Material Reqirements
A : Cement Works.
Materials Required
Fine Coarse Aggregates
Sl no Items of Work Quantity Cement
Sand Sand 10mm 20mm 40mm
tonne m3 m3 m3 m3 m3
Cement Mortar :
1 1:1 1 m3 1.02 0.71
2 1:2 1 m3 0.68 0.95
3 1:3 1 m3 0.51 1.07
4 1:4 1 m3 0.38 1.07
5 1:5 1 m3 0.31 1.07
6 1:6 1 m3 0.25 1.07
Concrete :
7 1 m3 0.40 0.425 0.85
1 : 1.5 : 3 with 10mm nominal size aggregate.
8 1 m3 0.40 0.425 0.28 0.57
1 : 1.5 : 3 with 20mm nominal size aggregate.
9 1 m3 0.32 0.445 0.89
1 : 2 : 4 with 10mm nominal size aggregate.
10 1 m3 0.32 0.445 0.22 0.67
1 : 2 : 4 with 20mm nominal size aggregate.
11 1 m3 0.32 0.445 0.11 0.22 0.52
1 : 2 : 4 with 40mm nominal size aggregate.
12 1 m3 0.22 0.47 0.24 0.70
1 : 3 : 6 with 20mm nominal size aggregate.
13 1 m3 0.22 0.47 0.24 0.65
1 : 3 : 6 with 40mm nominal size aggregate.
14 1 m3 0.17 0.47 0.24 0.65
1 : 4 : 8 with 40mm nominal size aggregate.
15 1 m3 0.13 0.47 0.24 0.65
1 : 5 : 10 with 40mm nominal size aggregate.
B : Brick Works.
Materials Required
Sl no Items of Work Quantity Cement Fine Sand Brick
tonne m3 nos
Full brick work in :
1 C.M 1 : 3 1 m3 0.1275 0.2675 494
2 C.M 1 : 4 1 m3 0.0950 0.2675 494
3 C.M 1 : 6 1 m3 0.0625 0.2675 494
Half bick work in :
4 C.M 1 : 3 10 m2 0.1428 0.2996 565
5 C.M 1 : 4 10 m2 0.1064 0.2996 565
6 C.M 1 : 6 10 m2 0.0700 0.2996 565
Brick on edge in :
7 C.M 1 : 3 10 m2 0.0923 0.1937 377
8 C.M 1 : 4 10 m2 0.0688 0.1937 377
Honey combed half bick work in :
9 C.M 1 : 3 10 m2 0.0880 0.1846 341
10 C.M 1 : 4 10 m2 0.0656 0.1846 341
11 Dry brick pitching half brick thk 10 m2 645
Pointing on brick work in C.M 1 : 3 :
12 Flush pointing 10 m2 0.0153 0.0321
13 Ruled pointing 10 m2 0.0153 0.0321
14 Struck or weathered pointing 10 m2 0.0153 0.0321
15 Raised and cut pointing 10 m2 0.0235 0.0492
Pointing on brick flooring in C.M 1 : 3 :
16 Flush pointing 10 m2 0.0102 0.0214
17 Ruled pointing 10 m2 0.0102 0.0214
Pointing on brick flooring in C.M 1 : 4 :
18 Flush pointing 10 m2 0.0076 0.0214
19 Ruled pointing 10 m2 0.0076 0.0214
C : Stone Works.
Materials Required
Sl no Items of Work Quantity Cement Fine Sand Masonry Stone T & B Stone
tonne m3 m3 m3
Regular coursed rubble masonry in :
1 C.M 1 : 3 1 m3 0.153 0.321 1.21 0.16
2 C.M 1 : 4 1 m3 0.114 0.321 1.21 0.16
3 C.M 1 : 6 1 m3 0.075 0.321 1.21 0.16
Coursed rubble masonry in :
4 C.M 1 : 3 1 m3 0.153 0.321 1.10 0.16
5 C.M 1 : 4 1 m3 0.114 0.321 1.10 0.16
6 C.M 1 : 6 1 m3 0.075 0.321 1.10 0.16
Random rubble masonry in :
7 C.M 1 : 3 1 m3 0.1683 0.3531 1.00 0.16
8 C.M 1 : 4 1 m3 0.1254 0.3531 1.00 0.16
9 C.M 1 : 6 1 m3 0.0825 0.3531 1.00 0.16
10 Stone pitching in C.M 1 : 3 1 m3 0.1683 0.3531 1.00
11 Dry coursed masonry 1 m3 1.21 0.16
12 Dry stone pitching 22.5 cm thk 10 sqm 2.25
Pointing on stone in C.M 1 : 3 :
13 Flush pointing 10 sqm 0.0117 0.0246
14 Ruled 10 sqm 0.0117 0.0246
15 Raised and cut 10 sqm 0.0194 0.0407
D : Painting Works.
Required
Sl no Items of Work Quantity Materials Unit
quantity
1 White washing with lime on new work
8 Water proof cement paint (three or more coats) 10 m2 Water proof paint 5.47 kg
9 Water proof cement paint (one or more coats) 10 m2 Water proof paint 2.20 kg
11 Zinc chromate priming coat on steel work 10 m2 Zinc chr. primer 0.54 litre
13 Roof paint on G.I sheet (new work) 10 m2 Roof paint 0.80 litre
14 Roof paint on G.I sheet (old work) 10 m2 Roof paint 0.46 litre
19 Varnishing on new work (two or more coats) 10 m2 Copal varnish 1.86 litre
20 Varnishing on old work (one or more coats) 10 m2 Copal varnish 0.70 litre
E : Earthwork.
Materials Required
Sl Quantit Special
Items of Work Gelatine
Detonator Safety Fuse
no y
kg nos coil
Earthwork in excavation i
1 Soft rock 1 m3 0.250 1.20 0.100
2 Hard rock 1 m3 0.390 1.40 0.130
Earthwork in excavation i
3 Soft rock 1 m3 0.335 1.30 0.100
4 Hard rock 1 m3 0.535 1.40 0.125
Materials Required
Gravel Aggregates Borrow
Sl Quantit crushed
Items of Work 5.6-
Area
Sand
no y 22.4-90 Sand
22.4 10mm 20mm 40mm
mm
mm
m3 m3 m3 m3 m3 m3 m3
1 Gravel Sub-Base 100 m3 29.00 30.00 73.00
2 Crushed Stone Sub-Base 100 m3 47.50 22.50 39.50 22.50
3 Wet Mix Macadam 100 m3 39.60 46.20 13.20 13.20 19.80
G : Water Bound Macadam.
Materials Required
Sl Quantit IRC Grade Stones Aggregates
Items of Work
no y Gr- I Gr- II Gr- III 11.20 mm 13.20 mm
m3 m3 m3 m3 m3
1 IRC Gr - I 100 m3 132.0 27.00
2 IRC Gr - II 100 m3 132.0 26.67
3 IRC Gr - III 100 m3 132.0 24.00
H : Bituminous Work.
Materials Required
Aggregates
Sl Quantit Emulsio Bitume 40 mm 20 mm 5.6mm cement
Items of Work n
n 10 mm crushed (filler)
no y Bitumen averag averag
average
&
sand
e e below
3 100 m2 0.09
Emulsion primer for surface of low & medium porosity
4 100 m2 0.13
Emulsion primer for surface of high porosity
Materials Required
Aggregates
Sl Quantit Emulsio Bitume 40 mm 20 mm 5.6mm cement
Items of Work n
n 10 mm crushed (filler)
no y Bitumen averag averag
average
&
sand
e e below
6 100 m2 0.075
On granular surface treated with primer
7 100 m2 0.10
On granular surface not treated with primer
9 100 m2 0.038
On granular surface treated with primer
10 100 m2 0.04
On granular surface not treated with primer
11 Bituminous Macadam 110 m3 9.68 91.9 22.94 36.96
Firewood
21 100 m2 0.17 2.36 qtl 2.40
Premix Carpet 2cm thick as per MPWD Specification