Daniel Natividad Proposal v2
Daniel Natividad Proposal v2
Daniel Natividad Proposal v2
UNIT COST
ITEM DESCRIPTION QTY UNIT TOTAL COST
LABOR MATERIALS
1 GENERAL REQUIREMENTS
Building permit and processing 1.00 ls BY OWNER
HOA construction bond and processing 1.00 ls BY OWNER
Electrical permit and processing 1.00 ls BY OWNER
Fire safety requirements and processing 1.00 ls BY OWNER
Water permit and processing 1.00 ls BY OWNER
Sub-total
2 MOBILIZATION / DEMOBILIZATION
Mobilization / Demobilization 1.00 ls 6,280.12 6,280.12
Sub-total 6,280.12
3 SITE CLEARING
Site Clearing
Sub-total
4 TEMPORARY FACILITIES
Temfacil ( Site Office, Barracks, Toilet & Warehouse )
Water Consumption (Monthly Consumption) BY OWNER
Power Consumption (Monthly Consumption) BY OWNER
Sub-total
5 CIVIL WORKS
CONSTRUCTION WORKS
Demolition/ Removal works
Demolition of wall @ BR1 1.00 ls 9,043.37 9,043.37
Demolition of wall @ BR2 1.00 ls 9,043.37 9,043.37
Structural works
Rebarworks
Extension for BR-1
Column 378.00 kg 10.05 50.24 22,789.29
Roof beam 139.65 kg 10.05 50.24 8,419.38
Extension for BR-2
Column 378.00 kg 10.05 50.24 22,789.29
Roof beam 108.45 kg 10.05 50.24 6,538.35
Concrete casting works
Extension for BR-1
Column 1.08 m³ 1,884.03 4,019.27 6,375.57
Roof beam 0.56 m³ 1,884.03 4,019.27 3,297.59
Extension for BR-2
Column 1.08 m³ 1,884.03 4,019.27 6,375.57
Roof beam 0.43 m³ 1,884.03 4,019.27 2,560.86
Formworks
1 of 4
CONSTRUCTION OF BEDROOM EXTENSION
ST. AGATHA HOMES BRGY. TIKAY
MALOLOS BULACAN
MR. DANIEL NATIVIDAD
UNIT COST
ITEM DESCRIPTION QTY UNIT TOTAL COST
LABOR MATERIALS
Cocolumber
2x3x10ft 500.00 bdft 36.42 18,212.34
Plywood
1/2 10.00 bds 1,004.82 10,048.19
G.I. wire Ga.16 1.00 rolls 4,772.89 4,772.89
Miscellaneous item 1.00 ls 6,908.13 6,908.13
Labor 1.00 ls 28,166.32 28,166.32
Masonry works
CHB laying
Exterior wall
BR-1 36.78 m² 392.35 891.78 47,230.10
BR-2 28.65 m² 392.35 891.78 36,790.17
Plastering
Exterior wall
BR-1 36.78 m² 183.62 225.30 15,040.03
BR-2 28.65 m² 183.62 225.30 11,715.52
Interior wall
BR-1 36.78 m² 174.88 225.30 14,718.43
BR-2 28.65 m² 174.88 225.30 11,465.01
Installation of floor tiles
BR-1 extension 7.10 m² 558.98 1,018.27 11,198.48
BR-2 extension 11.36 m² 558.98 1,018.27 17,917.57
Glass and glazing
Sliding glass and aluminum window
Window @ BR-1 (1.20m x 1.35m) - 1 set 1.62 m² 1,884.03 4,396.08 10,173.79
Window @ BR-2 (1.20m x 1.35m) - 1 set 1.62 m² 1,884.03 4,396.08 10,173.79
Ceiling works
BR-1 extension 7.10 m² 326.57 390.23 5,089.27
BR-2 extension 11.36 m² 326.57 390.23 8,142.83
Eaves 5.27 m² 391.88 390.23 4,121.73
Painting works
Wall painting
Interior wall
BR-1 36.78 m² 147.18 255.57 14,812.82
BR-2 28.65 m² 147.18 255.57 11,538.54
Exterior wall
BR-1 36.78 m² 161.89 281.12 16,294.11
BR-2 28.65 m² 161.89 281.12 12,692.39
Ceiling painting
BR-1 extension 7.10 m² 160.24 238.82 2,833.33
2 of 4
CONSTRUCTION OF BEDROOM EXTENSION
ST. AGATHA HOMES BRGY. TIKAY
MALOLOS BULACAN
MR. DANIEL NATIVIDAD
UNIT COST
ITEM DESCRIPTION QTY UNIT TOTAL COST
LABOR MATERIALS
3 of 4
CONSTRUCTION OF BEDROOM EXTENSION
ST. AGATHA HOMES BRGY. TIKAY
MALOLOS BULACAN
MR. DANIEL NATIVIDAD
UNIT COST
ITEM DESCRIPTION QTY UNIT TOTAL COST
LABOR MATERIALS
Sub-total 22,558.18
VAT excluded
4 of 4