Pending works in Khilchipur Jeerapur Road as on 12 Jul 2019

S. No. Chainage Detail of Structure / Works pending


Pavement Work
1 6+300 MNB (1x12) 1. Metal Beam Crash barrier on approaches not yet done
Reconstruction – 2. Footpath Railing work not yet done
3. Pitching work in progress. About 20% of stones are undersize. Filter material not
provided below the pitching.
4. Shoulder Width of Bridge Approaches is insufficient.
5. Road Furniture is still balance, required in accordance with provision of section
9 of the Manual and IRC 67.
6. Drainage spouts needs clearing
7. Weep holes to be cleaned
8. Waterway clearance

2 7+950 Jamunia village 1. Existing structure of 1000 mm size of PMGSY widened. The structure is required
Junction, LHS new as per cl 7.2.4 (c).
2. Stem in the BT works up to 150 m length(bell mouth + tapper portion +
matching stem) as required in jn details drawings not constructed.
3. Bell mouth not developed.
4. Apron and quadrant pitching not done
3 8+260 MNB (2x10) 1. Metal Beam Crash barrier on approaches not yet done
Reconstruction 2. Footpath Railing work not yet done
3. Pitching work in progress. A2 side in progress. About 20% of stones are
undersize. Filter material not provided below the pitching.
4. Shoulder Width of Bridge Approaches is insufficient.
5. Road Furniture is still balance, required in accordance with provision of section
9 of the Manual and IRC 67. Drainage spouts needs clearing
6. Weep holes to be cleaned
7. Waterway clearance
4 8+440 Moyakheda Junction, 1. Existing structure of 1000 mm size of PMGSY widened. The structure is required
LHS new as per cl 7.2.4 (c).
2. Stem in the BT works up to 150 m length(bell mouth + tapper portion +
matching stem) as required in jn details drawings not constructed.
3. Bell mouth not developed.
4. Apron and quadrant pitching not done
5 9+360 Obstacle on RHS 1. Tree on shoulder, needs trimming
shoulder
6 10+500 Bus Lay bye and 1. Bus shelter not yet constructed.
shelter 2. Shoulder width needs improvement.
3. Road Furniture is still balance, required in accordance with provision of section
9 of the Manual and IRC 67.
7 11+700 Drain length in Babdi 1. Drain incomplete about 12 m length.
Kheda village 2. Paver block in progress.
3. Road Furniture is still balance, required in accordance with provision of section
9 of the Manual and IRC 67.
8 11+920 Gadiymar village 1. Developed on LHS
junction, RHS 2. Stem in the BT works up to 150 m length (bell mouth + tapper portion +
matching stem) as required in jn details drawings not constructed.
3. Bell mouth not developed.
4. Apron and quadrant pitching not done
9 11+700 Drain 1. Length incomplete.
2. Paver block in progress.
3. Road Furniture is still balance, required in accordance with provision of section
9 of the Manual and IRC 67.
10 11+890 Shivnath pura village, 1. Existing structure of 1000 mm size of PMGSY widened. The structure is required
Junction new as per cl 7.2.4 (c).
2. Stem in the BT works up to 150 m length (bell mouth + tapper portion +
matching stem) as required in jn details drawings not constructed.
3. Bell mouth not developed.
4. Apron and quadrant pitching not done
11 14+300 Box culvert widening 1. Apron and quadrant pitching not done
12 15+300 Box culvert widening 1. Apron and quadrant pitching not done
2. Minor pot holes in PQC
13 15+600 Devpur village 1. Junction not yet improved
Junction, RHS 2. Shoulder not yet completed
3. RCC drain incomplete.
14 15+880 Minor Bridge (3x18.8), 1. Metal Beam Crash barrier on approaches not yet done
new construction 2. Footpath Railing work not yet done
3. Pitching work in progress. About 20% of stones are undersize. Filter material not
provided below the pitching.
4. Shoulder Width of Bridge Approaches is insufficient.
5. Road Furniture is still balance, required in accordance with provision of section
9 of the Manual and IRC 67.
6. Drainage spouts needs clearing
7. Weep holes to be cleaned
8. Waterway clearance

15 16+520 HPC widening 1. Inadequate length as required by toe width, needs further widening.
16 16+790 Chhapera Village, LHS 1. HPC not constructed. The structure is required new as per cl 7.2.4 (c).
2. Stem in the BT works up to 150 m length(bell mouth + tapper portion +
matching stem) as required in jn details drawings not constructed.
3. Bell mouth not developed.

17 17+190 Gurjarkhedi 1. Stem in the BT works up to 150 m length (bell mouth + tapper portion +
villageJunction , LHS matching stem) as required in jn details drawings not constructed.
2. Bell mouth not developed.
3. Apron and quadrant pitching not done
18 16+900 Canal HPC retain 1. Shoulder to be developed till the head wall
2. Vent clearance
19 17+640 MNB (2x10), 1. Metal Beam Crash barrier on approaches not yet done
Reconstruction 2. Footpath Railing work not yet done
3. Pitching work in progress. About 20% of stones are undersize. Filter material not
provided below the pitching.
4. Shoulder Width of Bridge Approaches is insufficient.
5. Road Furniture is still balance, required in accordance with provision of section
9 of the Manual and IRC 67.
6. Drainage spouts needs clearing
Weep holes to be cleaned
20 19+900 Truck laybye 1. Work in progress
21 19+900 Village LHS T Jn 1. There is no requirement since no road.
2. The location could be shifted to Khumanpur village
22 20+500 Bus Shelter 1. Being developed
23 20+675 HPC new 1. Headwall needs repair.
24 21+120 Sadalpur Village 1. HPC not constructed.
Junction LHS 2. Stem in the BT works up to 150 m length (bell mouth + tapper portion +
matching stem) as required in jn details drawings not constructed.
3. Bell mouth not developed.
25 21+337 Box culvert widening 1. Apron and quadrant pitching not done
26 21+430 HPC 1. Under widening
27 22+680 Peeplada Village 1. Existing structure of 1000 mm size of PMGSY widened. The structure is required
Junction LHS new as per cl 7.2.4 (c).
2. Stem in the BT works up to 150 m length(bell mouth + tapper portion +
matching stem) as required in jn details drawings not constructed.
3. Bell mouth not developed.
4. Apron and quadrant pitching not done
28 Common
Points
A RCC drain 1. Pedestrian railing in drain locations.
2. Drain lengths yet pending at various locations.
B Earthen Drain 1. At most lengths not yet dug
C W Beam Crash 1. About 1500 m WB crash barrier not constructed.
Barrier
D Cracks in 1. Expert opinion to be obtained and repairs carried out accordingly.
about 300 m
length
E Utility Ducts 1. Utility pipes total required as per contract vis-à-vis actually constructed needs
reconciliation.
2. Headwall not constructed.
3. Chambers for facilities in built-up areas.
F Shoulder 1. Compaction and final finish
2. The drainage layer on slopes should be exposed for drainage functioning.
3. Slope and toe width to be improved at various locations.
G Plantation 1. No plantation has yet been started.
H Rainwater 1. No works yet carried out
Harvesting