LT18102700 #Project Schedule
LT18102700 #Project Schedule
LT18102700 #Project Schedule
LT18102700 FEED FOR MIC PORT 14-Aug-18 07-Sep-19 07-Sep-19 04:00 PM, LT18102700 FEED FOR MIC
08:00 AM 04:00 PM
LT18102700.1 Project Initiation 14-Aug-18 08:00
28-Aug-18
AM 04:00 PM 28-Aug-18 04:00 PM, LT18102700.1 Project Initiation
A0.1.0 Stat Milestone 14-Aug-18 08:00 AM Stat Milestone, 14-Aug-18 08:00 AM
A0.1.1 Kickoff Meeting 14-Aug-18 08:00
14-Aug-18
AM 04:00
Kickoff
PM Meeting
A0.1.2 Project Plane Submition 15-Aug-18 08:00
16-Aug-18
AM 04:00
Project
PM Plane Submition
A0.1.3 Plane Review 18-Aug-18 08:00
20-Aug-18
AM 04:00 PM
Plane Review
A0.1.4 Mobilization 21-Aug-18 08:00
28-Aug-18
AM 04:00 PM Mobilization
Actual Level of Effort Remaining Work Milestone Date Revision Checked Approved
Page 1 of 4
08-Jun-18 11:0... #1
Actual Work Critical Remaining Work summary
Prepared By : Shiyam, iFluids Engg
FEED for Upgrade & Replacement of Fire Protection Systems at
Berth No. 6, MIC Port
Activity ID Activity Name Start Finish Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
A3.2.7 Piping Demolition Drawings 21-Nov-18 08:00
26-Nov-18
AM 04:00 PM Piping Demolition Drawings
LT18102700.3.3 Piping Reports & Calculations 20-Dec-18 08:00
12-Jan-19
AM 04:00 PM 12-Jan-19 04:00 PM, LT18102700.3.3 Piping Reports & Calculations
A3.3.1 Thickness Calculation Report for GRE Piping 20-Dec-18 08:00
25-Dec-18
AM 04:00 PM Thickness Calculation Report for GRE Piping
A3.3.2 Piping Stress Analysis Report 26-Dec-18 08:00
31-Dec-18
AM 04:00 PM Piping Stress Analysis Report
A3.3.3 Material Handling/Lifting study Report 01-Jan-19 08:00
06-Jan-19
AM 04:00 PM Material Handling/Lifting study Report
A3.3.4 Material Selection Study Report for piping and equipment 07-Jan-19 08:00
12-Jan-19
AM 04:00 PM Material Selection Study Report for piping and equipment
LT18102700.3.4 Piping Schedule & Material Take-off (MTO) 13-Jan-19 08:00
04-Feb-19
AM 04:00 PM 04-Feb-19 04:00 PM, LT18102700.3.4 Piping Schedule & Material Take-off (MTO)
A3.4.1 Tie-In Schedule and Tie-In Engineering Package 13-Jan-19 08:00
17-Jan-19
AM 04:00 PM Tie-In Schedule and Tie-In Engineering Package
A3.4.2 Valve Schedule 19-Jan-19 08:00
23-Jan-19
AM 04:00 PM Valve Schedule
A3.4.3 Preliminary Piping MTO 24-Jan-19 08:00
29-Jan-19
AM 04:00 PM Preliminary Piping MTO
A3.4.4 Piping Support Schedule and Pipe Support Details 30-Jan-19 08:00
04-Feb-19
AM 04:00 PM Piping Support Schedule and Pipe Support Details
LT18102700.3.5 Static Equipment Design 05-Dec-18 08:00
08-Jan-19
AM 04:00 PM 08-Jan-19 04:00 PM, LT18102700.3.5 Static Equipment Design
A3.5.1 Mechanical Design Basis 05-Dec-18 08:00
10-Dec-18
AM 04:00 PM Mechanical Design Basis
A3.5.2 Production of data sheets, and specifications for all mechanical equipment
11-Dec-18
including
08:00
16-Dec-18
packaged
AM 04:00units
PM Production of data sheets, and specifications for all mechanical equipment including packaged units
A3.5.3 Design Calculations of Mechanical Equipments 17-Dec-18 08:00
22-Dec-18
AM 04:00 PM Design Calculations of Mechanical Equipments
A3.5.4 Prepare / Submission of the Equipment List 23-Dec-18 08:00
27-Dec-18
AM 04:00 PM Prepare / Submission of the Equipment List
A3.5.5 Material Handling Study Reports 29-Dec-18 08:00
02-Jan-19
AM 04:00 PM Material Handling Study Reports
A3.5.6 Complete material requisition for identified Mechanical Equipment 03-Jan-19 08:00
08-Jan-19
AM 04:00 PM Complete material requisition for identified Mechanical Equipment
LT18102700.3.6 Rotating Equipment Design 31-Oct-18 08:00
04-Dec-18
AM 04:00 PM 04-Dec-18 04:00 PM, LT18102700.3.6 Rotating Equipment Design
A3.6.1 Mechanical Design Basis 31-Oct-18 08:00
05-Nov-18
AM 04:00 PM Mechanical Design Basis
A3.6.2 Production of data sheets, and specifications for all mechanical equipment
06-Nov-18
including
08:00
11-Nov-18
packaged
AM 04:00units
PM Production of data sheets, and specifications for all mechanical equipment including packaged units
A3.6.3 Design Calculations of Mechanical Equipments 12-Nov-18 08:00
17-Nov-18
AM 04:00 PM Design Calculations of Mechanical Equipments
A3.6.4 Prepare / Submission of the Equipment List5 18-Nov-18 08:00
22-Nov-18
AM 04:00 PM Prepare / Submission of the Equipment List5
A3.6.5 Material Handling Study Reports 24-Nov-18 08:00
28-Nov-18
AM 04:00 PM Material Handling Study Reports
A3.6.6 Complete material requisition for identified Mechanical Equipment 29-Nov-18 08:00
04-Dec-18
AM 04:00 PM Complete material requisition for identified Mechanical Equipment
Actual Level of Effort Remaining Work Milestone Date Revision Checked Approved
Page 2 of 4
08-Jun-18 11:0... #1
Actual Work Critical Remaining Work summary
Prepared By : Shiyam, iFluids Engg
FEED for Upgrade & Replacement of Fire Protection Systems at
Berth No. 6, MIC Port
Activity ID Activity Name Start Finish Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
A5.3.008 HVAC Control Schematic 11-Jul-19 08:00
16-Jul-19
AM 04:00 PM HVAC Control Schematic
A5.3.009 HVAC Air Flow Diagram 17-Jul-19 08:00
22-Jul-19
AM 04:00 PM HVAC Air Flow Diagram
A5.3.010 HVAC Standard Details 23-Jul-19 08:00
28-Jul-19
AM 04:00 PM HVAC Standard Details
Actual Level of Effort Remaining Work Milestone Date Revision Checked Approved
Page 3 of 4
08-Jun-18 11:0... #1
Actual Work Critical Remaining Work summary
Prepared By : Shiyam, iFluids Engg
FEED for Upgrade & Replacement of Fire Protection Systems at
Berth No. 6, MIC Port
Activity ID Activity Name Start Finish Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
A10.3.1 Develop FEED Project Specific Design and drawings for the Civil / Structural
05-Mar-19
works
08:00
10-Mar-19
as specified
AM 04:00 PM Develop FEED Project Specific Design and drawings for the Civil / Structural works as specified
Actual Level of Effort Remaining Work Milestone Date Revision Checked Approved
Page 4 of 4
08-Jun-18 11:0... #1
Actual Work Critical Remaining Work summary
Prepared By : Shiyam, iFluids Engg