INDEX
1. Package Scope Definition / Status Section
A. Package Title and Narrative Description
B. Drawing Lists
1. List of Drawings Attached
2. List of Drawings Referenced
3. List of Procedures / ITPs Attached
C. Package Status Section
D. Outstanding Work/ Deficiencies List Section (Punchlist)
2. Mechanical Section
A. Mechanical Scope List
1. List of Mechanical Equipment
2. List of Manual Valves
B. Construction/Startup Mechanical Quality Certification
C. Mechanical Construction/Startup Checkout Documentation
4. Electrical Section
A. Electrical Scope List
1. List of Circuits
2. List of Electrical Equipment
3. List of Motors
B. Construction/Startup Electrical Quality Certification
C. Electrical Construction/Startup Checkout Documentation
6. Package Drawings
The 33HSJ-1 startup package will cover all system components required for operation of the sub-system.
Scope boundaries are established to allow for sub-system operation.
1. B - Drawing Lists
1.B – 1. List of Drawings Attached
Number Title
1.C - A
Note(s): 33HSJ-1 - SCR AMMONIA STORAGE AND SUPPLY EQUIPMENT AND PLC installed, walk-down
and turnover of QA/QC documents completed.
Conclusion: SC/B&V certify that the erection, installation, construction, examination, testing, inspection, stamping,
certification and documentation for all onsite construction works included in the 33HSJ-1 - SCR AMMONIA STORAGE
AND SUPPLY EQUIPMENT AND PLC sub-system has been completed in accordance with the construction
specifications pertinent to this system. Upon acceptance of this certificate the system will be placed under the control of
the B&V Commissioning Manager and any Construction personnel will abide by the requirements of the B&V LOTO &
PTW system as it is administered by the Startup/Operation personnel.
Full Name Full Name Full Name Full Name Full Name
1.C - B
I hereby certify that the examination, testing, inspection, startup checkout, commissioning, and documentation required for
proper commissioning of the 33HSJ-1 sub-system has been completed in accordance with the purchase and construction
specifications pertinent to this system.
____________________________________________________ __________________
B&V Startup Manager Date
____________________________________________________ __________________
Sumitomo Startup Manager Date
SC/B&V is hereby making notice to "Client" of our intention to initiate the turnover process for the above mentioned system.
____________________________________________________ __________________
Client Date
1.C - C
"Client" hereby acknowledges substantial completion of the 33HSJ-1 sub-system and that the sub-system and associated
turnover package documentation is ready for turnover. In no way does this certification relieve contractual obligations
relative to guaranties, warranties, demonstrations, or any other stipulated responsibilities such as repair of damage caused by
SC/B&V or its' subcontractors.
This certification is an acknowledgment of the system substantial completion and the satisfactory completion of the Turnover
Package, which includes a punchlist of all remaining items to be resolved in order to consider the system complete.
____________________________________________________ __________________
Client Date
2. MECHANICAL SECTION
2.b.c-10 All belts, chains, sheaves, pulleys etc. have been checked for Const. Mech.
proper alignment and tension.
2.b.c-11 All pipe restraints have been properly installed, location verified, Const. Mech.
and adjusted.
2.b.c-12 All piping has been pressure tested as required and the Const. Mech.
completed Pressure Test Data Reports are attached.
2.b.c-13 All pipe supports have been properly installed and adjusted, all Const. Mech.
spring can pins pulled and hangers checked for proper cold
settings.
2.b.c-14 All expansion joints have been properly installed, alignment Const. Mech.
verified, and tie rods adjusted in accordance with the
specifications and drawings.
Name:_____________________________
Last Revision: 28/Aug/2017
DUYEN HAI 3 EXTENSION TPPP
Startup Package 33HSJ-1
2.b.s-2 All manual valves have been operated to ensure proper SU Mech.
operation and seating.
2.b.s-3 All required post run-in alignment and doweling has been SU Mech.
completed.
2.b.s-4 All equipment cooling and sealing systems have been SU Mech.
checked for proper flow and operation.
2.b.s-5 All rotating equipment greater than 37kW has been checked SU Mech.
for vibration and the completed Vibration Data sheets are
attached
2.b.s-6 All vessels have been inspected for interior coatings, SU Mech.
cleanliness, the manways closed, and the completed Vessel
Closure Inspection Reports are attached.
2.b.s-7 All piping has been properly flushed or blown clean and the SU Mech.
completed Flushing and Blowdown Reports are attached.
3.b.c-4 All instruments have been inspected and verified to be free Const. I/C
from defects.
3.b.c-5 All instrument sensing lines have been installed with proper Const. I/C
supports, slope, vents and blowdown valves.
Name:_____________________________
4. ELECTRICAL SECTION
Name:_____________________________
6. PACKAGE DRAWING
EVNTPMB3
CONSULTANT
EVNPECC2
CONTRACTOR
SUBCONTRACTOR
ORIGINATOR
33HSK-1
OWNER
EVNTPMB3
CONSULTANT
EVNPECC2
CONTRACTOR
SUBCONTRACTOR
ORIGINATOR
33HSJ-1 OWNER
EVNTPMB3
CONSULTANT
EVNPECC2
CONTRACTOR
SUBCONTRACTOR
ORIGINATOR
done
OWNER
EVNTPMB3
CONSULTANT
EVNPECC2
CONTRACTOR
SUBCONTRACTOR
ORIGINATOR
done
OWNER
EVNTPMB3
CONSULTANT
EVNPECC2
CONTRACTOR
SUBCONTRACTOR
ORIGINATOR
done
OWNER
EVNTPMB3
CONSULTANT
EVNPECC2
CONTRACTOR
SUBCONTRACTOR
ORIGINATOR
done
OWNER
EVNTPMB3
CONSULTANT
EVNPECC2
CONTRACTOR
SUBCONTRACTOR
ORIGINATOR
33BLE-2
33BLE-2
33HSJ-1
33HSJ-1
33HSJ-1
33HSJ-1
33BLE-2
33BLE-1
33PUR-1
33HSJ-1
33HSJ-1
33HSJ-1
TO DCS
EVNTPMB3