JSA # 3 Column Erection
JSA # 3 Column Erection
PPE Inspection Physical Hazards Use of PPES like safety helmet, safety
Goggles, Safety Shoes, Reflective Jackets,
Hand Gloves, safety harness, etc.
Material shifting to its All statutory compliances to be done before
erection location with the Hit by object / material while shifting starting the activity at site (Labour licence,
help of F-15 ESIC/WC policy, PF registration, all related
registers, etc.)
Take necessary work permit before starting
the activity
JSA based tool box meeting should be
conducted before starting the activity.
Material shifting activity should be carried
out in day light only
Do not plan column erection activity during
heavy wind pressure
Ensure and other lifting tool tackles is in
good condition and certified by 3 rd. party
Ensure work should be carried out with
competent supervision only
Deploy skilled and experienced man power
for the task
Ensure all / F-15movement area levelled
and compacted
Road survey to be carried out before
starting the activity
F-15operator should have the valid DL and
competency letter and should be medically
fit.
Stay away from suspended load
Provide tag line (Min- 4m length) while
material shifting
Barricade the working area to prevent
unauthorised entry
Pinch points While applying sling to material do not
keep hand in between material and sling
While material lifting do not put hand in
between gap of two member
Ensure proper wooden packing/ supports
given to material while placing on ground
Crush between Ensure there is sufficient clear space for F-
15 movement
Ensure while operating the F-15, operators
vision is clear
Ensure signal man is in safe place while
movement
Ensure there is sufficient space between
two stacks
Ensure before lifting adjacent material is
stable or is in rigid position
Ensure after shifting the material adjacent
material is in stable condition
Barricade the working area to prevent
unauthorized entry
Topple of F-15 Inspect F-15before starting the activity
Ensure all vehicle (F-15) movement area
levelled and compacted
Before starting the activity road survey to
be carried out
Ensure all vehicle equipment should be
operated by authorized person only
Nobody permitted in operator cabin
excluding operator
Failure of sling All lifting tool/ tackles to be inspected by
competent person before taking in use
Ensure all tool/ tackle free from any type of
damage
Ensure all F-15 movement area levelled
and compacted, to avoid any type of
sudden jerk while movement
Provide rubber packing in between
material and sling to avoid damage to sling
Ensure column weight not exceeding the
SWL of sling
F-15positioning at the Crane will struck due to sludgy condition Ensure all crane movement area should be
erection location of road/ incompact ground surface levelled and compacted
Road survey to be carried out before
starting the activity
Avoid water logging on road
Crush in between Ensure there is sufficient clear space for
crane movement
Ensure while operating the crane operators
vision is clear
Ensure signal man is in safe place while
crane movement
Barricade the working area to prevent
unauthorised entry
Hit to object / person Crane positioning activity should be carried
out in day light only
Ensure all / F-15/ crane movement area
levelled and compacted
Road survey to be carried out before
starting the activity
Crane will be carried out in the guidance of
flag man/ signal man only
Barricade the working area to prevent
unauthorised entry
Electrical hazard Ensure before moving the crane from one
place to other place ensure all electrical
cables routed properly (overhead and
underground)
Keep safe distance from overhead electrical
cables
Crane will be carried out in the guidance of
flag man/ signal man only
Lifting and placing the Hit by member Column erection activity should be going on
column over anchor bolt according to lifting plan only
top with the help of crane Column erection activity should be carried
out in day light only
Do not plan column erection activity in
heavy wind pressure Ensure all F-
15movement area levelled and compacted
Road survey to be carried out before
starting the activity Stay
away from suspended load
Provide tag line (Min- 4m) while material
shifting
Barricade the working area to prevent
unauthorised entry
Pinch points While applying sling to material do not keep
hand in between material and sling
While material positioning do not put hand
in between gap of member
Ensure proper wooden packing/ supports
given to material while positioning
Fall of material from height Do not keep any loose material on height
Ensure all hand tools tied properly, hand
tool tie off system to be implemented
Erection area to be barricaded to restrict
unauthorized entry
Provide sign boards should be provided
Deploy skilled and experienced manpower
to perform the height work
Failure of sling/crane All lifting tool/ tackles to be inspected by
competent person before taking in use
Ensure all tool/ tackle free from any type of
damage
Ensure all / F-15/ crane movement area
levelled and compacted, to avoid any type
of sudden jerk while movement
Provide rubber packing in between material
and sling to avoid damage to sling
Ensure column weight not exceeding the
SWL of sling
Crush in between Ensure there is sufficient clear space for
swing / movement of crane
Ensure while operating the crane operators
vision is clear
Ensure signal man is in safe place while
crane movement
Barricade the working area to prevent
unauthorised entry
Bolting, Guy rope fixing Fall of person from height Fall protection to be provided to working at
and de-slinging by using height , workers should be trained for
boom lift proper use of full body harness with double
lanyard and energy absorber
Workmen will anchor full body safety
harness to boom lift bucket Ensure 100%
full body harness anchorage
Deploy skilled and experienced manpower
for the task, workers are trained for working
at height
Ensure workers are physically/medically fit
for height work
Ensure all boom lift movement area levelled
and compacted to avoid sudden jerk during
operation
Fall of material from height Do not keep any loose material on height
Use only 12 mm dia wire rope for tie the
column
Ensure before deslinging all ( two) guy rope
are fixed properly with rigid structure or peg
angle to give stability to erected column
Ensure all ‘U’ clamp are tightened properly
Ensure all hand tools tied properly, hand
tool tie off system to be implemented
Erection area to be barricaded to restrict
unauthorized entry
Provide sign boards should be provided
Deploy skilled and experienced manpower
to perform the height work task
Topple of boom lift Inspect boom lift before starting the
activity
Ensure all boom lift movement area
levelled and compacted
Before starting the activity road survey to
be carried out
Ensure all vehicle equipment should be
operated by authorized person only
Nobody permitted in operator cabin
excluding operator
Pinch points While applying guy rope to column do not
keep hand in between column and guy rope
While positioning column over anchor bolt
do not put hand in-between gap of pedestal
and column base plate
Ensure proper wooden packing/ supports
given to column while positioning
Cut/scratches due to broken wires of guy Before applying the guy rope to column on
rope ground level visual inspection to be done by
competent person
Use anti cut- type hand gloves while fixing
the guy rope
Note:-
1) Barricade the work Area before start the work.
2) Housekeeping should be always before & after the work.
3) Take All Work Permit before starting the work.
4) Use always recommended PPE’s like Helmet, Goggle & Safety shoes and according to work should be use.
5) Organize scheduled training for the workers.
6) Safety Supervisor should be present always while work is going on.
7) All tools and tackles should be certified.
8) Work related Caution Boards should be displayed at the site.