P L T
ukuran PLAT 0.6 x 0.6 0.2
kolom 0.3 x 0.2
Ketinggian besi di baw 1.6
tebal selimut 0.025 m
over stage 0.48 m
jarak sengkang 0.15 m
diameter besi Ø 12 mm
diameter besi Ø 8 mm
Lantai kerja 0.05 m
banyaknya tulangan k 8 bh
volume beton
plat 0.6 0.6 0.2 0.072
foot 0.3 0.2 1.35 0.081
0.153
Tulangan dlm 1 m3 35.34468 0.153 242.5616 berat besi utk analiasa
volume beton
plat 0.8 0.8 0.2 0.128
foot 0.2 0.2 1 0.04
0.168
Tulangan dlm 1 m3 51.20649 0.168 320.0406 berat besi utk analiasa
sloop 15x20 P L T
( ISI DATA YG BERTANDA TULISAN MERAH )
dimensi 0.2 0.15
tebal selimut 0.02 m
balok 15x25 P L T
( ISI DATA YG BERTANDA TULISAN MERAH )
dimensi 0.25 0.15
tebal selimut 0.02 m
Kolom 15x20 P L T
( ISI DATA YG BERTANDA TULISAN MERAH )
dimensi 0.2 0.15
tebal selimut 0.02 m
begisting
1.4 17.06667 23.89333 m2
Balok 25x45 P L T
( ISI DATA YG BERTANDA TULISAN MERAH )
dimensi 0.25 0.45
tebal selimut 0.03 m
Balok 20/20 P L T
( ISI DATA YG BERTANDA TULISAN MERAH )
dimensi 0.2 0.2
tebal selimut 0.03 m
begisting 0.8 25 20 m2
BALOK 20 X 30
volume beton
plat 1.2 1.2 0.2 0.288
foot 0.3 0.3 1 0.09
0.378
berat besi utk analiasa Tulangan dlm 1 m3 75.2615 0.378 209.05972 berat besi utk analiasa
luas begisting utk analisa 2.16 0.378 5.7142857 luas begisting utk analisa
begisting 0.8 25 20 m2
sloop 15x15 P L T
( ISI DATA YG BERTANDA TULISAN MERAH )
dimensi 0.15 0.15
146.2423 13.071895425 tebal selimut 0.025 m
begisting 1 16 16 m2 begisting
1.24
Balok 20x35 P L T Balok 20x30
( ISI DATA YG BERTANDA TULISAN MERAH )
dimensi 0.2 0.35 dimensi
tebal selimut 0.03 m tebal selimut
Balok 20x50 P L T
( ISI DATA YG BERTANDA TULISAN MERAH )
dimensi 0.2 0.5
tebal selimut 0.03 m
begisting 1.4 10 14 m2
berat besi utk analiasa
0.15 m
16 mm
0 mm
8 mm
3 bh
0
1 16.66667 16.66667 m2
L T
( ISI DATA YG BERTANDA TULISAN MERAH )
0.3
bj besi berat besi
0.88776 6 118.368
0 0 0
0.22194 149.1481 27.80563
153.4823 kg
22.22222 13.33333 m2
L T Kolom 20x30 P L
( ISI DATA YG BERTANDA TULISAN MERAH ) ( ISI DATA YG BERTANDA TULISAN MERAH )
0.3 dimensi 0.2 0.3
m tebal selimut 0.03 m
Kolom 20x20 P L
( ISI DATA YG BERTANDA TULISAN MERAH ) ( ISI DATA YG BERTANDA TULISAN MERAH )
mtr 1 dimensi 0.2 0.2
mtr tebal selimut 0.02 m
1.24 10.63093
begisting 0.8 25
6
589.5042 kg 0.39456 12 4.73472
124.5067
6
589.5042 34.33333 20.28 696.28 58.02333
49.12535 67.66667 10.28 695.6133 57.96778
115.9911
T
TA YG BERTANDA TULISAN MERAH )
berat besi
4 147.96
0 0
278.7778 63.79684
222.3447 kg
16.66667 m2
T
TA YG BERTANDA TULISAN MERAH )
berat besi
6 88.776
112.1111 38.04172
133.1586 kg
16.66667 m2
T
TA YG BERTANDA TULISAN MERAH )
berat besi
6 133.164
251 73.28557
216.7721 kg
20 m2
TIME SCHEDULLE
KEGIATAN : PENINGKATAN / REHABILITASI SARANA DAN PRASARANA PUSKESMAS/PUSKESMAS PEMBANTU
DAN JARINGANNYA PADA DINAS KESEHATAN KABUPATEN TASIKMALAYA.
PEKERJAAN : PENGEMBANGAN PUSKESMAS DTP CIPATUJAH
LOKASI : KECAMATAN CIPATUJAH KABUPATEN TASIKMALAYA
IV. PEKERJAAN BETON 14.139 1.116 2.605 2.605 2.605 2.605 2.605
V. PEKERJAAN DINDING DAN PLESTERAN 17.246 2.874 2.874 2.874 2.874 2.874 2.874
VI. PEKERJAAN KUSEN, PINTU DAN JENDELA 7.492 1.498 1.498 1.498 1.498 1.498
VII. PEKERJAAN ATAP DAN KUDA-KUDA 21.304 4.261 4.261 4.261 4.261 4.261
VIII. PEKERJAAN RANGKA DAN PENUTUP PLAFOND 5.063 1.266 1.266 1.266 1.266
IX. PEKERJAAN LANTAI, RABAT DAN SALURAN 8.849 2.212 2.212 2.212 2.212
XIII. PEKERJAAN PLUMBING DAN SANITAIR 3.526 0.441 1.029 1.029 1.029
AKUMULATIF KEMAJUAN PEKERJAAN 100.00 3.333 4.721 6.650 7.042 7.042 8.078 6.538 3.775 4.168 5.544 9.429 9.642 7.563 3.359 5.922 5.771 1.
RENCANA KEMAJUAN PEKERJAAN 3.333 8.054 14.704 21.745 28.787 36.866 43.403 47.178 51.346 56.889 66.318 75.960 83.523 86.883 92.804 98.576
CEPAT / LAMBAT
ADE HERYANTO
Direktur
HEDULLE
50
1.350
1.424
100
DAFTAR HARGA UPAH KERJA
WILAYAH KOTA TASIKMALAYA
TAHUN ANGGARAN 2014
UPAH
NO. JENIS TENAGA KERJA SATUAN
( Rp )
(a) (b) (c) (e)
12 Kusen Pintu Alumunium KM/WC Komplit dg kunci (Harga sudah terpasang) Unit 736,000.00
8 Baja Ringan Zinc Alum c75, Tebal Standar 0,7/ 0,75 mm (Harga Terpasang) m2 160,000.00
14 List Pintu dan Jendela Alumunium (Harga sudah terpasang) m1 10,000.00
35 Daun Pintu dan Jendela Alumunium (harga sudah terpasang) m¹ 64,000.00
39 Besi Hoolo 20.40 btg 43,000.00
40 Besi Hoolo 40.40 btg 57,000.00
41 Gantungan Plafond Rangka Hollo m1 1,500.00
D. BAHAN PERPIPAAN
1 Pipa PVC Ø 1/2" (Setara Maspion ) m1 2,750.00
2 Pipa PVC Ø 3/4" (Setara Maspion) m1 3,750.00
3 Pipa PVC Ø 1" (Setara Maspion ) m1 19,750.00
4 Pipa PVC Ø 1 1/2" (Setara Maspion) m1 25,750.00
5 Pipa PVC Ø 2" (Setara Maspion) m1 32,500.00
6 Pipa PVC Ø 2 1/2" (Setara Wavin) m1 36,500.00
7 Pipa PVC Ø 3" (Setara Wavin) m1 64,250.00
8 Pipa PVC Ø 4" (Setara Wavin) m1 94,500.00
9 Talang 4 M' m1 7,000.00
10 Gantungan Plat bh 1,250.00
11 Gantungan Plastik bh 750.00
12 Pipa GIV 2" m1 205,250.00
I. BAHAN KACA
1 Kaca Polos 3 mm m2 50,100.00
2 Kaca Polos 5 mm m2 61,700.00
Q. HARGA BBM *)
1 Premium Ltr 6,100.00
2 Minyak Tanah Ltr 8,300.00
3 Minyak Bekisting Ltr 20,900.00
4 Minyak Pelumas Ltr 20,900.00
5 Minyak Bakar Ltr 5,700.00
ANALISA HARGA SATUAN PEKERJAAN
WILAYAH KOTA TASIKMALAYA
TAHUN ANGGARAN 2014
A PEKERJAAN PERSIAPAN
B PEKERJAAN TANAH
C PEKERJAAN PONDASI
D PEKERJAAN DINDING
E PEKERJAAN PLESTERAN
F PEKERJAAN KAYU
G PEKERJAAN BETON
I PEKERJAAN LANGIT-LANGIT
I-04a 1 m2 LANGIT-LANGIT GRC (1.20X2.40 ) Cm, RANGKA KAYU GUNUNG KELAS III
Kayu Gunung Kls II, balok 0.0120 m3 1,881,000.00 22,572.00
Paku biasa 0.0600 Kg 18,800.00 1,128.00
GRC 0.3820 Lbr 52,200.00 19,940.40
Pekerja 0.1800 HOK 45,000.00 8,100.00
Tukang kayu 0.3200 HOK 60,000.00 19,200.00
Kepala tukang 0.0320 HOK 70,000.00 2,240.00
Mandor 0.0090 HOK 70,000.00 630.00
Jumlah 30,170.00 43,640.40
Keuntungan 3,017.00 4,364.04
Jumlah Total 33,187.00 48,004.44 81,191.44
Dibulatkan 81,191.00
I-06 1 m2 LANGIT-LANGIT GRC (1.20X2.40 ) Cm, RANGKA BESI HOLLO 20.40 dan 40.40
Besi Hollo 20.40 0.4167 btg 43,000.00 17,918.10
Besi Hollo 40.40 0.4167 btg 57,000.00 23,751.90
Skrup 24.0000 bh 100.00 2,400.00
Gantungan Dari Kawat 1 mm 1.8000 m1 1,500.00 2,700.00
GRC 0.3819 Lbr 52,200.00 19,937.50
Pekerja 0.1800 HOK 45,000.00 8,100.00
Tukang besi 0.3200 HOK 60,000.00 19,200.00
Kepala tukang 0.0320 HOK 70,000.00 2,240.00
Mandor 0.0090 HOK 70,000.00 630.00
Jumlah 30,170.00 66,707.50
Keuntungan 3,017.00 6,670.75
Jumlah Total 33,187.00 73,378.25 106,565.25
Dibulatkan 106,565.00
I-05 1 m2 LANGIT-LANGIT ETERNITE (100 X 100 ) Cm, RANGKA KAYU GUNUNG KLAS III
Kayu Gunung Klas II 5/7 0.0120 m3 1,881,000.00 22,572.00
Paku biasa 0.0600 Kg 18,800.00 1,128.00
Eternit 1.1000 Lbr 8,500.00 9,350.00
Pekerja 0.1800 HOK 45,000.00 8,100.00
Tukang kayu 0.3200 HOK 60,000.00 19,200.00
a b c d e f=(cxe) g=(cxe) h
Kepala tukang 0.0320 HOK 70,000.00 2,240.00
Mandor 0.0090 HOK 70,000.00 630.00
Jumlah 30,170.00 33,050.00
Keuntungan 3,017.00 3,305.00
Jumlah Total 33,187.00 36,355.00 69,542.00
Dibulatkan 69,542.00
J PEKERJAAN SANITASI
J-07 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA (45X45) CM TANPA TUTUP
Batu bata 0.9600 m2 97,448.00 93,550.08
Plesteran 1 : 5 1.1200 m2 30,486.00 34,144.32
Acian 1 : 5 1.1200 m2 21,703.00 24,307.36
Galian Tanah 0.1500 m3 22,880.00 3,432.00
Jumlah 3,432.00 152,001.76
Keuntungan 343.20 15,200.18
Jumlah Total 3,775.20 167,201.94 170,977.14
Dibulatkan 170,977.00
J-09 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA (60X60) CM TANPA TUTUP
Batu bata 1.4400 m2 97,448.00 140,325.12
Plesteran 1 : 5 1.3200 m2 30,486.00 40,241.52
Acian 1 : 5 1.3200 m2 21,703.00 28,647.96
Galian Tanah 0.2940 m3 22,880.00 6,726.72
Jumlah 6,726.72 209,214.60
Keuntungan 672.67 20,921.46
Jumlah Total 7,399.39 230,136.06 237,535.45
Dibulatkan 237,535.00
J-23 1 UNIT SEPTICTANK 1.5 x 1.0 X 1.5 m (TYPE KECIL) + REMBESAN (A082)
Galian Tanah 2.2500 m3 22,880.00 51,480.00
Pasir urug 0.1071 m3 118,580.00 12,699.92
Lantai kerja 1 : 3 : 5 0.7750 m3 687,285.00 532,645.88
Pasangan bata + Plesteran 1 : 3 5.2500 m2 103,942.00 545,695.50
Plat beton penutup + balok 0.1500 m3 3,170,650.00 475,597.50
a b c d e f=(cxe) g=(cxe) h
Pipa PVC 4" AW + sambungan 5.0000 m' 23,625.00 118,125.00
Pipa GIF 2" 0.6000 m' 205,250.00 123,150.00
Galian tanah untuk rembesan 1.3750 m3 22,880.00 31,460.00
Pasangan ijuk 2.7000 kg 7,500.00 20,250.00
Urugan kerikil 3.5 cm 0.5250 m3 85,500.00 44,887.50
Pipa PVC 4" AW berlobang 5.0000 m' 23,625.00 118,125.00
Urugan kembali perataan tanah 0.5625 m3 10,967.00 6,168.94
Tambahan upah kerja 0.0850 Ls 36,000.00 3,060.00
Jumlah 3,060.00 2,080,285.23
Keuntungan 306.00 208,028.52
Jumlah Total 3,366.00 2,288,313.75 2,291,679.75
Dibulatkan 2,291,679.00
K-03 1 m' PASANG TALANG 1/2 LINGKARAN Ø10 cm, SENG BJLS 28
Seng plat 3' x 6' BJLS 28 0.3000 Lbr 70,500.00 21,150.00
Paku biasa 1/2" - 1" 0.1000 Kg 18,800.00 1,880.00
Kayu papan Kls II (Kayu gunung) 0.0190 m3 1,881,000.00 35,739.00
Besi strip 0.5000 Kg 17,500.00
Pekerja 0.1500 HOK 45,000.00 6,750.00
Tukang kayu 0.2500 HOK 60,000.00 15,000.00
Kepala tukang 0.0250 HOK 70,000.00 1,750.00
Mandor 0.00125 HOK 70,000.00 87.50
Jumlah 23,587.50 37,619.00
Keuntungan
Jumlah Total
Dibulatkan
N PEKERJAAN PENGECATAN
N-03 1 m2 PENGECATAN BIDANG KAYU BARU (1 Lapis Plamir; 1 Lapis Cat dasar; 3 Lapis Cat Penutup)
Cat meni 0.2000 Kg 16,700.00 3,340.00
Plamir 0.1500 Kg 14,600.00 2,190.00
Cat dasar 0.1700 Kg 47,000.00 7,990.00
Cat Penutup ( 3 kali ) 0.3500 Kg 42,700.00 14,945.00
Pekerja 0.0700 HOK 45,000.00 3,150.00
Tukang cat 0.1050 HOK 47,500.00 4,987.50
Kepala tukang 0.0040 HOK 70,000.00 280.00
Mandor 0.0025 HOK 70,000.00 175.00
Jumlah 8,592.50 28,465.00
Keuntungan 859.25 2,846.50
Jumlah Total 9,451.75 31,311.50 40,763.25
Dibulatkan 40,763.00
N-05 1 m2 PENGECATAN BIDANG TEMBOK BARU (1 Lapis Plamir; 1 Lapis Cat dasar; 2 Lapis Cat Penutup)
Plamir 0.1000 Kg 25,000.00 2,500.00
a b c d e f=(cxe) g=(cxe) h
Cat dasar 0.1000 Kg 47,000.00 4,700.00
Cat Penutup ( 2 kali ) 0.2600 Kg 15,600.00 4,056.00
Pekerja 0.0200 HOK 45,000.00 900.00
Tukang cat 0.0630 HOK 47,500.00 2,992.50
Kepala tukang 0.0063 HOK 70,000.00 441.00
Mandor 0.0025 HOK 70,000.00 175.00
Jumlah 4,508.50 11,256.00
Keuntungan 450.85 1,125.60
Jumlah Total 4,959.35 12,381.60 17,340.95
Dibulatkan 17,340.00
N-08 1 m2 PENGECATAN GENTENG BARU (1 Lapis Cat dasar; 2 Lapis Cat Penutup)
Cat dasar 0.1000 Kg 56,400.00 5,640.00
Cat Penutup ( 2 kali ) 0.2600 Kg 56,400.00 14,664.00
Pekerja 0.0200 HOK 45,000.00 900.00
Tukang cat 0.0630 HOK 47,500.00 2,992.50
Kepala tukang 0.0063 HOK 70,000.00 441.00
Mandor 0.0025 HOK 70,000.00 175.00
Jumlah 4,508.50 20,304.00
Keuntungan 450.85 2,030.40
Jumlah Total 4,959.35 22,334.40 27,293.75
Dibulatkan 27,293.00
N-09 1 m2 PENGECATAN BATU TEMPEL BARU (1 Lapis Cat dasar; 2 Lapis Cat Penutup)
Cat Penutup ( 2 kali ) 0.2600 Kg 77,400.00 20,124.00
Pekerja 0.0200 HOK 45,000.00 900.00
Tukang cat 0.0630 HOK 47,500.00 2,992.50
Kepala tukang 0.0063 HOK 70,000.00 441.00
Mandor 0.0025 HOK 70,000.00 175.00
Jumlah 4,508.50 20,124.00
Keuntungan 450.85 2,012.40
Jumlah Total 4,959.35 22,136.40 27,095.75
Dibulatkan 27,095.00
A PEKERJAAN PERSIAPAN
1 1 m' PEKERJAAN PENGUKURAN DAN PEMASANGAN BOUWPLANK A-02 25,570.00
2 1 m2 PEKERJAAN MEMBERSIHKAN DAN PERATAAN LAPANGAN A-05 8,800.00
B PEKERJAAN TANAH
1 1 m3 GALIAN TANAH BIASA SEDALAM 1 METER B-01 22,880.00
2 1 m3 URUGAN KEMBALI B-06 10,967.00
3 1 m3 PEMADATAN TANAH B-07 28,600.00
4 1 m3 URUGAN TANAH DIPADATKAN B-08 35,970.00
5 1 m3 URUGAN PASIR B-09 118,580.00
6 1 m3 URUGAN TANAH BELI DARI LUAR B-10 75,680.00
C PEKERJAAN PONDASI
1 1 m3 PASANGAN PONDASI BATU KALI, 1 Pc : 4 Ps C-01 595,727.00
1 1 m3 PASANGAN PONDASI BATU KALI, 1 Pc : 5 Ps C-03 499,499.00
2 1 m3 PASANGAN PONDASI BATU KOSONG C-04 221,496.00
D PEKERJAAN DINDING
1 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 5 Ps D-02 97,448.00
E PEKERJAAN PLESTERAN
1 1 m2 PLESTERAN 1 PC : 5 Ps, TEBAL 15 mm E-03 30,486.00
2 1 m2 ACIAN PLESTERAN E-05 21,703.00
F PEKERJAAN KAYU
1 1 m3 PASANG KUSEN PINTU DAN JENDELA KAYU GUNUNG KELAS II F-02 5,044,875.00
2 1 m2 PASANG PINTU PANEL KAYU GUNUNG KELAS II F-05 397,650.00
3 1 m2 JENDELA KACA KAYU GUNUNG KELAS II (Tanpa Kaca) F-07 199,182.00
4 1 m' PASANG LIST PLAFOND KAYU PROFIL F-22 9,009.00
5 1 m' PASANG LIST PLAFOND GYPSUN F-23 18,826.00
G PEKERJAAN BETON
1 1 m3 MEMBUAT BETON TUMBUK, 1 PC : 3 Ps : 5 Kr G-01 687,285.00
2 1 m2 MEMBUAT LANTAI KERJA BETON TUMBUK TEBAL 5 cm, 1 PC : 3 Ps : 5 Kr G-02 86,662.00
3 1 m3 MEMBUAT BETON DENGAN MUTU K-175 G-03 628,050.00
4 1 Kg PEMBESIAN DENGAN BESI POLOS ATAU ULIR G-07 15,042.00
5 1 m2 PASANG BEKISTING UNTUK PONDASI G-08 125,664.00
6 1 m2 PASANG BEKISTING UNTUK SLOOF G-09 137,626.00
7 1 m2 PASANG BEKISTING UNTUK KOLOM G-10 228,365.00
8 1 m2 PASANG BEKISTING UNTUK BALOK G-11 235,562.00
9 1 m2 PASANG BEKISTING UNTUK LANTAI G-12 270,715.00
10 1 m2 PASANG BEKISTING UNTUK DINDING G-13 229,350.00
11 1 m2 PASANG BEKISTING UNTUK TANGGA G-14 259,259.00
12 1 m3 MEMBUAT PONDASI BETON BERTULANG T= 25 CM + Bekisting G-15 3,922,878.00
13 1 m3 MEMBUAT SLOOF 30/40 BETON BERTULANG + Bekisting G-16 2,223,898.00
13 1 m3 MEMBUAT SLOOF 15/20 BETON BERTULANG + Bekisting G-17 5,628,472.00
14 1 m3 MEMBUAT SLOOF BETON 20/35 BERTULANG + Bekisting (S3) G-18 4,666,256.00
15 1 m3 MEMBUAT LISTPLANK BETON 10/60 BERTULANG + Bekisting G-19 3,170,650.00
16 1 m3 MEMBUAT KOLOM STRUKTUR BETON BERTULANG 30/30 (+ Bekisting) (K1) G-20 4,886,340.00
17 1 m3 MEMBUAT KOLOM STRUKTUR BETON BERTULANG 20/20 (+ Bekisting) (K2) G-21 7,993,231.00
18 1 m3 MEMBUAT KOLOM BETON PRAKTIS 15/15 BERTULANG + Bekisting (K3) G-22 8,626,474.00
19 1 m3 MEMBUAT BALOK 20/40 BETON BERTULANG (+ Bekisting) (B1) G-23 3,868,590.00
20 1 m3 MEMBUAT BALOK 15/30 BETON BERTULANG (+ Bekisting) (B2) G-24 5,524,802.00
21 1 m3 MEMBUAT BALOK 15/32 BETON BERTULANG (+ Bekisting) (B3) G-25 5,203,208.00
22 1 m3 MEMBUAT BALOK 15/20 BETON BERTULANG (+ Bekisting) (B4) G-26 6,920,456.00
23 1 m3 MEMBUAT BALOK 12/15 BETON BERTULANG (+ Bekisting) (BR) G-27 7,803,586.00
24 1 m3 MEMBUAT BALOK LINTEL 12/15 BETON BERTULANG (+ Bekisting) (BL) G-28 7,803,586.00
(a) (b) (c) (d)
25 1 m3 MEMBUAT PLAT BETON T = 10 CM Bekisting G-29 3,159,893.00
26 1 m3 MEMBUAT PLAT BETON T = 12 CM Bekisting G-30 3,777,592.00
I PEKERJAAN LANGIT-LANGIT
1 1 m2 LANGIT-LANGIT GRC (1.20X2.40 ) Cm, RANGKA KAYU GUNUNG KELAS II I-04 89,349.00
2 1 m2 LANGIT-LANGIT GRC (1.20X2.40 ) Cm, RANGKA KAYU GUNUNG KELAS III I-04a 81,191.00
J PEKERJAAN SANITASI
1 MEMASANG 1 BUAH KLOSET JONGKOK PORSELIN J-01 437,976.00
2 MEMASANG 1 BUAH KLOSET DUDUK PORSELIN J-01a 1,902,736.00
2 MEMASANG 1 BUAH WASTAFEL J-02 595,756.00
3 MEMASANG 1 BUAH BAK MANDI FIBREGLASS 0,30M3 J-03 648,857.00
4 MEMASANG 1 METER PIPA BETON, Ø 15-20 CM J-04 0.00
5 MEMASANG 1 METER PIPA BETON, Ø 30-100 CM J-05 0.00
6 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA (45X45) CM J-06 0.00
4 MEMASANG 1 BUAH BAK KONTROL PASANGAN GREVEL BATU BATA (45X45) CM TANP J-07 170,977.00
5 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA (60x60) CM J-08 438,902.00
6 MEMASANG 1 BUAH BAK KONTROL PASANGAN GREVEL BATU BATA (60x60) CM TANP J-09 237,535.00
7 MEMASANG 1 METER PIPA PVC TIPE AW Ø 1/2" J-10 6,689.00
8 MEMASANG 1 METER PIPA PVC TIPE AW Ø 3/4" J-11 7,116.00
9 MEMASANG 1 METER PIPA PVC TIPE AW Ø 1" J-12 13,936.00
10 MEMASANG 1 METER PIPA PVC TIPE AW Ø 1 1/2" J-13 16,493.00
10 MEMASANG 1 METER PIPA PVC TIPE AW Ø 2" J-14 22,129.00
12 MEMASANG 1 METER PIPA PVC TIPE AW Ø 2 1/2" J-15 21,075.00
9 MEMASANG 1 METER PIPA PVC TIPE AW Ø 3" J-16 39,805.00
10 MEMASANG 1 METER PIPA PVC TIPE AW Ø 4" J-17 52,699.00
14 MEMASANG 1 BUAH BAK CUCI PIRING STAINLESS-STEEL J-18 330,005.00
11 MEMASANG 1 BUAH BAK CUCI PIRING STAINLESS-STEEL J-18 330,005.00
12 MEMASANG 1 BUAH KRAN Ø 1/2" ATAU Ø 3/4" J-19 23,421.00
13 MEMASANG 1 BUAH FLOOR DRAIN J-20 105,545.00
14 1 M' SALURAN GRAFEL BETON 1/2 Ø 20 cm + PASANGAN J-21 72,781.00
17 1 M' GORONG-GORONG BUIS BETON Ø 20 cm + PASANGAN (A137) J-21A 158,299.00
18 1 M' SALURAN GRAFEL BETON 1/2 Ø 30 cm + PASANGAN J-24 2,633,683.00
15 1 UNIT SEPTICTANK 2.5 x 1.5 X 2 m (TYPE BESAR) + REMBESAN J-22 8,894,407.00
20 1 UNIT SEPTICTANK 1.5 x 1.0 X 1.5 m (TYPE KECIL) + REMBESAN (A082) J-23 2,291,679.00
21 1 UNIT PEK. SEPTICKTANK BUIS BETON Ø 80 CM + RESAPAN J-24 2,633,683.00
N PEKERJAAN PENGECATAN
1 1 m2 PENGECATAN BIDANG KAYU BARU (1 Lapis Plamir; 1 Lapis Cat dasar; 3 Lapis Cat Penu N-03 40,763.00
2 1 m2 PELABURAN BIDANG KAYU DENGAN CAT RESIDU DAN TER N-04 6,859.00
3 1 m2 PENGECATAN BIDANG TEMBOK BARU (1 Lapis Plamir; 1 Lapis Cat dasar; 2 Lapis Cat Pe N-05 17,340.00
6 1 m2 PENGECATAN BIDANG TEMBOK ULANG N-06 13,389.00
4 1 m2 PENGECATAN PLAFOND N-07 21,025.00
5 1 m2 PENGECATAN GENTING N-08 27,293.00
6 1 m2 PENGECATAN BATU TEMPEL BARU (1 Lapis Cat dasar; 2 Lapis Cat Penutup) N-09 27,095.00
Halaman 1
ANALISA
HARGA JUMLAH
KODE
NO. URAIAN PEKERJAAN VOL. SAT. SATUAN HARGA
(Rp.) (Rp.)
I Pekerjaan Persiapan
1 Pembuatan Papan Nama Proyek 1.000 Ls ls 300,000.00 300,000.00
2 Pengukuran Ulang 1.000 Ls ls 500,000.00 500,000.00
3 Pek.Pemasangan Bouwplank 150.000 A-02 m' 25,570.00 3,835,500.00
4 Pek Direksi Keet (Sewa) 1.000 A-03 ls 1,000,000.00 1,000,000.00
5,635,500.00
II. Perkerjaan Galian dan Urugan
1 Pek. Galian Tanah 44.100 B-01 m³ 22,880.00 1,009,008.00
2 Pek. Urugan Kembali 17.440 B-06 m³ 10,967.00 191,264.48
3 Pek. Urugan Pasir Bawah Pondasi 3.100 B-09 m³ 118,580.00 367,598.00
4 Pek. Urugan Pasir Bawah Lantai 14.540 B-09 m³ 118,580.00 1,724,153.20
3,292,023.68
III. Pekerjaan Pondasi
1 Pas. Lantai Kerja 1 : 3 : 5 1.125 G-02 m³ 86,662.00 97,494.75
2 Pek. Pondasi Plat T = 25 cm 5.510 G-15 m³ 3,922,878.00 21,615,057.78
21,712,552.53
IV. Pekerjaan Beton
1 Pek. Sloof Beton 15/20 0.290 G-17 m³ 5,628,472.00 1,632,256.88
2 Pek. Sloof Beton 30/40 9.360 G-16 m³ 2,223,898.00 20,815,685.28
3 Pek. Kolom Beton Struktur 30/30 (K1) 3.650 G-20 m³ 4,886,340.00 17,835,141.00
4 Pek. Kolom Beton Struktur 20/20 (K2) 4.420 G-21 m³ 7,993,231.00 35,330,081.02
5 Pek. Kolom Beton Praktis 15/15 (KP) 0.790 G-22 m³ 8,626,474.00 6,814,914.46
6 Pek. Balok Beton Struktur 20/40 (B1) 6.720 G-23 m³ 3,868,590.00 25,996,924.80
8 Pek. Balok Beton Struktur 15/30 (B2) 0.620 G-24 m³ 5,524,802.00 3,425,377.24
9 Pek. Balok Beton Struktur 15/20 (RB) 2.560 G-26 m³ 6,920,456.00 17,716,367.36
11 Pek. Plat Beton T = 12 cm 10.820 G-30 m³ 3,777,592.00 40,873,545.44
12 Pek. Plat Beton T = 10 cm (Untuk Plat Tangga + Bordes) 0.790 G-29 m³ 3,159,893.00 2,496,315.47
13 Pek. Plat Beton T = 10 cm (Untuk Meja Beton) 0.294 G-29 m³ 3,159,893.00 929,008.54
173,865,617.49
V. Pekerjaan Dinding Dan Plesteran
Lantai 1
1 Pasangan Dinding 1/2 Bata 1 : 5 51.410 D-02 m² 97,448.00 5,009,801.68
2 Pekerjaan Plesteran 1 : 5 44.150 E-03 m² 30,486.00 1,345,956.90
3 Pekerjaan Acian Plesteran Bata 44.150 E-05 m² 21,703.00 958,187.45
7,313,946.03
Halaman 2
ANALISA
HARGA JUMLAH
KODE
NO. URAIAN PEKERJAAN VOL. SAT. SATUAN HARGA
(Rp.) (Rp.)
ANALISA
HARGA JUMLAH
KODE
NO. URAIAN PEKERJAAN VOL. SAT. SATUAN HARGA
(Rp.) (Rp.)
TERBILANG : TIGA RATUS LIMA PULUH ENAM JUTA TIGA RATUS ENAM PULUH LIMA RIBU RUPIAH\
HARGA
1 M3 KOLOM 20 X 20 20 X 20 CM
Panjang/M3 1 : 0.2 : 0.2 = 25.00 M
20
Besi diameter 12 juml 6
Besi diameter juml
Besi diameter juml 20
HARGA
1 M3 BALOK 15 X 20 15 X 20 CM
Panjang/M3 1 : 0.15 : 0.2 = 33.33 M
15
Besi diameter 12 juml 4
Besi diameter 10 juml 0
Besi diameter juml 20
HARGA
1 M3 SLOOF 25 X 20 25 X 20 CM
Panjang/M3 1 : 0.25 : 0.2 = 20.00 M
25
Besi diameter 12 juml 6
Besi diameter 0 juml 0
Besi diameter juml 20
HARGA
1 M3 RINGBALK 15 X 20 15 X 20 CM
Panjang/M3 1 : 0.15 : 0.2 = 33.33 M
15
Besi diameter 12 juml 4
Besi diameter 10 juml 2
Besi diameter juml 20
Begel diameter 8 jarak 15 cm
besi diameter
LAYER 1 (X) 10 jarak 20 cm 0.2 Y
(Y) 10 jarak 20 cm 0.2
2 Pas.Pondasi Kali 1 : 5
a.Pondasi Plat Kaki 1 1 0.275 m3 5.50 20 Plat Kaki
b.Pondasi Tangga 0.6 0.6 0.25 m3 0.09 1 Pondasi Tangga
c.pondasi Benteng 6.25 0.3 0.3 m3 0.56
IV Pekerjaan Beton
1 Pek.Sloof Beton 30/40 78 0.3 0.4 m3 9.36
2 Pek.Sloof Beton 15/20 9.5 0.15 0.2 m3 0.29
3 Pek Kolom Praktis 15/15 35.05 0.15 0.15 m3 0.79
4 Pek.Kolom Struktur I 30/30 40.56 0.3 0.3 m3 3.65
5 Pek.Kolom Struktur II 20/20 110.54 0.2 0.2 m3 4.42
6 Pek.Balok I 20/40 84 0.2 0.4 m3 6.72
7 Pek.Balok II 15/30 13.7 0.15 0.3 m3 0.62
8 Ring Balk 15/20 85.2 0.15 0.2 m3 2.56
9 Plat kantiever 16.38 0.1 m3 1.64
10 Plat Lantai 90.13 0.12 m3 10.82
11 Plat Tangga dan Bodres 6.6 0.9 0.12 m3 0.79
b.Kuda-Kuda
Balok Tarik 8/15 8.35 0.15 0.8 m3 1.00
Balok sokong 8/12 6.2 0.12 0.8 m3 1.19
Balok Pengunci 8/15 1 0.15 0.8 m3 0.48
Balok Nok 8/12 3 0.12 0.8 m3 0.29
Balok Gapit 6/12 5.5 0.12 0.6 m3 0.79
Balok Silang Angin 6/12 2 0.12 0.6 m3 0.29
Balok Balok Silang Gempa 6/12 3 0.12 0.6 m3 0.86
Papan Ruiter 2/20 3 0.2 0.02 m3 0.01
Tiang Kuda-Kuda 8/12 2.7 0.12 0.8 m3 0.52
Kaki Kuda-Kuda 8/12 9.4 0.12 0.8 m3 1.80
Gording 8/12 3 0.12 0.8 m3 0.58
Jumlah 7.82