PEMBESIAN PONDASI setempat ( ISI DATA YG BERTANDA TULISAN MERAH )

P L T
ukuran PLAT 0.6 x 0.6 0.2
kolom 0.3 x 0.2
Ketinggian besi di baw 1.6
tebal selimut 0.025 m
over stage 0.48 m
jarak sengkang 0.15 m
diameter besi Ø 12 mm
diameter besi Ø 8 mm
Lantai kerja 0.05 m
banyaknya tulangan k 8 bh

panjang besi banyaknya sengkang bj besi berat besi


plat 1.5 5 2 0.88776 13.3164
foot
dia 12 20.68 0.88776 18.35888

dia 8 0.9 10.33333 0.39456 3.669408


35.34468

volume beton
plat 0.6 0.6 0.2 0.072
foot 0.3 0.2 1.35 0.081
0.153
Tulangan dlm 1 m3 35.34468 0.153 242.5616 berat besi utk analiasa

begisting Keliling Tinggi


plat 2.4 0.2 0.48
foot 1 1.35 1.35
1.83

1.83 0.153 11.96078 luas begisting utk analisa

PEMBESIAN PONDASI setempat ( ISI DATA YG BERTANDA TULISAN MERAH )


P L T
ukuran PLAT 0.8 x 0.8 0.2
kolom 0.2 x 0.2
Ketinggian besi di baw 1.25
tebal selimut 0.025 m
over stage 0.4 m
jarak sengkang 0.15 m
diameter besi Ø 10 mm
diameter besi Ø 8 mm
Lantai kerja 0.05 m
banyaknya tulangan10 kolom 15 bh

panjang besi banyaknya sengkang bj besi berat besi


plat 1.9 6.333333 2 0.88776 21.36542
foot
dia 12 31.125 0.88776 27.63153

dia 8 0.7 8 0.39456 2.209536


51.20649

volume beton
plat 0.8 0.8 0.2 0.128
foot 0.2 0.2 1 0.04
0.168
Tulangan dlm 1 m3 51.20649 0.168 320.0406 berat besi utk analiasa

begisting Keliling Tinggi


plat 3.2 0.2 0.64
foot 0.8 1 0.8
1.44

1.44 0.168 8.571429 luas begisting utk analisa

kolom ukuran 30x20 P L T


( ISI DATA YG BERTANDA TULISAN MERAH )
dimensi 0.3 0.2
tebal selimut 0.025 m

jarak sengkang 0.15 m


diameter besi Ø 12 mm
diameter besi Ø 8 mm
banyaknya tulangan12
kolom 6 bh

bj besi berat besi


panjang besi 16.66667 0.88776 6 88.776
ring 0.9 0.39456 112.1111 39.811104
135.0165 kg

begisting 1 16.66667 16.66667 m2

sloop 15x20 P L T
( ISI DATA YG BERTANDA TULISAN MERAH )
dimensi 0.2 0.15
tebal selimut 0.02 m

jarak sengkang 0.15 m


diameter besi 12 mm
diameter besi 6 mm
banyaknya tulangan12
kolom 4 bh 0.88776
banyaknya tulangan kolom Ø

bj besi berat besi


panjang besi 33.33333 0.88776 4 118.368
ring 0.64 0.22194 223.2222 31.70684
165.0823 kg

begisting 0.4 33.33333 13.33333 m2

balok 15x25 P L T
( ISI DATA YG BERTANDA TULISAN MERAH )
dimensi 0.25 0.15
tebal selimut 0.02 m

jarak sengkang 0.15 m


diameter besi Ø 12 mm
diameter besi Ø mm
diameter besi Ø 8 mm
banyaknya tulangan12
kolom 6 bh
banyaknya tulangan kolom
0 0 bh

bj besi berat besi


panjang besi 26.66667 0.88776 6 142.0416
26.66667 0 0 0
ring 0.74 0.39456 178.7778 52.19853
203.9521 kg

begisting 0.65 26.66667 17.33333 m2

Ring balok 15x20 P L T


( ISI DATA YG BERTANDA TULISAN MERAH )
dimensi 0.2 0.15
tebal selimut 0.02 m

jarak sengkang 0.15 m


diameter besi Ø 12 mm
diameter besi Ø 0 mm
diameter besi Ø 8 mm
banyaknya tulangan kolom 5 bh 12
banyaknya tulangan kolom 0 bh 0

bj besi berat besi


panjang besi 33.33333 0.88776 5 147.96
33.33333 0 0 0
ring 0.64 0.39456 223.2222 56.36772
214.5441 kg

begisting 0.4 33.33333 13.33333 m2

Kolom 15x20 P L T
( ISI DATA YG BERTANDA TULISAN MERAH )
dimensi 0.2 0.15
tebal selimut 0.02 m

jarak sengkang 0.15 m


diameter besi Ø 12 mm
diameter besi Ø 8 mm
banyaknya tulangan12
kolom 6 bh

bj besi berat besi


panjang besi 33.33333 0.88776 6 177.552
ring 0.64 0.39456 223.2222 56.36772
245.6157 kg

begisting 0.7 33.33333 23.33333 m2

PEMBESIAN PLAT LANT


dua layer
( ISI DATA YG BERTANDA TULISAN MERAH )
tebal plat 0.1 mtr 1
panjang besi dlm 1 mtr 10 mtr

jarak sengkang 0.15 mtr


diameter besi Ø 8 mm
diameter besi Ø mm
tebal selimut 0.025 mtr
pangang besi bj besi
banyaknya sengkang m 66.66667 2.1 1 0.39456 55.2384
banyaknya sengkang 6.666667 20.1 1 0.39456 52.87104
113.5149 kg

begisting 10.2 1.2 12.24 m2

PEMBESIAN PLAT LANT


satu layer
( ISI DATA YG BERTANDA TULISAN MERAH )
tebal plat 0.1 mtr 1
panjang besi dlm 1 mtr 10 mtr

jarak sengkang 0.15 mtr


diameter besi Ø 8 mm
diameter besi Ø 0 mm
tebal selimut 0.025 mtr
pangang besi bj besi
banyaknya sengkang m 66.66667 1.1 1 0.39456 28.9344
banyaknya sengkang 6.666667 10.1 1 0.39456 26.56704
58.27651 kg

begisting 10.2 1.2 12.24 m2

PEMBESIAN PLAT LANTAI tangga T 12 CM dua layer


( ISI DATA YG BERTANDA TULISAN MERAH )
tebal plat 0.12 mtr 1
panjang besi dlm 1 mtr 8.333333 mtr

jarak sengkang 0.15 mtr


diameter besi Ø 12 mm
diameter besi Ø 8 mm
tebal selimut 0.025 m
pangang besi bj besi
banyaknya sengkang m 55.55556 2.14 1 0.88776 105.5448
banyaknya sengkang 6.666667 16.80667 1 0.88776 99.46858
215.264 kg

begisting 8.573333 1.24 10.63093 m2

PEMBESIAN anak tangga T 12 CM


P L T
( ISI DATA YG BERTANDA TULISAN MERAH )
dimensi anak tangga 1.2 mtr 0.3 0.2

panjang besi dlm 1 mtr 16.66667 mtr 1

jarak sengkang 0.15 mtr


diameter besi Ø 12 mm
diameter besi Ø 8 mm
tebal selimut 0.025 mtr
pangang besi bj besi
banyaknya sengkang 2 1.4 1 0.88776 2.485728
banyaknya sengkang m 111.1111 0.55 1 0.88776 54.252
59.57461 kg

begisting
1.4 17.06667 23.89333 m2
Balok 25x45 P L T
( ISI DATA YG BERTANDA TULISAN MERAH )
dimensi 0.25 0.45
tebal selimut 0.03 m

jarak sengkang 0.15 m


diameter besi Ø 13 mm
diameter besi Ø 12 mm
diameter besi Ø 10 mm
banyaknya tulangan kolom 7 bh
banyaknya tulangan kolom 4

bj besi berat besi


panjang besi 8.888889 1.041885 7 64.8284
panjang besi 8.888889 0.88776 4 31.5648
ring 1.26 0.6165 60.25926 46.80879
150.3621 kg

begisting 1.4 8.888889 12.44444 m2

Balok 20/20 P L T
( ISI DATA YG BERTANDA TULISAN MERAH )
dimensi 0.2 0.2
tebal selimut 0.03 m

jarak sengkang 0.15 m


diameter besi Ø 12 mm
diameter besi Ø 0 mm
diameter besi Ø ( cincin) 8 mm
banyaknya tulangan kolom 4 bh
banyaknya tulangan kolom Ø 12

bj besi berat besi


panjang besi 25 0.88776 4 88.776
panjang besi 25 0 0 0
ring 0.66 0.39456 167.6667 43.66201
139.0599 kg

begisting 0.8 25 20 m2
BALOK 20 X 30

MEMANJANG 0.6 9 0.6165 1 3.3291


MELINTANG 1.56 3 0.6165 1 2.88522
6.21432 KG/M2
0.03 207.144 KG/M2

16.66667 9 0.6165 1 92.475


16.66667 3 0.6165 1 30.825
123.3
pembuktian

panjang bespanjang besi plat


1.525 1.1
0.1 0.4
0.48 0.1
0.48 1.6
2.585
4
10.34
ring
0.6
0.1
0.7

berat besi utk analiasa

luas begisting utk analisa

PEMBESIAN PONDASI setempat ( ISI DATA YG BERTANDA TULISAN MERAH )


P L T
ukuran PLAT 1.2 x 1.2 0.2
kolom 0.3 x 0.3
Ketinggian besi di baw 1.6
tebal selimut 0.025 m
over stage 0.48 m
jarak sengkang 0.15 m
diameter besi Ø 12 mm
diameter besi Ø 8 mm
Lantai kerja 0.05 m
banyaknya tulangan12 kolom 8 bh

panjang besi banyaknya sengkang bj besi berat besi


plat 2.7 9 2 0.88776 43.145136
foot
dia 12 31.125 0.88776 27.63153

dia 8 1.1 10.33333 0.39456 4.484832


75.261498

volume beton
plat 1.2 1.2 0.2 0.288
foot 0.3 0.3 1 0.09
0.378
berat besi utk analiasa Tulangan dlm 1 m3 75.2615 0.378 209.05972 berat besi utk analiasa

begisting Keliling Tinggi


plat 4.8 0.2 0.96
foot 1.2 1 1.2
2.16

luas begisting utk analisa 2.16 0.378 5.7142857 luas begisting utk analisa

kolom ukuran 20x20 P L T


( ISI DATA YG BERTANDA TULISAN MERAH )
dimensi 0.2 0.2
tebal selimut 0.025 m

jarak sengkang 0.15 m


diameter besi Ø 13 mm
diameter besi Ø 8 mm
banyaknya tulangan kolom
13 8 bh

bj besi berat besi


panjang besi 25 1.041885 8 208.377
ring 0.7 0.39456 167.6667 46.30819
267.4195 kg

begisting 0.8 25 20 m2

sloop 15x15 P L T
( ISI DATA YG BERTANDA TULISAN MERAH )
dimensi 0.15 0.15
146.2423 13.071895425 tebal selimut 0.025 m

jarak sengkang 0.15 m


diameter besi 12 mm
diameter besi 8 mm
banyaknya tulangan kolom 4 bh
banyaknya tulangan kolom Ø 8

bj besi berat besi


panjang besi 44.44444 0.88776 4 157.824
0.54 ring 0.5 0.39456 297.2963 58.650613
238.12207 kg

begisting 0.3 44.44444 13.333333 m2

balok 20x40 P L T balok lintel 12x15


( ISI DATA YG BERTANDA TULISAN MERAH )
dimensi 0.4 0.2 dimensi
tebal selimut 0.03 m tebal selimut

jarak sengkang 0.15 m jarak sengkang


diameter besi Ø 12 mm diameter besi Ø
diameter besi Ø 10 mm diameter besi Ø
diameter besi Ø 8 mm diameter besi Ø
banyaknya tulangan kolom
12 7 bh banyaknya tulangan10
kolom
banyaknya tulangan kolom
10 2 bh banyaknya tulangan kolom
0

bj besi berat besi


panjang besi 12.5 0.88776 7 77.679 panjang besi
12.5 0.6165 2 15.4125
ring 1.06 0.39456 84.33333 35.27103 ring
134.7807 kg

begisting 1 12.5 12.5 m2 begisting

Ring balok 20x20 P L T Ring 15x15


( ISI DATA YG BERTANDA TULISAN MERAH )
dimensi 0.2 0.2 dimensi
tebal selimut 0.025 m tebal selimut

jarak sengkang 0.15 m jarak sengkang


diameter besi Ø 12 mm diameter besi
diameter besi Ø 10 mm diameter besi
diameter besi Ø 8 mm diameter besi
banyaknya tulangan kolom 4 bh 12 banyaknya tulangan kolom
banyaknya tulangan kolom 0 bh 10 banyaknya tulangan kolom

bj besi berat besi


panjang besi 25 0.88776 4 88.776 panjang besi
25 0.6165 0 0
ring 0.7 0.39456 167.6667 46.30819 ring
141.8384 kg

begisting 0.6 25 15 m2 begisting

Kolom 25x25 P L T Kolom 12x12


( ISI DATA YG BERTANDA TULISAN MERAH )
dimensi 0.25 0.25 dimensi
tebal selimut 0.02 m tebal selimut

jarak sengkang 0.1 m jarak sengkang


diameter besi Ø 12 mm diameter besi
diameter besi Ø 8 mm diameter besi
banyaknya tulangan kolom 8 bh banyaknya tulangan kolom

bj besi berat besi


panjang besi 16 0.88776 8 113.6333 panjang besi
ring 0.94 0.39456 161 59.71271 ring
182.0133 kg

begisting 1 16 16 m2 begisting

PEMBESIAN PLAT LANTAI dua layer Kolom 15x15


( ISI DATA YG BERTANDA TULISAN MERAH )
tebal plat 0.15 mtr 1 dimensi
panjang besi dlm 1 mtr 6.666667 mtr tebal selimut

jarak sengkang 0.15 mtr jarak sengkang


diameter besi Ø 10 mm diameter besi
diameter besi Ø mm diameter besi
tebal selimut 0.025 mtr banyaknya tulangan kolom
pangang besi bj besi
banyaknya sengkang melin 44.44444 2.2 1 0.6165 60.28
banyaknya sengkang mem 6.666667 13.53333 1 0.6165 55.622 panjang besi
121.6971 kg ring

begisting 6.966667 1.3 9.056667 m2


begisting

PEMBESIAN PLAT LANT


satu layer
( ISI DATA YG BERTANDA TULISAN MERAH )
tebal plat 0.08 mtr 1
panjang besi dlm 1 mtr 12.5 mtr

jarak sengkang 0.15 mtr


diameter besi Ø 8 mm
diameter besi Ø 0 mm
tebal selimut 0.025 mtr
pangang besi bj besi
banyaknya sengkang m 83.33333 1.08 1 0.39456 35.5104
banyaknya sengkang 6.666667 12.58 1 0.39456 33.090432
72.030874 kg

begisting 12.66 1.16 14.6856 m2


379.94
6.666667 379.94
283.385
1889.233

1.24
Balok 20x35 P L T Balok 20x30
( ISI DATA YG BERTANDA TULISAN MERAH )
dimensi 0.2 0.35 dimensi
tebal selimut 0.03 m tebal selimut

jarak sengkang 0.15 m jarak sengkang


diameter besi Ø 16 mm diameter besi Ø
diameter besi Ø mm diameter besi Ø
diameter besi Ø 8 mm diameter besi Ø
banyaknya tulangan kolom 3 bh banyaknya tulangan kolom
banyaknya tulangan kolom Ø 12 banyaknya tulangan kolom

bj besi berat besi


panjang besi 14.28571 1.57824 3 67.63886 panjang besi
panjang besi 14.28571 0 0 0 panjang besi
ring 0.96 0.39456 96.2381 36.45283 ring
109.2963 kg

begisting 1.1 14.28571 15.71429 m2 begisting

Balok 20x50 P L T
( ISI DATA YG BERTANDA TULISAN MERAH )
dimensi 0.2 0.5
tebal selimut 0.03 m

jarak sengkang 0.15 m


diameter besi Ø 16 mm
diameter besi Ø mm
diameter besi Ø 8 mm
banyaknya tulangan kolom 5 bh
banyaknya tulangan kolom Ø 8

bj besi berat besi


panjang besi 10 1.57824 5 78.912
panjang besi 10 0 0 0
ring 1.26 0.39456 67.66667 33.64019
118.1798 kg

begisting 1.4 10 14 m2
berat besi utk analiasa

luas begisting utk analisa

Balok Kontileper 15x20 P L T


( ISI DATA YG BERTANDA TULISAN MERAH )
dimensi 0.2 0.15
tebal selimut 0.02 m

jarak sengkang 0.1 m


diameter besi 10 mm
diameter besi 6 mm
banyaknya tulangan10
kolom 4 bh
banyaknya tulangan kolom Ø

bj besi berat besi


panjang besi 33.33333 0.6165 4 82.2
ring 0.64 0.22194 334.3333 47.48924
142.6582 kg

begisting 0.55 33.33333 18.33333 m2

P L T balok lintel 15x30 P


( ISI DATA YG BERTANDA TULISAN MERAH ) ( ISI DATA YG BERTANDA TULISAN
0.12 0.15 dimensi 0.15
0.02 m tebal selimut 0.02 m

0.15 m jarak sengkang 0.15 m


10 mm diameter besi Ø 12 mm
mm diameter besi Ø mm
6 mm diameter besi Ø 6 mm
4 bh banyaknya tulangan12
kolom 6 bh
0 bh banyaknya tulangan kolom
0 0 bh

bj besi berat besi


55.55556 0.6165 4 137 panjang besi 22.22222
55.55556 0 0 0 22.22222
0.48 0.22194 371.3704 39.56253 ring 0.84
185.3907 kg

0.39 55.55556 21.66667 m2 begisting 0.6

Ring 15x15 P L T Ring balok 15x30 P


( ISI DATA YG BERTANDA TULISAN MERAH )
0.15 0.15 dimensi 0.3
tebal selimut 0.025 m tebal selimut 0.025

jarak sengkang 0.15 m jarak sengkang 0.15


diameter besi Ø 12 mm diameter besi Ø 12
diameter besi Ø 10 mm diameter besi Ø 10
diameter besi Ø 8 mm diameter besi Ø 8
banyaknya tulangan kolom 4 bh 12 banyaknya tulangan kolom 4
banyaknya tulangan kolom 0 bh 10 banyaknya tulangan kolom 2

bj besi berat besi


panjang besi 44.44444 0.88776 4 157.824 panjang besi 22.22222
44.44444 0.6165 0 0 22.22222
0.5 0.39456 297.2963 58.65061 ring 0.8
227.2983 kg

0.45 44.44444 20 m2 begisting 0.6

Kolom 12x12 P L T Kolom 30x30 P


( ISI DATA YG BERTANDA TULISAN MERAH )
0.12 0.12 dimensi 0.3
tebal selimut 0.025 m tebal selimut 0.03

jarak sengkang 0.15 m jarak sengkang 0.15


diameter besi Ø 12 mm diameter besi Ø 13
diameter besi Ø 8 mm diameter besi Ø 8
banyaknya tulangan kolom 4 bh banyaknya tulangan kolom 8

bj besi berat besi


panjang besi 69.44444 0.88776 4 246.6 panjang besi 11.11111
0.38 0.39456 463.963 69.56327 ring 1.06
331.9714 kg

0.24 69.44444 16.66667 m2 begisting 1.2

Kolom 15x15 P L T PEMBESIAN PLAT LANT


dua layer
( ISI DATA YG BERTANDA TULISAN MERAH )
0.15 0.15 tebal plat 0.12
tebal selimut 0.025 m panjang besi dlm 1 mtr 8.333333

jarak sengkang 0.15 m jarak sengkang 0.15


diameter besi Ø 12 mm diameter besi Ø 8
diameter besi Ø 8 mm diameter besi Ø 8
12 4 bh tebal selimut 0.025
bj besi berat besi banyaknya sengkang m 55.55556
panjang besi 44.44444 0.88776 4 157.824 banyaknya sengkang 6.666667
0.5 0.39456 297.2963 58.65061
227.2983 kg
begisting 8.573333
0.45 44.44444 20 m2

PEMBESIAN PLAT LANT


satu layer
( ISI DATA YG BERTANDA TULISAN MERAH )
tebal plat 0.12 mtr 1
panjang besi dlm 1 mtr 8.333333 mtr

jarak sengkang 0.15 mtr


diameter besi Ø 8 mm
diameter besi Ø 0 mm
tebal selimut 0.025 mtr
pangang besi bj besi
banyaknya sengkang m 55.55556 1.12 2 0.39456 49.1008
banyaknya sengkang 6.666667 8.453333 2 0.39456 44.4713
98.2507 kg

begisting 8.573333 1.24 10.63093 m2


P L T
( ISI DATA YG BERTANDA TULISAN MERAH )
0.2 0.3
0.03 m

0.15 m
16 mm
0 mm
8 mm
3 bh
0

bj besi berat besi


16.66667 1.57824 3 78.912
16.66667 0 0 0
0.86 0.39456 112.1111 38.04172
122.8014 kg

1 16.66667 16.66667 m2
L T
( ISI DATA YG BERTANDA TULISAN MERAH )
0.3
bj besi berat besi
0.88776 6 118.368
0 0 0
0.22194 149.1481 27.80563
153.4823 kg

22.22222 13.33333 m2

L T Ring balok 12x20 P L


( ISI DATA YG BERTANDA TULISAN MERAH ) ( ISI DATA YG BERTANDA TULISAN MERAH )
0.15 dimensi 0.2 0.12
m tebal selimut 0.02 m

m jarak sengkang 0.15 m


mm diameter besi Ø 12 mm
mm diameter besi Ø 0 mm
mm diameter besi Ø 8 mm
bh 12 banyaknya tulangan kolom 4 bh 12
bh 10 banyaknya tulangan kolom 0 bh 10

bj besi berat besi bj besi


0.88776 4 78.912 panjang besi 41.66667 0.88776
0.6165 2 27.4 41.66667 0
0.39456 149.1481 47.07831 ring 0.58 0.39456
161.0598 kg

22.22222 13.33333 m2 begisting 0.4 41.66667

L T Kolom 20x30 P L
( ISI DATA YG BERTANDA TULISAN MERAH ) ( ISI DATA YG BERTANDA TULISAN MERAH )
0.3 dimensi 0.2 0.3
m tebal selimut 0.03 m

m jarak sengkang 0.15 m


mm diameter besi Ø 12 mm
mm diameter besi Ø 8 mm
bh banyaknya tulangan kolom 6 bh

bj besi berat besi bj besi


1.041885 8 92.612 panjang besi 16.66667 0.88776
0.39456 75.07407 31.3985 ring 0.86 0.39456
130.211 kg

11.11111 13.33333 m2 begisting 1 16.66667

Kolom 20x20 P L
( ISI DATA YG BERTANDA TULISAN MERAH ) ( ISI DATA YG BERTANDA TULISAN MERAH )
mtr 1 dimensi 0.2 0.2
mtr tebal selimut 0.02 m

mtr jarak sengkang 0.1 m


mm diameter besi Ø 12 mm
mm diameter besi Ø 8 mm
mtr banyaknya tulangan kolom 6 bh
pangang besi bj besi
2.14 1 0.39456 46.9088 bj besi
16.80667 1 0.39456 44.20826 panjang besi 25 0.88776
95.67291 ring 0.74 0.39456

1.24 10.63093
begisting 0.8 25

6
589.5042 kg 0.39456 12 4.73472
124.5067

6
589.5042 34.33333 20.28 696.28 58.02333
49.12535 67.66667 10.28 695.6133 57.96778
115.9911
T
TA YG BERTANDA TULISAN MERAH )

berat besi
4 147.96
0 0
278.7778 63.79684
222.3447 kg

16.66667 m2

T
TA YG BERTANDA TULISAN MERAH )

berat besi
6 88.776
112.1111 38.04172
133.1586 kg

16.66667 m2

T
TA YG BERTANDA TULISAN MERAH )
berat besi
6 133.164
251 73.28557
216.7721 kg

20 m2
TIME SCHEDULLE
KEGIATAN : PENINGKATAN / REHABILITASI SARANA DAN PRASARANA PUSKESMAS/PUSKESMAS PEMBANTU
DAN JARINGANNYA PADA DINAS KESEHATAN KABUPATEN TASIKMALAYA.
PEKERJAAN : PENGEMBANGAN PUSKESMAS DTP CIPATUJAH
LOKASI : KECAMATAN CIPATUJAH KABUPATEN TASIKMALAYA

BOBOT MINGGU KE-


NO URAIAN PEKERJAAN
(%)
I II III IV V VI VII VIII IX X XI XII XIII XIV XV XVI XV
I. PEKERJAAN PERSIAPAN 1.107 0.065 0.065 0.065 0.065 0.065 0.065 0.065 0.065 0.065 0.065 0.065 0.065 0.065 0.065 0.065 0.065 0.

II. PEKERJAAN GALIAN DAN URUGAN 2.751 1.751 1.001

III. PEKERJAAN PONDASI 8.597 1.517 3.540 3.540

IV. PEKERJAAN BETON 14.139 1.116 2.605 2.605 2.605 2.605 2.605

V. PEKERJAAN DINDING DAN PLESTERAN 17.246 2.874 2.874 2.874 2.874 2.874 2.874

VI. PEKERJAAN KUSEN, PINTU DAN JENDELA 7.492 1.498 1.498 1.498 1.498 1.498

VII. PEKERJAAN ATAP DAN KUDA-KUDA 21.304 4.261 4.261 4.261 4.261 4.261

VIII. PEKERJAAN RANGKA DAN PENUTUP PLAFOND 5.063 1.266 1.266 1.266 1.266

IX. PEKERJAAN LANTAI, RABAT DAN SALURAN 8.849 2.212 2.212 2.212 2.212

X. PEKERJAAN PENGECATAN DAN LABURAN 5.402 1.350 1.350 1.350 1.

XI. PEKERJAAN GANTUNGAN DAN KUNCI 1.887 0.944 0.944

XII. PEKERJAAN INSTALASI LISTRIK 2.635 0.878 0.878 0.878

XIII. PEKERJAAN PLUMBING DAN SANITAIR 3.526 0.441 1.029 1.029 1.029

AKUMULATIF KEMAJUAN PEKERJAAN 100.00 3.333 4.721 6.650 7.042 7.042 8.078 6.538 3.775 4.168 5.544 9.429 9.642 7.563 3.359 5.922 5.771 1.

RENCANA KEMAJUAN PEKERJAAN 3.333 8.054 14.704 21.745 28.787 36.866 43.403 47.178 51.346 56.889 66.318 75.960 83.523 86.883 92.804 98.576

REALISASI KEMAJUAN PEKERJAAN

CEPAT / LAMBAT

Tasikmalaya, 17 Juli 2009


Penawar,
CV. ADIS PRATAMA

ADE HERYANTO
Direktur
HEDULLE

MINGGU KE- PROSENTASE


(%)
XVII
0.074 100

50

1.350

1.424

100
DAFTAR HARGA UPAH KERJA
WILAYAH KOTA TASIKMALAYA
TAHUN ANGGARAN 2014

UPAH
NO. JENIS TENAGA KERJA SATUAN
( Rp )
(a) (b) (c) (e)

1 Pekerja (setengah terampil) HOK 45,000.00

2 Pekerja ( terampil) HOK 47,500.00

3 Tukang Gali HOK 45,000.00

4 Tukang Batu ( setengah terampil) HOK 47,500.00

5 Tukang Batu ( terampil) HOK 60,000.00

6 Kepala Tukang Batu HOK 70,000.00

7 Tukang Kayu ( setengah terampil) HOK 60,000.00

8 Tukang Kayu ( terampil) HOK 65,000.00

9 Kepala Tukang Kayu HOK 70,000.00

10 Tukang Cat / Plitur ( setengah terampil) HOK 47,500.00

11 Tukang Cat / Plitur ( terampil) HOK 60,000.00

12 Kepala Tukang Cat / Plitur HOK 70,000.00

13 Tukang Besi Beton ( setengah terampil) HOK 60,000.00

14 Tukang Besi Beton ( terampil) HOK 65,000.00

15 Kepala Tukang Besi Beton HOK 70,000.00

16 Tukang Besi Frofil ( setengah terampil) HOK 60,000.00

17 Tukang Besi Frofil ( terampil) HOK 65,000.00

18 Kepala Tukang Besi Beton HOK 70,000.00

19 Mandor HOK 70,000.00

20 Mekanik HOK 70,000.00

21 Pembantu Mekanik HOK 55,000.00

22 Operator Alat Besar HOK 70,000.00

23 Pembantu Operator HOK 60,000.00

24 Supir Truk HOK 60,000.00

25 Kenek Truk / Pembantu Supir Truk HOK 45,000.00

26 Penjaga Malam HOK 45,000.00


DAFTAR HARGA BAHAN BANGUNAN
WILAYAH KOTA TASIKMALAYA
TAHUN ANGGARAN 2014
Halaman 1
HARGA
NO. JENIS BAHAN SATUAN
( Rp )
(a) (b) (c) (e)

A. AGREGAT KASAR, BAHAN PEREKAT DAN BAHAN JADINYA


1 Abu Batu m3 157,500.00
1 Tanah Urug/ Timbunan Pilihan/ Barangkal m3 45,500.00
2 Sirtu ( tersaring bergradasi ) m3 85,500.00
3 Pasir Urug /Bawah lantai m3 78,000.00
4 Pasir Pasang /Pasang Kali m3 123,500.00
5 Pasir Pasang /gunung pilihan m3 95,000.00
6 Pasir Beton m3 152,000.00
7 Batu Belah m3 95,000.00
8 Batu Pecah ( tersaring bergradasi ) m3 125,000.00
8 Batu Pecah 0,5/1 ( Screen ) m3 161,500.00
9 Batu Pecah 0 - 5 m3 184,000.00
10 Batu Pecah 5 - 10 & 10 - 20 mm m3 184,000.00
10 Batu Pecah 1/2 m3 175,500.00
9 Batu Pecah 2/3 m3 175,500.00
10 Batu Pecah 3/5 m3 142,500.00
11 Batu Pecah 5/7 m3 119,500.00
12 Batu Pecah 10/15 m3 91,000.00
9 Batu Candi m3 92,000.00
10 Batu Muka m3 -
11 Batu Tempel (Beraturan) m2 92,000.00
12 Batako Kecil ( 8x10x20 ) bh 9,500.00
13 Batako Besar ( 8x20x30 ) bh 3,000.00
14 Hollow Block 15 cm (HB-15) /batako lubang bh 2,400.00
15 Hollow Block 20 cm (HB-20) /batako lubang bg 2,400.00
16 Formtie/Spacer Beton bh 2,500.00
16 Teracorta (10 x 20) cm bh 1,600.00
10 Bata Merah bh 700.00
11 Semen Portland ( PC ) /50 Kg Zak 68,000.00
12 Semen Portland ( PC ) Putih Zak 99,500.00
13 Semen Warna Kg 9,000.00

C. BAHAN LOGAM DAN BAHAN JADINYA


1 Besi Plat Kg 17,500.00
2 Besi Beton ( ukuran rata rata) Kg 12,000.00
3 Besi Frofil Kg 18,500.00
4 Tralis Minimalis m2 285,000.00
5 Tralis Besi Tempa m2 190,000.00
4 Kawat Beton Kg 18,000.00
5 Seng Plat BJLS 28 " lbr 70,500.00
6 Lem Kuning ( aibond ) Kg 128,000.00
7 Lem Fox Kg 12,500.00
10 Kusen Alumunium 4" Silver (harga sudah terpasang) m¹ 76,000.00
11 Kusen Alumunium 4" Brown (harga sudah terpasang) m¹ 90,000.00
(a) (b) (c) (e)

12 Kusen Pintu Alumunium KM/WC Komplit dg kunci (Harga sudah terpasang) Unit 736,000.00
8 Baja Ringan Zinc Alum c75, Tebal Standar 0,7/ 0,75 mm (Harga Terpasang) m2 160,000.00
14 List Pintu dan Jendela Alumunium (Harga sudah terpasang) m1 10,000.00
35 Daun Pintu dan Jendela Alumunium (harga sudah terpasang) m¹ 64,000.00
39 Besi Hoolo 20.40 btg 43,000.00
40 Besi Hoolo 40.40 btg 57,000.00
41 Gantungan Plafond Rangka Hollo m1 1,500.00

C. BAHAN SALURAN AIR KOTOR /BERSIH


1 Grefel U-20 cm m' 19,000.00
2 Injuk Kg 7,500.00

D. BAHAN PERPIPAAN
1 Pipa PVC Ø 1/2" (Setara Maspion ) m1 2,750.00
2 Pipa PVC Ø 3/4" (Setara Maspion) m1 3,750.00
3 Pipa PVC Ø 1" (Setara Maspion ) m1 19,750.00
4 Pipa PVC Ø 1 1/2" (Setara Maspion) m1 25,750.00
5 Pipa PVC Ø 2" (Setara Maspion) m1 32,500.00
6 Pipa PVC Ø 2 1/2" (Setara Wavin) m1 36,500.00
7 Pipa PVC Ø 3" (Setara Wavin) m1 64,250.00
8 Pipa PVC Ø 4" (Setara Wavin) m1 94,500.00
9 Talang 4 M' m1 7,000.00
10 Gantungan Plat bh 1,250.00
11 Gantungan Plastik bh 750.00
12 Pipa GIV 2" m1 205,250.00

E. BAHAN KAYU BERIKUT BAHAN JADINYA


1 Bambu Diameter 5 s/d 7 cm btg 6,200.00
2 Bambu Diameter 7 s/d 10 cm btg 9,400.00
3 Bambu Gombong btg 21,900.00
4 Dolken 5 s/d 7 cm btg 28,200.00
(a) (b) (c) (e)

5 Dolken 7 s/d 10 cm btg 84,600.00


6 Kayu Balok Kayu Gunung Klas II 6/12, 8/12, 8/15* m3 2,850,000.00
7 Kayu Kaso 5/7, 5/10 Kayu Gunung Klas II* m3 2,499,000.00
8 Papan Kayu Gunung Klas II Setara Rasamala m3 3,325,000.00
9 Kayu Papan /Kaso, Kayu Gunung Klas III ( Albasia )* m3 1,881,000.00
10 Kayu Papan /Kayu Gunung Klas III ( Albasia )* m3 1,881,000.00
11 Kayu Reng 2/3 Gunung Klas II Kuat m' 5,700.00
12 Kayu Reng 3/4 Gunung Klas II Kuat m' 5,500.00
13 List Frofil Kayu Kamper m' 6,500.00
14 List Frofil Kayu Gunung Klas II m' 5,500.00
15 List Frofil Gypsun 9 mm m1 14,000.00

F. BAHAN PENUTUP RANGKA PLAFOND


1 Eternit 1x1 M2 bh 8,500.00
2 Gypsun 120 x 240 cm, t = 9 mm ex DN lbr 76,000.00
3 Calsibot 120 x 240 cm, t = 6 mm lbr 57,000.00
4 Bahan Plapon GRC 5 mm 120 x 240 cm lbr 52,200.00
5 GRC 40 x 240 cm, t = 9 mm L = 20 cm Untuk Listplank m1 53,200.00

G. BAHAN KAYU LAPIS DAN DINDING PELAPIS


1 Triplek 3 mm 120 x 240 lbr 47,200.00
2 Triplek 4 mm 120 x 240 lbr 60,600.00
3 Triplek 4 mm Uk/ Pintu lbr 115,900.00
4 Multiplex T = 10 mm m2 37,657.89
5 HPL Warna m2 56,805.97

H. BAHAN FINISHING : LABURAN, PENGISIAN DAN ALATNYA


1 Ampelas Lbr 1,800.00
2 Cat Besi SIEV Kg 37,600.00
3 Cat Genting Kg 56,400.00
4 Cat Kayu Stara AVIAN Kg 42,700.00
5 Cat Kayu Stara SIEV Kg 42,700.00
6 Cat Kayu Stara AMCO Kg 54,100.00
7 Cat Batu Kg 77,400.00
8 Cat Dasar Kg 47,000.00
9 Cat Soligneum Galon /5 Ltr 18,800.00
10 Cat Tembok Stara Sanlex Kg 15,600.00
11 Cat Tembok Stara Sanlex ( Putih ) Kg 15,600.00
12 Dempul Halus /INFRA ( Wood Filler ) Kg 35,100.00
13 Dempul Kayu Kg 15,600.00
14 Kape Kayu Bh 6,200.00
15 Kape Tembok Bh 6,200.00
16 Kawas 3 " bh 9,400.00
17 Kawas 4 " bh 12,600.00
16 Kumpon Kg 4,300.00
17 Meni Kayu /Besi Kg 16,700.00
18 Oker Coklat Kg 35,500.00
19 Oker Putih Kg 35,500.00
20 Plamir Cat Kg 14,600.00
21 Plamir Tembok Kg 25,000.00
22 Rol cat Tembok Bh 12,500.00
23 Sincromat Kg 14,600.00
(a) (b) (c) (e)

24 Sirlak Ex India Kg 75,200.00


25 Spirtus Ltr 14,600.00
(a) (b) (c) (e)

26 Terpentin Ltr 3,000.00


27 Tiner A Ltr 8,700.00
28 Tiner ND Ltr 20,100.00
29 Water Profing Emulision Kg 104,500.00
30 Vernis Kg 17,300.00

I. BAHAN KACA
1 Kaca Polos 3 mm m2 50,100.00
2 Kaca Polos 5 mm m2 61,700.00

J. BAHAN PAKU DAN MUR-BAUT


1 Beugel Kuda-kuda Kg 31,500.00
2 Paku ( berbagai macam ukuran ) Kg 18,800.00
3 Paku Beton 2 cm s/d 5 cm bh 500.00
4 Paku Tembok 3 cm dus 39,300.00

L. BAHAN PENUTUP ATAP


1 Bubung Morando Natural bh 3,500.00
2 Bubung Morando Glatsur bh 3,800.00
3 Genteng Morando Natural 18 bh/m2 bh 2,200.00
4 Genteng Morando Glatsur 18 bh/m2 bh 2,600.00

M. BAHAN MEKANIKAL & ELEKTRIKAL ( ME )


1 Box Sikring In-bouw C4 bh 49,800.00
2 Lampu Pijar 25 Watt bh 4,800.00
3 Lampu Pijar 40 Watt bh 8,400.00
4 Lampu SL 18 Watt bh 41,800.00
5 Saklar Triple Broco bh -
6 Saklar Ganda Broco bh 17,100.00
7 Saklar Tunggal Broco bh 12,800.00
8 Stop Kontak Broco bh 13,300.00
9 Titik Cahaya Ttk 139,300.00
10 Instalasi Stop Kontak Ttk 139,300.00
11 Biaya Penyambungan Dari Bangunan Lama Ls 285,000.00

N. BAHAN ALAT PENGGANTUNG KUNCI


1 Engsel Jendela bh 19,000.00
2 Engsel Jendela Stara Unilon bh 3,900.00
3 Engsel Pintu bh 34,200.00
4 Engsel Pintu Stara Unilon bh 9,500.00
5 Espangnolet Psg 34,500.00
6 Hak Angin Kait Biasa Psg 3,300.00
7 Hak Angin Jendela Dorong Psg 24,800.00
8 Hak Angin Kait Jendela Biasa Psg 3,300.00
9 Kunci tanam 2 Slaggh Stara Tesa bh 138,700.00
10 Slot Jendela bh 4,800.00
11 Slot Pintu bh 7,100.00

P. BAHAN LANTAI DAN PELAPIS DINDING


1 Keramik 30 x 30 KW I DN Putih ( polos) m2 /Dus 37,900.00
2 Keramik 30 x 30 KW I DN ( Warna) m2 /Dus 42,900.00
(a) (b) (c) (e)

3 Keramik 30 x 30 KW I DN Warna Anti slip m2 /Dus 47,500.00


(a) (b) (c) (e)

Q. HARGA BBM *)
1 Premium Ltr 6,100.00
2 Minyak Tanah Ltr 8,300.00
3 Minyak Bekisting Ltr 20,900.00
4 Minyak Pelumas Ltr 20,900.00
5 Minyak Bakar Ltr 5,700.00
ANALISA HARGA SATUAN PEKERJAAN
WILAYAH KOTA TASIKMALAYA
TAHUN ANGGARAN 2014

HARGA HARGA SATUAN


HARGA
KODE JENIS PEKERJAAN KOEFISIEN SATUAN UPAH BAHAN PEKERJAAN
( Rp ) ( Rp ) ( Rp ) ( Rp )
a b c d e f=(cxe) g=(cxe) h

A PEKERJAAN PERSIAPAN

A-02 1 m2 PEKERJAAN PEMASANGAN BOUWPLANK


Kayu 5/7 0.0080 m3 1,881,000.00 15,048.00
Paku biasa 2"-5" 0.0200 Kg 18,800.00 376.00
Kayu papan 3/20 0.0025 m3 1,881,000.00 4,702.50
Ongkos pasang 0.1550 Lot 20,126.50 3,119.61
Jumlah 3,119.61 20,126.50
Keuntungan 311.96 2,012.65
Jumlah Total 3,431.57 22,139.15 25,570.72
Dibulatkan 25,570.00

A-05 1 m2 PEKERJAAN MEMBERSIHKAN DAN PERATAAN LAPANGAN


Pekerja 0.1000 HOK 45,000.00 4,500.00
Mandor 0.0500 HOK 70,000.00 3,500.00
Jumlah 8,000.00
Keuntungan 800.00
Jumlah Total 8,800.00 8,800.00
Dibulatkan 8,800.00

B PEKERJAAN TANAH

B-01 1 m3 GALIAN TANAH BIASA SEDALAM 1 METER


Pekerja 0.4000 HOK 45,000.00 18,000.00
Mandor 0.0400 HOK 70,000.00 2,800.00
Jumlah 20,800.00
Keuntungan 2,080.00
Jumlah Total 22,880.00 22,880.00
Dibulatkan 22,880.00

B-06 1 m3 URUGAN KEMBALI


Pekerja 0.1920 HOK 45,000.00 8,640.00
Mandor 0.0190 HOK 70,000.00 1,330.00
Jumlah 9,970.00
Keuntungan 997.00
Jumlah Total 10,967.00 10,967.00
Dibulatkan 10,967.00

B-07 1 m3 PEMADATAN TANAH


Pekerja 0.5000 HOK 45,000.00 22,500.00
Mandor 0.0500 HOK 70,000.00 3,500.00
Jumlah 26,000.00
Keuntungan 2,600.00
Jumlah Total 28,600.00 28,600.00
Dibulatkan 28,600.00

B-08 1 m3 URUGAN TANAH DIPADATKAN 35,970.00


(B-06+B-07)

B-09 1 m3 URUGAN PASIR


Pasir urug 1.2000 m3 78,000.00 93,600.00
Pekerja 0.3000 HOK 45,000.00 13,500.00
Mandor 0.0100 HOK 70,000.00 700.00
Jumlah 14,200.00 93,600.00
Keuntungan 1,420.00 9,360.00
Jumlah Total 15,620.00 102,960.00 118,580.00
a b c d e f=(cxe) g=(cxe) h
Dibulatkan 118,580.00

B-10 1 m3 URUGAN TANAH BELI DARI LUAR


Pasir urug 1.2000 m3 45,500.00 54,600.00
Pekerja 0.3000 HOK 45,000.00 13,500.00
Mandor 0.0100 HOK 70,000.00 700.00
Jumlah 14,200.00 54,600.00
Keuntungan 1,420.00 5,460.00
Jumlah Total 15,620.00 60,060.00 75,680.00
Dibulatkan 75,680.00

C PEKERJAAN PONDASI

C-03 1 m3 PASANGAN PONDASI BATU KALI, 1 Pc : 5 Ps


Batu belah 15/20 cm 1.1000 m3 95,000.00 104,500.00
Semen PC (50 kg) 2.7200 Zak 68,000.00 184,960.00
Pasir pasang kali 0.5440 m3 95,000.00 51,680.00
Pekerja 1.5000 HOK 45,000.00 67,500.00
Tukang batu 0.6000 HOK 60,000.00 36,000.00
Kepala tukang 0.0600 HOK 70,000.00 4,200.00
Mandor 0.0750 HOK 70,000.00 5,250.00
Jumlah 112,950.00 341,140.00
Keuntungan 11,295.00 34,114.00
Jumlah Total 124,245.00 375,254.00 499,499.00
Dibulatkan 499,499.00

C-04 1 m3 PASANGAN PONDASI BATU KOSONG


Batu belah 15/20 cm 1.2000 m3 95,000.00 114,000.00
Pasir urug 0.3000 m3 78,000.00 23,400.00
Pekerja 0.7800 HOK 45,000.00 35,100.00
Tukang batu 0.3900 HOK 60,000.00 23,400.00
Kepala tukang 0.0390 HOK 70,000.00 2,730.00
Mandor 0.0390 HOK 70,000.00 2,730.00
Jumlah 63,960.00 137,400.00
Keuntungan 6,396.00 13,740.00
Jumlah Total 70,356.00 151,140.00 221,496.00
Dibulatkan 221,496.00

D PEKERJAAN DINDING

D-02 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 5 Ps


Bata merah ( 5x11x22 ) cm 70.0000 Bh 700.00 49,000.00
Semen PC (50 kg) 0.1936 Zak 68,000.00 13,164.80
Pasir pasang 0.0450 m3 95,000.00 4,275.00
Pekerja 0.3200 HOK 45,000.00 14,400.00
Tukang batu 0.1000 HOK 60,000.00 6,000.00
Kepala tukang 0.0100 HOK 70,000.00 700.00
Mandor 0.0150 HOKK 70,000.00 1,050.00
Jumlah 22,150.00 66,439.80
Keuntungan 2,215.00 6,643.98
Jumlah Total 24,365.00 73,083.78 97,448.78
Dibulatkan 97,448.00

E PEKERJAAN PLESTERAN

E-03 1 m2 PLESTERAN 1 PC : 5 Ps, TEBAL 15 mm


Semen PC (50 kg) 0.0864 Zak 68,000.00 5,875.20
Pasir pasang 0.0220 m3 95,000.00 2,090.00
Pekerja 0.2000 HOK 45,000.00 9,000.00
Tukang batu 0.1500 HOK 60,000.00 9,000.00
Kepala tukang 0.0150 HOK 70,000.00 1,050.00
Mandor 0.0100 HOK 70,000.00 700.00
Jumlah 19,750.00 7,965.20
Keuntungan 1,975.00 796.52
Jumlah Total 21,725.00 8,761.72 30,486.72
Dibulatkan 30,486.00
a b c d e f=(cxe) g=(cxe) h

E-05 1 m2 ACIAN PLESTERAN (A077)


Semen PC (50 kg) 0.0800 Zak 68,000.00 5,440.00
Pekerja 0.1430 HOK 45,000.00 6,435.00
Tukang batu 0.1070 HOK 60,000.00 6,420.00
Kepala tukang 0.0105 HOK 70,000.00 735.00
Mandor 0.0100 HOK 70,000.00 700.00
Jumlah 14,290.00 5,440.00
Keuntungan 1,429.00 544.00
Jumlah Total 15,719.00 5,984.00 21,703.00
Dibulatkan 21,703.00

F PEKERJAAN KAYU

F-02 1 m3 PASANG KUSEN PINTU DAN JENDELA KAYU GUNUNG KELAS II


Kayu Gunung Kls II, balok 1.1000 m3 2,850,000.00 3,135,000.00
Paku 1.2500 kg 18,800.00 23,500.00
Lem Putih ( FOX) 0.5000 kg 12,500.00 6,250.00
Pekerja Terampil 4.0000 HOK 47,500.00 190,000.00
Tukang kayu terampil 15.5000 HOK 65,000.00 1,007,500.00
Kepala tukang 2.7000 HOK 70,000.00 189,000.00
Mandor 0.5000 HOK 70,000.00 35,000.00
Jumlah 1,421,500.00 3,164,750.00
Keuntungan 142,150.00 316,475.00
Jumlah Total 1,563,650.00 3,481,225.00 5,044,875.00
Dibulatkan 5,044,875.00

F-05 1 m2 PASANG PINTU PANEL KAYU GUNUNG KELAS II


Kayu Gunung Kls II, papan 0.0400 m3 3,325,000.00 133,000.00
Pekerja 1.0000 HOK 45,000.00 45,000.00
Tukang kayu trampil 2.5000 HOK 65,000.00 162,500.00
Kepala tukang 0.2500 HOK 70,000.00 17,500.00
Mandor 0.0500 HOK 70,000.00 3,500.00
Jumlah 228,500.00 133,000.00
Keuntungan 22,850.00 13,300.00
Jumlah Total 251,350.00 146,300.00 397,650.00
Dibulatkan 397,650.00

F-07 1 m2 JENDELA KACA KAYU GUNUNG KELAS II (Tanpa Kaca)


Rangka Kayu Gunung Klas II 0.0170 m3 3,325,000.00 56,525.00
Lem Putih ( FOX ) 0.1000 kg 12,500.00 1,250.00
List Kayu Gunung Klas II 4.0000 m' 5,500.00 22,000.00
Pekerja 1/2 Terampil 0.3000 HOK 45,000.00 13,500.00
Tukang kayu Terampil 1.2000 HOK 65,000.00 78,000.00
Kepala tukang 0.1200 HOK 70,000.00 8,400.00
Mandor 0.0200 HOK 70,000.00 1,400.00
Jumlah 101,300.00 79,775.00
Keuntungan 10,130.00 7,977.50
Jumlah Total 111,430.00 87,752.50 199,182.50
Dibulatkan 199,182.00

F-22 1 m' PASANG LIST PLAFOND KAYU PROFIL


Kayu profil 1.0500 m' 5,500.00 5,775.00
Pekerja 1/2 trampil 0.0210 HOK 45,000.00 945.00
Tukang kayu 1/2 trampil 0.0210 HOK 60,000.00 1,260.00
Kepala tukang 0.0020 HOK 70,000.00 140.00
Mandor 0.0010 HOK 70,000.00 70.00
Jumlah 2,415.00 5,775.00
Keuntungan 241.50 577.50
Jumlah Total 2,656.50 6,352.50 9,009.00
Dibulatkan 9,009.00

G PEKERJAAN BETON

G-01 1 m3 MEMBUAT BETON TUMBUK, 1 PC : 3 Ps : 5 Kr


Semen PC (50 kg) 4.3600 Zak 68,000.00 296,480.00
a b c d e f=(cxe) g=(cxe) h
Pasir beton 0.5200 m3 152,000.00 79,040.00
Koral beton 0.8700 m3 175,500.00 152,685.00
Pekerja 1.6500 HOK 45,000.00 74,250.00
Tukang batu 0.2500 HOK 60,000.00 15,000.00
Kepala tukang 0.0250 HOK 70,000.00 1,750.00
Mandor 0.0800 HOK 70,000.00 5,600.00
Jumlah 96,600.00 528,205.00
Keuntungan 9,660.00 52,820.50
Jumlah Total 106,260.00 581,025.50 687,285.50
Dibulatkan 687,285.00

G-02 1 m2 MEMBUAT LANTAI KERJA BETON TUMBUK TEBAL 5 cm, 1 PC : 3 Ps : 5 Kr


Semen PC (50 kg) 0.2000 Zak 68,000.00 13,600.00
Pasir beton 0.0260 m3 152,000.00 3,952.00
Split 2/3 0.0440 m3 175,500.00 7,722.00
Pekerja 1.1500 HOK 45,000.00 51,750.00
Tukang batu 0.0200 HOK 60,000.00 1,200.00
Kepala tukang 0.0020 HOK 70,000.00 140.00
Mandor 0.0060 HOK 70,000.00 420.00
Jumlah 53,510.00 25,274.00
Keuntungan 5,351.00 2,527.40
Jumlah Total 58,861.00 27,801.40 86,662.40
Dibulatkan 86,662.00

G-03 1 m3 MEMBUAT BETON DENGAN MUTU K-175


Semen PC (50 kg) 4.6400 Zak 68,000.00 315,520.00
Pasir beton 0.5200 m3 152,000.00 79,040.00
Split 2/3 0.7800 m3 175,500.00 136,890.00
Pekerja 1.6500 HOK 45,000.00 74,250.00
Tukang batu 0.2500 HOK 60,000.00 15,000.00
Kepala tukang 0.0250 HOK 70,000.00 1,750.00
Mandor 0.0800 HOK 70,000.00 5,600.00
Jumlah 96,600.00 531,450.00
Keuntungan 9,660.00 53,145.00
Jumlah Total 106,260.00 584,595.00 690,855.00
Dibulatkan 10/11 628,050.00

G-07 1 Kg PEMBESIAN DENGAN BESI POLOS ATAU ULIR


Besi beton ( polos /ulir ) 1.0500 Kg 12,000.00 12,600.00
Kawat beton 0.0150 Kg 18,000.00 270.00
Pekerja 0.0070 HOK 45,000.00 315.00
Tukang besi 0.0070 HOK 60,000.00 420.00
Kepala tukang 0.0007 HOK 70,000.00 49.00
Mandor 0.0003 HOK 70,000.00 21.00
Jumlah 805.00 12,870.00
Keuntungan 80.50 1,287.00
Jumlah Total 885.50 14,157.00 15,042.50
Dibulatkan 15,042.00

G-08 1 m2 PASANG BEKISTING UNTUK PONDASI


Kayu terentang 0.0400 m3 1,881,000.00 75,240.00
Paku biasa 2'-5" 0.3000 Kg 18,800.00 5,640.00
Minyak bekisting 0.1000 Ltr 20,900.00 2,090.00
Pekerja 0.3000 HOK 45,000.00 13,500.00
Tukang kayu 0.2600 HOK 60,000.00 15,600.00
Kepala tukang 0.0260 HOK 70,000.00 1,820.00
Mandor 0.0050 HOK 70,000.00 350.00
Jumlah 31,270.00 82,970.00
Keuntungan 3,127.00 8,297.00
Jumlah Total 34,397.00 91,267.00 125,664.00
Dibulatkan 125,664.00

G-09 1 m2 PASANG BEKISTING UNTUK SLOOF


Kayu terentang 0.0450 m3 1,881,000.00 84,645.00
Paku biasa 2'-5" 0.3000 Kg 18,800.00 5,640.00
a b c d e f=(cxe) g=(cxe) h
Minyak bekisting 0.1000 Ltr 20,900.00 2,090.00
Pekerja 0.3000 HOK 45,000.00 13,500.00
Tukang kayu 0.2600 HOK 60,000.00 15,600.00
Kepala tukang 0.0260 HOK 70,000.00 1,820.00
Mandor 0.0260 HOK 70,000.00 1,820.00
Jumlah 32,740.00 92,375.00
Keuntungan 3,274.00 9,237.50
Jumlah Total 36,014.00 101,612.50 137,626.50
Dibulatkan 137,626.00

G-10 1 m2 PASANG BEKISTING UNTUK KOLOM


Kayu terentang 0.0400 m3 1,881,000.00 75,240.00
Paku biasa 2'-5" 0.4000 Kg 18,800.00 7,520.00
Minyak bekisting 0.2000 Ltr 20,900.00 4,180.00
Balok kayu 0.0150 m3 1,881,000.00 28,215.00
Papan Albasiah 0.0200 m3 1,881,000.00 37,620.00
Bambu Batang dia 7cm 2.0000 Batang 9,400.00 18,800.00
Pekerja 0.3000 HOK 45,000.00 13,500.00
Tukang kayu 0.3300 HOK 60,000.00 19,800.00
Kepala tukang 0.0330 HOK 70,000.00 2,310.00
Mandor 0.0060 HOK 70,000.00 420.00
Jumlah 36,030.00 171,575.00
Keuntungan 3,603.00 17,157.50
Jumlah Total 39,633.00 188,732.50 228,365.50
Dibulatkan 228,365.00

G-11 1 m2 PASANG BEKISTING UNTUK BALOK


Kayu terentang 0.0400 m3 1,881,000.00 75,240.00
Paku biasa 2'-5" 0.4000 Kg 18,800.00 7,520.00
Minyak bekisting 0.2000 Ltr 20,900.00 4,180.00
Balok kayu 0.0180 m3 1,881,000.00 33,858.00
Papan Albasia 0.0200 m3 1,881,000.00 37,620.00
Bambu Batang dia 7cm 2.0000 Batang 9,400.00 18,800.00
Pekerja 0.3200 HOK 45,000.00 14,400.00
Tukang kayu 0.3300 HOK 60,000.00 19,800.00
Kepala tukang 0.0330 HOK 70,000.00 2,310.00
Mandor 0.0060 HOK 70,000.00 420.00
Jumlah 36,930.00 177,218.00
Keuntungan 3,693.00 17,721.80
Jumlah Total 40,623.00 194,939.80 235,562.80
Dibulatkan 235,562.00

G-12 1 m2 PASANG BEKISTING UNTUK LANTAI


Kayu terentang 0.0400 m3 1,881,000.00 75,240.00
Paku biasa 2'-5" 0.4000 Kg 18,800.00 7,520.00
Minyak bekisting 0.2000 Ltr 20,900.00 4,180.00
Balok kayu 0.0150 m3 1,881,000.00 28,215.00
Papan Albasia 0.0200 m3 1,881,000.00 37,620.00
Bambu Batang dia 7cm 6.0000 Batang 9,400.00 56,400.00
Pekerja 0.3200 HOK 45,000.00 14,400.00
Tukang batu 0.3300 HOK 60,000.00 19,800.00
Kepala tukang 0.0330 HOK 70,000.00 2,310.00
Mandor 0.0060 HOK 70,000.00 420.00
Jumlah 36,930.00 209,175.00
Keuntungan 3,693.00 20,917.50
Jumlah Total 40,623.00 230,092.50 270,715.50
Dibulatkan 270,715.00

G-13 1 m2 PASANG BEKISTING UNTUK DINDING


Kayu terentang 0.0300 m3 1,881,000.00 56,430.00
Paku biasa 2'-5" 0.4000 Kg 18,800.00 7,520.00
Minyak bekisting 0.2000 Ltr 20,900.00 4,180.00
Balok kayu 0.0200 m3 1,881,000.00 37,620.00
Papan Albasia 0.0200 m3 1,881,000.00 37,620.00
Bambu Batang dia 7cm 3.0000 Batang 9,400.00 28,200.00
Pekerja 0.3200 HOK 45,000.00 14,400.00
a b c d e f=(cxe) g=(cxe) h
Tukang batu 0.3300 HOK 60,000.00 19,800.00
Kepala tukang 0.0330 HOK 70,000.00 2,310.00
Mandor 0.0060 HOK 70,000.00 420.00
Jumlah 36,930.00 171,570.00
Keuntungan 3,693.00 17,157.00
Jumlah Total 40,623.00 188,727.00 229,350.00
Dibulatkan 229,350.00

G-14 1 m2 PASANG BEKISTING UNTUK TANGGA


Kayu terentang 0.0300 m3 1,881,000.00 56,430.00
Paku biasa 2'-5" 0.4000 Kg 18,800.00 7,520.00
Minyak bekisting 0.2000 Ltr 20,900.00 4,180.00
Balok kayu 0.0200 m3 1,881,000.00 37,620.00
Formtie /spacer /penjaga jarak bekisting 4.0000 Bh 2,500.00 10,000.00
Papan Albasia 0.0200 m3 1,881,000.00 37,620.00
Bambu Batang dia 7cm 3.0000 Batang 9,400.00 28,200.00
Pekerja 0.6600 HOK 45,000.00 29,700.00
Tukang batu 0.3300 HOK 60,000.00 19,800.00
Kepala tukang 0.0330 HOK 70,000.00 2,310.00
Mandor 0.0330 HOK 70,000.00 2,310.00
Jumlah 54,120.00 181,570.00
Keuntungan 5,412.00 18,157.00
Jumlah Total 59,532.00 199,727.00 259,259.00
Dibulatkan 259,259.00

G-15 1 m3 MEMBUAT PONDASI BETON BERTULANG T= 25 CM + Bekisting


Besi beton + Kawat Pengikat 147.0528 kg 15,042.00 2,211,968.22
Bekisting 4.0000 m2 270,715.00 1,082,860.00
Cor Beton K-225 1.0000 m3 628,050.00 628,050.00
Jumlah 3,922,878.22
Jumlah Total 3,922,878.22 3,922,878.22
Dibulatkan 3,922,878.00

G-16 1 m3 MEMBUAT SLOOF 30/40 BETON BERTULANG + Bekisting


Besi Beton + Kawat Pengikat 75.5946 kg 15,042.00 1,137,094.71
Bekisting 3.3333 m2 137,626.00 458,753.33
Cor Beton K-175 1.0000 m3 628,050.00 628,050.00
Jumlah 2,223,898.04
Jumlah Total 2,223,898.04 2,223,898.04
Dibulatkan 2,223,898.00

G-17 1 m3 MEMBUAT SLOOF 15/20 BETON BERTULANG + Bekisting


Besi Beton + Kawat Pengikat 179.9399 kg 15,042.00 2,706,655.84
Bekisting 16.6667 m2 137,626.00 2,293,766.67
Cor Beton K-175 1.0000 m3 628,050.00 628,050.00
Jumlah 5,628,472.51
Jumlah Total 5,628,472.51 5,628,472.51
Dibulatkan 5,628,472.00

G-20 1 m3 MEMBUAT KOLOM STRUKTUR BETON BERTULANG 30/30 (+ Bekisting) (K1)


Besi Beton + Pengikat 114.4064 Kg 15,042.00 1,720,901.31
Begisting 11.1111 m2 228,365.00 2,537,388.89
Beton 1 PC : 2 Psr : 3 Kr 1.0000 m3 628,050.00 628,050.00
Jumlah 4,886,340.20
Jumlah Total 4,886,340.20 4,886,340.20
Dibulatkan 4,886,340.00

G-21 1 m3 MEMBUAT KOLOM STRUKTUR BETON BERTULANG 20/20 (+ Bekisting) (K2)


Besi Beton + Pengikat 186.0046 Kg 15,042.00 2,797,881.80
Begisting 20.0000 m2 228,365.00 4,567,300.00
Beton 1 PC : 2 Psr : 3 Kr 1.0000 m3 628,050.00 628,050.00
Jumlah 7,993,231.80
Jumlah Total 7,993,231.80 7,993,231.80
Dibulatkan 7,993,231.00

G-22 1 m3 MEMBUAT KOLOM BETON PRAKTIS 15/15 BERTULANG + Bekisting (K3)


a b c d e f=(cxe) g=(cxe) h
Besi Beton + Pengikat 228.1029 Kg 15,042.00 3,431,124.45
Begisting 20.0000 m2 228,365.00 4,567,300.00
Beton 1 PC : 2 Psr : 3 Kr 1.0000 M3 628,050.00 628,050.00
Jumlah 8,626,474.45
Jumlah Total 8,626,474.45 8,626,474.45
Dibulatkan 8,626,474.00

G-23 1 m3 MEMBUAT BALOK 20/40 BETON BERTULANG (+ Bekisting) (B1)


Besi Beton + Pengikat 117.5560 Kg 15,042.00 1,768,277.51
Begisting 6.2500 m2 235,562.00 1,472,262.50
Beton 1 PC : 2 Psr : 3 Kr 1.0000 m3 628,050.00 628,050.00
Jumlah 3,868,590.01
Jumlah Total 3,868,590.01 3,868,590.01
Dibulatkan 3,868,590.00

G-24 1 m3 MEMBUAT BALOK 15/30 BETON BERTULANG (+ Bekisting) (B2)


Besi Beton + Pengikat 151.5355 Kg 15,042.00 2,279,396.67
Begisting 11.1111 m2 235,562.00 2,617,355.56
Beton 1 PC : 2 Psr : 3 Kr 1.0000 m3 628,050.00 628,050.00
Jumlah 5,524,802.23
Jumlah Total 5,524,802.23 5,524,802.23
Dibulatkan 5,524,802.00

G-26 1 m3 MEMBUAT BALOK 15/20 BETON BERTULANG (+ Bekisting) (B4)


Besi Beton + Pengikat 209.5187 Kg 15,042.00 3,151,580.15
Begisting 13.3333 m2 235,562.00 3,140,826.67
Beton 1 PC : 2 Psr : 3 Kr 1.0000 m3 628,050.00 628,050.00
Jumlah 6,920,456.82
Jumlah Total 6,920,456.82 6,920,456.82
Dibulatkan 6,920,456.00

G-29 1 m3 MEMBUAT PLAT BETON T = 10 CM Bekisting


Besi Beton + Pengikat 93.3296 kg 15,042.00 1,403,863.84
Begisting 4.1667 m2 270,715.00 1,127,979.17
Beton 1 PC : 2 Psr : 3 Kr 1.0000 m3 628,050.00 628,050.00
Jumlah 3,159,893.01
Jumlah Total 3,159,893.01 3,159,893.01
Dibulatkan 3,159,893.00

G-30 1 m3 MEMBUAT PLAT BETON T = 12 CM Bekisting


Besi Beton + Pengikat 73.0400 kg 15,042.00 1,098,667.68
Begisting 8.3333 m2 246,105.00 2,050,875.00
Beton 1 PC : 2 Psr : 3 Kr 1.0000 m3 628,050.00 628,050.00
Jumlah 3,777,592.68
Jumlah Total 3,777,592.68 3,777,592.68
Dibulatkan 3,777,592.00

H PEKERJAAN PENUTUP ATAP

H-02 1 m2 PASANG ATAP GENTENG MORANDO NATURAL 18 BH/M2


Genteng Morando Glatsur 18.0000 Bh 2,200.00 39,600.00
Pekerja 0.1500 HOK 45,000.00 6,750.00
Tukang kayu 0.0750 HOK 60,000.00 4,500.00
Kepala tukang 0.0080 HOK 70,000.00 560.00
Mandor 0.0080 HOK 70,000.00 560.00
Jumlah 12,370.00 39,600.00
Keuntungan 1,237.00 3,960.00
Jumlah Total 13,607.00 43,560.00 57,167.00
Dibulatkan 57,167.00

H-03 1 m2 PASANG ATAP GENTENG MORANDO LAMA


Pekerja 0.1500 HOK 45,000.00 6,750.00
Tukang kayu 0.0750 HOK 60,000.00 4,500.00
Kepala tukang 0.0080 HOK 70,000.00 560.00
Mandor 0.0080 HOK 70,000.00 560.00
Jumlah 12,370.00 0.00
a b c d e f=(cxe) g=(cxe) h
Keuntungan 1,237.00 0.00
Jumlah Total 13,607.00 0.00 13,607.00
Dibulatkan 13,607.00

H-03 1 m' PASANG BUBUNG GENTENG MORANDO


Genteng bubung Morando 5.0000 Bh 3,500.00 17,500.00
Semen PC (50 kg) 0.1600 Zak 68,000.00 10,880.00
Pasir pasang 0.0320 m3 95,000.00 3,040.00
Pekerja 0.4000 HOK 45,000.00 18,000.00
Tukang kayu 0.2000 HOK 60,000.00 12,000.00
Kepala tukang 0.0200 HOK 70,000.00 1,400.00
Mandor 0.0020 HOK 70,000.00 140.00
Jumlah 31,540.00 31,420.00
Keuntungan 3,154.00 3,142.00
Jumlah Total 34,694.00 34,562.00 69,256.00
Dibulatkan 69,256.00

I PEKERJAAN LANGIT-LANGIT

I-04 1 m2 LANGIT-LANGIT GRC (1.20X2.40 ) Cm, RANGKA KAYU GUNUNG KELAS II


Kayu Gunung Kls II, balok 0.0120 m3 2,499,000.00 29,988.00
Paku biasa 0.0600 Kg 18,800.00 1,128.00
GRC 0.3820 Lbr 52,200.00 19,940.40
Pekerja 0.1800 HOK 45,000.00 8,100.00
Tukang kayu 0.3200 HOK 60,000.00 19,200.00
Kepala tukang 0.0320 HOK 70,000.00 2,240.00
Mandor 0.0090 HOK 70,000.00 630.00
Jumlah 30,170.00 51,056.40
Keuntungan 3,017.00 5,105.64
Jumlah Total 33,187.00 56,162.04 89,349.04
Dibulatkan 89,349.00

I-04a 1 m2 LANGIT-LANGIT GRC (1.20X2.40 ) Cm, RANGKA KAYU GUNUNG KELAS III
Kayu Gunung Kls II, balok 0.0120 m3 1,881,000.00 22,572.00
Paku biasa 0.0600 Kg 18,800.00 1,128.00
GRC 0.3820 Lbr 52,200.00 19,940.40
Pekerja 0.1800 HOK 45,000.00 8,100.00
Tukang kayu 0.3200 HOK 60,000.00 19,200.00
Kepala tukang 0.0320 HOK 70,000.00 2,240.00
Mandor 0.0090 HOK 70,000.00 630.00
Jumlah 30,170.00 43,640.40
Keuntungan 3,017.00 4,364.04
Jumlah Total 33,187.00 48,004.44 81,191.44
Dibulatkan 81,191.00

I-06 1 m2 LANGIT-LANGIT GRC (1.20X2.40 ) Cm, RANGKA BESI HOLLO 20.40 dan 40.40
Besi Hollo 20.40 0.4167 btg 43,000.00 17,918.10
Besi Hollo 40.40 0.4167 btg 57,000.00 23,751.90
Skrup 24.0000 bh 100.00 2,400.00
Gantungan Dari Kawat 1 mm 1.8000 m1 1,500.00 2,700.00
GRC 0.3819 Lbr 52,200.00 19,937.50
Pekerja 0.1800 HOK 45,000.00 8,100.00
Tukang besi 0.3200 HOK 60,000.00 19,200.00
Kepala tukang 0.0320 HOK 70,000.00 2,240.00
Mandor 0.0090 HOK 70,000.00 630.00
Jumlah 30,170.00 66,707.50
Keuntungan 3,017.00 6,670.75
Jumlah Total 33,187.00 73,378.25 106,565.25
Dibulatkan 106,565.00

I-05 1 m2 LANGIT-LANGIT ETERNITE (100 X 100 ) Cm, RANGKA KAYU GUNUNG KLAS III
Kayu Gunung Klas II 5/7 0.0120 m3 1,881,000.00 22,572.00
Paku biasa 0.0600 Kg 18,800.00 1,128.00
Eternit 1.1000 Lbr 8,500.00 9,350.00
Pekerja 0.1800 HOK 45,000.00 8,100.00
Tukang kayu 0.3200 HOK 60,000.00 19,200.00
a b c d e f=(cxe) g=(cxe) h
Kepala tukang 0.0320 HOK 70,000.00 2,240.00
Mandor 0.0090 HOK 70,000.00 630.00
Jumlah 30,170.00 33,050.00
Keuntungan 3,017.00 3,305.00
Jumlah Total 33,187.00 36,355.00 69,542.00
Dibulatkan 69,542.00

J PEKERJAAN SANITASI

J-01 MEMASANG 1 BUAH KLOSET JONGKOK PORSELIN


Kloset jongkok porselin 1.0000 Bh 156,600.00 156,600.00
Semen PC (50 kg) 0.1200 Zak 68,000.00 8,160.00
Pasir pasang 0.0100 m3 95,000.00 950.00
Pekerja 1.0000 HOK 45,000.00 45,000.00
Tukang batu 1.5000 HOK 47,500.00 71,250.00
Kepala tukang 1.5000 HOK 70,000.00 105,000.00
Mandor 0.1600 HOK 70,000.00 11,200.00
Jumlah 232,450.00 165,710.00
Keuntungan 23,245.00 16,571.00
Jumlah Total 255,695.00 182,281.00 437,976.00
Dibulatkan 437,976.00

J-01a MEMASANG 1 BUAH KLOSET DUDUK PORSELIN


Kloset Duduk porselin 1.0000 Bh 1,488,200.00 1,488,200.00
Semen PC (50 kg) 0.1200 Zak 68,000.00 8,160.00
Pasir pasang 0.0100 m3 95,000.00 950.00
Pekerja 1.0000 HOK 45,000.00 45,000.00
Tukang batu 1.5000 HOK 47,500.00 71,250.00
Kepala tukang 1.5000 HOK 70,000.00 105,000.00
Mandor 0.1600 HOK 70,000.00 11,200.00
Jumlah 232,450.00 1,497,310.00
Keuntungan 23,245.00 149,731.00
Jumlah Total 255,695.00 1,647,041.00 1,902,736.00
Dibulatkan 1,902,736.00

J-02 MEMASANG 1 BUAH WASTAFEL


Wastafel 1.0000 Bh 350,100.00 350,100.00
Semen PC (50 kg) 0.1200 zak 68,000.00 8,160.00
Pasir pasang 0.0100 m3 95,000.00 950.00
Perlengkapan 12.0% wastafel 350,100.00 42,012.00
Pekerja 1.2000 HOK 45,000.00 54,000.00
Tukang batu 1.4500 HOK 47,500.00 68,875.00
Kepala tukang 0.1500 HOK 70,000.00 10,500.00
Mandor 0.1000 HOK 70,000.00 7,000.00
Jumlah 140,375.00 401,222.00
Keuntungan 14,037.50 40,122.20
Jumlah Total 154,412.50 441,344.20 595,756.70
Dibulatkan 595,756.00

J-03 MEMASANG 1 BUAH BAK MANDI FIBREGLASS 0,30M3


Bak fibreglass 1.0000 Bh 284,000.00 284,000.00
Perlengkapan 18.0% Hrg Bak 284,000.00 51,120.00
Pekerja 1.8000 HOK 45,000.00 81,000.00
Tukang batu 2.7000 HOK 47,500.00 128,250.00
Kepala tukang 0.5400 HOK 70,000.00 37,800.00
Mandor 0.1100 HOK 70,000.00 7,700.00
Jumlah 254,750.00 335,120.00
Keuntungan 25,475.00 33,512.00
Jumlah Total 280,225.00 368,632.00 648,857.00
Dibulatkan 648,857.00

J-04 MEMASANG 1 METER PIPA BETON, Ø 15-20 CM


Pipa beton 1.1000 bh 81,500.00 89,650.00
Batu bata 5x11x22 0.0270 m3 700.00 18.90
Semen PC (50 kg) 0.0784 Zak 68,000.00 5,331.20
Pasir Pasang 0.0560 m3 95,000.00 5,320.00
a b c d e f=(cxe) g=(cxe) h
Pasir Urug 0.2400 m3 78,000.00 18,720.00
Pekerja 0.1400 HOK 45,000.00 6,300.00
Tukang batu 0.0700 HOK 47,500.00 3,325.00
Kepala tukang 0.0070 HOK 70,000.00 490.00
Mandor 0.0070 HOK 70,000.00 490.00
Jumlah 10,605.00 29,371.20
Keuntungan 1,060.50 2,937.12
Jumlah Total 11,665.50 32,308.32
Dibulatkan

J-05 MEMASANG 1 METER PIPA BETON, Ø 30 CM


Pipa beton 1.1000 bh 116,000.00 127,600.00
Batu bata ( 5x11x22 ) 0.0550 m3 700.00 38.50
Semen PC (50 kg) 0.2060 Zak 68,000.00 14,008.00
Pasir Pasang 0.0610 m3 95,000.00 5,795.00
Pasir Urug 0.0690 m3 78,000.00 5,382.00
Pekerja 0.3800 HOK 45,000.00 17,100.00
Tukang batu 0.1900 HOK 47,500.00 9,025.00
Kepala tukang 0.0190 HOK 70,000.00 1,330.00
Mandor 0.0190 HOK 70,000.00 1,330.00
Jumlah 28,785.00 25,185.00
Keuntungan 2,878.50 2,518.50
Jumlah Total 31,663.50 27,703.50
Dibulatkan

J-06 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA (45X45) CM


Batu bata ( 5x11x22 ) 0.2500 m3 700.00 175.00
Semen PC (50 kg) 1.5400 Zak 68,000.00 104,720.00
Pasir Pasang 0.1300 m3 95,000.00 12,350.00
Batu kerikil 0.0200 m3 175,500.00 3,510.00
Besi beton 2.6000 Kg 12,000.00 31,200.00
Pasir beton 0.0900 m3 123,500.00 11,115.00
Pekerja 1.4200 HOK 45,000.00 63,900.00
Tukang batu 0.4730 HOK 47,500.00 22,467.50
Kepala tukang 0.0470 HOK 70,000.00 3,290.00
Mandor 0.0710 HOK 70,000.00 4,970.00
Jumlah 94,627.50 45,825.00
Keuntungan 9,462.75 4,582.50
Jumlah Total 104,090.25 50,407.50
Dibulatkan

J-07 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA (45X45) CM TANPA TUTUP
Batu bata 0.9600 m2 97,448.00 93,550.08
Plesteran 1 : 5 1.1200 m2 30,486.00 34,144.32
Acian 1 : 5 1.1200 m2 21,703.00 24,307.36
Galian Tanah 0.1500 m3 22,880.00 3,432.00
Jumlah 3,432.00 152,001.76
Keuntungan 343.20 15,200.18
Jumlah Total 3,775.20 167,201.94 170,977.14
Dibulatkan 170,977.00

J-08 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA (60x60) CM


Batu bata ( 5x11x22 ) 0.3710 m3 700.00 259.70
Semen PC (50 kg) 2.2800 Zak 68,000.00 155,040.00
Pasir Pasang 0.1840 m3 95,000.00 17,480.00
Batu kerikil 0.0330 m3 142,500.00 4,702.50
Besi beton 4.8500 Kg 12,000.00 58,200.00
Pasir beton 0.1200 m3 123,500.00 14,820.00
Pekerja 2.1600 HOK 45,000.00 97,200.00
Tukang batu 0.7200 HOK 47,500.00 34,200.00
Tukang gali 0.1000 HOK 45,000.00 4,500.00
Kepala tukang 0.0720 HOK 70,000.00 5,040.00
Mandor 0.1080 HOK 70,000.00 7,560.00
Jumlah 148,500.00 250,502.20
Keuntungan 14,850.00 25,050.22
Jumlah Total 163,350.00 275,552.42 438,902.42
a b c d e f=(cxe) g=(cxe) h
Dibulatkan 438,902.00

J-09 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA (60X60) CM TANPA TUTUP
Batu bata 1.4400 m2 97,448.00 140,325.12
Plesteran 1 : 5 1.3200 m2 30,486.00 40,241.52
Acian 1 : 5 1.3200 m2 21,703.00 28,647.96
Galian Tanah 0.2940 m3 22,880.00 6,726.72
Jumlah 6,726.72 209,214.60
Keuntungan 672.67 20,921.46
Jumlah Total 7,399.39 230,136.06 237,535.45
Dibulatkan 237,535.00

J-10 MEMASANG 1 METER PIPA PVC TIPE AW Ø 1/2"


Pipa PVC 1.2000 m' 687.50 825.00
Perlengkapan 35.0% Hrg-pipa 687.50 240.63
Pekerja 0.0360 HOK 45,000.00 1,620.00
Tukang batu 0.0600 HOK 47,500.00 2,850.00
Kepala tukang 0.0060 HOK 70,000.00 420.00
Mandor 0.0018 HOK 70,000.00 126.00
Jumlah 5,016.00 1,065.63
Keuntungan 501.60 106.56
Jumlah Total 5,517.60 1,172.19 6,689.79
Dibulatkan 6,689.00

J-11 MEMASANG 1 METER PIPA PVC TIPE AW Ø 3/4"


Pipa PVC 1.2000 m' 937.50 1,125.00
Perlengkapan 35.0% Hrg-pipa 937.50 328.13
Pekerja 0.0360 HOK 45,000.00 1,620.00
Tukang batu 0.0600 HOK 47,500.00 2,850.00
Kepala tukang 0.0060 HOK 70,000.00 420.00
Mandor 0.0018 HOK 70,000.00 126.00
Jumlah 5,016.00 1,453.13
Keuntungan 501.60 145.31
Jumlah Total 5,517.60 1,598.44 7,116.04
Dibulatkan 7,116.00

J-12 MEMASANG 1 METER PIPA PVC TIPE AW Ø 1"


Pipa PVC 1.2000 m' 4,937.50 5,925.00
Perlengkapan 35.0% Hrg-pipa 4,937.50 1,728.13
Pekerja 0.0360 HOK 45,000.00 1,620.00
Tukang batu 0.0600 HOK 47,500.00 2,850.00
Kepala tukang 0.0060 HOK 70,000.00 420.00
Mandor 0.0018 HOK 70,000.00 126.00
Jumlah 5,016.00 7,653.13
Keuntungan 501.60 765.31
Jumlah Total 5,517.60 8,418.44 13,936.04
Dibulatkan 13,936.00

J-13 MEMASANG 1 METER PIPA PVC TIPE AW Ø 1 1/2"


Pipa PVC 1.2000 m' 6,437.50 7,725.00
Perlengkapan 35.0% Hrg-pipa 6,437.50 2,253.13
Pekerja 0.0360 HOK 45,000.00 1,620.00
Tukang batu 0.0600 HOK 47,500.00 2,850.00
Kepala tukang 0.0060 HOK 70,000.00 420.00
Mandor 0.0018 HOK 70,000.00 126.00
Jumlah 5,016.00 9,978.13
Keuntungan 501.60 997.81
Jumlah Total 5,517.60 10,975.94 16,493.54
Dibulatkan 16,493.00

J-14 MEMASANG 1 METER PIPA PVC TIPE AW Ø 2"


Pipa PVC 1.2000 m' 8,125.00 9,750.00
Perlengkapan 35.0% Hrg-pipa 8,125.00 2,843.75
Pekerja 0.0540 HOK 45,000.00 2,430.00
Tukang batu 0.0900 HOK 47,500.00 4,275.00
Kepala tukang 0.0090 HOK 70,000.00 630.00
a b c d e f=(cxe) g=(cxe) h
Mandor 0.0027 HOK 70,000.00 189.00
Jumlah 7,524.00 12,593.75
Keuntungan 752.40 1,259.38
Jumlah Total 8,276.40 13,853.13 22,129.53
Dibulatkan 22,129.00

J-15 MEMASANG 1 METER PIPA PVC TIPE AW Ø 2 1/2"


Pipa PVC 1.2000 m' 9,125.00 10,950.00
Perlengkapan 35.0% Hrg-pipa 9,125.00 3,193.75
Pekerja 0.0360 HOK 45,000.00 1,620.00
Tukang batu 0.0600 HOK 47,500.00 2,850.00
Kepala tukang 0.0060 HOK 70,000.00 420.00
Mandor 0.0018 HOK 70,000.00 126.00
Jumlah 5,016.00 14,143.75
Keuntungan 501.60 1,414.38
Jumlah Total 5,517.60 15,558.13 21,075.73
Dibulatkan 21,075.00

J-16 MEMASANG 1 METER PIPA PVC TIPE AW Ø 3"


Pipa PVC 1.2000 m' 16,062.50 19,275.00
Perlengkapan 35.0% Hrg-pipa 16,062.50 5,621.88
Pekerja 0.0810 HOK 45,000.00 3,645.00
Tukang batu 0.1350 HOK 47,500.00 6,412.50
Kepala tukang 0.0135 HOK 70,000.00 945.00
Mandor 0.0041 HOK 70,000.00 287.00
Jumlah 11,289.50 24,896.88
Keuntungan 1,128.95 2,489.69
Jumlah Total 12,418.45 27,386.56 39,805.01
Dibulatkan 39,805.00

J-17 MEMASANG 1 METER PIPA PVC TIPE AW Ø 4"


Pipa PVC 1.2000 m' 23,625.00 28,350.00
Perlengkapan 35.0% Hrg-pipa 23,625.00 8,268.75
Pekerja 0.0810 HOK 45,000.00 3,645.00
Tukang batu 0.1350 HOK 47,500.00 6,412.50
Kepala tukang 0.0135 HOK 70,000.00 945.00
Mandor 0.0041 HOK 70,000.00 287.00
Jumlah 11,289.50 36,618.75
Keuntungan 1,128.95 3,661.88
Jumlah Total 12,418.45 40,280.63 52,699.08
Dibulatkan 52,699.00

J-18 MEMASANG 1 BUAH BAK CUCI PIRING STAINLESS-STEEL


Bak cuci stainles steel 1.0000 Bh 192,500.00 192,500.00
Water drain + asesories 1.0000 Set 89,700.00 89,700.00
Pekerja 0.0300 HOK 45,000.00 1,350.00
Tukang batu 0.3000 HOK 47,500.00 14,250.00
Kepala tukang 0.0300 HOK 70,000.00 2,100.00
Mandor 0.0015 HOK 70,000.00 105.00
Jumlah 17,805.00 282,200.00
Keuntungan 1,780.50 28,220.00
Jumlah Total 19,585.50 310,420.00 330,005.50
Dibulatkan 330,005.00

J-19 MEMASANG 1 BUAH KRAN Ø 1/2" ATAU Ø 3/4"


Kran air 1.0000 Bh 15,000.00 15,000.00
Seal tape 0.0250 Set 1,700.00 42.50
Pekerja 0.0100 HOK 45,000.00 450.00
Tukang batu 0.1000 HOK 47,500.00 4,750.00
Kepala tukang 0.0100 HOK 70,000.00 700.00
Mandor 0.0050 HOK 70,000.00 350.00
Jumlah 6,250.00 15,042.50
Keuntungan 625.00 1,504.25
Jumlah Total 6,875.00 16,546.75 23,421.75
Dibulatkan 23,421.00
a b c d e f=(cxe) g=(cxe) h
J-20 MEMASANG 1 BUAH FLOOR DRAIN
Floor drain 1.0000 Bh 89,700.00 89,700.00
Pekerja 0.0100 HOK 45,000.00 450.00
Tukang batu 0.1000 HOK 47,500.00 4,750.00
Kepala tukang 0.0100 HOK 70,000.00 700.00
Mandor 0.0050 HOK 70,000.00 350.00
Jumlah 6,250.00 89,700.00
Keuntungan 625.00 8,970.00
Jumlah Total 6,875.00 98,670.00 105,545.00
Dibulatkan 105,545.00

J-21 1 M' SALURAN GRAFEL BETON 1/2 Ø 20 cm + PASANGAN (A137)


Galian Tanah 0.1500 m3 22,880.00 3,432.00
Grafel beton Ø 20 cm 1.0000 Bh 19,000.00 19,000.00
Pasangan bata + Plesteran 1 : 3 1.0000 m2 27,469.20 27,469.20
Upah kerja 0.3500 Ls 46,469.20 16,264.22
Jumlah 16,264.22 49,901.20
Keuntungan 1,626.42 4,990.12
Jumlah Total 17,890.64 54,891.32 72,781.96
Dibulatkan 72,781.00

J-21A 1 M' GORONG-GORONG BUIS BETON Ø 20 cm + PASANGAN (A137)


Galian Tanah 0.2500 m3 22,880.00 5,720.00
Buis beton Ø 20 cm 1.0000 Bh 81,500.00 81,500.00
Pasangan bata 1 : 3 1.0000 m2 20,861.64 20,861.64
Upah kerja 0.3500 Ls 102,361.64 35,826.57
Jumlah 35,826.57 108,081.64
Keuntungan 3,582.66 10,808.16
Jumlah Total 39,409.23 118,889.80 158,299.04
Dibulatkan 158,299.00

J-22 1 M' SALURAN GRAFEL BETON 1/2 Ø 30 cm + PASANGAN (A138)


Galian Tanah 0.2000 m3 22,880.00 4,576.00
Grafel beton Ø 30 cm 1.0000 Bh 22,500.00 22,500.00
Pasangan bata + Plesteran 1 : 3 1.0000 m 27,469.20 27,469.20
Upah kerja 0.3500 Ls 46,469.20 16,264.22
Jumlah 130,909.26 400,406.45
Keuntungan
Jumlah Total
Dibulatkan

J-22 1 UNIT SEPTICTANK 2.5 x 1.5 X 2 m (TYPE BESAR) + REMBESAN (A080)


Galian Tanah 7.5000 m3 22,880.00 171,600.00
Pasir urug 0.3570 m3 118,580.00 42,333.06
Lantai kerja 1 : 3 : 5 3.7500 m3 687,285.00 2,577,318.75
Pasangan bata + Plesteran 1 : 3 25.0000 m2 103,942.00 2,598,550.00
Plat beton penutup + balok 0.5000 m3 3,170,650.00 1,585,325.00
Pipa PVC 4" AW + sambungan 9.0000 m' 23,625.00 212,625.00
Pipa GIF 2" 2.0000 m' 205,250.00 410,500.00
Galian tanah untuk rembesan 5.6250 m3 22,880.00 128,700.00
Pasangan ijuk 9.0000 kg 7,500.00 67,500.00
Urugan kerikil 3.5 cm 1.7500 m3 85,500.00 149,625.00
Pipa PVC 4" AW berlobang 5.0000 m' 23,625.00 118,125.00
Urugan kembali perataan tanah 1.8750 m3 10,967.00 20,563.13
Tambahan upah kerja 0.0850 Ls 36,000.00 3,060.00
Jumlah 3,060.00 8,082,764.94
Keuntungan 306.00 808,276.49
Jumlah Total 3,366.00 8,891,041.43 8,894,407.43
Dibulatkan 8,894,407.00

J-23 1 UNIT SEPTICTANK 1.5 x 1.0 X 1.5 m (TYPE KECIL) + REMBESAN (A082)
Galian Tanah 2.2500 m3 22,880.00 51,480.00
Pasir urug 0.1071 m3 118,580.00 12,699.92
Lantai kerja 1 : 3 : 5 0.7750 m3 687,285.00 532,645.88
Pasangan bata + Plesteran 1 : 3 5.2500 m2 103,942.00 545,695.50
Plat beton penutup + balok 0.1500 m3 3,170,650.00 475,597.50
a b c d e f=(cxe) g=(cxe) h
Pipa PVC 4" AW + sambungan 5.0000 m' 23,625.00 118,125.00
Pipa GIF 2" 0.6000 m' 205,250.00 123,150.00
Galian tanah untuk rembesan 1.3750 m3 22,880.00 31,460.00
Pasangan ijuk 2.7000 kg 7,500.00 20,250.00
Urugan kerikil 3.5 cm 0.5250 m3 85,500.00 44,887.50
Pipa PVC 4" AW berlobang 5.0000 m' 23,625.00 118,125.00
Urugan kembali perataan tanah 0.5625 m3 10,967.00 6,168.94
Tambahan upah kerja 0.0850 Ls 36,000.00 3,060.00
Jumlah 3,060.00 2,080,285.23
Keuntungan 306.00 208,028.52
Jumlah Total 3,366.00 2,288,313.75 2,291,679.75
Dibulatkan 2,291,679.00

J-24 1 UNIT PEK. SEPTICKTANK BUIS BETON Ø 80 CM + RESAPAN


- Galian m3 2.4120 22,880.00 55,186.56
- Buis Beton Ø 80 cm m1 4.0000 208,000.00 832,000.00
- Plat Penutup T = 8 cm m3 0.1700 3,159,893.01 537,181.81
- Beton Tumbuk 1 : 3 : 5 m3 0.1240 687,285.00 85,223.34
- Pipa GIV Ø 1/2" m1 1.5000 205,250.00 307,875.00
- Pas, Bata 1 : 3 m2 2.3450 103,942.52 243,745.21
- Plesteran 1 : 3 m2 4.6900 33,404.58 156,667.48
- Split pecah mesin 2/3 m3 0.3560 175,500.00 62,478.00
- Injuk kg 8.0000 7,500.00 60,000.00
- Upah Kerja lot 0.0500 1,078,004.40 53,900.22
Jumlah 1,078,004.40 1,316,253.22
Keuntungan 107,800.44 131,625.32
Jumlah Total 1,185,804.84 1,447,878.54 2,633,683.38
Dibulatkan 2,633,683.00

K PEKERJAAN BESI DAN ALUMINIUM

K-01 1 m' PASANG TALANG DATAR, SENG BJLS 28


Seng plat 3' x 6' BJLS 28 0.5000 Lbr 70,500.00 35,250.00
Paku biasa 1/2" - 1" 0.0150 Kg 18,800.00 282.00
Kayu papan Kls II (Kayu gunung) 0.0096 m3 1,881,000.00 18,057.60
Flincote /meni besi 0.2500 Kg 16,700.00
Pekerja 0.1500 HOK 45,000.00 6,750.00
Tukang kayu 0.4000 HOK 60,000.00 24,000.00
Kepala tukang 0.0250 HOK 70,000.00 1,750.00
Mandor 0.00125 HOK 70,000.00 87.50
Jumlah 32,587.50 53,589.60
Keuntungan 3,258.75 5,358.96
Jumlah Total 35,846.25 58,948.56 94,794.81
Dibulatkan 94,794.00

K-01a 1 m' PASANG TALANG MIRING, ZINK ALUM


Plat Aluunium 0.5000 m2 0.00 0.00
Paku biasa 1/2" - 1" 0.0150 Kg 18,800.00 282.00
Kayu papan Kls II (Kayu gunung) 0.0190 m3 1,881,000.00 35,739.00
Flincote /meni besi 0.3000 Kg 16,700.00
Pekerja 0.0400 HOK 45,000.00 1,800.00
Tukang kayu 0.4000 HOK 60,000.00 24,000.00
Kepala tukang 0.0250 HOK 70,000.00 1,750.00
Mandor 0.00125 HOK 70,000.00 87.50
Jumlah 27,637.50 36,021.00
Keuntungan 2,763.75 3,602.10
Jumlah Total 30,401.25 39,623.10 70,024.35
Dibulatkan 70,024.00

K-02 1 m' PASANG TALANG MIRING, SENG BJLS 28


Seng plat 3' x 6' BJLS 28 0.5000 Lbr 70,500.00 35,250.00
Paku biasa 1/2" - 1" 0.0150 Kg 18,800.00 282.00
Kayu papan Kls II (Kayu gunung) 0.0190 m3 1,881,000.00 35,739.00
Flincote /meni besi 0.3000 Kg 16,700.00
Pekerja 0.0400 HOK 45,000.00 1,800.00
Tukang kayu 0.4000 HOK 60,000.00 24,000.00
a b c d e f=(cxe) g=(cxe) h
Kepala tukang 0.0250 HOK 70,000.00 1,750.00
Mandor 0.00125 HOK 70,000.00 87.50
Jumlah 27,637.50 71,271.00
Keuntungan 2,763.75 7,127.10
Jumlah Total 30,401.25 78,398.10 108,799.35
Dibulatkan 108,799.00

K-03 1 m' PASANG TALANG 1/2 LINGKARAN Ø10 cm, SENG BJLS 28
Seng plat 3' x 6' BJLS 28 0.3000 Lbr 70,500.00 21,150.00
Paku biasa 1/2" - 1" 0.1000 Kg 18,800.00 1,880.00
Kayu papan Kls II (Kayu gunung) 0.0190 m3 1,881,000.00 35,739.00
Besi strip 0.5000 Kg 17,500.00
Pekerja 0.1500 HOK 45,000.00 6,750.00
Tukang kayu 0.2500 HOK 60,000.00 15,000.00
Kepala tukang 0.0250 HOK 70,000.00 1,750.00
Mandor 0.00125 HOK 70,000.00 87.50
Jumlah 23,587.50 37,619.00
Keuntungan
Jumlah Total
Dibulatkan

K-08 1 m2 PASANG PINTU GULUNG BESI


Pintu gulung besi 1.0000 m2 0.00
Pekerja 1.2000 HOK 0.00
Tukang besi konstruksi 1.2000 HOK 0.00
Kepala tukang 0.1200 HOK 0.00
Mandor 0.0060 HOK 0.00
Total 0.00 0.00
Total Harga -

K-09 1 m2 PASANG PINTU LIPAT


Pintu lipat 1.0000 m2 0.00
Pekerja 1.0500 HOK 0.00
Tukang besi konstruksi 1.0500 HOK 0.00
Kepala tukang 0.1050 HOK 0.00
Mandor 0.0052 HOK 0.00
Total 0.00 0.00
Total Harga -

K-10 1 m2 PASANG PINTU SUNSCREEN ALLUMINIUM


Sunscreen alluminium 1.0000 m2 0.00
Pekerja 0.0800 HOK 0.00
Tukang besi konstruksi 0.8000 HOK 0.00
Kepala tukang 0.0800 HOK 0.00
Mandor 0.0040 HOK 0.00
Total 0.00 0.00
Total Harga -

K-11 1 m2 PASANG ROLLING DOOR


Rolling door 1.0000 m2 0.00
Pekerja 1.5000 HOK 0.00
Tukang besi konstruksi 1.0500 HOK 0.00
Kepala tukang 0.1050 HOK 0.00
Mandor 0.0052 HOK 0.00
Total 0.00 0.00
Total Harga -

K-12 1 m2 PASANG PINTU ALLUMINIUM


Pintu alluminium 1.0000 m2 0.00
Pekerja 1.0500 HOK 0.00
Tukang besi konstruksi 1.0500 HOK 0.00
Kepala tukang 0.1050 HOK 0.00
Mandor 0.0052 HOK 0.00
Total 0.00 0.00
Total Harga -
a b c d e f=(cxe) g=(cxe) h
K-13 1 m2 PASANG VENETIONS BLINDS
Venetions blinds 1.0000 m2 0.00
Pekerja 0.3500 HOK 0.00
Tukang kayu 0.3500 HOK 0.00
Kepala tukang 0.0350 HOK 0.00
Mandor 0.00175 HOK 0.00
Total 0.00 0.00
Total Harga -

K-14 1 m2 PASANG VERTICAL BLINDS


Vertical blinds 1.0000 m2 0.00
Pekerja 0.3500 HOK 0.00
Tukang besi konstruksi 0.3500 HOK 0.00
Kepala tukang 0.0350 HOK 0.00
Mandor 0.00175 HOK 0.00
Total 0.00 0.00
Total Harga -

K-15 1 m2 PASANG KAWAT HARMONIKA


Kawat harmonika 1.1000 m2 0.00
Paku biasa 1/2" - 1" 0.0200 Kg 0.00
Kayu papan kamper 0.0018 m3 0.00
Pekerja 0.1000 HOK 0.00
Tukang kayu 0.1000 HOK 0.00
Kepala tukang 0.0100 HOK 0.00
Mandor 0.0005 HOK 0.00
Total 0.00 0.00
Total Harga -

K-16 1 m2 PASANG KAWAT KASSA


Kawat kassa 1.1000 m2 0.00
Paku biasa 1/2" - 1" 0.0200 Kg 0.00
Kayu papan kamper 0.0018 m3 0.00
Pekerja 0.1000 HOK 0.00
Tukang kayu 0.1000 HOK 0.00
Kepala tukang 0.0100 HOK 0.00
Mandor 0.0005 HOK 0.00
Total 0.00 0.00
Total Harga -

K-17 1 m2 PASANG KAWAT BURUNG


Kawat burung 1.1000 m2 0.00
Paku biasa 1/2" - 1" 0.0200 Kg 0.00
Kayu papan kamper 0.0018 m3 0.00
Pekerja 0.1000 HOK 0.00
Tukang kayu 0.1000 HOK 0.00
Kepala tukang 0.0100 HOK 0.00
Mandor 0.0005 HOK 0.00
Total 0.00 0.00
Total Harga -

L PEKERJAAN KUNCI DAN KACA

L-01 1 BUAH PASANG KUNCI TANAM BIASA


Kunci tanam 1.0000 bh 138,700.00 138,700.00
Pekerja 0.0600 HOK 45,000.00 2,700.00
Tukang kayu 0.6000 HOK 60,000.00 36,000.00
Kepala tukang 0.0060 HOK 70,000.00 420.00
Mandor 0.0030 HOK 70,000.00 210.00
Jumlah 39,330.00 138,700.00
Keuntungan 3,933.00 13,870.00
Jumlah Total 43,263.00 152,570.00 195,833.00
Dibulatkan 195,833.00

L-03 1 BUAH PASANG ENGSEL PINTU


Engsel pintu 1.0000 bh 9,500.00 9,500.00
a b c d e f=(cxe) g=(cxe) h
Pekerja 0.0150 HOK 45,000.00 675.00
Tukang kayu 0.1500 HOK 60,000.00 9,000.00
Kepala tukang 0.0150 HOK 70,000.00 1,050.00
Mandor 0.00075 HOK 70,000.00 52.50
Jumlah 10,777.50 9,500.00
Keuntungan 1,077.75 950.00
Jumlah Total 11,855.25 10,450.00 22,305.25
Dibulatkan 22,305.00

L-04 1 BUAH PASANG ENGSEL JENDELA KUPU-KUPU


Engsel jendela 1.0000 bh 3,900.00 3,900.00
Pekerja 0.0100 HOK 45,000.00 450.00
Tukang kayu 0.1000 HOK 60,000.00 6,000.00
Kepala tukang 0.0100 HOK 70,000.00 700.00
Mandor 0.0005 HOK 70,000.00 35.00
Jumlah 7,185.00 3,900.00
Keuntungan 718.50 390.00
Jumlah Total 7,903.50 4,290.00 12,193.50
Dibulatkan 12,193.00

L-05 1 BUAH PASANG KUNCI SELOT JENDELA


Selot jendela 1.0000 bh 4,800.00 4,800.00
Pekerja 0.0200 HOK 45,000.00 900.00
Tukang kayu 0.2000 HOK 60,000.00 12,000.00
Kepala tukang 0.0200 HOK 70,000.00 1,400.00
Mandor 0.0010 HOK 70,000.00 70.00
Jumlah 14,370.00 4,800.00
Keuntungan 1,437.00 480.00
Jumlah Total 15,807.00 5,280.00 21,087.00
Dibulatkan 21,087.00

L-06 1 BUAH PASANG KUNCI SELOT PINTU


Engsel jendela 1.0000 bh 7,100.00 7,100.00
Pekerja 0.0200 HOK 45,000.00 900.00
Tukang kayu 0.2000 HOK 60,000.00 12,000.00
Kepala tukang 0.0200 HOK 70,000.00 1,400.00
Mandor 0.0010 HOK 70,000.00 70.00
Jumlah 14,370.00 7,100.00
Keuntungan 1,437.00 710.00
Jumlah Total 15,807.00 7,810.00 23,617.00
Dibulatkan 23,617.00

L-07 1 BUAH PASANG KAIT ANGIN


Kait angin 1.0000 bh 3,300.00 3,300.00
Pekerja 0.0150 HOK 45,000.00 675.00
Tukang kayu 0.1500 HOK 60,000.00 9,000.00
Kepala tukang 0.0150 HOK 70,000.00 1,050.00
Mandor 0.00075 HOK 70,000.00 52.50
Jumlah 10,777.50 3,300.00
Keuntungan 1,077.75 330.00
Jumlah Total 11,855.25 3,630.00 15,485.25
Dibulatkan 15,485.00

L-08 1 m2 BUAH PASANG KACA TEBAL 3 mm


Kaca 1.1000 bh 50,100.00 55,110.00
Pekerja 0.0150 HOK 45,000.00 675.00
Tukang kayu 0.1500 HOK 60,000.00 9,000.00
Kepala tukang 0.0150 HOK 70,000.00 1,050.00
Mandor 0.00075 HOK 70,000.00 52.50
Jumlah 10,777.50 55,110.00
Keuntungan 1,077.75 5,511.00
Jumlah Total 11,855.25 60,621.00 72,476.25
Dibulatkan 72,476.00

L-09 1 m2 BUAH PASANG KACA TEBAL 5 mm


Kaca 1.1000 bh 61,700.00 67,870.00
a b c d e f=(cxe) g=(cxe) h
Pekerja 0.0150 HOK 45,000.00 675.00
Tukang kayu 0.1500 HOK 60,000.00 9,000.00
Kepala tukang 0.0150 HOK 70,000.00 1,050.00
Mandor 0.00075 HOK 70,000.00 52.50
Jumlah 10,777.50 67,870.00
Keuntungan 1,077.75 6,787.00
Jumlah Total 11,855.25 74,657.00 86,512.25
Dibulatkan 86,512.00

M PEKERJAAN PENUTUP LANTAI DAN DINDING

M-03 1 m2 PASANG LANTAI KERAMIK 30X30 cm PUTIH


Ubin keramik 30x30 cm 1.0100 m2 37,900.00 38,279.00
Semen PC (50 kg) 0.1600 Zak 68,000.00 10,880.00
Pasir pasang 0.0300 m3 95,000.00 2,850.00
Semen warna 0.0130 Kg 9,000.00 117.00
Pekerja terampil 0.1875 HOK 47,500.00 8,906.25
Tukang batu trampil 0.3750 HOK 60,000.00 22,500.00
Kepala tukang 0.0750 HOK 70,000.00 5,250.00
Mandor 0.0188 HOK 70,000.00 1,316.00
Jumlah 37,972.25 52,126.00
Keuntungan 3,797.23 5,212.60
Jumlah Total 41,769.48 57,338.60 99,108.08
Dibulatkan 99,108.00

M-04 1 m2 PASANG LANTAI KERAMIK 30X30 cm ANTI SELIP


Ubin keramik 30x30 cm anti selip 1.0100 m2 47,500.00 47,975.00
Semen PC (50 kg) 0.1860 Zak 68,000.00 12,648.00
Pasir pasang 0.0180 m3 95,000.00 1,710.00
Semen warna 1.5000 Kg 9,000.00 13,500.00
Pekerja trampil 0.6000 HOK 47,500.00 28,500.00
Tukang batu trampil 0.1000 HOK 60,000.00 6,000.00
Kepala tukang 0.0450 HOK 70,000.00 3,150.00
Mandor 0.0300 HOK 70,000.00 2,100.00
Jumlah 39,750.00 75,833.00
Keuntungan 3,975.00 7,583.30
Jumlah Total 43,725.00 83,416.30 127,141.30
Dibulatkan 127,141.00

N PEKERJAAN PENGECATAN

N-03 1 m2 PENGECATAN BIDANG KAYU BARU (1 Lapis Plamir; 1 Lapis Cat dasar; 3 Lapis Cat Penutup)
Cat meni 0.2000 Kg 16,700.00 3,340.00
Plamir 0.1500 Kg 14,600.00 2,190.00
Cat dasar 0.1700 Kg 47,000.00 7,990.00
Cat Penutup ( 3 kali ) 0.3500 Kg 42,700.00 14,945.00
Pekerja 0.0700 HOK 45,000.00 3,150.00
Tukang cat 0.1050 HOK 47,500.00 4,987.50
Kepala tukang 0.0040 HOK 70,000.00 280.00
Mandor 0.0025 HOK 70,000.00 175.00
Jumlah 8,592.50 28,465.00
Keuntungan 859.25 2,846.50
Jumlah Total 9,451.75 31,311.50 40,763.25
Dibulatkan 40,763.00

N-04 1 m2 PELABURAN BIDANG KAYU DENGAN CAT RESIDU DAN TER


Residu atau ter 0.3500 Ltr 3,760.00 1,316.00
Pekerja 0.1000 HOK 45,000.00 4,500.00
Mandor 0.0060 HOK 70,000.00 420.00
Jumlah 4,920.00 1,316.00
Keuntungan 492.00 131.60
Jumlah Total 5,412.00 1,447.60 6,859.60
Dibulatkan 6,859.00

N-05 1 m2 PENGECATAN BIDANG TEMBOK BARU (1 Lapis Plamir; 1 Lapis Cat dasar; 2 Lapis Cat Penutup)
Plamir 0.1000 Kg 25,000.00 2,500.00
a b c d e f=(cxe) g=(cxe) h
Cat dasar 0.1000 Kg 47,000.00 4,700.00
Cat Penutup ( 2 kali ) 0.2600 Kg 15,600.00 4,056.00
Pekerja 0.0200 HOK 45,000.00 900.00
Tukang cat 0.0630 HOK 47,500.00 2,992.50
Kepala tukang 0.0063 HOK 70,000.00 441.00
Mandor 0.0025 HOK 70,000.00 175.00
Jumlah 4,508.50 11,256.00
Keuntungan 450.85 1,125.60
Jumlah Total 4,959.35 12,381.60 17,340.95
Dibulatkan 17,340.00

N-07 1 m2 PENGECATAN PLAFOND


Plamir Tembok 0.1600 Kg 25,000.00 4,000.00
Cat Penutup ( 2 kali ) 0.2000 Kg 15,600.00 3,120.00
Roll Cat 0.0100 bh 12,500.00 125.00
Steager Werk 1.0000 lot 7,245.00 7,245.00
Ampelas 0.5000 lbr 1,800.00 900.00
Pekerja 1/2 Terampil 0.0280 HOK 45,000.00 1,260.00
Tukang cat 1/2 Terampil 0.0420 HOK 47,500.00 1,995.00
Kepala tukang 0.0042 HOK 70,000.00 294.00
Mandor 0.0025 HOK 70,000.00 175.00
Jumlah 3,724.00 15,390.00
Keuntungan 372.40 1,539.00
Jumlah Total 4,096.40 16,929.00 21,025.40
Dibulatkan 21,025.00

N-08 1 m2 PENGECATAN GENTENG BARU (1 Lapis Cat dasar; 2 Lapis Cat Penutup)
Cat dasar 0.1000 Kg 56,400.00 5,640.00
Cat Penutup ( 2 kali ) 0.2600 Kg 56,400.00 14,664.00
Pekerja 0.0200 HOK 45,000.00 900.00
Tukang cat 0.0630 HOK 47,500.00 2,992.50
Kepala tukang 0.0063 HOK 70,000.00 441.00
Mandor 0.0025 HOK 70,000.00 175.00
Jumlah 4,508.50 20,304.00
Keuntungan 450.85 2,030.40
Jumlah Total 4,959.35 22,334.40 27,293.75
Dibulatkan 27,293.00

N-09 1 m2 PENGECATAN BATU TEMPEL BARU (1 Lapis Cat dasar; 2 Lapis Cat Penutup)
Cat Penutup ( 2 kali ) 0.2600 Kg 77,400.00 20,124.00
Pekerja 0.0200 HOK 45,000.00 900.00
Tukang cat 0.0630 HOK 47,500.00 2,992.50
Kepala tukang 0.0063 HOK 70,000.00 441.00
Mandor 0.0025 HOK 70,000.00 175.00
Jumlah 4,508.50 20,124.00
Keuntungan 450.85 2,012.40
Jumlah Total 4,959.35 22,136.40 27,095.75
Dibulatkan 27,095.00

O PEKERJAAN KUSEN PINTU & JENDELA ALUMUNIUM

O-01 1 BH PEKERJAAN PINTU ALUMUNIUM TYPE P1


BAHAN + TENAGA
Kusen Alumunium 4" 3.5000 M¹ 76,000.00 266,000.00
Rangka Daun Pintu Almunium 10.2400 M¹ 64,000.00 655,360.00
List Almunium 5.4000 M¹ 10,000.00 54,000.00
Kaca Polos 5 mm 2.1810 M¹ 61,700.00 134,567.70
Karet 9.6800 m1 4,700.00 45,496.00
Engsel Pintu 9.0000 BH 26,400.00 237,600.00
Handle Pintu 4.0000 BH 66,000.00 264,000.00
Kunci 1.0000 BH 142,500.00 142,500.00
Slot Pintu 2.0000 BH 7,100.00 14,200.00
lem Silicon 0.7500 TB 36,800.00 27,600.00
Jumlah 1,841,323.70
Keuntungan 184,132.37
Jumlah Total 2,025,456.07 2,025,456.07
a b c d e f=(cxe) g=(cxe) h
Dibulatkan 2,025,456.00

O-02 1 BH PEKERJAAN PINTU ALUMUNIUM TYPE P4


BAHAN + TENAGA
Kusen Alumunium 4" 8.8500 M¹ 76,000.00 672,600.00
Rangka Daun Pintu Almunium 5.2200 M¹ 64,000.00 334,080.00
List Almunium 8.6900 M¹ 10,000.00 86,900.00
Kaca Polos 5 mm 2.1390 M¹ 61,700.00 131,976.30
Karet 8.8800 m1 4,700.00 41,736.00
Engsel Pintu 3.0000 BH 26,400.00 79,200.00
Handle Pintu 2.0000 BH 66,000.00 132,000.00
Kunci 1.0000 BH 142,500.00 142,500.00
Slot Pintu 1.0000 BH 7,100.00 7,100.00
lem Silicon 0.8000 TB 36,800.00 29,440.00
Jumlah 1,657,532.30
Keuntungan 165,753.23
Jumlah Total 1,823,285.53 1,823,285.53
Dibulatkan 1,823,285.00

O-03 1 BH PEKERJAAN PINTU ALUMUNIUM TYPE P5


BAHAN + TENAGA
Kusen Alumunium 4" 4.7000 M¹ 76,000.00 357,200.00
Rangka Daun Pintu Almunium 5.1200 M¹ 64,000.00 327,680.00
Panil Almunium 1.0900 M² 64,000.00 69,760.00
List Almunium 4.7000 M¹ 10,000.00 47,000.00
Kaca Polos 5 mm 0.0000 M¹ 61,700.00 0.00
Karet 0.0000 m1 4,700.00 0.00
Engsel Pintu 3.0000 BH 26,400.00 79,200.00
Handle Pintu 2.0000 BH 66,000.00 132,000.00
Kunci 1.0000 BH 142,500.00 142,500.00
Slot Pintu 1.0000 BH 7,100.00 7,100.00
lem Silicon 0.7500 TB 36,800.00 27,600.00
Jumlah 1,190,040.00
Keuntungan 119,004.00
Jumlah Total 1,309,044.00 1,309,044.00
Dibulatkan 1,309,044.00

O-04 1 BH PEKERJAAN PINTU ALUMUNIUM TYPE PJ


BAHAN + TENAGA
Kusen Alumunium 4" 15.9200 M¹ 76,000.00 1,209,920.00
Rangka Daun Pintu Almunium 5.3200 M¹ 64,000.00 340,480.00
Rangka Daun Jendela Almunium 6.6400 M¹ 64,000.00 424,960.00
List Almunium 21.0000 M¹ 10,000.00 210,000.00
Kaca Es 5 mm 4.0590 M² 245,800.00 997,702.20
Karet 17.7200 m1 4,700.00 83,284.00
Engsel Pintu 3.0000 BH 26,400.00 79,200.00
Engsel Jendela 4.0000 BH 3,900.00 15,600.00
Kunci 1.0000 PS 142,500.00 142,500.00
Slot Pintu 1.0000 BH 7,100.00 7,100.00
Rambuncis 2.0000 BH 12,200.00 24,400.00
lem Silicon 1.0000 TB 36,800.00 36,800.00
Jumlah 3,571,946.20
Keuntungan 357,194.62
Jumlah Total 3,929,140.82 3,929,140.82
Dibulatkan 3,929,140.00

O-05 1 BH PEKERJAAN KUSEN PARTISI TYPE I


BAHAN + TENAGA
Kusen Alumunium 4" 28.6600 M¹ 76,000.00 2,178,160.00
Kusen Alumunium 8/8 9.9000 M¹ 64,000.00 633,600.00
Rangka Daun Pintu Almunium 29.7600 M¹ 64,000.00 1,904,640.00
List Almunium 92.6400 M¹ 10,000.00 926,400.00
Kaca Polos 5 mm 14.5050 M² 61,700.00 894,958.50
Karet 64.0800 M¹ 4,700.00 301,176.00
Multiplex T = 10 mm 1.9180 M² 37,657.89 72,227.83
HPL Warna 3.8360 M² 56,805.97 217,907.69
a b c d e f=(cxe) g=(cxe) h
Engsel Pintu 18.0000 BH 26,400.00 475,200.00
Handle Pintu 12.0000 BH 66,000.00 792,000.00
Kunci 1.0000 PS 142,500.00 142,500.00
Slot Pintu 6.0000 BH 7,100.00 42,600.00
lem Silicon 1.5000 TB 36,800.00 55,200.00
Jumlah 8,636,570.01
Keuntungan 863,657.00
Jumlah Total 9,500,227.02 9,500,227.02
Dibulatkan 9,500,227.00

O-06 1 BH PEKERJAAN KUSEN PARTISI TYPE 2


BAHAN + TENAGA
Kusen Alumunium 4" 26.6880 M¹ 76,000.00 2,028,288.00
Kusen Alumunium 8/8 3.3000 M¹ 64,000.00 211,200.00
List Almunium 45.8320 M¹ 10,000.00 458,320.00
Kaca Polos 5 mm 7.6630 M² 61,700.00 472,807.10
Karet 31.5680 M¹ 4,700.00 148,369.60
Multiplex T = 10 mm 3.1760 M² 37,657.89 119,601.45
HPL Warna 6.3520 M² 56,805.97 360,831.50
lem Silicon 1.5000 TB 36,800.00 55,200.00
Jumlah 3,854,617.65
Keuntungan 385,461.76
Jumlah Total 4,240,079.41 4,240,079.41
Dibulatkan 4,240,079.00

O-07 1 BH PEKERJAAN KUSEN PARTISI TYPE 3


BAHAN + TENAGA
Kusen Alumunium 4" 22.8000 M¹ 76,000.00 1,732,800.00
Kusen Alumunium 8/8 6.6000 M¹ 64,000.00 422,400.00
List Almunium 45.0300 M¹ 10,000.00 450,300.00
Kaca Polos 5 mm 8.3880 M² 61,700.00 517,539.60
Karet 31.0600 M¹ 4,700.00 145,982.00
Multiplex T = 10 mm 3.0960 M² 37,657.89 116,588.82
HPL Warna 6.1920 M² 56,805.97 351,742.54
lem Silicon 1.4000 TB 36,800.00 51,520.00
Jumlah 3,788,872.96
Keuntungan 378,887.30
Jumlah Total 4,167,760.26 4,167,760.26
Dibulatkan 4,167,760.00

O-08 1 BH PEKERJAAN KUSEN PARTISI TYPE 4


BAHAN + TENAGA
Kusen Alumunium 4" 25.2480 M¹ 76,000.00 1,918,848.00
Kusen Alumunium 8/8 2.8000 M¹ 64,000.00 179,200.00
List Almunium 42.4720 M¹ 10,000.00 424,720.00
Kaca Polos 5 mm 6.2140 M² 61,700.00 383,403.80
Karet 28.2080 M¹ 4,700.00 132,577.60
Multiplex T = 10 mm 3.1760 M² 37,657.89 119,601.45
HPL Warna 6.3520 M² 56,805.97 360,831.50
lem Silicon 1.5000 TB 36,800.00 55,200.00
Jumlah 3,574,382.35
Keuntungan 357,438.23
Jumlah Total 3,931,820.58 3,931,820.58
Dibulatkan 3,931,820.00

O-09 1 BH PEKERJAAN KUSEN PARTISI TYPE 5a


BAHAN + TENAGA
Kusen Alumunium 4" 12.5500 M¹ 76,000.00 953,800.00
Kusen Alumunium 8/8 3.3000 M¹ 64,000.00 211,200.00
Rangka Daun Pintu Almunium 5.3200 M¹ 64,000.00 340,480.00
List Almunium 16.3500 M¹ 10,000.00 163,500.00
Kaca Polos 5 mm 4.5090 M² 61,700.00 278,205.30
Karet 17.5400 M¹ 4,700.00 82,438.00
Multiplex T = 10 mm 0.9250 M² 37,657.89 34,833.55
HPL Warna 1.8500 M² 56,805.97 105,091.04
Engsel Pintu 3.0000 BH 26,400.00 79,200.00
a b c d e f=(cxe) g=(cxe) h
Handle Pintu 2.0000 BH 66,000.00 132,000.00
Kunci 1.0000 PS 142,500.00 142,500.00
Slot Pintu 1.0000 BH 7,100.00 7,100.00
lem Silicon 1.0000 TB 36,800.00 36,800.00
Jumlah 2,567,147.88
Keuntungan 256,714.79
Jumlah Total 2,823,862.67 2,823,862.67
Dibulatkan 2,823,862.00

O-09 1 BH PEKERJAAN KUSEN PARTISI TYPE 5b


BAHAN + TENAGA
HARGA SATUAN PEKERJAAN
WILAYAH KOTA TASIKMALAYA
TAHUN ANGGARAN 2014

KODE HARGA SATUAN


KODE JENIS PEKERJAAN ANALISA PEKERJAAN
( Rp )
(a) (b) (c) (d)

A PEKERJAAN PERSIAPAN
1 1 m' PEKERJAAN PENGUKURAN DAN PEMASANGAN BOUWPLANK A-02 25,570.00
2 1 m2 PEKERJAAN MEMBERSIHKAN DAN PERATAAN LAPANGAN A-05 8,800.00

B PEKERJAAN TANAH
1 1 m3 GALIAN TANAH BIASA SEDALAM 1 METER B-01 22,880.00
2 1 m3 URUGAN KEMBALI B-06 10,967.00
3 1 m3 PEMADATAN TANAH B-07 28,600.00
4 1 m3 URUGAN TANAH DIPADATKAN B-08 35,970.00
5 1 m3 URUGAN PASIR B-09 118,580.00
6 1 m3 URUGAN TANAH BELI DARI LUAR B-10 75,680.00

C PEKERJAAN PONDASI
1 1 m3 PASANGAN PONDASI BATU KALI, 1 Pc : 4 Ps C-01 595,727.00
1 1 m3 PASANGAN PONDASI BATU KALI, 1 Pc : 5 Ps C-03 499,499.00
2 1 m3 PASANGAN PONDASI BATU KOSONG C-04 221,496.00

D PEKERJAAN DINDING
1 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 5 Ps D-02 97,448.00

E PEKERJAAN PLESTERAN
1 1 m2 PLESTERAN 1 PC : 5 Ps, TEBAL 15 mm E-03 30,486.00
2 1 m2 ACIAN PLESTERAN E-05 21,703.00

F PEKERJAAN KAYU
1 1 m3 PASANG KUSEN PINTU DAN JENDELA KAYU GUNUNG KELAS II F-02 5,044,875.00
2 1 m2 PASANG PINTU PANEL KAYU GUNUNG KELAS II F-05 397,650.00
3 1 m2 JENDELA KACA KAYU GUNUNG KELAS II (Tanpa Kaca) F-07 199,182.00
4 1 m' PASANG LIST PLAFOND KAYU PROFIL F-22 9,009.00
5 1 m' PASANG LIST PLAFOND GYPSUN F-23 18,826.00

G PEKERJAAN BETON
1 1 m3 MEMBUAT BETON TUMBUK, 1 PC : 3 Ps : 5 Kr G-01 687,285.00
2 1 m2 MEMBUAT LANTAI KERJA BETON TUMBUK TEBAL 5 cm, 1 PC : 3 Ps : 5 Kr G-02 86,662.00
3 1 m3 MEMBUAT BETON DENGAN MUTU K-175 G-03 628,050.00
4 1 Kg PEMBESIAN DENGAN BESI POLOS ATAU ULIR G-07 15,042.00
5 1 m2 PASANG BEKISTING UNTUK PONDASI G-08 125,664.00
6 1 m2 PASANG BEKISTING UNTUK SLOOF G-09 137,626.00
7 1 m2 PASANG BEKISTING UNTUK KOLOM G-10 228,365.00
8 1 m2 PASANG BEKISTING UNTUK BALOK G-11 235,562.00
9 1 m2 PASANG BEKISTING UNTUK LANTAI G-12 270,715.00
10 1 m2 PASANG BEKISTING UNTUK DINDING G-13 229,350.00
11 1 m2 PASANG BEKISTING UNTUK TANGGA G-14 259,259.00
12 1 m3 MEMBUAT PONDASI BETON BERTULANG T= 25 CM + Bekisting G-15 3,922,878.00
13 1 m3 MEMBUAT SLOOF 30/40 BETON BERTULANG + Bekisting G-16 2,223,898.00
13 1 m3 MEMBUAT SLOOF 15/20 BETON BERTULANG + Bekisting G-17 5,628,472.00
14 1 m3 MEMBUAT SLOOF BETON 20/35 BERTULANG + Bekisting (S3) G-18 4,666,256.00
15 1 m3 MEMBUAT LISTPLANK BETON 10/60 BERTULANG + Bekisting G-19 3,170,650.00
16 1 m3 MEMBUAT KOLOM STRUKTUR BETON BERTULANG 30/30 (+ Bekisting) (K1) G-20 4,886,340.00
17 1 m3 MEMBUAT KOLOM STRUKTUR BETON BERTULANG 20/20 (+ Bekisting) (K2) G-21 7,993,231.00
18 1 m3 MEMBUAT KOLOM BETON PRAKTIS 15/15 BERTULANG + Bekisting (K3) G-22 8,626,474.00
19 1 m3 MEMBUAT BALOK 20/40 BETON BERTULANG (+ Bekisting) (B1) G-23 3,868,590.00
20 1 m3 MEMBUAT BALOK 15/30 BETON BERTULANG (+ Bekisting) (B2) G-24 5,524,802.00
21 1 m3 MEMBUAT BALOK 15/32 BETON BERTULANG (+ Bekisting) (B3) G-25 5,203,208.00
22 1 m3 MEMBUAT BALOK 15/20 BETON BERTULANG (+ Bekisting) (B4) G-26 6,920,456.00
23 1 m3 MEMBUAT BALOK 12/15 BETON BERTULANG (+ Bekisting) (BR) G-27 7,803,586.00
24 1 m3 MEMBUAT BALOK LINTEL 12/15 BETON BERTULANG (+ Bekisting) (BL) G-28 7,803,586.00
(a) (b) (c) (d)
25 1 m3 MEMBUAT PLAT BETON T = 10 CM Bekisting G-29 3,159,893.00
26 1 m3 MEMBUAT PLAT BETON T = 12 CM Bekisting G-30 3,777,592.00

H PEKERJAAN PENUTUP ATAP


1 1 m2 PASANG ATAP GENTENG MORANDO NATURAL 18 BH/M2 H-02 57,167.00
2 1 m2 PASANG ATAP GENTENG MORANDO LAMA H-03 13,607.00
3 1 m' PASANG BUBUNG GENTENG MORANDO H-03 69,256.00

I PEKERJAAN LANGIT-LANGIT
1 1 m2 LANGIT-LANGIT GRC (1.20X2.40 ) Cm, RANGKA KAYU GUNUNG KELAS II I-04 89,349.00
2 1 m2 LANGIT-LANGIT GRC (1.20X2.40 ) Cm, RANGKA KAYU GUNUNG KELAS III I-04a 81,191.00

J PEKERJAAN SANITASI
1 MEMASANG 1 BUAH KLOSET JONGKOK PORSELIN J-01 437,976.00
2 MEMASANG 1 BUAH KLOSET DUDUK PORSELIN J-01a 1,902,736.00
2 MEMASANG 1 BUAH WASTAFEL J-02 595,756.00
3 MEMASANG 1 BUAH BAK MANDI FIBREGLASS 0,30M3 J-03 648,857.00
4 MEMASANG 1 METER PIPA BETON, Ø 15-20 CM J-04 0.00
5 MEMASANG 1 METER PIPA BETON, Ø 30-100 CM J-05 0.00
6 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA (45X45) CM J-06 0.00
4 MEMASANG 1 BUAH BAK KONTROL PASANGAN GREVEL BATU BATA (45X45) CM TANP J-07 170,977.00
5 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA (60x60) CM J-08 438,902.00
6 MEMASANG 1 BUAH BAK KONTROL PASANGAN GREVEL BATU BATA (60x60) CM TANP J-09 237,535.00
7 MEMASANG 1 METER PIPA PVC TIPE AW Ø 1/2" J-10 6,689.00
8 MEMASANG 1 METER PIPA PVC TIPE AW Ø 3/4" J-11 7,116.00
9 MEMASANG 1 METER PIPA PVC TIPE AW Ø 1" J-12 13,936.00
10 MEMASANG 1 METER PIPA PVC TIPE AW Ø 1 1/2" J-13 16,493.00
10 MEMASANG 1 METER PIPA PVC TIPE AW Ø 2" J-14 22,129.00
12 MEMASANG 1 METER PIPA PVC TIPE AW Ø 2 1/2" J-15 21,075.00
9 MEMASANG 1 METER PIPA PVC TIPE AW Ø 3" J-16 39,805.00
10 MEMASANG 1 METER PIPA PVC TIPE AW Ø 4" J-17 52,699.00
14 MEMASANG 1 BUAH BAK CUCI PIRING STAINLESS-STEEL J-18 330,005.00
11 MEMASANG 1 BUAH BAK CUCI PIRING STAINLESS-STEEL J-18 330,005.00
12 MEMASANG 1 BUAH KRAN Ø 1/2" ATAU Ø 3/4" J-19 23,421.00
13 MEMASANG 1 BUAH FLOOR DRAIN J-20 105,545.00
14 1 M' SALURAN GRAFEL BETON 1/2 Ø 20 cm + PASANGAN J-21 72,781.00
17 1 M' GORONG-GORONG BUIS BETON Ø 20 cm + PASANGAN (A137) J-21A 158,299.00
18 1 M' SALURAN GRAFEL BETON 1/2 Ø 30 cm + PASANGAN J-24 2,633,683.00
15 1 UNIT SEPTICTANK 2.5 x 1.5 X 2 m (TYPE BESAR) + REMBESAN J-22 8,894,407.00
20 1 UNIT SEPTICTANK 1.5 x 1.0 X 1.5 m (TYPE KECIL) + REMBESAN (A082) J-23 2,291,679.00
21 1 UNIT PEK. SEPTICKTANK BUIS BETON Ø 80 CM + RESAPAN J-24 2,633,683.00

K PEKERJAAN BESI DAN ALUMINIUM


1 1 m' PASANG TALANG DATAR, SENG BJLS 28 K-01 94,794.00
1 1 m' PASANG TALANG MIRING, ZINK ALUM K-01a 70,024.00
3 1 m' PASANG TALANG MIRING, SENG BJLS 28 K-02 108,799.00
4 1 m' PASANG TALANG 1/2 LINGKARAN Ø10 cm, SENG BJLS 28 K-03 0.00
K- 1 m2 PASANG PINTU GULUNG BESI
K- 1 m2 PASANG PINTU LIPAT
K- 1 m2 PASANG PINTU SUNSCREEN ALLUMINIUM
K- 1 m2 PASANG ROLLING DOOR
K- 1 m2 PASANG PINTU ALLUMINIUM
K- 1 m2 PASANG VENETIONS BLINDS
K- 1 m2 PASANG VERTICAL BLINDS
K- 1 m2 PASANG KAWAT HARMONIKA
K- 1 m2 PASANG KAWAT KASSA
K- 1 m2 PASANG KAWAT BURUNG
(a) (b) (c) (d)
L PEKERJAAN KUNCI DAN KACA
1 1 BUAH PASANG KUNCI SETARA TESA L-01 195,833.00
3 1 BUAH PASANG ENGSEL PINTU L-03 22,305.00
4 1 BUAH PASANG ENGSEL JENDELA KUPU-KUPU L-04 12,193.00
5 1 BUAH PASANG KUNCI SELOT JENDELA L-05 21,087.00
6 1 BUAH PASANG KUNCI SELOT PINTU L-06 23,617.00
7 1 BUAH PASANG KAIT ANGIN L-07 15,485.00
8 1 m2 BUAH PASANG KACA TEBAL 3 mm L-08 72,476.00
9 1 m2 BUAH PASANG KACA TEBAL 5 mm L-09 86,512.00

M PEKERJAAN PENUTUP LANTAI DAN DINDING


1 1 m2 PASANG LANTAI KERAMIK 20X20 cm M-01 105,370.00
2 1 m2 PASANG LANTAI KERAMIK 30X30 cm ANTI SELIP M-04 127,141.00

N PEKERJAAN PENGECATAN
1 1 m2 PENGECATAN BIDANG KAYU BARU (1 Lapis Plamir; 1 Lapis Cat dasar; 3 Lapis Cat Penu N-03 40,763.00
2 1 m2 PELABURAN BIDANG KAYU DENGAN CAT RESIDU DAN TER N-04 6,859.00
3 1 m2 PENGECATAN BIDANG TEMBOK BARU (1 Lapis Plamir; 1 Lapis Cat dasar; 2 Lapis Cat Pe N-05 17,340.00
6 1 m2 PENGECATAN BIDANG TEMBOK ULANG N-06 13,389.00
4 1 m2 PENGECATAN PLAFOND N-07 21,025.00
5 1 m2 PENGECATAN GENTING N-08 27,293.00
6 1 m2 PENGECATAN BATU TEMPEL BARU (1 Lapis Cat dasar; 2 Lapis Cat Penutup) N-09 27,095.00

O PEKERJAAN KUSEN PINTU & JENDELA ALUMUNIUM


1 1 BH PEKERJAAN PINTU ALUMUNIUM TYPE P1 O-01 2,025,456.00
2 1 BH PEKERJAAN PINTU ALUMUNIUM TYPE P4 O-02 1,823,285.00
2 1 BH PEKERJAAN PINTU ALUMUNIUM TYPE P5 O-03 1,309,044.00
3 1 BH PEKERJAAN PINTU ALUMUNIUM TYPE PJ O-04 3,929,140.00
3 1 BH PEKERJAAN KUSEN PARTISI TYPE I O-05 9,500,227.00
4 1 BH PEKERJAAN KUSEN PARTISI TYPE 2 O-06 4,240,079.00
4 1 BH PEKERJAAN KUSEN PARTISI TYPE 3 O-07 4,167,760.00
5 1 BH PEKERJAAN KUSEN PARTISI TYPE 4 O-08 3,931,820.00
5 1 BH PEKERJAAN KUSEN PARTISI TYPE 5a O-09 2,823,862.00
6 1 BH PEKERJAAN KUSEN PARTISI TYPE 5b O-09 3,486,464.00
DAFTAR KUANTITAS HARGA
KEGIATAN : PEMELIHARAAN GEDUNG RSUD dr. SOEKARDJO KOTA TASIKMALAYA
PEKERJAAN : REHABILITASI RUANG PICU LANTAI 2 DAN PEMBANGUNAN RAMPH
RSUD DR.SOEKARDJO KOTA TASIKMALAYA
LOKASI : KOTA TASIKMALAYA

Halaman 1

ANALISA
HARGA JUMLAH

KODE
NO. URAIAN PEKERJAAN VOL. SAT. SATUAN HARGA
(Rp.) (Rp.)

I Pekerjaan Persiapan
1 Pembuatan Papan Nama Proyek 1.000 Ls ls 300,000.00 300,000.00
2 Pengukuran Ulang 1.000 Ls ls 500,000.00 500,000.00
3 Pek.Pemasangan Bouwplank 150.000 A-02 m' 25,570.00 3,835,500.00
4 Pek Direksi Keet (Sewa) 1.000 A-03 ls 1,000,000.00 1,000,000.00

5,635,500.00
II. Perkerjaan Galian dan Urugan
1 Pek. Galian Tanah 44.100 B-01 m³ 22,880.00 1,009,008.00
2 Pek. Urugan Kembali 17.440 B-06 m³ 10,967.00 191,264.48
3 Pek. Urugan Pasir Bawah Pondasi 3.100 B-09 m³ 118,580.00 367,598.00
4 Pek. Urugan Pasir Bawah Lantai 14.540 B-09 m³ 118,580.00 1,724,153.20
3,292,023.68
III. Pekerjaan Pondasi
1 Pas. Lantai Kerja 1 : 3 : 5 1.125 G-02 m³ 86,662.00 97,494.75
2 Pek. Pondasi Plat T = 25 cm 5.510 G-15 m³ 3,922,878.00 21,615,057.78
21,712,552.53
IV. Pekerjaan Beton
1 Pek. Sloof Beton 15/20 0.290 G-17 m³ 5,628,472.00 1,632,256.88
2 Pek. Sloof Beton 30/40 9.360 G-16 m³ 2,223,898.00 20,815,685.28
3 Pek. Kolom Beton Struktur 30/30 (K1) 3.650 G-20 m³ 4,886,340.00 17,835,141.00
4 Pek. Kolom Beton Struktur 20/20 (K2) 4.420 G-21 m³ 7,993,231.00 35,330,081.02
5 Pek. Kolom Beton Praktis 15/15 (KP) 0.790 G-22 m³ 8,626,474.00 6,814,914.46
6 Pek. Balok Beton Struktur 20/40 (B1) 6.720 G-23 m³ 3,868,590.00 25,996,924.80
8 Pek. Balok Beton Struktur 15/30 (B2) 0.620 G-24 m³ 5,524,802.00 3,425,377.24
9 Pek. Balok Beton Struktur 15/20 (RB) 2.560 G-26 m³ 6,920,456.00 17,716,367.36
11 Pek. Plat Beton T = 12 cm 10.820 G-30 m³ 3,777,592.00 40,873,545.44
12 Pek. Plat Beton T = 10 cm (Untuk Plat Tangga + Bordes) 0.790 G-29 m³ 3,159,893.00 2,496,315.47
13 Pek. Plat Beton T = 10 cm (Untuk Meja Beton) 0.294 G-29 m³ 3,159,893.00 929,008.54
173,865,617.49
V. Pekerjaan Dinding Dan Plesteran
Lantai 1
1 Pasangan Dinding 1/2 Bata 1 : 5 51.410 D-02 m² 97,448.00 5,009,801.68
2 Pekerjaan Plesteran 1 : 5 44.150 E-03 m² 30,486.00 1,345,956.90
3 Pekerjaan Acian Plesteran Bata 44.150 E-05 m² 21,703.00 958,187.45
7,313,946.03
Halaman 2

ANALISA
HARGA JUMLAH

KODE
NO. URAIAN PEKERJAAN VOL. SAT. SATUAN HARGA
(Rp.) (Rp.)

VI. Pekerjaan Kusen, Pintu, Jendela dan Partisi


1 Pas. Kusen Pintu ,Jendela dan Bouv Kayu Gunung Klas II 1.250 F-02 m³ 5,044,875.00 6,306,093.75
2 Pas. Daun Jendela Kaca Kayu Gunung Klas II Tanpa Kaca 2.240 F-07 m² 199,182.00 446,167.68
3 Pas Kaaca Polos 3 mm 24.026 L-08 m² 72,476.00 1,741,308.38
8,493,569.81
VII. Pekerjaan Rangka dan Penutup Plapond
1 Pek. Plafond GRC (1,2x2,4) + Rangka Kayu Gunung Klas III 155.000 I-04a m² 81,191.00 12,584,605.00
2 Pek. List Plafond Kayu Gunung Klas II 255.000 F-22 m¹ 9,009.00 2,297,295.00
14,881,900.00
VIII. Pekerjaan Lantai
1 Pas. Lantai Keramik 30 x 30 Anti Slip Putih Polos Setara Mulia 136.020 M-04 m² 127,141.00 17,293,718.82
3 Pas. Lantai Keramik 20x20 KM/WC Corak Anti Slip 12.000 M-02 m² 117,702.00 1,412,424.00
4 Pas. Keramik Dinding KM/WC 20 x 25 43.925 M-07 m² 119,358.00 5,242,800.15
5 Pas. Keramik Dinding Meja Beton 20 x 25 1.680 M-07 m² 119,358.00 200,521.44
6 Pas. Rabat Beton Tumbuk T = 5 Cm 35.650 G-02 m¹ 86,662.00 3,089,500.30
27,238,964.71
IX. Pekerjaan Pengecatan Dan Laburan
1 Pek. Cat Kayu + Meni Setara Avian 38.928 N-02 m² 31,673.00 1,232,966.54
2 Pek. Cat Tembok Setara Sanlex 44.150 N-05 m² 17,340.00 765,561.00
3 Pek. Cat Tembok Ulang Setara Sanlex 449.772 N-06 m² 13,389.00 6,021,997.31
4 Pek. Cat Plafond Setara Sanlex 155.000 N-07 m² 21,025.00 3,258,875.00
11,279,399.85
X. Pekerjaan Gantungan dan Kunci
1 Pas. Engsel Jendela 3" Setara Unillon 12.000 L-04 bh 12,193.00 146,316.00
2 Pas. Hak Angin Kait 12.000 L-07 bh 15,485.00 185,820.00
3 Pas. Slot Jendela 6.000 L-05 bh 21,087.00 126,522.00
458,658.00
XI. Pekerjaan Instalasi Listrik
1 Pas. Instalasi Titik Lampu 7.000 U&B ttk 139,300.00 975,100.00
2 Pas. Lampu SL 18 Watt 7.000 U&B bh 41,800.00 292,600.00
3 Pas. Saklar Ganda Broco 1.000 U&B bh 17,100.00 17,100.00
4 Biaya Penyambungan Kembali 1.000 U&B ls 250,000.00 250,000.00
1,534,800.00
Halaman 3

ANALISA
HARGA JUMLAH

KODE
NO. URAIAN PEKERJAAN VOL. SAT. SATUAN HARGA
(Rp.) (Rp.)

XII. Pekerjaan Plumbing dan Sanitair


1 Pas.Closet Duduk Setara INA 2.000 J-01a bh 1,902,736.00 3,805,472.00
2 Pas.Wastafel Kumplit 1.000 J-02 bh 595,756.00 595,756.00
3 Pas. Floor Drain 2.000 J-20 bh 105,545.00 211,090.00
4 Pas. Pipa PVC 4" + Sambungan ke Septicktank 12.000 J-17 m¹ 52,699.00 632,388.00
5 Pas. Pipa PVC 3" + Sambungan 12.000 J-16 m¹ 39,805.00 477,660.00
6 Pas. Pipa PVC 2" + Sambungan 16.000 J-14 m¹ 22,129.00 354,064.00
7 Pas. Pipa PVC 3/4" + Sambungan 16.000 J-11 m¹ 7,116.00 113,856.00
8 Pas. Pipa PVC 1/2" + Sambungan 4.000 J-10 m¹ 6,689.00 26,756.00
6,217,042.00
REKAPITULASI DAFTAR KUANTITAS HARGA

KEGIATAN : PEMELIHARAAN GEDUNG RSUD dr. SOEKARDJO KOTA TASIKMALAYA


PEKERJAAN : REHABILITASI RUANG PICU LANTAI 2 DAN PEMBANGUNAN RAMPH
RSUD DR.SOEKARDJO KOTA TASIKMALAYA
LOKASI : KOTA TASIKMALAYA

NO. URAIAN PEKERJAAN SAT. JUMLAH HARGA

I. PEKERJAAN PERSIAPAN Rp. 5,635,500.00


II. PEKERJAAN GALIAN DAN URUGAN Rp. 3,292,023.68
III. PEKERJAAN PONDASI Rp. 21,712,552.53
IV. PEKERJAAN BETON Rp. 173,865,617.49
V. PEKERJAAN DINDING DAN PLESTERAN Rp. 7,313,946.03
VI. PEKERJAAN KUSEN, PINTU DAN JENDELA Rp. 8,493,569.81
VII. PEKERJAAN RANGKA DAN PENUTUP PLAFOND Rp. 14,881,900.00
VIII. PEKERJAAN LANTAI Rp. 27,238,964.71
IX. PEKERJAAN PENGECATAN DAN LABURAN Rp. 11,279,399.85
X. PEKERJAAN GANTUNGAN DAN KUNCI Rp. 458,658.00
XI. PEKERJAAN INSTALASI LISTRIK Rp. 1,534,800.00

JUMLAH REAL COST Rp. 275,706,932.10

PPN 10% Rp. 27,570,693.21

JUMLAH TOTAL Rp. 303,277,625.31

DIBULATKAN Rp. 303,277,000.00

TERBILANG : TIGA RATUS LIMA PULUH ENAM JUTA TIGA RATUS ENAM PULUH LIMA RIBU RUPIAH\

Tasikmalaya, Agustus 2014


Konsultan Perencana
CV. GATRIEC ENGINEERING

Ir. H. YEYE NITA SUSIANO


Direktur
PERHITUNGAN BESI BETON DAN BEKISTING / M3
DENGAN PENDEKATAN PERHITUNGAN DI LAPANGAN

(kotak hijau diisi dengan dimensi pekerjaan yang akan dicari)


(kotak kuning diisi dengan harga satuan pekerjaan yang digunakan)

HARGA
1 M3 KOLOM 20 X 20 20 X 20 CM
Panjang/M3 1 : 0.2 : 0.2 = 25.00 M
20
Besi diameter 12 juml 6
Besi diameter juml
Besi diameter juml 20

Begel diameter 8 jarak 15 cm

Besi diameter 12 25.00 X 6 X 0.89 KG = = 133.164


Besi diameter 0 25.00 X 0 X 0 KG = = 0.000
Besi diameter 0 25.00 X 0 X 0 KG = = 0.000
Begel diameter 8 ( 25.00 : 0.15 ) X ( 0.2 + 0.2 + 0.2 + 0.2 )] X 0.4 = 52.608
185.772 Kg
Bekisting 25.00 X ( 0.2 + 0.20 + 0.2 + 0.2 ) = 20.000 m2

E003 Beton 1.00 X 699,880.00 = 699,880.00


E004 Besi 185.772 X 13,780.00 = 2,559,938.16
E007 Bekisting Kolom 20.000 X 250,470.00 = 5,009,400.00
Jumlah 8,269,218.16
Jumlah Total 8,269,218.16
DIBULATKAN 8,269,000.00

HARGA
1 M3 BALOK 15 X 20 15 X 20 CM
Panjang/M3 1 : 0.15 : 0.2 = 33.33 M
15
Besi diameter 12 juml 4
Besi diameter 10 juml 0
Besi diameter juml 20

Begel diameter 8 jarak 15 cm

Besi diameter 12 33.33 X 4 X 0.89 KG = = 118.368


Besi diameter 10 33.33 X 0 X 0.62 KG = = 0.000
Besi diameter 0 33.33 X 0 X 0 KG = = 0.000
Begel diameter 8 ( 33.33 : 0.15 ) X ( 0.15 + 0.2 + 0.15 + 0.2 )] X 0.4 = 61.376
179.744 Kg
Bekisting 33.33 X ( 0.15 + 0.2 + 0.15 ) = 16.667 m2

E003 Beton 1.00 X 699,880.00 = 699,880.00


E004 Besi 179.744 X 13,780.00 = 2,476,872.32
E008 Bekisting Balok 16.667 X 256,190.00 = 4,269,833.33
Jumlah 7,446,585.65
Jumlah Total 7,446,585.65
DIBULATKAN 7,446,000.00
HARGA
1 M3 SLOOF 20 X 15 20 X 15 CM
Panjang/M3 1 : 0.2 : 0.15 = 33.33 M
20
Besi diameter 12 juml 4
Besi diameter 10 juml 0
Besi diameter juml 15

Begel diameter 8 jarak 15 cm

Besi diameter 12 33.33 X 4 X 0.89 KG = = 118.368


Besi diameter 10 33.33 X 0 X 0.62 KG = = 0.000
Besi diameter 0 33.33 X 0 X 0 KG = = 0.000
Begel diameter 8 ( 33.33 : 0.15 ) X ( 0.2 + 0.15 + 0.2 + 0.15 )] X 0.4 = 61.376
179.744 Kg
Bekisting 33.33 X ( 0.2 + 0.2 ) = 13.333 m2

E003 Beton 1.00 X 699,880.00 = 699,880.00


E004 Besi 179.744 X 13,780.00 = 2,476,872.32
E006 Bekisting Sloof 13.333 X 141,560.00 = 1,887,466.67
Jumlah 5,064,218.99
Jumlah Total 5,064,218.99
DIBULATKAN 5,064,000.00

HARGA
1 M3 SLOOF 25 X 20 25 X 20 CM
Panjang/M3 1 : 0.25 : 0.2 = 20.00 M
25
Besi diameter 12 juml 6
Besi diameter 0 juml 0
Besi diameter juml 20

Begel diameter 8 jarak 15 cm

Besi diameter 12 20.00 X 6 X ### KG = = 106.531


Besi diameter 0 20.00 X 0 X 0 KG = = 0.000
Besi diameter 0 20.00 X 0 X 0 KG = = 0.000
Begel diameter 8 ( 20.00 : 0.15 ) X ( 0.25 + 0.2 + 0.25 + 0.2 )] X 0.4 = 47.347
153.878 Kg
Bekisting 20.00 X ( 0.25 + 0.25 ) = 10.000 m2

E003 Beton 1.00 X 699,880.00 = 699,880.00


E004 Besi 153.878 X 13,780.00 = 2,120,444.35
E021 Bekisting Sloof 10.000 X 86,480.00 = 864,800.00
Jumlah 3,685,124.35
Jumlah Total 3,685,124.35
DIBULATKAN 3,685,000.00

HARGA
1 M3 RINGBALK 15 X 20 15 X 20 CM
Panjang/M3 1 : 0.15 : 0.2 = 33.33 M
15
Besi diameter 12 juml 4
Besi diameter 10 juml 2
Besi diameter juml 20
Begel diameter 8 jarak 15 cm

Besi diameter 12 33.33 X 4 X 0.89 KG = = 118.368


Besi diameter 10 33.33 X 2 X 0.62 KG = = 41.100
Besi diameter 0 33.33 X 0 X 0 KG = = 0.000
Begel diameter 8 ( 33.33 : 0.15 ) X ( 0.15 + 0.2 + 0.15 + 0.2 )] X 0.4 = 61.376
220.844 Kg
Bekisting 33.33 X ( 0.15 + 0.15 ) = 10.000 m2

E003 Beton 1.00 X 699,880.00 = 699,880.00


E004 Besi 220.844 X 13,780.00 = 3,043,230.32
E008 Bekisting Balok 10.000 X 256,190.00 = 2,561,900.00
Jumlah 6,305,010.32
Jumlah Total 6,305,010.32
DIBULATKAN 6,305,000.00
1 M3 PLAT LANTAI T = 12CM
Tebal 12 CM LUAS / M3 = 1 : 0.12 = 8.333 M2
1 M2
Panjang 1.00 M1
Lebar 1.00 M1

besi diameter
LAYER 1 (X) 10 jarak 20 cm 0.2 Y
(Y) 10 jarak 20 cm 0.2

LAYER 2 (X) 10 jarak 20 cm 0.2


(Y) 10 jarak 20 cm 0.2
X
LAYER 1 (X) (1/0.2) X 0.62 = 3.083
(Y) (1/0.2) X 0.62 = 3.083

LAYER 2 (X) (1/0.2) X 0.62 = 3.083


(Y) (1/0.2) X 0.62 = 3.083
12.330 Kg
1 M3 = 102.750 Kg

E003 Beton 1.00 X 699,880.00 = 699,880.00


E004 Besi 102.750 X 13,780.00 = 1,415,895.00
E009 Bekisting Lantai 8.333 X 320,070.00 = 2,667,250.00
Jumlah 4,783,025.00
Jumlah Total 4,783,025.00
DIBULATKAN 4,783,000.00 /m3
573,960.000 /m2
VOLUME KUBIKASI RUMAH TYPE 160/150 2 LANTAI
DIMENSI
NO URAIAN PEKERJAAN SATUAN VOLUME KETERANGAN
P L T
I Pekerjaan Persiapan
1.Pekerjaan Pembersihan lokasi 14 10.72 m2 150
2.Pengukuran ulang 1
3.Pek. Pemasangan Bouwplank 48.25 m1 48.25
4.Pek.Direksikeet (sewa) 1

II pekerjaan Galian Dan Urugan


1 Pekerjaan Galian Tanah
a.Pondasi Plat Kaki 1.2 1.2 1.5 m3 43.2 20 Plat Kaki
b.Pondasi Tangga 0.6 0.6 0.95 m3 0.34 1 Pondasi Tangga
c.pondasi Benteng 6.25 0.3 0.3 m3 0.56
Jumlah 44.10

2 Pekerjaan Urugan Kembali


a.Pondasi Plat Kaki 17.28 40% dari galian
b.Pondasi Tangga 0.6 0.2 0.66 m3 0.16
Jumlah 17.44

3 Pekerjaan Urugan Pasir Bawah Pondasi


a.Pondasi Plat Kaki 1.2 1.2 0.1 m3 2.88 20 Plat kaki
b.Pondasi Tangga 0.6 0.6 0.1 m3 0.04 1 Pondasi Tangga
c.pondasi Benteng 6.25 0.3 0.1 m3 0.19
Jumlah 3.10

4 Pek.Urugan Pasir Bawah Lantai


a.Teras Depan 2.5 1.5 0.1 m3 0.38
b.Teras Belakang 2 1 0.1 m3 0.2
c.R.Tamu 2.5 5 0.1 m3 1.25
d.R.Makan 5.5 3 0.1 m3 1.65
e.Wc & Depan Wc 1 3 2.5 0.1 m3 0.75
f.R.Tidur I 3 3 0.1 m3 0.9
g.R.Tidur II 3 3 0.1 m3 0.9
h.Musola 3 2 0.15 m3 0.9
i.Dapur 4.5 2 0.1 m3 0.9
j.Garasi 5 3 0.1 m3 1.5
k.Balkon Depan 2.5 1.5 0.05 m3 0.19
l.Balkon Tempat Jemuran 5.5 2 0.05 m3 0.55
m.Ruang keluarga 2.5 5 0.1 m3 1.25
n.Wc & Depan Wc 2 3 2.5 0.05 m3 0.38
o.Wc & Depan Wc 3 2 1.5 0.05 m3 0.15
p.R.Tidur III 3 3 0.1 m3 0.9
q.R.Tidur IV 3 3 0.1 m3 0.9
r.R.Tidur V 3 3 0.1 m3 0.9
Jumlah 14.54

5 Pek.Urugan Tanah Peninggi Lantai


a.Teras Depan 2.5 1.5 0.12 m3 0.45
b.Teras Belakang 2 1 0.12 m3 0.24
c.R.Tamu 2.5 5 0.12 m3 1.5
e.R.Makan 5.5 3 0.12 m3 1.98
f.Wc & Depan Wc 3 2.5 0.12 m3 0.9
g.R.Tidur I 3 3 0.12 m3 1.08
h.R.Tidur II 3 3 0.12 m3 1.08
i.Musola 3 2 0.12 m3 0.72
j.Dapur 4.5 2 0.12 m3 1.08
k.Garasi 5 3 0.12 m3 1.8
Jumlah 10.83

III Pekerjaan Pondasi


1 Pas.Astamping
a.pondasi tangga 0.6 0.6 0.1 m3 0.04
b.Pondasi Benteng 6.25 0.3 0.1 m3 0.19
Jumlah 0.22

2 Pas.Pondasi Kali 1 : 5
a.Pondasi Plat Kaki 1 1 0.275 m3 5.50 20 Plat Kaki
b.Pondasi Tangga 0.6 0.6 0.25 m3 0.09 1 Pondasi Tangga
c.pondasi Benteng 6.25 0.3 0.3 m3 0.56

IV Pekerjaan Beton
1 Pek.Sloof Beton 30/40 78 0.3 0.4 m3 9.36
2 Pek.Sloof Beton 15/20 9.5 0.15 0.2 m3 0.29
3 Pek Kolom Praktis 15/15 35.05 0.15 0.15 m3 0.79
4 Pek.Kolom Struktur I 30/30 40.56 0.3 0.3 m3 3.65
5 Pek.Kolom Struktur II 20/20 110.54 0.2 0.2 m3 4.42
6 Pek.Balok I 20/40 84 0.2 0.4 m3 6.72
7 Pek.Balok II 15/30 13.7 0.15 0.3 m3 0.62
8 Ring Balk 15/20 85.2 0.15 0.2 m3 2.56
9 Plat kantiever 16.38 0.1 m3 1.64
10 Plat Lantai 90.13 0.12 m3 10.82
11 Plat Tangga dan Bodres 6.6 0.9 0.12 m3 0.79

V Pekerjaan Dinding Dan Plesteran


1 Pas.Dinding Bata 1 : 3
a.Lantai 1 7.6 0.12 3.12 m3 2.85
b.Lantai 2 14.6 0.12 3.9 m3 6.83
2 Pas.Dinding Bata 1 : 5
a.Lantai 1 51.00 0.12 3.12 m3 19.09
b.Lantai 2 48.37 0.12 3.9 m3 22.64
3 Pek.Plesteran 1 : 3
a.Lantai 1 7.6 0.03 3.12 m3 0.71
b.Lantai 2 14.6 0.03 3.9 m3 1.71
4 Pek.Plesteran 1 : 5
a.Lantai 1 51.00 0.12 3.12 m3 19.09
b.Lantai 2 48.37 0.12 3.9 m3 22.64
5 Pek.Acian
a.Lantai 1 58.6 0 3.12 m3 0.05
b.Lantai 2 62.97 0 3.9 m3 0.07
Jumlah Pas.Bata 51.41
Jumlah Pas.plesteran 44.15
Jumlah Pas.Acian 0.13

VI Pek. Kusen Pintu,Jendela & bouvenlight


1 Pek.Kusen Pintu,Jendela Dan Bouvenligh
a.Type P1 (9BH) 6.7 0.14 0.05 m3 0.42
b.Type P2 (3BH) 4.85 0.14 0.05 m3 0.10
c.Type Pj (2BH) 10.48 0.14 0.05 m3 0.15
e.Type J1 (3BH) 7.3 0.14 0.05 m3 0.15
f.Type J2 (10BH) 4.2 0.14 0.05 m3 0.29
h.Bouvenligh (7BH) 2.6 0.14 0.05 m3 0.13
Jumlah 1.25

2 Pek.Daun Pintu Panil dan jendela


a.Type P1 (10BH) 2 0.8 0.04 m3 0.64
b.Type P2 (3BH) 2 0.7 0.04 m3 0.17
c.Type Pj (2BH)
Pintu ganda 5.74 0.07 0.04 m3 0.06
Jendela 3.34 0.07 0.3 m3 0.14
e.Type J1 (3BH) 3.92 0.07 0.3 m3 0.49
f.Type J2 (10BH) 3.48 0.07 0.3 m3 0.73
Jumlah 2.24

VII Pekerjaan Atap Dan Kuda-Kuda


a.Kuda-Kuda 1
Balok Tarik 8/15 8.85 0.15 0.8 m3 3.19
Balok sokong 8/12 6.6 0.12 0.8 m3 1.90
Balok Pengunci 8/15 1 0.15 0.8 m3 0.72
Balok Nok 8/12 7.25 0.12 0.8 m3 0.70
Balok Gapit 6/12 5.94 0.12 0.6 m3 1.28
Balok Silang Angin 6/12 2.85 0.12 0.6 m3 0.82
Balok Balok Silang Gempa 6/12 2.85 0.12 0.6 m3 1.64
Papan Ruiter 2/20 7.25 0.2 0.02 m3 0.03
Tiang Kuda-Kuda 8/12 2.75 0.12 0.8 m3 0.792
Kaki Kuda-Kuda 8/12 10.26 0.12 0.8 m3 2.95
Gording 8/12 7.25 0.12 0.8 m3 4.18
Jumlah 18.20

b.Kuda-Kuda
Balok Tarik 8/15 8.35 0.15 0.8 m3 1.00
Balok sokong 8/12 6.2 0.12 0.8 m3 1.19
Balok Pengunci 8/15 1 0.15 0.8 m3 0.48
Balok Nok 8/12 3 0.12 0.8 m3 0.29
Balok Gapit 6/12 5.5 0.12 0.6 m3 0.79
Balok Silang Angin 6/12 2 0.12 0.6 m3 0.29
Balok Balok Silang Gempa 6/12 3 0.12 0.6 m3 0.86
Papan Ruiter 2/20 3 0.2 0.02 m3 0.01
Tiang Kuda-Kuda 8/12 2.7 0.12 0.8 m3 0.52
Kaki Kuda-Kuda 8/12 9.4 0.12 0.8 m3 1.80
Gording 8/12 3 0.12 0.8 m3 0.58
Jumlah 7.82

VIII Pekerjaan Rangka Dan Penutup Plafond


1 Pek.Plafond Enternit + Rangka Kayu Albasiah
a.Teras Depan 2.5 1.5 m2 3.75
b.Teras Belakang 2 1 m2 2
c.R.Tamu 2.5 5 m2 12.5
d.R.Makan 5.5 3 m2 16.5
e.Km/Wc 3 2.5 m2 7.5
f.R.Tidur I 3 3 m2 9
g.R.Tidur II 3 3 m2 9
h.Musola 3 2 m2 6
i.Dapur 4.5 2 m2 9
j.Garasi 5 3 m2 15
k.Balkon Depan 2.5 1.5 m2 3.75
l.lisplank 5.5 2 m2 11
m.Ruang keluarga 2.5 5 m2 12.5
n.Km/Wc 3 2.5 m2 7.5
o.Km/Wc 2 1.5 m2 3
p.R.Tidur III 3 3 m2 9
q.R.Tidur IV 3 3 m2 9
r.R.Tidur V 3 3 m2 9
Jumlah 155

2 Pek.List Plafond Kayu Gunung Klas II 1/4


a.List Plafond Lantai I 110 m1 110
b.List Plafond Lantai II 145 m1 145
Jumlah 255

IX Pekerjaan Lantai,Rabat Dan Saluran


1 Pas.Lantai Keramik 20X20 wc Corak Anti Slip
a.Wc I 2.5 1.8 m2 4.5
b.wc II 2.5 1.8 m2 4.5
c.WC III 2 1.5 m2 3
Jumlah 12

2 Pas.Lantai Keramik 30X30 Putih Polos


a.Teras Depan 2.65 1.8 m2 4.77
b.Teras Belakang 2 1 m2 2
c.R.Tamu 5 2.5 m2 12.5
d.R.Makan 5.5 3 m2 16.5
e.R.Tidur I 3 3 m2 9
f.R.Tidur II 3 3 m2 9
g.Musola 3 2 m2 6
h.Dapur 4.5 2 m2 9
i.Garasi 5 3 m2 15
j.Balkon Depan 2.5 1.5 m2 3.75
k.Ruang keluarga 5 2.5 m2 12.5
l.R.Tidur III 3 3 m2 9
m.R.Tidur IV 3 3 m2 9
n.R.Tidur V 3 3 m2 9
o.Depan Wc I 2.5 1.2 m2 3
p.Depan Wc II 2.5 1.2 m2 3
q.Depan Wc III 2 1.5 m2 3
Jumlah 136.02

3 Pas.Kramik 30x30 Anti Slip


a.Balkon belakang (Tempat Jemuran) 5.5 2 m2 11
b.Carfort depan 2.1 1.5 m2 3.15
c.Carfort belakang 1.2 0.9 m2 1.08
Jumlah 15.23

3 Pas.Dinding Keramik 20X25 Biru Polos


Dinding WC I 7.8 1.75 m2 13.65
Dinding WC II 7.8 1.75 m2 13.65
Dinding WC III 6 1.75 m2 10.5
Dinding Dapur 3.5 1.75 m2 6.125
d.Meja Dapur 2.8 0.6 m2 1.68
Jumlah 43.925

X Pekerjaan Pengecatan Dan Leburan


1 Pek. Cat Kayu + Setaraf Avian
a.Pek.Cat Kusen
Type P1 (9BH) 6.7 0.24 m2 1.608
Type P2 (3BH) 4.85 0.24 m2 1.164
Type Pj (2BH) 10.48 0.24 m2 2.5152
Type J1 (3BH) 7.3 0.24 m2 1.752
Type J2 (10BH) 4.2 0.24 m2 1.008
Bouvenligh (7BH) 2.6 0.24 m2 0.624
Jumlah 8.6712

b.Pek.Cat Daun Pintu Dan Jendela


a.Type P1 (10BH) 2 1.68 m2 3.36
b.Type P2 (3BH) 2 1.48 m2 2.96
c.Type Pj (2BH)
Pintu ganda 5.74 2.56 m2 14.69
Jendela 3.34 0.7 m2 2.34
e.Type J1 (3BH) 3.92 1.14 m2 4.47
f.Type J2 (10BH) 3.48 0.7 m2 2.44
Jumlah 30.2572

2 Pek.Cat Tembok Baru Setaraf Sanlex


a.Teras Depan 3.75 3.12 m2 11.7
b.Teras Belakang 2 3.12 m2 6.24
c.R.Tamu 12.5 3.12 m2 39
d.R.Makan 16.5 3.12 m2 51.48
e.Km/Wc 7.5 3.12 m2 23.4
f.R.Tidur I 9 3.12 m2 28.08
g.R.Tidur II 9 3.12 m2 28.08
h.Musola 6 3.12 m2 18.72
i.Dapur 9 3.12 m2 28.08
j.Garasi 15 3.12 m2 46.8
k.Balkon Depan 3.75 3.9 m2 14.63
l.lisplank 11 3.9 m2 42.9
m.Ruang keluarga 12.5 3.9 m2 48.75
n.Km/Wc 7.5 3.9 m2 29.25
o.Km/Wc 3 3.9 m2 11.7
p.R.Tidur III 9 3.9 m2 35.1
q.R.Tidur IV 9 3.9 m2 35.1
r.R.Tidur V 9 3.9 m2 35.1
Jumlah 534.105

3 Pek.Cat Plafond Setaraf Sanlex


a.Teras Depan 2.5 1.5 m2 3.75
b.Teras Belakang 2 1 m2 2
c.R.Tamu 2.5 5 m2 12.5
d.R.Makan 5.5 3 m2 16.5
e.Km/Wc 3 2.5 m2 7.5
f.R.Tidur I 3 3 m2 9
g.R.Tidur II 3 3 m2 9
h.Musola 3 2 m2 6
i.Dapur 4.5 2 m2 9
j.Garasi 5 3 m2 15
k.Balkon Depan 2.5 1.5 m2 3.75
l.lisplank 5.5 2 m2 11
m.Ruang keluarga 2.5 5 m2 12.5
n.Km/Wc 3 2.5 m2 7.5
o.Km/Wc 2 1.5 m2 3
p.R.Tidur III 3 3 m2 9
q.R.Tidur IV 3 3 m2 9
r.R.Tidur V 3 3 m2 9
Jumlah 155

XI Pekerjaan Gantungan dan Kunci


1 1Buah Pasang Kunci Tanam Biasa bh
2 1 Bh Pas. Kunci Slaag Sekualitas "ASTON" bh
3 Pas.Engsel Pintu 4" Sekualitas Unillon bh 33
4 Pas.Engsel Jendela 3" Sekualitas Unillon bh 32
5 Pas.Hak Angin Kait bh 16
6 Pas.Slot Pintu bh 4
7 Pas.Slot Jendela bh 16

XII Pekerjaan Instalasi Listrik


1 Pas.Instalasi Titik Lampu ttk
2 Pas.Instalasi Stop Kontak ttk
3 Pas.Armatur Lampu SL 25 Watt
4 Pas.Saklar Ganda Broco
5 Pas.Saklar Ganda Tunggal Broco
6 Pas.Box Zekering in-bouw C4
7 Pas.MCB
8 Biaya Pemasangan BP Baru 900 Watt

XIII Pekerjaan Plumbing dan Sanister


1 Pas.Closet Duduk Setaraf INA
2 Pas.Bak Mandi Fber Kecil
3 Pas.Foor Drain (FD)
4 Pas.Kran Tembok 1/2"
5 Pas.Kitchen Zink Stainless Standar Lokal (1 Lobang)
6 Septic Tank dan Resapan
7 Pek.Pipa PVC 4" + Sambungan ke Septic Tank
8 Pas.Pipa PVC 3" + Sambungan
9 Pas.Pipa PVC 3/4" + Sambungan
10 Pas.Pipa PVC 1/2" + Sambungan
11 Pompa jet-Pump W Sanyo
12 Pas.Sumur Galian
13.195 0.5 0.7 m3 4.62
6.38 0.5 0.7 m3 2.23
33.115 0.5 0.7 m3 11.6
31.75 0.5 0.7 m3 11.11
14.7 0.5 0.7 m3 5.15
24 0.5 0.7 m3 8.4
24 0.5 0.7 m3 8.4
19 0.5 0.7 m3 6.65
31.5 0.5 0.7 m3 11.03
38 0.5 0.7 m3 13.3
13.195 0.5 0.7 m3 4.62
48.15 0.5 0.7 m3 16.85
33.115 0.5 0.7 m3 11.5903
14.7 0.5 0.7 m3 5.15
10.5 0.5 0.7 m3 3.68
24 0.5 0.7 m3 8.4
24 0.5 0.7 m3 8.4
31 0.5 0.7 m3 10.85