Professional Documents
Culture Documents
Anexo 1
Anexo 1
Summary
Equipment Database
Standard 2014,(USA Avg)
Layout Summary
Description Value Units
CONSTRUCTION
COSTS
Unit process construction $8,530,000 $
costs
Other direct construction $5,690,000 $
costs
Other indirect $2,200,000 $
construction costs
Total construction costs $16,400,000 $
ANNUAL COSTS
LABOR COSTS
Administration labor cost $6,700 $/yr
Laboratory labor cost $9,000 $/yr
Unit process operation $52,200 $/yr
labor cost
Unit process maintenance $12,000 $/yr
labor cost
Total labor costs $79,900 $/yr
MATERIAL COSTS
Total material cost $251,000 $/yr
CHEMICAL COSTS
Total chemical cost $163,000 $/yr
ENERGY COSTS
Total energy cost $339,000 $/yr
CONSTRUCTION
COST
AMORTIZATION
Amortization cost for $864,000 $/yr
total construction cost
PROJECT SUMMARY
Present worth $39,200,000 $
Total project cost $16,400,000 $
Total operation labor cost $67,900 $/yr
Total maintenance labor $12,000 $/yr
cost
Total material cost $251,000 $/yr
Total chemical cost $163,000 $/yr
Total energy cost $339,000 $/yr
Total amortization cost $864,000 $/yr
Process Summary
Process Construction Operation Maintenance Material Chemical Energy Amortizatio
($) ($/yr) ($/yr) ($/yr) ($/yr) ($/yr) n ($/yr)
Preliminary 288000 3220 1370 15600 0 3560 27000
Treatment
Influent 1090000 2180 1470 7610 0 24400 57000
Pump
Station
Complete 4060000 8640 4220 93100 0 238000 229000
Mix
Activated
Sludge
Secondary 745000 4440 2180 7300 0 2170 40000
Clarifier(1)
Ultra-Violet 134000 0 738 1340 4360 34400 38300
Disinfection
Gravity Belt 357000 1580 316 0 79100 12600 18000
Thickener
Effluent 0 0 0 0 0 0 0
Screw Press 807000 29400 1680 22000 79400 24800 27500
Hauling and 374000 2690 0 104000 0 0 56100
Land Filling
Blower 679000 0 0 0 0 0 29400
System
Other Costs 7890000 15700 0 0 0 0 341000
INDIRECT COSTS
Cost of land 0 $
Miscellaneous cost 14900 $
Legal cost 14900 $
Engineering design fee 448000 $
Inspection cost 14900 $
Contingency 747000 $
Technical 14900 $
Interest during construction 232000 $
Profit 711000 $
Total indirect construction costs 2200000 $
LABOR COSTS
Administration labor cost 6700 $/yr
Laboratory labor cost 9000 $/yr
Influent Wastewater
Water Quality Data
Parameter Influent Effluent Units
Maximum flow 33700 33700 m3/d
Minimum flow 13000 13000 m3/d
Average flow 17300 17300 m3/d
Suspended solids 621 621 g/m3
% volatile solids 85.0 85.0 %
BOD 276 276 g/m3
Soluble BOD 110 110 g/m3
COD 556 556 g/m3
Soluble COD 222 222 g/m3
TKN 41.4 41.4 gN/m3
Soluble TKN 24.8 24.8 gN/m3
Ammonia 24.8 24.8 gN/m3
Nitrite 0.0 0.0 gN/m3
Nitrate 0.0 0.0 gN/m3
Total phosphorus 11.0 11.0 gP/m3
pH 7.5 7.5 -
Cations 160 160 g/m3
Anions 160 160 g/m3
Settleable solids 10.0 10.0 g/m3
Oil and grease 100 100 g/m3
Summer temperature 19.5 19.5 deg C
Winter temperature 19.5 19.5 deg C
Preliminary Treatment
Design Output Data
Description Value Units
Preliminary Treatment
Design Information
Mechanically Cleaned Bar Screen
Bar size 0.636 cm
Bar spacing 0.6 cm
Slope of bars from horizontal 30.0 degrees
Head loss through screen NaN m
Approach velocity 0.5 m/s
Average flow through velocity 0.8 m/s
(screen)
Maximum flow through velocity 0.9 m/s
(screen)
Screen channel width 0.816 m
Average channel depth 0.305 m
Horizontal Flow Grit Chamber
Maximum flow 33500 m3/d
Average flow 17200 m3/d
Minimum flow 12900 m3/d
Temperature 19.5 deg C
Maximum flow through velocity 0.457 m/s
(grit chamber)
Average flow through velocity 0.305 m/s
(grit chamber)
Size of smallest particle 100% 0.02 cm
removed
Specific gravity of particle 2.65
Number of units 2.0
Maximum flow/unit 16800 m3/d
Width of channel 0.348 m
Depth of channel 1.22 m
Length of channel 36.5 m
Settling velocity of particle 0.026 m/s
Slope of channel bottom 0.00146
Allowance for currents 1.7
Manning coefficient 0.035
Hydraulic retention time 1.33 min
Volume of grit 0.517 m3/d
Costs
Construction and equipment cost Overridden
Operational labor cost 3220 $/yr
Maintenance labor cost 1370 $/yr
Material and supply cost 15600 $/yr
Chemical cost 0 $/yr
Energy cost 3560 $/yr
Amortization cost 27000 $/yr
Secondary Clarifier(1)
Design Output Data
Description Value Units
Secondary Clarification
Design Information
Surface area 1120 m2
Surface area per circular clarifier 560 m2
Diameter of each circular clarifier 26.8 m
Number of clarifiers per battery 2.0
Number of batteries 1.0
Solids loading rate 114 kg/(m2·d)
Hydraulic retention time 6.62 hr
Designed surface overflow rate 16.3 m3/(m2·d)
Weir length 186 m
Volume of wasted sludge 1050 m3/d
Quantities
Operation labor required 1150 pers-hrs/yr
Maintenance labor required 632 pers-hrs/yr
Electrical energy required 10400 kWh/yr
Volume of earthwork required 4480 m3
Slab thickness 29.5 cm
Volume of slab concrete required 382 m3
Wall thickness 36.6 cm
Volume of wall concrete required 311 m3
Costs
Construction and equipment cost 695000 $
Earthwork Cost 224000 $
Wall Concrete Cost 72500 $
Slab Concrete Cost 43900 $
Installed Equipment Cost 249000 $
Misc Costs 106000 $
Operational labor cost 3350 $/yr
Maintenance labor cost 1480 $/yr
Material and supply cost 6950 $/yr
Chemical cost 0 $/yr
Energy cost 1150 $/yr
Amortization cost 37100 $/yr
Waste Sludge Pumping
Design Information
Average daily pumping rate 1050 m3/d
Total pumping capacity 1050 m3/d
Design capacity per pump 525 m3/d
Number of pumps 3.0
Number of batteries 1.0
Firm pumping capacity 1050 m3/d
Quantities
Operation labor required 373 pers-hrs/yr
Maintenance labor required 298 pers-hrs/yr
Electrical energy required 9320 kWh/yr
Volume of earthwork required 46.5 m3
Area of pump building 19.1 m2
Costs
Construction and equipment cost 49900 $
Earthwork Cost 2330 $
Pump Building Cost 12100 $
Installed Pump Cost 27900 $
Misc Costs 7610 $
Operational labor cost 1090 $/yr
Maintenance labor cost 697 $/yr
Material and supply cost 349 $/yr
Chemical cost 0 $/yr
Energy cost 1030 $/yr
Amortization cost 2920 $/yr
Ultra-Violet Disinfection
Design Output Data
Description Value Units
Ultra-Violet Disinfection
Design Information
Design based on a model 0.00425 m3/(min·W)
calculated UV loading
Total number of lamps needed for 368
disinfection
Number of spare channels 1.0
Total number of lamps used in 420
optimum design
Number of excess lamps 52.0
Number of lamps/modules 2.0
Number of modules/bank 3.0
Number of banks/channel 7.0
Number of channels 10.0
Calculated headloss 141 cm
Costs
Construction and equipment cost 134000 $
Cost of installation 80500 $
Total cost of UV lamps 53700 $
Operational labor cost 0 $/yr
Maintenance labor cost 738 $/yr
Material and supply cost 1340 $/yr
Chemical cost 4360 $/yr
Energy cost 34400 $/yr
Amortization cost 38300 $/yr
Effluent
Design Output Data
Description Value Units
Costs
Construction and equipment cost 0 $
Operational labor cost 0 $/yr
Maintenance labor cost 0 $/yr
Material and supply cost 0 $/yr
Chemical cost 0 $/yr
Energy cost 0 $/yr
Amortization cost 0 $/yr
Screw Press
Design Output Data
Description Value Units
Screw Press
Design Information
Total power required 34.7 kW
Power required per unit 34.7 kW
Excess capacity factor 1.25
Number of units 1.0
Chemical dose 1.0 % dry wt
Chemicals required 107 kg/d
Sludge flow 203 m3/d
Initial solid conc 5.0 %
Operational hours per day 20.0 hr
Operational days per week 6.0 d
Quantities
Number of Screw Press 1.0
Power required per unit 34.7 kW
Area of building 18.6 m2
Dry solids produced 7250 kg/d
Operation labor required 4290 pers-hrs/yr
Maintenance labor required 718 pers-hrs/yr
Electrical energy required 226000 kWh/yr
Costs
Construction and equipment cost 435000 $
Operational labor cost 12500 $/yr
Maintenance labor cost 1680 $/yr
Material and supply cost 14600 $/yr
Chemical cost 0 $/yr
Energy cost 24800 $/yr
Amortization cost 27500 $/yr
Polymer Feed System
Quantities
Polymer dosage 88.9 kg/d
Liquid chemical solution fed 35.6 m3/d
O&M labor required 4560 pers-hrs/yr
Dry material handling and mixing 1230 pers-hrs/yr
labor required
Total operation labor required 5790 pers-hrs/yr
Costs
Construction and equipment cost 372000 $
Operational labor cost 16900 $/yr
Maintenance labor cost 0 $/yr
Material and supply cost 7450 $/yr
Chemical cost 79400 $/yr
Energy cost 0 $/yr
Amortization cost 0 $/yr
Summary
Equipment Database
Hydromantis 2014,(USA Avg)
Layout Summary
Description Value Units
CONSTRUCTION
COSTS
Unit process construction $7,330,000 $
costs
Other direct construction $5,690,000 $
costs
Other indirect $2,010,000 $
construction costs
Total construction costs $15,000,000 $
ANNUAL COSTS
LABOR COSTS
Administration labor cost $6,700 $/yr
Laboratory labor cost $9,000 $/yr
Unit process operation $90,300 $/yr
labor cost
Unit process maintenance $15,700 $/yr
labor cost
Total labor costs $122,000 $/yr
MATERIAL COSTS
Total material cost $229,000 $/yr
CHEMICAL COSTS
Total chemical cost $271,000 $/yr
ENERGY COSTS
Total energy cost $191,000 $/yr
CONSTRUCTION
COST
AMORTIZATION
Amortization cost for $768,000 $/yr
total construction cost
PROJECT SUMMARY
Present worth $36,500,000 $
Total project cost $15,000,000 $
Total operation labor cost $106,000 $/yr
Total maintenance labor $15,700 $/yr
cost
Total material cost $229,000 $/yr
Total chemical cost $271,000 $/yr
Total energy cost $191,000 $/yr
Total amortization cost $768,000 $/yr
Process Summary
Process Construction Operation Maintenance Material Chemical Energy Amortizatio
($) ($/yr) ($/yr) ($/yr) ($/yr) ($/yr) n ($/yr)
Preliminary 288000 3220 1400 15600 0 3560 27000
Treatment
Influent 1090000 2190 1510 7620 0 24700 57000
Pump
Station
Upflow 1680000 30000 4870 30600 0 19000 76500
Anaerobic
Sludge
Blanket
Reactor
Trickling 1340000 2960 2060 4870 0 47300 68500
Filter
Secondary 708000 4190 2070 6970 0 1440 38100
Clarifier
Gravity Belt 357000 2640 540 0 133000 20200 18000
Thickener
Ultra-Violet 134000 0 753 1340 4360 34400 38300
Disinfection
Screw Press 1240000 40600 2480 35900 133000 40100 41700
Effluent 0 0 0 0 0 0 0
Hauling and 497000 4530 0 126000 0 0 70200
Land Filling
Other Costs 7700000 15700 0 0 0 0 333000
INDIRECT COSTS
Cost of land 0 $
Miscellaneous cost 13700 $
Legal cost 13700 $
Engineering design fee 410000 $
Inspection cost 13700 $
Contingency 684000 $
Technical 13700 $
Interest during construction 213000 $
Profit 651000 $
Total indirect construction costs 2010000 $
LABOR COSTS
Administration labor cost 6700 $/yr
Laboratory labor cost 9000 $/yr
Influent Wastewater
Water Quality Data
Parameter Influent Effluent Units
Maximum flow 33700 33700 m3/d
Minimum flow 13000 13000 m3/d
Average flow 17300 17300 m3/d
Suspended solids 621 621 g/m3
% volatile solids 85.0 85.0 %
BOD 276 276 g/m3
Soluble BOD 110 110 g/m3
COD 556 556 g/m3
Soluble COD 222 222 g/m3
TKN 41.4 41.4 gN/m3
Soluble TKN 24.8 24.8 gN/m3
Ammonia 24.8 24.8 gN/m3
Nitrite 0.0 0.0 gN/m3
Nitrate 0.0 0.0 gN/m3
Total phosphorus 11.0 11.0 gP/m3
pH 7.5 7.5 -
Cations 160 160 g/m3
Anions 160 160 g/m3
Settleable solids 10.0 10.0 g/m3
Oil and grease 100 100 g/m3
Summer temperature 19.5 19.5 deg C
Winter temperature 19.5 19.5 deg C
Preliminary Treatment
Design Output Data
Description Value Units
Preliminary Treatment
Design Information
Mechanically Cleaned Bar Screen
Bar size 0.636 cm
Bar spacing 0.6 cm
Slope of bars from horizontal 30.0 degrees
Head loss through screen NaN m
Approach velocity 0.5 m/s
Average flow through velocity 0.8 m/s
(screen)
Maximum flow through velocity 0.9 m/s
(screen)
Screen channel width 0.816 m
Average channel depth 0.305 m
Horizontal Flow Grit Chamber
Maximum flow 33500 m3/d
Average flow 17200 m3/d
Minimum flow 12900 m3/d
Temperature 19.5 deg C
Maximum flow through velocity 0.457 m/s
(grit chamber)
Average flow through velocity 0.305 m/s
(grit chamber)
Size of smallest particle 100% 0.02 cm
removed
Specific gravity of particle 2.65
Number of units 2.0
Maximum flow/unit 16800 m3/d
Width of channel 0.348 m
Depth of channel 1.22 m
Length of channel 36.5 m
Settling velocity of particle 0.026 m/s
Slope of channel bottom 0.00146
Allowance for currents 1.7
Manning coefficient 0.035
Hydraulic retention time 1.33 min
Volume of grit 0.517 m3/d
Costs
Construction and equipment cost Overridden
Operational labor cost 3220 $/yr
Maintenance labor cost 1400 $/yr
Material and supply cost 15600 $/yr
Chemical cost 0 $/yr
Energy cost 3560 $/yr
Amortization cost 27000 $/yr
Trickling Filter
Design Output Data
Description Value Units
Trickling Filtration
Design Information
Reaction rate constant 0.00213
Hydraulic loading rate 10.8 m3/(m2·d)
Total hydraulic loading rate 29.3 m3/(m2·d)
Recirculation ratio 1.72
Number of towers per stage 2.0
Number of stages 1.0
Depth of filter tower 2.91 m
Diameter of filter tower 32.1 m
Surface area per filter tower 812 m2
Total surface area 1620 m2
Volume per filter tower 2360 m3
Total volume 4720 m3
Quantities
Operation labor required 325 pers-hr/yr
Maintenance labor required 282 pers-hr/yr
Volume of earthwork required 6760 m3
Volume of slab concrete required 330 m3
Volume of wall concrete required 353 m3
Number of posts per tower 608
Total length of precast beams 2910 m
Costs
Construction and equipment cost 1130000 $
Earthwork Cost 338000 $
Wall Concrete Cost 82300 $
Slab Concrete Cost 37900 $
Concrete Beam Cost 105000 $
Media Cost 95100 $
Installed Distributor Arm Cost 242000 $
Misc Costs 225000 $
Operational labor cost 950 $/yr
Maintenance labor cost 674 $/yr
Material and supply cost 3370 $/yr
Chemical cost 0 $/yr
Energy cost 1240 $/yr
Amortization cost 55900 $/yr
Internal Recycle Pumping
Design Information
Average daily pumping rate 47600 m3/d
Total pumping capacity 47600 m3/d
Design capacity per pump 23800 m3/d
Number of pumps 3.0
Number of batteries 1.0
Firm pumping capacity 47600 m3/d
Quantities
Operation labor required 688 pers-hrs/yr
Maintenance labor required 581 pers-hrs/yr
Electrical energy required 419000 kWh/yr
Volume of earthwork required 102 m3
Area of pump building 41.6 m2
Costs
Construction and equipment cost 213000 $
Earthwork Cost 5080 $
Pump Building Cost 26400 $
Installed Pump Cost 149000 $
Misc Costs 32600 $
Operational labor cost 2010 $/yr
Maintenance labor cost 1390 $/yr
Material and supply cost 1490 $/yr
Chemical cost 0 $/yr
Energy cost 46100 $/yr
Amortization cost 12500 $/yr
Secondary Clarifier
Design Output Data
Description Value Units
Secondary Clarification
Design Information
Surface area 1070 m2
Surface area per circular clarifier 537 m2
Diameter of each circular clarifier 26.2 m
Number of clarifiers per battery 2.0
Number of batteries 1.0
Solids loading rate 2.1 kg/(m2·d)
Hydraulic retention time 6.62 hr
Designed surface overflow rate 16.3 m3/(m2·d)
Weir length 182 m
Volume of wasted sludge 313 m3/d
Quantities
Operation labor required 1120 pers-hrs/yr
Maintenance labor required 616 pers-hrs/yr
Electrical energy required 10300 kWh/yr
Volume of earthwork required 4250 m3
Slab thickness 29.5 cm
Volume of slab concrete required 366 m3
Wall thickness 36.6 cm
Volume of wall concrete required 304 m3
Costs
Construction and equipment cost 672000 $
Earthwork Cost 213000 $
Wall Concrete Cost 70900 $
Slab Concrete Cost 42000 $
Installed Equipment Cost 244000 $
Misc Costs 103000 $
Operational labor cost 3260 $/yr
Maintenance labor cost 1470 $/yr
Material and supply cost 6720 $/yr
Chemical cost 0 $/yr
Energy cost 1140 $/yr
Amortization cost 36000 $/yr
Waste Sludge Pumping
Design Information
Average daily pumping rate 313 m3/d
Total pumping capacity 313 m3/d
Design capacity per pump 156 m3/d
Number of pumps 3.0
Number of batteries 1.0
Firm pumping capacity 313 m3/d
Quantities
Operation labor required 319 pers-hrs/yr
Maintenance labor required 249 pers-hrs/yr
Electrical energy required 2780 kWh/yr
Volume of earthwork required 45.7 m3
Area of pump building 18.7 m2
Costs
Construction and equipment cost 36000 $
Earthwork Cost 2280 $
Pump Building Cost 11900 $
Installed Pump Cost 16300 $
Misc Costs 5490 $
Operational labor cost 933 $/yr
Maintenance labor cost 596 $/yr
Material and supply cost 252 $/yr
Chemical cost 0 $/yr
Energy cost 306 $/yr
Amortization cost 2110 $/yr
Ultra-Violet Disinfection
Design Output Data
Description Value Units
Ultra-Violet Disinfection
Design Information
Design based on a model 0.00425 m3/(min·W)
calculated UV loading
Total number of lamps needed for 367
disinfection
Number of spare channels 1.0
Total number of lamps used in 420
optimum design
Number of excess lamps 53.0
Number of lamps/modules 2.0
Number of modules/bank 3.0
Number of banks/channel 7.0
Number of channels 10.0
Calculated headloss 141 cm
Costs
Construction and equipment cost 134000 $
Cost of installation 80500 $
Total cost of UV lamps 53700 $
Operational labor cost 0 $/yr
Maintenance labor cost 753 $/yr
Material and supply cost 1340 $/yr
Chemical cost 4360 $/yr
Energy cost 34400 $/yr
Amortization cost 38300 $/yr
Screw Press
Design Output Data
Description Value Units
Screw Press
Design Information
Total power required 58.4 kW
Power required per unit 58.4 kW
Excess capacity factor 1.25
Number of units 1.0
Chemical dose 1.0 % dry wt
Chemicals required 179 kg/d
Sludge flow 341 m3/d
Initial solid conc 5.0 %
Operational hours per day 20.0 hr
Operational days per week 6.0 d
Quantities
Number of Screw Press 1.0
Power required per unit 58.4 kW
Area of building 18.6 m2
Dry solids produced 12200 kg/d
Operation labor required 6140 pers-hrs/yr
Maintenance labor required 1040 pers-hrs/yr
Electrical energy required 365000 kWh/yr
Costs
Construction and equipment cost 657000 $
Operational labor cost 17900 $/yr
Maintenance labor cost 2480 $/yr
Material and supply cost 24200 $/yr
Chemical cost 0 $/yr
Energy cost 40100 $/yr
Amortization cost 41700 $/yr
Polymer Feed System
Quantities
Polymer dosage 149 kg/d
Liquid chemical solution fed 59.8 m3/d
O&M labor required 6350 pers-hrs/yr
Dry material handling and mixing 1420 pers-hrs/yr
labor required
Total operation labor required 7770 pers-hrs/yr
Costs
Construction and equipment cost 580000 $
Operational labor cost 22700 $/yr
Maintenance labor cost 0 $/yr
Material and supply cost 11600 $/yr
Chemical cost 133000 $/yr
Energy cost 0 $/yr
Amortization cost 0 $/yr
Effluent
Design Output Data
Description Value Units
Costs
Construction and equipment cost 0 $
Operational labor cost 0 $/yr
Maintenance labor cost 0 $/yr
Material and supply cost 0 $/yr
Chemical cost 0 $/yr
Energy cost 0 $/yr
Amortization cost 0 $/yr
MBR
Summary
Equipment Database
Hydromantis 2014,(USA Avg)
Layout Summary
Description Value Units
CONSTRUCTION
COSTS
Unit process construction $15,200,000 $
costs
Other direct construction $5,690,000 $
costs
Other indirect $3,230,000 $
construction costs
Total construction costs $24,100,000 $
ANNUAL COSTS
LABOR COSTS
Administration labor cost $6,700 $/yr
Laboratory labor cost $9,000 $/yr
Unit process operation $70,200 $/yr
labor cost
Unit process maintenance $21,500 $/yr
labor cost
Total labor costs $107,000 $/yr
MATERIAL COSTS
Total material cost $276,000 $/yr
CHEMICAL COSTS
Total chemical cost $211,000 $/yr
ENERGY COSTS
Total energy cost $697,000 $/yr
CONSTRUCTION
COST
AMORTIZATION
Amortization cost for $2,120,000 $/yr
total construction cost
PROJECT SUMMARY
Present worth $78,800,000 $
Total project cost $24,100,000 $
Total operation labor cost $85,900 $/yr
Total maintenance labor $21,500 $/yr
cost
Total material cost $276,000 $/yr
Total chemical cost $211,000 $/yr
Total energy cost $697,000 $/yr
Total amortization cost $2,120,000 $/yr
Process Summary
Process Construction Operation Maintenance Material Chemical Energy Amortizatio
($) ($/yr) ($/yr) ($/yr) ($/yr) ($/yr) n ($/yr)
Preliminary 623000 3220 1430 15600 0 3560 27000
Treatment
Influent 1090000 2170 1530 7600 0 24000 56900
Pump
Station
Plug Flow 2810000 9380 4910 58900 0 285000 163000
Activated
Sludge with
MBR
Membrane 6780000 21200 11200 66600 46600 334000 1270000
Bioreactor(1
)
Ultra-Violet 46000 0 265 460 1490 11800 13100
Disinfection
Gravity Belt 255000 1610 338 0 81400 12800 12300
Thickener
Effluent 0 0 0 0 0 0 0
Screw Press 827000 29800 1790 22600 81800 25500 28100
Hauling and 377000 2770 0 104000 0 0 56200
Land Filling
Blower 2420000 0 0 0 0 0 105000
System
Other Costs 8920000 15700 0 0 0 0 386000
LABOR COSTS
Administration labor cost 6700 $/yr
Laboratory labor cost 9000 $/yr
Influent Wastewater
Water Quality Data
Parameter Influent Effluent Units
Maximum flow 33700 33700 m3/d
Minimum flow 13000 13000 m3/d
Average flow 17300 17300 m3/d
Suspended solids 621 621 g/m3
% volatile solids 85.0 85.0 %
BOD 276 276 g/m3
Soluble BOD 110 110 g/m3
COD 556 556 g/m3
Soluble COD 222 222 g/m3
TKN 41.4 41.4 gN/m3
Soluble TKN 24.8 24.8 gN/m3
Ammonia 24.8 24.8 gN/m3
Nitrite 0.0 0.0 gN/m3
Nitrate 0.0 0.0 gN/m3
Total phosphorus 11.0 11.0 gP/m3
pH 7.5 7.5 -
Cations 160 160 g/m3
Anions 160 160 g/m3
Settleable solids 10.0 10.0 g/m3
Oil and grease 100 100 g/m3
Summer temperature 19.5 19.5 deg C
Winter temperature 19.5 19.5 deg C
Preliminary Treatment
Design Output Data
Description Value Units
Preliminary Treatment
Design Information
Mechanically Cleaned Bar Screen
Bar size 0.636 cm
Bar spacing 0.1 cm
Slope of bars from horizontal 30.0 degrees
Head loss through screen NaN m
Approach velocity 0.5 m/s
Average flow through velocity 0.8 m/s
(screen)
Maximum flow through velocity 0.9 m/s
(screen)
Screen channel width 0.816 m
Average channel depth 0.305 m
Horizontal Flow Grit Chamber
Maximum flow 33500 m3/d
Average flow 17200 m3/d
Minimum flow 12900 m3/d
Temperature 19.5 deg C
Maximum flow through velocity 0.457 m/s
(grit chamber)
Average flow through velocity 0.305 m/s
(grit chamber)
Size of smallest particle 100% 0.02 cm
removed
Specific gravity of particle 2.65
Number of units 2.0
Maximum flow/unit 16800 m3/d
Width of channel 0.348 m
Depth of channel 1.22 m
Length of channel 36.5 m
Settling velocity of particle 0.026 m/s
Slope of channel bottom 0.00146
Allowance for currents 1.7
Manning coefficient 0.035
Hydraulic retention time 1.33 min
Volume of grit 0.517 m3/d
Costs
Construction and equipment cost 623000 $
Operational labor cost 3220 $/yr
Maintenance labor cost 1430 $/yr
Material and supply cost 15600 $/yr
Chemical cost 0 $/yr
Energy cost 3560 $/yr
Amortization cost 27000 $/yr
Water Quality Data
Parameter Influent Effluent Units
Maximum flow 33700 33700 m3/d
Minimum flow 13000 13000 m3/d
Average flow 17300 17300 m3/d
Suspended solids 621 621 g/m3
% volatile solids 85.0 85.0 %
BOD 276 276 g/m3
Soluble BOD 110 110 g/m3
COD 556 556 g/m3
Soluble COD 222 222 g/m3
TKN 41.4 41.4 gN/m3
Soluble TKN 24.8 24.8 gN/m3
Ammonia 24.8 24.8 gN/m3
Nitrite 0.0 0.0 gN/m3
Nitrate 0.0 0.0 gN/m3
Total phosphorus 11.0 11.0 gP/m3
pH 7.5 7.5 -
Cations 160 160 g/m3
Anions 160 160 g/m3
Settleable solids 10.0 10.0 g/m3
Oil and grease 100 100 g/m3
Summer temperature 19.5 19.5 deg C
Winter temperature 19.5 19.5 deg C
Membrane Bioreactor(1)
Design Output Data
Description Value Units
Membrane Bioreactor
Design Information
Total volume of reactors 1410 m3
Length of parallel train 11.9 m
Width of parallel train 5.94 m
Sidewater depth 5.0 m
Number of batteries 1.0
Number of parallel trains per 4.0
battery
Total Membrane Area 63500 m2
Total Scour Air Requirement 28600 N m3/hr
Quantities
Operation labor required 6280 pers-hrs/yr
Maintenance labor required 3750 pers-hrs/yr
Electrical energy required 2890000 kWh/yr
Volume of earthwork required 1110 m3
Volume of slab concrete required 731 m3
Volume of wall concrete required 351 m3
Handrail length 215 m
Number of diffusers per train 468
Number of swing arm headers per 2.0
train
Costs
Construction and equipment cost 6380000 $
Earthwork Cost 55500 $
Wall Concrete Cost 81800 $
Slab Concrete Cost 84000 $
Handrail Cost 8170 $
Membrane Cost 5480000 $
Installed Aerator Equipment 224000 $
Cost
Air Piping Cost 352000 $
Misc Cost 113000 $
Operational labor cost 18300 $/yr
Maintenance labor cost 9200 $/yr
Material and supply cost 63800 $/yr
Chemical cost 46600 $/yr
Energy cost 318000 $/yr
Amortization cost 1250000 $/yr
Permeate Pumping
Design Information
Average daily pumping rate 5960 m3/d
Total pumping capacity 11400 m3/d
Design capacity per pump 6350 m3/d
Number of pumps 9.0
Number of batteries 1.0
Firm pumping capacity 38100 m3/d
Quantities
Operation labor required 638 pers-hrs/yr
Maintenance labor required 540 pers-hrs/yr
Electrical energy required 142000 kWh/yr
Volume of earthwork required 60.3 m3
Area of pump building 24.7 m2
Costs
Construction and equipment cost 362000 $
Earthwork Cost 9040 $
Pump Building Cost 47000 $
Installed Pump Cost 251000 $
Misc Costs 55200 $
Operational labor cost 1860 $/yr
Maintenance labor cost 1320 $/yr
Material and supply cost 2530 $/yr
Chemical cost 0 $/yr
Energy cost 15600 $/yr
Amortization cost 21200 $/yr
Waste Sludge Pumping
Design Information
Average daily pumping rate 627 m3/d
Total pumping capacity 627 m3/d
Design capacity per pump 313 m3/d
Number of pumps 3.0
Number of batteries 1.0
Firm pumping capacity 627 m3/d
Quantities
Operation labor required 349 pers-hrs/yr
Maintenance labor required 276 pers-hrs/yr
Electrical energy required 5570 kWh/yr
Volume of earthwork required 46.0 m3
Area of pump building 18.9 m2
Costs
Construction and equipment cost 43000 $
Earthwork Cost 2300 $
Pump Building Cost 12000 $
Installed Pump Cost 22200 $
Misc Costs 6560 $
Operational labor cost 1020 $/yr
Maintenance labor cost 676 $/yr
Material and supply cost 301 $/yr
Chemical cost 0 $/yr
Energy cost 613 $/yr
Amortization cost 2520 $/yr
Ultra-Violet Disinfection
Design Output Data
Description Value Units
Ultra-Violet Disinfection
Design Information
Design based on a model 0.0122 m3/(min·W)
calculated UV loading
Total number of lamps needed for 128
disinfection
Number of spare channels 1.0
Total number of lamps used in 144
optimum design
Number of excess lamps 16.0
Number of lamps/modules 2.0
Number of modules/bank 3.0
Number of banks/channel 2.0
Number of channels 12.0
Calculated headloss 27.0 cm
Costs
Construction and equipment cost 46000 $
Cost of installation 27600 $
Total cost of UV lamps 18400 $
Operational labor cost 0 $/yr
Maintenance labor cost 265 $/yr
Material and supply cost 460 $/yr
Chemical cost 1490 $/yr
Energy cost 11800 $/yr
Amortization cost 13100 $/yr
Effluent
Design Output Data
Description Value Units
Costs
Construction and equipment cost 0 $
Operational labor cost 0 $/yr
Maintenance labor cost 0 $/yr
Material and supply cost 0 $/yr
Chemical cost 0 $/yr
Energy cost 0 $/yr
Amortization cost 0 $/yr
Screw Press
Design Output Data
Description Value Units
Screw Press
Design Information
Total power required 35.8 kW
Power required per unit 35.8 kW
Excess capacity factor 1.25
Number of units 1.0
Chemical dose 1.0 % dry wt
Chemicals required 110 kg/d
Sludge flow 209 m3/d
Initial solid conc 5.0 %
Operational hours per day 20.0 hr
Operational days per week 6.0 d
Quantities
Number of Screw Press 1.0
Power required per unit 35.8 kW
Area of building 18.6 m2
Dry solids produced 7470 kg/d
Operation labor required 4360 pers-hrs/yr
Maintenance labor required 729 pers-hrs/yr
Electrical energy required 232000 kWh/yr
Costs
Construction and equipment cost 445000 $
Operational labor cost 12700 $/yr
Maintenance labor cost 1790 $/yr
Material and supply cost 15000 $/yr
Chemical cost 0 $/yr
Energy cost 25500 $/yr
Amortization cost 28100 $/yr
Polymer Feed System
Quantities
Polymer dosage 91.5 kg/d
Liquid chemical solution fed 36.7 m3/d
O&M labor required 4620 pers-hrs/yr
Dry material handling and mixing 1240 pers-hrs/yr
labor required
Total operation labor required 5860 pers-hrs/yr
Costs
Construction and equipment cost 382000 $
Operational labor cost 17100 $/yr
Maintenance labor cost 0 $/yr
Material and supply cost 7640 $/yr
Chemical cost 81800 $/yr
Energy cost 0 $/yr
Amortization cost 0 $/yr