Jakarta MRT Project: Minutes of Inspection
Jakarta MRT Project: Minutes of Inspection
MINUTES OF INSPECTION
Time : 09.00 AM
Venue : DEPOT
Item Remark
Item of Inspecton Result of inspection
No.
Lighting Installation and fixture Lower Deck
1. Target 23/ 3/ 2018
Grid D, E and Central Deck.
2. Lighting installation and Fixture under Rail. Target 25/ 3/ 2018
3. Hi Bay lighting installation and fixture Target 23/ 3/ 2018
Public Address and Exit Installation Grid D & After Finishing
4. Target 25/ 3/ 2018
E TCI 23/03/18
Fire Alarm (Detector) Installation and Fixture
5. Target 25/ 3/ 2018
Grid D - E
6. Hydrant Box Grid D Target 21/ 3/ 2018
After Finishing
7. Hydrant Box Grid E Target 25/ 3/ 2018
TCI 23/03/18
8. Water Supply & Hydrant Installation Grid D-E Target 21/ 3/ 2018
9. BAS Target 25/ 3/ 2018
10. Receptacle Installation and Fixture grid D Target 25/ 3/ 2018
11. Megger Test and Visual Check all Target 24/ 3/ 2018 Start 10am
Name of
MRTJ JMCMC SC TWJO SUA/TCI
company:
Name:
Signature:
TWJO-STD-F07-revA Page 1 / 1