Goal MOC-18-0001

Sr. no PIC
Description
1 Propose modification in DOCMAP C/E
2 Approval from Class for the proposed modification Tech Supt
3 RQN for material to raise C/E
Tech Supt /
4 Supply of material Purchaser

5 Carry out the modification as per Class Aproved Drawing C/E

Modified system verification as per proposed drawing with Tech Supt to liase
6 class and endorsement. with Class
Training of on board staff for operation & Maintenance of
7 C/E
the system
8 Update drwgs & instruction manual on board C/E
9 Update drwgs in Office Tech Assistant
10 Close out MOC C/E
Estimated completion
date date completion
8-Aug-18
31-Oct-18
15-Nov-18

30-Nov-18

15-Dec-18

15-Jan-19

20-Jan-19

25-Jan-19
27-Jan-19
31-Jan-19