Download as pdf or txt
Download as pdf or txt
You are on page 1of 50

PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works

Jajaran Sungai Buloh ‐ Kajang  Section G3 – Site Establishment
 

Provision For  G3.11  (1)  The  Works  Package  Contractor  shall  provide  for  the  sole 
Survey  use of the PDP’s and Supervising Consultant’s staff all such 
Instruments and  instruments,  equipment  and  chainmen  as  the  PDP  may 
Chainmen  require to enable him to check the accuracy of the Works 
Package  Contractor’s  setting  out  and  any  measurements 
taken.    The  chainmen  shall  have  knowledge  of  Bahasa 
Malaysia  or  English  and  as  far  as  possible  the  same  men 
shall be provided throughout the Contract period. 

    (2)  The  instruments  and  equipment  to  be  provided  are  as 
listed in Specifications. 

    (3)  The  Works  Package  Contractor  shall  be  responsible 


throughout  the  Contract  period  for  all  such  instruments, 
equipment  and  chainmen  and  shall  ensure  that  the 
instruments  and  equipment  are  at  all  times  in  good 
working  condition  and  adjustment.    All  instruments  and 
equipment shall remain the property of the Works Package 
Contractor on completion of the Works. 

    (4)  The  PDP  or  his  agents  will  not  be  responsible  for  loss, 
damage  or  normal  wear  and  tear  to  surveying  equipment 
provided. 

    (5)  The acceptance of chainmen and labourers shall be at the 
discretion of the PDP as regards reliability and suitability. 

  G3.12  Photographic Records 

Cameras for the  G3.12.1  (1)  The  Works  Package  Contractor  shall  provide  to  the  PDP  / 
PDP / PDPR / SC  PDPR / SC and maintain for proper functioning  during the 
Contract  period  two  digital  cameras,  or  other  quantity 
specified in the Contract, with a set of accessories for each 
camera as follows. 

    a)  The  camera  shall  be  the  compact  digital  type, 


shockproof  and  waterproof,  which  can  produce 
image  resolution  of  not  less  than  5.0  Mega  Pixels. 
The  setting  of  focus,  aperture  and  built‐in  flash  of 
the  camera  shall  be  fully  automatic.  The  aperture 
shall  have  wide  angle  capability  and  zooming  shall 
not  be  less  than  12X  digital  and  optical  zoom 
combined,  with  a  minimum  optical  zoom 
component of 5X. The format of the image shall be 
JPEG.  The  interface  shall  be  compatible  with  USB 
2.0  port.  The  drivers  shall  be  compatible  with  the 
Microsoft Windows Operating System from version 
Windows XP Professional and later. 

b)  The camera shall be provided with the full package 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G3‐10 of 12 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G3 – Site Establishment
 
of  accessories  from  the  manufacturer  including  a 
made‐to‐fit carrying case. In addition to the built‐in 
memory  for  the  storage  of  the  images,  the  Works 
Package  Contractor  shall  provide  an  additional 
memory  card  of  at  least  4GB  storage  capacity 
compatible  with  the  camera.    If  the  camera  uses 
rechargeable  batteries,  the  Works  Package 
Contractor shall provide a spare set of batteries and 
a battery charger. 

c)  Any  deviation  from  the  above  shall  be  subject  to 
the PDP’s approval. 

Photographic  G3.12.2  (1)  Digital  colour  progress  photographs  showing  the  progress 
Records of the  of  the  Works  and  the  quality  of  the  materials  and 
Works  workmanship  shall  be  taken  by  the  Works  Package 
Contractor.  The  photographs  shall  be  taken  by  a  skilled 
professional  photographer  approved  by  the  PDP.  The 
photographs  shall  be  taken  under  the  direction  of  the 
Supervising  Consultant  at  locations  selected  by  him. 
Photographs shall be taken once every month and at other 
times instructed by the PDP. 

    (2)  The following shall be provided to the PDP within seven (7) 
days of the progress photographs being taken: 

    a)  one  set  of  each  record  photograph  comprising  a 


CD‐ROM  containing  the  JPEG  images  and  two  4R 
size prints; 

b)  albums for the photographs and CD‐ROM; and 

c)  printed  labels  attached  to  the  back  of  each 


photograph with the following information: date and 
time  of  exposure,  identification  reference  number, 
brief description of the work including chainage and 
direction of view. 

    (3)  Each  print  of  the  record  photographs  shall  be 


authenticated  by  the  Contractor  and  the  Supervising 
Consultant by signing a printed label attached to the back 
of the print. 

    (4)  One  print  of  each  selected  progress  photograph  shall  be 
authenticated  by  the  Contractor  and  the  Supervising 
Consultant by signing a printed label attached to the back 
of the print. 

    (5)  The  photographs  and  associated  digital  files  shall  be  the 
property of the PDP and no prints or files may be supplied 
to any person or persons except with the authority of the 
PDP. 
KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G3‐11 of 12 Revision: 01
 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G3 – Site Establishment
 

Prohibition of  G3.13  The  Works  Package  Contractor  shall  treat  the  Contract  and 
Advertising  everything  written  as  private  and  confidential.  In  particular,  the 
Works  Package  Contractor  shall  not  publish  any  information, 
advertisement, drawing or photograph relating to the Works and 
shall  not  use  the  Site  for  advertising  purposes,  except  with  the 
written  consent  of  the  PDP  and  subject  to  such  conditions  as  he 
may prescribe. 
 
 
 
 
END OF SECTION 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G3‐12 of 12 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G4 – The Works
 

    SECTION G4 
THE WORKS 

Project  G4.1  (1)  Within  thirty  (30)  days  from  the  date  of  the  Letter  of 
Execution Plan  Acceptance, the Works Package Contractor shall provide the 
PDP  with  an  overview  of  his  intended  methods  of 
constructing the various parts of the Works in the form of a 
Project Execution Plan.  This shall include but not be limited 
to: 

a)  A  narrative  and  drawings  describing  the  main 


operations and sub‐operations; 

b)  The sequence of the Works; 

c)  The  quantities  of  major  elements  and  production 


rates to be achieved; 

d)  The resources to be employed; and 

e)  The responsibilities and processes requisite to ensure 
the successful completion of the Works. 

(2)  Within  two  (2)  months  from  the  date  of  the  Letter  of 
Acceptance  or  by  the  date  agreed  with  the  PDP,  the  Works 
Package  Contractor  shall  supplement  the  Project  Execution 
Plan with: 

a)  Details  of  the  Method  Statements  which  will  be 


developed as required by Clause G4.2; 

b)  Details  of  any  Temporary  Works  which  will  be 


required (or the date by which they will be procured);

c)  Details of the personnel who will control the works; 

d)  Proposals for quality control; and 

e)  Safety precautions to be employed. 

    (3)  The  Works  Package  Contractor  shall,  whenever  required  by 


the  PDP,  furnish  for  his  information  further  and  more 
detailed particulars in writing of his method of construction, 
the  amount  and  nature  of  the  Works  Package  Contractor’s 
Equipment and manpower he proposes to use. 

    (4)  The  PDP  shall  have  the  authority  to  order  the  immediate 
removal and replacement of any Works Package Contractor’s 
Equipment  which,  in  his  opinion,  is  unsatisfactory  for  its 
purpose. 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G4‐1 of 12 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G4 – The Works
 

  G4.2  Method Statements, and Inspection and Testing Plans 

Method  G4.2.1  (1)  The Works  Package Contractor shall submit for the approval 


Statements,  of  the  PDP  a  Method  Statement  and  an  Inspection  and 
Inspection and  Testing  Plan  addressing  construction  procedures,  safety  and 
Testing Plans  health procedures, environmental issues, and quality control 
procedures for each major or non‐standard work task not less 
than  twenty  one  (21)  days  prior  to  the  start  of  the  related 
construction  activities.    The  Method  Statement  and 
Inspection and Testing Plan shall have been approved by the 
PDP prior to the Works Package Contractor commencing any 
work on the task described. 

(2)  Within  twenty  one  (21)  days  of  the  date  of  the  Notice  to 
Proceed, the Works Package Contractor shall provide for the 
PDP’s  reference,  a  list  of  proposed  Method  Statements  and 
Inspection  and  Testing  Plans  which  shall  be  compatible  with 
the  Baseline  Programme,  for  various  general  and  specific 
construction  works  which  will  arise  during  the  course  of  the 
Contract. 

Training for  G4.2.2  (1)  Before  the  commencement  of  the  work,  specific  method 
Work using  statement  training  shall  be  provided  to  the  supervisors  and 
Method  workers  involved  in  the  work,  on  the  agreed  safe  work 
Statement  method and safety precautions to be implemented. 

(2)  The  Works  Package  Contractor  shall  provide  to  each 


supervisor involved with the work a simplified set of method 
statement. 

(3)  The  supervisor  shall  sign  for  the  method  statement  to  say 
that  he  or  she  has  conducted  the  required  briefings  to  all 
workers involved.  

(4)  A list of attendees at the training and briefings, shall be kept 
by the supervisor of the safety section. 

(5)  Prior  to  work  starting,  a  Supervisor  or  ganger  shall  brief  all 
persons  involved  with  the  work,  on  the  safe  work  method 
and  the  safety  precautions  stipulated  in  the  method 
statement during their daily briefing.  

(6)  No  person  shall  start  work  without  receiving  the  required 
training and briefings for the work to be conducted. 

(7)  In the event of a change in the work methods, retraining shall 
be given to all persons involved.  

Normal working  G4.3  (1)  Normal  working  hours  at  the  Site  shall  be  defined  as  the 
hours at Site  period  between  0700  hours  and  1900  hours  on  all  days 
excluding  General  Holidays.    Any  works  performed  by  the 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G4‐2 of 12 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G4 – The Works
 
Works Package Contractor outside normal working hours (ie. 
Night Work) and on General Holidays shall be subject to the 
Works Package Contractor obtaining the prior approval from 
the  Relevant  Authorities  and  having  given  the  PDP  prior 
written notification. 

    (2)  The  Works  Package  Contractor  shall  inform  the  PDP  twenty 
four (24) hours, or such shorter period permitted by the PDP, 
in  advance  of  any  occasion  when  work  outside  normal 
working hours is proposed. 

Drawings and  G4.4  Detailed  manufacturing  drawings  for  plant  and  equipment  for  the 
schedules for  Permanent Works will not normally be required to be submitted for 
plant and  review  by  the  PDP  but  shall  be  available  on  the  Works  Package 
equipment  Contractor's or his sub‐contractor's premises if required. The Works 
Package Contractor shall also maintain at Site a comprehensive and 
up‐to‐date set of drawings properly indexed and catalogued, which 
shall  include  complete  sets  of  detailed  working  and,  where 
applicable, manufacturing  drawings  and  shall  permit  free access  to 
such  drawings  by  the  PDP  and  the  Supervising  Consultant  at  any 
reasonable time. 

Stage  G4.5  (1)  The  Works  will  be  the  subject  of  a  formalised  system  of 
notification and  written  applications  for  inspection.    The  Works  Package 
inspection of  Contractor shall submit for the PDP’s approval his proposed 
Works  Request  for  Inspection  /  Test  /  Survey  Check  Forms.  Failure 
on  the  part  of  the  Works  Package  Contractor  to  make 
application  in  respect  of  the  work  may  result  in  the  PDP 
withholding Approval of the work. 

    (2)  The Works Package Contractor shall give adequate notice in 
writing to the PDP of requests for inspection and approval of 
any parts of the Works. Where no period of notice is stated 
in  the  Contract,  such  notice  shall  be  not  less  than  twenty 
four  (24)  hours  of  normal  working  time  before  the  work  is 
ready  for  final  inspection.  The  PDP  will  require  reasonable 
time to carry out any inspection which shall be during normal 
working hours except as may be otherwise agreed. 

    (3)  In  the  case  of  a  part  of  the  Works  being  executed  off‐site, 
the  Works  Package  Contractor  shall  give  the  PDP  at  least 
seven  (7)  days’  notice  in  writing  stating  when  and  where 
such work is due to commence. 

    (4)  Work which is carried out without prior approval of the PDP, 
with  or  without  conditions,  may  be  subject  to  additional 
testing,  at  the  PDP’s  discretion  and  at  the  Works  Package 
Contractor’s cost. 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G4‐3 of 12 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G4 – The Works
 

    (5)  The  stages  appropriate  to  each  type  of  work  shall  be 
proposed by the Works Package Contractor and approved by 
the  PDP.    The  Works  Package  Contractor  shall  ensure  that 
the PDP is given the opportunity to inspect each stage before 
proceeding with the next. 

Demolition  G4.6  (1)  Demolition  works  shall  comply  with  all  relevant  Statutory 
works  Requirements. 

(2)  The  Works  Package  Contractor  shall  provide  all  necessary 


safety  measures  including  but  not  limited  to  shoring,  catch 
fans, screens, scaffolding and hoardings. 

(3)  The  Works  Package  Contractor  shall  ensure  that  demolition 


works will not cause damage to or undermine the structural 
integrity,  stability,  serviceability,  operation  and  function  of 
adjacent  buildings,  structures,  railways,  utilities,  services, 
roads, footpaths and slopes. 

(4)  All  voids  formed  by  demolition  works  shall  be  completely 
filled by an approved method unless otherwise instructed by 
the PDP. 

    (5)  The Works Package Contractor shall, in an approved manner, 
make good any damage resulting from the demolition works.

(6)  The  Works  Package  Contractor  shall  remove  all  equipment 


and  materials  resulting  from  demolition  works  from  Site 
except as specified in the Contract. 

(7)  Prior  to  commencement  of  demolition  works,  the  Works 


Package Contractor shall: 

a)  carry out a thorough survey and examine all as‐built 
drawings; 

b)  locate  and  mark  the  positions  of  all  utilities  and 
services which may be affected; 

c)  submit  a  detailed  method  statement  for  approval 


which shall take due cognisance of the structure to be 
demolished, and which shall be checked and certified 
in accordance with Clause G4.8.2; and 

d)  submit  for  approval  an  appraisal  report  which  shall 


include,  but  not  be  limited  to,  an  assessment  of  the 
condition  of  the  structures  to  be  demolished  and 
structural  analysis  and  any  other  checking  deemed 
necessary by the PDP. 

Construction  G4.7  (1)  The  Works  Package  Contractor  shall  design  and  implement 
restraints  temporary traffic management schemes in accordance with 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G4‐4 of 12 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G4 – The Works
 
the provisions of Section G5. 

    (2)  Where all or part of the Works is within a Railway Protection 
zone,  the  Works  Package  Contractor  shall  follow  the 
provisions of Section G6.8 in particular. 

    (3)  The Works Package Contractor shall ensure that the design, 
construction,  performance  and  removal  of  all  Temporary 
Works and the construction of all Permanent Works shall be 
such that any vibration or ground movements in and around 
the  Site  will  not  result  in  settlement  and/or  subsidence  of 
the ground that causes damage to any buildings, structures, 
rail, roads, footpaths, slopes, utilities, services and the like. 

    (4)  The Works Package Contractor shall ensure that the method 
of installation of any part of the Permanent Works (prior to 
dewatering  and  excavation)  minimises  movement,  vibration 
or  settlement  in  the  adjacent  ground  or  buildings.  
Dewatering  of  an  excavation  will  not  be  permitted  until  a 
closed perimeter of impermeable wall is complete. 

    (5)  The  Works  Package  Contractor's  design  of  dewatering 


methods shall as far as possible avoid lowering of the water 
table outside the excavations.  The reduction in piezometric 
pressure shall in no case be greater than 1 metre in adjacent 
ground,  unless  the  Works  Package  Contractor  can  clearly 
demonstrate  that  building,  structures,  roads,  footpaths  and 
utilities  within  the  influence  of  the  dewatering  will  not  be 
damaged by the proposed dewatering. 

  G4.8  Temporary Works 

Temporary  G4.8.1  (1)  Unless  otherwise  specified  in  the  Contract,  the  Works 
Works Design  Package  Contractor  shall  design  all  Temporary  Works  of 
whatever  nature,  including  Permanent  Works  that  will  be 
used as Temporary Works during construction to suit his own 
construction sequence and methodology, and which shall be 
endorsed  by  a  Professional  Engineer  registered  with  the 
Board of Engineers Malaysia, and submitted for the approval 
of the PDP.  The design of the Temporary Works shall also be 
independently checked in accordance with the requirements 
of Clause G4.8.2. 

    (2)  Without  relieving  the  Works  Package  Contractor  from  the 


responsibilities  of  the  foregoing  sub‐clause  (1),  where  the 
PDP has carried out reference designs for certain Temporary 
Works,  these  are  made  available  to  the  Works  Package 
Contractor  for  information  only  and  as  may  be  included  in 
the Drawings.  The Works Package Contractor is at liberty to 
adopt  these  reference  designs  or  details  and  if  he  so 
chooses, however, the PDP does not warrant (and shall not 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G4‐5 of 12 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G4 – The Works
 
be  deemed  to  have  so  warranted)  the  accuracy  or 
completeness  of  any  such  designs  and/or  details  and 
disclaims any responsibility or liability to the Works Package 
Contractor or to any other person, firm or company, for the 
completeness  of,  or  any  error,  omission,  ambiguity  or 
inaccuracy in, any such designs and details. 

    (3)  Details  of  any  Temporary  Works,  methods  of  construction 


and  sequence  of  works  and  their  impact  on  existing 
buildings,  structures,  and  utilities,  etc.  shown  or  implied  by 
the  Specifications,  or  the  Drawings  or  any  reports,  are 
indicative  only  and  shall  not  relieve  the  Works  Package 
Contractor  of  his  liabilities  with  respect  to  the  design  and 
construction  of  Temporary  Works,  the  construction 
sequence  of  the  Works  and  also  their  impact  on  the 
surrounding  ground  and  structures.    Construction  shafts, 
construction  adits,  entrance  shafts,  retaining  walls,  shoring, 
grouting  for  water  cut‐off  or  ground  improvement, 
temporary  tunnel  supports,  temporary  supports  and 
pumping  tests  for  cofferdam  construction,  and  any 
construction sequences etc. shall be regarded as Temporary 
Works to be designed by the Works Package Contractor. 

    (4)  Unless  otherwise  specified  in  the  Contract,  the  Works 


Package  Contractor  shall  remove  off  Site  all  Temporary 
Works  upon  completion  of  the  related  works.    Where  the 
Works  Package  Contractor  proposes  to  leave  Temporary 
Works in place, approval from the Relevant Authorities shall 
be a prerequisite to approval from the PDP and, in any event, 
the proposed left‐in Temporary Works shall not be less than 
2m  below  finished  ground  level.    The  Works  Package 
Contractor  shall  note  that  temporary  anchors,  tie‐backs 
and/or  soil  nails  used  for  temporary  excavation  support 
should  not  permanently  encroach  into  private  lots  without 
approval from the Relevant Authorities and the PDP. 

    (5)  Notwithstanding  any  information  indicated  or  supplied  on 


the  Drawings,  the  responsibility  for  obtaining  all  permits, 
approvals and agreements from the Relevant Authorities and 
utility  undertakers  as  required  by  the  Works  Package 
Contractor to suit his construction sequence and programme 
of Works, shall remain with the Works Package Contractor. 

    (6)  Temporary Works designs shall include predictions of ground 
movements  resulting  from  the  Execution  of  the  Works  and 
the effects on adjacent buildings, utilities and other features. 
Predicted  ground  movements  shall not  exceed the  levels as 
may be specified in the Contract.  The geological model and 
the  method  of  analysis  chosen  including  any  numerical 
analysis  and  centrifuge modelling  to  be  performed,  shall  be 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G4‐6 of 12 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G4 – The Works
 
appropriate  to  the  case  being  examined  and  subject  to 
consultation with the Relevant Authorities. 

    (7)  When excavating within retaining structures and cofferdams, 
the  Works  Package  Contractor  shall  provide  sufficient 
instrumentation  to  monitor  the  ground  movement,  water 
level  and  deflection  of  the  retaining  structures  and 
cofferdam wall, and shall review the monitoring results on a 
regular basis. Actual movements shall be compared with the 
design  assumptions  in  order  to  verify  that  the  retaining 
structure and cofferdam is performing as predicted. 

    (8)  The  Works  Package  Contractor  shall  be  responsible  for 


preparing  and  obtaining  all  approvals,  permits,  or 
endorsements as appropriate from the PDP and the Relevant 
Authorities  for  the  construction  and  demolition  of  the 
temporary structures that will be constructed as part of the 
Contract. 

Independent  G4.8.2  (1)  The  Works  Package  Contractor  shall  engage  a  Contractor’s 
Checking of  Independent  Checking  Engineer  (CICE)  at  his  own  cost  to 
Design  check  and  certify  the  design  of  all  major  Temporary  Works.  
The  independent  check  shall  verify  that  the  Temporary 
Works design will not adversely affect the Permanent Works, 
third party properties, and the public. 

    (2)  The CICE shall be a Professional Engineer and an Accredited 
Checker  registered  with  the  Board  of  Engineers  Malaysia 
with  experience  in  the  design  methods  and  elements  being 
checked.  The appointment of the CICE shall be approved by 
the  PDP  one  (1)  month  prior  to  the  relevant  design 
submission. 

    (3)  The  Works  Package  Contractor  shall  submit  a  certificate 


signed  by  the  CICE  for  all  relevant  Temporary  Works  in  a 
format which shall be approved by the PDP.  Erection of the 
Temporary  Works  shall  not  commence  until  the  signed 
certificate has been approved by the PDP. 

    (4)  Loading  or  dismantling  of  the  Temporary  Works  shall  not 
commence until the Works Package Contractor has certified 
to  the  PDP  that  the  Temporary  Works  has  been  erected  in 
accordance with the design, and which shall be endorsed by 
the CICE. 

    (5)  Further  to  sub‐clause  (1)  above,  the  following  shall  be 
regarded  as  major  Temporary  Works,  but  shall  not  be 
construed to be exhaustive: 

(a)  All major Temporary Works exceeding 2.5m height; 

(b)  Any  excavation  and  lateral  support  to  resist 


KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G4‐7 of 12 Revision: 01
 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G4 – The Works
 
horizontal earth and water pressure arising from sub‐
soil conditions; 

(c)  All safety measures associated with the construction 
of rigid barriers, flexible barriers, hoardings, covered 
walkways,  fencings,  soil  nailing  and  any  boulder 
stabilization  on  slopes  to  facilitate  the  protection  of 
the workers, public and the Works; 

(d)  All  temporary  soil  nails,  rock  dowels  or  ground 


anchors; 

(e)  All  falsework  and  formwork  for  concrete  pours  of 


depths exceeding 0.4 metres each; 

(f)  Temporary  diversion  schemes  for  existing 


watercourses affected by the Works; 

(g)  Excavation,  dewatering  and  groundwater  control 


works; 

(h)  Ground treatment works; 

(i)  Scaffolding and falsework; 

(j)  Demolition works; 

(k)  Temporary road decking; 

(l)  Temporary support of utilities; 

(m)  Major concreting works; and 

(n)  Viaduct launching and support gantries. 

Off‐Site  G4.9  The  Works  Package  Contractor  shall  provide  sufficient  full‐time 
Fabrication  supervisory  staff  to  supervise  the  fabrication  of  any  identified  pre‐
Works  fabrication  element  for  the  Permanent  Works  that  is  to  be 
fabricated  off‐Site,  either  within  or  outside  Malaysia.    As  a 
minimum,  the  Works  Package  Contractor  shall  appoint  a  full‐time 
Quality  Control  Engineer  and  Supervisor  /  Foreman  to  lead  the 
supervision of the off‐Site fabrication.  The Quality Control Engineer 
and Supervisor / Foreman shall be directly employed by the Works 
Package  Contractor,  and  shall  have  adequate  experience  in  the 
specific  pre‐fabrication  element  to  ensure  compliance  with  the 
QA/QC Plan. 

Construction  G4.10  (1)  The  Works  Package  Contractor’s  construction  equipment 


equipment and  and  plant  shall  be  less  than  ten  (10)  years  old  when  first 
plant  utilised  on  the  Site  for  the  Execution  of  the  Works.    The 
equipment  and  plant  shall  have  a  full  maintenance  history 
which  shall  be  in  accordance  the  manufacturer’s 
specification. 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G4‐8 of 12 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G4 – The Works
 

    (2)  The  Works  Package  Contractor’s  construction  equipment 


and  plant  shall  be  fitted  with  protection  and  safety  related 
devices as follows: 

a)  Internal  combustion  engine  exhaust  mufflers  less 


than three (3) years old; 

b)  Reverse  travel  motion  alarms  on  all  wheeled 


equipment; 

c)  Travel  and  slew  motion  alarms  on  all  crawler 


mounted equipment; 

d)  At least one rotating beacon (yellow or orange) on all 
mobile plant and equipment; 

e)  Fully  functional  directional  indicator  lights,  brake 


warning  lights,  reversing  lights  and  driving  lights  on 
all wheeled equipment; 

f)  Task lighting on all slewing equipment; 

g)  All  engine  compartments  shall  be  enclosed  with 


proprietary  enclosure  panels  that  incorporate  noise 
suppression materials; 

h)  All  plant  and  equipment  shall  be  provided  with  at 
least one suitable fire extinguisher; 

i)  All mobile plant and equipment shall be fitted with a 
proprietary roll over protection system; 

j)  All  mobile  plant  and  equipment  shall  have 


proprietary seat belts; 

k)  all  plant  and  equipment  with  internal  combustion 


engines  that  are  to  be  operated  in  shafts, 
underground,  or  in  areas  with  restricted  air 
movement,  shall  be  fitted  with  catalytic  converters; 
and 

l)  Hose rupture valves on all hydraulic equipment. 

  G4.11  Protection of the Works 

Protection from  G4.11.1  (1)  Unless  otherwise  permitted  by  the  PDP,  all  work  shall  be 
water  carried  out,  as  near  as  may  be  practicable  in  the 
circumstances,  in  dry  conditions,  except  where  the  work  is 
required to be carried out in or with water or other fluids. 

    (2)  The  Permanent  Works,  including  materials  for  use  in  the 
Permanent  Works,  shall,  where  necessary  and  as  near  as 
may  be  practicable,  be  kept  free  of  water  and  protected 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G4‐9 of 12 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G4 – The Works
 
from  damage  due  to  water.    Water  on  the  Site  and  water 
entering  the  Site  shall  be  disposed  of  in  accordance  with 
Clause G6.2.  

    (3)  Measures  shall  be  taken  to  prevent  flotation  of  new  and 
existing structures. 

Protection from  G4.11.2  (1)  Work  shall  not  be  carried  out  in  weather  conditions  which 
weather  may adversely affect the work unless protection by methods 
approved by the PDP is provided. 
    (2)  The  Permanent  Works,  including  materials  for  the 
Permanent Works, shall be protected by methods approved 
by the PDP from exposure to weather conditions which may 
adversely affect the Permanent Works. 

Protection of  G4.11.3  (1)  Finished  work  shall  be  protected  by  methods  reviewed 
work  without objection by the PDP from damage which could arise 
from the execution of adjacent work 

(2)  As  part  of  his  coordination  responsibilities  under  Clause 


G13.3 the Works Package Contractor shall ensure, so far as is 
possible,  that  work  carried  out  by  him  or  by  Other  Works 
Contractors or utility undertakings does not cause damage to 
the previously completed works of any party and he shall be 
responsible for programming the works to minimise this risk 
and  for  proposing  protective  measures,  when  required,  to 
the PDP. 

  G4.12  Approvals from Relevant Authorities 

Local /  G4.12.1  (1)  The  Works  Package  Contractor  shall  obtain  any  necessary 
Government  work  permits  (excavation  and  or  stockpiling  of  construction 
Authorities  materials  etc.)  from  the  Relevant  Authority  prior  to  the 
Execution  of  the  Works  or  any  Temporary  Works  on,  under 
and  adjacent  to  state,  municipal  or  town  roads  from  the 
respective  road  authorities  having  jurisdiction  of  the  same, 
and shall pay all money deposits, fees and charges and other 
associated  costs  required  to  be  deposited,  given  or  paid 
under any written law, by‐laws, ordinance, regulation, rules 
and requirements in relation to the Execution of the Works 
or  any  Temporary  Works  which  are  in  effect  or  which  may 
become effective during the Contract period. 

    (2)  The  above  sub‐clause  (1)  shall  also  apply  for  obtaining 
approvals  and  work  permits  from  Malaysian  Highway 
Authority  (MHA)  and/or  other  highway  concessionaire 
companies (if any). 

Transport  G4.12.2  The Works Package Contractor shall obtain approval for way leaves 


Authority and  and  work  permits  (excavation,  laying  and  or  stockpiling  of 
Operators  construction  materials)  prior  to  the  Execution  of  the  Works  or  any 
KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G4‐10 of 12 Revision: 01
 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G4 – The Works
 
Temporary  Works  on,  under  and  adjacent  to  state,  municipal  or 
town roads from the respective transport authorities and operators 
(KTMB, ERL, STARLINK etc.) having jurisdiction of the same including 
engagement  of  consultants,  payment  of  all  money  deposits,  fees 
and  charges  and  other  associated  costs  required  to  be  deposited, 
given or paid under any written law, by‐laws, ordinance, regulation, 
rules and requirements in relation to the Execution of the Works or 
any  Temporary  Works  which  are  in  effect  or  which  may  become 
effective during the Contract period. 

Technology  G4.13  If applicable, the Works Package Contractor shall identify to the PDP 


Transfer  those  areas  of  his  expertise  which  may  be  considered  suitable 
pursuant to a programme for technology transfer. 
 
 
 
 
END OF SECTION 
   

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G4‐11 of 12 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G4 – The Works
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Page Not Used 
 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G4‐12 of 12 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G5 – Work In Roads
 

    SECTION G5 
WORK IN ROADS 
 

Maintenance of  G5.1  (1)  The  Works  Package  Contractor  shall  maintain  all  sections  of
Existing Roads,  existing  roads  and  all  bridges,  drains  and  culverts  included 
Bridges,  therein  within  the  Site  to  the  conditions  at  the  time  of
Culverts, etc.  possession of Site for the full duration of the Contract and at 
his own cost. Such maintenance shall include routine activities 
such as grass cutting, clearing of drains, patching of potholes, 
etc. He shall also be responsible for maintaining the free flow
of traffic on these sections of existing road. 

    (2)  The  Works  Package  Contractor  shall  arrange  for  the


conveyance  of  materials  and  plants  so  as  to  cause  minimum
damage  to  existing  roads  and  installations  and  minimum
inconvenience to the public. He shall not deposit or store any 
earth, rubbish, slurry, mud, materials, or equipment upon any 
road,  street,  pavement  or  footway  and  cause  hindrance  or 
obstruction  to  vehicles  or  pedestrians.    The  Works  Package 
Contractor’s trucks and equipment leaving the Site shall have 
all dirt and mud cleaned off by hosing, passing through a lorry 
wash‐trough, and other such cleaning facilities. 

    (3)  The  Works  Package  Contractor  shall  be  responsible  for  any 
damage  caused  by  any  work  carried  out  by  him,  nominated 
sub‐contractors  under  the  Contract,  or  by  his/their 
construction traffic to any existing roads or installations from
whatsoever  cause  arising  thereof  and  shall  repair,  maintain
and  reinstate  the  same  to  the  original  condition  to  the
satisfaction  of  the  PDP.  The  Works  Package  Contractor  shall
also  keep  such  roads  clear  of  construction  materials,  slurry, 
boulders and loose earth which may be dropped in the course
of transportation. For the Works Package Contractor’s trucks 
carrying sand, aggregates, earth and other loose construction
materials,  tarpaulin  or  other  suitable  materials  shall  be  used
to  cover  such  open  trucks/equipment  to  avoid  spillage  on 
roadways.    If  spillages  occur,  the  Works  Package  Contractor 
shall  immediately  clear  away  the  detritus  and  the  like  to 
reinstate the road to its original condition. 

    (4)  Upon failure on the part of the Works Package Contractor to
fulfill  his  obligations  under  this  Section,  the  PDP  may  take
whatever  action  and  any  means  necessary  to  satisfy  the
requirements,  and  all  costs  incurred  by  the  PDP  shall  be
deducted  from  any  monies  due  or  to  become  due  to  the
Works Package Contractor under this Contract. 

     
KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G5‐1 of 14 Revision: 01
 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G5 – Work In Roads
 

  G5.2  Temporary diversions and traffic management 

General  G5.2.1  (1)  Temporary  diversions  and  associated  traffic  management 


Requirements  plans  shall  be  constructed  wherever  the  Site  encroaches  on
existing  roads,  footpaths,  cycle  tracks,  access  to  properties,
etc.  No traffic signs, road markings, and other traffic control
devices  shall  be  erected,  relocated  or  removed  in  the  public
road  unless  authorised  by  the  Relevant  Authorities  and  the 
PDP. 

    (2)  Such diversion routes shall be of a standard of construction at
least  equivalent  to  that  of  the  original  road,  path,  track  or
access. They shall be constructed in advance of the closure of
the  existing  routes  and  regularly  maintained,  for  as  long  as 
required,  in  a  satisfactory  condition.  On  completion  of  the
work,  the  original  routes  shall  be  reinstated  to  their  original 
condition  to  the  approval  of  the  PDP.  The  Works  Package
Contractor shall submit for the PDP’s review his proposals for
temporary  diversions  of  traffic  at  least  twenty  one  (21)  days 
prior  to  seeking  necessary  approvals  from  the  Relevant 
Authority  in  the  form  of  a  Traffic  Management  Plan
submission  together  with  supporting  documents  (see  Clause 
G5.2.2).    For  major  diversion  schemes,  the  Works  Package
Contractor  shall  first  seek  the  opinion  of  the  relevant
stakeholders before preparing the formal submission. 

    (3)  Where  access  roads  are  to  be  permanently  closed  by  the
construction  of  the  Works,  diversion  ways  shall  not  be
required.  Such  closures  shall  not  be  implemented  until  a 
specified  alternative  access  has  been  provided  and  with  the 
written approval from the Relevant Authority and the PDP. 

    (4)  The Works Package Contractor shall maintain reasonable and 
safe  access  to  all  existing  properties  accesses  adjoining  the 
Works  during  construction,  and  shall  ensure  that  all  the 
necessary  fences,  planking,  pedestrian  walkways  and 
gangways are adequately lit to the satisfaction of the PDP. 

    (5)  Where the Works Package Contractor proposes to use existing
local streets as temporary diversion routes, he shall first seek 
the  views  of  the  PDP  before  applying  to  the  Relevant
Authority  for  approval.  The  Works  Package  Contractor  shall
maintain  these  temporary  diversion  routes  to  the  required
condition  throughout  the  entire  duration  of  the  temporary
diversion,  all  to  the  satisfaction  of  the  PDP.  If  the  Works
Package  Contractor  fails  to  maintain  these  temporary
diversion routes to the satisfaction of the PDP, the PDP shall 
have  right  to  carry  out  these  works  himself  and  all  costs
incurred shall be deducted from the Contract Sum. 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G5‐2 of 14 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G5 – Work In Roads
 

    (6)  Where, in the opinion of the PDP, a diversion is not feasible, 
construction  shall  be  planned  and  sequenced  such  that  not 
more  than  half  of  the  full  width  of  the  roadway  may  be 
occupied by the Works at any time, subject to the approval of 
the  Relevant  Authorities.  The  lengths  of  such  half‐width 
construction shall be kept as short as is practicable. 

    (7)  For  all  temporary  diversions,  the  Works  Package  Contractor


shall  provide,  install  and  maintain  adequate  temporary
construction signs in accordance with Clause G5.4. 

    (8)  Where  approved  by  the  PDP  and  the  Relevant  Authority,
temporary  closure  of  roads  and  accesses  may  be  allowed 
provided  that  adequate  detour  facilities  are  provided.
Temporary  lane  closures  are  not  permitted  unless  with  the 
prior approval of the PDP and the Relevant Authority. 

    (9)  At least twenty eight (28) days prior to commencement of his 
construction  operations  in  any  particular  area,  the  Works
Package  Contractor  shall  submit  to  the  Relevant  Authority  a
Traffic  Management  Plan  proposal  together  with  supporting 
documents for the area affect by his operations, and all such 
submissions  shall  be  copied  to  the  PDP.    Construction 
operations  shall  not  commence  until  such  proposals  have
been approved by the PDP and the Relevant Authority. 

    (10)  It  is  the  responsibility  of  the  Works  Package  Contractor  to
allow  sufficient  time  in  his  programme  for  the  preparation,
approval  and  implementation  of  the  temporary  traffic
management  plans.  Any  delay  to  the  Works  which  results 
from  the  Works  Package  Contractor's  delay  in  submission  or
from his failure to submit sufficient and correct design details 
shall be the responsibility of the Works Package Contractor. 

    (11)  The  Works  Package  Contractor’s  Traffic  Management  Team


(see  Clause  G5.10)  shall  inspect  the  temporary  traffic 
management schemes day and night, and shall carry out any 
work  to  maintain  the  scheme  as  per  the  approved  Traffic
Management  Plan,  or  as  per  the  scheme(s)  implemented 
under  Subclause  G5.2.1(13).  Traffic  lights,  lights,  road 
markings,  robotic  flagman,  variable  message  and  static  signs 
shall  be  kept  clean  and  easy  to  read.  Equipment  which  is 
damaged, dirty, incorrectly positioned or not in working order
shall be repaired, repainted or replaced immediately. 

    (12)  The  Works  Package  Contractor  shall  not  vary  the  traffic
management  scheme  without  the  prior  endorsement  of  the 
Relevant Authority and by the PDP. 

     

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G5‐3 of 14 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G5 – Work In Roads
 

    (13)  The PDP, Relevant Authority, and Police reserves the right to
modify any approved temporary traffic management scheme
during  implementation  and  after  the  scheme  has  been
implemented to suit the local traffic and road conditions.  This 
may  include  incidental  diversions/detours  away  from  works 
areas, additional traffic control devices, additional manpower,
and  additional  equipment/plant  deemed  necessary  to
alleviate traffic congestion or disruptions.  The Works Package 
Contractor,  under  no  circumstances  shall  be  entitled  to  any 
further or additional payment due to such modification.    

    (14)  The  Works  Package  Contractor  shall,  when  required  by  the
PDP,  attend  meetings  with  the  Government  Departments,
district bodies, local representatives and transport companies 
to  present  and  explain  the  proposed  traffic  management
plans, and shall prepare any necessary presentation materials
accordingly. 

    (15)  The  Works  Package  Contractor  shall,  when  required  by  the
PDP,  respond  to  complaints  on  the  temporary  traffic 
management  schemes  raised  by  members  of  the  public,  the
media, district bodies and other interested parties from time
to  time.    The  responses  and  replies  shall  be  provided  to  the
PDP within seven (7) days of receiving such complaints.  The 
Works  Package  Contractor  shall  also  inform  and  refer  to  the
PDP any complaints directly received by him arising from the 
implementation  of  the  temporary  traffic  management
schemes.  The Works Package Contractor shall respond to the
complaints in accordance with the PDP’s Complaints Handling 
Procedure  and  shall  notify  the  PDP  upon  resolution  so  that 
such actions may be verified an closed out. 

    (16)  Whenever  any  works  are  stopped  for  any  reason,  including
but not limited to, waiting for utility undertakings to carry out 
diversion works, or if required by the PDP in response to the
traffic  conditions  of  the  road,  the  Works  Package  Contractor
shall reinstate or deck over any road excavation and open the
road  to  traffic  within  a  period  specified  by  the  PDP.    The 
Works Package Contractor shall also provide traffic protection
equipment and/or traffic controllers at the affected locations
if deemed necessary by the PDP.  The temporary decking shall 
always be secured in position and shall cover the whole area 
of the trench in the carriageway without causing any danger
to  road  users.  The  provision  of  temporary  decking  shall  also 
be subject to the requirements of Clause G4.8. 

    (17)  The Works Package Contractor shall arrange and conduct road
trials,  public  briefings,  and  stakeholders’  meetings,  when
requested by the Relevant Authority for any proposed traffic 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G5‐4 of 14 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G5 – Work In Roads
 
management plan, and shall make such modifications that are 
necessary as a result of such event(s) prior to commencing the 
implementation  of  the  approved  temporary  traffic 
management plan.  

    (18)  The Works Package Contractor shall also propose, submit for
approval  and  implement  all  temporary  traffic  management
plans concerning utility diversions necessary for the Execution
of the Works. 

    (19)  The  Works  Package  Contractor  shall  assist  the  PDP  and  the
Relevant  Authority  with  the  preparation  of  plans  and
diagrammatic  representations  to  accompany  publicity
material  relating  to  the  approved  temporary  traffic
management  schemes.    The  Works  Package  Contractor  shall 
draft  a  press  release  to  accompany  each  temporary  traffic
management  scheme  submission  to  the  PDP  and  Relevant 
Authority. Public announcements prior to the implementation
of approved traffic management schemes shall only be made
by the Relevant Authority. 

    (20)  The  Works  Package  Contractor  shall  adjust  his  temporary


traffic  management  scheme(s)  and  traffic  signal  control 
settings as necessary during construction to ensure maximum
traffic  capacities  are  maintained  through  junctions,  in
consultation with the Relevant Authority. 

Traffic  G5.2.2  (1)  The  Works  Package  Contractor  shall  be  responsible  for 
Management  designing,  obtaining  approval  from  the  Relevant  Authorities
Submissions  and  implementing  all  such  temporary  traffic  management
schemes required for the Execution of the Works.  Any related
documents  prepared  and  made  available  by  the  PDP  are  for
information only. 

    (2)  Further  to  Sub‐Clauses  G5.2.1(2)  and  G5.2.1(9)  concerning 


the  submission  of  traffic  management  proposals,  the  Works 
Package  Contractor  shall  engage  a  competent  traffic 
consultant approved by the PDP to prepare: 

a)  Traffic  Management  Plans(TMP)  containing  details  of 


the  temporary  traffic  management  scheme(s)  taking 
into  consideration  and  showing  the  Works  Package 
Contractor’s  construction  sequences,  methods
(including  construction  traffic  and  access
requirements),  and  programme.    The  TMP  shall  also 
include a reference manual of relevant standards and
specifications  to  be  adopted,  organisation  structure 
for  traffic  management  which  includes  the  traffic
management  team(s)  and  emergency  response 
team(s), and the Works Package Contractor’s standard 
operating  procedures  for,  but  not  limited  to,  the
KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G5‐5 of 14 Revision: 01
 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G5 – Work In Roads
 
following: 

i)  Induction,  certification,  standard  tools  for  the 


members of the Traffic Management Team(s); 

ii)  Routine  surveillance  covering  normal  incident 


free  conditions,  minor  maintenance  activities, 
and vehicle breakdown incidents; 

iii)  Emergency  response  covering  accidents,  pipe 


bursts,  falling  trees,  construction  related 
hazards, flash floods, detours etc.; and 

iv)  Crisis  response  eg.  for  sink  holes,  collapse  of 


buildings/structures. 

b)  Traffic  Impact  Assessments  (TIA)  to  supplement  and 


support the TMP, containing traffic impact analyses to 
demonstrate  the  impact  of  the  proposed  traffic
management  scheme(s)  and  construction  traffic  on 
the  surrounding  road  and  footway  network,  including 
details  of  any  field  surveys  and  studies  conducted  to 
establish traffic conditions where appropriate. 

c)  Traffic  counts  on  the  roads  and  junctions  affected  by


the Works shall be conducted during the affected peak
hour periods of the day. The counts shall be conducted
over  a  minimum  period  of  seven  (7)  days  before  the 
implementation of the proposed TMP and of seven (7)
days  after  the  implementation  of  each  TMP  stage,  or 
in  accordance  with  the  requirements  of  the  Relevant
Authorities.  The  traffic  counts,  and  subsequent 
analysis if required, shall be used to demonstrate the 
effectiveness of the approved TMP. 

    (3)  The  TMP  and  TIA  shall  be  subjected  to  a  Road  Safety  Audit
(RSA) and endorsed by a Government registered Road Safety 
Auditor  prior  to  submission  to  the  Relevant  Authorities  for
approval.  All such submissions shall be copied to the PDP. 

    (4)  The TMP shall be prepared and executed in accordance with
one of the following documents as applicable to the Relevant 
Authority  having  jurisdiction  over  the  temporary  traffic
management proposals: 

a)  New  Guidelines  for  Traffic  Management  During 


Construction  (Road  Engineering  Association  of 
Malaysia); or 

b)  Garis  Panduan  Pelaksanaan  Pengurusan  Trafik,


Lembaga  Lebuhraya  Malaysia  document  no. 
LLM/GP/T6‐08  (Malaysia  Highway  Authority’s  Traffic 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G5‐6 of 14 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G5 – Work In Roads
 
Management Implementation Guidelines); or 

c)  ARAHAN  TEKNIK  (JALAN)  2C/85  (Manual  on  Traffic 


Control Devices for Temporary Signs and Works Zones
Control),  published  by  Cawangan  Jalan,  Ibu  Pejabat
JKR, Kuala Lumpur. 

    (5)  The  Works  Package  Contractor  shall  submit  a  Traffic  Safety 


Report to the Relevant Authorities and copied to the PDP on a 
monthly  basis  detailing  individual  traffic  incidents  involving
either accidents or vehicle breakdowns, the parties involved,
and  the  response  actions  undertaken.    In  the  event  of  any
incidents  occurring  during  the  reporting  period,  the  report 
shall  also  review  the  effectiveness  of  the  Works  Package
Contractor’s  standard  operating  procedure  for  emergency
response,  traffic  control  and  surveillance,  which  shall  be 
modified and improved if deemed necessary by the PDP. 

Implementation  G5.2.3  (1)  Sections  of  the  Project  will  be  constructed  within  highly
of the approved  trafficked  and  strategic  road  corridors  in  the  Klang  Valley 
TMP  area,  and  which  are  sensitive  to  any  operational
perturbations.  In this regard, the Works Package Contractor’s 
special  attention  is  drawn  to  the  vital  importance  of
implementing  all  traffic  management  measures  in  strict 
compliance  with  the  approved  TMP  and  any  associated
conditions  imposed  by  the  Relevant  Authorities,  in  order  to 
maintain  free  flowing  traffic  and  with  due  consideration  to
traffic safety at all times.  The Works Package Contractor shall 
be  cognisant  of  the  prevailing  traffic  conditions  at  all  times
during  the  implementation  and  operation  of  the  temporary 
traffic  management  schemes,  and  which  may  require 
supplementary signage and equipment to be provided by the 
Works  Package  Contractor,  particularly  in  relation  to  the 
provision  of  sufficient  advance  warnings  to  motorists  along 
approach routes. 

    (2)  If  the  Works  Package  Contractor  fails  to  comply  with  the 
approved  TMP  and  associated  conditions  thereof,  and  he  is 
unable  or  unwilling  or  fails  to  remedy  the  non‐compliances 
within the notified time required by the PDP, the PDP may on 
his  own  or  by  engaging  a  third  party,  remedy  the  said  non‐
compliances,  all  at  the  risk,  cost  and  expense  of  the  Works
Package  Contractor.    All  costs  and  expenses  incurred  by  the
PDP shall be recoverable from the Works Package Contractor
in  accordance  with  the  Conditions  of  Contract.    The  Works 
Package  Contractor  shall  be  responsible  for  the  completed
remedial works. 

    (3)  For works within particularly sensitive and strategic highways,
the Works Package Contractor shall implement and constantly 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G5‐7 of 14 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G5 – Work In Roads
 
monitor traffic conditions by a closed circuit television system, 
unless  existing  systems  are  already  under  operation  by  the
Relevant  Authorities.    Where  such  systems  are  required,  the
associated display monitors shall be located within the Works
Package  Contractor’s  accommodation  for  the  Traffic 
Management Manager, or the Emergency Response Team, or
other location approved by the PDP. 

Half‐width  G5.3  (1)  Where  half‐width  construction  is  necessary  and  approved  by 
Construction  the  Relevant  Authorities,  the  Works  Package  Contractor’s 
and Traffic  methodology and sequencing of the related works within the
Control  road  shall  ensure  that  at  least  half  the  full  width  shall  be 
available for use by the public at all times. 

    (2)  In  the  event  of  the  operation  of  single‐lane  traffic  becoming 
necessary  and  when  approved  by  the  Relevant  Authorities 
and the PDP on any particular length of the Works or on the
Works or on the approaches to the Works, the Works Package
Contractor shall maintain through traffic routes by providing a
width of at least 3.3 metres for single‐lane traffic. 

    (3)  The  Works  Package  Contractor  shall  appoint  a  competent


Traffic  Manager  or  Engineer  approved  by  the  PDP,  for  the 
maintenance  of  existing  roads  and  protection  of  traffic,  in 
accordance with his approved Traffic Management Plan. 

    (4)  The  Works  Package  Contractor  shall  make  suitable


arrangements  for  emergency  servicing  of  the  electrically
operated  traffic  signals  to  be  available  at  all  times.  Manually
operated “Stop/Go” signs shall only be used when: 

a)  prior approval from the PDP and Relevant Authorities
is obtained; and 

b)  the  size,  colour  and  type  comply  with  the


requirements of the Relevant Authorities. 

    (5)  At  least  twenty  one  (21)  days  notice  in  writing  of  any 
proposed  single‐way  traffic  system  shall  be  given  to  the
Relevant Authority for approval and copied to the PDP before 
such a system can be implemented. 

Temporary  G5.4  (1)  The Works Package Contractor shall at all times take full and


Traffic Signs  sufficient  precautions  to  ensure  the  safety  of  all  traffic
through and around the Work Site and of the diverted traffic.

    (2)  To  this  end  the  Works  Package  Contractor  shall  erect  and
maintain  on  the  Site  and  at  prescribed  points  on  the
approaches  to  the  Site,  all  traffic  signs,  signals  and  warning
lights  necessary  for  the  direction  and  control  of  traffic.    The
sizes  of  all  such  signs  and  the  lettering  and  wording  thereon 
shall  be  as  prescribed  in  the  Works  Package  Contractor’s 
KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G5‐8 of 14 Revision: 01
 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G5 – Work In Roads
 
approved TMP before erection.  Construction and excavation 
works  shall  be  sign  posted  and,  during  periods  of  darkness,
shall be lit to the approval of the PDP. 

    (3)  Temporary traffic signs shall comply with the requirements of
the  Relevant  Authorities,  and  shall  be  reflectorised  and  kept 
clean and legible at all times. 

    (4)  The Works Package Contractor shall position, cover or remove
these signs as may be directed by the PDP. 

Temporary  G5.5  The Works Package Contractor shall provide, maintain and remove all


Routes  temporary works including diversion roads, tracks, staging, bridging, 
etc.,  and  shall  the  routes  safe  and  suitable  in  every  respect  as  a 
passage way for its intended purpose. 

Use of roads  G5.6  (1)  The Works Package Contractor shall not make use of public or


and footways  private rights of way for depositing or storing Works Package
Contractor’s  Equipment  or  materials,  other  than  such  Works
Package  Contractor’s  Equipment,  materials,  tools  and
implements  as  shall  from  time  to  time  be  required  for
immediate use in the execution of the Works.  Works Package
Contractor’s Equipment, materials and Temporary Works shall
be  placed  in  such  a  way  as  to  cause  minimum  interference 
with the use of any right of way by the public and the Works
Package Contractor shall maintain those parts of the right of
way not temporarily occupied by the Permanent Works or the
Temporary  Works  in  a  clean,  passable  and  safe  state  at  all 
times. 

    (2)  Measures shall be taken to prevent excavated material, silt or
debris  from  entering  drainage  systems  in  roads,  footways,
cycle tracks or other paved areas; entry of water to the gullies
and catchpits shall not be obstructed. 

    (3)  Surfaced roads on the Site and leading to the Site shall not be
used  by  tracked  vehicles  unless  protection  against  damage  is
provided. 

    (4)  Barricades, guardrailing and the like shall be provided alongside
trenching  and  other  open  excavations  within  or  directly
adjacent to roads to safeguard the public. 

Pedestrian  G5.7  (1)  For  the  Works  located  at  pedestrian  facilities,  the  Works 
requirements  Package Contractor shall as far as possible maintain the access 
from  and  to  existing  shops  and  buildings.    The  locations  of
these  facilities  may  be  modified  subject  to  obtaining  further 
approval  from  the  PDP  to  suit  the  previously  approved 
temporary traffic diversion scheme. 

    (2)  The  Works  Package  Contractor  shall  ensure  that  his


operations  do  not  obstruct  or  inconvenience  pedestrians
KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G5‐9 of 14 Revision: 01
 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G5 – Work In Roads
 
using  footpaths,  staircases  and  escalators  within  the  vicinity
of the Works.  Approved temporary traffic diversions shall be 
in place prior to the commencement of any works which may
affect pedestrians. 

    (3)  Sufficient  footpath  width  shall  be  provided  to  accommodate


the normal or diverted pedestrian volumes. Unless otherwise
agreed  with  the  PDP,  the  Works  Package  Contractor  shall 
submit, not less than one (1) month prior to implementation, 
the  footpath  width  narrowing,  widening  and  diversion
proposal(s) for the PDP’s review. 

    (4)  The  Works  Package  Contractor  shall  pay  particular  attention


to  the  special  needs  of  the  blind  and  disabled  in  designing 
temporary measures for the public in and around the Site. 

    (5)  Temporary traffic diversion proposals affecting pedestrians to
be  submitted  to  the  Relevant  Authorities  for  approval  shall
include as a minimum: 

a)  pedestrian flows along the affected pedestrian routes, 
including  diversion  route(s)  if  applicable,  prior  to
implementation; 

b)  width  of  the  pedestrian  facilities  along  the  affected


pedestrian routes; 

c)  Level  Of  Service  of  the  pedestrian  route  prior  to  and
after implementation; 

d)  temporary pedestrian signage arrangements; and 

e)  analysis  of  any  associated  impacts  on  road  traffic, 


traffic signals and traffic signs. 

    (6)  Coverings,  canopies,  and  shelters  along  footpaths  which  are


required  to  be  temporarily  diverted,  shall  be  reprovided  by
the Works Package Contractor on a ‘like for like’ basis as part
of the diversion works. 

Temporary  G5.8  (1)  Where the Works interfere with or affect the operation of the 


street lighting  existing  lighting,  the  Works  Package  Contractor  shall  provide
and  maintain  temporary  street  lighting  to  the  satisfaction  of
the  PDP  and  the  Relevant  Authority.    The  Works  Package
Contractor  shall  ensure  at  all  times  that  the  level  of 
illumination conforms to the required street lighting standard.
Temporary  street  lighting  shall  be  provided  prior  to  the
removal of any existing street lighting. 

    (2)  The  Works  Package  Contractor  shall  give  adequate  notice  to


the Relevant Authority and the PDP for removal, resiting and
re‐energising of any parts of the street lighting system which

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G5‐10 of 14 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G5 – Work In Roads
 
are affected by the Works. 

Reinstatement  G5.9  Before  the  commencement  of  works  on  roads  and  footways,  the
of roads and  Works Package Contractor shall carry out a detailed survey of existing
footways  conditions including but not limited to survey data on levels, widths
and  record  photographs.    Temporary  diversions,  pedestrian  access 
and  lighting,  signing,  guarding  and  traffic  control  equipment  shall  be 
removed  immediately  by  the  Works  Package  Contractor  when  they 
are no longer required.  Roads, footways and other items affected by
temporary traffic arrangements and control shall be reinstated to new
condition  on  a  like‐for  like  basis  and  in  accordance  with  the  relevant 
standards prevailing at the time of the reinstatement or to such other
condition as may be approved by the PDP. 

  G5.10  Traffic Management Implementation Team 

Organisation  G5.10.1  (1)  The  Works  Package  Contractor  shall  establish  a  dedicated
team  to  implement  and  maintain  all  traffic  management
related  works.    The  Traffic  Management  Implementation 
Team shall be led by a Traffic Management Manager, whose 
appointment  shall  be  approved  by  the  PDP,  and  shall  be 
supported  by  Traffic  Management  Teams  and  Emergency 
Response Teams. 

    (2)  Within  twenty  eight  (28)  days  of  the  date  of  the  Letter  of 
Acceptance,  the  Works  Package  Contractor  shall  submit  the
following for approval by the PDP: 

a)  Traffic  Management  Implementation  Team 


Organisation Structure; 

b)  Reporting  structure  within  the  organisation  and 


outside the organisation; 

c)  Roles  and  responsibilities  of  each  individual  in  the 


organisation; 

d)  Maintenance and monitoring schedule and forms; 

e)  Emergency procedures and forms; 

f)  Emergency contact details of all supervisory staff; and

g)  Equipment  and  plant  assigned  to  each  component


team. 

    (3)  The  each  member  of  the  implementation  team  shall  be


equipped  with  suitable  PPE,  which  as  a  minimum  shall
comprise  a  hard  hat,  reflective  safety  vest,  gloves,  safety 
footwear,  whistle,  warning  flags  (for  Traffic  Controllers), 
baton light (for Traffic Controllers), and a two‐way radio. 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G5‐11 of 14 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G5 – Work In Roads
 

Traffic  G5.10.2  (1)  The  duty  of  the  Traffic  Management  Team  is  to  implement
Management  and  maintain  the  traffic  management  works,  control  and
Teams  monitor  traffic  conditions  where  applicable,  and  to  support 
the  Emergency  Response  Team  during  incidents  arising  from
the  Works.    Each  Traffic  Management  Team  shall,  as  a 
minimum, comprise of: 

a)  One (1) Traffic Management Officer; 

b)  One (1) Traffic Management Supervisor; and 

c)  Two  (2)  traffic  management  units  each  consisting  of 


three  (3)  Traffic  Controllers  and  one  (1)  driver  with  a 
one (1) tonne lorry. 

  Each lorry shall carry a supply of traffic management devices
such  as  battery  operated  blinking  lights,  cones,  string
delineators, baton lights, and portable flashing arrow units. 

    (2)  The  Works  Package  Contractor  shall  deploy  a  sufficient


number  of  Traffic  Management  Teams  to  implement  and
maintain  all  those  temporary  traffic  management  schemes 
under  operation  at  any  one  time.    For  the  monitoring  and 
maintenance of the traffic management works, there shall be
a minimum of one (1) Traffic Controller per kilometre of road
affected,  or  in  the  case  of  dual  carriageways,  a  minimum  of
one  (1)  Traffic  Controller  per  kilometre  of  road  in  each
direction affected. 

    (3)  The Traffic Management Teams shall maintain the temporary
road  systems  so  as  to  ensure  that  the  temporary  roads  are
kept  in  a  safe  and  roadworthy  condition.  The  maintenance
works to be carried out by the Traffic Management Teams or 
other  teams  of  the  Works  Package  Contractor  shall  include, 
but  not  be  limited  to,  the  following  activities  and  shall  be
carried out within the time limits as specified below: 

a)  removal  and  disposal  of  obstructions  on  the  roads:


within 2 hours; 

b)  repair of loose signs/plates likely to dislodge: within 2 
hours; 

c)  repair of damaged traffic signs: within 36 hours; 

d)  repair  or  replacement  of  defective  railings/safety


fence/boundary  fence/vehicle  parapets/traffic  posts
and the like: within 2 days; 

e)  removal of those parts protruding onto any part of the 
carriageway,  including  marginal  strips  and  shoulders:
within 2 hours; 
KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G5‐12 of 14 Revision: 01
 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G5 – Work In Roads
 

f)  wash  and  clear  oil  or  liquid  pollutant  on  the
carriageway: within 2 hours; 

g)  repair/replacement  of  dented  /  scratched  /  folded  /


traffic  /  directional  sign  plates  and  street  furniture; 
tightening  parts  of  street  furniture;  replacement  of
missing bolts, nuts and fittings; repair or replacement
of road traffic sign with bent supports; replacement of
broken chainage markers: within 28 days; 

h)  re‐construction  of  footings  of  traffic/directional  signs 


and  street  furniture  with  loose  footings:  within  28
days; 

i)  cleaning of all traffic signs, directional signs (including
those  on  the  sign  gantries),  sign  faces,  barriers  (all
types),  safety  fences  (all  types),  parapets  (all  types), 
railings  (all  types),  rails  (all  types),  crash  cushions,
emergency  crash  gates,  concrete  profile  barriers,
water  filled  barriers,  inner  face  of  noise  barriers  and
semi‐noise enclosure (all types), other street furniture, 
and  outer  face  of  temporary  noise  barrier  and 
hoardings: every month; 

j)  regular  inspection  and cleaning  of road  drainage,  and


cleaning  up  blocked  drains  within  flooded  areas: 
within the shortest possible time; 

k)  repair of potholes: within 12 hours; 

l)  making  good  of  running  surfaces  (including  but  not


limited  to  unevenness  and  loose  chippings):
immediately; and 

m)  other  defects  identified  by  the  PDP,  within  a 


timeframe as directed by the PDP. 

Emergency  G5.10.3  (1)  The duty of the Emergency Response Team is to manage any


Response Team  traffic incidents and accidents arising from the Works, and to
liaise and support the PDP’s emergency response procedures 
and  the  public  emergency  services  if  required.    The
Emergency Response Team shall be available at all times and 
shall, as a minimum, comprise of: 

a)  One (1) Traffic Management Officer, who may also be
leading a Traffic Management Team; 

b)  One  (1)  Emergency  Response  Team  Supervisor


equipped  with  a  motorcycle  and  radio
communications  for  rapid  access  and  response  in  the 
event of traffic congestion arising from an incident; 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G5‐13 of 14 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G5 – Work In Roads
 

c)  Two  (2)  emergency  response  units  each  consisting  of


one (1) Traffic Controller and one (1) driver with a one 
(1) tonne lorry; and 

d)  One (1) driver with a tow truck on standby at all times 
within or in close proximity to the Site; and 

e)  Pre‐arranged call out tow service with heavy duty tow
truck(s) available. 

    (2)  When  informed  of  an  incident  from  the  Traffic  Management
Team  or  from  an  external  source,  the  Emergency  Response 
Team  shall  be  responsible,  but  not  limited  to,  the  following
duties: 

a)  immediately  deployed  to  take  charge  and  control  of 


the  traffic  within  a  target  response  time  of  five  (5) 
minutes; 

b)  call  ‘999’  or  any  pre‐arranged  contacts  with  the 


emergency services; 

c)  notify the PDP/MRT hotline manager; and 

d)  assist the emergency service(s) on location. 

  In  addition  to  the  incident  report(s)  prepared  by  the


emergency service(s), the Works Package Contractor shall also
investigate  the  incident,  the  findings  of  which  shall  be 
documented  and  appended  to  the  monthly  Traffic  Safety
Report described in Sub‐clause G5.2.2(5). 
 
 
 
 
END OF SECTION 
 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G5‐14 of 14 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G6 – Damage and Interference
 

    SECTION G6 
DAMAGE AND INTERFERENCE 
 

Damage and  G6.1  (1)  Work shall be carried out in such a manner that, as far as is 


interference  practicable,  there  is  no  damage  to  or  interference  with  the 
following,  other  than  such  damage  as  is  required  to  enable 
the execution of the Works: 

a)  watercourses,  drainage  systems,  open  channels  and 


sewerage systems; 

b)  utilities,  existing  structures,  roads  including  street 


furniture, or other property; 

c)  existing railways and railway systems; 

d)  public  or  private  vehicular  or  pedestrian  accesses; 


and 

e)  trees, graves or burial urns. 

  The  Works  Package  Contractor  shall  not  divert,  remove  or 


relocate  any  such  item,  utility  or  thing  without  such 
diversion,  removal,  or  relocation  having  been  approved  by 
the Relevant Authority or utility undertaking. 

    (2)  The Works Package Contractor shall inform the PDP as soon 
as practicable of any item, utility or thing which is not stated 
in the Contract as requiring diversion, removal or relocation 
but  which  the  Works  Package  Contractor  considers  as 
requiring  diversion,  removal  or  relocation  to  enable  the 
Works to be executed.   

    (3)  Items  which  are  damaged  or  interfered  with  as  a  result  of 
the  work  being  carried  out  and  items  which  are  diverted, 
removed or relocated to enable the work to be carried out, 
shall  be  reinstated  to  the  same  condition  as  was  existing 
before the work started or to such other condition as may be 
approved or directed by the PDP. 

    (4)   Prior  to  trench  excavation,  the  Works  Package  Contractor 


shall  carry  out  investigations  to  locate  utilities  and  other 
underground  installations  by  means  of  hand‐dug  inspection 
pits.  The locations and number of inspection pits required in 
meeting  the  Works  Package  Contractor's  obligations  to 
establish  the  location  of  existing  utilities  and  underground 
features  shall  be  determined  by  the  Works  Package 
Contractor.    The  Works  Package  Contractor  shall  note  that 
many  existing  pipes/ducts/cables  may  not  be  shown  in  the 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G6‐1 of 16 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G6 – Damage and Interference
 
records  kept  by  the  utility  undertakings,  and  may  only  be 
exposed as the excavation proceeds.  The trench excavation 
shall  be  carried  out  by  hand  where  there  are  utilities 
adjacent  to  or  within  the  excavation  works  and  the  Works 
Package Contractor shall have allowed in his programme the 
time  required  for  the  exposing,  temporary  support  and 
diversion  of  these  recorded  or  unrecorded  utilities.    Should 
any  pipes/ducts/cables  or  cover  tiles  be  exposed,  the 
respective  utility  undertaking  shall  be  contacted  to 
determine  if  all  the  utilities  have  been  located.    Cover  tiles 
and utilities shall only be removed by the utility undertakings 
concerned. 

    (5)  Where  the  PDP  has  previously  conducted  utility,  ground 


investigation,  and  surveys  of  buildings  and  structures  in 
relation  to  the  Works,  the  data  obtained  from  such 
investigations may be obtained from the PDP. 

Watercourses  G6.2  (1)  Existing  watercourses  and  drainage  systems  shall  be 
and drainage  temporarily diverted as required to enable the Works to be 
systems  carried  out.    Particulars  of  the  diversions  proposed  by  the 
Works  Package  Contractor,  shall  be  submitted  to  the 
Relevant Authority and the PDP for approval at least twenty 
one  (21)  days  before  the  relevant  work  starts  or  other 
duration as may be required by the Relevant Authority.  The 
findings  of  the  submission  will  be  used  as  the  basis  for 
setting  any  requirements  on  drainage  provisions,  flooding 
mitigation  measures  and  performance  monitoring  tasks 
which  may  be  placed  on  the  Works.    Any  mitigation 
measures  shall  be  completed  before  the  diversion  or 
obstruction  giving  rise  to  the  impact  is  effected.    The 
diversions  shall  be  maintained  while  the  work  is  being 
carried out and shall be reinstated, including the removal of 
any  obstructions  to  flow,  as  soon  as  practicable  after  the 
work is complete. 

    (2)  Discharges into the sea, watercourses and either to storm or 
foul  drainage  systems  shall  not  exceed  the  limits  permitted 
by the Relevant Authorities.  The Works Package Contractor 
shall immediately rectify any exceedances of these limits. 

    (3)   Runoff  from  the  Site  shall  be  controlled  to  ensure  that 
adjacent areas are not affected and disturbance to the public 
is  kept  to  a  minimum.    Under  no  circumstances  shall  foul 
sewage flow be diverted into existing stormwater drains and 
vice  versa.    Should  the  Works  Package  Contractor  discover 
that  existing  foul  sewage  flow  has  been  connected  into  a 
stormwater drain, or vice versa, he shall immediately notify 
the PDP and Relevant Authority. 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G6‐2 of 16 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G6 – Damage and Interference
 

    (4)  All  Works  conducted  in  or  affecting  drainage  facilities, 


including  watercourses,  shall  be  conducted  such  that  the 
capacity  of  the  facility  will  be  sufficient  to  accommodate 
design flows as required by the Relevant Authority. 

    (5)  No  temporary  or  permanent  structure  shall  be  erected 


within  areas  designated  as  a  drainage  reserve  unless  with 
the prior approval from the Relevant Authority.  Any planting 
within  the  drainage  reserve  shall  be  limited  to  plants  and 
shrubs  with  shallow  rooting  systems.    The  Relevant 
Authority’s officers and workmen shall have free access at all 
times  to  the  said  area  for  the  purpose  of  laying,  repairing 
and maintaining drains, sewers and all other services across, 
through  or  under  it  which  the  Relevant  Authority  may 
require. 

  G6.3  Utilities and other services 

Location and  G6.3.1  (1)  The  Works  Package  Contractor  shall  be  responsible  for 
protection of  locating  the  position  of  all  public  and  other  utility 
utilities  installations,  including  water  mains,  overhead  and 
underground cables, pipes, sewers and drains and all service 
connections  to  buildings,  and  where  necessary,  shall  adopt 
such methods of excavation as may required by the Relevant 
Authorities or owners to ensure that no damage is caused to 
them. 

    (2)  The details of existing utilities where available, are given for 
information  only  and  the  accuracy  of  the  details  is  not 
warranted.    The  Works  Package  Contractor  shall  make  his 
own enquiries and shall use underground services detection 
equipment  to  locate  underground  utilities.  The  Works 
Package  Contractor  shall  take  notice  of  the  limitations  of 
such  equipment  and  shall  carefully  excavate  hand‐dug  trial 
holes to locate accurately the utilities indicated to him by the 
utility undertakings. Portable mechanical tools may be used 
but  shall  be  restricted  to  the  breaking  of  the  pavement 
surface.  Due  care  shall  be  exercised  to  prevent  damage  to 
underground  cables,  water  pipes,  gas  pipes  or  other  utility 
installations. 

    (3)  The  Works  Package  Contractor  shall  make  good,  at  his  own 
expense, any damage caused by him to the existing services 
to the approval of and in accordance with the instruction of 
the appropriate authority or owner concerned. 

    (4)  All such installations which are encountered in the course of 
the Works shall be adequately supported, slung‐up, strutted 
or  otherwise  protected  from  damage  to  the  satisfaction  of 
the Relevant Authority or owner. 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G6‐3 of 16 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G6 – Damage and Interference
 

    (5)  The Works Package Contractor shall inform the PDP and the 
utility undertakings without delay of the following: 

    a)  damage to utilities; 

    b)  leakage of utilities; 

    c)  discovery of utilities not shown on any records; and 

    d)  diversion,  removal,  repositioning  or  re‐erection  of 


utilities which is required to enable the execution of 
the Works.  

    (6)  Smoking  and  use  of  naked  flames  shall  be  prohibited  if  gas 
pipes are present. 

Diversion of  G6.3.2  (1)  Unless  specified  otherwise,  the  temporary  diversion  or 
utilities and  relocation  of  any  service  within  or  outside  the  Works  to 
services  permit  the  construction  of  the  Works  shall  be  the 
responsibility  of  the  Works  Package  Contractor.    Where  a 
service is required to be interrupted or relocated, the Works 
Package  Contractor  shall  inform  and  obtain  the  approval  of 
the appropriate authority or owner, of the required removal 
and/or relocation. 

    (2)  Temporary  diversion  shall  mean  works  involved  in  the 


diversion  of  services  that  will  be  reinstated  to  their  original 
position  and  condition  on  completion  of  the  works  in  the 
affected  areas.    In  planning  his  work  for  the  diversion  or 
relocation  of  services,  the  Works  Package  Contractor  shall 
make reasonable allowance for the time necessary to obtain 
the  PDP’s  approval  for  the  work  and  for  the  appropriate 
authorities  or  owners  to  authorise  the  work,  obtain  the 
necessary materials and carry out the work. 

    (3)  The  Works  Package  Contractor  shall  not  be  entitled  to  any 
extension of time due to his failure to allow for a reasonable 
period  of  time  necessary  for  obtaining  approval  and 
completing the work. 

    (4)  The  temporary  diversion  or  relocation  of  any  service  within 
or  outside  the  Works  to  permit  the  construction  of  the 
Works  shall  be  the  responsibility  of  the  Works  Package 
Contractor.  The  Works  Package  Contractor  shall  be 
responsible for arranging with the Relevant Authority for all 
temporary diversions required in connection with the Works. 
He shall keep the PDP fully informed of his negotiations. No 
final  arrangements  shall  be  made  without  the  approval  of 
the PDP. 

    (5)  All  temporary  diversions  shall  be  subject  to  the  approval  of 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G6‐4 of 16 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G6 – Damage and Interference
 
the PDP and the Relevant Authority or owner. The cost of all 
temporary  diversions  whether  undertaken  by  the  Works 
Package Contractor or a Service Authority or their contractor 
shall be borne or paid for by the Works Package Contractor. 

    (6)  Maintenance  of  existing  services  shall  also  include  street 


lights, traffic lights and road furniture. 

Coordination of  G6.3.3  (1)  The  Works  Package  Contractor  shall  co‐ordinate  the 
utilities related   activities  of  the  utility  undertakings  in  connection  with  the 
works  diversion of utility services necessary for the execution of the 
Works and shall take all steps necessary to enable the utility 
undertakings to proceed in accordance with the programme 
agreed  between  the  Works  Package  Contractor  and  the 
utility undertakings. 

    (2)  The Works Package Contractor shall monitor the progress of 
utility undertakings against the agreed programmes and shall 
notify the PDP of any slippage to these programmes.  In the 
event  of  any  such  slippage  the  Works  Package  Contractor 
shall prepare and execute a plan of action with the relevant 
utility undertaking to redress the slippage.  Such a plan may, 
if necessary, include provision of Works Package Contractor's 
labour  resources,  materials  and/or  plant  to  the  utility 
undertaking. 

Recording of  G6.3.4  (1)  Records of existing utilities encountered shall be kept by the 


utilities and  Works  Package  Contractor  on  the  Site  and  a  copy  provided 
services  for  the  PDP  and  the  relevant  owners.    The  records  shall  be 
agreed by the PDP and shall contain the following details: 

    a)  location of utility; 

    b)  date on which utility was encountered; 

    c)  nature and size of utility; 

    d)  condition  of  utility  with  photographs  and  video 


survey recordings for drainage and sewerage systems 
(Clause G1.11.1 refers); and 

    e)  temporary or permanent supports provided. 

    (2)  The Works Package Contractor shall produce as‐built records 
of  all  newly  laid  utilities  and  services  and  all  relocated 
utilities and services within the Site, and shall submit them to 
the  PDP  and  the  corresponding  utility  undertaking  for 
record. 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G6‐5 of 16 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G6 – Damage and Interference
 

Condition  G6.4  (1)  The  Works  Package  Contractor  shall  carry  out  a  pre‐
survey of  construction  condition  survey  of  all  existing  buildings  and 
existing  structures  located  within  the  influence  zone  of  the  Works 
buildings and  which  may  be  within  or  adjacent  to  the  Site,  in  accordance 
structures  with the requirements of the Particular Specification (Clause 
G1.11.1(9) also refers). 

(2)  The condition survey shall be undertaken by an independent 
surveyor engaged by the Works Package Contractor and who 
shall be approved by the PDP. 

(3)  Construction activities with the potential to cause damage or 
interference with any existing buildings and structures within 
the  vicinity  of  the  related  works,  shall  not  commence  until 
the  condition  survey  for  those  properties  have  been 
approved by the PDP. 

Structures,  G6.5  The Works Package Contractor shall immediately inform the PDP of 


roads and other  any damage to structures, roads or other property which are not to 
property  be demolished as part of the Works. 

Trees and other  G6.6  (1)  Trees which are to be retained or which are not required to 


similar  be  removed  in  order  to  carry  out  the  Works,  shall  be 
obstructions  protected from damage at all times by methods approved by 
the PDP.  Materials, including excavated materials, shall not 
be banked around such trees and they shall not be trimmed 
or cut without having been approved by the PDP. 

    (2)  If  any  trees  are  to  be  removed  during  the  execution  of  the 
Works,  the  Works  Package  Contractor  shall  prepare  and 
submit  the  necessary  Tree  Cutting  Permit  to  the  Relevant 
Authority  for  approval.    Trees  shall  not  be  cut  or  relocated 
until such approval is granted. 

    (3)  If  any  tree(s)  which  are  to  be  retained  or  which  are  not 
required to be removed in order to carry out the Works are 
damaged  by  the  Works  Package  Contractor  and  in  the 
opinion  of  the  Relevant  Authority  and  the  PDP  cannot  be 
rejuvenated to its original condition prior to the occurrence 
of  the  damage,  the  Works  Package  Contractor  shall  replace 
the tree(s) with similar species, size and form as approved by 
the PDP. 

Avoidance of  G6.7  The Works Package Contractor shall take all reasonable precautions 


nuisance  to  avoid  causing  a  nuisance  with  dust,  noise  or  vibrations  arising 
from  his  operations.    The  Works  Package  Contractor’s  attention  is 
also drawn to the related requirements contained in Section G11. 

     

     

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G6‐6 of 16 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G6 – Damage and Interference
 

  G6.8  Protection of Existing Railways 

Works near  G6.8.1  It is imperative that the construction activities of the Works Package 


existing railways  Contractor  must  not  disrupt,  interfere,  or  endanger  the  operations 
of the LRT, KTM, KL Monorail, and KLIA Ekspres railways and transit 
systems  of  the  Klang  Valley.  References  to  railways  in  the 
Specifications shall also mean guideway based transit systems. Any 
works near or within the railways shall not commence without the 
necessary approval of the relevant Railway Operator for the Works 
Package Contractor’s protection proposals if required. 

Designated  G6.8.2  (1)  Where  any  part  of  the  Works  or  the  Site  fall  within  a 
Railway  designated railway protection zone of an existing railway or 
Protection Zone  transit  system,  as  defined  under  relevant  railway  related 
enactments,  the  Works  Package  Contractor  shall  comply 
with  the  safety  and  protection  related  requirements  of  the 
relevant  Railway  Operator.    If  no  protection  zone  has  been 
formally  designated  for  a  particular  railway,  a  notional 
protection  zone  of  30m  either  side  of  the  railway  lot 
boundary  shall  be  assumed,  or  as  agreed  with  the  Railway 
Operator. 

    (2)  No  works  including  site  investigation,  shall  be  undertaken 


within  the  railway  protection  zone  unless  details  of  the 
proposed  works  including  method  statements  and  any 
protection measures if required have been approved by the 
Railway  Operator  and  the  PDP  beforehand.    Once  approval 
has been granted, the Works Package Contractor shall abide 
by  the  requirements  and  conditions  set  by  the  Railway 
Operator. 

Working within  G6.8.3  (1)  When  the  Works  Package  Contractor  is  required  to  work 
the Railway  within  the  railway  protection  zone  or  within  areas  of  the 
Protection Zone  operating  railway  therein,  the  requirements  stated  in  the 
regulations  of  the  railway  and  the  associated  Statutory 
Requirements shall be strictly followed. 

(2)  The  Works  Package  Contractor  shall  ensure  that  his  works 
programme and method statements include the restrictions 
imposed by the operating railway (including the payment of 
any related fees) including: 

    a)  The need for track possessions for all work within or 
adjacent to operating tracks; 

b)  Track  access  being  under  the  control  of  the  Railway 
Operator, with track related works only to be carried 
out  in  non‐traffic  hours,  as  determined  by  the 
relevant Railway Operator; 

c)  The  Works  Package Contractor  shall  provide  suitably 


KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G6‐7 of 16 Revision: 01
 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G6 – Damage and Interference
 
trained  staff  to  undertaken  safety  and  coordination 
duties along the trackside; 

d)  Within  stations,  depots  and  ancillary  buildings 


restrictions  on  access  during  to  non‐operational 
hours; 

e)  Provision of trained fire marshalls and lookouts; 

f)  The need for multi‐stage working; 

g)  Impact  assessment  of  the  works  on  the  operating 


railway  and  how  disruption  to  train  services  and 
passengers will be mitigated in consultation with the 
Railway Operator; 

h)  Provision  of  contingency  plans  and  materials  in  the 


event of a problem associated with the Works; 

i)  The  need  for  gauge  checking  and  line  clearance 


before  the  commencement  of  revenue  service  each 
day; and 

j)  Protection  of  existing  railway  infrastructure,  cables 


and rolling stock. 

  G6.9  Electromagnetic Compatibility 

General  G6.9.1  (1)  Electromagnetic compatibility (EMC) is defined as the ability 


of  an  equipment  or  system  to  function  satisfactorily  in  its 
electromagnetic  environment  without  introducing 
intolerable electromagnetic disturbances to other equipment 
or system in that environment. 

(2)  This  Section  G6.9  contains  details  of  the  minimum  EMC 
requirements for this Contract.  The requirements cover EMC 
between  equipment  under  this  Contract  and  other 
equipment on provided in the Project and adjacent railways 
and  transit  systems.    All  Plant  under  this  Contract  shall 
operate reliably in terms of performance and functionality in 
the  electromagnetic  environment  of  the  railway  under 
construction and shall not affect other railways and transits 
systems within the vicinity of the Project. 

(3)  A  list  of  standards  relevant  to  EMC  is  included  in  Appendix 
AG6.1 for reference. 

Scope  G6.9.2  Plant which might cause electro‐magnetic disturbance shall include, 


but not be limited to the following: 

Luminaries 

a)  Station/tunnel lighting 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G6‐8 of 16 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G6 – Damage and Interference
 

b)  Emergency lighting 

c)  Illuminated signage and advertising panels 

Motor operated equipment 

a)  Chiller Plant 

b)  Air Conditioning Units, including but not limited to packaged 
AC units, unitary systems, fan coil units, etc 

c)  Air  Handling  Units,  computer  room  air  conditioning  units, 


etc. 

d)  Fans 

e)  Motor Operated Dampers/Air Flow Regulators 

f)  Pumps 

g)  Actuators 

    Power Distribution 

a)  HV/LV switchgear 

b)  Transformers 

c)  Power Factors Correction Equipment 

d)  Harmonic Filters 

e)  Uninterruptible Power Supply 

f)  Centralised Battery System 

g)  Power Cables and Distribution 

    Control Systems/microprocessor based system 

a)  Building  Management  System,  including  the  Local  and 


Central Control Equipment 

b)  Status monitoring systems 

c)  Control panels 

d)  Motor Control Centres 

e)  Sensors and/or Limit Switches 

f)  ELV Cables and Distribution 

Potential  G6.9.3  The Other Works Contractors’ and third party equipment / systems 


equipment /  most likely to be affected by EMC typically includes: 
systems 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G6‐9 of 16 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G6 – Damage and Interference
 
affected 
a)  Video display units/ monitors 

b)  Computers / microprocessor based systems 

c)  Communication  systems  including  such  as  telephones, 


mobile  communication  equipment,  radios,  and  public 
address systems 

d)  Train control and signalling systems 

Certification  G6.9.4  Plant  supplied  by  the  Works  Package  Contractor  deemed  likely  to 
produce electromagnetic disturbance shall be tested and certified to 
meet  the  minimum  requirements  specified  in  the  relevant  EMC 
standards and to the satisfaction of the PDP. 

Interference  G6.9.5  The Works Package Contractor shall take into account the following 


considerations  interference  mechanisms  in  his  design  of  Plant,  and  shall  take  all 
necessary measures to eliminate their potential adverse impacts on 
the  operation  of  the  railway  under  construction  as  well  as  existing 
railway in the vicinity of the Works. 

    (1)  Radiated interference ‐ The performance of equipment shall 
meet  the  relevant  EMC  related  specifications  at  their 
installed  locations  under  the  radiated  interference  of 
radiating antennas and/or handheld transceivers. 

(2)  Induced  interference  ‐  The  Works  Package  Contractor  shall 


ensure  that  any  signal  and  control  cables  other  than  power 
cables  used  by  one  system  are  properly  screened,  bonded 
and  earthed  to  prevent  noise  and  electric  shock  from 
exceeding the levels of:‐ 

a)  Longitudinal voltage to earth (continuous) ‐ 60V 

b)  Longitudinal voltage to earth (fault condition) ‐ 430V 

c)  Psophometrically weighted transverse voltage; 1mV 

(3)  Electrostatic  discharge  –  Any  equipment  which  contains 


sensitive  electronic  components  and  is  likely  to  be  handled 
or  touched  by  persons  shall  be  protected  against 
electrostatic  discharge.  Equipment  shall  be  tested  to  8kV 
using  air  discharge  or  6kV  using  contact  discharge  in 
accordance with EN 61000‐4‐2. 

(4)  Conducted  interference  ‐  Contractor  shall  submit 


information  on  magnitudes  and  duration  of  a.c.  fault 
currents,  including  line‐to‐line  fault  and  line‐to‐earth  fault 
throughout the low voltage power supply system to the PDP 
for  approval.    As  a  minimum  requirement,  the  maximum 
levels  of  conducted  electromagnetic  interference  of  the 
installation shall not exceed the levels specified in EN 61000‐

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G6‐10 of 16 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G6 – Damage and Interference
 
6‐2. 

(5)  Fast  transient  /  burst  –  Equipment  shall  be  tested  to  2kV 
peak as defined in EN 61000‐4‐4. 

(6)  Surge – Equipment shall be tested to 2kV (common mode) / 
1kV (differential mode) as defined in EN 61000‐4‐5. 

Electromagnetic  G6.9.5  (1)  The  Contractor  shall  ensure  that  the  EMI  generated  by  the 
interference  equipment under this Contract does not adversely affect the 
(EMI)  sensitive electronic equipment installed adjacent to them. As 
a minimum, the maximum emission levels of the equipment 
shall not exceed the levels specified in EN 61000‐6‐4. 

(2)  Any  sensitive  electronic  equipment  supplied  will  operate  in 


an  environment  with  substantial  amount  of  radiated 
interference  present.  The  equipment  may  be  subjected  to 
radiated  energy  from  handheld  transceivers  and  other 
communications systems. 

(3)  As a minimum, the immunity levels of equipment shall meet 
the requirements specified in EN 61000‐6‐2. 

    (4)  Electrical  Motor  Operated  Equipment  ‐  For  electrical  motor 


operated  equipment  such  as  for  environmental  control 
systems  (ECS)  and  pumps,  the  disturbance  voltage  and 
disturbance power shall meet the requirements specified in 
the European Standard EN 61000‐6‐2 and EN 61000‐6‐4. 

(5)  Microprocessor  Based  Control  Equipment  ‐  For 


microprocessor  based  control  equipment  such  as  the  ECS, 
the  equipment  shall  be  immune  to  the  following  conditions 
as specified in the European Standard EN 61000‐6‐2: 

a)  Radiated field susceptibility ‐  80‐1000MHz,  10V/m, 


80% A.M. modulated at 1kHz. 

b)  Conducted  radio  frequency  susceptibility  ‐  150kHz  ‐ 


80MHz, 10Vrms (unmod). 

c)  Surges (Power line) ‐ 2kV (peak) common mode, 1kV 
(peak) differential mode. 

d)  Fast  burst  transients  (Power  line  and  signal  line) 


power lines ‐ 2kV (peak). 

e)  Electrostatic  discharge  ‐  8kV  air  discharge,  6kV 


contact discharge. 

    (6)  Fluorescent  Lamps  and  Luminaires  ‐  All  lighting  equipment 


with  a  primary  function  of  generating  and/or  distributing 
light  intended  for  illumination  purposes  and  connected  to 
the  low  voltage  electricity  supply  or  battery  operation  shall 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G6‐11 of 16 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G6 – Damage and Interference
 
meet  the  emission  requirements  of  European  Standard  EN 
55015.    The  specification  provides  minimum  limits  for 
lighting  devices  operating  at  frequencies  higher  than  100Hz 
for the following: 

a)  disturbance voltages at the mains supply terminals in 
the range of 9kHz to 30MHz; and 

b)  radiated  magnetic  field  interference  in  the  range  of 


9kHz to 30MHz. 

    (7)  Light  Dimmers  ‐  Light  dimmers  incorporating  regulation 


control (if any) shall meet the requirements for disturbance 
voltage on their input and output in the frequency range of 
48.5kHz  to  30MHz  using  incandescent  lamps  to  provide  the 
correct load specified in the European Standard EN 55014. 

EMC  G6.9.6  (1)  The  Works  Package  Contractor  shall  nominate  an  EMC 
Management  coordinator  to  coordinate  all  EMC  matters.    The  EMC 
coordinator shall be an experienced professional in the EMC 
field. 

(2)  The  Works  Package  Contractor  shall  interface,  liaise,  co‐


ordinate  and  exchange  EMC  data  with  Other  Works 
Contractors to ensure EMC integrity in the design stage, and 
to  appropriately  demonstrate  compatibility  in  the  testing 
and  commissioning  stage  of  the  Project  in  conjunction  with 
the  Other  Works  Contractors.    The  Works  Package 
Contractor shall submit a copy of all EMC related information 
exchange to the PDP for reference. 

    (3)  The Works Package Contractor shall prepare and submit for 
approval  by  the  PDP  an  EMC  Management  Plan.  The  Plan 
shall  

a)  define  the  EMC  philosophy,  activities,  means  of 


control  for  the  design  processes  and  EMC 
submissions,  to  be  supplied  to  demonstrate 
compliance with the Specifications;  

b)  identify  a  comprehensive  list  of  specifications, 


standards, method statements and procedures to be 
submitted to the PDP for review;  

c)  include  an  initial  list  of  design  documentation,  test 


specifications  and  test  reports  with  a  single 
paragraph  description  of  each  document  to  indicate 
compliance with the Specifications; 

d)  include  a  programme  which  shall  identify  the  dates 


for EMC submissions;  

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G6‐12 of 16 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G6 – Damage and Interference
 

e)  include  a  definition  and  description  of  the  process 


and  methods  used  for  verification  and  validation  of 
the  Works  compliance  with  the  required  EMC 
parameters in all respects; 

f)  designate  a  person  as  the  point  of  contact  to  deal 
with EMC matters; and 

g)  provide  details  of  the  nominated  person  and  any 


subsequent  change  of  the  nominated  person  for 
approval by the PDP. 

    (4)  The  Works  Package  Contractor  shall  demonstrate  that  the 


Plant  complies  with  the  EMC  requirements  in  the  factory 
during the Factory Acceptance Test stage. 

    (5)  In  the  Testing  and  Commissioning  phase  of  the  Project,  the 
Works  Package  Contractor  shall  verify,  in  co‐operation  with 
all  Other  Works  Contractors,  through  testing  on‐site  that 
their  systems  are  electromagnetically  compatible.    The 
concerned  contractors  shall  demonstrate  that  their 
respective systems operate to the specification requirements 
in the design environment where all the items of equipment 
of the railway as a whole are set to operate. 
 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G6‐13 of 16 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G6 – Damage and Interference
 
APPENDIX AG6.1 
REFERENCE LIST OF STANDARDS RELATING TO EMC 
 
IEC TR 1000‐2‐5  Electromagnetic  compatibility  (EMC).    Environment.    Classification  of 
electromagnetic environments.  Basic EMC publication 

BS 4727‐1  Glossary  of  electro  technical,  power,  telecommunication,  electronic, 


lighting  and  colour  terms.    Terms  common  to  power,  telecommunications 
and electronic.  Electromagnetic compatibility 
IEC 60050(121)   International Electrotechnical Vocabulary – Chapter 121: Electromagnetism 
IEC 61000‐2‐7  Electromagnetic  compatibility  (EMC).    Environment.    Low  frequency 
magnetic fields in various environments 
IEC 61000‐3‐8  Electromagnetic  compatibility  (EMC).    Limits.    Guide  to  signalling  on  low‐
voltage  electrical  installations.    Emission  levels,  frequency  bands  and 
electromagnetic disturbance levels 
IEC 61000‐5‐1  Electromagnetic compatibility (EMC).  Installation and mitigation guidelines.  
General considerations.  Basic ENC publication 
IEC 61000‐5‐2  Electromagnetic compatibility (EMC).  Installation and mitigation guidelines.  
Earthing and cabling 
DD IEC TS  Electromagnetic  compatibility  (EMC).    General.    Methodology  for  the 
61000‐1‐2  achievement of the functional safety of electrical and electronic equipment 
with regard to electromagnetic phenomena 

EN 12015  Electromagnetic compatibility.  Product family standard for lifts, escalators 
and passenger conveyors.  Emission 

EN 12016  Electromagnetic compatibility.  Product family standard for lifts, escalators 
and passenger conveyors.  Immunity 

EN 13309  Construction  machinery.    Electromagnetic  compatibility  of  machines  with 


internal electrical power supply. 

EN 50091‐2  Specification  for  Uninterruptible  Power  Systems  (UPS)  Part  2  EMC 


Requirements 

EN 50121‐1  Railway Applications EMC Part 1: General 

EN 50121‐2  Railway applications.  Electromagnetic compatibility.  Emission of the whole 
railway system to the outside world 

EN 50121‐3‐1  Railway  applications.    Electromagnetic  compatibility.    Rolling  stock.    Train 


and complete vehicle 

EN 50121‐3‐2  Railway  applications.    Electromagnetic  compatibility.    Rolling  stock.  


Apparatus 
 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G6‐14 of 16 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G6 – Damage and Interference
 
REFERENCE LIST OF STANDARDS RELATING TO EMC  (continued) 
 

EN 50121‐4  Railway  applications.    Electromagnetic  compatibility.    Emission  and 


immunity of the signalling and telecommunications apparatus 

EN 50121‐5  Railway  Applications  EMC  Part  5:  Emission  and  Immunity  of  Fixed  Power 
Supply Installations and Apparatus 

EN 50130‐4  Alarm  systems.    Electromagnetic  compatibility.    Product  family  standard:  


Immunity  requirements  for  components  of  fire,  intruder  and  social  alarm 
systems 

EN 50263  Electromagnetic  compatibility  (EMC).    Product  standard  for  measuring 


relays and protection equipment 

EN 50270  Electromagnetic  compatibility.    Electrical  apparatus  for  the  detection  and 


measurement of combustible gases, toxic gases or oxygen 

EN 55011  Industrial,  scientific,  and  medial  (ISM)  radio‐frequency  equipment  ‐  Radio 


disturbance characteristics ‐ Limits and methods of measurement 

EN 55014  Limits and methods of measurement of radio disturbance characteristics of 
electrical motor operated and thermal appliances for household and similar 
purposes, electric tools and similar electrical apparatus 

EN 55015  Limits and methods of measurement of radio disturbance characteristics of 
electrical lighting and similar equipment 

EN 55022  Limits and methods of measurement of radio disturbance characteristics of 
industrial, scientific, medial (ISM) radio‐frequency equipment. 

IEC 61000‐3‐4  EMC Part 3‐4: Limits – Limitation of Emission of Harmonic Currents in Low‐
voltage  Power  Supply  Systems  for  Equipment  with  rated  Current  greater 
than 16A 

EN 61000‐4‐1  EMC  Part  4‐1:  Testing  and  measurement  techniques  ‐  Overview  of  IEC 
61000‐4 series 

EN 61000‐4‐2  EMC  Part  4,  Testing  and  measurement  techniques  Section  2:  Electrostatic 
Discharge Immunity Test 

EN 61000‐4‐3  EMC  Part  4,  Testing  and  measurement  techniques  Section  3:  Radiated 
Radio‐frequency Electromagnetic Field Immunity Test 

EN 61000‐4‐4  EMC  Part  4,  Testing  and  measurement  techniques  Section  4:  Fast 
Transients/Burst Immunity Test 

EN 61000‐4‐5  EMC  Part  4,  Testing  and  measurement  techniques  Section  5:  Surges 
Immunity Test 

EN 61000‐4‐6  EMC  Part  4,  Testing  and  measurement  techniques  Section  6:  Immunity  to 
Conducted Disturbances induced by Radio‐frequency Fields 
 
KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G6‐15 of 16 Revision: 01
 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G6 – Damage and Interference
 
REFERENCE LIST OF STANDARDS RELATING TO EMC  (continued) 
 

EN 61000‐4‐8  EMC  Part  4,  Testing  and  measurement  techniques  Section  8:  Testing  and 
Measuring Techniques Power Frequency Magnetic Field Immunity Tests 

EN 61000‐4‐11  EMC Part 4, Testing and measurement techniques Section 11: Voltage Dips, 
Short Interruptions and Voltage Variations Immunity Tests 

EN 61000‐4‐13  EMC  Part  4,  Testing  and  measurement  techniques  Section  13:  Harmonics 
and  Inter‐harmonics  including  Mains,  Signalling  at  a.c.  Power  Port,  Low 
Frequency Immunity Tests 

EN 61000‐5‐7  Electromagnetic compatibility (EMC).  Installation and mitigation guidelines.  
Installation and mitigation guidelines.  Degrees of protection by enclosures 
against electromagnetic disturbances (EM code) 

EN 61000‐6‐2  Electromagnetic  compatibility  ‐  Part  6‐2  Generic  standards  ‐  Immunity  for 


Industrial environments 

EN 61000‐6‐4  Electromagnetic  compatibility  –  Part  6  Generic  standards  –  Section  4: 


Emission standard for industrial environments 

PD 6582  Electromagnetic compatibility (EMC).  Guide to generic EMC standards 
PD IEC TR  Electromagnetic compatibility (EMC).  Installation and mitigation guidelines.  
61000‐5‐6  Mitigation of external EM influences. 
PD ISO/TR  Lifts,  escalators  and  passenger  conveyors.    Comparison  of  worldwide 
16764  standards on electromagnetic interference / electromagnetic compatibility 
 
 
 
 
END OF SECTION 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G6‐16 of 16 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G7 – Temporary Electricity Supply
 

    SECTION G7 
TEMPORARY ELECTRICITY SUPPLY 

Work on Site  G7.1  (1)  Temporary  Electricity  Supply  shall  mean  the  electricity
power  supply  being  distributed  via  temporary  generators,
Tenaga  Nasional  Berhad  (TNB)  energy  meters  (construction
stage) or permanent energy meters for the Works and works
of  the  Other  Works  Contractors  until  the  permanent  meter
account is transferred to another party. 

    (2)  The  Works  Package  Contractor  shall  nominate  a


representative  whose  name  and  qualifications  shall  be
submitted in writing for approval by the PDP and who shall
ensure the safety of all temporary electrical installations and
equipment on Site. 

    (3)  The  name  and  contact  telephone  number  of  the


representative  having  been  approved  shall  be  displayed  at
the  main  distribution  board  for  the  temporary  electrical
supply so that he can be contacted in case of emergency. 

    (4)  Schematic diagrams and the details of the equipment for all
temporary  electrical  installations  shall  be  submitted  by  the
Works  Package  Contractor,  and  these  diagrams  together
with the temporary electrical equipment shall be submitted
for approval by the PDP. 

    (5)  All electrical installation work on Site shall be carried out in
accordance with the requirements laid down in BS 7375 and
this  GS.  All  work  shall  be  supervised  and  executed  by
qualified electrical workers of appropriate grade. 

Electrical ‐  G7.2  Temporary electrical site installations and distribution systems shall


general  be  in  accordance  with  the  following  codes  and  standards  of  the
latest version:‐ 

    a)   TNB’s supply rules and requirements; 

    b)   IEE Regulations for Electrical Installations; 

    c)   BS  7375  Distribution  of  Electricity  on  Construction  and


Building Sites; 

d)   BS  4363  Distribution  Assemblies  for  Electricity  Supplies  for


Construction and Building Sites; and 

    e)   BS  6164  Safety  in  Tunnelling  in  the  Construction  Industry
except that the background lighting level of the tunnel shall
follow Clause G7.13(2)(b)(ii). 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G7‐1 of 8 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G7 – Temporary Electricity Supply
 

Scope  G7.3  The  Works  Package  Contractor  shall  provide  and  maintain  the
temporary electrical installations from the load side of the points of
supply,  and  shall  ensure  that  all  necessary  precautions  are  taken
with regard to the safety of persons on Site. 

Materials,  G7.4  All  materials,  appliances  and  components  used  within  the
appliances and  distribution system shall comply with BS 4363 and BS 7375. 
components 

Design  G7.5  (1)  Distribution  equipment  utilised  within  the  temporary


considerations  electrical  distribution  system  shall  embody  the  following
features: 

    a)  Flexibility in application for repeated use; 

    b)  Suitability for transport and storage; 

    c)  Robust  construction  to  resist  moisture  and  damage;


and 

    d)  Safety in use. 

    (2)  All cabling shall be run at high level whenever possible and
firmly  secured  to  ensure  they  do  not  present  a  hazard  or
obstruction to people and equipment. When cables are laid
on ground, they must be waterproof and be protected from
mechanical damage. 

    (3)  The  installation  on  Site  shall  allow  convenient  access  to


authorised  and  competent  operatives  to  work  on  the
apparatus contained within. 

    (4)  For  special  equipment  and  plant  requiring  significant  load


requirements  (eg.  for  tunnel  boring  machines),  the  Works
Package Contractor is advised to negotiate with TNB as early
as  possible  in  order  to  secure  a  suitable  temporary  power
supply in a timely manner. 

Mains voltage  G7.6  (1)  The  mains  voltage  shall be  as  for  TNB’s  supplies,  415Vac  3‐
phase 50 Hz or 240Vac 1‐phase 50 Hz. 

    (2)  Voltages shall conform to BS 7375. 

Types of  G7.7  (1)  The  following  voltages  shall  be  adhered  to  for  typical
distribution  applications throughout the distribution systems: 
supply 
a)  Fixed plant ‐ 415Vac 3‐phase 50 Hz; 

b)  Movable plant fed by trailing cable ‐ 415V 3‐phase 50
Hz  (except  for  major  plant  such  as  tunnel  boring
machines); and 

c)  Installations in Site buildings ‐ 240Vac 1‐phase 50 Hz;

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G7‐2 of 8 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G7 – Temporary Electricity Supply
 

d)  Fixed flood lighting ‐ 240V 1‐phase 50 Hz; 

e)  Portable and hand held tools ‐110V 1‐phase 50 Hz; 

f)  Site  lighting  (other than flood lighting) - 110V 1-phase 50


Hz;

g) Portable hand‐lamps  (general use) - 110V 1-phase 50


Hz.

    (2)  When  the  low  voltage  supply  is  energised  by  TNB  at  the
Power On Date, any power utilised from that source shall be
either  415Vac  3‐phase  50  Hz  or  240Vac  1‐phase  50  Hz  as
appropriate.  The  Works  Package  Contractor  shall  convert
what  may  be  necessary  to  enable  him  to  use  power  from
that source. 

Protection of  G7.8  (1)  Protection  shall  be  provided  for  all  main  and  sub‐circuits
circuits  against excess current, residual current and earth faults. The
protective  devices  shall  be  capable  of  interrupting  without
damage any short circuit current that may occur. 

    (2)  Discrimination between circuit breakers, circuit breakers and
fuses shall be in accordance with:‐ 

    a)  BS 88; 

    b)  BS EN 60898; and 

    c)  BS 7375. 

Earthing  G7.9  (1)  Earthing  and  bonding  shall  be  provided  for  all  electrical
installations  and  equipment  to  prevent  the  possibility  of
dangerous voltage rises and to ensure that faults are rapidly
cleared by installed circuit protection. 

    (2)  Earthing systems shall conform to the following standards of
the latest version:‐ 

    a)  IEE Regulations for Electrical Installations; 

    b)  BS 7430; 

    c)  BS 7375; and 

    d)  IEEE  Standard  80  Guide  for  safety  in  sub‐station


earthing. 

Plugs, socket  G7.10  Low  voltage  plugs,  sockets  and  couplers  shall  be  colour  coded  in
outlets and  accordance with BS 7375, and constructed to conform to BS 4343.
couplers  High  voltage  couplers  and  'T'  connections  shall  be  in  accordance
with BS 3905. 

Cables  G7.11  Cables shall be selected after full consideration of the conditions to

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G7‐3 of 8 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G7 – Temporary Electricity Supply
 
which  they  will  be  exposed  and  the  duties  for  which  they  are
required. Supply cables up to 3.3KV shall be of armoured cables in
accordance with the relevant British Standards corresponding to the
required  duties  and  usages.  Separate  circuit  protective  conductors
(CPC) of appropriate type and size shall be installed for each circuit
if  the  equivalent  /  effective  size  of  the  cable  armouring  is
inadequate to perform as a CPC. 

Transformers  G7.12  Transformers  and  switchgear  to  be  used  generally  in  tunnels  shall
and switchgear  be in accordance with BS 6164. 
in tunnels 

Lighting  G7.13  (1)  Luminaries shall have a degree of protection not less than IP


installation  54.  In  particularly  bad  environments  where  the  luminaries
are  exposed  to  excesses  of  dust  and  water,  a  degree  of
protection to IP 65 shall be employed. 

    (2)  The  Works  Package  Contractor  shall  provide  temporary


lighting  for  the  Works  and  works  by  the  Other  Works
Contractors  until  the  lighting  systems  for  the  Permanent
Works have been commissioned, as follows:‐ 

    a)  All Areas except Tunnels: 

(i)  All  shafts  including  lift  shafts,  staircases,


access  routes,  corridors,  escape  routes  shall
have a minimum lighting level of  50 lux at all
times. 

(ii)  All  areas  where  construction,  installation  or


finishing  works  by  the  Works  Package
Contractor  and  Other  Works  Contractors  are
in progress shall have a minimum lighting level
of 100 lux at all times. 

    b)  Tunnels: 

(i)  All  shafts  including  lift  shafts,  staircases,


access routes, corridors, shall have a minimum
lighting level of 50 lux at all times. 

(ii)  In  all  areas  the  Works  Package  Contractor


shall  ensure  that  background  lighting  shall  be
provided  to  an  average  level  of  30  lux  at
walkway level. 

    (3)  Luminaries  shall  be  provided  with  suitable  enclosures  to


protect against accidental damage. 

Electrical  G7.14  (1)  Electrical  motors  for  tunnelling  plant  shall  be  suitable  for
motors  415Vac 3‐phase supply. Earthing shall be in accordance with
Clause G7.9(1). 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G7‐4 of 8 Revision: 01


 
PROJEK MASS RAPID TRANSIT LEMBAH KELANG  General Specification for Civil Engineering Works
Jajaran Sungai Buloh ‐ Kajang  Section G7 – Temporary Electricity Supply
 

    (2)  Motor control and protection circuits in all locations shall be
as  stipulated  in  BS  6164.  Emergency  stops  for  machinery
shall be provided. 

Inspection and  G7.15  Electrical  installations  on  Site  shall  be  inspected  and  tested  in
testing  accordance  with  the  requirements  of  the  IEE  Regulations  and  the
statutory codes. 

Identification  G7.16  Identification  and  warning  labels  shall  be  affixed  to  all  electrical
switches, circuit breakers and motors to specify their purpose. 

Maintenance  G7.17  Strict  maintenance  and  regular  checks  of  control  apparatus  and
wiring  distribution  systems  shall  be  carried  out  by  personnel  of
appropriate  grade  to  ensure  safety  and  efficient  operation.  The
details  of  maintenance  schedule  and  maintenance  works  record
shall be made available for review as requested by the PDP. 

Maintenance  G7.18  All  portable  electrical  appliances  shall  be  permanently  numbered
record  (scarf  tag  labels  or  similar)  and  a  record  kept  of  the  date  of  issue,
date  of  the  last  inspection  carried  out  and  the  recommended
inspection period. 

Electricity  G7.19  (1)  The  Works  Package  Contractor  shall  provide  and  maintain
supply for  temporary  electricity  supplies  in  the  form  of  a  supply  kiosk
Other Works  for  the  works  by  the  Other  Works  Contractors,  including
Contractors and  testing  commissioning,  trial  operations,  in  accordance  with
trial operations  the following: 

a)  Total  electrical  loads  in  a  station,  depot,  and/or  an


ancillary  building  shall  be  calculated  on  the  basis  of
16VA/sq.m. of the gross area. 

    b)  Total  number  of  kiosks  shall  be  calculated  on  the
basis  of  one  (1)  number  for  every  2,500  sq.m.  for  a
station, an ancillary building and a depot. 

    c)  For a station and a depot, there shall be at least five
(5) number of LV power supply kiosks of minimum 60
amps 3 phase per level, and for an ancillary building,
there  shall  be  at  least  one  (1)number  kiosk  of  the
same rating per level. 

    d)  For  tunnels  there  shall  be  at  least  one  LV  power
supply kiosk of minimum 60 amps, 3‐phase for every
250 metres run of tunnel. 

    e)  Electricity  shall  be  supplied  at  the  voltages  specified


in Subclause G7.6(1). 

    (2)  Each  of  the  supply  kiosks  shall  comprise  one  8‐way  TPN
(Triple Pole and Neutral) MCCB / MCB distribution board. 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001  G7‐5 of 8 Revision: 01


 

You might also like