ANALISA PEKERJAAN

NO URAIAN KOEF SAT

1 2 3 4

A. ANALISA PEKERJAAN PERSIAPAN / PENDAH


A1 1 M2 Pembersihan Lahan
SNI
6.8 Jack Hammer 0.1000 hari
03-2835-2002 Pekerja 0.1000 org
Mandor 0.0500 org
Jumlah

A2 1 M' Pengukuran dan Pemasangan Bouwplank


SNI kayu meranti bouwplank 5/7 0.0120 M³
6.4 Paku Biasa 0.0200 kg
03-2835-2002 Kayu Papan Meranti Bouwplank 3/20 0.0070 M³
Pekerja 0.100 org
Tukang 0.100 org
Kepala tukang 0.010 org
Mandor 0.0050 org
Jumlah

A3 1 M2 PEMBUATAN DIREKSI KEET


Kayu Dolken D 8-10 cm - 4 m 1.700 Btg
Kayu Meranti 0.210 M3
Paku 0.300 Kg
Semen Portland 10.500 Kg
Pasir Pasang 0.030 m3
Koral Beton 0.050 m3
Seng Gelombang BJLS 30 1.500 Lbr
Pekerja 1.0000 org
tukang kayu 2.0000 org
Kepala tukang 0.2000 org
Mandor 0.0500 org
Jumlah

B. ANALISA PEKERJAAN PONDASI / TANA


SNI 2835:2008
B1 1 M3 PEK. GALIAN TANAH BIASA MAX KEDALAMAN 1 M'
SNI 2835:2008 Pekerja 0.7500 org
Mandor 0.0250 org
Jumlah
B2 1 M3 PEK. GALIAN TANAH BIASA MAX KEDALAMAN 2 M'
Pekerja 0.9000 org
Mandor 0.0450 org
Jumlah

B3 1 M3 PEK. URUGAN TANAH KEMBALI


Pekerja 0.1920 org
Mandor 0.0190 org
Alat bantu 0.0000 lot
Jumlah

B4 1 M3 URUGAN TANAH
Tanah urug 1.2000 m3
Pekerja / buruh tak terlatih 0.300 org
Mandor 0.010 org
Jumlah

B5 PEMADATAN TANAH
Pekerja / buruh tak terlatih 0.500 org
Mandor 0.050 org
Jumlah

B6 1 M3 URUGAN PASIR
Pasir urug 1.2000 m3
Pekerja 0.3000 org
Mandor 0.0100 org
Jumlah

B7 1 Titik Cerucuk Kayu Ulin


Kayu Ulin 10/10 - 2 m' 0.0200 m3
Pekerja 0.2070 org
Tukang Kayu 0.2700 org
Ka. Tukang Kayu 0.1500 org
Mandor 0.0900 org
Jumlah

B7A 1 M3 PAPAN KALANG ULIN MENERUS DAN SUNDUK ULIN


Balok Ulin Uk. 5/10 + Papan Ulin Uk. 2/20 1.0000 m3
Paku Ulin 1.0000 Kg
Pekerja 5.0000 org
Tukang Kayu 15.0000 org
Ka. Tukang Kayu 1.5000 org
Mandor 0.2500 org
Jumlah
B8 1 M3 Sloop dan Gelagar Ulin
Balok Ulin Uk. 10/10 1.1000 m3
Paku Ulin 1.0000 Kg
Pekerja 5.0000 org
Tukang Kayu 15.0000 org
Ka. Tukang Kayu 1.5000 org
Mandor 0.2500 org
Jumlah

B8A 1 M3 LANTAI PAPAN ULIN 5/20


Papan Ulin Uk. 5/20 1.1000 m3
Paku Ulin 2.0000 Kg
Pekerja 5.0000 org
Tukang Kayu 15.0000 org
Ka. Tukang Kayu 1.5000 org
Mandor 0.2500 org
Jumlah

Bc 1 Titik Cerucuk Kayu Ulin


Kayu Ulin 10/10 - 12 m' 0.1200 m3
Pekerja 0.2070 org
Tukang Kayu 0.2700 org
Ka. Tukang Kayu 0.1500 org
Mandor 0.0900 org
Jumlah

B9 1 M3 PASANGAN ANSTAMPING BATU GUNUNG


SNI Batu gunung 1.2000 m3
6.14 Pasir urug 0.3000 m3
03-2836-2002 Pekerja 0.7800 org
Tukang batu 0.3900 org
Kepala tukang batu 0.0390 org
Mandor 0.0390 org
Jumlah

B10 1 M3 PASANGAN BATU GUNUNG 1 : 4


SNI Batu gunung 1.1000 m3
6.9 PC ( 50 kg ) 163.0000 kg
03-2836-2002 Pasir pasang 0.5200 m3
Pekerja 1.5000 org
Tukang batu 0.6000 org
Kepala tukang batu 0.0600 org
Mandor 0.0750 org
Jumlah
C. ANALISA PEKERJAAN BETON
C1 1 M3 LANTAI KERJA/ BETON TUMBUK 1 PC : 3 PS : 5 KRL
SNI PC ( 50 kg ) 218.0000 kg
6.1 Pasir beton 0.5200 m3
03-2837-2002 Koral Beton 0.8700 m3
Pekerja 1.6500 org
Tukang batu 0.2500 org
Kepala tukang batu 0.0250 org
Mandor 0.0800 org
Jumlah

C6 1 Kg. Besi beton polos/Ulir


SNI besi beton (polos/ulir) 1.0500 kg
7394:2008 kawat beton 0.0150 kg
Pekerja 0.0070 org
Tukang besi 0.0070 org
Kepala tukang batu 0.0007 org
Mandor 0.0003 org
Jumlah
SNI 7394:2008
C8 1 M2 BEKESTING DENGAN PAPAN UNTUK PONDASI/POOR PLAT
SNI Kayu Kelas III papan meranti begesting 0.0400 M³
6.20 paku 5 cm-10 cm 0.3000 kg
7394:2008 minyak begesting 0.1000 Ltr
Pekerja 0.5200 org
Tukang kayu 0.2600 org
Kepala tukang kayu 0.0260 org
Mandor 0.0260 org
Jumlah
B
C9 1 M2 BEKESTING DENGAN PAPAN UNTUK SLOOF
SNI Kayu Kelas III papan meranti begesting 0.0450 M³
6.21 paku 5 cm-10 cm 0.3000 kg
7394:2008 minyak begesting 0.1000 Ltr
Pekerja 0.5200 org
Tukang kayu 0.2600 org
Kepala tukang kayu 0.0260 org
Mandor 0.0260 org
Jumlah
B
C10 1 M2 BEKESTING UNTUK KOLOM
SNI Kayu Kelas III papan meranti begesting 0.0400 M³
6.22 paku 5 cm-10 cm 0.4000 kg
7394:2008 minyak begesting 0.2000 Ltr
Balok Kayu Meranti kayu kelas II 0.0150 M³
Plywood tebal 9 mm 0.3500 Lbr
Dolken kayu galam d8-10 / 4 m 2.0000 Btg
Pekerja 0.6600 org
Tukang kayu 0.3300 org
Kepala tukang kayu 0.0330 org
Mandor 0.0330 org
Jumlah
B
C11 1 M2 BEKESTING DENGAN PAPAN UNTUK RING BALK
papan begesting 0.0450 M³
paku 0.3000 kg
minyak begesting 0.1000 Ltr
Pekerja 0.3000 org
Tukang kayu 0.2600 org
Kepala tukang kayu 0.0260 org
Mandor 0.0050 org
Jumlah
B
C12 1 M2 BEKESTING UNTUK LANTAI
papan begesting 0.0400 M³
paku 0.4000 kg
minyak begesting 0.2000 Ltr
Balok Kayu Meranti 0.0140 M³
Dolken ( kayu perancah ) 6.0000 Btg
Plywood Tebal 12 mm 0.3500 Lbr
Pekerja 0.3200 org
Tukang kayu 0.3300 org
Kepala tukang kayu 0.0330 org
Mandor 0.0060 org
Jumlah
B
C12a 1 M2 BEKESTING UNTUK LANTAI PLAT DECKER
papan begesting 0.0400 M³
paku 0.4000 kg
minyak begesting 0.2000 Ltr
Balok Kayu Meranti 0.0140 M³
Dolken ( kayu perancah ) Btg
Plywood Tebal 12 mm 0.3500 Lbr
Pekerja 0.3200 org
Tukang kayu 0.3300 org
Kepala tukang kayu 0.0330 org
Mandor 0.0060 org
Jumlah
B
C13 1 M2 BEKESTING UNTUK BALOK
papan begesting 0.0400 M³
paku 0.4000 kg
minyak begesting 0.2000 Ltr
Balok Kayu Meranti 0.0180 M³
Dolken ( kayu perancah ) 2.0000 Btg
Plywood Tebal 12 mm 0.3500 Lbr
Pekerja 0.3200 org
Tukang kayu 0.3300 org
Kepala tukang kayu 0.0330 org
Mandor 0.0060 org
Jumlah
B
C15 1 M3 BETON K-250
SNI 7394:2008 PC ( 50 kg ) 384.000 kg
Pasir beton 0.499 m3
Split pecah mesin 2/3 0.582 m3
Pekerja 1.650 org
Tukang batu 0.275 org
Kepala tukang batu 0.028 org
Mandor 0.083 org
Jumlah
SNI 7394:2008
C16 1 M3 BETON BERTULANG PONDASI
Begesting untuk pondasi 42.0000 m2
Besi beton polos/Ulir 1,911.0000 Kg
Cor Beton K-250 14.7000 m3
jumlah
jadi untuk 1 m3 beton bertulang adalah jumlah total dibagi volume cor beton
C17 1 M3 BETON BERTULANG SLOOP 20/30
Begesting untuk Sloof 114.6000 m2
Besi beton polos/Ulir 802.2000 Kg
Cor Beton K-250 11.4600 m3
jumlah
jadi untuk 1 m3 beton bertulang adalah jumlah total dibagi volume cor beton
C18 1 M3 BETON BERTULANG SLOOP 15/20
Begesting untuk Sloof 44.0000 m2
Besi beton polos/Ulir 462.0000 Kg
Cor Beton K-250 3.3000 m3
jumlah
jadi untuk 1 m3 beton bertulang adalah jumlah total dibagi volume cor beton
C19 1 M3 BETON BERTULANG BALOK EL. 3.40 25/45
Begesting untuk Balok 305.1625 m2
Besi beton polos/Ulir 4,394.3400 Kg
Cor Beton K-250 27.4646 m3
jumlah
jadi untuk 1 m3 beton bertulang adalah jumlah total dibagi volume cor beton
C19.A 1 M3 BETON BERTULANG BALOK EL. 3.40 20/30
Begesting untuk Balok 152.4125 m2
Besi beton polos/Ulir 1,170.5280 Kg
Cor Beton K-250 7.3158 m3
jumlah
jadi untuk 1 m3 beton bertulang adalah jumlah total dibagi volume cor beton
C20 1 M3 BETON BERTULANG BALOK EL. 6.00 15/20
Begesting untuk Balok 45.1000 m2
Besi beton polos/Ulir 480.2057 Kg
Cor Beton K-250 2.4600 m3
jumlah
jadi untuk 1 m3 beton bertulang adalah jumlah total dibagi volume cor beton
C21 1 M3 BETON BERTULANG BALOK GEWEL15/20
Begesting untuk Balok 19.3600 m2
Besi beton polos/Ulir 206.1371 Kg
Cor Beton K-250 1.0560 m3
jumlah
jadi untuk 1 m3 beton bertulang adalah jumlah total dibagi volume cor beton
C22 1 M3 BETON BERTULANG KOLOM UTAMA 40/40
Begesting untuk Balok 176.0000 m2
Besi beton polos/Ulir 2,464.0000 Kg
Cor Beton K-250 17.6000 m3
jumlah
jadi untuk 1 m3 beton bertulang adalah jumlah total dibagi volume cor beton
C23 1 M3 BETON BERTULANG KOLOM PRAKTIS 15/15
Begesting untuk Balok 51.0000 m2
Besi beton polos/Ulir 535.5000 Kg
Cor Beton K-250 3.8250 m3
jumlah
jadi untuk 1 m3 beton bertulang adalah jumlah total dibagi volume cor beton
C24 1 M3 BETON BERTULANG PLAT DECK 10CM
Begesting untuk Plat Lantai 123.0000 m2
Besi beton polos/Ulir 1,771.2000 Kg
Cor Beton K-250 14.7600 m3
jumlah
jadi untuk 1 m3 beton bertulang adalah jumlah total dibagi volume cor beton

D. ANALISA PEKERJAAN KERAMIK DAN PENUTUP


D2 1 M2 LANTAI KERAMIK 40/40
Keramik 1.0000 m2
PC ( 50 kg ) 11.3800 kg
Pasir pasang 0.0420 m3
Semen warna 1.5000 kg
Pekerja 0.6200 org
Tukang batu 0.3500 org
Kepala tukang batu 0.0350 org
Mandor 0.0300 org
Jumlah

D3 1 M2 DINDING KERAMIK 20/20


Keramik 1.0000 m2
PC ( 50 kg ) 11.3800 kg
Pasir pasang 0.0180 m3
Semen warna 1.5000 kg
Pekerja 0.6000 org
Tukang batu 0.4500 org
Kepala tukang batu 0.0450 org
Mandor 0.0300 org
Jumlah

D5 1 M2 DINDING BATU ALAM


Keramik 1.0500 m2
PC ( 50 kg ) 11.7500 kg
Pasir pasang 0.0350 m3
Semen warna kg
Pekerja 0.6200 org
Tukang batu 0.3500 org
Kepala tukang batu 0.0350 org
Mandor 0.0300 org
Jumlah

E. ANALISA PEKERJAAN DINDING


E1 1 M2 PASANGAN BATA MERAH 1/2 BATA 1 : 2
Bata merah 55.0000 bh
PC ( 50 kg ) 18.9500 kg
Pasir pasang 0.0380 m3
Pekerja 0.3200 org
Tukang batu 0.1000 org
Kepala tukang batu 0.0100 org
Mandor 0.0150 org
Jumlah

E2 1 M2 PASANGAN BATA MERAH 1/2 BATA 1 : 4


Bata merah 55.0000 bh
PC ( 50 kg ) 11.5000 kg
Pasir pasang 0.0430 m3
Pekerja 0.3200 org
Tukang batu 0.1000 org
Kepala tukang batu 0.0100 org
Mandor 0.0150 org
Jumlah

E2.a 1 M2 PASANGAN BATA MERAH 1 BATA 1 : 4


SNI Bata merah 101.7500 bh
6.4 PC ( 50 kg ) 21.2750 kg
03-2837-2002 Pasir pasang 0.0796 m3
Pekerja 0.5920 org
Tukang batu 0.1850 org
Kepala tukang batu 0.0185 org
Mandor 0.0278 org
Jumlah

E3 1 M2 PLESTERAN DINDING / SIAR 1 : 2 + ACIAN tebal 20 mm


PC ( 50 kg ) 14.2800 kg
Pasir pasang 0.0230 m3
Pekerja 0.2500 org
Tukang batu 0.2000 org
Kepala tukang batu 0.0200 org
Mandor 0.0125 org
Jumlah

E4 1 M2 PLESTERAN DINDING / SIAR 1 : 4 + ACIAN tebal 20 cm


PC ( 50 kg ) 8.6800 kg
Pasir pasang 0.0280 m3
Pekerja 0.2500 org
Tukang batu 0.2000 org
Kepala tukang batu 0.0200 org
Mandor 0.0125 org
Jumlah

E5 1 M' Plesteran Sponing 1 : 2


PC ( 50 kg ) 0.0250 kg
Pasir pasang 0.0001 m3
Pekerja 0.0029 org
Tukang batu 0.0019 org
Kepala tukang batu 0.0019 org
Mandor 0.0001 org
Jumlah

E6 1 M2 Plesteran Sponing 1 : 2 Type Kotak


PC ( 50 kg ) 4.3200 kg
Pasir pasang 0.0160 m3
Pekerja 0.2500 org
Tukang batu 0.1000 org
Kepala tukang batu 0.0100 org
Mandor 0.0150 org
Jumlah

F. ANALISA PEKERJAAN CAT


F1 1 M2 PENGECATAN TEMBOK BARU BAGIAN DALAM ( 1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAP
Plamir Tembok 0.1000 kg
Cat Dasar morilex 0.1000 kg
Cat Penutup dalam morilex 2x 0.2600 kg
Pekerja 0.0200 org
Tukang cat 0.0630 org
Kepala tukang cat 0.0063 org
Mandor 0.0025 org
Jumlah

F2 1 M2 PENGECATAN TEMBOK BARU BAGIAN LUAR ( 1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS
Alkali 0.1000 kg
Cat Dasar morilex 0.1000 kg
Cat Penutup Luar morilex 2x 0.2600 kg
Pekerja 0.0200 org
Tukang cat 0.0630 org
Kepala tukang cat 0.0063 org
Mandor 0.0025 org
Jumlah

F3 1 M2 PENGECATAN KAYU, 1 LAPIS PLAMIR, 1 LAPIS MENI, 2 LAPIS CAT


Meni kayu 0.2000 kg
Plamir kayu 0.1500 kg
Cat kayu dasar morilex 0.1700 kg
Cat kayu penutup morilex 0.2600 kg
Pekerja 0.0700 org
Tukang cat 0.0090 org
Kepala tukang cat 0.0060 org
Mandor 0.0025 org
Jumlah

F4 1 M2 MENDEMPUL DAN MENGGOSOK KAYU


Dempul 0.0800 kg
Minyak cat 0.0200 Ltr
Amplas 2.0000 Lbr
Pekerja 0.0400 org
Tukang cat 0.0400 org
Kepala tukang cat 0.0040 org
Mandor 0.0025 org
Jumlah

F5 1 M2 MELAMIN / DECO
Clear Doof 0.6667 Ltr
Wood Filler 0.4000 kg
Wood Fstain (Pewarna) 0.4000 kg
Ampelas 0.8000 Lbr
Sanding Sailer 0.6667 Kg
Tinner A 1.4000 Ltr
Pekerja 0.1600 org
Tukang cat 0.1600 org
Kepala tukang cat 0.0160 org
Mandor 0.0025 org
Jumlah

G. ANALISA PEKERJAAN PLAFON


E.001 1 M2 PAS. RANGKA PLAFOND HOLLOW ( HANYA RANGKA UKURAN 1 X 1 M' )
Hollow 0,40 mm + Asesoris 4.0000 M1
Sekrup + Asesoris 1.0000 Ls
Pekerja 0.1500 org
Tukang 0.2500 org
Kepala tukang 0.0250 org
Mandor 0.0750 org
Jumlah
G2 1 M2 PAS. BAHAN PLAFOND GYPSUM BOARD TEBAL 9 MM PENUTUP PADA RANGKA
Gypsum Board 9 mm 0.3040 Lbr
Paku Sekrup 0.1100 kg
Pekerja 0.1000 org
Tukang kayu 0.0650 org
Kepala tukang kayu 0.0065 org
Mandor 0.0065 org
Jumlah

G4 1 M' List Plafon gypsum


List gypsum 1.1000 Lbr
Paku 0.0100 kg
Pekerja 0.0500 org
Tukang kayu 0.0500 org
Kepala tukang kayu 0.0050 org
Mandor 0.0030 org
Jumlah

F. ANALISA KUSEN & DAUN PINTU


F.001 Membuat dan Memasang 1 m3 kusen pintu dan kusen jendela
Balok Kayu 1.1000 M3

Paku 10 cm 1.2500 Kg

Lem Kayu 1.0000 Kg


Pekerja 7.0000 OH
Tukang kayu 21.0000 OH

Kepala tukang 2.1000 OH


Mandor 0.3500 OH
Jumlah
untuk 1 m1 kusen kayu
F.002 Membuat dan Memasang 1 m2 pintu daun pintu panel
Papan Kayu 0.0400 M3

Lem Kayu 0.5000 kg


Pekerja 1.0000 OH

Tukang besi konstruksi 3.0000 OH

Kepala tukang 0.3000 OH


Mandor 0.0500 OH
Jumlah
F.003 Membuat dan Memasang 1 m2 pintu dan jendela kaca
Papan Kayu 0.0240 M3

Lem Kayu 0.3000 kg


Pekerja 0.8000 OH

Tukang besi konstruksi 2.4000 OH

Kepala tukang 0.2400 OH


Mandor 0.0400 OH
Jumlah
H5 1 M2 JALUSI PAPAN BANGKIRAI
Papan Bangkirai 0.0600 m3
Paku Biasa 0.1500 Kg
Pekerja 0.5000 org
Tukang kayu 2.0000 org
Kepala tukang kayu 0.2000 org
Mandor 0.0250 org
Jumlah

I. ANALISA PEKERJAAN ATAP


I1 1 M2 KUDA-KUDA & RANGKA ATAP BAJA RINGAN
Besi baja Ringan C 75 5 0,5 6.5000 m1
Reng tipe R-35 9.0000 m1
Sekrup + Asesoris 30% 1.0000 ls
Pekerja 0.680 kg
Tukang Besi 0.680 org
Kepala tukang 0.068 org
Mandor 0.034 org
Jumlah

I2 1 M' PEKERJAAN LISTPLANK PAPAN GRC BOARD


Papan GRC 0.3850 M2
Paku 0.0500 kg
Pekerja 0.1000 org
Tukang kayu 0.2000 org
Kepala tukang kayu 0.0250 org
Mandor 0.0050 org
Jumlah

I3 1 M2 PENUTUP ATAP Genteng Metal


Genteng Metal Multi Roof 1.7857 Bh
Paku Genteng Metal 0.0500 Kg
Pekerja 0.1315 org
Tukang kayu 0.0700 org
Kepala tukang kayu 0.0080 org
Mandor 0.0080 org
Jumlah

I4 1 M' PASANG NOK Genteng Metal


Nok Genteng Metal Multi Roof 3.0000 Bh
Paku Genteng 0.0100 kg
Pekerja 0.4000 org
Tukang kayu 0.2000 org
Kepala tukang kayu 0.0200 org
Mandor 0.0020 org
Jumlah
K. ANALISA PEKERJAAN KUNCI DAN KAC

K1 1 BH PASANG GERENDEL
Gerendel 1.0000 bh
Pekerja 0.0150 org
Tukang 0.1500 org
Kepala tukang 0.0150 org
Mandor 0.00075 org
Jumlah

K2 1 BH PASANG KUNCI SILINDER


Kunci silinder 1.0000 bh
Pekerja 0.0050 org
Tukang 0.5000 org
Kepala tukang 0.0050 org
Mandor 0.00025 org
Jumlah

K3 1 BH PASANG KUNCI TANAM 1 PUTARAN


Kunci Tanam 1 Putaran 1.0000 bh
Pekerja 0.0050 org
Tukang 0.5000 org
Kepala tukang 0.0050 org
Mandor 0.00025 org
Jumlah

K4 1 BH PASANG KUNCI TANAM 2 PUTARAN


Kunci Tanam 2 Putaran 1.0000 bh
Pekerja 0.0050 org
Tukang 0.5000 org
Kepala tukang 0.0050 org
Mandor 0.00025 org
Jumlah

K5 1 BH PASANG ENGSEL PINTU KUPU - KUPU BESAR


Engsel pintu 1.0000 bh
Pekerja 0.0150 org
Tukang 0.1500 org
Kepala tukang 0.0150 org
Mandor 0.00075 org
Jumlah

K6 1 BH PASANG ENGSEL JENDELA KUPU - KUPU KECIL


Engsel jendela 1.0000 bh
Pekerja 0.0100 org
Tukang 0.1000 org
Kepala tukang 0.0100 org
Mandor 0.00050 org
Jumlah

K7 1 BH PASANG KAIT / HAK ANGIN


kait angin 1.0000 bh
Pekerja 0.0150 org
Tukang 0.0150 org
Kepala tukang 0.0015 org
Mandor 0.00075 org
Jumlah

K8 1 BH PASANG PEGANGAN PINTU / DOOR HOLDER


Door holder 1.0000 bh
Pekerja 0.0500 org
Tukang 0.5000 org
Kepala tukang 0.0500 org
Mandor 0.00250 org
Jumlah

K9 1 BH PASANG HANDLE JENDELA


Handle Jendela 1.0000 bh
Pekerja 0.0150 org
Tukang 0.1500 org
Kepala tukang 0.0150 org
Mandor 0.00075 org
Jumlah

K10 1 M2 PASANG KACA BENING , TEBAL 5 MM


Kaca bening 5 mm 1.0000 m2
Pekerja 0.0150 org
Tukang kayu 0.1500 org
Kepala tukang kayu 0.0150 org
Mandor 0.0008 org
Jumlah

M. ANALISA PEKERJAAN SANITASI


M1 Memasang 1 bh Kloset Duduk Porselin
closet duduk porselin ex toto 1.0000 bh
semen PC 6.0000 kg
pasir pasang 0.0100 m3
Pekerja 1.0000 org
Tukang 1.5000 org
Kepala tukang 1.5000 org
Mandor 0.1600 org
Jumlah

M4 Memasang 1 bh kran 1/2"


Kran 1/2" 1.0000 bh
Seal Tape 0.0250 Bh
Pekerja 0.0100 org
Tukang 0.1000 org
Kepala tukang 0.0100 org
Mandor 0.0050 org
Jumlah

M5 Memasang Bak Mandi Teraso


Bak Mandi Teraso 1.0000 bh
Semen Portland 6.0000 Kg
Pasir Pasang 0.0100 M3
Pekerja 2.1000 org
Tukang 0.7500 org
Kepala tukang 0.0700 org
Mandor 0.1100 org
Jumlah

M7 1 M' Memasang Pipa PVC 1/2"


Pipa PVC 1/2" AW 1.2000 m'
Perlengkapan 35 % x Pipa 1.0000 Bh
Pekerja 0.0360 org
Tukang 0.0600 org
Kepala tukang 0.0060 org
Mandor 0.0018 org
Jumlah

M8 Memasang Stop Kran 1/2"


Stop Kran 1.0000 Bh
Seal Tape 0.0250 Bh
Pekerja 0.0100 org
Tukang 0.1000 org
Kepala tukang 0.0100 org
Mandor 0.0050 org
Jumlah

M10 Memasang Floor Drain


Foor Drain 1.0000 Bh
Pekerja 0.0100 org
Tukang 0.1000 org
Kepala tukang 0.0100 org
Mandor 0.0050 org
Jumlah

M11 Memasang 1 bh kran 1/2"


Kran 1/2" 1.0000 bh
Seal Tape 0.0250 Bh
Pekerja 0.0100 org
Tukang 0.1000 org
Kepala tukang 0.0100 org
Mandor 0.0050 org
Jumlah

M12 Mmasang Pipa PVC 3"


Pipa PVC 1.2000 m'
Perlengkapan 35 % x Pipa 1.0000 Bh
Pekerja 0.0810 org
Tukang 0.1350 org
Kepala tukang 0.0135 org
Mandor 0.0041 org
Jumlah

M13 Mmasang Pipa PVC 4"


Pipa PVC 1.2000 m'
Perlengkapan 35 % x Pipa 1.0000 Bh
Pekerja 0.0810 org
Tukang 0.1350 org
Kepala tukang 0.0135 org
Mandor 0.0041 org
Jumlah
ISA PEKERJAAN

HARGA SAT HARGA BAHAN HARGA UPAH JUMLAH

5 6 7 8

AAN PERSIAPAN / PENDAHULUAN

165,000.00 16,500.00 16,500.00


135,000.00 13,500.00 13,500.00
200,000.00 10,000.00 10,000.00
0.00 23,500.00 40,000.00

2,600,000.00 31,200.00 31,200.00


18,500.00 370.00 370.00
2,600,000.00 18,200.00 18,200.00
135,000.00 13,500.00 13,500.00
135,000.00 13,500.00 13,500.00
180,000.00 1,800.00 1,800.00
200,000.00 1,000.00 1,000.00
49,770.00 29,800.00 79,570.00

25,000.00 42,500.00 42,500.00


2,600,000.00 546,000.00 546,000.00
18,500.00 5,550.00 5,550.00
5,500.00 57,750.00 57,750.00
395,000.00 11,850.00 11,850.00
507,000.00 25,350.00 25,350.00
125,000.00 187,500.00 187,500.00
135,000.00 135,000.00 135,000.00
135,000.00 270,000.00 270,000.00
180,000.00 36,000.00 36,000.00
200,000.00 10,000.00 10,000.00
876,500.00 451,000.00 1,327,500.00

KERJAAN PONDASI / TANAH

135,000.00 101,250.00 101,250.00


200,000.00 5,000.00 5,000.00
0.00 106,250.00 106,250.00
135,000.00 121,500.00 121,500.00
200,000.00 9,000.00 9,000.00
130,500.00 130,500.00

135,000.00 25,920.00 25,920.00


200,000.00 3,800.00 3,800.00
25,000.00 0.00 0.00
0.00 29,720.00 29,720.00

75,000.00 90,000.00 90,000.00


135,000.00 40,500.00 40,500.00
200,000.00 2,000.00 2,000.00
90,000.00 42,500.00 132,500.00

135,000.00 67,500.00 67,500.00


200,000.00 10,000.00 10,000.00
0.00 77,500.00 77,500.00

125,000.00 150,000.00 150,000.00


135,000.00 40,500.00 40,500.00
200,000.00 2,000.00 2,000.00
150,000.00 42,500.00 192,500.00

5,900,000.00 118,000.00 118,000.00


135,000.00 27,945.00 27,945.00
135,000.00 36,450.00 36,450.00
180,000.00 27,000.00 27,000.00
200,000.00 18,000.00 18,000.00
118,000.00 109,395.00 227,395.00

5,900,000.00 5,900,000.00 5,900,000.00


18,500.00 18,500.00 18,500.00
135,000.00 675,000.00 675,000.00
135,000.00 2,025,000.00 2,025,000.00
180,000.00 270,000.00 270,000.00
200,000.00 50,000.00 50,000.00
5,918,500.00 3,020,000.00 8,938,500.00
5,900,000.00 6,490,000.00 6,490,000.00
22,500.00 22,500.00 22,500.00
135,000.00 675,000.00 675,000.00
135,000.00 2,025,000.00 2,025,000.00
180,000.00 270,000.00 270,000.00
200,000.00 50,000.00 50,000.00
6,512,500.00 3,020,000.00 9,532,500.00

5,900,000.00 6,490,000.00 6,490,000.00


22,500.00 45,000.00 45,000.00
135,000.00 675,000.00 675,000.00
135,000.00 2,025,000.00 2,025,000.00
180,000.00 270,000.00 270,000.00
200,000.00 50,000.00 50,000.00
6,535,000.00 3,020,000.00 9,555,000.00

5,900,000.00 708,000.00 708,000.00


135,000.00 27,945.00 27,945.00
135,000.00 36,450.00 36,450.00
180,000.00 27,000.00 27,000.00
200,000.00 18,000.00 18,000.00
708,000.00 109,395.00 817,395.00

450,000.00 540,000.00 540,000.00


125,000.00 37,500.00 37,500.00
135,000.00 105,300.00 105,300.00
135,000.00 52,650.00 52,650.00
180,000.00 7,020.00 7,020.00
200,000.00 7,800.00 7,800.00
577,500.00 172,770.00 750,270.00

450,000.00 495,000.00 495,000.00


98,000.00 15,974,000.00 15,974,000.00
395,000.00 205,400.00 205,400.00
135,000.00 202,500.00 202,500.00
135,000.00 81,000.00 81,000.00
180,000.00 10,800.00 10,800.00
200,000.00 15,000.00 15,000.00
16,674,400.00 309,300.00 16,983,700.00
A PEKERJAAN BETON

98,000.00 21,364,000.00 21,364,000.00


395,000.00 205,400.00 205,400.00
507,000.00 441,090.00 441,090.00
135,000.00 222,750.00 222,750.00
135,000.00 33,750.00 33,750.00
180,000.00 4,500.00 4,500.00
200,000.00 16,000.00 16,000.00
22,010,490.00 277,000.00 22,287,490.00

32,000.00 33,600.00 33,600.00


25,000.00 375.00 375.00
135,000.00 945.00 945.00
135,000.00 945.00 945.00
180,000.00 126.00 126.00
200,000.00 60.00 60.00
33,975.00 2,076.00 36,051.00

2,600,000.00 104,000.00 104,000.00


18,500.00 5,550.00 5,550.00
20,500.00 2,050.00 2,050.00
135,000.00 70,200.00 70,200.00
135,000.00 35,100.00 35,100.00
180,000.00 4,680.00 4,680.00
200,000.00 5,200.00 5,200.00
111,600.00 115,180.00 226,780.00
BAHAN 2X PAKAI 170,980.00

2,600,000.00 117,000.00 117,000.00


18,500.00 5,550.00 5,550.00
20,500.00 2,050.00 2,050.00
135,000.00 70,200.00 70,200.00
135,000.00 35,100.00 35,100.00
180,000.00 4,680.00 4,680.00
200,000.00 5,200.00 5,200.00
124,600.00 115,180.00 239,780.00
BAHAN 2X PAKAI 177,480.00

2,600,000.00 104,000.00 104,000.00


18,500.00 7,400.00 7,400.00
20,500.00 4,100.00 4,100.00
135,000.00 2,025.00 2,025.00
165,000.00 57,750.00 57,750.00
25,000.00 50,000.00 50,000.00
135,000.00 89,100.00 89,100.00
135,000.00 44,550.00 44,550.00
180,000.00 5,940.00 5,940.00
200,000.00 6,600.00 6,600.00
225,275.00 146,190.00 371,465.00
BAHAN 2X PAKAI 258,827.50

2,600,000.00 117,000.00 117,000.00


18,500.00 5,550.00 5,550.00
20,500.00 2,050.00 2,050.00
135,000.00 40,500.00 40,500.00
135,000.00 35,100.00 35,100.00
180,000.00 4,680.00 4,680.00
200,000.00 1,000.00 1,000.00
124,600.00 81,280.00 205,880.00
BAHAN 2X PAKAI 143,580.00

0.00 0.00
18,500.00 7,400.00 7,400.00
20,500.00 4,100.00 4,100.00
3,100,000.00 43,400.00 43,400.00
25,000.00 150,000.00 150,000.00
198,000.00 69,300.00 69,300.00
135,000.00 43,200.00 43,200.00
135,000.00 44,550.00 44,550.00
180,000.00 5,940.00 5,940.00
200,000.00 1,200.00 1,200.00
274,200.00 94,890.00 369,090.00
BAHAN 2X PAKAI 231,990.00

0.00 0.00
18,500.00 7,400.00 7,400.00
20,500.00 4,100.00 4,100.00
3,100,000.00 43,400.00 43,400.00
25,000.00 0.00 0.00
198,000.00 69,300.00 69,300.00
135,000.00 43,200.00 43,200.00
135,000.00 44,550.00 44,550.00
180,000.00 5,940.00 5,940.00
200,000.00 1,200.00 1,200.00
124,200.00 94,890.00 219,090.00
BAHAN 2X PAKAI 156,990.00
2,600,000.00 104,000.00 104,000.00
18,500.00 7,400.00 7,400.00
20,500.00 4,100.00 4,100.00
2,600,000.00 46,800.00 46,800.00
25,000.00 50,000.00 50,000.00
198,000.00 69,300.00 69,300.00
135,000.00 43,200.00 43,200.00
135,000.00 44,550.00 44,550.00
180,000.00 5,940.00 5,940.00
200,000.00 1,200.00 1,200.00
281,600.00 94,890.00 376,490.00
BAHAN 2X PAKAI 235,690.00

98,000.00 37,632,000.00 37,632,000.00


395,000.00 196,935.71 196,935.71
507,000.00 294,905.00 294,905.00
135,000.00 222,750.00 222,750.00
135,000.00 37,125.00 37,125.00
180,000.00 5,040.00 5,040.00
200,000.00 16,600.00 16,600.00
38,123,840.71 281,515.00 38,405,355.71

170,980.00 7,181,160.00 7,181,160.00


36,051.00 68,893,461.00 68,893,461.00
38,405,355.71 564,558,729.00 564,558,729.00
640,633,350.00 640,633,350.00
ume cor beton 43,580,500.00

177,480.00 20,339,208.00 20,339,208.00


36,051.00 28,920,112.20 28,920,112.20
38,405,355.71 440,125,376.49 440,125,376.49
489,384,696.69 489,384,696.69
ume cor beton 42,703,725.71

177,480.00 7,809,120.00 7,809,120.00


36,051.00 16,655,562.00 16,655,562.00
38,405,355.71 126,737,673.86 126,737,673.86
151,202,355.86 151,202,355.86
ume cor beton 45,818,895.71

235,690.00 71,923,749.63 71,923,749.63


36,051.00 158,420,351.34 158,420,351.34
38,405,355.71 1,054,788,692.68 1,054,788,692.68
1,285,132,793.65 1,285,132,793.65
ume cor beton 46,792,293.49

37,125.00 5,658,314.06 5,658,314.06


36,051.00 42,198,704.93 42,198,704.93
38,405,355.71 280,965,901.33 280,965,901.33
328,822,920.33 328,822,920.33
ume cor beton 44,946,953.21

235,690.00 10,629,619.00 10,629,619.00


36,051.00 17,311,894.49 17,311,894.49
38,405,355.71 94,477,175.06 94,477,175.06
122,418,688.55 122,418,688.55
ume cor beton 49,763,694.53

235,690.00 4,562,958.40 4,562,958.40


36,051.00 7,431,447.39 7,431,447.39
38,405,355.71 40,556,055.63 40,556,055.63
52,550,461.42 52,550,461.42
ume cor beton 49,763,694.53

258,827.50 45,553,640.00 45,553,640.00


36,051.00 88,829,664.00 88,829,664.00
38,405,355.71 675,934,260.57 675,934,260.57
810,317,564.57 810,317,564.57
ume cor beton 46,040,770.71

258,827.50 13,200,202.50 13,200,202.50


36,051.00 19,305,310.50 19,305,310.50
38,405,355.71 146,900,485.61 146,900,485.61
179,405,998.61 179,405,998.61
ume cor beton 46,903,529.05

231,990.00 28,534,770.00 28,534,770.00


36,051.00 63,853,531.20 63,853,531.20
38,405,355.71 566,863,050.34 566,863,050.34
659,251,351.54 659,251,351.54
ume cor beton 44,664,725.71

N KERAMIK DAN PENUTUP DINDING

Per m2 #VALUE! #VALUE!


Per kg #VALUE! #VALUE!
Per m3 #VALUE! #VALUE!
Per kg #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per m2 #VALUE! #VALUE!


Per kg #VALUE! #VALUE!
Per m3 #VALUE! #VALUE!
Per kg #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

0.00 0.00 0.00


Per kg #VALUE! #VALUE!
Per m3 #VALUE! #VALUE!
Per kg #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

PEKERJAAN DINDING

Per bh #VALUE! #VALUE!


Per kg #VALUE! #VALUE!
Per m3 #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per bh #VALUE! #VALUE!


Per kg #VALUE! #VALUE!
Per m3 #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per bh #VALUE! #VALUE!


Per kg #VALUE! #VALUE!
Per m3 #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per kg #VALUE! #VALUE!


Per m3 #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per kg #VALUE! #VALUE!


Per m3 #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per kg #VALUE! #VALUE!


Per m3 #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per kg #VALUE! #VALUE!


Per m3 #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

SA PEKERJAAN CAT
PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP )
Per kg #VALUE! #VALUE!
Per kg #VALUE! #VALUE!
Per kg #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

LAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP )


Per kg #VALUE! #VALUE!
Per kg #VALUE! #VALUE!
Per kg #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per kg #VALUE! #VALUE!


Per kg #VALUE! #VALUE!
Per kg #VALUE! #VALUE!
Per kg #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per kg #VALUE! #VALUE!


Per lt #VALUE! #VALUE!
Per Lbr #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per lt #VALUE! #VALUE!


Per kg #VALUE! #VALUE!
Per kg #VALUE! #VALUE!
Per Lbr #VALUE! #VALUE!
Per Kg #VALUE! #VALUE!
Per lt #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

A PEKERJAAN PLAFON
URAN 1 X 1 M' )
8,750.00 35,000.00 35,000.00
7,500.00 7,500.00 7,500.00
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
42,500.00 #VALUE! #VALUE!
ENUTUP PADA RANGKA
Per Lbr #VALUE! #VALUE!
Per kg #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per M' #VALUE! #VALUE!


Per kg #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

KUSEN & DAUN PINTU


en jendela
Per m3 #VALUE! #VALUE!

Per kg #VALUE! #VALUE!

Per Kg #VALUE! #VALUE!


Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!

Orang Per Hari #VALUE! #VALUE!


Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
102.56 0.01 #VALUE!

#VALUE! #VALUE!
Per m3
#VALUE! #VALUE!
Per Kg
Orang Per Hari #VALUE! #VALUE!

#VALUE! #VALUE!

Orang Per Hari


#VALUE! #VALUE!
Orang Per Hari
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

#VALUE! #VALUE!
Per m3
#VALUE! #VALUE!
Per Kg
Orang Per Hari #VALUE! #VALUE!

#VALUE! #VALUE!

Orang Per Hari


#VALUE! #VALUE!
Orang Per Hari
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per Lbr #VALUE! #VALUE!


Per kg
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

A PEKERJAAN ATAP

12,500.00 81,250.00 81,250.00


9,500.00 85,500.00 85,500.00
6,600.00 6,600.00 6,600.00
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per Lbr #VALUE! #VALUE!


Per kg #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per Lbr #VALUE! #VALUE!


Per kg #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per Bh #VALUE! #VALUE!


Per kg #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
KERJAAN KUNCI DAN KACA

Per bh #VALUE! #VALUE!


Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per bh #VALUE! #VALUE!


Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per bh #VALUE! #VALUE!


Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per bh #VALUE! #VALUE!


Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per bh #VALUE! #VALUE!


Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per bh #VALUE! #VALUE!


Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per bh #VALUE! #VALUE!


Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per bh #VALUE! #VALUE!


Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per bh #VALUE! #VALUE!


Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per m2 #VALUE! #VALUE!


Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

A PEKERJAAN SANITASI

Per bh #VALUE! #VALUE!


Per kg #VALUE! #VALUE!
Per m3 #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per bh #VALUE! #VALUE!


Per bh #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per bh #VALUE! #VALUE!


Per kg #VALUE! #VALUE!
Per m3 #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per m' #VALUE! #VALUE!


#VALUE! #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per bh #VALUE! #VALUE!


Per bh #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per bh #VALUE! #VALUE!


Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per bh #VALUE! #VALUE!


Per bh #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per m' #VALUE! #VALUE!


#VALUE! #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

Per m' #VALUE! #VALUE!


#VALUE! #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
Orang Per Hari #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
DAFTAR HARGA SATUAN UPAH TENAGA, SATUAN BAHAN & PERALATAN

LOKASI : Jl. ......................................, Samarinda


TAHUN : 2013

MACAM
NO.
BAHAN/ALAT
01 02

A. MACAM TENAGA
1 Kepala Tukang Kayu
2 Kepala Tukang Batu
3 Kepala Tukang Besi
4 Mandor
5 Operator
6 Pekerja Batu
7 Pekerja Besi
8 Pekerja Kayu
9 Tukang Batu
10 Tukang Besi
11 Tukang Kayu

B. MACAM ALAT
1 Jack Hammer
2 Genset
3 Molen
4 Concrete Pump
5 Concrete Vibrator
6 Curing Beton
7 Alat Pancang Beton

C. MACAM BAHAN
1 Alkali
2 Amplas / Ampril / kertas gosok
3 Baja Profil
4 Bak Mandi Teraso
5 Bak Cuci Stainliss
6 Batchup
7 Batu Bata Herbel
8 Batu gunung ( gebal/besar )
9 Batu Alam
10 Batu Kumbung
11 Bendrad
12 Besi beton polos/Ulir
13 Besi strip
14 Besi profil
15 Besi / Kawat Berduri
16 Box Meteran Listrik
17 Cincin Pipa Besi Ø 4" Tebal 5mm-20cm
18 Cat tembok dalam setara mowilex
19 Cat tembok luar setara mowilex
20 Cat tembok dasar setara mowilex
21 Cat kayu besi setara aftelak
22 Cat kayu besi setara mowilex
23 Cat M e n y kayu / besi setara nippon
24 Cat M e n y kayu setara nippon
25 Cat Clear Doof
26 Closet jongkok ex toto
27 Closet duduk ex toto
28 Urinoir Ex toto
29 Wastafel komplit kaca & asesories Ex Toto
30 Dempul
31 Engsel jendela 3"
32 Engsel pintu 4"
33 Fiber Bergelombang
34 Floor drain
35 Genteng Keramik
36 Genteng Nok Metal
37 Genteng Metal 2 susun setara sakura elang
38 Gerendel jendela / bouvenlist
39 Gypsum Board 9 mm
40 Gypsum List
41 GRC BOARD
42 Kabel NYY 2,5 mm
43 Kaca bening t = 5 mm
44 Kaca bening Frameless t = 12 mm
45 Kaca riben t = 5 mm
46 Kait Angin / Hak Angin
47 Kasa
48 Kayu bangkirai Papan 2/10
49 Kayu Bangkirai Balok 5/7, 6/12, 8/12
50 Kayu Bangkirai Listpalnk
51 Kayu Kapur Papan 2/10
52 Kayu Kapur Balok 5/7, 6/12, 8/12
53 Kayu Kapur / Bangkirai Lumber Siring
54 Kayu meranti Balok 5/7
55 Kayu Meranti Papan 3/20, 2/20
56 Kayu Meranti Bouwplank / Begesting
57 ( Kayu perancah / perancah d 8 cm panjang 4 m )
58 Kayu Ulin Balok 10/10
59 Kayu Ulin Papan 3/30
60 Keramik Dinding 20 x 25 cm ex. Roman
61 Keramik lantai 20 x 20 cm ex. Roman
62 Keramik lantai 30 x 30 cm ex. Roman
63 Keramik lantai 40 x 40 cm ex. Roman
64 Keramik list dinding 10 x 20 cm ex. Roman
65 Keramik list dinding 10 x 40 cm ex. Roman
66 Keramik lantai 40 x 40 cm ex. Ezenza
67 Keramik lantai 30 x 30 cm ex. Ezenza
68 Koral Beton
69 Kran air / stop k 1/2"
70 Kuas 2,5"
71 Kunci Tanam 1 putaran untuk wc/km
72 Kunci Tanam 2 putaran
73 Kunci Silinder sekualitas ELT
74 Kusen pintu/jendela aluminium
75 Lampu TL Philips 2 x 20 Watt
76 Lampu Gantung TL Philips 2 x 20 Watt
77 Lampu TL Philips 2 x 40 Watt
78 Lampu XL Philips 10 Watt
79 Lampu XL Philips 18 Watt
80 Lem Kayu (Fox)
81 Minyak Begesting
82 Minyak Cat / Tiner A
83 Nok/kerpus atap multi roof
84 Nok/kerpus atap Fiberglass
85 Paku Biasa
86 Paku Baut
87 Paku Gypsum ( Paku sekrup )
88 Paku Genteng Metal
89 Paku Plywood 1,5 mm
90 Pasir beton / palu
91 Pasir pasang Tenggarong
92 Pasir urug Mahakam
93 Paving Blok
94 Pegangan / Handle Jendela
95 Pegangan / Door Holder
96 Penyekat Urinoir
97 Pipa pralon PVC dia. 4" AW
98 Pipa pralon PVC dia. 3" AW
99 Pipa pralon PVC dia. 2" AW
100 Pipa pralon PVC dia. 3/4" AW
101 Pipa pralon PVC dia. 1/2"
102 Pipa pralon untuk listrik
103 Plamir kayu
104 Plastik cor
105 Plywood/ tripleks tb. 4 mm
106 Plywood/ tripleks tb. 9 mm
107 Plywood/ tripleks tb. 12 mm
108 Plywood/ tripleks sungkai
109 Rangka Atap Baja Ringan
110 Residu
111 Saklar Tunggal
112 Saklar Double
113 Saklar Triple
114 Sambungan Tiang Pancang Kayu / Shock 4"
115 Sambungan Tiang Pancang Beton / Las
116 Sanding Sailer
117 Seal Tape
118 Sekring Lokal
119 Semen Portland @ 50 Kg
120 Semen Portland
121 Semen warna
122 Seng gelombang 0,8 x 2,10 BJLS 30 ( Zincalume )
123 Seng gelombang 0,8 x 2,10 BJLS 20
124 Seng gelombang 0,8 x 2,10 BJLS 18
125 Stop Kontak
126 Talang seng t=0.2 mm, L=60 cm
127 T Dos
128 T a n a h Urug
129 Tiang Pancang □ 20 x 20 K-450
130 Water Proofing
131 Wood Filler
132 Wood Stain (pewarna)
NAGA, SATUAN BAHAN & PERALATAN

HARGA
SATUAN
SATUAN Rp.
03 04

Orang Per Hari Rp 180,000.00


Orang Per Hari Rp 180,000.00
Orang Per Hari Rp 180,000.00
Orang Per Hari Rp 200,000.00
Orang Per Hari Rp 180,000.00
Orang Per Hari Rp 135,000.00
Orang Per Hari Rp 135,000.00
Orang Per Hari Rp 135,000.00
Orang Per Hari Rp 165,000.00
Orang Per Hari Rp 165,000.00
Orang Per Hari Rp 165,000.00

Hari Rp 165,000.00
Hari Rp 250,000.00
Hari Rp 450,000.00
Jam
Jam
Jam
Jam

Per Kg Rp 65,000.00
Per Lbr Rp 7,000.00
Per Kg Rp 450,000.00
Per bh Rp 1,150,000.00
Per bh Rp 950,000.00
Per bh Rp 1,000,000.00
Per bh Rp 8,000.00
Per m3 Rp 450,000.00
Per M2 Rp 175,000.00
Per Bh Rp 15,000.00
Per kg Rp 25,000.00
Per kg Rp 32,000.00
Per kg Rp 27,000.00
Per kg Rp 22,000.00
Per kg Rp 450,000.00
Per Bh Rp 150,000.00
Per Bh Rp 35,000.00
Per kg Rp 55,000.00
Per kg Rp 75,000.00
Per kg Rp 50,000.00
Per kg Rp 45,000.00
Per kg Rp 65,000.00
Per kg Rp 35,000.00
Per kg Rp 15,000.00
Per lt Rp 125,000.00
Per bh Rp 850,000.00
Per bh Rp 1,500,000.00
Per bh Rp 3,500,000.00
Per bh Rp 3,500,000.00
Per kg Rp 18,000.00
Per bh Rp 55,000.00
Per bh Rp 65,000.00
Per Lbr Rp 85,000.00
Per bh Rp 150,000.00
Per Bh Rp 20,000.00
Per Bh Rp 45,000.00
Per Lbr Rp 75,000.00
Per bh Rp 37,500.00
Per Lbr Rp 125,000.00
Per M' Rp 35,500.00
Per Lbr Rp 85,500.00
Per Rol Rp 250,000.00
Per m2 Rp 120,000.00
Per m2 Rp 275,000.00
Per m2 Rp 153,750.00
Per bh Rp 35,000.00
Per M' Rp 5,000.00
Per m3 Rp 6,000,000.00
Per m3 Rp 5,500,000.00
Per m' Rp 67,000.00
Per m3 Rp 4,200,000.00
Per m3 Rp 3,900,000.00
Per Lbr Rp 55,500.00
Per m3 Rp 3,100,000.00
Per m3 Rp 2,900,000.00
Per m3 Rp 2,600,000.00
Per Btg Rp 25,000.00
Per m3 Rp 5,900,000.00
Per m3 Rp 6,500,000.00
Per m2 Rp 90,280.00
Per m2 Rp 90,280.00
Per m2 Rp 90,280.00
Per m2 Rp 20,180.00
Per bh Rp 35,000.00
Per bh Rp 45,000.00
Per m2 Rp 220,100.00
Per m2 Rp 220,100.00
Per m3 Rp 507,000.00
Per bh Rp 125,500.00
Per bh Rp 12,500.00
Per bh Rp 180,950.00
Per bh Rp 320,000.00
Per bh Rp 210,750.00
Per m' Rp 275,000.00
Per bh Rp 175,000.00
Per bh Rp 225,000.00
Per bh Rp 275,000.00
Per bh Rp 37,250.00
Per bh Rp 42,500.00
Per Kg Rp 30,000.00
Per lt Rp 20,500.00
Per lt Rp 28,500.00
Per bh Rp 30,750.00
Per bh Rp 42,500.00
Per kg Rp 18,500.00
Per Bh Rp 12,000.00
Per kg Rp 32,500.00
Per kg Rp 32,500.00
Per kg Rp 22,500.00
Per m3 Rp 395,000.00
Per m3 Rp 395,000.00
Per m3 Rp 125,000.00
Per Bh Rp 7,500.00
Per bh Rp 55,000.00
Per bh Rp 75,000.00
Per bh Rp 395,000.00
Per m' Rp 110,000.00
Per m' Rp 100,000.00
Per m' Rp 95,000.00
Per m' Rp 55,000.00
Per m' Rp 55,000.00
Per m' Rp 10,000.00
Per kg Rp 75,000.00
Per m2 Rp 7,500.00
Per lb Rp 95,000.00
Per lb Rp 165,000.00
Per lb Rp 198,000.00
Per lb Rp 135,000.00
Per M2 Rp 450,000.00
Per ltr Rp 20,500.00
Per bh Rp 35,000.00
Per bh Rp 65,000.00
Per bh Rp 85,000.00
Per bh Rp 65,700.00
Per Titik Rp 75,000.00
Per Kg Rp 37,500.00
Per bh Rp 12,500.00
Per bh Rp 82,500.00
Per kg Rp 5,500.00
Per Zak Rp 98,000.00
Per kg Rp 12,500.00
Per lb Rp 125,000.00
Per lb Rp 56,750.00
Per lb Rp 47,500.00
Per bh Rp 35,000.00
Per m' Rp 20,500.00
Per bh Rp 18,750.00
Per m3 Rp 75,000.00
Per m' Rp 20,500.00
Per m2 Rp 185,000.00
Per kg Rp 47,800.00
Per kg Rp 45,000.00