Pook Alitaptap Billing #4
Pook Alitaptap Billing #4
1 Installation of Panel Boards, Wire Gutter, lot 1 8,700.00 8,700.00 12.43% 0.00% - 0.00% 20.00% 1,740.00 2.49%
Breakers, Wiring & Termination
2 Sub Metering Installation For Each Bamboo Stall sets 9 500.00 4,500.00 6.43% 0.00% - 0.00% 20.00% 900.00 1.29%
3 Wiring Home Run from Panel Board to each lot 1 8,000.00 8,000.00 11.43% 100.00% 8,000.00 11.43% 100.00% 8,000.00 11.43%
Bamboo Stall with mounting panel
Roughing Ins, Wiring & all electrical fixture
4 installation for each Bamboo stall (6 CO & 6 sets 7 2,500.00 17,500.00 25.00% 100.00% 17,500.00 25.00% 100.00% 17,500.00 25.00%
lightings)
5 Completion of wirings of Bamboo Stall & All sets 2 1,000.00 2,000.00 2.86% 100.00% 2,000.00 2.86% 100.00% 2,000.00 2.86%
electrical fixture installation
Wiring for Flood Lights including (7.6 M) steel
6 post erection & 200 watts flood light sets 9 2,700.00 24,300.00 34.71% 100.00% 24,300.00 34.71% 100.00% 24,300.00 34.71%
8 Completion of Clamp Shell CR Feeder Line lot 1 1,000.00 1,000.00 1.43% 100.00% 1,000.00 1.43% 100.00% 1,000.00 1.43%
Installation from Alitaptap Panel Boards
TOTAL 70,000.00 100.00% 56,000.00 80.00% 59,040.00 84.34%
TOTAL COST 3,040.00
Prepared By:
Sylvia S. Imperial
Contractor