AUDIT PARA REPLIES

CONSTRCUTION OF FLYOVER AT AZIZ CROSS GUJRANWALA


Para Audit Para Details Replies
No.
22 In the rate analysis for item ‘steel G-60’, 1 The observation by the audit is based on a
No. crane (20ton) and 1 No. Dumper (10-12 misconception. It is clarified that at the
ton) was added. These provision were not projects of instant fast track basis it is not
required to be provided because the rate of possible to cut in size and fabricate the steel
steel G-60 were of site rate and no cost of at every location of the structural
lifting and carriage was admissible. component. Once the steel is shifted to the
site in steel yard, it is cut and bent asper
design for installation at site. The crane is
required to load the steel in dumper truck
and then it is delivered from yard to
specified site location.

Additionally, the rate have been approved by


competent authority and then payments are
made to the contractor at bidder rates
accepted by C&W. Hence no loss of Govt. has
been made.

20 In the rate analysis of item’ granular sub- The rate for carriage of crushed stone has
base ‘, the lead for carriage of crushed stone been worked out from Sargodha Sikhawali,
has been taken 172 km(source not which is 172 km away from site area. The
mentioned) instead of 117 km of lead for rate analysis for subbase with Sargodah
quarry situated in Dina. Extra 55 km lead Quarry has been duly approved by the
resulted in approval of higher rate. competent authority and fulfill the material
specifications.

Additionally, the rate have been approved by


competent authority and then payments are
made to the contractor at bidder rates
accepted by C&W. Hence no overpayment is
involved. The para may be settled.

17 In rate analysis prepared by NESPAK for item The equipment / machinery rent charges
23 ABC and AWC, labour charges @ 12.5% of include the drivers and operators of the
equipment/machinery rent charges have machinery. The road side crew like
been included.
supervisor skilled and un skilled labour
Whereas, the labour charges are already
deployed for spreading / raking of asphalt
included in rent charges of machinery.
concrete at transverse and longitudinal joints
of carpeting are not included in the
equipment / machinery rent charges. Their
charges @ 12.5% of equipment charges have
been incorporated in the rate analysis, which
are justified.

Additionally, the rate have been approved by


competent authority and then payments are
made to the contractor at bidder rates
AUDIT PARA REPLIES

CONSTRCUTION OF FLYOVER AT AZIZ CROSS GUJRANWALA


accepted by C&W. Hence no overpayment is
involved. The para may be settled.

Para Audit Para Details Replies


No.
24 In the rate analysis of item ‘Earthwork for The observation by the audit is based on a
making embankment from borrow misconception. It is clarified that at the
excavation of common material’, 4 No. projects of instant fast track basis and at site
tractor trolley and 1 No. pump 4” delivery of heavy vehicular load, it is not possible to
(diesel) was added. These provisions were dump all material at every location of the
not required to be provided. earth work area. To dump borrow material a
specified location was finalized by the
Further, in “Material component” a lead of 8 engineer in charge. 8 km lead was added to
km was added, so there is no role of tractor take the material from borrow to specified
trolley. location. The material is shifted from
specified location to site through tractor
trolley, which is justified.

The compaction of earth work have been


done in layers as prescribed in the
specifications. To get the required
compaction, it is necessary to sprinkled
water on earth. Due to water requirement 4”
delivery pump was added in the rate
analysis.

Additionally, the rate have been approved by


competent authority and then payments are
made to the contractor at bidder rates
accepted by C&W. Hence no loss of Govt. has
been made.

25 In the rate analysis of’ Cast in situ piles During piling work, the continuous supply of
including A3 concrete’ under ‘Equipment’, 2 water based bentonite slurry is supplied and
No’s pump 4” delivery (diesel) were added. thus the delivery pump is used to circulate
that and 14 hours is estimated for complete
For rate analysis of ‘concrete class A3’ also, 1 piling works.
No. pump 4” delivery (diesel) was added.
Also during preparation of concrete at
batching plant water is needed to prepare
the concrete for piles.

Additionally, the rate have been approved by


competent authority and then payments are
AUDIT PARA REPLIES

CONSTRCUTION OF FLYOVER AT AZIZ CROSS GUJRANWALA


made to the contractor at bidder rates
accepted by C&W. Hence no overpayment is
involved. The para may be settled.