Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 16

ATTN TO : AXVENTURE SDN.BHD.

Date : 24/5/2018
Claim No : 01
PROJECT : PUNCAK ALAM
No Descriptions Unit TOTAL
Rate (RM) ZONE 1 ZONE 2 AMOUNT (RM)
INSTALLATION WORK QTY
1 Scaffolding Main Frame No 3.30 522 522 1,722.60
2 Wall Tie No 2.50 0 -
3 GI Pipe No 3.00 88 88 264.00
4 Steel Cat walk No 3.00 0 -
5 Safety Net Pcs 3.00 0 -
6 Cantilever Bracket No 60.00 159 350 509 30,540.00
7 Cat walk ladder Pcs 3.00 0 -
8 Supply skill workers for temporary work 75.00
9 Competen scaffolding for erection /Visit 400.00
DISMANTLING WORK
1 Scaffolding Main Frame No 2.00 0 -
2 Wall Tie No 1.50 0 -
3 GI Pipe No 2.00 0 -
4 Steel Cat walk No 2.20 0 -
5 Safety Net Pcs 1.50 0 -
6 Cantilever Bracket No 30.00 0 -
7 Cat walk ladder Pcs 2.50 0
TOTAL AMOUNT: 32,526.60
ATTN TO : AXVENTURE SDN.BHD. Date : 24/6/2018
Claim No : 02
PROJECT : PUNCAK ALAM
No Descriptions Unit TOTAL
Rate (RM) HOSPITAL AMOUNT (RM)
INSTALLATION WORK QTY
1 Scaffolding Main Frame No 3.30 365 365 1,204.50
2 Wall Tie No 2.50 21 21 52.50
3 GI Pipe No 3.00 18 18 54.00
4 Steel Cat walk No 3.00 0 -
5 Safety Net Pcs 3.00 0 -
6 Cantilever Bracket No 60.00 251 251 15,060.00
7 Cat walk ladder Pcs 3.00 0 -
8 Supply skill workers for temporary work 75.00
9 Competen scaffolding for erection /Visit 400.00
DISMANTLING WORK
1 Scaffolding Main Frame No 2.00 0 -
2 Wall Tie No 1.50 0 -
3 GI Pipe No 2.00 0 -
4 Steel Cat walk No 2.50 0 -
5 Safety Net Pcs 1.50 0 -
6 Cantilever Bracket No 30.00 0 -
7 Cat walk ladder Pcs 2.50 0
TOTAL AMOUNT: 16,371.00
ATTN TO : AXVENTURE SDN.BHD. Date : 24/7/2018
Claim No : 03
PROJECT : PUNCAK ALAM
No Descriptions Unit STAFF TOTAL
Rate (RM) HOSPITAL AMOUNT (RM)
INSTALLATION WORK ACCOMDATION QTY
1 Scaffolding Main Frame No 3.30 1036 70 1106 3,649.80
2 Wall Tie No 2.50 141 141 352.50
3 GI Pipe No 3.00 127 127 381.00
4 Steel Cat walk No 3.00 0 -
5 Safety Net Pcs 3.00 0 -
6 Cantilever Bracket No 60.00 176 40 238 454 27,240.00
7 Cat walk ladder Pcs 3.00 0 -
8 Supply skill workers for temporary work 75.00
9 Competen scaffolding for erection /Visit 400.00
DISMANTLING WORK
1 Scaffolding Main Frame No 2.00 101 101 202.00
2 Wall Tie No 1.50 0 -
3 GI Pipe No 2.00 27 27 54.00
4 Steel Cat walk No 2.50 0 -
5 Safety Net Pcs 1.50 0 -
6 Cantilever Bracket No 30.00 0 -
7 Cat walk ladder Pcs 2.50 0
TOTAL AMOUNT: 31,879.30
ATTN TO : AXVENTURE SDN.BHD. Date : 8/24/2018
Claim No : 04
PROJECT : PUNCAK ALAM
No Descriptions Unit STAFF TOTAL
Rate (RM) HOSPITAL AMOUNT (RM)
INSTALLATION WORK ACCOMDATION QTY
1 Scaffolding Main Frame No 3.30 1703 775 2478 8,177.40
2 Wall Tie No 2.50 214 310 524 1,310.00
3 GI Pipe No 3.00 184 176 360 1,080.00
4 Steel Cat walk No 3.00 0 -
5 Safety Net Pcs 3.00 0 -
6 Cantilever Bracket No 60.00 65 163 228 13,680.00
7 Cat walk ladder Pcs 3.00 0 -
8 Supply skill workers for temporary work 75.00
9 Competen scaffolding for erection /Visit 400.00
DISMANTLING WORK
1 Scaffolding Main Frame No 2.00 0 -
2 Wall Tie No 1.50 0 -
3 GI Pipe No 2.00 0 -
4 Steel Cat walk No 2.50 0 -
5 Safety Net Pcs 1.50 0 -
6 Cantilever Bracket No 30.00 38 38 1,140.00
7 Cat walk ladder Pcs 2.50 0
TOTAL AMOUNT: 25,387.40
ATTN TO : AXVENTURE SDN.BHD. Date : 9/24/2018
Claim No : 05
PROJECT : PUNCAK ALAM
No Descriptions Unit STAFF TOTAL
Rate (RM) HOSPITAL AMOUNT (RM)
INSTALLATION WORK ACCOMDATION QTY
1 Scaffolding Main Frame No 3.30 2244 1437 3681 12,147.30
2 Wall Tie No 2.50 444 621 1065 2,662.50
3 GI Pipe No 3.00 320 326 646 1,938.00
4 Steel Cat walk No 3.00 0 -
5 Safety Net Pcs 3.00 582 582 1,746.00
6 Cantilever Bracket No 60.00 151 57 208 12,480.00
7 Cat walk ladder Pcs 3.00 0 -
8 Supply skill workers for temporary work 75.00
9 Competen scaffolding for erection /Visit 400.00
DISMANTLING WORK
1 Scaffolding Main Frame No 2.00 610 610 1,220.00
2 Wall Tie No 1.50 0 -
3 GI Pipe No 2.00 36 36 72.00
4 Steel Cat walk No 2.50 0 -
5 Safety Net Pcs 1.50 0 -
6 Cantilever Bracket No 30.00 205 205 6,150.00
7 Cat walk ladder Pcs 2.50 0
TOTAL AMOUNT: 38,415.80
ATTN TO : AXVENTURE SDN.BHD. Date : 10/24/2018
Claim No : 06
PROJECT : PUNCAK ALAM
No Descriptions Unit STAFF TOTAL
Rate (RM) HOSPITAL AMOUNT (RM)
INSTALLATION WORK ACCOMDATION QTY
1 Scaffolding Main Frame No 3.30 2728 1070 3798 12,533.40
2 Wall Tie No 2.50 634 518 1152 2,880.00
3 GI Pipe No 3.00 426 196 622 1,866.00
4 Steel Cat walk No 3.00 0 -
5 Safety Net Pcs 3.00 459 278 737 2,211.00
6 Cantilever Bracket No 60.00 224 72 296 17,760.00
7 Cat walk ladder Pcs 3.00 0 -
8 Supply skill workers for temporary work 75.00
9 Competen scaffolding for erection /Visit 400.00
DISMANTLING WORK
1 Scaffolding Main Frame No 2.00 1453 8 1461 2,922.00
2 Wall Tie No 1.50 96 96 144.00
3 GI Pipe No 2.00 271 271 542.00
4 Steel Cat walk No 2.50 0 -
5 Safety Net Pcs 1.50 0 -
6 Cantilever Bracket No 30.00 170 19 189 5,670.00
7 Cat walk ladder Pcs 2.50 0
TOTAL AMOUNT: 46,528.40
ATTN TO : AXVENTURE SDN.BHD. Date : 11/24/2018
Claim No : 07
PROJECT : PUNCAK ALAM
No Descriptions Unit STAFF TOTAL
Rate (RM) PLANT HOUSE PORENSIK HOSPITAL AMOUNT (RM)
INSTALLATION WORK ACCOMDATION QTY
1 Scaffolding Main Frame No 3.30 1489 1259 380 4478 7606 25,099.80
2 Wall Tie No 2.50 449 190 1442 2081 5,202.50
3 GI Pipe No 3.00 331 155 128 574 1188 3,564.00
4 Steel Cat walk No 3.00 670 180 850 2,550.00
5 Safety Net Pcs 3.00 463 42 90 647 1242 3,726.00
6 Cantilever Bracket No 60.00 7 215 222 13,320.00
7 Cat walk ladder Pcs 3.00 0 -
8 Supply skill workers for temporary work 75.00
9 Competen scaffolding for erection /Visit 400.00
DISMANTLING WORK
1 Scaffolding Main Frame No 2.00 150 450 380 2481 3461 6,922.00
2 Wall Tie No 1.50 60 207 267 400.50
3 GI Pipe No 2.00 32 32 128 265 457 914.00
4 Steel Cat walk No 2.50 180 180 450.00
5 Safety Net Pcs 1.50 50 90 153 293 439.50
6 Cantilever Bracket No 30.00 40 40 526 606 18,180.00
7 Cat walk ladder Pcs 2.50 0
TOTAL AMOUNT: 80,768.30
ATTN TO : AXVENTURE SDN.BHD. Date : 12/24/2018
Claim No : 08
PROJECT : PUNCAK ALAM
No Descriptions Unit STAFF TOTAL
Rate (RM) PLANT HOUSE PORENSIK HOSPITAL AMOUNT (RM)
INSTALLATION WORK ACCOMDATION QTY
1 Scaffolding Main Frame No 3.30 7377 7377 24,344.10
2 Wall Tie No 2.50 3613 3613 9,032.50
3 GI Pipe No 3.00 905 905 2,715.00
4 Steel Cat walk No 3.00 0 -
5 Safety Net Pcs 3.00 1758 1758 5,274.00
6 Cantilever Bracket No 60.00 88 88 5,280.00
7 Cat walk ladder Pcs 3.00 0 -
8 Supply skill workers for temporary work 75.00 156 Day + 2 Hours 11,718.75
9 Competen scaffolding for erection /Visit 400.00
DISMANTLING WORK
1 Scaffolding Main Frame No 2.00 879 9171 10050 20,100.00
2 Wall Tie No 1.50 190 2452 2642 3,963.00
3 GI Pipe No 2.00 123 1227 1350 2,700.00
4 Steel Cat walk No 2.50 670 - 670 1,675.00
5 Safety Net Pcs 1.50 42 903 945 1,417.50
6 Cantilever Bracket No 30.00 476 476 14,280.00
7 Cat walk ladder Pcs 2.50 0
TOTAL AMOUNT: 102,499.85

User:
,
ATTN TO : AXVENTURE SDN.BHD. Date : 1/24/2019
Claim No : 09
PROJECT : PUNCAK ALAM
No Descriptions Unit STAFF TOTAL
Rate (RM) PLANT HOUSE PORENSIK HOSPITAL AMOUNT (RM)
INSTALLATION WORK ACCOMDATION QTY
1 Scaffolding Main Frame No 3.30 148 3498 3646 12,031.80
2 Wall Tie No 2.50 1593 1593 3,982.50
3 GI Pipe No 3.00 863 863 2,589.00
4 Steel Cat walk No 3.00 75 75 225.00
5 Safety Net Pcs 3.00 947 947 2,841.00
6 Cantilever Bracket No 60.00 14 14 840.00
7 Cat walk ladder Pcs 3.00 0 -
8 Supply skill workers for temporary work 75.00
9 Competen scaffolding for erection /Visit 400.00
DISMANTLING WORK
1 Scaffolding Main Frame No 2.00 148 492 640 1,280.00
2 Wall Tie No 1.50 92 92 138.00
3 GI Pipe No 2.00 250 250 500.00
4 Steel Cat walk No 2.50 0 -
5 Safety Net Pcs 1.50 62 62 93.00
6 Cantilever Bracket No 30.00 0 -
7 Cat walk ladder Pcs 2.50 0
TOTAL AMOUNT: 24,520.30

User:
,
ATTN TO : AXVENTURE SDN.BHD. Date : 2/24/2019
Claim No : 10
PROJECT : PUNCAK ALAM
No Descriptions Unit STAFF TOTAL
Rate (RM) PLANT HOUSE PORENSIK HOSPITAL AMOUNT (RM)
INSTALLATION WORK ACCOMDATION QTY
1 Scaffolding Main Frame No 3.30 64 1739 1803 5,949.90
2 Wall Tie No 2.50 32 459 491 1,227.50
3 GI Pipe No 3.00 42 639 681 2,043.00
4 Steel Cat walk No 3.00 46 46 138.00
5 Safety Net Pcs 3.00 27 600 627 1,881.00
6 Cantilever Bracket No 60.00 10 10 600.00
7 Cat walk ladder Pcs 3.00 0 -
8 Supply skill workers for temporary work 75.00
9 Competen scaffolding for erection /Visit 400.00
DISMANTLING WORK
1 Scaffolding Main Frame No 2.00 32 32 64.00
2 Wall Tie No 1.50 16 16 24.00
3 GI Pipe No 2.00 9 9 18.00
4 Steel Cat walk No 2.50 0 -
5 Safety Net Pcs 1.50 8 8 12.00
6 Cantilever Bracket No 30.00 0 -
7 Cat walk ladder Pcs 2.50 0
TOTAL AMOUNT: 11,957.40

User:
,
ATTN TO : AXVENTURE SDN.BHD. Date : 3/24/2019
Claim No : 11
PROJECT : PUNCAK ALAM
No Descriptions Unit STAFF TOTAL
Rate (RM) PLANT HOUSE PORENSIK HOSPITAL AMOUNT (RM)
INSTALLATION WORK ACCOMDATION QTY
1 Scaffolding Main Frame No 3.30 128 282 4056 4466 14,737.80
2 Wall Tie No 2.50 1599 1599 3,997.50
3 GI Pipe No 3.00 34 94 7098 7226 21,678.00
4 Steel Cat walk No 3.00 0 -
5 Safety Net Pcs 3.00 12 94 1079 1185 3,555.00
6 Cantilever Bracket No 60.00 90 90 5,400.00
7 Cat walk ladder Pcs 3.00 0 -
8 Supply skill workers for temporary work 75.00
9 Competen scaffolding for erection /Visit 400.00
DISMANTLING WORK
1 Scaffolding Main Frame No 2.00 80 440 520 1,040.00
2 Wall Tie No 1.50 142 142 213.00
3 GI Pipe No 2.00 20 100 120 240.00
4 Steel Cat walk No 2.50 0 -
5 Safety Net Pcs 1.50 159 159 238.50
6 Cantilever Bracket No 30.00 0 -
7 Cat walk ladder Pcs 2.50 0
TOTAL AMOUNT: 51,099.80

User:
,
ATTN TO : AXVENTURE SDN.BHD. Date : 4/24/2019
Claim No : 12
PROJECT : PUNCAK ALAM
No Descriptions Unit STAFF TOTAL
Rate (RM) PLANT HOUSE SURAU PORENSIK HOSPITAL AMOUNT (RM)
INSTALLATION WORK ACCOMDATION QTY
1 Scaffolding Main Frame No 3.30 409 2735 3144 10,375.20
2 Wall Tie No 2.50 760 760 1,900.00
3 GI Pipe No 3.00 52 2064 2116 6,348.00
4 Steel Cat walk No 3.00 70 70 210.00
5 Safety Net Pcs 3.00 711 711 2,133.00
6 Cantilever Bracket No 60.00 41 41 2,460.00
7 Cat walk ladder Pcs 3.00 0 -
8 Supply skill workers for temporary work 75.00 -
9 Competen scaffolding for erection /Visit 400.00 -
DISMANTLING WORK -
1 Scaffolding Main Frame No 2.00 48 282 337 667 1,334.00
2 Wall Tie No 1.50 201 201 301.50
3 GI Pipe No 2.00 14 94 232 340 680.00
4 Steel Cat walk No 2.50 0 -
5 Safety Net Pcs 1.50 12 94 105 211 316.50
6 Cantilever Bracket No 30.00 0 -
7 Cat walk ladder Pcs 2.50 -
TOTAL AMOUNT: 26,058.20

0 0

User:
,
ATTN TO : AXVENTURE SDN.BHD. Date : 4/24/2019
Claim No : 12
PROJECT : PUNCAK ALAM
Contract
No Descriptions Current Amount Previous Cumulative Cumulative To Date
Unit Value
Rate
INSTALLATION WORK QTY AMOUNT (RM) QTY AMOUNT (RM) QTY AMOUNT (RM)
(RM)
1 Scaffolding Main Frame No 3.30 3144 10,375.20 4466 14,737.80 7610 25,113.00
2 Wall Tie No 2.50 760 1,900.00 1599 3,997.50 2359 5,897.50
3 GI Pipe No 3.00 2116 6,348.00 7226 21,678.00 9342 28,026.00
4 Steel Cat walk No 3.00 70 210.00 0.00 70 210.00
5 Safety Net Pcs 3.00 711 2,133.00 1185 3,555.00 1896 5,688.00
6 Cantilever Bracket No 60.00 41 2,460.00 90 5,400.00 131 7,860.00
7 Cat walk ladder Pcs 3.00 0.00 0.00 0.00
8 Supply skill workers for temporary work 75.00 0.00
9 Competen scaffolding for erection /Visit 400.00 0.00 0.00
DISMANTLING WORK 0.00 0.00
1 Scaffolding Main Frame No 2.00 667 1,334.00 520 1,040.00 1187 2,374.00
2 Wall Tie No 1.50 201 301.50 142 213.00 343 514.50
3 GI Pipe No 2.00 340 680.00 120 240.00 460 920.00
4 Steel Cat walk No 2.50 0.00 0.00 0.00
5 Safety Net Pcs 1.50 211 316.50 159 238.50 370 555.00
6 Cantilever Bracket No 30.00 0.00 0.00 0.00
7 Cat walk ladder Pcs 2.50 0.00
TOTAL 26,058.20 51,099.80 77,158.00
PROJECT : PUNCAK ALAM

SCOPE OF WORKS : SCAFFOLDING


Rate Claim No.1 Claim No.2 Claim No.3 Claim No.4 Claim No.5 Claim No.6 Claim No.7 Claim No.10 Claim No.11 Claim No.12 TOTAL
No DESCRIPTION
( RM ) HOSPITAL HOSPITAL HOSPITAL PLANT HOUSE STAFF HOSPITAL STAFF HOSPITAL STAFF HOSPITAL STAFF STAFF PLANT HOUSE PORENSIK HOSPITAL PLANT HOUSE HOSPITAL PLANT HOUSE HOSPITAL STAFF HOSPITAL PLANT HOUSE PORENSIK HOSPITAL PLANT HOUSE PORENSIK HOSPITAL SURAU QTY

A MAIN FRAME 1219 X 1700MM no


1 Erection 3.30 522 365 1036 70 1703 775 2244 1437 2728 1070 1489 1259 380 4478 7377 148 3498 64 1739 128 282 4056 2735 409 39992
2 Dismantle 2.00 101 610 1453 8 150 450 380 2481 879 9171 148 492 32 80 440 48 282 337 17542
B G.I PIPE 6M/3M no
1 Erection 3.00 88 18 184 176 320 326 426 196 331 155 128 574 905 863 42 639 34 94 7098 2064 52 14713
2 Dismantle 2.00 36 271 32 32 128 265 123 1227 250 9 20 100 14 94 232 2833
C WALL TIE no
1 Erection 2.50 21 214 310 444 621 634 518 449 190 1442 3613 1593 32 491 1559 760 12891
2 Dismantle 1.50 96 60 207 190 2452 92 16 142 201 3456
D NETTING no
1 Erection 3.00 582 459 278 463 42 90 647 1758 947 27 600 12 94 1079 711 7789
2 Dismantle 1.50 50 90 153 42 903 62 8 159 12 94 105 1678
E CATWALK LADDER no
1 Erection 3.00 0
2 Dismantle 2.50 670 670
F METAL CATWALK FRAME no
1 Erection 3.00 670 180 75 46 70 1041
2 Dismantle 2.50 180 180
G CANTILEVER BRACKET no
1 Erection 60.00 509 251 176 40 238 65 163 151 57 224 72 7 215 88 88 10 90 41 2485
2 Dismantle 30.00 38 205 170 19 40 40 526 476 476 1990
KY AROTEK ENGINEERING & TRADING (NS0145779-H)

LOT.73 ,KUALA LUKUT BATU 3 1/2 JALAN SEREMBAN LUKUT 71010 PORT DICKSON
NEGERI SEMBILAN DARUL KHUSUS
MOBILE: 012-3306474 - 017-6720400
E-MAIL : KYAROTEK @Yahoo.com

PROJECT : PUNCAK ALAM

SCOPE OF WORKS : SCAFFOLDING


PAYMENT ITEM : 30 DAYS Claim No.12

SUMMARY OF CERTIFIED PAYMENT

PROGRESS CLAIM CERTIFIED PAYMENT RECEIVED


CLAIM PERIOD Submission Amount Amount Contra Amount
Date ACCUMULATION Date
NO ENDING Date ( RM ) CERTIFIED ( RM ) ( RM )
1 24/5/2018 32,526.60 30,900.27 30,900.27 30,900.27
2 24/6/2018 16,371.00 14,717.40 45,617.67 14,717.40
3 24/7/2018 31,879.30 30,285.34 75,903.01 30,285.34
4 24-Aug-18 25,387.40 24,118.04 100,021.05 24,118.04
5 24-Sep-18 38,415.80 36,495.01 136,516.06 36,495.01
6 24-Oct-18 46,528.40 44,201.98 180,718.04 44,201.98
7 24-Nov-18 80,768.30 76,729.89 257,447.93 76,729.89
8 24-Dec-18 102,499.85 97,374.00 354,821.93 97,374.00
9 24-Jan-19 24,520.30 23,294.29 378,116.22 23,294.29
10 24-Feb-19 11,957.40
11 24-Mar-19 51,099.80
12 24-Apr-19 26,058.20
13
14
488,012.35 378,116.22 TOTAL AMOUNT - 378,116.22

TOTAL AMOUNT OF WORK DONE TO- date : RM 488,012.35


TOTAL PAYMENT RECEIVED : RM 378,116.22
Cumulative Outstanding Including This Claim : RM 109,896,13

All progress payment base 30 days opens.


Cheque should be crossed and made payable to : KY AROTEK ENGINEERING & TRADING
Bank A/C No: AM BANK 8881008389441
We trust the above meets your requirement and looking forward for you confirmation soon
I certify the above to be true and correct to the best my knowladge

KY AROTEK ENGINEERING & TRADING


RECEIVEDBY…………………………………..
Date : 4/24/2019 NAME/COP/SIGN
KY AROTEK ENGINEERING & TRADING (NS0145779-H)

Our Ref : KYAENG/AXV/CO12LOT30352/2019


Date : 24 APRIL 2019
AXVENTURE SDN BHD
G-10-03 BLOCK G,SETIA WALK,
Persiaran Wawasan,Pusat Bandar Puchong,47160 Puchong Selangor Darul Ehsan

Attention :

Project Name : PUNCAK ALAM


v
CADANGAN MEREKABENTUK,MEMBINA,MELENGKAP MENTAULIAH DAN MENYELENGGARAKAN KERJA
INFRASTRUKTUR DAN BANGUNAN UNTUK HOSPITAL PENGAJAR UNIVERSITI TEKNOLOGI MARA,(ZON 1 FASA 3)
DENGAN KAEDAH PRIVATE FINANCE INITIATIVE ( PFI )
1. SATU (1) BLOK 10 TINGKAT BANGUNAN HOSPITAL PENGAJAR
BERSERTA PUSAT AKADEMI PERUBATAN DAN WAD ( 400 KATIL )
2. SATU (1) BLOK 8 TINGKAT BANGUNAN KUARTERS JURURAWAT DAN HOUSEMAN
3. SATU (1) BLOK 1 TINGKAT SURAU
4. SATU (1) BLOK 1 TINGKAT RUMAH MAYAT
5. SATU (1) BLOK 2 TINGKAT RUMAH LOJI
6. DUA (2) PONDOK PENGAWAL DAN BANGUNAN-BANGUNAN SOKONGAN
DI ATAS SEBAHAGIAN LOT PT 1567,PT1568,PUNCAK ALAM.MUKIM,JERAM DAERAH KUALA SELANGOR DARUL
UNTUK TETUAN UNIVERSITI TEKNOLOGI MARA.

Subject :PROGRESS CLAIM NO.12 FOR APRIL 2019

With reference for the above matter, please kindly find bellow our claim No.12, as per attached for your approval.
TOTAL CLAIM : RM 26,058.20

VERIFIED BY : ACNKOWLEDGE BY : CERTIFIED BY :

Name : Name : Name :


Date : Date : Date :

You might also like