Professional Documents
Culture Documents
Commis and Quali
Commis and Quali
June 2017
Introduction
Introduction
References / guidelines
Commissioning Master Plan
Qualification Master Plan
Overview of CQV steps / stages
Commissioning Test Plan – NF Skid
Commissioning Test Protocols – NF Skid
Purpose of the Commission Master Plan is to describe the overall approach for the
commissioning of the facility:
Commissioning and qualification strategy
Risk assessments
Test matrix
Family approach
Leveraging
Need for qualification
Direct Impact vs. Indirect / No Impact
Direct Impact will be commissioned and qualified
Indirect and No Impact equipment systems will be commissioned only
Develop System
Boundaries
NO
Purpose is to describe the overall approach for the qualification of the facility:
Qualification strategy
Direct Impact equipment groups
Demonstration / verification of the design, installation and operation
Testing against the URS
Leveraging strategy
Commissioning Test Protocols which were pre-approved as Q relevant
No critical deviation
Change control in effect
Family approach
Equipment groups of similar designs (size, software, location, etc.)
Testing of one member can support other members
Reduced testing based on risk assessments
Supplier audits
Vendor maintains acceptable quality standards
Assure that suppliers have acceptable support documentation
Risk assessment to identify areas of risk and remediation
System documentation
URS
Risk assessments
Test matrix
Computer System Validation (included in Qualification)
Qualification
Design Qualification (DQ)
Installation Qualification (IQ)
Operation Qualification (OQ)
Performance Qualification (PQ) (by owner)
Qualification Report
System
Classification
Approve
CQMP DQ/DR
Profile
Component
Classification
Planning
Design
Construction
QA
Requirements
Procurement Initial Cals
Loops Commissioning
Package
Construction/
Installation
Project
Simulation/
Commissioning IQ OQ PQ
Offline Testing
Qualification
Owner
IV
FT Validation
RV
SAT
FAT Startup
Approve System- Operations/
level Plans Maintenance
Deficiency List
Deviation List
Post Approval
Commissioning Lead
Process Lead
Qualification Lead
HSE Lead
Verify that the system calculation for differential pressure is correct and meets the
process tolerance
Simulate the process value for the NF inlet and outlet pressure.
P(inlet) = 1.00 Bar
P(outlet) = 0.95 Bar
Confirm that differential pressure displayed on control system is 0.05 Bar
Simulate the process value for the NF inlet and outlet pressure.
P(inlet) = 4.00 Bar
P(outlet) = 0.00 Bar
Confirm that differential pressure displayed on control system is 4.00 Bar
Process tolerance is 0.05 Bar