward final claim Amount of
Erection component as per CA clause no. “1.1 F” .
The above final bills are raised considering the final amendment quantity and already submitted RA Bill No.30
& RA Bill No. 31 dated 30.06.2017 which is lying with you for further processing.
Request you kindly check the same from your end and process the same for final payment.
List of documents enclosed: -
- Commercial Invoice(s).
- Details Statement of RA bill wise Passed quantity w.r.t final amendment.
- Bill register for Payment Reconciliation
Authorised Signatory
Encl: As above.
cc: Mr.A K Das, CM (F& A), PGNMTL - For your information please.
Ref: TLL/SS/G-290/Final Bill Date: 12.11.2017
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,+
Bangalore 560064, Karnataka
Kind Attn.: Mr. Joseph Kurion – DGM
Sub.: 1. Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem Transmission Line
(Part-II) (with Hex Zebra Conductor) associated with Transmission System pertaining to IPPs of
Nagapattinam / Cuddalore Area: Package - A under Tariff Based Competitive Bidding
Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE02
Dear Sir,
With reference to the above, we are enclosing herewith the following invoice toward final claim Amount of
Erection component as per CA clause no. “1.1 F” .
The above final bills are raised considering the final amendment quantity and already submitted RA Bill No.30
& RA Bill No. 31 dated 30.06.2017 which is lying with you for further processing.
Request you kindly check the same from your end and process the same for final payment.
List of documents enclosed: -
- Commercial Invoice(s).
- Details Statement of RA bill wise Passed quantity w.r.t final amendment.
- Bill register for Payment Reconciliation
Authorised Signatory
Encl: As above.
cc: Mr.A K Das, CM (F& A), PGNMTL - For your information please.
Ref: TLL/SS/G-289&290/22349 Date: 21.11.2017
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,+
Bangalore 560064, Karnataka
Kind Attn.: Mr. Joseph Kurion – DGM
Sub.: 1. Tower Erection Package – ERE01 & ERE02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I&II) (with Hex Zebra Conductor) associated with Transmission System
pertaining to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff Based
Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01, TBCB/765KV/02(N-M)/ERE02
Ref.:1. NOA No. PGNMTL/765 kV/02(N-M)/ERE01/NOA-I/10 & NOA-II/11 dated 16.05.2014.
2. NOA No. PGNMTL/765 kV/02(N-M)/ERE02/NOA-I/12 & NOA-II/13 dated 16.05.2014.
Dear Sir,
With reference to the subject contract and as per Powergrid MOM dated 25.06.2017 and
notification dated 28.06.2017 (copy attached), it was inform to us that all invoices related to
completed Supplies / services before 30.06.2017, need to be submitted at concern POWERGRID
office by 30.06.2017.
As per above guidelines we have submitted following erection Bill(s) at PGCIL office which work
has been completed before June’2017 for further processing. The acknowledgement copy of the
same are also attached for your reference. Details of the bills are as under –
Regarding the above bill(s), we want to inform you that we have already booked this bill(s) in our
book and also paid the service tax against those bills. Now we need to close our account after
processing of the bill(s) from your end.
Therefore we are requesting you to please process our above pending bills and release our
payment so that we can close our account. Request you kindly do the needful.
Thanking you and assuring our best services always.
With Regards
For Transrail Lighting Limited,
Uday Patil
(Dy. General Manager, Contracts – T & D Business)
Encl: As Above
CC: Mr.A K Das, CM (F& A), PGNMTL Bangalore.
Ref: TLL/SS/G-289&290/22469 Date: 07.12.2017
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,+
Bangalore 560064, Karnataka
Kind Attn.: Mr. Joseph Kurion – DGM
Sub.: 1. Tower Erection Package – ERE01 & ERE02 for 765 kV D/C Nagapattinam - Salem
Transmission Line (Part-I&II) (with Hex Zebra Conductor) associated with Transmission System
pertaining to IPPs of Nagapattinam / Cuddalore Area: Package - A under Tariff Based
Competitive Bidding Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01, TBCB/765KV/02(N-M)/ERE02
Ref.:1. NOA No. PGNMTL/765 kV/02(N-M)/ERE01/NOA-I/10 & NOA-II/11 dated 16.05.2014.
2. NOA No. PGNMTL/765 kV/02(N-M)/ERE02/NOA-I/12 & NOA-II/13 dated 16.05.2014.
Dear Sir,
With reference to the subject contract and as per final amendment quantity we would like to bring
your kind attention regarding MICC of Pipe Type Earthing.
1) For MICC claim of Pipe type earthing along with Pipe same numbers of “D-Flat” & “C-Flat”
are required.
2) Please find below the present CIP available status for MICC claim, for your reference –
Total TOTA CIP TAKEN MICC MICC CIP AVL. FOR MICC
PACKAGE
Amnd Qty PIPE "D-Flat" "C-Flat" RCVD. BAL. PIPE "D-Flat" "C-Flat"
Part-I 170 175 150 272 100 70 75 50 172
Part-2 89 89 150 272 40 39 75 110 232
3) As per above status you can observe that, 20 Nos “D-Flat” are less in Part-I for MICC Claim
of 70 NOS Pipe Type Earthing.
4) Hence we request for transfer of 20 nos “D-Flat” of from Part-II CIP No. 293704 dated
02.03.2015 (copy attached), to “Part-I” for MICC claim only.
Therefore, we request you to please issue a letter for transfer of the same, so that we can claim the
MICC of Pipe type earthing and raise our final claim.
With Regards
For Transrail Lighting Limited,
Uday Patil
(Dy. General Manager, Contracts – T & D Business)
Encl: As Above
Ref: TLL/SS/G-290/22644 Date: 25.12.2017
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,+
Bangalore 560064, Karnataka
Kind Attn.: Mr. Ravindra Kumar – GM
Sub.: 1. Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem Transmission Line
(Part-II) (with Hex Zebra Conductor) associated with Transmission System pertaining to IPPs of
Nagapattinam / Cuddalore Area: Package - A under Tariff Based Competitive Bidding
Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE02
Dear Sir,
With reference to the subject contract we would like to bring your kind attention on following –
1) The subject line has been commissioned on 21.10.2016 and under commercial utilization by
PGNMTL since then.
2) TOC of the Line has been issued vide your letter No. PNMTL/SLM/ERE02/F-217/TOC dated
21.07.2017
3) The final time extension of the subject contract has been issued vide your letter no. SR-
II/C&M PGNMTL/02(N-M)/ERE02/FTE/1957 dated 28.11.2017.
In view of the above, we request you kindly release our withheld amount & 5% retention amount of
the subject contract. The details of the same are as under –
Uday Patil
(Dy. General Manager, Contracts – T & D Business)
Encl: As Above
cc: Mr. Joseph Kurain, DGM (ENGG), PGNMTL .
Ref: TLL/SS/G-290/25510 Date: 29.03.2018
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,+
Bangalore 560064, Karnataka
Kind Attn.: Mr. Ravindra Kumar – GM
Sub.: 1. Tower Erection Package – ERE02 for 765 kV D/C Nagapattinam - Salem Transmission Line
(Part-II) (with Hex Zebra Conductor) associated with Transmission System pertaining to IPPs of
Nagapattinam / Cuddalore Area: Package - A under Tariff Based Competitive Bidding
Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE02
Dear Sir,
Subject project was completed and commissioned on 21.10.16. also final checking, compliance of
punch point and handing over also completed. Issuance of TOC, time extension and final
amendment also completed. However our outstanding due of 3.15 Cr is balance to release. Bill-
wise details is enclosed in Annexure – I.
In view of the above in order to expedite release of payment, we request you as under –
In this regard we are deputing our Mr. Ashish Kumar Sharma at your office on 31st Macrh’18 and
request to give priority so that we get the payment within this financial year.
With Regards
For Transrail Lighting Limited,
Uday Patil
(Dy. General Manager, Projects)
Encl: As Above
cc: Mr. Joseph Kurain, DGM (ENGG), PGNMTL .
Mr.A K Das, CM (F& A), PGNMTL Bangalore.
Ref: TLL/SS/G-289/25509 Date: 29.03.2018
To
M/s. Powergrid NM Transmission Limited
C/o Power Grid Corporation of India Limited,
Yelehanka 400 Kv/220 KV GIS,
Near RTO test track, Singanaick ana halli,
Yelehanka Doddaballapur Road,+
Bangalore 560064, Karnataka
Kind Attn.: Mr. Joseph Kurion – DGM
Sub.: 1. Tower Erection Package – ERE01 for 765 kV D/C Nagapattinam - Salem Transmission Line
(Part-I)(with Hex Zebra Conductor) associated with Transmission System pertaining to IPPs of
Nagapattinam / Cuddalore Area: Package - A under Tariff Based Competitive Bidding
Route.
Tender Specification No.: TBCB/765KV/02(N-M)/ERE01
Dear Sir,
Subject project was completed and commissioned on 21.10.16. also final checking, compliance of
punch point and handing over also completed. Only Loc. 38/0 foundation rectification is balance
which is getting completed tomorrow. In this project our totals 5.93 Cr due are balance to release
as per Annexure–I enclosed.
In view of the above in order to expedite release of payment, we request you as under –
1) Issuance of TOC and time extension as Loc. 38/0 punch point also completed now.
2) Arrange to give time from finance department in 1st week of April for completing financial
reconciliation.
3) Release of payment of 5.93 Cr.
Request you to extend above support as already 18 months lapse since commissioning of project
and we are desperately in need of funds for other ongoing Powergrid projects.
With Regards
For Transrail Lighting Limited,
Uday Patil
(Dy. General Manager, Projects)
Encl: As Above
cc: Mr. Joseph Kurain, DGM (ENGG), PGNMTL .
Mr.A K Das, CM (F& A), PGNMTL Bangalore.