SCAFFOLDING CALCULATION

S.# Description Length Rft Qty Total Rate Amount


1 Pipe 2" Dia 20 200 4000 110 440,000
2 Pipe 2" Dia 12 500 6000 110 660,000
3 Pipe 2" Dia 6 100 600 110 66,000
4 Joint 5500 5500 105 577,500
5 Carriage 40000 40,000
Total Material 1,783,500

Labor
1 Basement Roof + Beams 9000 9000 9 81,000
2 G.F Roof 9200 9200 9 82,800
3 1st Floor Roof 6200 6200 9 55,800
Total Labor 219,600

Total Mat + Lab 2,003,100

Less Labor Using Probe


1 Basement Roof + Beams 9000 9000 5 45,000
2 Basement Roof + Beams 9200 9200 5 46,000
3 1st Floor Roof 6200 6200 5 31,000
Total Labor 122,000

Net F.E 1,881,100