PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
4 G02 Update Section 3.1.1, 3.2, 3.8, 5.4.4, 5.4.5, 5.5.1 16 August 2012
HAI SU TRANG & HAI SU DEN
PLATFORM AND PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
TABLE OF CONTENTS
TABLE OF CONTENTS...................................................................................................................... 4
1. INTRODUCTION................................................................................................................................. 8
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
LIST OF TABLES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
LIST OF FIGURES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
1. INTRODUCTION
1.1. General
Petrovietnam Technical Services Corporation, Mechanical and Construction Joint Stock Company (PTSC
M&C) is a Contractor incorporated in the Socialist Republic of Vietnam and having its registered office at No.
31, 30/4 Street, Vung Tau City, the Socialist Republic of Vietnam, hereinafter referred to as “Contractor”.
Thang Long Joint Operating Company plans to award a contract to Contractor for the detailed engineering,
procurement, fabrication, testing, pre-commissioning and onshore commissioning, load out and sea-
fastening, installation and hook-up (hereinafter referred to as “EPCI”) of two platforms and subsea pipelines
for the development of the Hai Su Trang (“HST”) and Hai Su Den (“HSD”) Fields located in Block 15-2/01
offshore the Socialist Republic of Vietnam.
The well-stream product from the HST and HSD Fields will be transported to the Te Giac Trang (“TGT”) H1
WHP, located approximately 3.0 km away from the HST platform adjacent Block 16-1, operated by Hoang
Long Joint Operating Company (“HLJOC”). Thereafter, the HST/HSD well-stream will be commingled with
the TGT well-stream prior to delivery to the TGT FPSO, where the commingled TGT and HST/HSD well-
streams will be processed to produce commingled crude oil and commingled export gas.
Under the EPCI contract, Company requires Contractor to subcontract the offshore transportation and
installation of the HST and HSD platforms and the associated infield subsea pipelines to an experienced
offshore installation company, approved by Company. The terms and conditions of the subcontract shall be
‘back to back’ with the EPCI contract between Company and Contractor.
Block 15-2/01 is geologically located in the Cuu Long Basin relative to the South Eastern coastline of the
Socialist Republic of Vietnam. The HST and HSD Fields are about 120 km east of Vung Tau City, and
separated from each other by approximately 9.0 km, refer Figure 1-2 below.
The project includes:
HST Wellhead Separation Platform (WHSP)
HSD Wellhead Platform (WHP)
Three (3) Pipelines approximately 3.0 km long between the HST WHSP and the TGT H1 platform,
comprising:
o One (1) x 16” dia. Production Pipeline
o One (1) x 8” dia. Water Injection Pipeline
o One (1) x 6” dia. Gas Lift Pipeline
Three (3) Pipelines approximately 9 km long including tie-in spools between HSD WHP and the HST
WHSP, comprising:
o One (1) x 10” dia. Production Pipeline
o One (1) x 6” dia. Water Injection Pipeline
o One (1) x 6” dia. Gas Lift Pipeline
HAI SU TRANG & HAI SU DEN
PLATFORM AND PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
2.5. Units
All information presented herein adopts the International System of Units (SI).
HAI SU TRANG & HAI SU DEN
PLATFORM AND PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
3. GENERAL INFORMATION
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
Coordinate
Facility Design Existing
UTM Geodetic UTM Geodetic
HSD-1X 825 135.800 mE 107 57’ 58.42” E 825 135.320 mE 107 57’ 58.41” E
WHP 1 116 504.600 mN 10 05’ 13.14” N 1 116 500.320 mN 10 05’ 13.00” N
HAI SU TRANG & HAI SU DEN
PLATFORM AND PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
HSD-5X 825 132.260 mE 107 57’ 58.31” E 825 132.060 mE 107 57’ 58.30” E
WHP 1 116 504.600 mN 10 05’ 13.14” N 1 116 500.750 mN 10 05’ 13.01” N
823 663.000 mE 107 57’ 07.53” E
HST WHP - -
1 107 825.000 mN 10 00’ 31.34” N
824 500.000 mE 107 57’ 34.22” E
H1 WHP - -
1 105 200.000 mN 09 59’ 05.74” N
Note: 1) UTM coordinates are based on Datum WGS84, Spheroid WGS84, UTM Zone 48, Northern Hemisphere,
o
Central Meridian (CM) 105 E
2) HSD Jacket location will be constrained by two existing wellhead.
3) HST coordinate reference is centerline of conductor slot #5
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
4. JACKET PRE-INSTALLATION
Note: The minimum BHP’s are then estimated with empiric equation: BHP 100 x BP.
4.3. Transportation
4.3.1. Bollard Pull Requirement
Table 4-2 presents bollard pull requirement that extracted from Ref. R83, R84 and R89 for HSD jacket, HST
Jacket and HSD & HST Piles.
HAI SU TRANG & HAI SU DEN
PLATFORM AND PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
Table 5-1 presents the Jacket and appurtenances installation sequence in a general perspective. Specific
section that detailing step by step of particular main activity is written under dedicated Section on remark
column. The installation sequences are applicable for HSD Jacket and HST Jacket with differences that
described later on.
Remark or
Sequence Main Activity
Reference
1. Jacket pre-installation debris-free survey Section 5.1
2. Castoro Otto preparation for jacket installation Section 5.2
3. Subsea template and docking pile installation Not applicable for
HST Jacket since
Subsea Template
only for HSD (Ref.
R66).
4. Jacket lifting operation Section 5.3.3
Jacket cargo barge mooring alongside Castoro Otto starboard side Section 5.4.1
Jacket pre-lifting inspection Section 5.4.2
Jacket rigging rig-up and seafastening cutting Section 5.4.3
Jacket lifting off cargo barge Section 5.4.4
5. Jacket upending and set down Section 5.4.5
6. Pile installation Section 5.5
7. Jacket leveling Section 5.5.5
8. Crown plate installation Section 5.5.5
9. Pile final cut-off Section 5.5.5
10. Transition piece installation and final cut-off Section 5.8
11. Boatlanding installation Section 5.10
12. Drilling deck installation Section 5.11
13. Miscellaneous activities Section 5.12
Flooding legs and removal flooding system Section 5.12.1
Removal of closure plate on top of jacket leg Section 5.12.2
Post installation survey Section 5.12.5
Removal installation aids on the Jacket Section 5.12.3
Offshore install jacket appurtenances Section 5.12.4
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
Remark or
Sequence Main Activity
Reference
1. Ensure Company approval of jacket seabed location and cleanliness.
2. Prepare JSA and permits for starting operations.
3. Confirm environment conditions are suitable to commence jacket installation Section 3.5, 3.6; Site
and the weather window, refer to forecast, is suitable for duration of the weather forecast.
activity.
4. Prepare mooring lines, spacers and fenders.
5. Confirm anchor spread is fully operational.
6. AHT is ready to perform mooring deployment
7. Position and moor Castoro Otto stand-off position approximately 150 m east Ref. R118 and R119
of jacket target location while Castoro Otto is heading to platform north.
Test Castoro Otto anchoring system.
8. Confirm Sub-contractors have set-up their equipments and ready for the
work:
Survey and positioning services
ROV services
Air diving services
Pile monitoring
Menck hammer control
Welding and NDT
9. Ensure all equipment/materials required for the operation are available and
layout on Castoro Otto deck is correct.
10. Rig up the following main spreads and ensure that the system work properly:
Piling system (hammer, power pack and reeling unit)
ILT system (ILT unit and power pack)
Jacket leveling system (power pack, jacks and reeling unit)
Note: functional test of equipments are also to be performed onshore prior
mobilization.
11. Ballast Castoro Otto for heavy lift draught.
Ballast arrangement will be decide by Castoro Otto Captain at site in order to
optimized the vessel stability throughout operation. This will consider the
actual sea-state condition, existing fluid level in tanks and lifting steps of the
jacket. Install two units 7.5 m fender system at Castoro Otto starboard side.
HAI SU TRANG & HAI SU DEN
PLATFORM AND PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
Remark or
Sequence Main Activity
Reference
1. Prepare sand bag and deploy to template footprint.
2. Deploy diver to seabed
3. Put necessary sand bag at subsea template footprint
5.3.2. Subsea Wellhead Template and Docking Pile Installation and Pile Frame Removal
Table 5-4 – Subsea Wellhead Template and Docking Pile Installation and Pile Frame Removal
Remark or
Sequence Main Activity
Reference
Subsea Template Installation
1. Confirm main tow tug and barge are ready for berthing operations.
2. Confirm AHT is ready in field and briefed on operational requirements.
3. Deploy marine crew to Cargo Barge by work boat. Marine crew to assist
handling of tugger lines as required.
4. Connect tugger lines from AHT to Cargo Barge.
5. With AHT assistance, manoeuvre Cargo Barge along Castoro Otto portside Ref. R130
with Cargo Barge stern to Castoro Otto bow.
6. Once cargo barge is at suitable distance alongside Castoro Otto, pass Ref. R130
mooring lines from Castoro Otto to Cargo Barge and secure the barge at
Castoro Otto portside.
7. Check suitability of weather condition
8. Connect subsea template pre-rigged lifting grommet to Auxiliary hook of Ref. R130, R117
Castoro Otto Clyde crane.
9. Perform cutting of subsea template seafastening. Working crews to move Ref. R130
away at safe distance. Lift subsea template above cargo barge to have
clearance.
10. Swing crane in counter clockwise direction and position subsea on starboard
side.
11. Submerge subsea template and lower it until near seabed.
12. Deploy ROV to monitoring the subsea template set down.
HAI SU TRANG & HAI SU DEN
PLATFORM AND PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
Lifting and stabbing of the subsea wellhead template over the wells will be
monitored by ROV. Transponders on the subsea wellhead template will give
position and ROV will provide the video. ROV will provide video while
stabbing the subsea wellhead template over the wells.
In order to guide the subsea wellhead template deployment into the right
position and orientation, survey equipment will identify and continuously
monitor the location of HSD-1x and 5x as reference.
14. Slack the rigging and check the subsea wellhead template levelness by Ref. R130, Section
monitoring the bull eyes on it. 5.3.1
In addition to the bull eye the divers can perform additional level checks with
spirit level in other corner of the subsea wellhead template.
In case of severe out of levelness than subsea wellhead template will be lifted
and divers to recover the out of levelness with additional sand bags or
removing some.
Note: If the subsea template is not level then procedure in Section 5.3.1 need
to be proceed.
15. Cut sacrificial sling as per Ref. R117 by ROV. Recover Auxiliary hook to Ref. R130, R117
Castoro Otto deck for next operation.
Docking Pile Installation (by Castoro Otto)
16. Cut docking piles seafastening. Ref. R105 (sheet-1,
8) R131
17. Rig-up Clyde Crane Auxiliary hook with ILT and insert ILT to top of docking Ref. R131
pile-1.
18. Rig-up Gantry crane hook to pre-rigged chocker sling on bottom of docking
pile-1.
19. Raise Auxiliary hook and Gantry crane hook simultaneously to have
clearance between cargo barge on to Castoro Otto deck.
20. Move Gantry crane to Clyde crane and maintain Gantry crane hook elevation.
Meanwhile, simultaneously raise Whip hook until docking pile in vertical
position.
21. Slack rigging on Gantry crane and recover rigging from docking pile.
22. Rotate Clyde crane until the pile on top of subsea template position.
23. Submerge docking pile until reach approximately 5.0 m from subsea
template.
HAI SU TRANG & HAI SU DEN
PLATFORM AND PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
The modified shims on the guide cone will ensure that pile is satisfactorily
vertical and in within jacket receiver cone. Therefore, once pile is in self-
penetration it will always be in within tolerance of verticality.
Note: ROV is monitoring the process.
25. Release ILT from docking pile and recover ILT to Castoro Otto deck.
26. Rig-up MHU150S rigging to Auxiliary hook.
27. Swing Clyde crane, lower the hammer and insert to docking pile.
Note: ROV is monitoring the process.
28. Drive docking pile until target penetration.
29. Recover hammer on board Castoro Otto.
30. Redo sequence 16 to 30 for docking pile-2.
Note: After the second Pile has been fully driven, then location and distance
of the top of the two piles needs to be measured and recorded to ensure piles
are installed within tolerances to allow for proper jacket installation stab-over.
This will be done by the divers assistance.
31. The divers cut hole for docking pin and then insert the docking pin Section 5.3.3
Pile Frame Removal (by DSV)
32. Deploy diver to near subsea template.
33. Remove DMR sleeve Ref. R71
Note:
HSD-1x : 18 x 24 mm bolts
HSD-5x : 4 x 24 mm bolts
34. Diver removes bolts on flange connection between pile frame and bottom Ref. R67
frame.
Note: 4 x 30 mm bolts on 4 connections.
35. Rig-up subsea template rigging for recovery to crane main hook. Ref. R117, R131
36. Swing and lower rigging to seabed.
37. Diver to connect rigging on subsea template (i.e. master link) to recovery
rigging.
38. Raise hook to lift pile frame from base frame and recover to DSV deck.
39. Recover diver to DSV deck
Docking Pile “Bullet” Installation (by Castoro Otto)
40. Rig-up Auxiliary hook to docking pile “bullet” by using subsea template rigging Ref. R131
arrangement.
41. Lift and lower it to seabed.
42. Insert docking pile bullet to top of pile.
Note: ROV to monitor the insertion process.
43. ROV hold the ROV friendly hook and open the latch. Pull the hook outside
the “bullet” lifting handle.
HAI SU TRANG & HAI SU DEN
PLATFORM AND PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
Remark or
Sequence Main Activity
Reference
1. Prepare Broco equipments and pile locking pin. Deploy it to near subsea Ref. R68, Ref. R133
template.
2. Deploy divers to subsea wellhead template.
3. Cut holes on subsea template until through the docking pile at two locations Ref. R67, R68, Ref.
on each docking pile. R133
4. Insert the pile locking pin through the holes. Ref. R67, R68, Ref.
Diver cut the pile locking pin extension. R133
5. Recover diver and equipment to Castoro Otto.
Remark or
Sequence Main Activity
Reference
1. Confirm main tow tug and barge are ready for berthing operations.
2. Confirm AHT is ready in field and briefed on operational requirements.
3. Deploy marine crew to Cargo Barge by workboat. Marine crew to assist
handling of tugger lines as required.
4. Connect tugger lines from AHT to Cargo Barge.
5. With AHT assistance, manoeuvre Cargo Barge along Castoro Otto starboard
with Cargo Barge stern to Castoro Otto stern.
6. Once cargo barge is at suitable distance alongside Castoro Otto, pass Ref. R124, R125
mooring lines from Castoro Otto to Cargo Barge and secure the barge at
Castoro Otto Starboard side.
HAI SU TRANG & HAI SU DEN
PLATFORM AND PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
Remark or
Sequence Main Activity
Reference
1. Once the jacket is safely secured, install gangway to connect Castoro Otto
deck to Cargo Barge.
Note: Gangway will be re-inspected prior usage.
2. Scaffolding tower around seafastening of Jacket/Boatlanding/Drill Deck for
cutting access need to be re-inspected and certified by qualified Safety
Officer or competent personnel.
3. MWS, CONTRACTOR & COMPANY to perform jacket pre-lifting inspection.
Ensure cargo barge and all cargoes are intact and in good condition.
Pay particular attention to the following items:
All temporary platforms and walkways are secured as per design drawings. Ref. R101
All riggings and tugger lines are installed with dimension and location as Ref. R98, R110,
per design drawing. R111
4. Re-ensure weather forecast window are suitable for lifting operation. Section 3.5, 3.6; Site
weather forecast.
5. Obtain Approval from MWS and COMPANY to commence jacket
seafastenings cutting and further jacket lifting preparation.
Remark or
Sequence Main Activity
Reference
1. Upon MWS, CONTRACTORS & COMPANY Approval, perform the below
Activity 2 to 10 in parallel.
2. Connect jacket tugger and mooring lines to Castoro Otto as per design Ref. R124, R125
drawing.
3. Set Castoro Otto Clyde Crane at sufficient height over the Jacket Horizontal Ref. R110 (sheet-1),
Rigging R111 (sheet-1)
Rig up lifting slings to Clyde crane Main Hook at two opposite prong. Raise
the hook to a suitable elevation but still maintaining slings slack.
4. Set Castoro Otto Clyde Crane at sufficient height over the Jacket Upending Ref. R110( sheet-2),
Rigging R111 (sheet-2)
Rig up lifting slings to Clyde crane Auxiliary Hook at two opposite prong.
Raise the hook to a suitable elevation but still maintaining slings slack.
5. Ensure the riggings are slack and not entangled/twisted and has enough
clearance to jacket.
6. Cut seafastenings at dedicated offshore cutting lines at El. (-) 42.130 m and Ref. R105 (sheet-4,
El. (-) 8.000 m of Leg-B1 and Leg-B2 1) 5, 6, 7), R107 (sheet-
4, 5, 6, 7)
7. Set Castoro Otto Clyde Crane in Fixed Mode
8. Raise Main hook and tension up to 100 t to recover slack on the main slings.
HAI SU TRANG & HAI SU DEN
PLATFORM AND PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
Remark or
Sequence Main Activity
Reference
1. Raise Main Hook of the Castoro Otto Clyde Crane gradually to increase the HLV stability
tension in the horizontal lifting slings. parameter (e.g. heel,
Keep upending sling attached on Auxiliary Hook in slack condition. trim) and Crane
This operation shall be carried in parallel with the adjustment of Castoro Otto parameter (boom
ballast pattern if and as required by Castoro Otto Master. reach, loading, etc)
can be monitored
from the HLV Bridge.
2. Connect first AHT to bow of Cargo Barge and the second AHT to the stern of Ref. R124, R125
Cargo Barge.
3. Perform final check to see if the Jacket is completely free from seafastening
connection to the cargo barge.
4. Marine crews stand-by on cargo barge for handling/controlling of mooring Ref. R124, R125
lines.
5. Raise Main Hook and lift Jacket to suitable clearance (approx. 5.0 m) from Ref. R124 (sheet-1),
jacket seafastening. R125 (sheet-1)
Dynamic Hook Load = 999.6 t (HSD Jacket).
Dynamic Hook Load = 1056.1 t (HST Jacket).
Once clearance from cargo barge is achieved, unmoor Cargo Barge from
Castoro Otto and relocate her to the Castoro Otto portside for next scope.
6. Lower Jacket into the water, until the jacket is approximately half submerged. Ref. R124 (sheet-2),
Keep the Main Hook at elevation (+) 50.7 m. R125 (sheet-2)
7. Rotate Jacket 90 counterclockwise.
8. Deploy ROV for upending operation assistance to monitor clearance Jacket
and seabed.
9. Raise Auxiliary Hook gradually to increase the tension in the upending lifting
slings.
Keep Main Hook elevation and check clearance for upending sling to Jacket.
10. Raise Auxiliary Hook until Jacket reach 20 pitch angle. Ref. R124 (sheet-3),
Keep Main Hook elevation. R125 (sheet-3)
Main Hook: Dynamic Hook Load = 315.6 t (HSD Jacket).
Auxiliary Hook: Dynamic Hook Load = 294.0 t (HSD Jacket).
Main Hook: Dynamic Hook Load = 258.1 t (HST Jacket).
Auxiliary Hook: Dynamic Hook Load = 309.1 t (HST Jacket).
HAI SU TRANG & HAI SU DEN
PLATFORM AND PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
Remark or
Sequence Main Activity
Reference
1. Deploy ROV to monitoring Jacket set down.
2. Set Auxiliary Hook radius approximately on top of docking pile. Ref. R124 (sheet-4)
3. Lower Auxiliary Hook to have pre-installed docking pile through Jacket Ref. R124 (sheet-4),
docking piles guide until Jacket set down on seabed. Section 5.3
Note: Stabbing process is monitored by ROV.
4. Slack upending rigging and dismantle upending shackles.
5. Flood Jacket legs by operating reach rods. Ref. R04, R90,
Note: Flooding jacket leg is based on Ref. R90. Section 5.12.1
Remark or
Sequence Main Activity
Reference
1. Deploy ROV to monitoring Jacket set down.
2. Deploy positioning personnel to Jacket by accessing ladder. Ref. R101
3. Personnel to come back to Castoro Otto
4. Rotate Jacket to adjust the Jacket heading and adjust Auxiliary Hook and Ref. R125 (sheet-4)
boom radius for jacket position.
5. Lower Auxiliary Hook until Jacket set down on seabed. Ref. R125 (sheet-4),
Note: Set down process is monitored by ROV. Section 5.3
HAI SU TRANG & HAI SU DEN
PLATFORM AND PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
Remark or
Sequence Main Activity
Reference
1. All legs Install riggings and ILT on Pile lead section (P1), handling and Ref. R122, R123,
stabbing to correlated leg. Section 5.5.2
2. All legs Disconnect ILT, Install scaffolding Ref. R122, R123
st
3. All legs Install riggings and ILT on Pile 1 -add on section (P2), Ref. R122, R123,
handling, stabbing to correlated P1, and remove ILT. Section 5.5.2
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
Remark or
Sequence Main Activity
Reference
1. On board of the cargo barge, cut seafastening of piles following the sequence Ref. R108
of installation.
2. Ensure pile pre-rigged chocker slings are correctly positioned on lifting point. Ref. R112, R114
3. Rig-up Clyde Whip hook with ILT and insert ILT to top of pile. Ref. R112, R122
(sheet-1, 2), R114,
R123 (sheet-1, 2)
4. Rig-up Gantry hook to pile pre-rigged chocker sling at bottom of pile.
5. Lift-up simultaneously the pile approximately 7.5 m above Ref. R122 (sheet-1,
barge/seafastening. 2), R123 (sheet-1, 2)
6. Rotate Gantry crane and Clyde crane until the pile above the Castoro Otto
deck.
Note: Keep clearance between pile and Castoro Otto deck.
7. Move gantry crane to the Clyde crane and maintain gantry hook elevation.
Meanwhile, simultaneously raise Whip hook until pile in vertical position.
8. Slack rigging on Gantry crane and recover rigging from pile
9. Rotate Clyde crane until the pile on top of correlated legs.
10. Stab the pile onto jacket leg or onto previous pile.
11. Release and retrieve ILT from pile.
Remark or
Sequence Main Activity
Reference
1. On board of the cargo barge, cut seafastening of piles following the sequence Ref. R108
of installation.
2. Ensure pile pre-rigged chocker grommets are correctly positioned on lifting Ref. R112, R114
point.
3. Rig-up transfer slings to Clyde Whip hook. Ref. R112, R122
(sheet-3), R114,
R123 (sheet-3)
4. Connect transfer slings to pile pre-rigged choker grommets.
5. Lift-up the pile approximately 7.5 m above the barge/seafastening. Ref. R122 (sheet-3),
R123 (sheet-3)
HAI SU TRANG & HAI SU DEN
PLATFORM AND PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
Remark or
Sequence Main Activity
Reference
1. Prepare fit-up equipment i.e. bullets, padeyes and turnbuckles. Ref. R103
2. Tack weld bullet to provide 11 mm gap between piles.
3. Weld padeye on previous pile for about 825 mm from top of pile.
4. Weld padeye on following pile for about 825 mm from bottom of pile.
5. Install turnbuckle and tighten it until piles have uniform gaps.
6. Perform weld and remove bullets before weld completion.
7. Perform NDT after weld completion.
8. Dismantle turnbuckle and remove padeyes.
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
If required weld stoppers on the other piles in order to prevent piles to slide
into the leg while levelling / raising the lowest leg.
3 Set levelling jacks and riggings that connecting cross beam and levelling
padeye.
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
Remark or
Sequence Main Activity
Reference
1. Prepare (grind and 100% MPI/UT) top of jacket legs surface for crown shims NDT Procedure
welding.
2. Conduct final jacket levelness survey. Ref. Section 3.3
3. If the level is out of tolerances, determine jacket leg to be lifted and estimate Ref. Section 3.3
jack stroke required to correct the tilt and continue to sequence 4 to 7,
otherwise continue to sequence 8.
4. Carry out the Jacket reading level check and identify the leg or legs to be
lifted.
st
5. Carry out the marking for the 1 cut off for the installation of the transition
pieces.
6. Grind the pile very well starting from the top of leg in order to permit the
slipping of the crown plates during the jacket lifting. The seam weld as well
has to be grinded off.
7. Grind very well the internal part of the crown plates in order to permit the
slipping during the jacking up of the jacket. Smooth the internal upper and
lower internal corner of the crown plated.
8. Install the crown plates in order to match the dimension of the deck after the
installation of the transition pieces. In the way the pile could be not in the
center if the dimension of the deck requires. Put an 2 mm hammered
electrode between the pile and the crown plate. By the hammered electrode
between the pile and the crown plate we can have a gap 0.5 – 1.0 mm
between the pile and the crown plate. So in this way is minimizing the friction
between crown plate – pile during jacking up.
9. Weld the bottom and vertical parts of the crown plates installed in the 2 nos Ref. R13, R18
legs to be lifted.
10. Install the jacking system of the jacket up to foreseen target. Ref. R100
11. Weld the upper part of the crown plates meanwhile will be installed and Ref. R13, R18
welded the crown plates on the remaining 2 nos legs. The crown plates will
be installed bearing in mind the dimension of the deck (as per sequence 9).
12. Release and recover the jacking system.
HAI SU TRANG & HAI SU DEN
PLATFORM AND PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
Remark or
Sequence Main Activity
Reference
1. Install and set-up the tidal gauge on the suitable position on the jacket
2. Adjust tide recorder to the theoretical datum
3. Measure the LAT/MSL
5.9. Pile Final Cut-off, Transition Piece Installation and Final Cut-off
Table 5-21 – Pile Final Cut-off, Transition Piece Installation and Final Cut-off
Remark or
Sequence Main Activity
Reference
4. Conduct pile final cut-off elevation at El. (+) 9.000 m and mark on the four Ref. R10, R11, R13,
pile. R16
5. Install cutting equipment on the pile and set to marked cutting line.
6. Rig-up Clyde Whip hook with ILT and insert ILT to top of pile.
7. Perform pile cutting and recover to Castoro Otto.
8. Repeat for sequence 2 to 4 for all piles.
9. Perform weld preparation on top of pile by bevel it as per design. Ref. R14, R19
10. Install transition piece installation guide on Jacket. Ref. R102
11. Moor jacket barge along Castoro portside.
12. Cut Transition Piece seafastening rack. Ref. R105, R107
13. Rig-up Clyde Whip hook with rigging and connect to Transition Piece Ref. R102
padeyes.
14. Put rope on Transition Piece for handling.
15. Lift up Transition Piece from seafastening to have clearance.
16. Swing Crane and stab Transition Piece to pile. Use the guide for installation.
17. Repeat for sequence 10 to 13 for remaining Transition Pieces.
Remark or
Sequence Main Activity
Reference
1. Check suitability of weather condition. Section 3.5, 3.6; Site
weather forecast.
HAI SU TRANG & HAI SU DEN
PLATFORM AND PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
Remark or
Sequence Main Activity
Reference
1. Check suitability of weather condition Section 3.5, 3.6; Site
weather forecast.
2. Connect drilling deck pre-rigged lifting slings to the Auxiliary Hook of Castoro Ref. R116, R128,
Otto R129
HAI SU TRANG & HAI SU DEN
PLATFORM AND PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
Remark or
Sequence Main Activity
Reference
1. Transfer personnel to top of Jacket by accessing the ladders. Ref. R101
2. Remove lashing on reach rod handle and safety bolt on disk. Ref. R04, R07
3. Turn the handle to open the valve. Ref. R04, R07
Note: If the handle are difficult to be operated then flooding hose onboard
Castoro Otto flooding spread will be used to flood the jacket legs thru the top
of jacket.
4. Remove flooding reach rods. Reach rods below water level will be done by Ref. R134
Air Diver assistance.
Remark or
Sequence Main Activity
Reference
1. Prepare cutting torch near top of leg. Ref. R06, R09
2. Install rigging on crane hook and connect to pre-installed round bar. Ref. R06, R09
3. Cut the shell plate of jacket leg closure.
HAI SU TRANG & HAI SU DEN
PLATFORM AND PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
PROVISION OF OFFSHORE
TRANSPORTATION AND INSTALLATION
OF THE ‘HST’ AND ‘HSD PLATFORMS AND
PIPELINES
APPENDIX A Castoro Otto clyde Crane Load Chart