General Submission Form

(For Submittals other than Shop Drawings)


WPM_PF_PJW_0069

Project ﹕ WIDUS TOWER 3 HOTEL


Package No ﹕ WP15 - SECURITY AND SURVEILLANCE SYSTEM
Trade Contractor ﹕ EMPIRE AUTOMATION PHILIPPINES
Submission Reference ﹕ WP15_WT3H_PRBL_CD_HTL_0001 Revision : 14
Subject ﹕ WP15 Baseline Construction Programme
Issued For ﹕ Approval Information
Submission Date ﹕ May 21, 2018 *Delivery Period/Lead time:

Submission Description:(if applicable)

Specification Reference(s):
Equipment / Material Specified Equipment / Material Offered
Manufacturer: N/A Manufacturer: N/A
Brand: N/A Brand: N/A
Country of Origin: N/A Country of Origin: N/A
Model No.: N/A Type: N/A

Purpose / Remark:

Details of Attachment
【 】 Catalogue of Manufacturer / Technical Data 【 】 Equipment Schedule
【 】 Certificate / Approval Letter 【 】 Compliance Statement
【 】 Testing Certificate / Approval Letter 【 】 Sample (To be submitted on sample board)
【X】Working Programme 【 】 Others (CDR)

Authorized Signature of Trade Contractor


Anthony Misarez Project Supervisor
Name Signature Position

Construction Manager / Lead Consultant's Comment


Status
【】 A – No adverse comment, proceed according to this submission
【】 B – Proceed in accordance with the comment and re-submit
【】 C – Do not proceed and re-submit according to comment within 10 days

Comment (Please add a separate sheet if required)

Commented by: Company: Date:

* ALL submissions except shopdrawings & sketches


Widus Schedule Period Highlight: 1 Plan Actual % Complete Actual (beyond plan)
Thu Fri Sat Sun Mon
% Complete (beyond plan)
Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat
26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar 1-Apr 2-Apr 3-Apr 4-Apr 5-Apr 6-Apr 7-Apr 8-Apr 9-Apr 10-Apr 11-Apr 12-Apr 13-Apr 14-Apr 15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr 29-Apr 30-Apr 1-May 2-May 3-May 4-May 5-May 6-May 7-May 8-May 9-May 10-May 11-May 12-May 13-May 14-May 15-May 16-May ###### ###### ###### ###### ###### ###### ###### ###### ###### 26-May 27-May 28-May 29-May 30-May 31-May 1-Jun 2-Jun
PLAN PLAN Completed ACTUAL
ACTIVITY START DURATION day DURATION Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun
IN DAYS Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day 10 Day 11 Day 12 Day 13 Day 14 Day 15 Day 16 Day 17 Day 18 Day 19 Day 20 Day 21 Day 22 Day 23 Day 24 Day 25 Day 26 Day 27 Day 28 Day 29 Day 30 Day 31 Day 32 Day 33 Day 34 Day 35 Day 36 Day 37 Day 38 Day 39 Day 40 Day 41 Day 42 Day 43 Day 44 Day 45 Day 46 Day 47 Day 48 Day 49 Day 50 Day 51 Day 52 Day 53 Day 54 Day 55 Day 56 Day 57 Day 58 Day 59 Day 60 Day 61 Day 62 Day 63 Day 64 Day 65 Day 66 Day 67 Day 68 Day 69

Basement completed access control cable installation, schedule and cable test results Day 1
Basement completed CCTV cable installation, schedule and cable test results Day 1
Finished walls, ceilings & doors Day 1
Secure monitor room Day 1
Monitor room funiture installed Day 1
Monitor room handover to Empire 15 Day 1
Monitor room installation Day 1 4 days
Basement access control panel installation Day 1 Completed Day 1 1
Basement floor access control panel termination Day 1 Completed Day 1 6
Basement floor access control fit off Day 1 6 days Day 6 1 2 3 4 5 6
Basement floor Camera fit off Day 1 6 days Day 6 1 2 3 4 5 6
Ground floor completed access control cable installation, schedule and cable test results Day 9
Ground floor completed CCTV cable installation, schedule and cable test results Day 9
Finished walls, ceilings & doors Day 9
Ground floor access control panel installation Day 9 Completed
Ground floor access control panel termination Day 9 started
Ground floor access control fit off Day 9 6 days Day 16 1 2 3 4 5 6
Ground floor Camera fit off Day 9 6 days Day 16 1 2 3 4 5 6
Ground floor mezzanine completed access control cable installation, schedule and cable test results Day 17
Ground floor mezzanine completed CCTV cable installation, schedule and cable test results Day 17
Finished walls, ceilings & doors Day 17
Server room handed over to Empire Day 17
Rack installation Day 17 1 day 1
Server room installation Day 17 10 Days day 28 1 2 3 4 5 6 7 8 9 10
Ground floor mezzanine access control panel installation Day 17 completed
Ground floor mezzanine access control panel termination Day 17 4 Days 1 2 3 4
Ground floor mezzanine access control fit off Day 17 6 days 1 2 3 4 5 6
Ground floor mezzanine Camera fit off Day 17 6 days 1 2 3 4 5 6
2nd floor completed access control cable installation, schedule and cable test results Day 25
2nd floor completed CCTV cable installation, schedule and cable test results Day 25
Finished walls, ceilings & doors Day 25
2nd floor access control panel installation Day 25 completed
2nd floor access control panel termination Day 25 4 Days 1 2 3 4
2nd floor access control fit off Day 25 6 days 1 2 3 4 5 6
2nd floor Camera fit off Day 25 6 days 1 2 3 4 5 6
3rd and 4th floor completed access control cable installation, schedule and cable test results Day 33
3rd and 4th floor mezzanine completed CCTV cable installation, schedule and cable test results Day 33
Finished walls, ceilings & doors Day 33
3rd floor Access control fit off Day 33 2 days 1 2
3rd floor Camera fit off Day 33 2 days 1 2
4th floor Access control fit off Day 33 2 days 1 2
4th floor Camera fit off Day 33 2 days 1 2
5th and 6th floor completed access control cable installation, schedule and cable test results Day 37
5th and 6th floor mezzanine completed CCTV cable installation, schedule and cable test results Day 37
Finished walls, ceilings & doors Day 37
5th floor access control panel installation Day 37 completed
5th floor access control panel termination Day 37 4 days 1 2 3 4
5th floor access control fit off Day 37 2 days 1 2
5th floor Camera fit off Day 37 2 days 1 2
6th floor Access control fit off Day 37 2 days 1 2
6th floor Camera fit off Day 37 2 days 1 2
7th and 8th floor completed access control cable installation, schedule and cable test results Day 43
7th and 8th floor mezzanine completed CCTV cable installation, schedule and cable test results Day 43
Finished walls, ceilings & doors Day 43
7th floor Access control fit off Day 43 2 days 1 2
7th floor Camera fit off Day 43 2 days 1 2
8th floor access control panel installation Day 43 completed 28-Jan 1
8th floor access control panel termination Day 43 4 days 1 2 3 4
8th floor access control fit off Day 43 2 days 1 2
8th floor Camera fit off Day 43 2 days 1 2
9th and 10th floor completed access control cable installation, schedule and cable test results Day 47
9th and 10th floor mezzanine completed CCTV cable installation, schedule and cable test results Day 47
Finished walls, ceilings & doors Day 47
9th floor Access control fit off Day 47 2 days 1 2
9th floor Camera fit off Day 47 2 days 1 2
10th floor Access control fit off Day 47 2 days 1 2
10th floor Camera fit off Day 47 2 days 1 2
11th and 12th floor completed access control cable installation, schedule and cable test results Day 53
11th and 12th floor mezzanine completed CCTV cable installation, schedule and cable test results Day 53
Finished walls, ceilings & doors Day 53
11th floor access control panel installation Day 53 completed
11th floor access control panel termination Day 53 4 days 1 2 3 4
11th floor access control fit off Day 53 2 days 1 2
11th floor Camera fit off Day 53 2 days 1 2
12th floor Access control fit off Day 53 2 days 1 2
12th floor Camera fit off Day 53 2 days 1 2
13th and 14th floor completed access control cable installation, schedule and cable test results Day 59
13th and 14th floor mezzanine completed CCTV cable installation, schedule and cable test results Day 59
Finished walls, ceilings & doors Day 59
13th floor Access control fit off Day 59 2 days
13th floor Camera fit off Day 59 2 days 1 2
14th floor access control panel installation Day 59 completed 1 2
14th floor access control panel termination Day 59 4 days 1 2 3 4
14th floor access control fit off Day 59 2 days 1 2
14th floor Camera fit off Day 59 2 days 1 2
15th floor completed access control cable installation, schedule and cable test results Day 65
15th floor mezzanine completed CCTV cable installation, schedule and cable test results Day 65
Finished walls, ceilings & doors Day 65 1 2
15th floor Access control fit off Day 65 2 days 1 2
15th floor Camera fit off Day 65 2 days
Access control training 13-Mar 5 days 1 2 3
Surveillance Training 13-Mar 5 days 1 2 3
Onsite 8-Jan 69 8-Jan 30
Handover 17-Mar 1
Clean power entire site 15-Feb
Air conditioner entire site 15-Feb

41 40 39 38 37 36 35 34 33 32 31 30 29 28 27 26 25 24 23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1

22-Jan
Widus Schedule 21-May 22-May 23-May 24-May 25-May 26-May 27-May 28-May 29-May 30-May 31-May 1-Jun 2-Jun 3-Jun 4-Jun 5-Jun 6-Jun 7-Jun 8-Jun 9-Jun 10-Jun 11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun 1-Jul 2-Jul 3-Jul 4-Jul 5-Jul 6-Jul 7-Jul 8-Jul 9-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 22-Jul 23-Jul 24-Jul 25-Jul 26-Jul
PLAN PLAN Completed PERCENT
ACTIVITY START DURATION day COMPLETE Ccompany Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu
IN DAYS Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day 10 Day 11 Day 12 Day 13 Day 14 Day 15 Day 16 Day 17 Day 18 Day 19 Day 20 Day 21 Day 22 Day 23 Day 24 Day 25 Day 26 Day 27 Day 28 Day 29 Day 30 Day 31 Day 32 Day 33 Day 34 Day 35 Day 36 Day 37 Day 38 Day 39 Day 40 Day 41 Day 42 Day 43 Day 44 Day 45 Day 46 Day 47 Day 48 Day 49 Day 50 Day 51 Day 52 Day 53 Day 54 Day 55 Day 56 Day 57 Day 58 Day 59 Day 60 Day 61 Day 62 Day 63 Day 64 Day 65 Day 66 Day 67
Basement completed access control cable installation, schedule and cable test results Day 1 Others
Basement completed CCTV cable installation, schedule and cable test results Day 1 Others
Finished walls, ceilings & doors Day 1 Others
Secure monitor room Day 1 Others
Monitor room funiture installed Day 1 Others
Monitor room handover to Empire 15 Day 1 Others
Monitor room installation Day 1 4 days 45% Empire
Basement access control panel installation Day 1 Completed Day 1 100% Empire
Basement floor access control panel termination Day 1 Completed Day 1 100% Empire
Basement floor access control fit off Day 1 8 days Day 6 95% Empire 1 2 3 4 5 6 7 8
Basement floor Camera fit off Day 1 8 days Day 6 95% Empire 1 2 3 4 5 6 7 8
Ground floor completed access control cable installation, schedule and cable test results Day 9 Others
Ground floor completed CCTV cable installation, schedule and cable test results Day 9 Others
Finished walls, ceilings & doors Day 9 Others
Ground floor access control panel installation Day 9 Completed 100% Empire
Ground floor access control panel termination Day 9 started 30% Empire
Ground floor access control fit off Day 9 8 days Day 16 0% Empire 1 2 3 4 5 6 7 8
Ground floor Camera fit off Day 9 8 days Day 16 5% Empire 1 2 3 4 5 6 7 8
Ground floor mezzanine completed access control cable installation, schedule and cable test results Day 17 Others
Ground floor mezzanine completed CCTV cable installation, schedule and cable test results Day 17 Others
Finished walls, ceilings & doors Day 17 Others
Server room handed over to Empire Day 17 Others
Rack installation Day 17 1 day Others 1
Server room installation Day 17 14 Days day 28 35% Empire 1 2 3 4 5 6 7 8 9 10 11 12 13 14
Ground floor mezzanine access control panel installation Day 17 completed 100% Empire
Ground floor mezzanine access control panel termination Day 17 6 Days 98% Empire 1 2 3 4 5 6
Ground floor mezzanine access control fit off Day 17 8 days 95% Empire 1 2 3 4 5 6 7 8
Ground floor mezzanine Camera fit off Day 17 completed 100% Empire 1 2 3 4 5 6 7 8
2nd floor completed access control cable installation, schedule and cable test results Day 25 Others
2nd floor completed CCTV cable installation, schedule and cable test results Day 25 Others
Finished walls, ceilings & doors Day 25 Others
2nd floor access control panel installation Day 25 completed 100% Empire
2nd floor access control panel termination Day 25 6 Days 90% Empire 1 2 3 4 5 6
2nd floor access control fit off Day 25 8 days 0% Empire 1 2 3 4 5 6 7 8
2nd floor Camera fit off Day 25 8 days 5% Empire 1 2 3 4 5 6 7 8
3rd and 4th floor completed access control cable installation, schedule and cable test results Day 33 Others
3rd and 4th floor mezzanine completed CCTV cable installation, schedule and cable test results Day 33 Others
Finished walls, ceilings & doors Day 33 Others
3rd floor Access control fit off Day 33 4 days 55% Empire 1 2 3 4
3rd floor Camera fit off Day 33 4 days 100% Empire 1 2 3 4
4th floor Access control fit off Day 33 4 days 50% Empire 1 2 3 4
4th floor Camera fit off Day 33 4 days 80% Empire 1 2 3 4
5th and 6th floor completed access control cable installation, schedule and cable test results Day 37 Others
5th and 6th floor mezzanine completed CCTV cable installation, schedule and cable test results Day 37 Others
Finished walls, ceilings & doors Day 37 Others
5th floor access control panel installation Day 37 completed 100% Empire
5th floor access control panel termination Day 37 4 days 95% Empire 1 2 3 4
5th floor access control fit off Day 37 4 days 70% Empire 1 2 3 4
5th floor Camera fit off Day 37 4 days 70% Empire 1 2 3 4
6th floor Access control fit off Day 37 4 days 0% Empire 1 2 3 4
6th floor Camera fit off Day 37 4 days 40% Empire 1 2 3 4
7th and 8th floor completed access control cable installation, schedule and cable test results Day 41 Others
7th and 8th floor mezzanine completed CCTV cable installation, schedule and cable test results Day 41 Others
Finished walls, ceilings & doors Day 41 Others
7th floor Access control fit off Day 41 4 days 0% Empire 1 2 3 4
7th floor Camera fit off Day 41 4 days 0% Empire 1 2 3 4
8th floor access control panel installation Day 41 completed 28-Jan 100% Empire 1 2 3 4 5 6
8th floor access control panel termination Day 41 6 days 20% Empire 1 2 3 4 5 6
8th floor access control fit off Day 41 4 days Empire 1 2 3 4
8th floor Camera fit off Day 41 4 days 0% Empire 1 2 3 4
9th and 10th floor completed access control cable installation, schedule and cable test results Day 47 Others
9th and 10th floor mezzanine completed CCTV cable installation, schedule and cable test results Day 47 Others
Finished walls, ceilings & doors Day 47 Others
9th floor Access control fit off Day 47 4 days 0% Empire 1 2 3 4
9th floor Camera fit off Day 47 4 days 0% Empire 1 2 3 4
10th floor Access control fit off Day 47 4 days 0% Empire 1 2 3 4
10th floor Camera fit off Day 47 4 days 0% Empire 1 2 3 4
11th and 12th floor completed access control cable installation, schedule and cable test results Day 53 Others
11th and 12th floor mezzanine completed CCTV cable installation, schedule and cable test results Day 53 Others
Finished walls, ceilings & doors Day 53 Others
11th floor access control panel installation Day 53 completed 100% Empire
11th floor access control panel termination Day 53 6 days 0% Empire 1 2 3 4 5 6
11th floor access control fit off Day 53 4 days 0% Empire 1 2 3 4
11th floor Camera fit off Day 53 4 days 0% Empire 1 2 3 4
12th floor Access control fit off Day 53 4 days 0% Empire 1 2 3 4
12th floor Camera fit off Day 53 4 days 0% Empire 1 2 3 4
13th and 14th floor completed access control cable installation, schedule and cable test results Day 59 Others
13th and 14th floor mezzanine completed CCTV cable installation, schedule and cable test results Day 59 Others
Finished walls, ceilings & doors Day 59 Others
13th floor Access control fit off Day 59 4 days 0% Empire 1 2 3 4
13th floor Camera fit off Day 59 24days 0% Empire 1 2 3 4
14th floor access control panel installation Day 59 completed 100% Empire
14th floor access control panel termination Day 59 4 days 0% Empire 1 2 3 4 5 6
14th floor access control fit off Day 59 4 days 0% Empire 1 2 3 4
14th floor Camera fit off Day 59 4 days 0% Empire 1 2 3 4
15th floor completed access control cable installation, schedule and cable test results Day 65 Others
15th floor mezzanine completed CCTV cable installation, schedule and cable test results Day 65 Others
Finished walls, ceilings & doors Day 65 Others
15th floor Access control fit off Day 65 3 days 0% Empire 1 2 3
15th floor Camera fit off Day 65 3 days 0% Empire 1 2 3
Access control training Day 64 4 days 0% Empire 1 2 3 4
Surveillance Training Day 64 4 days 0% Empire 1 2 3 4