Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
XXX 618 16-May-19 31-Jan-21 0

PROJECT MILESTONES 0 16-May-19 16-May-19 0 16-May-19, PROJECT MILESTONES


T4-GEN-PM-1000 Receipt of LOI 0 16-May-19 0% 0 Receipt of LOI
T4-GEN-PM-1010 Kick Off Meeting 0 16-May-19 0% 0 Kick Off Meeting

MAJOR MILESTONES 467 18-Oct-19 31-Jan-21 0


T4-GEN-MM-1020 Completion of Engineering 0 18-Oct-19 0% 215 Completion of Engineering
T4-GEN-MM-1050 Completion of MEP Installations for Supremus Floors (B2 to Level 22) (30-Jun-20) 0 30-Jun-20* 0% 0 Completion of MEP Installations fo
T4-GEN-MM1060 MEP Testing & Commissioning of Supremus Floor & Handover (31-Jul-20) 0 31-Jul-20* 0% 1 MEP Testing & Commissionin
T4-GEN-MM1070 Completion of MEP Installations for Excelus Floors (Level 23 to Roof) (31-Dec-20) 0 31-Dec-20* 0% 0 Com
T4-GEN-MM1080 MEP Testing & Commissioning of Entire Building & Handover (31-Jan-21) 0 31-Jan-21* 0% 0
T4-GEN-MM1090 Completion of MEP Installations for CFO Inspection (30-Jun-20) 0 28-Jun-20* 0% 0 Completion of MEP Installations for

SITE MOBILISATION 190 16-May-19 01-Jan-20 86 01-Jan-20, SITE MOBILISATION


T4-GEN-SM-1030 Establishment of Site Office 55 16-May-19 19-Jul-19 0% 86 Establishment of Site Office
T4-GEN-SM-1040 Establishment of Site Stores 40 16-May-19 02-Jul-19 0% 101 Establishment of Site Stores
T4-GEN-SM-1050 Mobilisation of Key Staff 100 20-Jul-19 20-Nov-19 0% 86 Mobilisation of Key Staff
T4-GEN-SM-1060 Deployment of Labour Contractor 90 13-Sep-19 01-Jan-20 0% 86 Deployment of Labour Contractor

DESIGN & ENGINEERING 129 16-May-19 18-Oct-19 309 18-Oct-19, DESIGN & ENGINEERING

CALCULATIONS 45 09-Jul-19 30-Aug-19 187 30-Aug-19, CALCULATIONS


SUBMISSION BY BLUE STAR 38 09-Jul-19 22-Aug-19 187 22-Aug-19, SUBMISSION BY BLUE STAR
T4-EN-CAL-ALL-1000 Submission of Pump Head Calculation (HVAC) 14 09-Jul-19 24-Jul-19 0% 31 Submission of Pump Head Calculation (HVAC)
T4-EN-CAL-ALL-1010 Submission of Lift well Pressurization Calculation (HVAC) 3 25-Jul-19 27-Jul-19 0% 93 Submission of Lift well Pressurization Calculation (HVAC)
T4-EN-CAL-ALL-1020 Submission of Staircase Pressurization Calculation (HVAC) 4 29-Jul-19 01-Aug-19 0% 93 Submission of Staircase Pressurization Calculation (HVAC)
T4-EN-CAL-ALL-1030 Submission of Liftlobby & Corridor Pressurization Calculation (HVAC) 5 02-Aug-19 07-Aug-19 0% 93 Submission of Liftlobby & Corridor Pressurization Calculation (HVAC)
T4-EN-CAL-ALL-1040 Submission of CFD Analysis for Car Park Ventilation (HVAC) 5 08-Aug-19 13-Aug-19 0% 93 Submission of CFD Analysis for Car Park Ventilation (HVAC)
T4-EN-CAL-ALL-1050 Submission of Pump Capacity Calculation (PHE) 7 25-Jul-19 01-Aug-19 0% 67 Submission of Pump Capacity Calculation (PHE)
T4-EN-CAL-ALL-1060 Submission of Water Supply Pipe Size Calculation (PHE) 5 02-Aug-19 07-Aug-19 0% 109 Submission of Water Supply Pipe Size Calculation (PHE)
T4-EN-CAL-ALL-1070 Submission of Pump Capacity Calculation (FF) 7 02-Aug-19 09-Aug-19 0% 102 Submission of Pump Capacity Calculation (FF)
T4-EN-CAL-ALL-1080 Submission of Hydrualic Calculation for Sprinkler System (FF) 5 10-Aug-19 16-Aug-19 0% 102 Submission of Hydrualic Calculation for Sprinkler System (FF)
T4-EN-CAL-ALL-1090 Submission of Orifice plate selection (FF) 5 17-Aug-19 22-Aug-19 0% 187 Submission of Orifice plate selection (FF)
T4-EN-CAL-ALL-1100 Submission of Cable Voltage Drop Calculation (ELE) 7 25-Jul-19 01-Aug-19 0% 31 Submission of Cable Voltage Drop Calculation (ELE)
T4-EN-CAL-ALL-1110 Submission of Discrimination Study (ELE) 5 02-Aug-19 07-Aug-19 0% 130 Submission of Discrimination Study (ELE)
RECEIPT OF APPROVAL FROM LODHA 31 25-Jul-19 30-Aug-19 187 30-Aug-19, RECEIPT OF APPROVAL FROM LODHA
T4-EN-CAL-ALL-1120 Receipt of Approval / Comments on Pump Head Calculation (HVAC) 7 25-Jul-19 01-Aug-19 0% 122 Receipt of Approval / Comments on Pump Head Calculation (HVAC)
T4-EN-CAL-ALL-1130 Receipt of Approval / Comments on Lift well Pressurization Calculation (HVAC) 7 29-Jul-19 05-Aug-19 0% 167 Receipt of Approval / Comments on Lift well Pressurization Calculation (HVAC)
T4-EN-CAL-ALL-1140 Receipt of Approval / Comments on Staircase Pressurization Calculation (HVAC) 7 02-Aug-19 09-Aug-19 0% 163 Receipt of Approval / Comments on Staircase Pressurization Calculation (HVAC)
T4-EN-CAL-ALL-1150 Receipt of Approval / Comments on Liftlobby & Corridor Pressurization Calculation (HVAC) 7 08-Aug-19 16-Aug-19 0% 158 Receipt of Approval / Comments on Liftlobby & Corridor Pressurization Calculation (HVAC)
T4-EN-CAL-ALL-1160 Receipt of Approval / Comments on CFD Analysis for Car Park Ventilation (HVAC) 7 14-Aug-19 22-Aug-19 0% 93 Receipt of Approval / Comments on CFD Analysis for Car Park Ventilation (HVAC)
T4-EN-CAL-ALL-1170 Receipt of Approval / Comments on Pump Capacity Calculation (PHE) 7 02-Aug-19 09-Aug-19 0% 67 Receipt of Approval / Comments on Pump Capacity Calculation (PHE)
T4-EN-CAL-ALL-1180 Receipt of Approval / Comments on Water Supply Pipe Size Calculation (PHE) 7 08-Aug-19 16-Aug-19 0% 109 Receipt of Approval / Comments on Water Supply Pipe Size Calculation (PHE)
T4-EN-CAL-ALL-1190 Receipt of Approval / Comments on Pump Capacity Calculation (FF) 7 10-Aug-19 19-Aug-19 0% 114 Receipt of Approval / Comments on Pump Capacity Calculation (FF)
T4-EN-CAL-ALL-1200 Receipt of Approval / Comments on Hydrualic Calculation for Sprinkler System (FF) 7 17-Aug-19 24-Aug-19 0% 102 Receipt of Approval / Comments on Hydrualic Calculation for Sprinkler System (FF)
T4-EN-CAL-ALL-1210 Receipt of Approval / Comments on Orifice plate selection (FF) 7 23-Aug-19 30-Aug-19 0% 187 Receipt of Approval / Comments on Orifice plate selection (FF)
T4-EN-CAL-ALL-1220 Receipt of Approval / Comments on Cable Voltage Drop Calculation (ELE) 7 02-Aug-19 09-Aug-19 0% 31 Receipt of Approval / Comments on Cable Voltage Drop Calculation (ELE)
T4-EN-CAL-ALL-1230 Receipt of Approval / Comments on Discrimination Study (ELE) 7 08-Aug-19 16-Aug-19 0% 130 Receipt of Approval / Comments on Discrimination Study (ELE)
DRAWING SUBMITTALS 129 16-May-19 18-Oct-19 309 18-Oct-19, DRAWING SUBMITTALS
SUBMISSION BY BLUESTAR 129 16-May-19 18-Oct-19 309 18-Oct-19, SUBMISSION BY BLUESTAR
PHE 107 06-Jun-19 12-Oct-19 313 12-Oct-19, PHE

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 1 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul A Sep Oct N Dec Jan F Mar Apr May J Jul
Float A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
SUBMISSION BY BLUE STAR 100 06-Jun-19 03-Oct-19 313 03-Oct-19, SUBMISSION BY BLUE STAR
T4-EN-LAY-PHE-1100 Submission of Standard Installation Details - Piping 5 03-Jul-19 08-Jul-19 0% 277 Submission of Standard Installation Details - Piping
T4-EN-LAY-PHE-1110 Submission of Schematic for Grey Water System 5 09-Jul-19 13-Jul-19 0% 277 Submission of Schematic for Grey Water System
T4-EN-LAY-PHE-1120 Submission of Schematic for Soil & Waste Water Drainage 5 09-Jul-19 13-Jul-19 0% 277 Submission of Schematic for Soil & Waste Water Drainage
T4-EN-LAY-PHE-1130 Submission of Schematic for Domestic Water System 5 15-Jul-19 19-Jul-19 0% 277 Submission of Schematic for Domestic Water System
T4-EN-LAY-PHE-1140 Submission of Schematic for Rain water Drainage 5 15-Jul-19 19-Jul-19 0% 277 Submission of Schematic for Rain water Drainage
T4-EN-LAY-PHE-1150 Submission of Schematic for Condensate Drain Recovery 5 20-Jul-19 25-Jul-19 0% 277 Submission of Schematic for Condensate Drain Recovery
T4-EN-LAY-PHE-1160 Submission of Schematic for Soft Water System 5 20-Jul-19 25-Jul-19 0% 277 Submission of Schematic for Soft Water System
T4-EN-LAY-PHE-1170 Submission of Plumbing Plant Room Layout at Basement 2 5 09-Jul-19 13-Jul-19 0% 287 Submission of Plumbing Plant Room Layout at Basement 2
T4-EN-LAY-PHE-1180 Submission of Plumbing Layout for Basement 2 5 03-Jul-19 08-Jul-19 0% 208 Submission of Plumbing Layout for Basement 2
T4-EN-LAY-PHE-1190 Submission of Plumbing Layout for Basement 1 5 09-Jul-19 13-Jul-19 0% 182 Submission of Plumbing Layout for Basement 1
T4-EN-LAY-PHE-1200 Submission of Plumbing Layout for Podium P0 4 13-Jul-19 17-Jul-19 0% 217 Submission of Plumbing Layout for Podium P0
T4-EN-LAY-PHE-1210 Submission of Plumbing Layout for Podium P1 5 16-Jul-19 20-Jul-19 0% 229 Submission of Plumbing Layout for Podium P1
T4-EN-LAY-PHE-1220 Submission of Plumbing Layout for Podium P2 4 22-Jul-19 25-Jul-19 0% 83 Submission of Plumbing Layout for Podium P2
T4-EN-LAY-PHE-1230 Submission of Plumbing Layout for Podium P3 5 23-Jul-19 27-Jul-19 0% 224 Submission of Plumbing Layout for Podium P3
T4-EN-LAY-PHE-1240 Submission of Plumbing Layout for Podium P4 5 26-Jul-19 31-Jul-19 0% 221 Submission of Plumbing Layout for Podium P4
T4-EN-LAY-PHE-1250 Submission of Plumbing Layout for Podium P5 4 01-Aug-19 05-Aug-19 0% 217 Submission of Plumbing Layout for Podium P5
T4-EN-LAY-PHE-1260 Submission of Plumbing Layout for Podium P6 to P10 4 06-Aug-19 09-Aug-19 0% 213 Submission of Plumbing Layout for Podium P6 to P10
T4-EN-LAY-PHE-1270 Submission of Plumbing Layout for Mechanical Floor S1 5 09-Aug-19 14-Aug-19 0% 165 Submission of Plumbing Layout for Mechanical Floor S1
T4-EN-LAY-PHE-1280 Submission of Plumbing Layout for Level 09 5 13-Aug-19 19-Aug-19 0% 192 Submission of Plumbing Layout for Level 09
T4-EN-LAY-PHE-1290 Submission of Plumbing Layout for Level 10 to Level 16 (Supremus Floors) 23 06-Jun-19 02-Jul-19 0% 238 Submission of Plumbing Layout for Level 10 to Level 16 (Supremus Floors)
T4-EN-LAY-PHE-1310 Submission of Plumbing Layout for Level 17 17 16-Aug-19 05-Sep-19 0% 158 Submission of Plumbing Layout for Level 17
T4-EN-LAY-PHE-1320 Submission of Plumbing Layout for Level 18 to Level 21 5 19-Aug-19 23-Aug-19 0% 346 Submission of Plumbing Layout for Level 18 to Level 21
T4-EN-LAY-PHE-1330 Submission of Plumbing Layout for Level 22 (Mechanical Floor) 10 20-Aug-19 30-Aug-19 0% 192 Submission of Plumbing Layout for Level 22 (Mechanical Floor)
T4-EN-LAY-PHE-1340 Submission of Plumbing Layout for Level 23 & Level 25 to Level 30 5 29-Aug-19 04-Sep-19 0% 337 Submission of Plumbing Layout for Level 23 & Level 25 to Level 30
T4-EN-LAY-PHE-1350 Submission of Plumbing Layout for Level 24 4 05-Sep-19 09-Sep-19 0% 333 Submission of Plumbing Layout for Level 24
T4-EN-LAY-PHE-1360 Submission of Plumbing Layout for Level 31 5 06-Sep-19 11-Sep-19 0% 331 Submission of Plumbing Layout for Level 31
T4-EN-LAY-PHE-1370 Submission of Plumbing Layout for Level 32 4 10-Sep-19 13-Sep-19 0% 329 Submission of Plumbing Layout for Level 32
T4-EN-LAY-PHE-1390 Submission of Plumbing Layout for Level 33 to Level 35 4 14-Sep-19 18-Sep-19 0% 325 Submission of Plumbing Layout for Level 33 to Level 35
T4-EN-LAY-PHE-1400 Submission of Plumbing Layout for Level 36 5 19-Sep-19 24-Sep-19 0% 320 Submission of Plumbing Layout for Level 36
T4-EN-LAY-PHE-1410 Submission of Plumbing Layout for Level 37 to Level 39 5 23-Sep-19 27-Sep-19 0% 317 Submission of Plumbing Layout for Level 37 to Level 39
T4-EN-LAY-PHE-1420 Submission of Plumbing Layout for Roof 4 28-Sep-19 03-Oct-19 0% 220 Submission of Plumbing Layout for Roof
RECEIPT OF APPROVAL FROM LODHA 84 03-Jul-19 12-Oct-19 313 12-Oct-19, RECEIPT OF APPROVAL FROM LODHA
T4-EN-LAY-PHE-1430 Receipt of Approval / Comments on Standard Installation Details - Piping 7 09-Jul-19 16-Jul-19 0% 292 Receipt of Approval / Comments on Standard Installation Details - Piping
T4-EN-LAY-PHE-1440 Receipt of Approval / Comments on Schematic for Grey Water System 7 15-Jul-19 22-Jul-19 0% 287 Receipt of Approval / Comments on Schematic for Grey Water System
T4-EN-LAY-PHE-1450 Receipt of Approval / Comments on Schematic for Soil & Waste Water Drainage 7 15-Jul-19 22-Jul-19 0% 287 Receipt of Approval / Comments on Schematic for Soil & Waste Water Drainage
T4-EN-LAY-PHE-1460 Receipt of Approval / Comments on Schematic for Domestic Water System 7 20-Jul-19 27-Jul-19 0% 282 Receipt of Approval / Comments on Schematic for Domestic Water System
T4-EN-LAY-PHE-1470 Receipt of Approval / Comments on Schematic for Rain water Drainage 7 20-Jul-19 27-Jul-19 0% 282 Receipt of Approval / Comments on Schematic for Rain water Drainage
T4-EN-LAY-PHE-1480 Receipt of Approval / Comments on Schematic for Condensate Drain Recovery 7 26-Jul-19 02-Aug-19 0% 277 Receipt of Approval / Comments on Schematic for Condensate Drain Recovery
T4-EN-LAY-PHE-1490 Receipt of Approval / Comments on Schematic for Soft Water System 7 26-Jul-19 02-Aug-19 0% 277 Receipt of Approval / Comments on Schematic for Soft Water System
T4-EN-LAY-PHE-1500 Receipt of Approval / Comments on Plumbing Plant Room Layout at Basement Level 2 7 15-Jul-19 22-Jul-19 0% 287 Receipt of Approval / Comments on Plumbing Plant Room Layout at Basement Level 2
T4-EN-LAY-PHE-1510 Receipt of Approval / Comments on Plumbing Layout for Basement 2 7 09-Jul-19 16-Jul-19 0% 208 Receipt of Approval / Comments on Plumbing Layout for Basement 2
T4-EN-LAY-PHE-1520 Receipt of Approval / Comments on Plumbing Layout for Basement 1 7 15-Jul-19 22-Jul-19 0% 182 Receipt of Approval / Comments on Plumbing Layout for Basement 1
T4-EN-LAY-PHE-1530 Receipt of Approval / Comments on Plumbing Layout for Podium P0 7 18-Jul-19 25-Jul-19 0% 217 Receipt of Approval / Comments on Plumbing Layout for Podium P0
T4-EN-LAY-PHE-1540 Receipt of Approval / Comments on Plumbing Layout for Podium P1 7 22-Jul-19 29-Jul-19 0% 229 Receipt of Approval / Comments on Plumbing Layout for Podium P1
T4-EN-LAY-PHE-1550 Receipt of Approval / Comments on Plumbing Layout for Podium P2 7 26-Jul-19 02-Aug-19 0% 83 Receipt of Approval / Comments on Plumbing Layout for Podium P2
T4-EN-LAY-PHE-1560 Receipt of Approval / Comments on Plumbing Layout for Podium P3 7 29-Jul-19 05-Aug-19 0% 224 Receipt of Approval / Comments on Plumbing Layout for Podium P3
T4-EN-LAY-PHE-1570 Receipt of Approval / Comments on Plumbing Layout for Podium P4 7 01-Aug-19 08-Aug-19 0% 221 Receipt of Approval / Comments on Plumbing Layout for Podium P4
T4-EN-LAY-PHE-1580 Receipt of Approval / Comments on Plumbing Layout for Podium P5 7 06-Aug-19 13-Aug-19 0% 217 Receipt of Approval / Comments on Plumbing Layout for Podium P5
T4-EN-LAY-PHE-1590 Receipt of Approval / Comments on Plumbing Layout for Podium P6 to P10 7 10-Aug-19 19-Aug-19 0% 213 Receipt of Approval / Comments on Plumbing Layout for Podium P6 to P10
T4-EN-LAY-PHE-1600 Receipt of Approval / Comments on Plumbing Layout for Mechanical Floor S1 7 16-Aug-19 23-Aug-19 0% 165 Receipt of Approval / Comments on Plumbing Layout for Mechanical Floor S1

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 2 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-EN-LAY-PHE-1610 Receipt of Approval / Comments on Plumbing Layout for Level 09 7 20-Aug-19 27-Aug-19 0% 192 Receipt of Approval / Comments on Plumbing Layout for Level 09
T4-EN-LAY-PHE-1620 Receipt of Approval / Comments on Plumbing Layout for Level 10 to Level 16 (Supremus Floors) 7 03-Jul-19 10-Jul-19 0% 238 Receipt of Approval / Comments on Plumbing Layout for Level 10 to Level 16 (Supremus Floors)
T4-EN-LAY-PHE-1640 Receipt of Approval / Comments on Plumbing Layout for Level 17 7 06-Sep-19 13-Sep-19 0% 158 Receipt of Approval / Comments on Plumbing Layout for Level 17
T4-EN-LAY-PHE-1650 Receipt of Approval / Comments on Plumbing Layout for Level 18 to Level 21 7 24-Aug-19 31-Aug-19 0% 346 Receipt of Approval / Comments on Plumbing Layout for Level 18 to Level 21
T4-EN-LAY-PHE-1660 Receipt of Approval / Comments on Plumbing Layout for Level 22 (Mechanical Floor) 7 31-Aug-19 09-Sep-19 0% 192 Receipt of Approval / Comments on Plumbing Layout for Level 22 (Mechanical Floor)
T4-EN-LAY-PHE-1670 Receipt of Approval / Comments on Plumbing Layout for Level 23 & Level 25 to Level 30 7 05-Sep-19 12-Sep-19 0% 337 Receipt of Approval / Comments on Plumbing Layout for Level 23 & Level 25 to Le
T4-EN-LAY-PHE-1680 Receipt of Approval / Comments on Plumbing Layout for Level 24 7 10-Sep-19 17-Sep-19 0% 333 Receipt of Approval / Comments on Plumbing Layout for Level 24
T4-EN-LAY-PHE-1690 Receipt of Approval / Comments on Plumbing Layout for Level 31 7 12-Sep-19 19-Sep-19 0% 331 Receipt of Approval / Comments on Plumbing Layout for Level 31
T4-EN-LAY-PHE-1700 Receipt of Approval / Comments on Plumbing Layout for Level 32 7 14-Sep-19 21-Sep-19 0% 329 Receipt of Approval / Comments on Plumbing Layout for Level 32
T4-EN-LAY-PHE-1720 Receipt of Approval / Comments on Plumbing Layout for Level 33 to Level 35 7 19-Sep-19 26-Sep-19 0% 325 Receipt of Approval / Comments on Plumbing Layout for Level 33 to Level 35
T4-EN-LAY-PHE-1730 Receipt of Approval / Comments on Plumbing Layout for Level 36 7 25-Sep-19 03-Oct-19 0% 320 Receipt of Approval / Comments on Plumbing Layout for Level 36
T4-EN-LAY-PHE-1740 Receipt of Approval / Comments on Plumbing Layout for Level 37 to Level 39 7 28-Sep-19 07-Oct-19 0% 317 Receipt of Approval / Comments on Plumbing Layout for Level 37 to Level 39
T4-EN-LAY-PHE-1750 Receipt of Approval / Comments on Plumbing Layout for Roof 7 04-Oct-19 12-Oct-19 0% 220 Receipt of Approval / Comments on Plumbing Layout for Roof
FF 107 06-Jun-19 12-Oct-19 308 12-Oct-19, FF
SUBMISSION BY BLUE STAR 100 06-Jun-19 03-Oct-19 308 03-Oct-19, SUBMISSION BY BLUE STAR
T4-EN-LAY-FF-1790 Submission of Standard Installation Details - Fire Fighting 5 03-Jul-19 08-Jul-19 0% 277 Submission of Standard Installation Details - Fire Fighting
T4-EN-LAY-FF-1800 Submission of Schematics for Fire Fighting System 5 03-Jul-19 08-Jul-19 0% 292 Submission of Schematics for Fire Fighting System
T4-EN-LAY-FF-1810 Submission of Fire Fighting Plant Room Layout at Basement 2 5 09-Jul-19 13-Jul-19 0% 287 Submission of Fire Fighting Plant Room Layout at Basement 2
T4-EN-LAY-FF-1820 Submission of Fire Fighting Layout for Basement 2 5 03-Jul-19 08-Jul-19 0% 178 Submission of Fire Fighting Layout for Basement 2
T4-EN-LAY-FF-1830 Submission of Fire Fighting Layout for Basement 1 5 09-Jul-19 13-Jul-19 0% 169 Submission of Fire Fighting Layout for Basement 1
T4-EN-LAY-FF-1840 Submission of Fire Fighting Layout for Podium P0 4 13-Jul-19 17-Jul-19 0% 212 Submission of Fire Fighting Layout for Podium P0
T4-EN-LAY-FF-1850 Submission of Fire Fighting Layout for Podium P1 5 16-Jul-19 20-Jul-19 0% 227 Submission of Fire Fighting Layout for Podium P1
T4-EN-LAY-FF-1860 Submission of Fire Fighting Layout for Podium P2 4 22-Jul-19 25-Jul-19 0% 69 Submission of Fire Fighting Layout for Podium P2
T4-EN-LAY-FF-1870 Submission of Fire Fighting Layout for Podium P3 5 23-Jul-19 27-Jul-19 0% 211 Submission of Fire Fighting Layout for Podium P3
T4-EN-LAY-FF-1880 Submission of Fire Fighting Layout for Podium P4 5 26-Jul-19 31-Jul-19 0% 208 Submission of Fire Fighting Layout for Podium P4
T4-EN-LAY-FF-1890 Submission of Fire Fighting Layout for Podium P5 4 01-Aug-19 05-Aug-19 0% 204 Submission of Fire Fighting Layout for Podium P5
T4-EN-LAY-FF-1900 Submission of Fire Fighting Layout for Podium P6 to P10 4 06-Aug-19 09-Aug-19 0% 196 Submission of Fire Fighting Layout for Podium P6 to P10
T4-EN-LAY-FF-1910 Submission of Fire Fighting Layout for Mechanical Floor S1 5 09-Aug-19 14-Aug-19 0% 184 Submission of Fire Fighting Layout for Mechanical Floor S1
T4-EN-LAY-FF-1920 Submission of Fire Fighting Layout for Level 09 5 13-Aug-19 19-Aug-19 0% 192 Submission of Fire Fighting Layout for Level 09
T4-EN-LAY-FF-1930 Submission of Fire Fighting Layout for Level 10 to Level 16 (Supremus Floors) 23 06-Jun-19 02-Jul-19 0% 238 Submission of Fire Fighting Layout for Level 10 to Level 16 (Supremus Floors)
T4-EN-LAY-FF-1950 Submission of Fire Fighting Layout for Level 17 17 16-Aug-19 05-Sep-19 0% 144 Submission of Fire Fighting Layout for Level 17
T4-EN-LAY-FF-1960 Submission of Fire Fighting Layout for Level 18 to Level 21 5 19-Aug-19 23-Aug-19 0% 341 Submission of Fire Fighting Layout for Level 18 to Level 21
T4-EN-LAY-FF-1970 Submission of Fire Fighting Layout for Level 22 (Mechanical Floor) 10 20-Aug-19 30-Aug-19 0% 192 Submission of Fire Fighting Layout for Level 22 (Mechanical Floor)
T4-EN-LAY-FF-1980 Submission of Fire Fighting Layout for Level 23 & Level 25 to Level 30 5 29-Aug-19 04-Sep-19 0% 332 Submission of Fire Fighting Layout for Level 23 & Level 25 to Level 30
T4-EN-LAY-FF-1990 Submission of Fire Fighting Layout for Level 24 4 05-Sep-19 09-Sep-19 0% 328 Submission of Fire Fighting Layout for Level 24
T4-EN-LAY-FF-2000 Submission of Fire Fighting Layout for Level 31 5 06-Sep-19 11-Sep-19 0% 326 Submission of Fire Fighting Layout for Level 31
T4-EN-LAY-FF-2010 Submission of Fire Fighting Layout for Level 32 4 10-Sep-19 13-Sep-19 0% 324 Submission of Fire Fighting Layout for Level 32
T4-EN-LAY-FF-2030 Submission of Fire Fighting Layout for Level 33 to Level 35 4 14-Sep-19 18-Sep-19 0% 320 Submission of Fire Fighting Layout for Level 33 to Level 35
T4-EN-LAY-FF-2040 Submission of Fire Fighting Layout for Level 36 5 19-Sep-19 24-Sep-19 0% 315 Submission of Fire Fighting Layout for Level 36
T4-EN-LAY-FF-2050 Submission of Fire Fighting Layout for Level 37 to Level 39 5 23-Sep-19 27-Sep-19 0% 312 Submission of Fire Fighting Layout for Level 37 to Level 39
T4-EN-LAY-FF-2060 Submission of Fire Fighting Layout for Roof 4 28-Sep-19 03-Oct-19 0% 220 Submission of Fire Fighting Layout for Roof
T4-EN-LAY-FF-2070 Submission of Fire Fighting Shaft Layout with Modular Supports (Shafts) 10 15-Jun-19 26-Jun-19 0% 217 Submission of Fire Fighting Shaft Layout with Modular Supports (Shafts)
RECEIPT OF APPROVAL FROM LODHA 89 27-Jun-19 12-Oct-19 308 12-Oct-19, RECEIPT OF APPROVAL FROM LODHA
T4-EN-LAY-FF-2080 Receipts of Approval / Comments on Standard Installation Details - Fire Fighting 7 09-Jul-19 16-Jul-19 0% 292 Receipts of Approval / Comments on Standard Installation Details - Fire Fighting
T4-EN-LAY-FF-2090 Receipts of Approval / Comments on Schematics for Fire Fighting System 7 09-Jul-19 16-Jul-19 0% 292 Receipts of Approval / Comments on Schematics for Fire Fighting System
T4-EN-LAY-FF-2100 Receipts of Approval / Comments on Fire Fighting Plant Room Layout at Basement 2 7 15-Jul-19 22-Jul-19 0% 287 Receipts of Approval / Comments on Fire Fighting Plant Room Layout at Basement 2
T4-EN-LAY-FF-2110 Receipts of Approval / Comments on Fire Fighting Layout for Basement 2 7 09-Jul-19 16-Jul-19 0% 178 Receipts of Approval / Comments on Fire Fighting Layout for Basement 2
T4-EN-LAY-FF-2120 Receipts of Approval / Comments on Fire Fighting Layout for Basement 1 7 15-Jul-19 22-Jul-19 0% 169 Receipts of Approval / Comments on Fire Fighting Layout for Basement 1
T4-EN-LAY-FF-2130 Receipts of Approval / Comments on Fire Fighting Layout for Podium P0 7 18-Jul-19 25-Jul-19 0% 212 Receipts of Approval / Comments on Fire Fighting Layout for Podium P0
T4-EN-LAY-FF-2140 Receipts of Approval / Comments on Fire Fighting Layout for Podium P1 7 22-Jul-19 29-Jul-19 0% 227 Receipts of Approval / Comments on Fire Fighting Layout for Podium P1
T4-EN-LAY-FF-2150 Receipts of Approval / Comments on Fire Fighting Layout for Podium P2 7 26-Jul-19 02-Aug-19 0% 69 Receipts of Approval / Comments on Fire Fighting Layout for Podium P2

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 3 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-EN-LAY-FF-2160 Receipts of Approval / Comments on Fire Fighting Layout for Podium P3 7 29-Jul-19 05-Aug-19 0% 211 Receipts of Approval / Comments on Fire Fighting Layout for Podium P3
T4-EN-LAY-FF-2170 Receipts of Approval / Comments on Fire Fighting Layout for Podium P4 7 01-Aug-19 08-Aug-19 0% 208 Receipts of Approval / Comments on Fire Fighting Layout for Podium P4
T4-EN-LAY-FF-2180 Receipts of Approval / Comments on Fire Fighting Layout for Podium P5 7 06-Aug-19 13-Aug-19 0% 204 Receipts of Approval / Comments on Fire Fighting Layout for Podium P5
T4-EN-LAY-FF-2190 Receipts of Approval / Comments on Fire Fighting Layout for Podium P6 to P10 7 10-Aug-19 19-Aug-19 0% 196 Receipts of Approval / Comments on Fire Fighting Layout for Podium P6 to P10
T4-EN-LAY-FF-2200 Receipts of Approval / Comments on Fire Fighting Layout for Mechanical Floor S1 7 16-Aug-19 23-Aug-19 0% 184 Receipts of Approval / Comments on Fire Fighting Layout for Mechanical Floor S1
T4-EN-LAY-FF-2210 Receipts of Approval / Comments on Fire Fighting Layout for Level 09 7 20-Aug-19 27-Aug-19 0% 192 Receipts of Approval / Comments on Fire Fighting Layout for Level 09
T4-EN-LAY-FF-2220 Receipts of Approval / Comments on Fire Fighting Layout for Level 10 to Level 16 (Supremus Floors) 7 03-Jul-19 10-Jul-19 0% 238 Receipts of Approval / Comments on Fire Fighting Layout for Level 10 to Level 16 (Supremus
T4-EN-LAY-FF-2240 Receipts of Approval / Comments on Fire Fighting Layout for Level 17 7 06-Sep-19 13-Sep-19 0% 144 Receipts of Approval / Comments on Fire Fighting Layout for Level 17
T4-EN-LAY-FF-2250 Receipts of Approval / Comments on Fire Fighting Layout for Level 18 to Level 21 7 24-Aug-19 31-Aug-19 0% 341 Receipts of Approval / Comments on Fire Fighting Layout for Level 18 to Level 21
T4-EN-LAY-FF-2260 Receipts of Approval / Comments on Fire Fighting Layout for Level 22 (Mechanical Floor) 7 31-Aug-19 09-Sep-19 0% 192 Receipts of Approval / Comments on Fire Fighting Layout for Level 22 (Mechanical
T4-EN-LAY-FF-2270 Receipts of Approval / Comments on Fire Fighting Layout for Level 23 & Level 25 to Level 30 7 05-Sep-19 12-Sep-19 0% 332 Receipts of Approval / Comments on Fire Fighting Layout for Level 23 & Level 25 t
T4-EN-LAY-FF-2280 Receipts of Approval / Comments on Fire Fighting Layout for Level 24 7 10-Sep-19 17-Sep-19 0% 328 Receipts of Approval / Comments on Fire Fighting Layout for Level 24
T4-EN-LAY-FF-2290 Receipts of Approval / Comments on Fire Fighting Layout for Level 31 7 12-Sep-19 19-Sep-19 0% 326 Receipts of Approval / Comments on Fire Fighting Layout for Level 31
T4-EN-LAY-FF-2300 Receipts of Approval / Comments on Fire Fighting Layout for Level 32 7 14-Sep-19 21-Sep-19 0% 324 Receipts of Approval / Comments on Fire Fighting Layout for Level 32
T4-EN-LAY-FF-2320 Receipts of Approval / Comments on Fire Fighting Layout for Level 33 to Level 35 7 19-Sep-19 26-Sep-19 0% 320 Receipts of Approval / Comments on Fire Fighting Layout for Level 33 to Level 35
T4-EN-LAY-FF-2330 Receipts of Approval / Comments on Fire Fighting Layout for Level 36 7 25-Sep-19 03-Oct-19 0% 315 Receipts of Approval / Comments on Fire Fighting Layout for Level 36
T4-EN-LAY-FF-2340 Receipts of Approval / Comments on Fire Fighting Layout for Level 37 to Level 39 7 28-Sep-19 07-Oct-19 0% 312 Receipts of Approval / Comments on Fire Fighting Layout for Level 37 to Level 39
T4-EN-LAY-FF-2350 Receipts of Approval / Comments on Fire Fighting Layout for Roof 7 04-Oct-19 12-Oct-19 0% 220 Receipts of Approval / Comments on Fire Fighting Layout for Roof
T4-EN-LAY-FF-2360 Receipts of Approval / Comments on Fire Fighting Shaft Layout with Modular Supports (Shafts) 7 27-Jun-19 04-Jul-19 0% 217 Receipts of Approval / Comments on Fire Fighting Shaft Layout with Modular Supports (Shafts)
HVAC 129 16-May-19 18-Oct-19 303 18-Oct-19, HVAC
SUBMISSION BY BLUE STAR 122 16-May-19 10-Oct-19 303 10-Oct-19, SUBMISSION BY BLUE STAR
T4-EN-LAY-HVAC-2100Submission of Standard Installation Details - Chilled Water Piping 5 13-Jun-19 18-Jun-19 0% 309 Submission of Standard Installation Details - Chilled Water Piping
T4-EN-LAY-HVAC-2110Submission of Standard Installation Details - Ducting 5 07-Jun-19 12-Jun-19 0% 309 Submission of Standard Installation Details - Ducting
T4-EN-LAY-HVAC-2120Submission of Schematics for Chilled Water System 18 16-May-19 06-Jun-19 0% 309 Submission of Schematics for Chilled Water System
T4-EN-LAY-HVAC-2130Submission of Schematics for Lift Lobby Pressurization 17 16-May-19 04-Jun-19 0% 31 Submission of Schematics for Lift Lobby Pressurization
T4-EN-LAY-HVAC-2140Submission of Schematics for Lift Well Pressurisation 19 16-May-19 07-Jun-19 0% 217 Submission of Schematics for Lift Well Pressurisation
T4-EN-LAY-HVAC-2150Submission of Schematics for Staircase Pressurisation 3 15-Jun-19 18-Jun-19 0% 309 Submission of Schematics for Staircase Pressurisation
T4-EN-LAY-HVAC-2160Submission of Schematics for HRW 6 08-Jun-19 14-Jun-19 0% 217 Submission of Schematics for HRW
T4-EN-LAY-HVAC-2170Submission of Schematics for Basement Ventilation 6 15-Jun-19 21-Jun-19 0% 306 Submission of Schematics for Basement Ventilation
T4-EN-LAY-HVAC-2180Submission of HVAC Plant Room Layout at Podium 2 5 18-Jul-19 23-Jul-19 0% 279 Submission of HVAC Plant Room Layout at Podium 2
T4-EN-LAY-HVAC-2200Submission of HVAC Layout for Basement 2 5 03-Jul-19 08-Jul-19 0% 31 Submission of HVAC Layout for Basement 2
T4-EN-LAY-HVAC-2210Submission of HVAC Layout for Basement 1 5 09-Jul-19 13-Jul-19 0% 48 Submission of HVAC Layout for Basement 1
T4-EN-LAY-HVAC-2220Submission of HVAC Layout for Podium P0 4 13-Jul-19 17-Jul-19 0% 48 Submission of HVAC Layout for Podium P0
T4-EN-LAY-HVAC-2230Submission of HVAC Layout for Podium P1 5 16-Jul-19 20-Jul-19 0% 48 Submission of HVAC Layout for Podium P1
T4-EN-LAY-HVAC-2240Submission of HVAC Layout for Podium P2 4 22-Jul-19 25-Jul-19 0% 48 Submission of HVAC Layout for Podium P2
T4-EN-LAY-HVAC-2250Submission of HVAC Layout for Podium P3 5 23-Jul-19 27-Jul-19 0% 144 Submission of HVAC Layout for Podium P3
T4-EN-LAY-HVAC-2260Submission of HVAC Layout for Podium P4 5 26-Jul-19 31-Jul-19 0% 144 Submission of HVAC Layout for Podium P4
T4-EN-LAY-HVAC-2270Submission of HVAC Layout for Podium P5 4 01-Aug-19 05-Aug-19 0% 144 Submission of HVAC Layout for Podium P5
T4-EN-LAY-HVAC-2280Submission of HVAC Layout for Podium P6 to P10 4 06-Aug-19 09-Aug-19 0% 144 Submission of HVAC Layout for Podium P6 to P10
T4-EN-LAY-HVAC-2290Submission of HVAC Layout for Mechanical Floor S1 5 09-Aug-19 14-Aug-19 0% 144 Submission of HVAC Layout for Mechanical Floor S1
T4-EN-LAY-HVAC-2300Submission of HVAC Layout for Level 09 5 13-Aug-19 19-Aug-19 0% 144 Submission of HVAC Layout for Level 09
T4-EN-LAY-HVAC-2310Submission of HVAC Layout for Level 10 to Level 16 (Supremus Floors) 23 06-Jun-19 02-Jul-19 0% 31 Submission of HVAC Layout for Level 10 to Level 16 (Supremus Floors)
T4-EN-LAY-HVAC-2330Submission of HVAC Layout for Level 17 5 16-Aug-19 21-Aug-19 0% 144 Submission of HVAC Layout for Level 17
T4-EN-LAY-HVAC-2340Submission of HVAC Layout for Level 18 to Level 21 5 19-Aug-19 23-Aug-19 0% 187 Submission of HVAC Layout for Level 18 to Level 21
T4-EN-LAY-HVAC-2350Submission of HVAC Layout for Level 22 (Mechanical Floor) 10 20-Aug-19 30-Aug-19 0% 187 Submission of HVAC Layout for Level 22 (Mechanical Floor)
T4-EN-LAY-HVAC-2360Submission of HVAC Layout for Level 23 & Level 25 to Level 30 5 29-Aug-19 04-Sep-19 0% 215 Submission of HVAC Layout for Level 23 & Level 25 to Level 30
T4-EN-LAY-HVAC-2370Submission of HVAC Layout for Level 24 4 05-Sep-19 09-Sep-19 0% 215 Submission of HVAC Layout for Level 24
T4-EN-LAY-HVAC-2380Submission of HVAC Layout for Level 31 5 06-Sep-19 11-Sep-19 0% 326 Submission of HVAC Layout for Level 31
T4-EN-LAY-HVAC-2390Submission of HVAC Layout for Level 32 4 10-Sep-19 13-Sep-19 0% 215 Submission of HVAC Layout for Level 32
T4-EN-LAY-HVAC-2410Submission of HVAC Layout for Level 33 to Level 35 4 14-Sep-19 18-Sep-19 0% 215 Submission of HVAC Layout for Level 33 to Level 35
T4-EN-LAY-HVAC-2420Submission of HVAC Layout for Level 36 5 19-Sep-19 24-Sep-19 0% 215 Submission of HVAC Layout for Level 36

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 4 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-EN-LAY-HVAC-2430Submission of HVAC Layout for Level 37 to Level 39 5 23-Sep-19 27-Sep-19 0% 215 Submission of HVAC Layout for Level 37 to Level 39
T4-EN-LAY-HVAC-2440Submission of HVAC Layout for Roof 4 28-Sep-19 03-Oct-19 0% 215 Submission of HVAC Layout for Roof
T4-EN-LAY-HVAC-2450Submission of HVAC Layout for Intermediate Roof 5 04-Oct-19 10-Oct-19 0% 215 Submission of HVAC Layout for Intermediate Roof
T4-EN-LAY-HVAC-2460Submission of HVAC Shaft Layout with Modular Supports (Shafts) 10 15-Jun-19 26-Jun-19 0% 217 Submission of HVAC Shaft Layout with Modular Supports (Shafts)
RECEIPT OF APPROVAL FROM LODHA 112 06-Jun-19 18-Oct-19 303 18-Oct-19, RECEIPT OF APPROVAL FROM LODHA
T4-EN-LAY-HVAC-2470Receipt of Approval / Comments on Standard Installation Details - Chilled Water Piping 7 19-Jun-19 26-Jun-19 0% 309 Receipt of Approval / Comments on Standard Installation Details - Chilled Water Piping
T4-EN-LAY-HVAC-2480Receipt of Approval / Comments on Standard Installation Details - Ducting 7 13-Jun-19 20-Jun-19 0% 314 Receipt of Approval / Comments on Standard Installation Details - Ducting
T4-EN-LAY-HVAC-2490Receipt of Approval / Comments on Schematics for Chilled Water System 7 07-Jun-19 14-Jun-19 0% 319 Receipt of Approval / Comments on Schematics for Chilled Water System
T4-EN-LAY-HVAC-2500Receipt of Approval / Comments on Schematics for Lift Lobby Pressurization 7 06-Jun-19 13-Jun-19 0% 320 Receipt of Approval / Comments on Schematics for Lift Lobby Pressurization
T4-EN-LAY-HVAC-2510Receipt of Approval / Comments on Schematics for Lift Well Pressurisation 7 08-Jun-19 15-Jun-19 0% 318 Receipt of Approval / Comments on Schematics for Lift Well Pressurisation
T4-EN-LAY-HVAC-2520Receipt of Approval / Comments on Schematics for Staircase Pressurisation 7 19-Jun-19 26-Jun-19 0% 309 Receipt of Approval / Comments on Schematics for Staircase Pressurisation
T4-EN-LAY-HVAC-2530Receipt of Approval / Comments on Schematics for HRW 7 15-Jun-19 22-Jun-19 0% 312 Receipt of Approval / Comments on Schematics for HRW
T4-EN-LAY-HVAC-2540Receipt of Approval / Comments on Schematics for Basement Ventilation 7 22-Jun-19 29-Jun-19 0% 306 Receipt of Approval / Comments on Schematics for Basement Ventilation
T4-EN-LAY-HVAC-2550Receipt of Approval / Comments on HVAC Plant Room Layout at Podium 2 7 24-Jul-19 31-Jul-19 0% 279 Receipt of Approval / Comments on HVAC Plant Room Layout at Podium 2
T4-EN-LAY-HVAC-2560Receipt of Approval / Comments on HVAC Layout for Basement 2 7 09-Jul-19 16-Jul-19 0% 185 Receipt of Approval / Comments on HVAC Layout for Basement 2
T4-EN-LAY-HVAC-2570Receipt of Approval / Comments on HVAC Layout for Basement 1 7 15-Jul-19 22-Jul-19 0% 169 Receipt of Approval / Comments on HVAC Layout for Basement 1
T4-EN-LAY-HVAC-2580Receipt of Approval / Comments on HVAC Layout for Podium P0 7 18-Jul-19 25-Jul-19 0% 212 Receipt of Approval / Comments on HVAC Layout for Podium P0
T4-EN-LAY-HVAC-2590Receipt of Approval / Comments on HVAC Layout for Podium P1 7 22-Jul-19 29-Jul-19 0% 229 Receipt of Approval / Comments on HVAC Layout for Podium P1
T4-EN-LAY-HVAC-2600Receipt of Approval / Comments on HVAC Layout for Podium P2 7 26-Jul-19 02-Aug-19 0% 49 Receipt of Approval / Comments on HVAC Layout for Podium P2
T4-EN-LAY-HVAC-2610Receipt of Approval / Comments on HVAC Layout for Podium P3 7 29-Jul-19 05-Aug-19 0% 211 Receipt of Approval / Comments on HVAC Layout for Podium P3
T4-EN-LAY-HVAC-2620Receipt of Approval / Comments on HVAC Layout for Podium P4 7 01-Aug-19 08-Aug-19 0% 208 Receipt of Approval / Comments on HVAC Layout for Podium P4
T4-EN-LAY-HVAC-2630Receipt of Approval / Comments on HVAC Layout for Podium P5 7 06-Aug-19 13-Aug-19 0% 204 Receipt of Approval / Comments on HVAC Layout for Podium P5
T4-EN-LAY-HVAC-2640Receipt of Approval / Comments on HVAC Layout for Podium P6 to P10 7 10-Aug-19 19-Aug-19 0% 191 Receipt of Approval / Comments on HVAC Layout for Podium P6 to P10
T4-EN-LAY-HVAC-2650Receipt of Approval / Comments on HVAC Layout for Mechanical Floor S1 7 16-Aug-19 23-Aug-19 0% 184 Receipt of Approval / Comments on HVAC Layout for Mechanical Floor S1
T4-EN-LAY-HVAC-2660Receipt of Approval / Comments on HVAC Layout for Level 09 7 20-Aug-19 27-Aug-19 0% 192 Receipt of Approval / Comments on HVAC Layout for Level 09
T4-EN-LAY-HVAC-2670Receipt of Approval / Comments on HVAC Layout for Level 10 to Level 16 (Supremus Floors) 7 03-Jul-19 10-Jul-19 0% 238 Receipt of Approval / Comments on HVAC Layout for Level 10 to Level 16 (Supremus Floors)
T4-EN-LAY-HVAC-2680Receipt of Approval / Comments on HVAC Layout for Level 17 7 22-Aug-19 29-Aug-19 0% 156 Receipt of Approval / Comments on HVAC Layout for Level 17
T4-EN-LAY-HVAC-2690Receipt of Approval / Comments on HVAC Layout for Level 18 to Level 21 7 24-Aug-19 31-Aug-19 0% 341 Receipt of Approval / Comments on HVAC Layout for Level 18 to Level 21
T4-EN-LAY-HVAC-2700Receipt of Approval / Comments on HVAC Layout for Level 22 (Mechanical Floor) 7 31-Aug-19 09-Sep-19 0% 210 Receipt of Approval / Comments on HVAC Layout for Level 22 (Mechanical Floor)
T4-EN-LAY-HVAC-2710Receipt of Approval / Comments on HVAC Layout for Level 23 & Level 25 to Level 30 7 05-Sep-19 12-Sep-19 0% 332 Receipt of Approval / Comments on HVAC Layout for Level 23 & Level 25 to Level 30
T4-EN-LAY-HVAC-2720Receipt of Approval / Comments on HVAC Layout for Level 24 7 10-Sep-19 17-Sep-19 0% 328 Receipt of Approval / Comments on HVAC Layout for Level 24
T4-EN-LAY-HVAC-2730Receipt of Approval / Comments on HVAC Layout for Level 31 7 12-Sep-19 19-Sep-19 0% 326 Receipt of Approval / Comments on HVAC Layout for Level 31
T4-EN-LAY-HVAC-2740Receipt of Approval / Comments on HVAC Layout for Level 32 7 14-Sep-19 21-Sep-19 0% 324 Receipt of Approval / Comments on HVAC Layout for Level 32
T4-EN-LAY-HVAC-2750Receipt of Approval / Comments on HVAC Layout for Level 33 to Level 35 7 19-Sep-19 26-Sep-19 0% 320 Receipt of Approval / Comments on HVAC Layout for Level 33 to Level 35
T4-EN-LAY-HVAC-2760Receipt of Approval / Comments on HVAC Layout for Level 36 7 25-Sep-19 03-Oct-19 0% 315 Receipt of Approval / Comments on HVAC Layout for Level 36
T4-EN-LAY-HVAC-2770Receipt of Approval / Comments on HVAC Layout for Level 37 to Level 39 7 28-Sep-19 07-Oct-19 0% 312 Receipt of Approval / Comments on HVAC Layout for Level 37 to Level 39
T4-EN-LAY-HVAC-2780Receipt of Approval / Comments on HVAC Layout for Roof 7 04-Oct-19 12-Oct-19 0% 280 Receipt of Approval / Comments on HVAC Layout for Roof
T4-EN-LAY-HVAC-2790Receipt of Approval / Comments on HVAC Layout for Intermediate Roof 7 11-Oct-19 18-Oct-19 0% 215 Receipt of Approval / Comments on HVAC Layout for Intermediate Roof
T4-EN-LAY-HVAC-2800Receipt of Approval / Comments on HVAC Shaft Layout with Modular Supports (Shafts) 7 27-Jun-19 04-Jul-19 0% 217 Receipt of Approval / Comments on HVAC Shaft Layout with Modular Supports (Shafts)
ELECTRICAL 112 06-Jun-19 18-Oct-19 309 18-Oct-19, ELECTRICAL
SUBMISSION BY BLUE STAR 105 06-Jun-19 10-Oct-19 303 10-Oct-19, SUBMISSION BY BLUE STAR
T4-EN-LAY-ELE-2850 Submission of Typical Installation Details 5 03-Jul-19 08-Jul-19 0% 282 Submission of Typical Installation Details
T4-EN-LAY-ELE-2860 Submission of Lightning Protection Layout 5 09-Jul-19 13-Jul-19 0% 282 Submission of Lightning Protection Layout
T4-EN-LAY-ELE-2870 Submission of Earthing Schematic Diagram 5 15-Jul-19 19-Jul-19 0% 282 Submission of Earthing Schematic Diagram
T4-EN-LAY-ELE-2880 Submission of SLD for Office Areas 5 03-Jul-19 08-Jul-19 0% 272 Submission of SLD for Office Areas
T4-EN-LAY-ELE-2890 Submission of SLD for Common Areas - Electrical 5 09-Jul-19 13-Jul-19 0% 272 Submission of SLD for Common Areas - Electrical
T4-EN-LAY-ELE-2900 Submission of SLD for Common Areas - HVAC Elec. 5 15-Jul-19 19-Jul-19 0% 272 Submission of SLD for Common Areas - HVAC Elec.
T4-EN-LAY-ELE-2910 Submission of SLD for Common Areas - PHE-FPS Elec. 5 20-Jul-19 25-Jul-19 0% 272 Submission of SLD for Common Areas - PHE-FPS Elec.
T4-EN-LAY-ELE-2960 Submission of Electrical Layout of Substation 5 26-Jul-19 31-Jul-19 0% 272 Submission of Electrical Layout of Substation
T4-EN-LAY-ELE-2970 Submission of Cable & Containment Tray Layout For Basement-2 Level 5 03-Jul-19 08-Jul-19 0% 189 Submission of Cable & Containment Tray Layout For Basement-2 Level
T4-EN-LAY-ELE-2980 Submission of Lighting & Power Layout for B2 5 03-Jul-19 08-Jul-19 0% 189 Submission of Lighting & Power Layout for B2

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 5 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
Float
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-EN-LAY-ELE-2990 Submission of Cable & Containment Tray Layout For Basement-1 Level 5 09-Jul-19 13-Jul-19 0% 174 Submission of Cable & Containment Tray Layout For Basement-1 Level
T4-EN-LAY-ELE-3000 Submission of Lighting & Power Layout for B1 5 09-Jul-19 13-Jul-19 0% 174 Submission of Lighting & Power Layout for B1
T4-EN-LAY-ELE-3010 Submission of Cable & Containment Tray Layout For Podium P0 Level 4 13-Jul-19 17-Jul-19 0% 208 Submission of Cable & Containment Tray Layout For Podium P0 Level
T4-EN-LAY-ELE-3020 Submission of Lighting & Power Layout for Podium P0 4 18-Jul-19 22-Jul-19 0% 208 Submission of Lighting & Power Layout for Podium P0
T4-EN-LAY-ELE-3030 Submission of Cable & Containment Tray Layout For Podium P1 Level 5 16-Jul-19 20-Jul-19 0% 227 Submission of Cable & Containment Tray Layout For Podium P1 Level
T4-EN-LAY-ELE-3040 Submission of Lighting & Power Layout for Podium P1 5 16-Jul-19 20-Jul-19 0% 227 Submission of Lighting & Power Layout for Podium P1
T4-EN-LAY-ELE-3050 Submission of Cable & Containment Tray Layout For Podium P2 Level 4 22-Jul-19 25-Jul-19 0% 57 Submission of Cable & Containment Tray Layout For Podium P2 Level
T4-EN-LAY-ELE-3060 Submission of Lighting & Power Layout for Podium P2 4 22-Jul-19 25-Jul-19 0% 57 Submission of Lighting & Power Layout for Podium P2
T4-EN-LAY-ELE-3070 Submission of Cable & Containment Tray Layout For Podium P3 Level 5 23-Jul-19 27-Jul-19 0% 211 Submission of Cable & Containment Tray Layout For Podium P3 Level
T4-EN-LAY-ELE-3080 Submission of Lighting & Power Layout for Podium P3 5 23-Jul-19 27-Jul-19 0% 211 Submission of Lighting & Power Layout for Podium P3
T4-EN-LAY-ELE-3090 Submission of Cable & Containment Tray Layout For Podium P4 Level 5 26-Jul-19 31-Jul-19 0% 208 Submission of Cable & Containment Tray Layout For Podium P4 Level
T4-EN-LAY-ELE-3100 Submission of Lighting & Power Layout for Podium P4 5 26-Jul-19 31-Jul-19 0% 208 Submission of Lighting & Power Layout for Podium P4
T4-EN-LAY-ELE-3110 Submission of Cable & Containment Tray Layout For Podium P5 Level 4 01-Aug-19 05-Aug-19 0% 204 Submission of Cable & Containment Tray Layout For Podium P5 Level
T4-EN-LAY-ELE-3120 Submission of Lighting & Power Layout for Podium P5 4 01-Aug-19 05-Aug-19 0% 204 Submission of Lighting & Power Layout for Podium P5
T4-EN-LAY-ELE-3130 Submission of Cable & Containment Tray Layout For Podium P6 to 10 Level 4 06-Aug-19 09-Aug-19 0% 196 Submission of Cable & Containment Tray Layout For Podium P6 to 10 Level
T4-EN-LAY-ELE-3140 Submission of Lighting & Power Layout for Podium P6 to 10 level 4 06-Aug-19 09-Aug-19 0% 196 Submission of Lighting & Power Layout for Podium P6 to 10 level
T4-EN-LAY-ELE-3150 Submission of Cable & Containment Tray Layout For S1 Mechanical Floor 5 09-Aug-19 14-Aug-19 0% 184 Submission of Cable & Containment Tray Layout For S1 Mechanical Floor
T4-EN-LAY-ELE-3160 Submission of Lighting & Power Layout for S1 Mechanical Floor 5 09-Aug-19 14-Aug-19 0% 184 Submission of Lighting & Power Layout for S1 Mechanical Floor
T4-EN-LAY-ELE-3170 Submission of Cable & Containment Tray Layout For Level 09 5 13-Aug-19 19-Aug-19 0% 192 Submission of Cable & Containment Tray Layout For Level 09
T4-EN-LAY-ELE-3180 Submission of Lighting & Power Layout for Level 09 5 13-Aug-19 19-Aug-19 0% 192 Submission of Lighting & Power Layout for Level 09
T4-EN-LAY-ELE-3190 Submission of Cable & Containment Tray Layout For Level 10 to 16 23 06-Jun-19 02-Jul-19 0% 238 Submission of Cable & Containment Tray Layout For Level 10 to 16
T4-EN-LAY-ELE-3200 Submission of Lighting & Power Layout for Level 10 to 16 23 06-Jun-19 02-Jul-19 0% 238 Submission of Lighting & Power Layout for Level 10 to 16
T4-EN-LAY-ELE-3210 Submission of Cable & Containment Tray Layout For Level 17 17 16-Aug-19 05-Sep-19 0% 144 Submission of Cable & Containment Tray Layout For Level 17
T4-EN-LAY-ELE-3220 Submission of Lighting & Power Layout for Level 17 17 16-Aug-19 05-Sep-19 0% 144 Submission of Lighting & Power Layout for Level 17
T4-EN-LAY-ELE-3230 Submission of Cable & Containment Tray Layout For Level 18 to 21 5 19-Aug-19 23-Aug-19 0% 341 Submission of Cable & Containment Tray Layout For Level 18 to 21
T4-EN-LAY-ELE-3240 Submission of Lighting & Power Layout for Level 18 to 21 5 19-Aug-19 23-Aug-19 0% 341 Submission of Lighting & Power Layout for Level 18 to 21
T4-EN-LAY-ELE-3250 Submission of Cable & Containment Tray Layout For Level 22 10 20-Aug-19 30-Aug-19 0% 187 Submission of Cable & Containment Tray Layout For Level 22
T4-EN-LAY-ELE-3260 Submission of Lighting & Power Layout for Level 22 10 20-Aug-19 30-Aug-19 0% 187 Submission of Lighting & Power Layout for Level 22
T4-EN-LAY-ELE-3270 Submission of Cable & Containment Tray Layout For Level 23 5 29-Aug-19 04-Sep-19 0% 332 Submission of Cable & Containment Tray Layout For Level 23
T4-EN-LAY-ELE-3280 Submission of Lighting & Power Layout for Level 23 5 29-Aug-19 04-Sep-19 0% 332 Submission of Lighting & Power Layout for Level 23
T4-EN-LAY-ELE-3290 Submission of Cable & Containment Tray Layout For Level 24 4 05-Sep-19 09-Sep-19 0% 328 Submission of Cable & Containment Tray Layout For Level 24
T4-EN-LAY-ELE-3300 Submission of Lighting & Power Layout for Level 24 4 05-Sep-19 09-Sep-19 0% 328 Submission of Lighting & Power Layout for Level 24
T4-EN-LAY-ELE-3310 Submission of Cable & Containment Tray Layout For Level 31 5 06-Sep-19 11-Sep-19 0% 326 Submission of Cable & Containment Tray Layout For Level 31
T4-EN-LAY-ELE-3320 Submission of Lighting & Power Layout for Level 31 5 06-Sep-19 11-Sep-19 0% 326 Submission of Lighting & Power Layout for Level 31
T4-EN-LAY-ELE-3330 `Submission of Cable & Containment Tray Layout For Level 32 4 10-Sep-19 13-Sep-19 0% 324 `Submission of Cable & Containment Tray Layout For Level 32
T4-EN-LAY-ELE-3340 Submission of Lighting & Power Layout for Level 32 4 10-Sep-19 13-Sep-19 0% 324 Submission of Lighting & Power Layout for Level 32
T4-EN-LAY-ELE-3350 Submission of Cable & Containment Tray Layout For Level 33 to 35 4 14-Sep-19 18-Sep-19 0% 320 Submission of Cable & Containment Tray Layout For Level 33 to 35
T4-EN-LAY-ELE-3360 Submission of Lighting & Power Layout for Level 33 to 35 4 14-Sep-19 18-Sep-19 0% 320 Submission of Lighting & Power Layout for Level 33 to 35
T4-EN-LAY-ELE-3370 Submission of Cable & Containment Tray Layout For Level 36 5 19-Sep-19 24-Sep-19 0% 315 Submission of Cable & Containment Tray Layout For Level 36
T4-EN-LAY-ELE-3380 Submission of Lighting & Power Layout for Level 36 5 19-Sep-19 24-Sep-19 0% 315 Submission of Lighting & Power Layout for Level 36
T4-EN-LAY-ELE-3390 Submission of Cable & Containment Tray Layout For Level 37 to 39 5 23-Sep-19 27-Sep-19 0% 312 Submission of Cable & Containment Tray Layout For Level 37 to 39
T4-EN-LAY-ELE-3400 Submission of Lighting & Power Layout for Level 37 to 39 5 23-Sep-19 27-Sep-19 0% 312 Submission of Lighting & Power Layout for Level 37 to 39
T4-EN-LAY-ELE-3410 Submission of Cable & Containment Tray Layout For Roof level 4 28-Sep-19 03-Oct-19 0% 274 Submission of Cable & Containment Tray Layout For Roof level
T4-EN-LAY-ELE-3420 Submission of Lighting & Power Layout for Roof level 4 28-Sep-19 03-Oct-19 0% 274 Submission of Lighting & Power Layout for Roof level
T4-EN-LAY-ELE-3430 Submission of Cable & Containment Tray Layout For intermediate Roof level 5 04-Oct-19 10-Oct-19 0% 215 Submission of Cable & Containment Tray Layout For intermediate Roof level
T4-EN-LAY-ELE-3440 Submission of Lighting & Power Layout for intermediate Roof level 5 04-Oct-19 10-Oct-19 0% 215 Submission of Lighting & Power Layout for intermediate Roof level
T4-EN-LAY-ELE-3450 Submission of Cable & Containment Tray Layout For Upper Roof level 5 04-Oct-19 10-Oct-19 0% 215 Submission of Cable & Containment Tray Layout For Upper Roof level
T4-EN-LAY-ELE-3460 Submission of Lighting & Power Layout for upper Roof level 5 04-Oct-19 10-Oct-19 0% 215 Submission of Lighting & Power Layout for upper Roof level
T4-EN-LAY-ELE-3470 Submission of Electrical Shafts Layout with Modular Support 10 15-Jun-19 26-Jun-19 0% 255 Submission of Electrical Shafts Layout with Modular Support
RECEIPT OF APPROVAL FROM LODHA 94 27-Jun-19 18-Oct-19 309 18-Oct-19, RECEIPT OF APPROVAL FROM LODHA
T4-EN-LAY-ELE-3480 Receipt of Approval / Comments on Typical Installation Details 7 09-Jul-19 16-Jul-19 0% 292 Receipt of Approval / Comments on Typical Installation Details

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 6 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
Float
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-EN-LAY-ELE-3490 Receipt of Approval / Comments on Lightning Protection Layout 7 15-Jul-19 22-Jul-19 0% 287 Receipt of Approval / Comments on Lightning Protection Layout
T4-EN-LAY-ELE-3500 Receipt of Approval / Comments on Earthing Schematic Diagram 7 20-Jul-19 27-Jul-19 0% 282 Receipt of Approval / Comments on Earthing Schematic Diagram
T4-EN-LAY-ELE-3510 Receipt of Approval / Comments on SLD for Office Areas 7 09-Jul-19 16-Jul-19 0% 292 Receipt of Approval / Comments on SLD for Office Areas
T4-EN-LAY-ELE-3520 Receipt of Approval / Comments on SLD for Common Areas - Electrical 7 15-Jul-19 22-Jul-19 0% 287 Receipt of Approval / Comments on SLD for Common Areas - Electrical
T4-EN-LAY-ELE-3530 Receipt of Approval / Comments on SLD for Common Areas - HVAC Elec. 7 20-Jul-19 27-Jul-19 0% 282 Receipt of Approval / Comments on SLD for Common Areas - HVAC Elec.
T4-EN-LAY-ELE-3540 Receipt of Approval / Comments on SLD for Common Areas - PHE-FPS Elec. 7 26-Jul-19 02-Aug-19 0% 277 Receipt of Approval / Comments on SLD for Common Areas - PHE-FPS Elec.
T4-EN-LAY-ELE-3590 Receipt of Approval / Comments on Electrical Layout of Substation 7 01-Aug-19 08-Aug-19 0% 272 Receipt of Approval / Comments on Electrical Layout of Substation
T4-EN-LAY-ELE-3600 Receipt of Approval / Comments on Cable & Containment Tray Layout For Basement-2 Level 7 09-Jul-19 16-Jul-19 0% 201 Receipt of Approval / Comments on Cable & Containment Tray Layout For Basement-2 Level
T4-EN-LAY-ELE-3610 Receipt of Approval / Comments on Lighting & Power Layout for B2 7 09-Jul-19 16-Jul-19 0% 189 Receipt of Approval / Comments on Lighting & Power Layout for B2
T4-EN-LAY-ELE-3620 Receipt of Approval / Comments on Cable & Containment Tray Layout For Basement-1 Level 7 15-Jul-19 22-Jul-19 0% 187 Receipt of Approval / Comments on Cable & Containment Tray Layout For Basement-1 Level
T4-EN-LAY-ELE-3630 Receipt of Approval / Comments on Lighting & Power Layout for B1 7 15-Jul-19 22-Jul-19 0% 174 Receipt of Approval / Comments on Lighting & Power Layout for B1
T4-EN-LAY-ELE-3640 Receipt of Approval / Comments on Cable & Containment Tray Layout For Podium P0 Level 7 18-Jul-19 25-Jul-19 0% 218 Receipt of Approval / Comments on Cable & Containment Tray Layout For Podium P0 Level
T4-EN-LAY-ELE-3650 Receipt of Approval / Comments on Lighting & Power Layout for Podium P0 7 23-Jul-19 30-Jul-19 0% 208 Receipt of Approval / Comments on Lighting & Power Layout for Podium P0
T4-EN-LAY-ELE-3660 Receipt of Approval / Comments on Cable & Containment Tray Layout For Podium P1 Level 7 22-Jul-19 29-Jul-19 0% 227 Receipt of Approval / Comments on Cable & Containment Tray Layout For Podium P1 Level
T4-EN-LAY-ELE-3670 Receipt of Approval / Comments on Lighting & Power Layout for Podium P1 7 22-Jul-19 29-Jul-19 0% 227 Receipt of Approval / Comments on Lighting & Power Layout for Podium P1
T4-EN-LAY-ELE-3680 Receipt of Approval / Comments on Cable & Containment Tray Layout For Podium P2 Level 7 26-Jul-19 02-Aug-19 0% 63 Receipt of Approval / Comments on Cable & Containment Tray Layout For Podium P2 Level
T4-EN-LAY-ELE-3690 Receipt of Approval / Comments on Lighting & Power Layout for Podium P2 7 26-Jul-19 02-Aug-19 0% 57 Receipt of Approval / Comments on Lighting & Power Layout for Podium P2
T4-EN-LAY-ELE-3700 Receipt of Approval / Comments on Cable & Containment Tray Layout For Podium P3 Level 7 29-Jul-19 05-Aug-19 0% 217 Receipt of Approval / Comments on Cable & Containment Tray Layout For Podium P3 Level
T4-EN-LAY-ELE-3710 Receipt of Approval / Comments on Lighting & Power Layout for Podium P3 7 29-Jul-19 05-Aug-19 0% 211 Receipt of Approval / Comments on Lighting & Power Layout for Podium P3
T4-EN-LAY-ELE-3720 Receipt of Approval / Comments on Cable & Containment Tray Layout For Podium P4 Level 7 01-Aug-19 08-Aug-19 0% 214 Receipt of Approval / Comments on Cable & Containment Tray Layout For Podium P4 Level
T4-EN-LAY-ELE-3730 Receipt of Approval / Comments on Lighting & Power Layout for Podium P4 7 01-Aug-19 08-Aug-19 0% 208 Receipt of Approval / Comments on Lighting & Power Layout for Podium P4
T4-EN-LAY-ELE-3740 Receipt of Approval / Comments on Cable & Containment Tray Layout For Podium P5 Level 7 06-Aug-19 13-Aug-19 0% 210 Receipt of Approval / Comments on Cable & Containment Tray Layout For Podium P5 Level
T4-EN-LAY-ELE-3750 Receipt of Approval / Comments on Lighting & Power Layout for Podium P5 7 06-Aug-19 13-Aug-19 0% 204 Receipt of Approval / Comments on Lighting & Power Layout for Podium P5
T4-EN-LAY-ELE-3760 Receipt of Approval / Comments on Cable & Containment Tray Layout For Podium P6 to 10 Level 7 10-Aug-19 19-Aug-19 0% 200 Receipt of Approval / Comments on Cable & Containment Tray Layout For Podium P6
T4-EN-LAY-ELE-3770 Receipt of Approval / Comments on Lighting & Power Layout for Podium P6 to 10 level 7 10-Aug-19 19-Aug-19 0% 196 Receipt of Approval / Comments on Lighting & Power Layout for Podium P6 to 10 level
T4-EN-LAY-ELE-3780 Receipt of Approval / Comments on Cable & Containment Tray Layout For S1 Mechanical Floor 7 16-Aug-19 23-Aug-19 0% 184 Receipt of Approval / Comments on Cable & Containment Tray Layout For S1 Mechan
T4-EN-LAY-ELE-3790 Receipt of Approval / Comments on Lighting & Power Layout for S1 Mechanical Floor 7 16-Aug-19 23-Aug-19 0% 184 Receipt of Approval / Comments on Lighting & Power Layout for S1 Mechanical Floor
T4-EN-LAY-ELE-3800 Receipt of Approval / Comments on Cable & Containment Tray Layout For Level 09 7 20-Aug-19 27-Aug-19 0% 192 Receipt of Approval / Comments on Cable & Containment Tray Layout For Level 09
T4-EN-LAY-ELE-3810 Receipt of Approval / Comments on Lighting & Power Layout for Level 09 7 20-Aug-19 27-Aug-19 0% 192 Receipt of Approval / Comments on Lighting & Power Layout for Level 09
T4-EN-LAY-ELE-3820 Receipt of Approval / Comments on Cable & Containment Tray Layout For Level 10 to 16 7 03-Jul-19 10-Jul-19 0% 238 Receipt of Approval / Comments on Cable & Containment Tray Layout For Level 10 to 16
T4-EN-LAY-ELE-3830 Receipt of Approval / Comments on Lighting & Power Layout for Level 10 to 16 7 03-Jul-19 10-Jul-19 0% 238 Receipt of Approval / Comments on Lighting & Power Layout for Level 10 to 16
T4-EN-LAY-ELE-3840 Receipt of Approval / Comments on Cable & Containment Tray Layout For Level 17 7 06-Sep-19 13-Sep-19 0% 150 Receipt of Approval / Comments on Cable & Containment Tray Layout For Level 17
T4-EN-LAY-ELE-3850 Receipt of Approval / Comments on Lighting & Power Layout for Level 17 7 06-Sep-19 13-Sep-19 0% 144 Receipt of Approval / Comments on Lighting & Power Layout for Level 17
T4-EN-LAY-ELE-3860 Receipt of Approval / Comments on Cable & Containment Tray Layout For Level 18 to 21 7 24-Aug-19 31-Aug-19 0% 347 Receipt of Approval / Comments on Cable & Containment Tray Layout For Level 18 to 21
T4-EN-LAY-ELE-3870 Receipt of Approval / Comments on Lighting & Power Layout for Level 18 to 21 7 24-Aug-19 31-Aug-19 0% 341 Receipt of Approval / Comments on Lighting & Power Layout for Level 18 to 21
T4-EN-LAY-ELE-3880 Receipt of Approval / Comments on Cable & Containment Tray Layout For Level 22 7 31-Aug-19 09-Sep-19 0% 193 Receipt of Approval / Comments on Cable & Containment Tray Layout For Level 22
T4-EN-LAY-ELE-3890 Receipt of Approval / Comments on Lighting & Power Layout for Level 22 7 31-Aug-19 09-Sep-19 0% 187 Receipt of Approval / Comments on Lighting & Power Layout for Level 22
T4-EN-LAY-ELE-3900 Receipt of Approval / Comments on Cable & Containment Tray Layout For Level 23 7 05-Sep-19 12-Sep-19 0% 338 Receipt of Approval / Comments on Cable & Containment Tray Layout For Level 23
T4-EN-LAY-ELE-3910 Receipt of Approval / Comments on Lighting & Power Layout for Level 23 7 05-Sep-19 12-Sep-19 0% 332 Receipt of Approval / Comments on Lighting & Power Layout for Level 23
T4-EN-LAY-ELE-3920 Receipt of Approval / Comments on Cable & Containment Tray Layout For Level 24 7 10-Sep-19 17-Sep-19 0% 334 Receipt of Approval / Comments on Cable & Containment Tray Layout For Level 24
T4-EN-LAY-ELE-3930 Receipt of Approval / Comments on Lighting & Power Layout for Level 24 7 10-Sep-19 17-Sep-19 0% 328 Receipt of Approval / Comments on Lighting & Power Layout for Level 24
T4-EN-LAY-ELE-3940 Receipt of Approval / Comments on Cable & Containment Tray Layout For Level 31 7 12-Sep-19 19-Sep-19 0% 332 Receipt of Approval / Comments on Cable & Containment Tray Layout For Level 31
T4-EN-LAY-ELE-3950 Receipt of Approval / Comments on Lighting & Power Layout for Level 31 7 12-Sep-19 19-Sep-19 0% 326 Receipt of Approval / Comments on Lighting & Power Layout for Level 31
T4-EN-LAY-ELE-3960 `Receipt of Approval / Comments on Cable & Containment Tray Layout For Level 32 7 14-Sep-19 21-Sep-19 0% 330 `Receipt of Approval / Comments on Cable & Containment Tray Layout For Level 32
T4-EN-LAY-ELE-3970 Receipt of Approval / Comments on Lighting & Power Layout for Level 32 7 14-Sep-19 21-Sep-19 0% 324 Receipt of Approval / Comments on Lighting & Power Layout for Level 32
T4-EN-LAY-ELE-3980 Receipt of Approval / Comments on Cable & Containment Tray Layout For Level 33 to 35 7 19-Sep-19 26-Sep-19 0% 326 Receipt of Approval / Comments on Cable & Containment Tray Layout For Leve
T4-EN-LAY-ELE-3990 Receipt of Approval / Comments on Lighting & Power Layout for Level 33 to 35 7 19-Sep-19 26-Sep-19 0% 320 Receipt of Approval / Comments on Lighting & Power Layout for Level 33 to 35
T4-EN-LAY-ELE-4000 Receipt of Approval / Comments on Cable & Containment Tray Layout For Level 36 7 25-Sep-19 03-Oct-19 0% 321 Receipt of Approval / Comments on Cable & Containment Tray Layout For Level 36
T4-EN-LAY-ELE-4010 Receipt of Approval / Comments on Lighting & Power Layout for Level 36 7 25-Sep-19 03-Oct-19 0% 315 Receipt of Approval / Comments on Lighting & Power Layout for Level 36
T4-EN-LAY-ELE-4020 Receipt of Approval / Comments on Cable & Containment Tray Layout For Level 37 to 39 7 28-Sep-19 07-Oct-19 0% 318 Receipt of Approval / Comments on Cable & Containment Tray Layout For Lev
T4-EN-LAY-ELE-4030 Receipt of Approval / Comments on Lighting & Power Layout for Level 37 to 39 7 28-Sep-19 07-Oct-19 0% 312 Receipt of Approval / Comments on Lighting & Power Layout for Level 37 to 39

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 7 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-EN-LAY-ELE-4040 Receipt of Approval / Comments on Cable & Containment Tray Layout For Roof level 7 04-Oct-19 12-Oct-19 0% 280 Receipt of Approval / Comments on Cable & Containment Tray Layout For Ro
T4-EN-LAY-ELE-4050 Receipt of Approval / Comments on Lighting & Power Layout for Roof level 7 04-Oct-19 12-Oct-19 0% 274 Receipt of Approval / Comments on Lighting & Power Layout for Roof level
T4-EN-LAY-ELE-4060 Receipt of Approval / Comments on Cable & Containment Tray Layout For intermediate Roof level 7 11-Oct-19 18-Oct-19 0% 215 Receipt of Approval / Comments on Cable & Containment Tray Layout For in
T4-EN-LAY-ELE-4070 Receipt of Approval / Comments on Lighting & Power Layout for intermediate Roof level 7 11-Oct-19 18-Oct-19 0% 215 Receipt of Approval / Comments on Lighting & Power Layout for intermediate
T4-EN-LAY-ELE-4080 Receipt of Approval / Comments on Cable & Containment Tray Layout For Upper Roof level 7 11-Oct-19 18-Oct-19 0% 215 Receipt of Approval / Comments on Cable & Containment Tray Layout For U
T4-EN-LAY-ELE-4090 Receipt of Approval / Comments on Lighting & Power Layout for upper Roof level 7 11-Oct-19 18-Oct-19 0% 215 Receipt of Approval / Comments on Lighting & Power Layout for upper Roof level
T4-EN-LAY-ELE-4100 Receipt of Approval / Comments on Electrical Shafts Layout with Modular Support 7 27-Jun-19 04-Jul-19 0% 255 Receipt of Approval / Comments on Electrical Shafts Layout with Modular Support
COMBINED SERVICES 112 06-Jun-19 18-Oct-19 303 18-Oct-19, COMBINED SERVICES
SUBMISSION BY BLUE STAR 105 06-Jun-19 10-Oct-19 303 10-Oct-19, SUBMISSION BY BLUE STAR
T4-EN-LAY-COM-4120 Submission of CO Layout for Basement 2 5 03-Jul-19 08-Jul-19 0% 185 Submission of CO Layout for Basement 2
T4-EN-LAY-COM-4130 Submission of CO Layout for Basement 1 5 09-Jul-19 13-Jul-19 0% 169 Submission of CO Layout for Basement 1
T4-EN-LAY-COM-4140 Submission of CO Layout for Podium P0 5 13-Jul-19 18-Jul-19 0% 211 Submission of CO Layout for Podium P0
T4-EN-LAY-COM-4150 Submission of CO Layout for Podium P1 5 16-Jul-19 20-Jul-19 0% 229 Submission of CO Layout for Podium P1
T4-EN-LAY-COM-4160 Submission of CO Layout for Podium P2 5 22-Jul-19 26-Jul-19 0% 48 Submission of CO Layout for Podium P2
T4-EN-LAY-COM-4170 Submission of CO Layout for Podium P3 5 23-Jul-19 27-Jul-19 0% 211 Submission of CO Layout for Podium P3
T4-EN-LAY-COM-4180 Submission of CO Layout for Podium P4 5 26-Jul-19 31-Jul-19 0% 208 Submission of CO Layout for Podium P4
T4-EN-LAY-COM-4190 Submission of CO Layout for Podium P5 5 01-Aug-19 06-Aug-19 0% 203 Submission of CO Layout for Podium P5
T4-EN-LAY-COM-4200 Submission of CO Layout for Podium P6 to 10 5 06-Aug-19 10-Aug-19 0% 190 Submission of CO Layout for Podium P6 to 10
T4-EN-LAY-COM-4210 Submission of CO Layout for S1 Mechanical Floor 5 09-Aug-19 14-Aug-19 0% 184 Submission of CO Layout for S1 Mechanical Floor
T4-EN-LAY-COM-4220 Submission of CO Layout for Level 09 5 13-Aug-19 19-Aug-19 0% 192 Submission of CO Layout for Level 09
T4-EN-LAY-COM-4230 Submission of CO Layout for Level 10 to 16 5 06-Jun-19 11-Jun-19 0% 256 Submission of CO Layout for Level 10 to 16
T4-EN-LAY-COM-4240 Submission of Level 10 to 16 Modular Support Layout 5 15-Jun-19 20-Jun-19 0% 242 Submission of Level 10 to 16 Modular Support Layout
T4-EN-LAY-COM-4260 Submission of CO Layout for Level 17 5 16-Aug-19 21-Aug-19 0% 156 Submission of CO Layout for Level 17
T4-EN-LAY-COM-4270 Submission of CO Layout for Level 18 to 21 5 19-Aug-19 23-Aug-19 0% 341 Submission of CO Layout for Level 18 to 21
T4-EN-LAY-COM-4280 Submission of CO Layout for Level 22 5 20-Aug-19 24-Aug-19 0% 215 Submission of CO Layout for Level 22
T4-EN-LAY-COM-4290 Submission of CO Layout for Level 23 5 29-Aug-19 04-Sep-19 0% 332 Submission of CO Layout for Level 23
T4-EN-LAY-COM-4300 Submission of CO Layout for Level 24 5 05-Sep-19 10-Sep-19 0% 327 Submission of CO Layout for Level 24
T4-EN-LAY-COM-4310 Submission of CO Layout for Level 31 5 06-Sep-19 11-Sep-19 0% 326 Submission of CO Layout for Level 31
T4-EN-LAY-COM-4320 Submission of CO Layout for Level 32 5 10-Sep-19 14-Sep-19 0% 323 Submission of CO Layout for Level 32
T4-EN-LAY-COM-4340 Submission of CO Layout for Level 33 to 35 5 14-Sep-19 19-Sep-19 0% 319 Submission of CO Layout for Level 33 to 35
T4-EN-LAY-COM-4350 Submission of CO Layout for Level 36 5 19-Sep-19 24-Sep-19 0% 315 Submission of CO Layout for Level 36
T4-EN-LAY-COM-4360 Submission of CO Layout for Level 37 to 39 5 23-Sep-19 27-Sep-19 0% 312 Submission of CO Layout for Level 37 to 39
T4-EN-LAY-COM-4370 Submission of CO Layout for Intermediate Roof level 5 04-Oct-19 10-Oct-19 0% 215 Submission of CO Layout for Intermediate Roof level
T4-EN-LAY-COM-4380 Submission of Mechanical Shaft CO Layout 5 15-Jun-19 20-Jun-19 0% 222 Submission of Mechanical Shaft CO Layout
T4-EN-LAY-COM-4390 Submission of Modular Support for Mech Shafts 5 15-Jun-19 20-Jun-19 0% 222 Submission of Modular Support for Mech Shafts
RECEIPT OF APPROVAL FROM LODHA 107 12-Jun-19 18-Oct-19 303 18-Oct-19, RECEIPT OF APPROVAL FROM LODHA
T4-EN-LAY-COM-4400 Receipt of Approval / Comments on CO Layout for Basement 2 7 09-Jul-19 16-Jul-19 0% 185 Receipt of Approval / Comments on CO Layout for Basement 2
T4-EN-LAY-COM-4410 Receipt of Approval / Comments on CO Layout for Basement 1 7 15-Jul-19 22-Jul-19 0% 169 Receipt of Approval / Comments on CO Layout for Basement 1
T4-EN-LAY-COM-4420 Receipt of Approval / Comments on CO Layout for Podium P0 7 19-Jul-19 26-Jul-19 0% 211 Receipt of Approval / Comments on CO Layout for Podium P0
T4-EN-LAY-COM-4430 Receipt of Approval / Comments on CO Layout for Podium P1 7 22-Jul-19 29-Jul-19 0% 229 Receipt of Approval / Comments on CO Layout for Podium P1
T4-EN-LAY-COM-4440 Receipt of Approval / Comments on CO Layout for Podium P2 7 27-Jul-19 03-Aug-19 0% 48 Receipt of Approval / Comments on CO Layout for Podium P2
T4-EN-LAY-COM-4450 Receipt of Approval / Comments on CO Layout for Podium P3 7 29-Jul-19 05-Aug-19 0% 211 Receipt of Approval / Comments on CO Layout for Podium P3
T4-EN-LAY-COM-4460 Receipt of Approval / Comments on CO Layout for Podium P4 7 01-Aug-19 08-Aug-19 0% 208 Receipt of Approval / Comments on CO Layout for Podium P4
T4-EN-LAY-COM-4470 Receipt of Approval / Comments on CO Layout for Podium P5 7 07-Aug-19 14-Aug-19 0% 203 Receipt of Approval / Comments on CO Layout for Podium P5
T4-EN-LAY-COM-4480 Receipt of Approval / Comments on CO Layout for Podium P6 to 10 7 12-Aug-19 20-Aug-19 0% 190 Receipt of Approval / Comments on CO Layout for Podium P6 to 10
T4-EN-LAY-COM-4490 Receipt of Approval / Comments on CO Layout for S1 Mechanical Floor 7 16-Aug-19 23-Aug-19 0% 184 Receipt of Approval / Comments on CO Layout for S1 Mechanical Floor
T4-EN-LAY-COM-4500 Receipt of Approval / Comments on CO Layout for Level 09 7 20-Aug-19 27-Aug-19 0% 192 Receipt of Approval / Comments on CO Layout for Level 09
T4-EN-LAY-COM-4510 Receipt of Approval / Comments on CO Layout for Level 10 to 16 7 12-Jun-19 19-Jun-19 0% 256 Receipt of Approval / Comments on CO Layout for Level 10 to 16
T4-EN-LAY-COM-4520 Receipt of Approval / Comments on Level 10 to 16 Modular Support Layout 7 21-Jun-19 28-Jun-19 0% 242 Receipt of Approval / Comments on Level 10 to 16 Modular Support Layout
T4-EN-LAY-COM-4540 Receipt of Approval / Comments on CO Layout for Level 17 7 22-Aug-19 29-Aug-19 0% 156 Receipt of Approval / Comments on CO Layout for Level 17
T4-EN-LAY-COM-4550 Receipt of Approval / Comments on CO Layout for Level 18 to 21 7 24-Aug-19 31-Aug-19 0% 341 Receipt of Approval / Comments on CO Layout for Level 18 to 21

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 8 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-EN-LAY-COM-4560 Receipt of Approval / Comments on CO Layout for Level 22 7 26-Aug-19 03-Sep-19 0% 215 Receipt of Approval / Comments on CO Layout for Level 22
T4-EN-LAY-COM-4570 Receipt of Approval / Comments on CO Layout for Level 23 7 05-Sep-19 12-Sep-19 0% 332 Receipt of Approval / Comments on CO Layout for Level 23
T4-EN-LAY-COM-4580 Receipt of Approval / Comments on CO Layout for Level 24 7 11-Sep-19 18-Sep-19 0% 327 Receipt of Approval / Comments on CO Layout for Level 24
T4-EN-LAY-COM-4590 Receipt of Approval / Comments on CO Layout for Level 31 7 12-Sep-19 19-Sep-19 0% 326 Receipt of Approval / Comments on CO Layout for Level 31
T4-EN-LAY-COM-4600 Receipt of Approval / Comments on CO Layout for Level 32 7 16-Sep-19 23-Sep-19 0% 323 Receipt of Approval / Comments on CO Layout for Level 32
T4-EN-LAY-COM-4620 Receipt of Approval / Comments on CO Layout for Level 33 to 35 7 20-Sep-19 27-Sep-19 0% 319 Receipt of Approval / Comments on CO Layout for Level 33 to 35
T4-EN-LAY-COM-4630 Receipt of Approval / Comments on CO Layout for Level 36 7 25-Sep-19 03-Oct-19 0% 315 Receipt of Approval / Comments on CO Layout for Level 36
T4-EN-LAY-COM-4640 Receipt of Approval / Comments on CO Layout for Level 37 to 39 7 28-Sep-19 07-Oct-19 0% 312 Receipt of Approval / Comments on CO Layout for Level 37 to 39
T4-EN-LAY-COM-4650 Receipt of Approval / Comments on CO Layout for Intermediate Roof level 7 11-Oct-19 18-Oct-19 0% 215 Receipt of Approval / Comments on CO Layout for Intermediate Roof level
T4-EN-LAY-COM-4660 Receipt of Approval / Comments on Mechanical Shaft CO Layout 7 21-Jun-19 28-Jun-19 0% 222 Receipt of Approval / Comments on Mechanical Shaft CO Layout
T4-EN-LAY-COM-4670 Receipt of Approval / Comments on Modular Support for Mech Shafts 7 21-Jun-19 28-Jun-19 0% 222 Receipt of Approval / Comments on Modular Support for Mech Shafts
MATERIAL SUBMITTALS 72 30-May-19 23-Aug-19 245 23-Aug-19, MATERIAL SUBMITTALS
PHE 60 11-Jun-19 20-Aug-19 231 20-Aug-19, PHE
CLASS A 33 12-Jul-19 20-Aug-19 231 20-Aug-19, CLASS A
SUBMISSION 26 12-Jul-19 10-Aug-19 113 10-Aug-19, SUBMISSION
T4-EN-MAS-PHE-1000 Submission of Technical Datasheets of Domestic Water Transfer Pump 6 12-Jul-19 18-Jul-19 0% 63 Submission of Technical Datasheets of Domestic Water Transfer Pump
T4-EN-MAS-PHE-1010 Submission of Technical Datasheets of Grey Water Transfer Pump 5 13-Jul-19 18-Jul-19 0% 63 Submission of Technical Datasheets of Grey Water Transfer Pump
T4-EN-MAS-PHE-1020 Submission of Technical Datasheets of Precharged Air Vessel (300 Ltr) 5 13-Jul-19 18-Jul-19 0% 63 Submission of Technical Datasheets of Precharged Air Vessel (300 Ltr)
T4-EN-MAS-PHE-1030 Submission of Technical Datasheets of Domestic Water Booster Pump 5 13-Jul-19 18-Jul-19 0% 63 Submission of Technical Datasheets of Domestic Water Booster Pump
T4-EN-MAS-PHE-1040 Submission of Technical Datasheets of Grey Water Booster Pump 5 13-Jul-19 18-Jul-19 0% 63 Submission of Technical Datasheets of Grey Water Booster Pump
T4-EN-MAS-PHE-1050 Submission of Technical Datasheets of Precharged Air Vessel for Booster Pumps 5 13-Jul-19 18-Jul-19 0% 63 Submission of Technical Datasheets of Precharged Air Vessel for Booster Pumps
T4-EN-MAS-PHE-1060 Submission of Technical Datasheets of Rain Water Transfer Pump 5 25-Jul-19 30-Jul-19 0% 63 Submission of Technical Datasheets of Rain Water Transfer Pump
T4-EN-MAS-PHE-1070 Submission of Technical Datasheets of Drainage Sump Pump 5 25-Jul-19 30-Jul-19 0% 113 Submission of Technical Datasheets of Drainage Sump Pump
T4-EN-MAS-PHE-1080 Submission of Technical Datasheets of Sewage Sump Pump 5 25-Jul-19 30-Jul-19 0% 113 Submission of Technical Datasheets of Sewage Sump Pump
T4-EN-MAS-PHE-1090 Submission of Technical Datasheets of Electrical Panels 10 31-Jul-19 10-Aug-19 0% 113 Submission of Technical Datasheets of Electrical Panels
APPROVAL 27 19-Jul-19 20-Aug-19 231 20-Aug-19, APPROVAL
T4-EN-MAS-PHE-1100 Approval of Technical Datasheets of Domestic Water Transfer Pump 7 19-Jul-19 26-Jul-19 0% 119 Approval of Technical Datasheets of Domestic Water Transfer Pump
T4-EN-MAS-PHE-1110 Approval of Technical Datasheets of Grey Water Transfer Pump 7 19-Jul-19 26-Jul-19 0% 124 Approval of Technical Datasheets of Grey Water Transfer Pump
T4-EN-MAS-PHE-1120 Approval of Technical Datasheets of Precharged Air Vessel (300 Ltr) 7 19-Jul-19 26-Jul-19 0% 115 Approval of Technical Datasheets of Precharged Air Vessel (300 Ltr)
T4-EN-MAS-PHE-1130 Approval of Technical Datasheets of Domestic Water Booster Pump 7 19-Jul-19 26-Jul-19 0% 251 Approval of Technical Datasheets of Domestic Water Booster Pump
T4-EN-MAS-PHE-1140 Approval of Technical Datasheets of Grey Water Booster Pump 7 19-Jul-19 26-Jul-19 0% 88 Approval of Technical Datasheets of Grey Water Booster Pump
T4-EN-MAS-PHE-1150 Approval of Technical Datasheets of Precharged Air Vessel for Booster Pumps 7 19-Jul-19 26-Jul-19 0% 130 Approval of Technical Datasheets of Precharged Air Vessel for Booster Pumps
T4-EN-MAS-PHE-1160 Approval of Technical Datasheets of Rain Water Transfer Pump 7 31-Jul-19 07-Aug-19 0% 63 Approval of Technical Datasheets of Rain Water Transfer Pump
T4-EN-MAS-PHE-1170 Approval of Technical Datasheets of Drainage Sump Pump 7 31-Jul-19 07-Aug-19 0% 125 Approval of Technical Datasheets of Drainage Sump Pump
T4-EN-MAS-PHE-1180 Approval of Technical Datasheets of Sewage Sump Pump 7 31-Jul-19 07-Aug-19 0% 132 Approval of Technical Datasheets of Sewage Sump Pump
T4-EN-MAS-PHE-1190 Approval of Technical Datasheets of Electrical Panels 7 12-Aug-19 20-Aug-19 0% 113 Approval of Technical Datasheets of Electrical Panels
CLASS B 34 11-Jun-19 19-Jul-19 216 19-Jul-19, CLASS B
SUBMISSION 27 11-Jun-19 11-Jul-19 132 11-Jul-19, SUBMISSION
T4-EN-MAS-PHE-1200 Submission of Technical Datasheets of UPVC Water Supply Pipes 4 17-Jun-19 20-Jun-19 0% 44 Submission of Technical Datasheets of UPVC Water Supply Pipes
T4-EN-MAS-PHE-1210 Submission of Technical Datasheets of CPVC Pipes 5 15-Jun-19 20-Jun-19 0% 44 Submission of Technical Datasheets of CPVC Pipes
T4-EN-MAS-PHE-1220 Submission of Technical Datasheets of Brass Ball Valve 5 15-Jun-19 20-Jun-19 0% 44 Submission of Technical Datasheets of Brass Ball Valve
T4-EN-MAS-PHE-1230 Submission of Technical Datasheets of Auto Air Vent 5 15-Jun-19 20-Jun-19 0% 44 Submission of Technical Datasheets of Auto Air Vent
T4-EN-MAS-PHE-1240 Submission of Technical Datasheets of Float Valve 5 15-Jun-19 20-Jun-19 0% 44 Submission of Technical Datasheets of Float Valve
T4-EN-MAS-PHE-1250 Submission of Technical Datasheets of Pressure Reducing Station 7 20-Jun-19 27-Jun-19 0% 44 Submission of Technical Datasheets of Pressure Reducing Station
T4-EN-MAS-PHE-1260 Submission of Technical Datasheets of FRP Grating & Manhole Covers 5 22-Jun-19 27-Jun-19 0% 144 Submission of Technical Datasheets of FRP Grating & Manhole Covers
T4-EN-MAS-PHE-1270 Submission of Technical Datasheets of UPVC Perforated pipe 5 22-Jun-19 27-Jun-19 0% 144 Submission of Technical Datasheets of UPVC Perforated pipe
T4-EN-MAS-PHE-1280 Submission of Technical Datasheets of CI Butterfly Valve 4 21-Jun-19 25-Jun-19 0% 44 Submission of Technical Datasheets of CI Butterfly Valve
T4-EN-MAS-PHE-1290 Submission of Technical Datasheets of HDPE Pipes 4 21-Jun-19 25-Jun-19 0% 44 Submission of Technical Datasheets of HDPE Pipes
T4-EN-MAS-PHE-1300 Submission of Technical Datasheets of CI Hubless Pipes 4 21-Jun-19 25-Jun-19 0% 44 Submission of Technical Datasheets of CI Hubless Pipes
T4-EN-MAS-PHE-1310 Submission of Technical Datasheets of UPVC SWR & Agri Pipes 4 21-Jun-19 25-Jun-19 0% 44 Submission of Technical Datasheets of UPVC SWR & Agri Pipes
T4-EN-MAS-PHE-1320 Submission of Technical Datasheets of UPVC Low Noise Pipes 4 21-Jun-19 25-Jun-19 0% 44 Submission of Technical Datasheets of UPVC Low Noise Pipes
T4-EN-MAS-PHE-1330 Submission of Technical Datasheets of Nitrile Rubber Insulation 4 28-Jun-19 02-Jul-19 0% 44 Submission of Technical Datasheets of Nitrile Rubber Insulation

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 9 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul A Sep Oct N Dec Jan F Mar Apr May J Jul
Float A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-EN-MAS-PHE-1340 Submission of Technical Datasheets of UPVC Traps 5 27-Jun-19 02-Jul-19 0% 44 Submission of Technical Datasheets of UPVC Traps
T4-EN-MAS-PHE-1350 Submission of Technical Datasheets of Rain Water Head 5 27-Jun-19 02-Jul-19 0% 44 Submission of Technical Datasheets of Rain Water Head
T4-EN-MAS-PHE-1360 Submission of Technical Datasheets of GI Pipes (Class B & C) 5 11-Jun-19 15-Jun-19 0% 0 Submission of Technical Datasheets of GI Pipes (Class B & C)
T4-EN-MAS-PHE-1370 Submission of Technical Datasheets of Grooved Coupling (Rigid & Flexible) 5 17-Jun-19 21-Jun-19 0% 128 Submission of Technical Datasheets of Grooved Coupling (Rigid & Flexible)
T4-EN-MAS-PHE-1380 Submission of Technical Datasheets of Motorised Butterfly Valve 5 01-Jul-19 05-Jul-19 0% 44 Submission of Technical Datasheets of Motorised Butterfly Valve
T4-EN-MAS-PHE-1390 Submission of Technical Datasheets of Water Hammer Arrestor 5 01-Jul-19 05-Jul-19 0% 44 Submission of Technical Datasheets of Water Hammer Arrestor
T4-EN-MAS-PHE-1400 Submission of Technical Datasheets of Check Valve 5 01-Jul-19 05-Jul-19 0% 44 Submission of Technical Datasheets of Check Valve
T4-EN-MAS-PHE-1410 Submission of Technical Datasheets of Y Type Strainer 5 01-Jul-19 05-Jul-19 0% 44 Submission of Technical Datasheets of Y Type Strainer
T4-EN-MAS-PHE-1420 Submission of Technical Datasheets of Flexible Rubber Connector 5 01-Jul-19 05-Jul-19 0% 44 Submission of Technical Datasheets of Flexible Rubber Connector
T4-EN-MAS-PHE-1430 Submission of Technical Datasheets of Pressure Gauge 5 01-Jul-19 05-Jul-19 0% 44 Submission of Technical Datasheets of Pressure Gauge
T4-EN-MAS-PHE-1440 Submission of Technical Datasheets of Water Level Sensor 5 04-Jul-19 09-Jul-19 0% 44 Submission of Technical Datasheets of Water Level Sensor
T4-EN-MAS-PHE-1450 Submission of Technical Datasheets of Level Indicator / Glass Tube Manometer 5 04-Jul-19 09-Jul-19 0% 44 Submission of Technical Datasheets of Level Indicator / Glass Tube Manometer
T4-EN-MAS-PHE-1460 Submission of Technical Datasheets of UPVC Bib Tap (AHU Rooms) 5 04-Jul-19 09-Jul-19 0% 63 Submission of Technical Datasheets of UPVC Bib Tap (AHU Rooms)
T4-EN-MAS-PHE-1470 Submission of Technical Datasheets of Mechanical Type Water Meter 5 04-Jul-19 09-Jul-19 0% 63 Submission of Technical Datasheets of Mechanical Type Water Meter
T4-EN-MAS-PHE-1480 Submission of Technical Datasheets of DI Pipes 5 06-Jul-19 11-Jul-19 0% 63 Submission of Technical Datasheets of DI Pipes
T4-EN-MAS-PHE-1780 Submission of Technical Datasheets of FRP Step Ladder 5 06-Jul-19 11-Jul-19 0% 63 Submission of Technical Datasheets of FRP Step Ladder
APPROVAL 29 17-Jun-19 19-Jul-19 216 19-Jul-19, APPROVAL
T4-EN-MAS-PHE-1490 Approval of Technical Datasheets of UPVC Water Supply Pipes 7 21-Jun-19 28-Jun-19 0% 150 Approval of Technical Datasheets of UPVC Water Supply Pipes
T4-EN-MAS-PHE-1500 Approval of Technical Datasheets of CPVC Pipes 7 21-Jun-19 28-Jun-19 0% 150 Approval of Technical Datasheets of CPVC Pipes
T4-EN-MAS-PHE-1510 Approval of Technical Datasheets of Brass Ball Valve 7 21-Jun-19 28-Jun-19 0% 150 Approval of Technical Datasheets of Brass Ball Valve
T4-EN-MAS-PHE-1520 Approval of Technical Datasheets of Auto Air Vent 7 21-Jun-19 28-Jun-19 0% 150 Approval of Technical Datasheets of Auto Air Vent
T4-EN-MAS-PHE-1530 Approval of Technical Datasheets of Float Valve 7 21-Jun-19 28-Jun-19 0% 150 Approval of Technical Datasheets of Float Valve
T4-EN-MAS-PHE-1540 Approval of Technical Datasheets of Pressure Reducing Station 7 28-Jun-19 05-Jul-19 0% 144 Approval of Technical Datasheets of Pressure Reducing Station
T4-EN-MAS-PHE-1550 Approval of Technical Datasheets of FRP Grating & Manhole Covers 7 28-Jun-19 05-Jul-19 0% 144 Approval of Technical Datasheets of FRP Grating & Manhole Covers
T4-EN-MAS-PHE-1560 Approval of Technical Datasheets of UPVC Perforated pipe 7 28-Jun-19 05-Jul-19 0% 144 Approval of Technical Datasheets of UPVC Perforated pipe
T4-EN-MAS-PHE-1570 Approval of Technical Datasheets of CI Butterfly Valve 7 26-Jun-19 03-Jul-19 0% 146 Approval of Technical Datasheets of CI Butterfly Valve
T4-EN-MAS-PHE-1580 Approval of Technical Datasheets of HDPE Pipes 7 26-Jun-19 03-Jul-19 0% 146 Approval of Technical Datasheets of HDPE Pipes
T4-EN-MAS-PHE-1590 Approval of Technical Datasheets of CI Hubless Pipes 7 26-Jun-19 03-Jul-19 0% 146 Approval of Technical Datasheets of CI Hubless Pipes
T4-EN-MAS-PHE-1600 Approval of Technical Datasheets of UPVC SWR & Agri Pipes 7 26-Jun-19 03-Jul-19 0% 146 Approval of Technical Datasheets of UPVC SWR & Agri Pipes
T4-EN-MAS-PHE-1610 Approval of Technical Datasheets of UPVC Low Noise Pipes 7 26-Jun-19 03-Jul-19 0% 146 Approval of Technical Datasheets of UPVC Low Noise Pipes
T4-EN-MAS-PHE-1620 Approval of Technical Datasheets of Nitrile Rubber Insulation 7 03-Jul-19 10-Jul-19 0% 140 Approval of Technical Datasheets of Nitrile Rubber Insulation
T4-EN-MAS-PHE-1630 Approval of Technical Datasheets of UPVC Traps 7 03-Jul-19 10-Jul-19 0% 140 Approval of Technical Datasheets of UPVC Traps
T4-EN-MAS-PHE-1640 Approval of Technical Datasheets of Rain Water Head 7 03-Jul-19 10-Jul-19 0% 140 Approval of Technical Datasheets of Rain Water Head
T4-EN-MAS-PHE-1650 Approval of Technical Datasheets of GI Pipes (Class B & C) 7 17-Jun-19 24-Jun-19 0% 154 Approval of Technical Datasheets of GI Pipes (Class B & C)
T4-EN-MAS-PHE-1660 Approval of Technical Datasheets of Grooved Coupling (Rigid & Flexible) 7 22-Jun-19 29-Jun-19 0% 128 Approval of Technical Datasheets of Grooved Coupling (Rigid & Flexible)
T4-EN-MAS-PHE-1670 Approval of Technical Datasheets of Motorised Butterfly Valve 7 06-Jul-19 13-Jul-19 0% 116 Approval of Technical Datasheets of Motorised Butterfly Valve
T4-EN-MAS-PHE-1680 Approval of Technical Datasheets of Water Hammer Arrestor 7 06-Jul-19 13-Jul-19 0% 137 Approval of Technical Datasheets of Water Hammer Arrestor
T4-EN-MAS-PHE-1690 Approval of Technical Datasheets of Check Valve 7 06-Jul-19 13-Jul-19 0% 137 Approval of Technical Datasheets of Check Valve
T4-EN-MAS-PHE-1700 Approval of Technical Datasheets of Y Type Strainer 7 06-Jul-19 13-Jul-19 0% 137 Approval of Technical Datasheets of Y Type Strainer
T4-EN-MAS-PHE-1710 Approval of Technical Datasheets of Flexible Rubber Connector 7 06-Jul-19 13-Jul-19 0% 137 Approval of Technical Datasheets of Flexible Rubber Connector
T4-EN-MAS-PHE-1720 Approval of Technical Datasheets of Pressure Gauge 7 06-Jul-19 13-Jul-19 0% 137 Approval of Technical Datasheets of Pressure Gauge
T4-EN-MAS-PHE-1730 Approval of Technical Datasheets of Water Level Sensor 7 10-Jul-19 17-Jul-19 0% 74 Approval of Technical Datasheets of Water Level Sensor
T4-EN-MAS-PHE-1740 Approval of Technical Datasheets of Level Indicator / Glass Tube Manometer 7 10-Jul-19 17-Jul-19 0% 44 Approval of Technical Datasheets of Level Indicator / Glass Tube Manometer
T4-EN-MAS-PHE-1750 Approval of Technical Datasheets of UPVC Bib Tap (AHU Rooms) 7 10-Jul-19 17-Jul-19 0% 113 Approval of Technical Datasheets of UPVC Bib Tap (AHU Rooms)
T4-EN-MAS-PHE-1760 Approval of Technical Datasheets of Mechanical Type Water Meter 7 10-Jul-19 17-Jul-19 0% 218 Approval of Technical Datasheets of Mechanical Type Water Meter
T4-EN-MAS-PHE-1770 Approval of Technical Datasheets of DI Pipes 7 12-Jul-19 19-Jul-19 0% 111 Approval of Technical Datasheets of DI Pipes
T4-EN-MAS-PHE-1790 Approval of Technical Datasheets of FRP Step Ladder 7 12-Jul-19 19-Jul-19 0% 99 Approval of Technical Datasheets of FRP Step Ladder
FF 45 11-Jun-19 01-Aug-19 233 01-Aug-19, FF
CLASS A 19 11-Jul-19 01-Aug-19 140 01-Aug-19, CLASS A
SUBMISSION 12 11-Jul-19 24-Jul-19 140 24-Jul-19, SUBMISSION
T4-EN-MAS-FF-1000 Submission of Technical Datasheets of Fire Hydrant , Sprinkler & Standby Pump at Basement 2 12 11-Jul-19 24-Jul-19 0% 128 Submission of Technical Datasheets of Fire Hydrant , Sprinkler & Standby Pump at Basement 2

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 10 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
Float
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-EN-MAS-FF-1010 Submission of Technical Datasheets of Jockey Hydrant & Sprinkler pump at Basement 2 12 11-Jul-19 24-Jul-19 0% 135 Submission of Technical Datasheets of Jockey Hydrant & Sprinkler pump at Basement 2
T4-EN-MAS-FF-1020 Submission of Technical Datasheets of Fire Hydrant , Sprinkler & Standby Pump at Terrace Level 12 11-Jul-19 24-Jul-19 0% 135 Submission of Technical Datasheets of Fire Hydrant , Sprinkler & Standby Pump at Terrace
T4-EN-MAS-FF-1030 Submission of Technical Datasheets of Jockey Hydrant & Sprinkler pump at Terrace Level 12 11-Jul-19 24-Jul-19 0% 140 Submission of Technical Datasheets of Jockey Hydrant & Sprinkler pump at Terrace Level
APPROVAL 7 25-Jul-19 01-Aug-19 140 01-Aug-19, APPROVAL
T4-EN-MAS-FF-1040 Approval of Technical Datasheets of Fire Hydrant , Sprinkler & Standby Pump at Basement 2 7 25-Jul-19 01-Aug-19 0% 128 Approval of Technical Datasheets of Fire Hydrant , Sprinkler & Standby Pump at Basement 2
T4-EN-MAS-FF-1050 Approval of Technical Datasheets of Jockey Hydrant & Sprinkler pump at Basement 2 7 25-Jul-19 01-Aug-19 0% 140 Approval of Technical Datasheets of Jockey Hydrant & Sprinkler pump at Basement 2
T4-EN-MAS-FF-1060 Approval of Technical Datasheets of Fire Hydrant , Sprinkler & Standby Pump at Terrace Level 7 25-Jul-19 01-Aug-19 0% 137 Approval of Technical Datasheets of Fire Hydrant , Sprinkler & Standby Pump at Terrace Level
T4-EN-MAS-FF-1070 Approval of Technical Datasheets of Jockey Hydrant & Sprinkler pump at Terrace Level 7 25-Jul-19 01-Aug-19 0% 140 Approval of Technical Datasheets of Jockey Hydrant & Sprinkler pump at Terrace Level
CLASS B 33 11-Jun-19 18-Jul-19 245 18-Jul-19, CLASS B
SUBMISSION 26 11-Jun-19 10-Jul-19 245 10-Jul-19, SUBMISSION
T4-EN-MAS-FF-1080 Submission of Technical Datasheets of Pressure Gauge 5 21-Jun-19 26-Jun-19 0% 75 Submission of Technical Datasheets of Pressure Gauge
T4-EN-MAS-FF-1090 Submission of Technical Datasheets of Y-Type Strainer 5 17-Jun-19 21-Jun-19 0% 75 Submission of Technical Datasheets of Y-Type Strainer
T4-EN-MAS-FF-1100 Submission of Technical Datasheets of CI Butterfly Valve 5 17-Jun-19 21-Jun-19 0% 75 Submission of Technical Datasheets of CI Butterfly Valve
T4-EN-MAS-FF-1110 Submission of Technical Datasheets of Sprinkler Alarm Valve 5 05-Jul-19 10-Jul-19 0% 128 Submission of Technical Datasheets of Sprinkler Alarm Valve
T4-EN-MAS-FF-1120 Submission of Technical Datasheets of Flexible Rubber Bellows 5 17-Jun-19 21-Jun-19 0% 75 Submission of Technical Datasheets of Flexible Rubber Bellows
T4-EN-MAS-FF-1130 Submission of Technical Datasheets of Pressure Switch 5 17-Jun-19 21-Jun-19 0% 75 Submission of Technical Datasheets of Pressure Switch
T4-EN-MAS-FF-1140 Submission of Technical Datasheets of Flowmeter 5 17-Jun-19 21-Jun-19 0% 75 Submission of Technical Datasheets of Flowmeter
T4-EN-MAS-FF-1150 Submission of Technical Datasheets of GI Pipes (Class B & C) 5 11-Jun-19 15-Jun-19 0% 0 Submission of Technical Datasheets of GI Pipes (Class B & C)
T4-EN-MAS-FF-1160 Submission of Technical Datasheets of CI Check Valve 5 19-Jun-19 24-Jun-19 0% 75 Submission of Technical Datasheets of CI Check Valve
T4-EN-MAS-FF-1170 Submission of Technical Datasheets of Pressure Relief Valve 5 02-Jul-19 06-Jul-19 0% 75 Submission of Technical Datasheets of Pressure Relief Valve
T4-EN-MAS-FF-1180 Submission of Technical Datasheets of Precharged Air Vessel (500 Liters) 5 03-Jul-19 08-Jul-19 0% 75 Submission of Technical Datasheets of Precharged Air Vessel (500 Liters)
T4-EN-MAS-FF-1190 Submission of Technical Datasheets of Flow Switch 5 03-Jul-19 08-Jul-19 0% 75 Submission of Technical Datasheets of Flow Switch
T4-EN-MAS-FF-1200 Submission of Technical Datasheets of Tamper Switch 5 03-Jul-19 08-Jul-19 0% 75 Submission of Technical Datasheets of Tamper Switch
T4-EN-MAS-FF-1210 Submission of Technical Datasheets of Auto Air Vent 5 19-Jun-19 24-Jun-19 0% 75 Submission of Technical Datasheets of Auto Air Vent
T4-EN-MAS-FF-1220 Submission of Technical Datasheets of Ball Valve 5 03-Jul-19 08-Jul-19 0% 91 Submission of Technical Datasheets of Ball Valve
T4-EN-MAS-FF-1230 Submission of Technical Datasheets of 4-way Breaching Inlet 5 19-Jun-19 24-Jun-19 0% 75 Submission of Technical Datasheets of 4-way Breaching Inlet
T4-EN-MAS-FF-1240 Submission of Technical Datasheets of Orifice Plate 5 25-Jun-19 29-Jun-19 0% 232 Submission of Technical Datasheets of Orifice Plate
T4-EN-MAS-FF-1250 Submission of Technical Datasheets of Deluge Valve 5 22-Jun-19 27-Jun-19 0% 75 Submission of Technical Datasheets of Deluge Valve
T4-EN-MAS-FF-1260 Submission of Technical Datasheets of Water Curtain Nozzles 5 22-Jun-19 27-Jun-19 0% 75 Submission of Technical Datasheets of Water Curtain Nozzles
T4-EN-MAS-FF-1270 Submission of Technical Datasheets of First Aid Hose Reel 5 22-Jun-19 27-Jun-19 0% 75 Submission of Technical Datasheets of First Aid Hose Reel
T4-EN-MAS-FF-1280 Submission of Technical Datasheets of Branch Pipe and Nozzle 5 22-Jun-19 27-Jun-19 0% 75 Submission of Technical Datasheets of Branch Pipe and Nozzle
T4-EN-MAS-FF-1290 Submission of Technical Datasheets of Fire Hose Pipe 5 22-Jun-19 27-Jun-19 0% 75 Submission of Technical Datasheets of Fire Hose Pipe
T4-EN-MAS-FF-1300 Submission of Technical Datasheets of Inline PRV 5 03-Jul-19 08-Jul-19 0% 75 Submission of Technical Datasheets of Inline PRV
T4-EN-MAS-FF-1310 Submission of Technical Datasheets of Single /Double Hydrant Landing Valve 5 19-Jun-19 24-Jun-19 0% 148 Submission of Technical Datasheets of Single /Double Hydrant Landing Valve
T4-EN-MAS-FF-1320 Submission of Technical Datasheets of Fire Hose Cabinet 5 26-Jun-19 01-Jul-19 0% 75 Submission of Technical Datasheets of Fire Hose Cabinet
T4-EN-MAS-FF-1330 Submission of Technical Datasheets of Fire Extinguisher 5 26-Jun-19 01-Jul-19 0% 75 Submission of Technical Datasheets of Fire Extinguisher
T4-EN-MAS-FF-1340 Submission of Technical Datasheets of Compressed Air Breathing Apparatus 5 02-Jul-19 06-Jul-19 0% 248 Submission of Technical Datasheets of Compressed Air Breathing Apparatus
T4-EN-MAS-FF-1350 Submission of Technical Datasheets of Sprinkler 5 26-Jun-19 01-Jul-19 0% 75 Submission of Technical Datasheets of Sprinkler
T4-EN-MAS-FF-1360 Submission of Technical Datasheets of Flexible Sprinkler Connector 5 26-Jun-19 01-Jul-19 0% 75 Submission of Technical Datasheets of Flexible Sprinkler Connector
T4-EN-MAS-FF-1370 Submission of Technical Datasheets of Grooved Coupling (Flexible & Rigid) 5 26-Jun-19 01-Jul-19 0% 75 Submission of Technical Datasheets of Grooved Coupling (Flexible & Rigid)
APPROVAL 28 17-Jun-19 18-Jul-19 245 18-Jul-19, APPROVAL
T4-EN-MAS-FF-1380 Approval of Technical Datasheets of Pressure Gauge 7 27-Jun-19 04-Jul-19 0% 235 Approval of Technical Datasheets of Pressure Gauge
T4-EN-MAS-FF-1390 Approval of Technical Datasheets of Y-Type Strainer 7 22-Jun-19 29-Jun-19 0% 149 Approval of Technical Datasheets of Y-Type Strainer
T4-EN-MAS-FF-1400 Approval of Technical Datasheets of CI Butterfly Valve 7 22-Jun-19 29-Jun-19 0% 149 Approval of Technical Datasheets of CI Butterfly Valve
T4-EN-MAS-FF-1410 Approval of Technical Datasheets of Sprinkler Alarm Valve 7 11-Jul-19 18-Jul-19 0% 133 Approval of Technical Datasheets of Sprinkler Alarm Valve
T4-EN-MAS-FF-1420 Approval of Technical Datasheets of Flexible Rubber Bellows 7 22-Jun-19 29-Jun-19 0% 149 Approval of Technical Datasheets of Flexible Rubber Bellows
T4-EN-MAS-FF-1430 Approval of Technical Datasheets of Pressure Switch 7 22-Jun-19 29-Jun-19 0% 149 Approval of Technical Datasheets of Pressure Switch
T4-EN-MAS-FF-1440 Approval of Technical Datasheets of Flowmeter 7 22-Jun-19 29-Jun-19 0% 149 Approval of Technical Datasheets of Flowmeter
T4-EN-MAS-FF-1450 Approval of Technical Datasheets of GI Pipes (Class B & C) 7 17-Jun-19 24-Jun-19 0% 149 Approval of Technical Datasheets of GI Pipes (Class B & C)
T4-EN-MAS-FF-1460 Approval of Technical Datasheets of CI Check Valve 7 25-Jun-19 02-Jul-19 0% 142 Approval of Technical Datasheets of CI Check Valve
T4-EN-MAS-FF-1470 Approval of Technical Datasheets of Pressure Relief Valve 7 08-Jul-19 15-Jul-19 0% 131 Approval of Technical Datasheets of Pressure Relief Valve

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 11 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
Float
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-EN-MAS-FF-1480 Approval of Technical Datasheets of Precharged Air Vessel (500 Liters) 7 09-Jul-19 16-Jul-19 0% 168 Approval of Technical Datasheets of Precharged Air Vessel (500 Liters)
T4-EN-MAS-FF-1490 Approval of Technical Datasheets of Flow Switch 7 09-Jul-19 16-Jul-19 0% 165 Approval of Technical Datasheets of Flow Switch
T4-EN-MAS-FF-1500 Approval of Technical Datasheets of Tamper Switch 7 09-Jul-19 16-Jul-19 0% 180 Approval of Technical Datasheets of Tamper Switch
T4-EN-MAS-FF-1510 Approval of Technical Datasheets of Auto Air Vent 7 25-Jun-19 02-Jul-19 0% 155 Approval of Technical Datasheets of Auto Air Vent
T4-EN-MAS-FF-1520 Approval of Technical Datasheets of Double Hydrant Landing Valve 7 09-Jul-19 16-Jul-19 0% 91 Approval of Technical Datasheets of Double Hydrant Landing Valve
T4-EN-MAS-FF-1530 Approval of Technical Datasheets of 4-way Breaching Inlet 7 25-Jun-19 02-Jul-19 0% 103 Approval of Technical Datasheets of 4-way Breaching Inlet
T4-EN-MAS-FF-1540 Approval of Technical Datasheets of Orifice Plate 7 01-Jul-19 08-Jul-19 0% 232 Approval of Technical Datasheets of Orifice Plate
T4-EN-MAS-FF-1550 Approval of Technical Datasheets of Deluge Valve 7 28-Jun-19 05-Jul-19 0% 135 Approval of Technical Datasheets of Deluge Valve
T4-EN-MAS-FF-1560 Approval of Technical Datasheets of Water Curtain Nozzles 7 28-Jun-19 05-Jul-19 0% 126 Approval of Technical Datasheets of Water Curtain Nozzles
T4-EN-MAS-FF-1570 Approval of Technical Datasheets of First Aid Hose Reel 7 28-Jun-19 05-Jul-19 0% 184 Approval of Technical Datasheets of First Aid Hose Reel
T4-EN-MAS-FF-1580 Approval of Technical Datasheets of Branch Pipe and Nozzle 7 28-Jun-19 05-Jul-19 0% 234 Approval of Technical Datasheets of Branch Pipe and Nozzle
T4-EN-MAS-FF-1590 Approval of Technical Datasheets of Fire Hose Pipe 7 28-Jun-19 05-Jul-19 0% 184 Approval of Technical Datasheets of Fire Hose Pipe
T4-EN-MAS-FF-1600 Approval of Technical Datasheets of Inline PRV 7 09-Jul-19 16-Jul-19 0% 75 Approval of Technical Datasheets of Inline PRV
T4-EN-MAS-FF-1610 Approval of Technical Datasheets of Single Hydrant Landing Valve 7 25-Jun-19 02-Jul-19 0% 148 Approval of Technical Datasheets of Single Hydrant Landing Valve
T4-EN-MAS-FF-1620 Approval of Technical Datasheets of Fire Hose Cabinet 7 02-Jul-19 09-Jul-19 0% 176 Approval of Technical Datasheets of Fire Hose Cabinet
T4-EN-MAS-FF-1630 Approval of Technical Datasheets of Fire Extinguisher 7 02-Jul-19 09-Jul-19 0% 253 Approval of Technical Datasheets of Fire Extinguisher
T4-EN-MAS-FF-1640 Approval of Technical Datasheets of Compressed Air Breathing Apparatus 7 08-Jul-19 15-Jul-19 0% 248 Approval of Technical Datasheets of Compressed Air Breathing Apparatus
T4-EN-MAS-FF-1650 Approval of Technical Datasheets of Sprinkler 7 02-Jul-19 09-Jul-19 0% 141 Approval of Technical Datasheets of Sprinkler
T4-EN-MAS-FF-1660 Approval of Technical Datasheets of Flexible Sprinkler Connector 7 02-Jul-19 09-Jul-19 0% 141 Approval of Technical Datasheets of Flexible Sprinkler Connector
T4-EN-MAS-FF-1670 Approval of Technical Datasheets of Grooved Coupling (Flexible & Rigid) 7 02-Jul-19 09-Jul-19 0% 122 Approval of Technical Datasheets of Grooved Coupling (Flexible & Rigid)
HVAC 62 12-Jun-19 23-Aug-19 245 23-Aug-19, HVAC
CLASS A 33 16-Jul-19 23-Aug-19 245 23-Aug-19, CLASS A
SUBMISSION 26 16-Jul-19 14-Aug-19 96 14-Aug-19, SUBMISSION
T4-EN-MAS-HVAC-1000Submission of Technical Datasheets of Expansion Tank, Air Separator, Pressurization System 7 02-Aug-19 09-Aug-19 0% 0 Submission of Technical Datasheets of Expansion Tank, Air Separator, Pressurization System
T4-EN-MAS-HVAC-1010Submission of Technical Datasheets of Secondary Chilled Water Pump 7 24-Jul-19 31-Jul-19 0% 0 Submission of Technical Datasheets of Secondary Chilled Water Pump
T4-EN-MAS-HVAC-1020Submission of Technical Datasheets of Primary Chilled Water Pump 7 24-Jul-19 31-Jul-19 0% 0 Submission of Technical Datasheets of Primary Chilled Water Pump
T4-EN-MAS-HVAC-1030Submission of Technical Datasheets of Condenser Pumps 7 24-Jul-19 31-Jul-19 0% 0 Submission of Technical Datasheets of Condenser Pumps
T4-EN-MAS-HVAC-1040Submission of Technical Datasheets of VFD Panel for Pumps 7 24-Jul-19 31-Jul-19 0% 0 Submission of Technical Datasheets of VFD Panel for Pumps
T4-EN-MAS-HVAC-1050Submission of Technical Datasheets of Filter Feed Pumps 7 24-Jul-19 31-Jul-19 0% 0 Submission of Technical Datasheets of Filter Feed Pumps
T4-EN-MAS-HVAC-1060Submission of Technical Datasheets of Cooling Towers 7 29-Jul-19 05-Aug-19 0% 0 Submission of Technical Datasheets of Cooling Towers
T4-EN-MAS-HVAC-1070Submission of Technical Datasheets of HRU with Energy Recovery Wheel 7 19-Jul-19 26-Jul-19 0% 0 Submission of Technical Datasheets of HRU with Energy Recovery Wheel
T4-EN-MAS-HVAC-1080Submission of Technical Datasheets of HRU with Energy Recovery Pipe 5 22-Jul-19 26-Jul-19 0% 0 Submission of Technical Datasheets of HRU with Energy Recovery Pipe
T4-EN-MAS-HVAC-1090Submission of Technical Datasheets of Treated Fresh Air Unit 5 22-Jul-19 26-Jul-19 0% 0 Submission of Technical Datasheets of Treated Fresh Air Unit
T4-EN-MAS-HVAC-1100Submission of Technical Datasheets of AHU's 5 22-Jul-19 26-Jul-19 0% 0 Submission of Technical Datasheets of AHU's
T4-EN-MAS-HVAC-1110Submission of Technical Datasheets of Active filteration of AHU 5 05-Aug-19 09-Aug-19 0% 0 Submission of Technical Datasheets of Active filteration of AHU
T4-EN-MAS-HVAC-1120Submission of Technical Datasheets of Fan Coil Unit 5 22-Jul-19 26-Jul-19 0% 0 Submission of Technical Datasheets of Fan Coil Unit
T4-EN-MAS-HVAC-1130Submission of Technical Datasheets of Plate Type Heat Exchanger 7 29-Jul-19 05-Aug-19 0% 0 Submission of Technical Datasheets of Plate Type Heat Exchanger
T4-EN-MAS-HVAC-1140Submission of Technical Datasheets of Chemical Dosing System 5 05-Aug-19 09-Aug-19 0% 96 Submission of Technical Datasheets of Chemical Dosing System
T4-EN-MAS-HVAC-1150Submission of Technical Datasheets of Vane Axial Fans 6 16-Jul-19 22-Jul-19 0% 0 Submission of Technical Datasheets of Vane Axial Fans
T4-EN-MAS-HVAC-1160Submission of Technical Datasheets of Smoke Spill Vane Axial Fans 5 17-Jul-19 22-Jul-19 0% 0 Submission of Technical Datasheets of Smoke Spill Vane Axial Fans
T4-EN-MAS-HVAC-1170Submission of Technical Datasheets of Inline Fans 5 17-Jul-19 22-Jul-19 0% 0 Submission of Technical Datasheets of Inline Fans
T4-EN-MAS-HVAC-1180Submission of Technical Datasheets of Propeller Fans 5 17-Jul-19 22-Jul-19 0% 0 Submission of Technical Datasheets of Propeller Fans
T4-EN-MAS-HVAC-1190Submission of Technical Datasheets of Cabinet Fans 5 17-Jul-19 22-Jul-19 0% 0 Submission of Technical Datasheets of Cabinet Fans
T4-EN-MAS-HVAC-1200Submission of Technical Datasheets of Jet Fans (With CO Sensors) 5 17-Jul-19 22-Jul-19 0% 0 Submission of Technical Datasheets of Jet Fans (With CO Sensors)
T4-EN-MAS-HVAC-1210Submission of Technical Datasheets of Hi Wall & Ducted Split Units 5 09-Aug-19 14-Aug-19 0% 96 Submission of Technical Datasheets of Hi Wall & Ducted Split Units
T4-EN-MAS-HVAC-1220Submission of Technical Datasheets of Hi Wall Chilled Water Unit 5 09-Aug-19 14-Aug-19 0% 96 Submission of Technical Datasheets of Hi Wall Chilled Water Unit
T4-EN-MAS-HVAC-1230Submission of Technical Datasheets of Water Treatment Plant For Cooling Tower 5 09-Aug-19 14-Aug-19 0% 96 Submission of Technical Datasheets of Water Treatment Plant For Cooling Tower
T4-EN-MAS-HVAC-1240Submission of Technical Datasheets of Electrical Panels 5 09-Aug-19 14-Aug-19 0% 96 Submission of Technical Datasheets of Electrical Panels
APPROVAL 27 23-Jul-19 23-Aug-19 245 23-Aug-19, APPROVAL
T4-EN-MAS-HVAC-1250Approval of Technical Datasheets of Expansion Tank, Air Separator, Pressurization System 7 10-Aug-19 19-Aug-19 0% 68 Approval of Technical Datasheets of Expansion Tank, Air Separator, Pressurization System
T4-EN-MAS-HVAC-1260Approval of Technical Datasheets of Secondary Chilled Water Pump 7 01-Aug-19 08-Aug-19 0% 86 Approval of Technical Datasheets of Secondary Chilled Water Pump

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 12 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-EN-MAS-HVAC-1270Approval of Technical Datasheets of Primary Chilled Water Pump 7 01-Aug-19 08-Aug-19 0% 72 Approval of Technical Datasheets of Primary Chilled Water Pump
T4-EN-MAS-HVAC-1280Approval of Technical Datasheets of Condenser Pumps 7 01-Aug-19 08-Aug-19 0% 71 Approval of Technical Datasheets of Condenser Pumps
T4-EN-MAS-HVAC-1290Approval of Technical Datasheets of VFD Panel for Pumps 7 01-Aug-19 08-Aug-19 0% 106 Approval of Technical Datasheets of VFD Panel for Pumps
T4-EN-MAS-HVAC-1300Approval of Technical Datasheets of Filter Feed Pumps 7 01-Aug-19 08-Aug-19 0% 77 Approval of Technical Datasheets of Filter Feed Pumps
T4-EN-MAS-HVAC-1310Approval of Technical Datasheets of Cooling Towers 7 06-Aug-19 13-Aug-19 0% 193 Approval of Technical Datasheets of Cooling Towers
T4-EN-MAS-HVAC-1320Approval of Technical Datasheets of HRU with Energy Recovery Wheel 7 27-Jul-19 03-Aug-19 0% 65 Approval of Technical Datasheets of HRU with Energy Recovery Wheel
T4-EN-MAS-HVAC-1330Approval of Technical Datasheets of HRU with Energy Recovery Pipe 7 27-Jul-19 03-Aug-19 0% 65 Approval of Technical Datasheets of HRU with Energy Recovery Pipe
T4-EN-MAS-HVAC-1340Approval of Technical Datasheets of Treated Fresh Air Unit 7 27-Jul-19 03-Aug-19 0% 103 Approval of Technical Datasheets of Treated Fresh Air Unit
T4-EN-MAS-HVAC-1350Approval of Technical Datasheets of AHU's 7 27-Jul-19 03-Aug-19 0% 24 Approval of Technical Datasheets of AHU's
T4-EN-MAS-HVAC-1360Approval of Technical Datasheets of Active filteration of AHU 7 10-Aug-19 19-Aug-19 0% 0 Approval of Technical Datasheets of Active filteration of AHU
T4-EN-MAS-HVAC-1370Approval of Technical Datasheets of Fan Coil Unit 7 27-Jul-19 03-Aug-19 0% 115 Approval of Technical Datasheets of Fan Coil Unit
T4-EN-MAS-HVAC-1380Approval of Technical Datasheets of Plate Type Heat Exchanger 7 06-Aug-19 13-Aug-19 0% 57 Approval of Technical Datasheets of Plate Type Heat Exchanger
T4-EN-MAS-HVAC-1390Approval of Technical Datasheets of Chemical Dosing System 7 10-Aug-19 19-Aug-19 0% 236 Approval of Technical Datasheets of Chemical Dosing System
T4-EN-MAS-HVAC-1400Approval of Technical Datasheets of Vane Axial Fans 7 23-Jul-19 30-Jul-19 0% 76 Approval of Technical Datasheets of Vane Axial Fans
T4-EN-MAS-HVAC-1410Approval of Technical Datasheets of Smoke Spill Vane Axial Fans 7 23-Jul-19 30-Jul-19 0% 88 Approval of Technical Datasheets of Smoke Spill Vane Axial Fans
T4-EN-MAS-HVAC-1420Approval of Technical Datasheets of Inline Fans 7 23-Jul-19 30-Jul-19 0% 103 Approval of Technical Datasheets of Inline Fans
T4-EN-MAS-HVAC-1430Approval of Technical Datasheets of Propeller Fans 7 23-Jul-19 30-Jul-19 0% 103 Approval of Technical Datasheets of Propeller Fans
T4-EN-MAS-HVAC-1440Approval of Technical Datasheets of Cabinet Fans 7 23-Jul-19 30-Jul-19 0% 103 Approval of Technical Datasheets of Cabinet Fans
T4-EN-MAS-HVAC-1450Approval of Technical Datasheets of Jet Fans (With CO Sensors) 7 23-Jul-19 30-Jul-19 0% 103 Approval of Technical Datasheets of Jet Fans (With CO Sensors)
T4-EN-MAS-HVAC-1460Approval of Technical Datasheets of Hi Wall & Ducted Split Units 7 16-Aug-19 23-Aug-19 0% 98 Approval of Technical Datasheets of Hi Wall & Ducted Split Units
T4-EN-MAS-HVAC-1470Approval of Technical Datasheets of Hi Wall Chilled Water Unit 7 16-Aug-19 23-Aug-19 0% 98 Approval of Technical Datasheets of Hi Wall Chilled Water Unit
T4-EN-MAS-HVAC-1480Approval of Technical Datasheets of Water Treatment Plant For Cooling Tower 7 16-Aug-19 23-Aug-19 0% 245 Approval of Technical Datasheets of Water Treatment Plant For Cooling Tower
T4-EN-MAS-HVAC-1490Approval of Technical Datasheets of Electrical Panels 7 16-Aug-19 23-Aug-19 0% 96 Approval of Technical Datasheets of Electrical Panels
CLASS B 46 12-Jun-19 03-Aug-19 204 03-Aug-19, CLASS B
SUBMISSION 39 12-Jun-19 26-Jul-19 204 26-Jul-19, SUBMISSION
T4-EN-MAS-HVAC-1500Submission of Technical Datasheets of MS Pipes 5 12-Jun-19 17-Jun-19 0% 0 Submission of Technical Datasheets of MS Pipes
T4-EN-MAS-HVAC-1510Submission of Technical Datasheets of UPVC Drain Pipe 5 20-Jun-19 25-Jun-19 0% 0 Submission of Technical Datasheets of UPVC Drain Pipe
T4-EN-MAS-HVAC-1520Submission of Technical Datasheets of Ball Valves 5 12-Jun-19 17-Jun-19 0% 0 Submission of Technical Datasheets of Ball Valves
T4-EN-MAS-HVAC-1530Submission of Technical Datasheets of Manual Butterfly Valves 5 12-Jun-19 17-Jun-19 0% 0 Submission of Technical Datasheets of Manual Butterfly Valves
T4-EN-MAS-HVAC-1540Submission of Technical Datasheets of Motorised Butterfly Valves 5 12-Jun-19 17-Jun-19 0% 0 Submission of Technical Datasheets of Motorised Butterfly Valves
T4-EN-MAS-HVAC-1550Submission of Technical Datasheets of Manual Balancing Valves 4 18-Jun-19 21-Jun-19 0% 0 Submission of Technical Datasheets of Manual Balancing Valves
T4-EN-MAS-HVAC-1560Submission of Technical Datasheets of Non Return Valves 5 17-Jun-19 21-Jun-19 0% 0 Submission of Technical Datasheets of Non Return Valves
T4-EN-MAS-HVAC-1570Submission of Technical Datasheets of Y - Strainers 5 17-Jun-19 21-Jun-19 0% 0 Submission of Technical Datasheets of Y - Strainers
T4-EN-MAS-HVAC-1580Submission of Technical Datasheets of Thermostat 5 26-Jun-19 01-Jul-19 0% 0 Submission of Technical Datasheets of Thermostat
T4-EN-MAS-HVAC-1590Submission of Technical Datasheets of BTU Meters 5 22-Jun-19 27-Jun-19 0% 0 Submission of Technical Datasheets of BTU Meters
T4-EN-MAS-HVAC-1600Submission of Technical Datasheets of Flexible Connections 5 17-Jun-19 21-Jun-19 0% 0 Submission of Technical Datasheets of Flexible Connections
T4-EN-MAS-HVAC-1610Submission of Technical Datasheets of PICV 5 22-Jun-19 27-Jun-19 0% 0 Submission of Technical Datasheets of PICV
T4-EN-MAS-HVAC-1620Submission of Technical Datasheets of Flow Meter for Decoupler Line 5 22-Jun-19 27-Jun-19 0% 0 Submission of Technical Datasheets of Flow Meter for Decoupler Line
T4-EN-MAS-HVAC-1630Submission of Technical Datasheets of Auto Air Vent 5 22-Jun-19 27-Jun-19 0% 0 Submission of Technical Datasheets of Auto Air Vent
T4-EN-MAS-HVAC-1640Submission of Technical Datasheets of Descaling Tee Valve 5 29-Jun-19 04-Jul-19 0% 0 Submission of Technical Datasheets of Descaling Tee Valve
T4-EN-MAS-HVAC-1650Submission of Technical Datasheets of PG - TG 5 12-Jun-19 17-Jun-19 0% 0 Submission of Technical Datasheets of PG - TG
T4-EN-MAS-HVAC-1660Submission of Technical Datasheets of Grooved Fittings 5 26-Jun-19 01-Jul-19 0% 0 Submission of Technical Datasheets of Grooved Fittings
T4-EN-MAS-HVAC-1670Submission of Technical Datasheets of GI Ducting 5 03-Jul-19 08-Jul-19 0% 0 Submission of Technical Datasheets of GI Ducting
T4-EN-MAS-HVAC-1680Submission of Technical Datasheets of Fire Paints 5 06-Jul-19 11-Jul-19 0% 0 Submission of Technical Datasheets of Fire Paints
T4-EN-MAS-HVAC-1690Submission of Technical Datasheets of Manual & Motorised VCD 5 03-Jul-19 08-Jul-19 0% 0 Submission of Technical Datasheets of Manual & Motorised VCD
T4-EN-MAS-HVAC-1700Submission of Technical Datasheets of Fire Damper with Fusible Link & Motorised 5 03-Jul-19 08-Jul-19 0% 0 Submission of Technical Datasheets of Fire Damper with Fusible Link & Motorised
T4-EN-MAS-HVAC-1710Submission of Technical Datasheets of Diffuser, Grilles, Slot Diffuser, Door Grilles, Non Return Dampers 5 03-Jul-19 08-Jul-19 0% 0 Submission of Technical Datasheets of Diffuser, Grilles, Slot Diffuser, Door Grilles, Non Return
T4-EN-MAS-HVAC-1720Submission of Technical Datasheets of Flexible Ducts 5 03-Jul-19 08-Jul-19 0% 0 Submission of Technical Datasheets of Flexible Ducts
T4-EN-MAS-HVAC-1730Submission of Technical Datasheets of Barometric pressure relief damper 5 03-Jul-19 08-Jul-19 0% 0 Submission of Technical Datasheets of Barometric pressure relief damper
T4-EN-MAS-HVAC-1740Submission of Technical Datasheets of Sound Attenuators 5 06-Jul-19 11-Jul-19 0% 0 Submission of Technical Datasheets of Sound Attenuators
T4-EN-MAS-HVAC-1750Submission of Technical Datasheets of Duct Thermal Insulation 5 10-Jul-19 15-Jul-19 0% 0 Submission of Technical Datasheets of Duct Thermal Insulation

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 13 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul A Sep Oct N Dec Jan F Mar Apr May J Jul
Float A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-EN-MAS-HVAC-1760Submission of Technical Datasheets of Accoustic Insulation 5 10-Jul-19 15-Jul-19 0% 0 Submission of Technical Datasheets of Accoustic Insulation
T4-EN-MAS-HVAC-1770Submission of Technical Datasheets of CHW Pipe Insulation -Fibre Glasswoool 5 10-Jul-19 15-Jul-19 0% 0 Submission of Technical Datasheets of CHW Pipe Insulation -Fibre Glasswoool
T4-EN-MAS-HVAC-1780Submission of Technical Datasheets of Underdeck Insulation - EPS 5 10-Jul-19 15-Jul-19 0% 0 Submission of Technical Datasheets of Underdeck Insulation - EPS
T4-EN-MAS-HVAC-2080Submission of Technical Datasheets of Flow Switch 5 16-Jul-19 20-Jul-19 0% 120 Submission of Technical Datasheets of Flow Switch
T4-EN-MAS-HVAC-2090Submission of Technical Datasheets of Differential Pressure Switch 5 22-Jul-19 26-Jul-19 0% 204 Submission of Technical Datasheets of Differential Pressure Switch
T4-EN-MAS-HVAC-2100Submission of Technical Datasheets of Canvass Duct Connection 5 03-Jul-19 08-Jul-19 0% 126 Submission of Technical Datasheets of Canvass Duct Connection
APPROVAL 41 18-Jun-19 03-Aug-19 204 03-Aug-19, APPROVAL
T4-EN-MAS-HVAC-1790Approval of Technical Datasheets of MS Pipes 7 18-Jun-19 25-Jun-19 0% 141 Approval of Technical Datasheets of MS Pipes
T4-EN-MAS-HVAC-1800Approval of Technical Datasheets of UPVC Drain Pipe 7 26-Jun-19 03-Jul-19 0% 134 Approval of Technical Datasheets of UPVC Drain Pipe
T4-EN-MAS-HVAC-1810Approval of Technical Datasheets of Ball Valves 7 18-Jun-19 25-Jun-19 0% 141 Approval of Technical Datasheets of Ball Valves
T4-EN-MAS-HVAC-1820Approval of Technical Datasheets of Manual Butterfly Valves 7 18-Jun-19 25-Jun-19 0% 141 Approval of Technical Datasheets of Manual Butterfly Valves
T4-EN-MAS-HVAC-1830Approval of Technical Datasheets of Motorised Butterfly Valves 7 18-Jun-19 25-Jun-19 0% 147 Approval of Technical Datasheets of Motorised Butterfly Valves
T4-EN-MAS-HVAC-1840Approval of Technical Datasheets of Manual Balancing Valves 7 22-Jun-19 29-Jun-19 0% 143 Approval of Technical Datasheets of Manual Balancing Valves
T4-EN-MAS-HVAC-1850Approval of Technical Datasheets of Non Return Valves 7 22-Jun-19 29-Jun-19 0% 143 Approval of Technical Datasheets of Non Return Valves
T4-EN-MAS-HVAC-1860Approval of Technical Datasheets of Y - Strainers 7 22-Jun-19 29-Jun-19 0% 143 Approval of Technical Datasheets of Y - Strainers
T4-EN-MAS-HVAC-1870Approval of Technical Datasheets of Thermostat 7 02-Jul-19 09-Jul-19 0% 135 Approval of Technical Datasheets of Thermostat
T4-EN-MAS-HVAC-1880Approval of Technical Datasheets of BTU Meters 7 28-Jun-19 05-Jul-19 0% 132 Approval of Technical Datasheets of BTU Meters
T4-EN-MAS-HVAC-1890Approval of Technical Datasheets of Flexible Connections 7 22-Jun-19 29-Jun-19 0% 137 Approval of Technical Datasheets of Flexible Connections
T4-EN-MAS-HVAC-1900Approval of Technical Datasheets of PICV 7 28-Jun-19 05-Jul-19 0% 138 Approval of Technical Datasheets of PICV
T4-EN-MAS-HVAC-1910Approval of Technical Datasheets of Flow Meter for Decoupler Line 7 28-Jun-19 05-Jul-19 0% 138 Approval of Technical Datasheets of Flow Meter for Decoupler Line
T4-EN-MAS-HVAC-1920Approval of Technical Datasheets of Auto Air Vent 7 28-Jun-19 05-Jul-19 0% 132 Approval of Technical Datasheets of Auto Air Vent
T4-EN-MAS-HVAC-1930Approval of Technical Datasheets of Descaling Tee Valve 7 05-Jul-19 12-Jul-19 0% 132 Approval of Technical Datasheets of Descaling Tee Valve
T4-EN-MAS-HVAC-1940Approval of Technical Datasheets of PG - TG 7 18-Jun-19 25-Jun-19 0% 62 Approval of Technical Datasheets of PG - TG
T4-EN-MAS-HVAC-1950Approval of Technical Datasheets of Grooved Fittings 7 02-Jul-19 09-Jul-19 0% 129 Approval of Technical Datasheets of Grooved Fittings
T4-EN-MAS-HVAC-1960Approval of Technical Datasheets of GI Ducting 7 09-Jul-19 16-Jul-19 0% 92 Approval of Technical Datasheets of GI Ducting
T4-EN-MAS-HVAC-1970Approval of Technical Datasheets of Fire Paints 7 12-Jul-19 19-Jul-19 0% 60 Approval of Technical Datasheets of Fire Paints
T4-EN-MAS-HVAC-1980Approval of Technical Datasheets of Manual & Motorised VCD 7 09-Jul-19 16-Jul-19 0% 123 Approval of Technical Datasheets of Manual & Motorised VCD
T4-EN-MAS-HVAC-1990Approval of Technical Datasheets of Fire Damper with Fusible Link & Motorised 7 09-Jul-19 16-Jul-19 0% 123 Approval of Technical Datasheets of Fire Damper with Fusible Link & Motorised
T4-EN-MAS-HVAC-2000Approval of Technical Datasheets of Diffuser, Grilles, Slot Diffuser, Door Grilles, Non Return Dampers 7 09-Jul-19 16-Jul-19 0% 92 Approval of Technical Datasheets of Diffuser, Grilles, Slot Diffuser, Door Grilles, Non Return
T4-EN-MAS-HVAC-2010Approval of Technical Datasheets of Flexible Ducts 7 09-Jul-19 16-Jul-19 0% 92 Approval of Technical Datasheets of Flexible Ducts
T4-EN-MAS-HVAC-2020Approval of Technical Datasheets of Barometric pressure relief damper 7 09-Jul-19 16-Jul-19 0% 142 Approval of Technical Datasheets of Barometric pressure relief damper
T4-EN-MAS-HVAC-2030Approval of Technical Datasheets of Sound Attenuators 7 12-Jul-19 19-Jul-19 0% 120 Approval of Technical Datasheets of Sound Attenuators
T4-EN-MAS-HVAC-2040Approval of Technical Datasheets of Duct Thermal Insulation 7 16-Jul-19 23-Jul-19 0% 117 Approval of Technical Datasheets of Duct Thermal Insulation
T4-EN-MAS-HVAC-2050Approval of Technical Datasheets of Accoustic Insulation 7 16-Jul-19 23-Jul-19 0% 117 Approval of Technical Datasheets of Accoustic Insulation
T4-EN-MAS-HVAC-2060Approval of Technical Datasheets of CHW Pipe Insulation -Fibre Glasswoool 7 16-Jul-19 23-Jul-19 0% 117 Approval of Technical Datasheets of CHW Pipe Insulation -Fibre Glasswoool
T4-EN-MAS-HVAC-2070Approval of Technical Datasheets of Underdeck Insulation - EPS 7 16-Jul-19 23-Jul-19 0% 78 Approval of Technical Datasheets of Underdeck Insulation - EPS
T4-EN-MAS-HVAC-2110Approval of Technical Datasheets of Flow Switch 7 22-Jul-19 29-Jul-19 0% 120 Approval of Technical Datasheets of Flow Switch
T4-EN-MAS-HVAC-2120Approval of Technical Datasheets of Differential Pressure Switch 7 27-Jul-19 03-Aug-19 0% 204 Approval of Technical Datasheets of Differential Pressure Switch
T4-EN-MAS-HVAC-2130Approval of Technical Datasheets of Canvass Duct Connection 7 09-Jul-19 16-Jul-19 0% 126 Approval of Technical Datasheets of Canvass Duct Connection
ELECTRICAL 67 30-May-19 17-Aug-19 218 17-Aug-19, ELECTRICAL
CLASS A 39 03-Jul-19 17-Aug-19 205 17-Aug-19, CLASS A
SUBMISSION 32 03-Jul-19 08-Aug-19 205 08-Aug-19, SUBMISSION
T4-EN-MAS-ELE-1000 Submission of Technical Datasheets of LT Panels / SUB-MAIN DBs / MCC / Isolators 18 09-Jul-19 29-Jul-19 0% 115 Submission of Technical Datasheets of LT Panels / SUB-MAIN DBs / MCC / Isolators
T4-EN-MAS-ELE-1010 Submission of Technical Datasheets of Common DBs (ELCB,MCB,RCCB) 5 03-Jul-19 08-Jul-19 0% 115 Submission of Technical Datasheets of Common DBs (ELCB,MCB,RCCB)
T4-EN-MAS-ELE-1020 Submission of Technical Datasheets of ATS 5 24-Jul-19 29-Jul-19 0% 145 Submission of Technical Datasheets of ATS
T4-EN-MAS-ELE-1030 Submission of Technical Datasheets of Invertor 6 30-Jul-19 05-Aug-19 0% 145 Submission of Technical Datasheets of Invertor
T4-EN-MAS-ELE-1040 Submission of Technical Datasheets of Invertor Batteries 5 31-Jul-19 05-Aug-19 0% 154 Submission of Technical Datasheets of Invertor Batteries
T4-EN-MAS-ELE-1050 Submission of Technical Datasheets of Lightning Protection System 5 03-Aug-19 08-Aug-19 0% 205 Submission of Technical Datasheets of Lightning Protection System
APPROVAL 34 09-Jul-19 17-Aug-19 205 17-Aug-19, APPROVAL
T4-EN-MAS-ELE-1060 Approval of Technical Datasheets of LT Panels / SUB-MAIN DBs / MCC / Isolators 7 30-Jul-19 06-Aug-19 0% 115 Approval of Technical Datasheets of LT Panels / SUB-MAIN DBs / MCC / Isolators
T4-EN-MAS-ELE-1070 Approval of Technical Datasheets of Common DBs (ELCB,MCB,RCCB) 7 09-Jul-19 16-Jul-19 0% 184 Approval of Technical Datasheets of Common DBs (ELCB,MCB,RCCB)
T4-EN-MAS-ELE-1080 Approval of Technical Datasheets of ATS 7 30-Jul-19 06-Aug-19 0% 145 Approval of Technical Datasheets of ATS

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 14 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-EN-MAS-ELE-1090 Approval of Technical Datasheets of Invertor 7 06-Aug-19 13-Aug-19 0% 145 Approval of Technical Datasheets of Invertor
T4-EN-MAS-ELE-1100 Approval of Technical Datasheets of Invertor Batteries 7 06-Aug-19 13-Aug-19 0% 154 Approval of Technical Datasheets of Invertor Batteries
T4-EN-MAS-ELE-1110 Approval of Technical Datasheets of Lightning Protection System 7 09-Aug-19 17-Aug-19 0% 205 Approval of Technical Datasheets of Lightning Protection System
CLASS B 37 30-May-19 12-Jul-19 248 12-Jul-19, CLASS B
SUBMISSION 30 30-May-19 04-Jul-19 171 04-Jul-19, SUBMISSION
T4-EN-MAS-ELE-1120 Submission of Technical Datasheets of GI Conduit 10 06-Jun-19 17-Jun-19 0% 66 Submission of Technical Datasheets of GI Conduit
T4-EN-MAS-ELE-1130 Submission of Technical Datasheets of PVC Conduit 5 13-Jun-19 18-Jun-19 0% 66 Submission of Technical Datasheets of PVC Conduit
T4-EN-MAS-ELE-1140 Submission of Technical Datasheets of Switch & Socket 5 27-Jun-19 02-Jul-19 0% 79 Submission of Technical Datasheets of Switch & Socket
T4-EN-MAS-ELE-1150 Submission of Technical Datasheets of HT Cables 5 21-Jun-19 26-Jun-19 0% 79 Submission of Technical Datasheets of HT Cables
T4-EN-MAS-ELE-1160 Submission of Technical Datasheets of LT Cables- Power & Control 7 14-Jun-19 21-Jun-19 0% 66 Submission of Technical Datasheets of LT Cables- Power & Control
T4-EN-MAS-ELE-1170 Submission of Technical Datasheets of FS Cables- Power & Control 7 14-Jun-19 21-Jun-19 0% 66 Submission of Technical Datasheets of FS Cables- Power & Control
T4-EN-MAS-ELE-1180 Submission of Technical Datasheets of Cable Trays & Trunking 5 19-Jun-19 24-Jun-19 0% 68 Submission of Technical Datasheets of Cable Trays & Trunking
T4-EN-MAS-ELE-1190 Submission of Technical Datasheets of Wires 5 19-Jun-19 24-Jun-19 0% 68 Submission of Technical Datasheets of Wires
T4-EN-MAS-ELE-1200 Submission of Technical Datasheets of Industrial Sockets with MCB Control 5 27-Jun-19 02-Jul-19 0% 79 Submission of Technical Datasheets of Industrial Sockets with MCB Control
T4-EN-MAS-ELE-1210 Submission of Technical Datasheets of Glands & Lugs 5 30-May-19 04-Jun-19 0% 66 Submission of Technical Datasheets of Glands & Lugs
T4-EN-MAS-ELE-1220 Submission of Technical Datasheets of Aviation Lighting Led 5 29-Jun-19 04-Jul-19 0% 115 Submission of Technical Datasheets of Aviation Lighting Led
T4-EN-MAS-ELE-1230 Submission of Technical Datasheets of HT Termination Kit 5 21-Jun-19 26-Jun-19 0% 79 Submission of Technical Datasheets of HT Termination Kit
T4-EN-MAS-ELE-1240 Submission of Technical Datasheets of Copper Strip & Earthing 5 24-Jun-19 28-Jun-19 0% 79 Submission of Technical Datasheets of Copper Strip & Earthing
T4-EN-MAS-ELE-1250 Submission of Technical Datasheets of GI Strip 5 24-Jun-19 28-Jun-19 0% 79 Submission of Technical Datasheets of GI Strip
T4-EN-MAS-ELE-1400 Submission of Technical Datasheets of MS Earth Strip 5 29-Jun-19 04-Jul-19 0% 162 Submission of Technical Datasheets of MS Earth Strip
T4-EN-MAS-ELE-1410 Submission of Technical Datasheets of Maintenance Free Earthing 5 29-Jun-19 04-Jul-19 0% 171 Submission of Technical Datasheets of Maintenance Free Earthing
APPROVAL 32 06-Jun-19 12-Jul-19 248 12-Jul-19, APPROVAL
T4-EN-MAS-ELE-1260 Approval of Technical Datasheets of GI Conduit 7 18-Jun-19 25-Jun-19 0% 214 Approval of Technical Datasheets of GI Conduit
T4-EN-MAS-ELE-1270 Approval of Technical Datasheets of PVC Conduit 7 19-Jun-19 26-Jun-19 0% 213 Approval of Technical Datasheets of PVC Conduit
T4-EN-MAS-ELE-1280 Approval of Technical Datasheets of Switch & Socket 7 03-Jul-19 10-Jul-19 0% 250 Approval of Technical Datasheets of Switch & Socket
T4-EN-MAS-ELE-1290 Approval of Technical Datasheets of HT Cables 7 27-Jun-19 04-Jul-19 0% 234 Approval of Technical Datasheets of HT Cables
T4-EN-MAS-ELE-1300 Approval of Technical Datasheets of LT Cables- Power & Control 7 22-Jun-19 29-Jun-19 0% 66 Approval of Technical Datasheets of LT Cables- Power & Control
T4-EN-MAS-ELE-1310 Approval of Technical Datasheets of FS Cables- Power & Control 7 22-Jun-19 29-Jun-19 0% 66 Approval of Technical Datasheets of FS Cables- Power & Control
T4-EN-MAS-ELE-1320 Approval of Technical Datasheets of Cable Trays & Trunking 7 25-Jun-19 02-Jul-19 0% 148 Approval of Technical Datasheets of Cable Trays & Trunking
T4-EN-MAS-ELE-1330 Approval of Technical Datasheets of Wires 7 25-Jun-19 02-Jul-19 0% 68 Approval of Technical Datasheets of Wires
T4-EN-MAS-ELE-1340 Approval of Technical Datasheets of Industrial Sockets with MCB Control 7 03-Jul-19 10-Jul-19 0% 79 Approval of Technical Datasheets of Industrial Sockets with MCB Control
T4-EN-MAS-ELE-1350 Approval of Technical Datasheets of Glands & Lugs 7 06-Jun-19 13-Jun-19 0% 233 Approval of Technical Datasheets of Glands & Lugs
T4-EN-MAS-ELE-1360 Approval of Technical Datasheets of Aviation Lighting Led 7 05-Jul-19 12-Jul-19 0% 232 Approval of Technical Datasheets of Aviation Lighting Led
T4-EN-MAS-ELE-1370 Approval of Technical Datasheets of HT Termination Kit 7 27-Jun-19 04-Jul-19 0% 81 Approval of Technical Datasheets of HT Termination Kit
T4-EN-MAS-ELE-1380 Approval of Technical Datasheets of Copper Strip & Earthing 7 29-Jun-19 06-Jul-19 0% 167 Approval of Technical Datasheets of Copper Strip & Earthing
T4-EN-MAS-ELE-1390 Approval of Technical Datasheets of GI Strip 7 29-Jun-19 06-Jul-19 0% 167 Approval of Technical Datasheets of GI Strip
T4-EN-MAS-ELE-1420 Approval of Technical Datasheets of MS Earth Strip 7 05-Jul-19 12-Jul-19 0% 162 Approval of Technical Datasheets of MS Earth Strip
T4-EN-MAS-ELE-1430 Approval of Technical Datasheets of Maintenance Free Earthing 7 05-Jul-19 12-Jul-19 0% 171 Approval of Technical Datasheets of Maintenance Free Earthing
METHOD STATEMENTS & ITP 88 28-May-19 10-Sep-19 243 10-Sep-19, METHOD STATEMENTS & ITP
PHE 69 31-May-19 21-Aug-19 254 21-Aug-19, PHE
SUBMISSION 62 31-May-19 12-Aug-19 254 12-Aug-19, SUBMISSION
T4-EN-MSS-PHE-1000 Submission of Method Statement for Installation of GI Pipes & Fittings 5 31-May-19 07-Jun-19 0% 192 Submission of Method Statement for Installation of GI Pipes & Fittings
T4-EN-MSS-PHE-1010 Submission of Method Statement for Installation of HDPE Pipes & Fittings 6 07-Jun-19 13-Jun-19 0% 217 Submission of Method Statement for Installation of HDPE Pipes & Fittings
T4-EN-MSS-PHE-1020 Submission of Method Statement for Installation of C.I. Class LA Pipes & Fittings 8 14-Jun-19 22-Jun-19 0% 217 Submission of Method Statement for Installation of C.I. Class LA Pipes & Fittings
T4-EN-MSS-PHE-1030 Submission of Method Statement for Installation of UPVC Pipes & Fittings 5 24-Jun-19 28-Jun-19 0% 217 Submission of Method Statement for Installation of UPVC Pipes & Fittings
T4-EN-MSS-PHE-1040 Submission of Method Statement for Installation of CPVC Pipes & Fittings 5 24-Jun-19 28-Jun-19 0% 217 Submission of Method Statement for Installation of CPVC Pipes & Fittings
T4-EN-MSS-PHE-1050 Submission of Method Statement for Installation of Supports / Brackets 2 29-Jun-19 01-Jul-19 0% 217 Submission of Method Statement for Installation of Supports / Brackets
T4-EN-MSS-PHE-1060 Submission of Method Statement for Installation of Low Noise Pipes & Fittings 5 26-Jun-19 01-Jul-19 0% 217 Submission of Method Statement for Installation of Low Noise Pipes & Fittings
T4-EN-MSS-PHE-1070 Submission of Method Statement for Installation of Screwed Valves 6 02-Jul-19 08-Jul-19 0% 217 Submission of Method Statement for Installation of Screwed Valves
T4-EN-MSS-PHE-1080 Submission of Method Statement for Installation of Flanged Valves 5 03-Jul-19 08-Jul-19 0% 217 Submission of Method Statement for Installation of Flanged Valves
T4-EN-MSS-PHE-1090 Submission of Method Statement for Installation of Flexible Neoprene Rubber Expansion Joints 9 09-Jul-19 18-Jul-19 0% 217 Submission of Method Statement for Installation of Flexible Neoprene Rubber Expansion Joints
T4-EN-MSS-PHE-1100 Submission of Method Statement for Installation of Brick Masonry Inspection Chambers 5 13-Jul-19 18-Jul-19 0% 217 Submission of Method Statement for Installation of Brick Masonry Inspection Chambers

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 15 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
Float
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-EN-MSS-PHE-1110 Submission of Method Statement for Installation of Puddle Flanges For Water Storage Tanks 3 19-Jul-19 22-Jul-19 0% 217 Submission of Method Statement for Installation of Puddle Flanges For Water Storage Tanks
T4-EN-MSS-PHE-1120 Submission of Method Statement for Installation of PHE Pumps 4 23-Jul-19 26-Jul-19 0% 217 Submission of Method Statement for Installation of PHE Pumps
T4-EN-MSS-PHE-1130 Submission of Method Statement for Installation of Water Closet 7 27-Jul-19 03-Aug-19 0% 217 Submission of Method Statement for Installation of Water Closet
T4-EN-MSS-PHE-1140 Submission of Method Statement for Installation of Wash Basin 5 05-Aug-19 09-Aug-19 0% 254 Submission of Method Statement for Installation of Wash Basin
T4-EN-MSS-PHE-1150 Submission of Method Statement for Installation of Urinal 2 10-Aug-19 12-Aug-19 0% 254 Submission of Method Statement for Installation of Urinal
APPROVAL 64 07-Jun-19 21-Aug-19 254 21-Aug-19, APPROVAL
T4-EN-MSS-PHE-1160 Approval of Method Statement for Installation of GI Pipes & Fittings 7 07-Jun-19 14-Jun-19 0% 267 Approval of Method Statement for Installation of GI Pipes & Fittings
T4-EN-MSS-PHE-1170 Approval of Method Statement for Installation of HDPE Pipes & Fittings 7 14-Jun-19 21-Jun-19 0% 261 Approval of Method Statement for Installation of HDPE Pipes & Fittings
T4-EN-MSS-PHE-1180 Approval of Method Statement for Installation of C.I. Class LA Pipes & Fittings 7 24-Jun-19 01-Jul-19 0% 253 Approval of Method Statement for Installation of C.I. Class LA Pipes & Fittings
T4-EN-MSS-PHE-1190 Approval of Method Statement for Installation of UPVC Pipes & Fittings 7 29-Jun-19 06-Jul-19 0% 248 Approval of Method Statement for Installation of UPVC Pipes & Fittings
T4-EN-MSS-PHE-1200 Approval of Method Statement for Installation of CPVC Pipes & Fittings 7 29-Jun-19 06-Jul-19 0% 248 Approval of Method Statement for Installation of CPVC Pipes & Fittings
T4-EN-MSS-PHE-1210 Approval of Method Statement for Installation of Supports / Brackets 7 02-Jul-19 09-Jul-19 0% 246 Approval of Method Statement for Installation of Supports / Brackets
T4-EN-MSS-PHE-1220 Approval of Method Statement for Installation of Low Noise Pipes & Fittings 7 02-Jul-19 09-Jul-19 0% 246 Approval of Method Statement for Installation of Low Noise Pipes & Fittings
T4-EN-MSS-PHE-1230 Approval of Method Statement for Installation of Screwed Valves 7 09-Jul-19 16-Jul-19 0% 240 Approval of Method Statement for Installation of Screwed Valves
T4-EN-MSS-PHE-1240 Approval of Method Statement for Installation of Flanged Valves 7 09-Jul-19 16-Jul-19 0% 240 Approval of Method Statement for Installation of Flanged Valves
T4-EN-MSS-PHE-1250 Approval of Method Statement for Installation of Flexible Neoprene Rubber Expansion Joints 7 19-Jul-19 26-Jul-19 0% 231 Approval of Method Statement for Installation of Flexible Neoprene Rubber Expansion Joints
T4-EN-MSS-PHE-1260 Approval of Method Statement for Installation of Brick Masonry Inspection Chambers 7 19-Jul-19 26-Jul-19 0% 231 Approval of Method Statement for Installation of Brick Masonry Inspection Chambers
T4-EN-MSS-PHE-1270 Approval of Method Statement for Installation of Puddle Flanges For Water Storage Tanks 7 23-Jul-19 30-Jul-19 0% 228 Approval of Method Statement for Installation of Puddle Flanges For Water Storage Tanks
T4-EN-MSS-PHE-1280 Approval of Method Statement for Installation of PHE Pumps 7 27-Jul-19 03-Aug-19 0% 228 Approval of Method Statement for Installation of PHE Pumps
T4-EN-MSS-PHE-1290 Approval of Method Statement for Installation of Water Closet 7 05-Aug-19 12-Aug-19 0% 217 Approval of Method Statement for Installation of Water Closet
T4-EN-MSS-PHE-1300 Approval of Method Statement for Installation of Wash Basin 7 10-Aug-19 19-Aug-19 0% 256 Approval of Method Statement for Installation of Wash Basin
T4-EN-MSS-PHE-1310 Approval of Method Statement for Installation of Urinal 7 13-Aug-19 21-Aug-19 0% 254 Approval of Method Statement for Installation of Urinal
FF 85 31-May-19 10-Sep-19 243 10-Sep-19, FF
SUBMISSION 78 31-May-19 31-Aug-19 192 31-Aug-19, SUBMISSION
T4-EN-MSS-FF-1320 Submission of Method Statement for Installation of Fire Hydrant, Sprinkler Pipes & Fittings 5 31-May-19 07-Jun-19 0% 192 Submission of Method Statement for Installation of Fire Hydrant, Sprinkler Pipes & Fittings
T4-EN-MSS-FF-1330 Submission of Method Statement for Installation of Installation Control Valves 5 18-Jun-19 22-Jun-19 0% 192 Submission of Method Statement for Installation of Installation Control Valves
T4-EN-MSS-FF-1340 Submission of Method Statement for Installation of Sprinklers Heads 6 20-Jul-19 26-Jul-19 0% 192 Submission of Method Statement for Installation of Sprinklers Heads
T4-EN-MSS-FF-1350 Submission of Method Statement for Installation of Sprinkler Flexible Drops 7 27-Jul-19 03-Aug-19 0% 192 Submission of Method Statement for Installation of Sprinkler Flexible Drops
T4-EN-MSS-FF-1360 Submission of Method Statement for Installation of Supports / Brackets 5 30-Jul-19 03-Aug-19 0% 192 Submission of Method Statement for Installation of Supports / Brackets
T4-EN-MSS-FF-1370 Submission of Method Statement for Installation of Fire Fighting Accessories 5 12-Aug-19 17-Aug-19 0% 192 Submission of Method Statement for Installation of Fire Fighting Accessories
T4-EN-MSS-FF-1380 Submission of Method Statement for Installation of Flanged Valves 5 12-Aug-19 17-Aug-19 0% 192 Submission of Method Statement for Installation of Flanged Valves
T4-EN-MSS-FF-1390 Submission of Method Statement for Installation of Screwed Valves 4 19-Aug-19 22-Aug-19 0% 192 Submission of Method Statement for Installation of Screwed Valves
T4-EN-MSS-FF-1400 Submission of Method Statement for Installation of Flexible Neoprene Rubber Expansion Joints 4 19-Aug-19 22-Aug-19 0% 192 Submission of Method Statement for Installation of Flexible Neoprene Rubber Expansio
T4-EN-MSS-FF-1410 Submission of Method Statement for Installation of Fire Pumps 8 23-Aug-19 31-Aug-19 0% 192 Submission of Method Statement for Installation of Fire Pumps
T4-EN-MSS-FF-1420 Submission of Method Statement for Color Scheme For FF Services 5 27-Aug-19 31-Aug-19 0% 192 Submission of Method Statement for Color Scheme For FF Services
APPROVAL 80 07-Jun-19 10-Sep-19 243 10-Sep-19, APPROVAL
T4-EN-MSS-FF-1430 Approval of Method Statement for Installation of Fire Hydrant, Sprinkler Pipes & Fittings 7 07-Jun-19 14-Jun-19 0% 265 Approval of Method Statement for Installation of Fire Hydrant, Sprinkler Pipes & Fittings
T4-EN-MSS-FF-1440 Approval of Method Statement for Installation of Installation Control Valves 7 24-Jun-19 01-Jul-19 0% 251 Approval of Method Statement for Installation of Installation Control Valves
T4-EN-MSS-FF-1450 Approval of Method Statement for Installation of Sprinklers Heads 7 27-Jul-19 03-Aug-19 0% 273 Approval of Method Statement for Installation of Sprinklers Heads
T4-EN-MSS-FF-1460 Approval of Method Statement for Installation of Sprinkler Flexible Drops 7 05-Aug-19 12-Aug-19 0% 266 Approval of Method Statement for Installation of Sprinkler Flexible Drops
T4-EN-MSS-FF-1470 Approval of Method Statement for Installation of Supports / Brackets 7 05-Aug-19 12-Aug-19 0% 215 Approval of Method Statement for Installation of Supports / Brackets
T4-EN-MSS-FF-1480 Approval of Method Statement for Installation of Fire Fighting Accessories 7 19-Aug-19 26-Aug-19 0% 209 Approval of Method Statement for Installation of Fire Fighting Accessories
T4-EN-MSS-FF-1490 Approval of Method Statement for Installation of Flanged Valves 7 19-Aug-19 26-Aug-19 0% 204 Approval of Method Statement for Installation of Flanged Valves
T4-EN-MSS-FF-1500 Approval of Method Statement for Installation of Screwed Valves 7 23-Aug-19 30-Aug-19 0% 200 Approval of Method Statement for Installation of Screwed Valves
T4-EN-MSS-FF-1510 Approval of Method Statement for Installation of Flexible Neoprene Rubber Expansion Joints 7 23-Aug-19 30-Aug-19 0% 200 Approval of Method Statement for Installation of Flexible Neoprene Rubber Expansio
T4-EN-MSS-FF-1520 Approval of Method Statement for Installation of Fire Pumps 7 03-Sep-19 10-Sep-19 0% 203 Approval of Method Statement for Installation of Fire Pumps
T4-EN-MSS-FF-1530 Approval of Method Statement for Color Scheme For FF Services 7 03-Sep-19 10-Sep-19 0% 192 Approval of Method Statement for Color Scheme For FF Services
HVAC 76 28-May-19 26-Aug-19 140 26-Aug-19, HVAC
SUBMISSION 69 28-May-19 17-Aug-19 140 17-Aug-19, SUBMISSION
T4-EN-MSS-HVAC-1540Submission of Method Statement for Installation of Piping 8 28-May-19 07-Jun-19 0% 133 Submission of Method Statement for Installation of Piping
T4-EN-MSS-HVAC-1550Submission of Method Statement for Installation of Ducting 6 07-Jun-19 13-Jun-19 0% 140 Submission of Method Statement for Installation of Ducting
T4-EN-MSS-HVAC-1560Submission of Method Statement for Installation of Insulation 9 14-Jun-19 24-Jun-19 0% 140 Submission of Method Statement for Installation of Insulation

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 16 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
Float
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-EN-MSS-HVAC-1570Submission of Method Statement for Installation of Air Distribution Product 4 25-Jun-19 28-Jun-19 0% 140 Submission of Method Statement for Installation of Air Distribution Product
T4-EN-MSS-HVAC-1580Submission of Method Statement for Installation of FCU 4 27-Jun-19 01-Jul-19 0% 140 Submission of Method Statement for Installation of FCU
T4-EN-MSS-HVAC-1590Submission of Method Statement for Installation of Fan 6 02-Jul-19 08-Jul-19 0% 140 Submission of Method Statement for Installation of Fan
T4-EN-MSS-HVAC-1600Submission of Method Statement for Installation of Pump 9 09-Jul-19 18-Jul-19 0% 140 Submission of Method Statement for Installation of Pump
T4-EN-MSS-HVAC-1610Submission of Method Statement for Installation of Pressurisation Unit 3 19-Jul-19 22-Jul-19 0% 140 Submission of Method Statement for Installation of Pressurisation Unit
T4-EN-MSS-HVAC-1620Submission of Method Statement for Installation of Cooling Tower 4 23-Jul-19 26-Jul-19 0% 140 Submission of Method Statement for Installation of Cooling Tower
T4-EN-MSS-HVAC-1630Submission of Method Statement for Installation of AHU 7 27-Jul-19 03-Aug-19 0% 140 Submission of Method Statement for Installation of AHU
T4-EN-MSS-HVAC-1640Submission of Method Statement for Installation of FCU Valve Station 5 05-Aug-19 09-Aug-19 0% 140 Submission of Method Statement for Installation of FCU Valve Station
T4-EN-MSS-HVAC-1650Submission of Method Statement for Installation of Air Seperator 4 08-Aug-19 12-Aug-19 0% 140 Submission of Method Statement for Installation of Air Seperator
T4-EN-MSS-HVAC-1660Submission of Method Statement for Installation of PHE Unit 5 07-Aug-19 12-Aug-19 0% 140 Submission of Method Statement for Installation of PHE Unit
T4-EN-MSS-HVAC-1670Submission of Method Statement for Installation of Heat Recovery Unit 4 13-Aug-19 17-Aug-19 0% 140 Submission of Method Statement for Installation of Heat Recovery Unit
APPROVAL 68 07-Jun-19 26-Aug-19 140 26-Aug-19, APPROVAL
T4-EN-MSS-HVAC-1680Approval of Method Statement for Installation of Piping 7 07-Jun-19 14-Jun-19 0% 201 Approval of Method Statement for Installation of Piping
T4-EN-MSS-HVAC-1690Approval of Method Statement for Installation of Ducting 7 14-Jun-19 21-Jun-19 0% 195 Approval of Method Statement for Installation of Ducting
T4-EN-MSS-HVAC-1700Approval of Method Statement for Installation of Insulation 7 25-Jun-19 02-Jul-19 0% 186 Approval of Method Statement for Installation of Insulation
T4-EN-MSS-HVAC-1710Approval of Method Statement for Installation of Air Distribution Product 7 29-Jun-19 06-Jul-19 0% 182 Approval of Method Statement for Installation of Air Distribution Product
T4-EN-MSS-HVAC-1720Approval of Method Statement for Installation of FCU 7 02-Jul-19 09-Jul-19 0% 180 Approval of Method Statement for Installation of FCU
T4-EN-MSS-HVAC-1730Approval of Method Statement for Installation of Fan 7 09-Jul-19 16-Jul-19 0% 174 Approval of Method Statement for Installation of Fan
T4-EN-MSS-HVAC-1740Approval of Method Statement for Installation of Pump 7 19-Jul-19 26-Jul-19 0% 165 Approval of Method Statement for Installation of Pump
T4-EN-MSS-HVAC-1750Approval of Method Statement for Installation of Pressurisation Unit 7 23-Jul-19 30-Jul-19 0% 162 Approval of Method Statement for Installation of Pressurisation Unit
T4-EN-MSS-HVAC-1760Approval of Method Statement for Installation of Cooling Tower 7 27-Jul-19 03-Aug-19 0% 158 Approval of Method Statement for Installation of Cooling Tower
T4-EN-MSS-HVAC-1770Approval of Method Statement for Installation of AHU 7 05-Aug-19 12-Aug-19 0% 151 Approval of Method Statement for Installation of AHU
T4-EN-MSS-HVAC-1780Approval of Method Statement for Installation of FCU Valve Station 7 10-Aug-19 19-Aug-19 0% 146 Approval of Method Statement for Installation of FCU Valve Station
T4-EN-MSS-HVAC-1790Approval of Method Statement for Installation of Air Seperator 7 13-Aug-19 21-Aug-19 0% 144 Approval of Method Statement for Installation of Air Seperator
T4-EN-MSS-HVAC-1800Approval of Method Statement for Installation of PHE Unit 7 13-Aug-19 21-Aug-19 0% 144 Approval of Method Statement for Installation of PHE Unit
T4-EN-MSS-HVAC-1810Approval of Method Statement for Installation of Heat Recovery Unit 7 19-Aug-19 26-Aug-19 0% 140 Approval of Method Statement for Installation of Heat Recovery Unit
ELE 85 31-May-19 10-Sep-19 133 10-Sep-19, ELE
SUBMISSION 78 31-May-19 31-Aug-19 133 31-Aug-19, SUBMISSION
T4-EN-MSS-ELE-1820 Submission of Method Statement for Installation of Embedded PVC Conduit & Accessories 5 31-May-19 07-Jun-19 0% 133 Submission of Method Statement for Installation of Embedded PVC Conduit & Accessories
T4-EN-MSS-ELE-1830 Submission of Method Statement for Installation of Lightning Protection Down conductor tape System. 6 07-Jun-19 13-Jun-19 0% 133 Submission of Method Statement for Installation of Lightning Protection Down conductor tape System.
T4-EN-MSS-ELE-1840 Submission of Method Statement for Installation of Exposed PVC Conduit & Accessories 8 14-Jun-19 22-Jun-19 0% 133 Submission of Method Statement for Installation of Exposed PVC Conduit & Accessories
T4-EN-MSS-ELE-1850 Submission of Method Statement for Installation of GI Conduit And Accessories 5 24-Jun-19 28-Jun-19 0% 133 Submission of Method Statement for Installation of GI Conduit And Accessories
T4-EN-MSS-ELE-1860 Submission of Method Statement for Installation of Cable Tray And Support 5 26-Jun-19 01-Jul-19 0% 133 Submission of Method Statement for Installation of Cable Tray And Support
T4-EN-MSS-ELE-1870 Submission of Method Statement for Installation of Earthing System 6 02-Jul-19 08-Jul-19 0% 133 Submission of Method Statement for Installation of Earthing System
T4-EN-MSS-ELE-1880 Submission of Method Statement for Installation of Isolator Installation 9 09-Jul-19 18-Jul-19 0% 133 Submission of Method Statement for Installation of Isolator Installation
T4-EN-MSS-ELE-1890 Submission of Method Statement for Installation of DB Installation 5 17-Jul-19 22-Jul-19 0% 133 Submission of Method Statement for Installation of DB Installation
T4-EN-MSS-ELE-1900 Submission of Method Statement for Installation of Wire Pulling 4 23-Jul-19 26-Jul-19 0% 133 Submission of Method Statement for Installation of Wire Pulling
T4-EN-MSS-ELE-1910 Submission of Method Statement for Installation of Exposed Cable Laying ( HT / LT ) 7 27-Jul-19 03-Aug-19 0% 133 Submission of Method Statement for Installation of Exposed Cable Laying ( HT / LT )
T4-EN-MSS-ELE-1920 Submission of Method Statement for Installation of Switch - Socket 5 05-Aug-19 09-Aug-19 0% 133 Submission of Method Statement for Installation of Switch - Socket
T4-EN-MSS-ELE-1930 Submission of Method Statement for Installation of LT Panels 5 07-Aug-19 12-Aug-19 0% 133 Submission of Method Statement for Installation of LT Panels
T4-EN-MSS-ELE-1940 Submission of Method Statement for Installation of HT Panels 5 07-Aug-19 12-Aug-19 0% 133 Submission of Method Statement for Installation of HT Panels
T4-EN-MSS-ELE-1950 Submission of Method Statement for Installation of Light Fixture 4 13-Aug-19 17-Aug-19 0% 133 Submission of Method Statement for Installation of Light Fixture
T4-EN-MSS-ELE-1960 Submission of Method Statement for HT Cable Termination 4 19-Aug-19 22-Aug-19 0% 133 Submission of Method Statement for HT Cable Termination
T4-EN-MSS-ELE-1970 Submission of Method Statement for LT Cable Termination 4 19-Aug-19 22-Aug-19 0% 133 Submission of Method Statement for LT Cable Termination
T4-EN-MSS-ELE-1980 Submission of Method Statement for Installation of Air Craft Warning Light 8 23-Aug-19 31-Aug-19 0% 133 Submission of Method Statement for Installation of Air Craft Warning Light
T4-EN-MSS-ELE-1990 Submission of Method Statement for Installation of Transformer 5 27-Aug-19 31-Aug-19 0% 133 Submission of Method Statement for Installation of Transformer
APPROVAL 80 07-Jun-19 10-Sep-19 133 10-Sep-19, APPROVAL
T4-EN-MSS-ELE-2000 Approval of Method Statement for Installation of Embedded PVC Conduit & Accessories 7 07-Jun-19 14-Jun-19 0% 206 Approval of Method Statement for Installation of Embedded PVC Conduit & Accessories
T4-EN-MSS-ELE-2010 Approval of Method Statement for Installation of Lightning Protection Down conductor tape System. 7 14-Jun-19 21-Jun-19 0% 200 Approval of Method Statement for Installation of Lightning Protection Down conductor tape System.
T4-EN-MSS-ELE-2020 Approval of Method Statement for Installation of Exposed PVC Conduit & Accessories 7 24-Jun-19 01-Jul-19 0% 192 Approval of Method Statement for Installation of Exposed PVC Conduit & Accessories
T4-EN-MSS-ELE-2030 Approval of Method Statement for Installation of GI Conduit And Accessories 7 29-Jun-19 06-Jul-19 0% 187 Approval of Method Statement for Installation of GI Conduit And Accessories

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 17 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
Float
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-EN-MSS-ELE-2040 Approval of Method Statement for Installation of Cable Tray And Support 7 02-Jul-19 09-Jul-19 0% 185 Approval of Method Statement for Installation of Cable Tray And Support
T4-EN-MSS-ELE-2050 Approval of Method Statement for Installation of Earthing System 7 09-Jul-19 16-Jul-19 0% 179 Approval of Method Statement for Installation of Earthing System
T4-EN-MSS-ELE-2060 Approval of Method Statement for Installation of Isolator Installation 7 19-Jul-19 26-Jul-19 0% 170 Approval of Method Statement for Installation of Isolator Installation
T4-EN-MSS-ELE-2070 Approval of Method Statement for Installation of DB Installation 7 23-Jul-19 30-Jul-19 0% 167 Approval of Method Statement for Installation of DB Installation
T4-EN-MSS-ELE-2080 Approval of Method Statement for Installation of Wire Pulling 7 27-Jul-19 03-Aug-19 0% 163 Approval of Method Statement for Installation of Wire Pulling
T4-EN-MSS-ELE-2090 Approval of Method Statement for Installation of Exposed Cable Laying ( HT / LT ) 7 05-Aug-19 12-Aug-19 0% 156 Approval of Method Statement for Installation of Exposed Cable Laying ( HT / LT )
T4-EN-MSS-ELE-2100 Approval of Method Statement for Installation of Switch - Socket 7 10-Aug-19 19-Aug-19 0% 151 Approval of Method Statement for Installation of Switch - Socket
T4-EN-MSS-ELE-2110 Approval of Method Statement for Installation of LT Panels 7 13-Aug-19 21-Aug-19 0% 149 Approval of Method Statement for Installation of LT Panels
T4-EN-MSS-ELE-2120 Approval of Method Statement for Installation of HT Panels 7 13-Aug-19 21-Aug-19 0% 149 Approval of Method Statement for Installation of HT Panels
T4-EN-MSS-ELE-2130 Approval of Method Statement for Installation of Light Fixture 7 19-Aug-19 26-Aug-19 0% 145 Approval of Method Statement for Installation of Light Fixture
T4-EN-MSS-ELE-2140 Approval of Method Statement for HT Cable Termination 7 23-Aug-19 30-Aug-19 0% 141 Approval of Method Statement for HT Cable Termination
T4-EN-MSS-ELE-2150 Approval of Method Statement for LT Cable Termination 7 23-Aug-19 30-Aug-19 0% 141 Approval of Method Statement for LT Cable Termination
T4-EN-MSS-ELE-2160 Approval of Method Statement for Installation of Air Craft Warning Light 7 03-Sep-19 10-Sep-19 0% 133 Approval of Method Statement for Installation of Air Craft Warning Light
T4-EN-MSS-ELE-2170 Approval of Method Statement for Installation of Transformer 7 03-Sep-19 10-Sep-19 0% 133 Approval of Method Statement for Installation of Transformer

PROCUREMENT 539 13-Jun-19 10-Dec-20 51 10-Dec

HVAC 470 25-Jun-19 14-Oct-20 108 14-Oct-20, HVAC


CLASS A 316 05-Aug-19 22-Jun-20 136 22-Jun-20, CLASS A
Expansion Tank 80 09-Dec-19 27-Feb-20 82 27-Feb-20, Expansion Tank
T4-PRO-HVAC-1000 PO Placement - Expansion Tank 14 09-Dec-19 26-Dec-19 0% 58 PO Placement - Expansion Tank
T4-PRO-HVAC-1015 Manufacturing - Expansion Tank 42 26-Dec-19 06-Feb-20 0% 82 Manufacturing - Expansion Tank
T4-PRO-HVAC-1025 Delivery at site - Expansion Tank 21 06-Feb-20 27-Feb-20 0% 82 Delivery at site - Expansion Tank
Air Separator 170 20-Aug-19 11-Feb-20 93 11-Feb-20, Air Separator
T4-PRO-HVAC-1580 PO Placement - Air Separator 14 20-Aug-19 06-Sep-19 0% 69 PO Placement - Air Separator
T4-PRO-HVAC-1590 Manufacturing - Air Separator 42 06-Sep-19 20-Oct-19 0% 93 Manufacturing - Air Separator
T4-PRO-HVAC-1600 Delivery at site - Air Separator 21 21-Jan-20 11-Feb-20 0% 93 Delivery at site - Air Separator
Pressurisation System 82 06-Nov-19 28-Jan-20 109 28-Jan-20, Pressurisation System
T4-PRO-HVAC-1610 PO Placement - Pressurisation System 14 06-Nov-19 25-Nov-19 0% 79 PO Placement - Pressurisation System
T4-PRO-HVAC-1620 Manufacturing - Pressurisation System 42 25-Nov-19 07-Jan-20 0% 109 Manufacturing - Pressurisation System
T4-PRO-HVAC-1630 Delivery at site - Pressurisation System 21 07-Jan-20 28-Jan-20 0% 109 Delivery at site - Pressurisation System
Secondary Chilled Water Pump 122 16-Sep-19 20-Jan-20 104 20-Jan-20, Secondary Chilled Water Pump
T4-PRO-HVAC-1640 PO Placement - Secondary Chilled Water Pump 14 16-Sep-19 03-Oct-19 0% 76 PO Placement - Secondary Chilled Water Pump
T4-PRO-HVAC-1650 Manufacturing - Secondary Chilled Water Pump 84 03-Oct-19 30-Dec-19 0% 104 Manufacturing - Secondary Chilled Water Pump
T4-PRO-HVAC-1660 Delivery at site - Secondary Chilled Water Pump 21 30-Dec-19 20-Jan-20 0% 104 Delivery at site - Secondary Chilled Water Pump
Primary Chilled Water Pump 124 04-Oct-19 08-Feb-20 86 08-Feb-20, Primary Chilled Water Pump
T4-PRO-HVAC-1670 PO Placement - Primary Chilled Water Pump 14 04-Oct-19 23-Oct-19 0% 63 PO Placement - Primary Chilled Water Pump
T4-PRO-HVAC-1680 Manufacturing - Primary Chilled Water Pump 84 23-Oct-19 18-Jan-20 0% 86 Manufacturing - Primary Chilled Water Pump
T4-PRO-HVAC-1690 Delivery at site - Primary Chilled Water Pump 21 18-Jan-20 08-Feb-20 0% 86 Delivery at site - Primary Chilled Water Pump
Condenser Pumps 123 27-Sep-19 01-Feb-20 85 01-Feb-20, Condenser Pumps
T4-PRO-HVAC-1700 PO Placement - Condenser Pumps 14 27-Sep-19 16-Oct-19 0% 62 PO Placement - Condenser Pumps
T4-PRO-HVAC-1710 Manufacturing - Condenser Pumps 84 16-Oct-19 11-Jan-20 0% 85 Manufacturing - Condenser Pumps
T4-PRO-HVAC-1720 Delivery at site - Condenser Pumps 21 11-Jan-20 01-Feb-20 0% 85 Delivery at site - Condenser Pumps
VFD Panel for Pumps 109 27-Sep-19 18-Jan-20 127 18-Jan-20, VFD Panel for Pumps
T4-PRO-HVAC-1730 PO Placement - VFD Panel for Pumps 14 27-Sep-19 16-Oct-19 0% 92 PO Placement - VFD Panel for Pumps
T4-PRO-HVAC-1740 Manufacturing - VFD Panel for Pumps 70 16-Oct-19 28-Dec-19 0% 127 Manufacturing - VFD Panel for Pumps
T4-PRO-HVAC-1750 Delivery at site - VFD Panel for Pumps 21 28-Dec-19 18-Jan-20 0% 127 Delivery at site - VFD Panel for Pumps
Filter Feed Pumps 109 27-Sep-19 18-Jan-20 93 18-Jan-20, Filter Feed Pumps
T4-PRO-HVAC-1760 PO Placement - Filter Feed Pumps 14 27-Sep-19 16-Oct-19 0% 68 PO Placement - Filter Feed Pumps
T4-PRO-HVAC-1770 Manufacturing - Filter Feed Pumps 70 16-Oct-19 28-Dec-19 0% 93 Manufacturing - Filter Feed Pumps
T4-PRO-HVAC-1780 Delivery at site - Filter Feed Pumps 21 28-Dec-19 18-Jan-20 0% 93 Delivery at site - Filter Feed Pumps
Cooling Tower 123 26-Sep-19 31-Jan-20 228 31-Jan-20, Cooling Tower
T4-PRO-HVAC-1790 PO Placement - Cooling Tower 14 26-Sep-19 15-Oct-19 0% 165 PO Placement - Cooling Tower
T4-PRO-HVAC-1800 Manufacturing - Cooling Tower 84 15-Oct-19 10-Jan-20 0% 228 Manufacturing - Cooling Tower

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 18 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-PRO-HVAC-1810 Delivery at site - Cooling Tower 21 10-Jan-20 31-Jan-20 0% 228 Delivery at site - Cooling Tower
HRU with Energy Recovery Wheel 124 18-Oct-19 21-Feb-20 76 21-Feb-20, HRU with Energy Recovery Wheel
T4-PRO-HVAC-1820 PO Placement - HRU with Energy Recovery Wheel 14 18-Oct-19 06-Nov-19 0% 56 PO Placement - HRU with Energy Recovery Wheel
T4-PRO-HVAC-1830 Manufacturing - HRU with Energy Recovery Wheel 84 06-Nov-19 31-Jan-20 0% 76 Manufacturing - HRU with Energy Recovery Wheel
T4-PRO-HVAC-1840 Delivery at site - HRU with Energy Recovery Wheel 21 31-Jan-20 21-Feb-20 0% 76 Delivery at site - HRU with Energy Recovery Wheel
HRU with Energy Recovery Pipe 124 18-Oct-19 21-Feb-20 76 21-Feb-20, HRU with Energy Recovery Pipe
T4-PRO-HVAC-1850 PO Placement - HRU with Energy Recovery Pipe 14 18-Oct-19 06-Nov-19 0% 56 PO Placement - HRU with Energy Recovery Pipe
T4-PRO-HVAC-1860 Manufacturing - HRU with Energy Recovery Pipe 84 06-Nov-19 31-Jan-20 0% 76 Manufacturing - HRU with Energy Recovery Pipe
T4-PRO-HVAC-1870 Delivery at site - HRU with Energy Recovery Pipe 21 31-Jan-20 21-Feb-20 0% 76 Delivery at site - HRU with Energy Recovery Pipe
Treated Fresh Air Unit 96 18-Oct-19 24-Jan-20 123 24-Jan-20, Treated Fresh Air Unit
T4-PRO-HVAC-1880 PO Placement - Treated Fresh Air Unit 14 18-Oct-19 06-Nov-19 0% 89 PO Placement - Treated Fresh Air Unit
T4-PRO-HVAC-1890 Manufacturing - Treated Fresh Air Unit 56 06-Nov-19 03-Jan-20 0% 123 Manufacturing - Treated Fresh Air Unit
T4-PRO-HVAC-1900 Delivery at site - Treated Fresh Air Unit 21 03-Jan-20 24-Jan-20 0% 123 Delivery at site - Treated Fresh Air Unit
AHU 266 05-Aug-19 03-May-20 31 03-May-20, AHU
T4-PRO-HVAC-2330 PO Placement - AHU 14 05-Aug-19 22-Aug-19 0% 22 PO Placement - AHU
T4-PRO-HVAC-2340 Manufacturing - AHU 49 22-Aug-19 13-Oct-19 0% 31 Manufacturing - AHU
T4-PRO-HVAC-2350 Delivery at site - AHU 200 13-Oct-19 03-May-20 0% 31 Delivery at site - AHU
Active Filteratio of AHU 259 20-Aug-19 10-May-20 0 10-May-20, Active Filteratio of AHU
T4-PRO-HVAC-1910 PO Placement - Active Filteration for AHU 14 20-Aug-19 06-Sep-19 0% 0 PO Placement - Active Filteration for AHU
T4-PRO-HVAC-1920 Manufacturing - Active Filteration for AHU 42 06-Sep-19 20-Oct-19 0% 0 Manufacturing - Active Filteration for AHU
T4-PRO-HVAC-1930 Delivery at site - Active Filteration for AHU 200 20-Oct-19 10-May-20 0% 0 Delivery at site - Active Filteration for AHU
Fan Coil Unit 316 05-Aug-19 22-Jun-20 136 22-Jun-20, Fan Coil Unit
T4-PRO-HVAC-1940 PO Placement - Fan Coil Unit 14 05-Aug-19 22-Aug-19 0% 101 PO Placement - Fan Coil Unit
T4-PRO-HVAC-1950 Manufacturing - Fan Coil Unit 49 22-Aug-19 13-Oct-19 0% 136 Manufacturing - Fan Coil Unit
T4-PRO-HVAC-1960 Delivery at site - Fan Coil Unit 250 13-Oct-19 22-Jun-20 0% 136 Delivery at site - Fan Coil Unit
Plate Type Heat Exchanger 121 28-Oct-19 28-Feb-20 69 28-Feb-20, Plate Type Heat Exchanger
T4-PRO-HVAC-1970 PO Placement - Plate Type Heat Exchanger 14 28-Oct-19 14-Nov-19 0% 50 PO Placement - Plate Type Heat Exchanger
T4-PRO-HVAC-1980 Manufacturing - Plate Type Heat Exchanger 84 14-Nov-19 07-Feb-20 0% 69 Manufacturing - Plate Type Heat Exchanger
T4-PRO-HVAC-1990 Delivery at site - Plate Type Heat Exchanger 21 07-Feb-20 28-Feb-20 0% 69 Delivery at site - Plate Type Heat Exchanger
Chemical Dosing System 147 20-Aug-19 19-Jan-20 279 19-Jan-20, Chemical Dosing System
T4-PRO-HVAC-2000 PO Placement - Chemical Dosing System 14 20-Aug-19 06-Sep-19 0% 202 PO Placement - Chemical Dosing System
T4-PRO-HVAC-2010 Manufacturing - Chemical Dosing System 49 06-Sep-19 27-Oct-19 0% 279 Manufacturing - Chemical Dosing System
T4-PRO-HVAC-2020 Delivery at site - Chemical Dosing System 21 29-Dec-19 19-Jan-20 0% 279 Delivery at site - Chemical Dosing System
Vane Axial Fans 122 14-Oct-19 15-Feb-20 91 15-Feb-20, Vane Axial Fans
T4-PRO-HVAC-2030 PO Placement - Vane Axial Fans 14 14-Oct-19 31-Oct-19 0% 66 PO Placement - Vane Axial Fans
T4-PRO-HVAC-2040 Manufacturing - Vane Axial Fans 84 31-Oct-19 25-Jan-20 0% 91 Manufacturing - Vane Axial Fans
T4-PRO-HVAC-2050 Delivery at site - Vane Axial Fans 21 25-Jan-20 15-Feb-20 0% 91 Delivery at site - Vane Axial Fans
Smoke Spill Vane Axial Fans 108 14-Oct-19 01-Feb-20 105 01-Feb-20, Smoke Spill Vane Axial Fans
T4-PRO-HVAC-2060 PO Placement - Smoke Spill Vane Axial Fans 14 14-Oct-19 31-Oct-19 0% 76 PO Placement - Smoke Spill Vane Axial Fans
T4-PRO-HVAC-2070 Manufacturing - Smoke Spill Vane Axial Fans 70 31-Oct-19 11-Jan-20 0% 105 Manufacturing - Smoke Spill Vane Axial Fans
T4-PRO-HVAC-2080 Delivery at site - Smoke Spill Vane Axial Fans 21 11-Jan-20 01-Feb-20 0% 105 Delivery at site - Smoke Spill Vane Axial Fans
Inline Fans 107 24-Sep-19 13-Jan-20 124 13-Jan-20, Inline Fans
T4-PRO-HVAC-2090 PO Placement - Inline Fans 14 24-Sep-19 11-Oct-19 0% 90 PO Placement - Inline Fans
T4-PRO-HVAC-2100 Manufacturing - Inline Fans 70 11-Oct-19 22-Dec-19 0% 124 Manufacturing - Inline Fans
T4-PRO-HVAC-2110 Delivery at site - Inline Fans 21 22-Dec-19 13-Jan-20 0% 124 Delivery at site - Inline Fans
Propeller Fans 107 24-Sep-19 13-Jan-20 124 13-Jan-20, Propeller Fans
T4-PRO-HVAC-2120 PO Placement - Propeller Fans 14 24-Sep-19 11-Oct-19 0% 90 PO Placement - Propeller Fans
T4-PRO-HVAC-2130 Manufacturing - Propeller Fans 70 11-Oct-19 22-Dec-19 0% 124 Manufacturing - Propeller Fans
T4-PRO-HVAC-2140 Delivery at site - Propeller Fans 21 22-Dec-19 13-Jan-20 0% 124 Delivery at site - Propeller Fans
Cabinet Fans 107 24-Sep-19 13-Jan-20 124 13-Jan-20, Cabinet Fans
T4-PRO-HVAC-2150 PO Placement - Cabinet Fans 14 24-Sep-19 11-Oct-19 0% 90 PO Placement - Cabinet Fans
T4-PRO-HVAC-2160 Manufacturing - Cabinet Fans 70 11-Oct-19 22-Dec-19 0% 124 Manufacturing - Cabinet Fans

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 19 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-PRO-HVAC-2170 Delivery at site - Cabinet Fans 21 22-Dec-19 13-Jan-20 0% 124 Delivery at site - Cabinet Fans
Jet Fans (CO sensors) 107 24-Sep-19 13-Jan-20 124 13-Jan-20, Jet Fans (CO sensors)
T4-PRO-HVAC-2180 PO Placement - Jet Fans 14 24-Sep-19 11-Oct-19 0% 90 PO Placement - Jet Fans
T4-PRO-HVAC-2190 Manufacturing - Jet Fans 70 11-Oct-19 22-Dec-19 0% 124 Manufacturing - Jet Fans
T4-PRO-HVAC-2200 Delivery at site - Jet Fans 21 22-Dec-19 13-Jan-20 0% 124 Delivery at site - Jet Fans
HI Wall & Ducted Split Unit 82 07-Nov-19 29-Jan-20 116 29-Jan-20, HI Wall & Ducted Split Unit
T4-PRO-HVAC-2210 PO Placement - HI Wall & Ducted Split Units 14 07-Nov-19 26-Nov-19 0% 83 PO Placement - HI Wall & Ducted Split Units
T4-PRO-HVAC-2220 Manufacturing - HI Wall & Ducted Split Units 42 26-Nov-19 08-Jan-20 0% 116 Manufacturing - HI Wall & Ducted Split Units
T4-PRO-HVAC-2230 Delivery at site - HI Wall & Ducted Split Units 21 08-Jan-20 29-Jan-20 0% 116 Delivery at site - HI Wall & Ducted Split Units
HI Wall Chilled Water Unit 82 07-Nov-19 29-Jan-20 116 29-Jan-20, HI Wall Chilled Water Unit
T4-PRO-HVAC-2240 PO Placement - HI Wall Chilled Water Unit 14 07-Nov-19 26-Nov-19 0% 83 PO Placement - HI Wall Chilled Water Unit
T4-PRO-HVAC-2250 Manufacturing - HI Wall Chilled Water Unit 42 26-Nov-19 08-Jan-20 0% 116 Manufacturing - HI Wall Chilled Water Unit
T4-PRO-HVAC-2260 Delivery at site - HI Wall Chilled Water Unit 21 08-Jan-20 29-Jan-20 0% 116 Delivery at site - HI Wall Chilled Water Unit
Water Treatment Plant for Cooling Tower 80 21-Oct-19 11-Jan-20 287 11-Jan-20, Water Treatment Plant for Cooling Tower
T4-PRO-HVAC-2270 PO Placement - Water Treatment Plant 14 21-Oct-19 07-Nov-19 0% 206 PO Placement - Water Treatment Plant
T4-PRO-HVAC-2280 Manufacturing - Water Treatment Plant 42 07-Nov-19 20-Dec-19 0% 287 Manufacturing - Water Treatment Plant
T4-PRO-HVAC-2290 Delivery at site - Water Treatment Plant 21 20-Dec-19 11-Jan-20 0% 287 Delivery at site - Water Treatment Plant
Electrical Panels 80 21-Oct-19 11-Jan-20 114 11-Jan-20, Electrical Panels
T4-PRO-HVAC-2300 PO Placement - Electrical Panels (HVAC) 14 21-Oct-19 07-Nov-19 0% 82 PO Placement - Electrical Panels (HVAC)
T4-PRO-HVAC-2310 Manufacturing - Electrical Panels (HVAC) 42 07-Nov-19 20-Dec-19 0% 114 Manufacturing - Electrical Panels (HVAC)
T4-PRO-HVAC-2320 Delivery at site - Electrical Panels (HVAC) 21 20-Dec-19 11-Jan-20 0% 114 Delivery at site - Electrical Panels (HVAC)
CLASS B 470 25-Jun-19 14-Oct-20 108 14-Oct-20, CLASS B
MS Pipes 399 25-Jun-19 04-Aug-20 165 04-Aug-20, MS Pipes
T4-PRO-HVAC-2325 PO Placement - MS Pipes (HVAC) 14 25-Jun-19 09-Jul-19 0% 165 PO Placement - MS Pipes (HVAC)
T4-PRO-HVAC-2335 Manufacturing - MS Pipes (HVAC) 35 09-Jul-19 13-Aug-19 0% 165 Manufacturing - MS Pipes (HVAC)
T4-PRO-HVAC-2345 Delivery at site - MS Pipes (HVAC) 350 13-Aug-19 04-Aug-20 0% 165 Delivery at site - MS Pipes (H
UPVC Drain Pipe 399 03-Jul-19 12-Aug-20 157 12-Aug-20, UPVC Drain Pipe
T4-PRO-HVAC-2360 PO Placement - UPVC Drain Pipes (HVAC) 14 03-Jul-19 17-Jul-19 0% 157 PO Placement - UPVC Drain Pipes (HVAC)
T4-PRO-HVAC-2370 Manufacturing - UPVC Drain Pipes (HVAC) 35 17-Jul-19 22-Aug-19 0% 157 Manufacturing - UPVC Drain Pipes (HVAC)
T4-PRO-HVAC-2380 Delivery at site - UPVC Drain Pipes (HVAC) 350 22-Aug-19 12-Aug-20 0% 157 Delivery at site - UPVC Dra
Ball Valves 399 25-Jun-19 04-Aug-20 165 04-Aug-20, Ball Valves
T4-PRO-HVAC-2390 PO Placement - Ball Valves (HVAC) 14 25-Jun-19 09-Jul-19 0% 165 PO Placement - Ball Valves (HVAC)
T4-PRO-HVAC-2400 Manufacturing - Ball Valves (HVAC) 35 09-Jul-19 13-Aug-19 0% 165 Manufacturing - Ball Valves (HVAC)
T4-PRO-HVAC-2410 Delivery at site - Ball Valves (HVAC) 350 13-Aug-19 04-Aug-20 0% 165 Delivery at site - Ball Valves
Manual Butterfly Valves 399 25-Jun-19 04-Aug-20 165 04-Aug-20, Manual Butterfly
T4-PRO-HVAC-2420 PO Placement - Manual Butterfly Valve (HVAC) 14 25-Jun-19 09-Jul-19 0% 165 PO Placement - Manual Butterfly Valve (HVAC)
T4-PRO-HVAC-2430 Manufacturing - Manual Butterfly Valve (HVAC) 35 09-Jul-19 13-Aug-19 0% 165 Manufacturing - Manual Butterfly Valve (HVAC)
T4-PRO-HVAC-2440 Delivery at site - Manual Butterfly Valve (HVAC) 350 13-Aug-19 04-Aug-20 0% 165 Delivery at site - Manual But
Motorised Butterfly Valves 399 25-Jun-19 04-Aug-20 172 04-Aug-20, Motorised Butter
T4-PRO-HVAC-2450 PO Placement - Motorised Butterfly Valve (HVAC) 14 25-Jun-19 09-Jul-19 0% 172 PO Placement - Motorised Butterfly Valve (HVAC)
T4-PRO-HVAC-2460 Manufacturing - Motorised Butterfly Valve (HVAC) 35 09-Jul-19 13-Aug-19 0% 172 Manufacturing - Motorised Butterfly Valve (HVAC)
T4-PRO-HVAC-2470 Delivery at site - Motorised Butterfly Valve (HVAC) 350 13-Aug-19 04-Aug-20 0% 172 Delivery at site - Motorised B
Manual Balancing Valves 399 29-Jun-19 08-Aug-20 168 08-Aug-20, Manual Balancin
T4-PRO-HVAC-2480 PO Placement - Manual Balancing Valve (HVAC) 14 29-Jun-19 13-Jul-19 0% 168 PO Placement - Manual Balancing Valve (HVAC)
T4-PRO-HVAC-2490 Manufacturing - Manual Balancing Valve (HVAC) 35 13-Jul-19 18-Aug-19 0% 168 Manufacturing - Manual Balancing Valve (HVAC)
T4-PRO-HVAC-2500 Delivery at site - Manual Balancing Valve (HVAC) 350 18-Aug-19 08-Aug-20 0% 168 Delivery at site - Manual Ba
Non Return Valves 399 29-Jun-19 08-Aug-20 168 08-Aug-20, Non Return Valves
T4-PRO-HVAC-2510 PO Placement - Non Return Valve (HVAC) 14 29-Jun-19 13-Jul-19 0% 168 PO Placement - Non Return Valve (HVAC)
T4-PRO-HVAC-2520 Manufacturing - Non Return Valve (HVAC) 35 13-Jul-19 18-Aug-19 0% 168 Manufacturing - Non Return Valve (HVAC)
T4-PRO-HVAC-2530 Delivery at site - Non Return Valve (HVAC) 350 18-Aug-19 08-Aug-20 0% 168 Delivery at site - Non Return
Y - Strainers 399 29-Jun-19 08-Aug-20 168 08-Aug-20, Y - Strainers
T4-PRO-HVAC-2540 PO Placement - Y Strainers (HVAC) 14 29-Jun-19 13-Jul-19 0% 168 PO Placement - Y Strainers (HVAC)
T4-PRO-HVAC-2550 Manufacturing - Y Strainers (HVAC) 35 13-Jul-19 18-Aug-19 0% 168 Manufacturing - Y Strainers (HVAC)

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 20 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-PRO-HVAC-2560 Delivery at site - Y Strainers (HVAC) 350 18-Aug-19 08-Aug-20 0% 168 Delivery at site - Y Strainers
Thermostat 399 09-Jul-19 18-Aug-20 158 18-Aug-20, Thermostat
T4-PRO-HVAC-2570 PO Placement - Thermostat 14 09-Jul-19 23-Jul-19 0% 158 PO Placement - Thermostat
T4-PRO-HVAC-2580 Manufacturing - Thermostat 35 23-Jul-19 28-Aug-19 0% 158 Manufacturing - Thermostat
T4-PRO-HVAC-2590 Delivery at site - Thermostat 350 28-Aug-19 18-Aug-20 0% 158 Delivery at site - Thermostat
BTU Meters 149 05-Jul-19 07-Dec-19 155 07-Dec-19, BTU Meters
T4-PRO-HVAC-2600 PO Placement - BTU Meter 14 05-Jul-19 19-Jul-19 0% 155 PO Placement - BTU Meter
T4-PRO-HVAC-2610 Manufacturing - BTU Meter 35 19-Jul-19 24-Aug-19 0% 155 Manufacturing - BTU Meter
T4-PRO-HVAC-2620 Delivery at site - BTU Meter 100 24-Aug-19 07-Dec-19 0% 155 Delivery at site - BTU Meter
Flexible Connections 399 29-Jun-19 08-Aug-20 161 08-Aug-20, Flexible Connections
T4-PRO-HVAC-2630 PO Placement - Flexible Connection 14 29-Jun-19 13-Jul-19 0% 161 PO Placement - Flexible Connection
T4-PRO-HVAC-2640 Manufacturing - Flexible Connection 35 13-Jul-19 18-Aug-19 0% 161 Manufacturing - Flexible Connection
T4-PRO-HVAC-2650 Delivery at site - Flexible Connection 350 18-Aug-19 08-Aug-20 0% 161 Delivery at site - Flexible Co
PIBCV 399 05-Jul-19 14-Aug-20 162 14-Aug-20, PIBCV
T4-PRO-HVAC-2660 PO Placement - PIBCV 14 05-Jul-19 19-Jul-19 0% 162 PO Placement - PIBCV
T4-PRO-HVAC-2670 Manufacturing - PIBCV 35 19-Jul-19 24-Aug-19 0% 162 Manufacturing - PIBCV
T4-PRO-HVAC-2680 Delivery at site - PIBCV 350 24-Aug-19 14-Aug-20 0% 162 Delivery at site - PIBCV
Flow Meter 399 05-Jul-19 14-Aug-20 162 14-Aug-20, Flow Meter
T4-PRO-HVAC-2690 PO Placement - Flow meter 14 05-Jul-19 19-Jul-19 0% 162 PO Placement - Flow meter
T4-PRO-HVAC-2700 Manufacturing - Flow meter 35 19-Jul-19 24-Aug-19 0% 162 Manufacturing - Flow meter
T4-PRO-HVAC-2710 Delivery at site - Flow meter 350 24-Aug-19 14-Aug-20 0% 162 Delivery at site - Flow meter
Auto Air Vent 399 05-Jul-19 14-Aug-20 155 14-Aug-20, Auto Air Vent
T4-PRO-HVAC-2720 PO Placement - Auto Air Vent 14 05-Jul-19 19-Jul-19 0% 155 PO Placement - Auto Air Vent
T4-PRO-HVAC-2730 Manufacturing - Auto Air Vent 35 19-Jul-19 24-Aug-19 0% 155 Manufacturing - Auto Air Vent
T4-PRO-HVAC-2740 Delivery at site - Auto Air Vent 350 24-Aug-19 14-Aug-20 0% 155 Delivery at site - Auto Air Vent
Descaling Tee Valve 399 12-Jul-19 21-Aug-20 155 21-Aug-20, Descaling Tee
T4-PRO-HVAC-2750 PO Placement - Descaling Tee Valve 14 12-Jul-19 26-Jul-19 0% 155 PO Placement - Descaling Tee Valve
T4-PRO-HVAC-2760 Manufacturing - Descaling Tee Valve 35 26-Jul-19 31-Aug-19 0% 155 Manufacturing - Descaling Tee Valve
T4-PRO-HVAC-2770 Delivery at site - Descaling Tee Valve 350 31-Aug-19 21-Aug-20 0% 155 Delivery at site - Descaling
PG - TG 149 12-Oct-19 12-Mar-20 73 12-Mar-20, PG - TG
T4-PRO-HVAC-2780 PO Placement - PG-TG 14 12-Oct-19 26-Oct-19 0% 73 PO Placement - PG-TG
T4-PRO-HVAC-2790 Manufacturing - PG-TG 35 26-Oct-19 02-Dec-19 0% 73 Manufacturing - PG-TG
T4-PRO-HVAC-2800 Delivery at site - PG-TG 100 02-Dec-19 12-Mar-20 0% 73 Delivery at site - PG-TG
Grooved Fittings 399 09-Jul-19 18-Aug-20 151 18-Aug-20, Grooved Fittings
T4-PRO-HVAC-2810 PO Placement - Grooved Fittings 14 09-Jul-19 23-Jul-19 0% 151 PO Placement - Grooved Fittings
T4-PRO-HVAC-2820 Manufacturing - Grooved Fittings 35 23-Jul-19 28-Aug-19 0% 151 Manufacturing - Grooved Fittings
T4-PRO-HVAC-2830 Delivery at site - Grooved Fittings 350 28-Aug-19 18-Aug-20 0% 151 Delivery at site - Grooved
GI Ducting 449 16-Jul-19 14-Oct-20 108 14-Oct-20, GI Ducting
T4-PRO-HVAC-2840 PO Placement - GI Ducting 14 16-Jul-19 30-Jul-19 0% 108 PO Placement - GI Ducting
T4-PRO-HVAC-2850 Manufacturing - GI Ducting 35 30-Jul-19 05-Sep-19 0% 108 Manufacturing - GI Ducting
T4-PRO-HVAC-2860 Delivery at site - GI Ducting 400 05-Sep-19 14-Oct-20 0% 108 Delivery at site -
Fire Paints 149 30-Sep-19 02-Mar-20 70 02-Mar-20, Fire Paints
T4-PRO-HVAC-2870 PO Placement - Fire Paints 14 30-Sep-19 16-Oct-19 0% 70 PO Placement - Fire Paints
T4-PRO-HVAC-2880 Manufacturing - Fire Paints 35 16-Oct-19 22-Nov-19 0% 70 Manufacturing - Fire Paints
T4-PRO-HVAC-2890 Delivery at site - Fire Paints 100 22-Nov-19 02-Mar-20 0% 70 Delivery at site - Fire Paints
Manual & motorised VCD 399 16-Jul-19 25-Aug-20 144 25-Aug-20, Manual & mo
T4-PRO-HVAC-2900 PO Placement - Manual & Motorised VCD 14 16-Jul-19 30-Jul-19 0% 144 PO Placement - Manual & Motorised VCD
T4-PRO-HVAC-2910 Manufacturing - Manual & Motorised VCD 35 30-Jul-19 05-Sep-19 0% 144 Manufacturing - Manual & Motorised VCD
T4-PRO-HVAC-2920 Delivery at site - Manual & Motorised VCD 350 05-Sep-19 25-Aug-20 0% 144 Delivery at site - Manual
Fire Damper with Fusible Link & Motorised 399 16-Jul-19 25-Aug-20 144 25-Aug-20, Fire Damper
T4-PRO-HVAC-2930 PO Placement - Fire Damper 14 16-Jul-19 30-Jul-19 0% 144 PO Placement - Fire Damper
T4-PRO-HVAC-2940 Manufacturing - Fire Damper 35 30-Jul-19 05-Sep-19 0% 144 Manufacturing - Fire Damper

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 21 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-PRO-HVAC-2950 Delivery at site - Fire Damper 350 05-Sep-19 25-Aug-20 0% 144 Delivery at site - Fire Damper
Diffuser, Grilles, Slot Diffuser, Door Grilles, Non Return Dampers 449 16-Jul-19 14-Oct-20 108 14-Oct-20, Diffus
T4-PRO-HVAC-2960 PO Placement - Diffuser / Grills 14 16-Jul-19 30-Jul-19 0% 108 PO Placement - Diffuser / Grills
T4-PRO-HVAC-2970 Manufacturing - Diffuser / Grills 35 30-Jul-19 05-Sep-19 0% 108 Manufacturing - Diffuser / Grills
T4-PRO-HVAC-2980 Delivery at site - Diffuser / Grills 400 05-Sep-19 14-Oct-20 0% 108 Delivery at site -
Flexible Ducts 449 16-Jul-19 14-Oct-20 108 14-Oct-20, Flexib
T4-PRO-HVAC-2990 PO Placement - Flexible Ducts 14 16-Jul-19 30-Jul-19 0% 108 PO Placement - Flexible Ducts
T4-PRO-HVAC-3000 Manufacturing - Flexible Ducts 35 30-Jul-19 05-Sep-19 0% 108 Manufacturing - Flexible Ducts
T4-PRO-HVAC-3010 Delivery at site - Flexible Ducts 400 05-Sep-19 14-Oct-20 0% 108 Delivery at site -
Barometric pressure relief damper 139 16-Jul-19 08-Dec-19 167 08-Dec-19, Barometric pressure relief damper
T4-PRO-HVAC-3020 PO Placement - Barometric Pressure Relief Damper 14 16-Jul-19 30-Jul-19 0% 167 PO Placement - Barometric Pressure Relief Damper
T4-PRO-HVAC-3030 Manufacturing - Barometric Pressure Relief Damper 35 30-Jul-19 05-Sep-19 0% 167 Manufacturing - Barometric Pressure Relief Damper
T4-PRO-HVAC-3040 Delivery at site - Barometric Pressure Relief Damper 90 05-Sep-19 08-Dec-19 0% 167 Delivery at site - Barometric Pressure Relief Damper
Sound Attenuators 409 19-Jul-19 07-Sep-20 141 07-Sep-20, Sound Atte
T4-PRO-HVAC-3050 PO Placement - Sound Attenuators 14 19-Jul-19 02-Aug-19 0% 141 PO Placement - Sound Attenuators
T4-PRO-HVAC-3060 Manufacturing - Sound Attenuators 35 02-Aug-19 08-Sep-19 0% 141 Manufacturing - Sound Attenuators
T4-PRO-HVAC-3070 Delivery at site - Sound Attenuators 360 08-Sep-19 07-Sep-20 0% 141 Delivery at site - Sound
Duct Thermal Insulation - Nitrile Rubber 409 23-Jul-19 11-Sep-20 137 11-Sep-20, Duct Therm
T4-PRO-HVAC-3080 PO Placement - Duct Thermal Insulation 14 23-Jul-19 06-Aug-19 0% 137 PO Placement - Duct Thermal Insulation
T4-PRO-HVAC-3090 Manufacturing - Duct Thermal Insulation 35 06-Aug-19 12-Sep-19 0% 137 Manufacturing - Duct Thermal Insulation
T4-PRO-HVAC-3100 Delivery at site - Duct Thermal Insulation 360 12-Sep-19 11-Sep-20 0% 137 Delivery at site - Duct
Accoustic Insulation 409 23-Jul-19 11-Sep-20 137 11-Sep-20, Accoustic I
T4-PRO-HVAC-3110 PO Placement - Acoustic Insuation 14 23-Jul-19 06-Aug-19 0% 137 PO Placement - Acoustic Insuation
T4-PRO-HVAC-3120 Manufacturing - Acoustic Insuation 35 06-Aug-19 12-Sep-19 0% 137 Manufacturing - Acoustic Insuation
T4-PRO-HVAC-3130 Delivery at site - Acoustic Insuation 360 12-Sep-19 11-Sep-20 0% 137 Delivery at site - Acous
CHW Pipe Insulation -Fibre Glasswoool 409 23-Jul-19 11-Sep-20 137 11-Sep-20, CHW Pipe
T4-PRO-HVAC-3140 PO Placement - CHW Pipe Insualtion- Fibre Glasswool 14 23-Jul-19 06-Aug-19 0% 137 PO Placement - CHW Pipe Insualtion- Fibre Glasswool
T4-PRO-HVAC-3150 Manufacturing - CHW Pipe Insualtion- Fibre Glasswool 35 06-Aug-19 12-Sep-19 0% 137 Manufacturing - CHW Pipe Insualtion- Fibre Glasswool
T4-PRO-HVAC-3160 Delivery at site - CHW Pipe Insualtion- Fibre Glasswool 360 12-Sep-19 11-Sep-20 0% 137 Delivery at site - CHW
Underdeck Insulation - EPS 409 23-Jul-19 11-Sep-20 92 11-Sep-20, Underdeck
T4-PRO-HVAC-3170 PO Placement - Underdeck Insulation 14 23-Jul-19 06-Aug-19 0% 92 PO Placement - Underdeck Insulation
T4-PRO-HVAC-3180 Manufacturing - Underdeck Insulation 35 06-Aug-19 12-Sep-19 0% 92 Manufacturing - Underdeck Insulation
T4-PRO-HVAC-3190 Delivery at site - Underdeck Insulation 360 12-Sep-19 11-Sep-20 0% 92 Delivery at site - Unde
Flow Switch 149 18-Nov-19 16-Apr-20 140 16-Apr-20, Flow Switch
T4-PRO-HVAC-3200 PO Placement - Flow Switch 14 18-Nov-19 02-Dec-19 0% 140 PO Placement - Flow Switch
T4-PRO-HVAC-3210 Manufacturing - Flow Switch 35 02-Dec-19 07-Jan-20 0% 140 Manufacturing - Flow Switch
T4-PRO-HVAC-3220 Delivery at site - Flow Switch 100 07-Jan-20 16-Apr-20 0% 140 Delivery at site - Flow Switch
Differential Pressure Switch 249 03-Aug-19 15-Apr-20 241 15-Apr-20, Differential Pressure Switch
T4-PRO-HVAC-3230 PO Placement - Differential Pressure Switch 14 03-Aug-19 18-Aug-19 0% 241 PO Placement - Differential Pressure Switch
T4-PRO-HVAC-3240 Manufacturing - Differential Pressure Switch 35 18-Aug-19 23-Sep-19 0% 241 Manufacturing - Differential Pressure Switch
T4-PRO-HVAC-3250 Delivery at site - Differential Pressure Switch 200 23-Sep-19 15-Apr-20 0% 241 Delivery at site - Differential Pressure Switch
Canvass Duct Connection 409 16-Jul-19 04-Sep-20 148 04-Sep-20, Canvass D
T4-PRO-HVAC-3260 PO Placement - Canvass Duct Connection 14 16-Jul-19 30-Jul-19 0% 148 PO Placement - Canvass Duct Connection
T4-PRO-HVAC-3270 Manufacturing - Canvass Duct Connection 35 30-Jul-19 05-Sep-19 0% 148 Manufacturing - Canvass Duct Connection
T4-PRO-HVAC-3280 Delivery at site - Canvass Duct Connection 360 05-Sep-19 04-Sep-20 0% 148 Delivery at site - Canva
PHE 528 24-Jun-19 10-Dec-20 51 10-Dec
CLASS A 203 29-Jul-19 23-Feb-20 249 23-Feb-20, CLASS A
Domestic Water Transfer Pump 121 30-Sep-19 02-Feb-20 80 02-Feb-20, Domestic Water Transfer Pump
T4-PRO-PHE-1590 PO Placement - Domestic Water Transfer pump 14 30-Sep-19 17-Oct-19 0% 59 PO Placement - Domestic Water Transfer pump
T4-PRO-PHE-1591 Manufacturing - Domestic Water Transfer pump 84 17-Oct-19 12-Jan-20 0% 80 Manufacturing - Domestic Water Transfer pump
T4-PRO-PHE-1592 Delivery at Site - Domestic Water Transfer pump 21 12-Jan-20 02-Feb-20 0% 80 Delivery at Site - Domestic Water Transfer pump
Grey Water Transfer Pump 122 29-Jul-19 03-Dec-19 147 03-Dec-19, Grey Water Transfer Pump
T4-PRO-PHE-1990 PO Placement - Grey Water Transfer Pump 14 29-Jul-19 15-Aug-19 0% 109 PO Placement - Grey Water Transfer Pump

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 22 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-PRO-PHE-2000 Manufacturing - Grey Water Transfer Pump 84 16-Aug-19 11-Nov-19 0% 147 Manufacturing - Grey Water Transfer Pump
T4-PRO-PHE-2010 Delivery at Site - Grey Water Transfer Pump 21 13-Nov-19 03-Dec-19 0% 147 Delivery at Site - Grey Water Transfer Pump
Pre Charged Air Vessel (300 Ltr) 88 10-Oct-19 08-Jan-20 134 08-Jan-20, Pre Charged Air Vessel (300 Ltr)
T4-PRO-PHE-2020 PO Placement - Pre Charged Air Vessel (300 Ltr) 14 10-Oct-19 29-Oct-19 0% 98 PO Placement - Pre Charged Air Vessel (300 Ltr)
T4-PRO-PHE-2030 Manufacturing - Pre Charged Air Vessel (300 Ltr) 48 29-Oct-19 17-Dec-19 0% 134 Manufacturing - Pre Charged Air Vessel (300 Ltr)
T4-PRO-PHE-2040 Delivery at Site - Pre Charged Air Vessel (300 Ltr) 21 17-Dec-19 08-Jan-20 0% 134 Delivery at Site - Pre Charged Air Vessel (300 Ltr)
Domestic Water Booster Pump 122 02-Sep-19 07-Jan-20 296 07-Jan-20, Domestic Water Booster Pump
T4-PRO-PHE-2230 PO Placement - Domestic Water Booster Pump 14 02-Sep-19 19-Sep-19 0% 215 PO Placement - Domestic Water Booster Pump
T4-PRO-PHE-2240 Manufacturing - Domestic Water Booster Pump 84 19-Sep-19 16-Dec-19 0% 296 Manufacturing - Domestic Water Booster Pump
T4-PRO-PHE-2250 Delivery at Site - Domestic Water Booster Pump 21 16-Dec-19 07-Jan-20 0% 296 Delivery at Site - Domestic Water Booster Pump
Grey Water Booster Pump 122 16-Sep-19 20-Jan-20 105 20-Jan-20, Grey Water Booster Pump
T4-PRO-PHE-2050 PO Placement - Grey Water Booster Pump 14 16-Sep-19 03-Oct-19 0% 77 PO Placement - Grey Water Booster Pump
T4-PRO-PHE-2060 Manufacturing - Grey Water Booster Pump 84 03-Oct-19 30-Dec-19 0% 105 Manufacturing - Grey Water Booster Pump
T4-PRO-PHE-2070 Delivery at Site - Grey Water Booster Pump 21 30-Dec-19 20-Jan-20 0% 105 Delivery at Site - Grey Water Booster Pump
Pre Charged Air Vessel for Booster Pump 122 29-Jul-19 03-Dec-19 154 03-Dec-19, Pre Charged Air Vessel for Booster Pump
T4-PRO-PHE-2080 PO Placement - Pre Charged Air Vessel for Booster Pump 14 29-Jul-19 15-Aug-19 0% 114 PO Placement - Pre Charged Air Vessel for Booster Pump
T4-PRO-PHE-2090 Manufacturing - Pre Charged Air Vessel for Booster Pump 84 16-Aug-19 11-Nov-19 0% 154 Manufacturing - Pre Charged Air Vessel for Booster Pump
T4-PRO-PHE-2100 Delivery at Site - Pre Charged Air Vessel for Booster Pump 21 13-Nov-19 03-Dec-19 0% 154 Delivery at Site - Pre Charged Air Vessel for Booster Pump
Rain Water Transfer Pump 122 22-Oct-19 23-Feb-20 75 23-Feb-20, Rain Water Transfer Pump
T4-PRO-PHE-2110 PO Placement - Rain Water Transfer Pump 14 22-Oct-19 08-Nov-19 0% 55 PO Placement - Rain Water Transfer Pump
T4-PRO-PHE-2120 Manufacturing - Rain Water Transfer Pump 84 08-Nov-19 02-Feb-20 0% 75 Manufacturing - Rain Water Transfer Pump
T4-PRO-PHE-2130 Delivery at Site - Rain Water Transfer Pump 21 02-Feb-20 23-Feb-20 0% 75 Delivery at Site - Rain Water Transfer Pump
Drainage Sump Pump 124 08-Aug-19 15-Dec-19 148 15-Dec-19, Drainage Sump Pump
T4-PRO-PHE-2140 PO Placement - Drainage Sump Pump 14 08-Aug-19 27-Aug-19 0% 110 PO Placement - Drainage Sump Pump
T4-PRO-PHE-2150 Manufacturing - Drainage Sump Pump 84 27-Aug-19 24-Nov-19 0% 148 Manufacturing - Drainage Sump Pump
T4-PRO-PHE-2160 Delivery at Site - Drainage Sump Pump 21 24-Nov-19 15-Dec-19 0% 148 Delivery at Site - Drainage Sump Pump
Sewage Sump Pump 124 08-Aug-19 15-Dec-19 156 15-Dec-19, Sewage Sump Pump
T4-PRO-PHE-2170 PO Placement - Sewage Sump Pump 14 08-Aug-19 27-Aug-19 0% 116 PO Placement - Sewage Sump Pump
T4-PRO-PHE-2180 Manufacturing - Sewage Sump Pump 84 27-Aug-19 24-Nov-19 0% 156 Manufacturing - Sewage Sump Pump
T4-PRO-PHE-2190 Delivery at Site - Sewage Sump Pump 21 24-Nov-19 15-Dec-19 0% 156 Delivery at Site - Sewage Sump Pump
Electrical Panels (PHE) 110 21-Aug-19 13-Dec-19 132 13-Dec-19, Electrical Panels (PHE)
T4-PRO-PHE-2200 PO Placement - Electrical Panels (PHE) 14 21-Aug-19 09-Sep-19 0% 99 PO Placement - Electrical Panels (PHE)
T4-PRO-PHE-2210 Manufacturing - Electrical Panels (PHE) 70 09-Sep-19 22-Nov-19 0% 132 Manufacturing - Electrical Panels (PHE)
T4-PRO-PHE-2220 Delivery at Site - Electrical Panels (PHE) 21 22-Nov-19 13-Dec-19 0% 132 Delivery at Site - Electrical Panels (PHE)
CLASS B 528 24-Jun-19 10-Dec-20 51 10-Dec
UPVC Water Supply Pipes 399 16-Aug-19 24-Sep-20 128 24-Sep-20, UPVC W
T4-PRO-PHE-1675 PO Placement - UPVC Water Supply Pipes 14 16-Aug-19 30-Aug-19 0% 128 PO Placement - UPVC Water Supply Pipes
T4-PRO-PHE-1685 Manufacturing - UPVC Water Supply Pipes 35 30-Aug-19 06-Oct-19 0% 128 Manufacturing - UPVC Water Supply Pipes
T4-PRO-PHE-1695 Delivery at site - UPVC Water Supply Pipes 350 06-Oct-19 24-Sep-20 0% 128 Delivery at site - UP
CPVC Pipes 399 28-Jun-19 07-Aug-20 176 07-Aug-20, CPVC Pipes
T4-PRO-PHE-2260 PO Placement - CPVC Pipes 14 28-Jun-19 12-Jul-19 0% 176 PO Placement - CPVC Pipes
T4-PRO-PHE-2270 Manufacturing - CPVC Pipes 35 12-Jul-19 17-Aug-19 0% 176 Manufacturing - CPVC Pipes
T4-PRO-PHE-2280 Delivery at site - CPVC Pipes 350 17-Aug-19 07-Aug-20 0% 176 Delivery at site - CPVC Pipes
Brass Ball Valve 399 28-Jun-19 07-Aug-20 176 07-Aug-20, Brass Ball Valve
T4-PRO-PHE-2290 PO Placement - Brass Ball Valve 14 28-Jun-19 12-Jul-19 0% 176 PO Placement - Brass Ball Valve
T4-PRO-PHE-2300 Manufacturing - Brass Ball Valve 35 12-Jul-19 17-Aug-19 0% 176 Manufacturing - Brass Ball Valve
T4-PRO-PHE-2310 Delivery at site - Brass Ball Valve 350 17-Aug-19 07-Aug-20 0% 176 Delivery at site - Brass Ball Valve
Auto Air Vent 399 28-Jun-19 07-Aug-20 176 07-Aug-20, Auto Air Vent
T4-PRO-PHE-2320 PO Placement - Auto Air Vent (PHE) 14 28-Jun-19 12-Jul-19 0% 176 PO Placement - Auto Air Vent (PHE)
T4-PRO-PHE-2330 Manufacturing - Auto Air Vent (PHE) 35 12-Jul-19 17-Aug-19 0% 176 Manufacturing - Auto Air Vent (PHE)
T4-PRO-PHE-2340 Delivery at site - Auto Air Vent (PHE) 350 17-Aug-19 07-Aug-20 0% 176 Delivery at site - Auto Air Ve
Float Valve 399 28-Jun-19 07-Aug-20 176 07-Aug-20, Float Valve
T4-PRO-PHE-2350 PO Placement - Float Valve 14 28-Jun-19 12-Jul-19 0% 176 PO Placement - Float Valve

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 23 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-PRO-PHE-2360 Manufacturing - Float Valve 35 12-Jul-19 17-Aug-19 0% 176 Manufacturing - Float Valve
T4-PRO-PHE-2370 Delivery at site - Float Valve 350 17-Aug-19 07-Aug-20 0% 176 Delivery at site - Float Valve
Pressure Reducing Valve Station 399 05-Jul-19 14-Aug-20 169 14-Aug-20, Pressure Redu
T4-PRO-PHE-2380 PO Placement - Pressure Reducing Valve Station 14 05-Jul-19 19-Jul-19 0% 169 PO Placement - Pressure Reducing Valve Station
T4-PRO-PHE-2390 Manufacturing - Pressure Reducing Valve Station 35 19-Jul-19 24-Aug-19 0% 169 Manufacturing - Pressure Reducing Valve Station
T4-PRO-PHE-2400 Delivery at site - Pressure Reducing Valve Station 350 24-Aug-19 14-Aug-20 0% 169 Delivery at site - Pressure R
FRP Grating & Manhole Covers 399 05-Jul-19 14-Aug-20 169 14-Aug-20, FRP Grating &
T4-PRO-PHE-2410 PO Placement - FRP Grating & Manhole Cover 14 05-Jul-19 19-Jul-19 0% 169 PO Placement - FRP Grating & Manhole Cover
T4-PRO-PHE-2420 Manufacturing - FRP Grating & Manhole Cover 35 19-Jul-19 24-Aug-19 0% 169 Manufacturing - FRP Grating & Manhole Cover
T4-PRO-PHE-2430 Delivery at site - FRP Grating & Manhole Cover 350 24-Aug-19 14-Aug-20 0% 169 Delivery at site - FRP Grat
UPVC Perforated Pipes 399 05-Jul-19 14-Aug-20 169 14-Aug-20, UPVC Perforat
T4-PRO-PHE-2440 PO Placement - UPVC Perforated Pipes 14 05-Jul-19 19-Jul-19 0% 169 PO Placement - UPVC Perforated Pipes
T4-PRO-PHE-2450 Manufacturing - UPVC Perforated Pipes 35 19-Jul-19 24-Aug-19 0% 169 Manufacturing - UPVC Perforated Pipes
T4-PRO-PHE-2460 Delivery at site - UPVC Perforated Pipes 350 24-Aug-19 14-Aug-20 0% 169 Delivery at site - UPVC Per
CI Butterfly Valve 399 03-Jul-19 12-Aug-20 171 12-Aug-20, CI Butterfly Valve
T4-PRO-PHE-2470 PO Placement - CI Butterfly Valve 14 03-Jul-19 17-Jul-19 0% 171 PO Placement - CI Butterfly Valve
T4-PRO-PHE-2480 Manufacturing - CI Butterfly Valve 35 17-Jul-19 22-Aug-19 0% 171 Manufacturing - CI Butterfly Valve
T4-PRO-PHE-2490 Delivery at site - CI Butterfly Valve 350 22-Aug-19 12-Aug-20 0% 171 Delivery at site - CI Butterfl
HDPE Pipe 399 03-Jul-19 12-Aug-20 171 12-Aug-20, HDPE Pipe
T4-PRO-PHE-2500 PO Placement - HDPE Pipe 14 03-Jul-19 17-Jul-19 0% 171 PO Placement - HDPE Pipe
T4-PRO-PHE-2510 Manufacturing - HDPE Pipe 35 17-Jul-19 22-Aug-19 0% 171 Manufacturing - HDPE Pipe
T4-PRO-PHE-2520 Delivery at site - HDPE Pipe 350 22-Aug-19 12-Aug-20 0% 171 Delivery at site - HDPE Pipe
CI Hubless Pipe 399 03-Jul-19 12-Aug-20 171 12-Aug-20, CI Hubless Pipe
T4-PRO-PHE-2530 PO Placement - CI Hubless Pipe 14 03-Jul-19 17-Jul-19 0% 171 PO Placement - CI Hubless Pipe
T4-PRO-PHE-2540 Manufacturing - CI Hubless Pipe 35 17-Jul-19 22-Aug-19 0% 171 Manufacturing - CI Hubless Pipe
T4-PRO-PHE-2550 Delivery at site - CI Hubless Pipe 350 22-Aug-19 12-Aug-20 0% 171 Delivery at site - CI Hubless Pipe
UPVC SWR & Agri Pipes 399 03-Jul-19 12-Aug-20 171 12-Aug-20, UPVC SWR &
T4-PRO-PHE-2560 PO Placement - UPVC SWR & Agri Pipes 14 03-Jul-19 17-Jul-19 0% 171 PO Placement - UPVC SWR & Agri Pipes
T4-PRO-PHE-2570 Manufacturing - UPVC SWR & Agri Pipes 35 17-Jul-19 22-Aug-19 0% 171 Manufacturing - UPVC SWR & Agri Pipes
T4-PRO-PHE-2580 Delivery at site - UPVC SWR & Agri Pipes 350 22-Aug-19 12-Aug-20 0% 171 Delivery at site - UPVC SW
UPVC Low Noise Pipes 399 03-Jul-19 12-Aug-20 171 12-Aug-20, UPVC Low Noi
T4-PRO-PHE-2590 PO Placement - UPVC Low Noise Pipes 14 03-Jul-19 17-Jul-19 0% 171 PO Placement - UPVC Low Noise Pipes
T4-PRO-PHE-2600 Manufacturing - UPVC Low Noise Pipes 35 17-Jul-19 22-Aug-19 0% 171 Manufacturing - UPVC Low Noise Pipes
T4-PRO-PHE-2610 Delivery at site - UPVC Low Noise Pipes 350 22-Aug-19 12-Aug-20 0% 171 Delivery at site - UPVC Low
Nitrile Rubber Insulation 399 10-Jul-19 19-Aug-20 164 19-Aug-20, Nitrile Rubber
T4-PRO-PHE-2620 PO Placement - Nitrile Rubber Insulation 14 10-Jul-19 24-Jul-19 0% 164 PO Placement - Nitrile Rubber Insulation
T4-PRO-PHE-2630 Manufacturing - Nitrile Rubber Insulation 35 24-Jul-19 29-Aug-19 0% 164 Manufacturing - Nitrile Rubber Insulation
T4-PRO-PHE-2640 Delivery at site - Nitrile Rubber Insulation 350 29-Aug-19 19-Aug-20 0% 164 Delivery at site - Nitrile Ru
UPVC Traps 399 10-Jul-19 19-Aug-20 164 19-Aug-20, UPVC Traps
T4-PRO-PHE-2650 PO Placement - UPVC Traps 14 10-Jul-19 24-Jul-19 0% 164 PO Placement - UPVC Traps
T4-PRO-PHE-2660 Manufacturing - UPVC Traps 35 24-Jul-19 29-Aug-19 0% 164 Manufacturing - UPVC Traps
T4-PRO-PHE-2670 Delivery at site - UPVC Traps 350 29-Aug-19 19-Aug-20 0% 164 Delivery at site - UPVC Traps
Rain Water Head 399 10-Jul-19 19-Aug-20 164 19-Aug-20, Rain Water Head
T4-PRO-PHE-2680 PO Placement - Rain Water Head 14 10-Jul-19 24-Jul-19 0% 164 PO Placement - Rain Water Head
T4-PRO-PHE-2690 Manufacturing - Rain Water Head 35 24-Jul-19 29-Aug-19 0% 164 Manufacturing - Rain Water Head
T4-PRO-PHE-2700 Delivery at site - Rain Water Head 350 29-Aug-19 19-Aug-20 0% 164 Delivery at site - Rain Wat
GI Pipe (Class B & C) 399 24-Jun-19 03-Aug-20 180 03-Aug-20, GI Pipe (Class B & C)
T4-PRO-PHE-2710 PO Placement - GI Pipes (Class B & C) 14 24-Jun-19 08-Jul-19 0% 180 PO Placement - GI Pipes (Class B & C)
T4-PRO-PHE-2720 Manufacturing - GI Pipes (Class B & C) 35 08-Jul-19 12-Aug-19 0% 180 Manufacturing - GI Pipes (Class B & C)
T4-PRO-PHE-2730 Delivery at site - GI Pipes (Class B & C) 350 12-Aug-19 03-Aug-20 0% 180 Delivery at site - GI Pipes (C
Grooved Coupling (Rigid & Flexible) 399 24-Jul-19 02-Sep-20 150 02-Sep-20, Grooved Co
T4-PRO-PHE-2740 PO Placement - Grooved Coupling 14 24-Jul-19 07-Aug-19 0% 150 PO Placement - Grooved Coupling

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 24 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-PRO-PHE-2750 Manufacturing - Grooved Coupling 35 07-Aug-19 13-Sep-19 0% 150 Manufacturing - Grooved Coupling
T4-PRO-PHE-2760 Delivery at site - Grooved Coupling 350 13-Sep-19 02-Sep-20 0% 150 Delivery at site - Groove
Brass bib tap with hose (Irrigation) 399 10-Aug-19 19-Sep-20 133 19-Sep-20, Brass bib
T4-PRO-PHE-2770 PO Placement - Brass Bib Tap 14 10-Aug-19 25-Aug-19 0% 133 PO Placement - Brass Bib Tap
T4-PRO-PHE-2780 Manufacturing - Brass Bib Tap 35 25-Aug-19 30-Sep-19 0% 133 Manufacturing - Brass Bib Tap
T4-PRO-PHE-2790 Delivery at site - Brass Bib Tap 350 30-Sep-19 19-Sep-20 0% 133 Delivery at site - Bras
Motorised Butterfly Valve 399 07-Aug-19 16-Sep-20 136 16-Sep-20, Motorised
T4-PRO-PHE-2800 PO Placement - Motorised Butterfly Valve 14 07-Aug-19 22-Aug-19 0% 136 PO Placement - Motorised Butterfly Valve
T4-PRO-PHE-2810 Manufacturing - Motorised Butterfly Valve 35 22-Aug-19 27-Sep-19 0% 136 Manufacturing - Motorised Butterfly Valve
T4-PRO-PHE-2820 Delivery at site - Motorised Butterfly Valve 350 27-Sep-19 16-Sep-20 0% 136 Delivery at site - Moto
Water Hammer Arrestor 399 13-Jul-19 22-Aug-20 161 22-Aug-20, Water Hamm
T4-PRO-PHE-2830 PO Placement - Water Hammer Arrestor 14 13-Jul-19 27-Jul-19 0% 161 PO Placement - Water Hammer Arrestor
T4-PRO-PHE-2840 Manufacturing - Water Hammer Arrestor 35 27-Jul-19 01-Sep-19 0% 161 Manufacturing - Water Hammer Arrestor
T4-PRO-PHE-2850 Delivery at site - Water Hammer Arrestor 350 01-Sep-19 22-Aug-20 0% 161 Delivery at site - Water H
Check Valve 399 13-Jul-19 22-Aug-20 161 22-Aug-20, Check Valve
T4-PRO-PHE-2860 PO Placement - Check Valve 14 13-Jul-19 27-Jul-19 0% 161 PO Placement - Check Valve
T4-PRO-PHE-2870 Manufacturing - Check Valve 35 27-Jul-19 01-Sep-19 0% 161 Manufacturing - Check Valve
T4-PRO-PHE-2880 Delivery at site - Check Valve 350 01-Sep-19 22-Aug-20 0% 161 Delivery at site - Check Valve
Y Type Strainer 399 13-Jul-19 22-Aug-20 161 22-Aug-20, Y Type Strainer
T4-PRO-PHE-2890 PO Placement - Y Type Strainer 14 13-Jul-19 27-Jul-19 0% 161 PO Placement - Y Type Strainer
T4-PRO-PHE-2900 Manufacturing - Y Type Strainer 35 27-Jul-19 01-Sep-19 0% 161 Manufacturing - Y Type Strainer
T4-PRO-PHE-2910 Delivery at site - Y Type Strainer 350 01-Sep-19 22-Aug-20 0% 161 Delivery at site - Y Type S
Flexible Rubber Connection 399 13-Jul-19 22-Aug-20 161 22-Aug-20, Flexible Rubb
T4-PRO-PHE-2920 PO Placement - Flexible Rubber Connection 14 13-Jul-19 27-Jul-19 0% 161 PO Placement - Flexible Rubber Connection
T4-PRO-PHE-2930 Manufacturing - Flexible Rubber Connection 35 27-Jul-19 01-Sep-19 0% 161 Manufacturing - Flexible Rubber Connection
T4-PRO-PHE-2940 Delivery at site - Flexible Rubber Connection 350 01-Sep-19 22-Aug-20 0% 161 Delivery at site - Flexible R
Pressure Gauge 399 13-Jul-19 22-Aug-20 161 22-Aug-20, Pressure Gauge
T4-PRO-PHE-2950 PO Placement - Pressure Gauge 14 13-Jul-19 27-Jul-19 0% 161 PO Placement - Pressure Gauge
T4-PRO-PHE-2960 Manufacturing - Pressure Gauge 35 27-Jul-19 01-Sep-19 0% 161 Manufacturing - Pressure Gauge
T4-PRO-PHE-2970 Delivery at site - Pressure Gauge 350 01-Sep-19 22-Aug-20 0% 161 Delivery at site - Pressure
Water Level Sensor 399 27-Sep-19 04-Nov-20 87 04-Nov-20, W
T4-PRO-PHE-2980 PO Placement - Water Level Sensor 14 27-Sep-19 13-Oct-19 0% 87 PO Placement - Water Level Sensor
T4-PRO-PHE-2990 Manufacturing - Water Level Sensor 35 13-Oct-19 19-Nov-19 0% 87 Manufacturing - Water Level Sensor
T4-PRO-PHE-3000 Delivery at site - Water Level Sensor 350 19-Nov-19 04-Nov-20 0% 87 Delivery at sit
Level Indicator / Glass tube Manometer 399 05-Nov-19 10-Dec-20 51 10-Dec
T4-PRO-PHE-3010 PO Placement - Level Inidcator / Manometer 14 05-Nov-19 20-Nov-19 0% 51 PO Placement - Level Inidcator / Manometer
T4-PRO-PHE-3020 Manufacturing - Level Inidcator / Manometer 35 20-Nov-19 26-Dec-19 0% 51 Manufacturing - Level Inidcator / Manometer
T4-PRO-PHE-3030 Delivery at site - Level Inidcator / Manometer 350 26-Dec-19 10-Dec-20 0% 51 Deliver
Upvc Bib Tap (Ahu Rooms) 249 17-Jul-19 29-Mar-20 256 29-Mar-20, Upvc Bib Tap (Ahu Rooms)
T4-PRO-PHE-3040 PO Placement - UPVC Bib Tap 14 17-Jul-19 31-Jul-19 0% 256 PO Placement - UPVC Bib Tap
T4-PRO-PHE-3050 Manufacturing - UPVC Bib Tap 35 31-Jul-19 06-Sep-19 0% 256 Manufacturing - UPVC Bib Tap
T4-PRO-PHE-3060 Delivery at site - UPVC Bib Tap 200 06-Sep-19 29-Mar-20 0% 256 Delivery at site - UPVC Bib Tap
Mechanical Type Water Meter 249 17-Jul-19 29-Mar-20 256 29-Mar-20, Mechanical Type Water Meter
T4-PRO-PHE-3070 PO Placement - Mechanical Type Water Meter 14 17-Jul-19 31-Jul-19 0% 256 PO Placement - Mechanical Type Water Meter
T4-PRO-PHE-3080 Manufacturing - Mechanical Type Water Meter 35 31-Jul-19 06-Sep-19 0% 256 Manufacturing - Mechanical Type Water Meter
T4-PRO-PHE-3090 Delivery at site - Mechanical Type Water Meter 200 06-Sep-19 29-Mar-20 0% 256 Delivery at site - Mechanical Type Water Meter
DI Pipes 399 13-Aug-19 22-Sep-20 130 22-Sep-20, DI Pipes
T4-PRO-PHE-3100 PO Placement - DI Pipes 14 13-Aug-19 28-Aug-19 0% 130 PO Placement - DI Pipes
T4-PRO-PHE-3110 Manufacturing - DI Pipes 35 28-Aug-19 04-Oct-19 0% 130 Manufacturing - DI Pipes
T4-PRO-PHE-3120 Delivery at site - DI Pipes 350 04-Oct-19 22-Sep-20 0% 130 Delivery at site - DI Pipes
FRP Step Ladder 149 30-Sep-19 02-Mar-20 116 02-Mar-20, FRP Step Ladder
T4-PRO-PHE-3130 PO Placement - FRP Step Ladder 14 30-Sep-19 16-Oct-19 0% 116 PO Placement - FRP Step Ladder

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 25 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-PRO-PHE-3140 Manufacturing - FRP Step Ladder 35 16-Oct-19 22-Nov-19 0% 116 Manufacturing - FRP Step Ladder
T4-PRO-PHE-3150 Delivery at site - FRP Step Ladder 100 22-Nov-19 02-Mar-20 0% 116 Delivery at site - FRP Step Ladder
FF 491 24-Jun-19 03-Nov-20 88 03-Nov-20, FF
CLASS A 145 02-Aug-19 31-Dec-19 147 31-Dec-19, CLASS A
Fire Hydrant Pump (B2 & Roof) 122 20-Aug-19 24-Dec-19 137 24-Dec-19, Fire Hydrant Pump (B2 & Roof)
T4-PRO-FF-1990 PO Placement - Fire Hydrant Pump (B2 & Roof) 14 20-Aug-19 06-Sep-19 0% 100 PO Placement - Fire Hydrant Pump (B2 & Roof)
T4-PRO-FF-2320 Manufacturing - Fire Hydrant Pump (B2 & Roof) 84 06-Sep-19 03-Dec-19 0% 137 Manufacturing - Fire Hydrant Pump (B2 & Roof)
T4-PRO-FF-2330 Delivery at Site - Fire Hydrant Pump (B2 & Roof) 21 03-Dec-19 24-Dec-19 0% 137 Delivery at Site - Fire Hydrant Pump (B2 & Roof)
Fire Sprinkler Pump (B2 & Roof) 122 26-Aug-19 31-Dec-19 137 31-Dec-19, Fire Sprinkler Pump (B2 & Roof)
T4-PRO-FF-2340 PO Placement - Fire Sprinkler Pump (B2 & Roof) 14 26-Aug-19 12-Sep-19 0% 101 PO Placement - Fire Sprinkler Pump (B2 & Roof)
T4-PRO-FF-2350 Manufacturing - Fire Sprinkler Pump (B2 & Roof) 84 12-Sep-19 09-Dec-19 0% 137 Manufacturing - Fire Sprinkler Pump (B2 & Roof)
T4-PRO-FF-2360 Delivery at Site - Fire Sprinkler Pump (B2 & Roof) 21 09-Dec-19 31-Dec-19 0% 137 Delivery at Site - Fire Sprinkler Pump (B2 & Roof)
Fire Jockey Pump- Hydrant (B2 & Roof) 124 02-Aug-19 09-Dec-19 165 09-Dec-19, Fire Jockey Pump- Hydrant (B2 & Roof)
T4-PRO-FF-2370 PO Placement - Fire Jockey Pump - Hydrant (B2 & Roof) 14 02-Aug-19 21-Aug-19 0% 122 PO Placement - Fire Jockey Pump - Hydrant (B2 & Roof)
T4-PRO-FF-2380 Manufacturing - Fire Jockey Pump - Hydrant (B2 & Roof) 84 21-Aug-19 18-Nov-19 0% 165 Manufacturing - Fire Jockey Pump - Hydrant (B2 & Roof)
T4-PRO-FF-2390 Delivery at Site - Fire Jockey Pump - Hydrant (B2 & Roof) 21 18-Nov-19 09-Dec-19 0% 165 Delivery at Site - Fire Jockey Pump - Hydrant (B2 & Roof)
Fire Jockey Pump - Sprinkler (B2 & Roof) 124 02-Aug-19 09-Dec-19 168 09-Dec-19, Fire Jockey Pump - Sprinkler (B2 & Roof)
T4-PRO-FF-2400 PO Placement - Fire Jockey Pump - Sprinkler (B2 & Roof) 14 02-Aug-19 21-Aug-19 0% 124 PO Placement - Fire Jockey Pump - Sprinkler (B2 & Roof)
T4-PRO-FF-2410 Manufacturing - Fire Jockey Pump - Sprinkler (B2 & Roof) 84 21-Aug-19 18-Nov-19 0% 168 Manufacturing - Fire Jockey Pump - Sprinkler (B2 & Roof)
T4-PRO-FF-2420 Delivery at Site - Fire Jockey Pump - Sprinkler (B2 & Roof) 21 18-Nov-19 09-Dec-19 0% 168 Delivery at Site - Fire Jockey Pump - Sprinkler (B2 & Roof)
Fire Standby Pump (B2 & Roof) 124 02-Aug-19 09-Dec-19 162 09-Dec-19, Fire Standby Pump (B2 & Roof)
T4-PRO-FF-2430 PO Placement - Fire Standby Pump (B2 & Roof) 14 02-Aug-19 21-Aug-19 0% 120 PO Placement - Fire Standby Pump (B2 & Roof)
T4-PRO-FF-2440 Manufacturing - Fire Standby Pump (B2 & Roof) 84 21-Aug-19 18-Nov-19 0% 162 Manufacturing - Fire Standby Pump (B2 & Roof)
T4-PRO-FF-2450 Delivery at Site - Fire Standby Pump (B2 & Roof) 21 18-Nov-19 09-Dec-19 0% 162 Delivery at Site - Fire Standby Pump (B2 & Roof)
CLASS B 491 24-Jun-19 03-Nov-20 88 03-Nov-20, C
Pressure Gauge 149 04-Jul-19 06-Dec-19 275 06-Dec-19, Pressure Gauge
T4-PRO-FF-2460 PO Placement - Pressure Gauge 14 04-Jul-19 18-Jul-19 0% 275 PO Placement - Pressure Gauge
T4-PRO-FF-2470 Manufacturing - Pressure Gauge 35 18-Jul-19 23-Aug-19 0% 275 Manufacturing - Pressure Gauge
T4-PRO-FF-2480 Delivery at Site - Pressure Gauge 100 23-Aug-19 06-Dec-19 0% 275 Delivery at Site - Pressure Gauge
Y Type Strainer 399 29-Jun-19 08-Aug-20 175 08-Aug-20, Y Type Strainer
T4-PRO-FF-2490 PO Placement - Y Type Strainer 14 29-Jun-19 13-Jul-19 0% 175 PO Placement - Y Type Strainer
T4-PRO-FF-2500 Manufacturing - Y Type Strainer 35 13-Jul-19 18-Aug-19 0% 175 Manufacturing - Y Type Strainer
T4-PRO-FF-2510 Delivery at Site - Y Type Strainer 350 18-Aug-19 08-Aug-20 0% 175 Delivery at Site - Y Type Strainer
CI Butterfly Valve 399 29-Jun-19 08-Aug-20 175 08-Aug-20, CI Butterfly Valve
T4-PRO-FF-2520 PO Placement - CI Butterfly Valve 14 29-Jun-19 13-Jul-19 0% 175 PO Placement - CI Butterfly Valve
T4-PRO-FF-2530 Manufacturing - CI Butterfly Valve 35 13-Jul-19 18-Aug-19 0% 175 Manufacturing - CI Butterfly Valve
T4-PRO-FF-2540 Delivery at Site - CI Butterfly Valve 350 18-Aug-19 08-Aug-20 0% 175 Delivery at Site - CI Butterfly
Sprinkler Alarm Valve 399 18-Jul-19 27-Aug-20 156 27-Aug-20, Sprinkler Ala
T4-PRO-FF-2550 PO Placement - Sprinkler Alarm Valve 14 18-Jul-19 01-Aug-19 0% 156 PO Placement - Sprinkler Alarm Valve
T4-PRO-FF-2560 Manufacturing - Sprinkler Alarm Valve 35 01-Aug-19 07-Sep-19 0% 156 Manufacturing - Sprinkler Alarm Valve
T4-PRO-FF-2570 Delivery at Site - Sprinkler Alarm Valve 350 07-Sep-19 27-Aug-20 0% 156 Delivery at Site - Sprinkle
Flexible Rubber Bellows 399 29-Jun-19 08-Aug-20 175 08-Aug-20, Flexible Rubber
T4-PRO-FF-2580 PO Placement - Flexible Rubber Bellows 14 29-Jun-19 13-Jul-19 0% 175 PO Placement - Flexible Rubber Bellows
T4-PRO-FF-2590 Manufacturing - Flexible Rubber Bellows 35 13-Jul-19 18-Aug-19 0% 175 Manufacturing - Flexible Rubber Bellows
T4-PRO-FF-2600 Delivery at Site - Flexible Rubber Bellows 350 18-Aug-19 08-Aug-20 0% 175 Delivery at Site - Flexible Ru
Pressure Switch 399 29-Jun-19 08-Aug-20 175 08-Aug-20, Pressure Switch
T4-PRO-FF-2610 PO Placement - Pressure Switch 14 29-Jun-19 13-Jul-19 0% 175 PO Placement - Pressure Switch
T4-PRO-FF-2620 Manufacturing - Pressure Switch 35 13-Jul-19 18-Aug-19 0% 175 Manufacturing - Pressure Switch
T4-PRO-FF-2630 Delivery at Site - Pressure Switch 350 18-Aug-19 08-Aug-20 0% 175 Delivery at Site - Pressure Switch
Flow meter 399 29-Jun-19 08-Aug-20 175 08-Aug-20, Flow meter
T4-PRO-FF-2640 PO Placement - Flowmeter 14 29-Jun-19 13-Jul-19 0% 175 PO Placement - Flowmeter
T4-PRO-FF-2650 Manufacturing - Flowmeter 35 13-Jul-19 18-Aug-19 0% 175 Manufacturing - Flowmeter
T4-PRO-FF-2660 Delivery at Site - Flowmeter 350 18-Aug-19 08-Aug-20 0% 175 Delivery at Site - Flowmeter

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 26 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul A Sep Oct N Dec Jan F Mar Apr May J Jul
Float A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
GI pipes (Class B & C) 399 24-Jun-19 03-Aug-20 175 03-Aug-20, GI pipes (Class B
T4-PRO-FF-2670 PO Placement - GI Pipes (Class B & C) 14 24-Jun-19 08-Jul-19 0% 175 PO Placement - GI Pipes (Class B & C)
T4-PRO-FF-2680 Manufacturing - GI Pipes (Class B & C) 35 08-Jul-19 12-Aug-19 0% 175 Manufacturing - GI Pipes (Class B & C)
T4-PRO-FF-2690 Delivery at Site - GI Pipes (Class B & C) 350 12-Aug-19 03-Aug-20 0% 175 Delivery at Site - GI Pipes (C
CI Check Valve 399 02-Jul-19 11-Aug-20 167 11-Aug-20, CI Check Valve
T4-PRO-FF-2700 PO Placement - CI Check Valve 14 02-Jul-19 16-Jul-19 0% 167 PO Placement - CI Check Valve
T4-PRO-FF-2710 Manufacturing - CI Check Valve 35 16-Jul-19 21-Aug-19 0% 167 Manufacturing - CI Check Valve
T4-PRO-FF-2720 Delivery at Site - CI Check Valve 350 21-Aug-19 11-Aug-20 0% 167 Delivery at Site - CI Check Valve
Pressure Relief Valve 149 15-Jul-19 17-Dec-19 154 17-Dec-19, Pressure Relief Valve
T4-PRO-FF-2730 PO Placement - Pressure Relief Valve 14 15-Jul-19 29-Jul-19 0% 154 PO Placement - Pressure Relief Valve
T4-PRO-FF-2740 Manufacturing - Pressure Relief Valve 35 29-Jul-19 04-Sep-19 0% 154 Manufacturing - Pressure Relief Valve
T4-PRO-FF-2750 Delivery at Site - Pressure Relief Valve 100 04-Sep-19 17-Dec-19 0% 154 Delivery at Site - Pressure Relief Valve
Precharged Air Vessel - 500 Liters 149 09-Sep-19 10-Feb-20 196 10-Feb-20, Precharged Air Vessel - 500 Liters
T4-PRO-FF-2760 PO Placement - Precharged Air Vessel- 500 Ltr 14 09-Sep-19 23-Sep-19 0% 196 PO Placement - Precharged Air Vessel- 500 Ltr
T4-PRO-FF-2770 Manufacturing - Precharged Air Vessel- 500 Ltr 35 23-Sep-19 31-Oct-19 0% 196 Manufacturing - Precharged Air Vessel- 500 Ltr
T4-PRO-FF-2780 Delivery at Site - Precharged Air Vessel- 500 Ltr 100 31-Oct-19 10-Feb-20 0% 196 Delivery at Site - Precharged Air Vessel- 500 Ltr
Flow Switch 149 26-Sep-19 27-Feb-20 193 27-Feb-20, Flow Switch
T4-PRO-FF-2790 PO Placement - Flow Switch 14 26-Sep-19 12-Oct-19 0% 193 PO Placement - Flow Switch
T4-PRO-FF-2800 Manufacturing - Flow Switch 35 12-Oct-19 18-Nov-19 0% 193 Manufacturing - Flow Switch
T4-PRO-FF-2810 Delivery at Site - Flow Switch 100 18-Nov-19 27-Feb-20 0% 193 Delivery at Site - Flow Switch
Tamper Switch 199 09-Sep-19 31-Mar-20 210 31-Mar-20, Tamper Switch
T4-PRO-FF-2820 PO Placement - Tamper Switch 14 09-Sep-19 23-Sep-19 0% 210 PO Placement - Tamper Switch
T4-PRO-FF-2830 Manufacturing - Tamper Switch 35 23-Sep-19 31-Oct-19 0% 210 Manufacturing - Tamper Switch
T4-PRO-FF-2840 Delivery at Site - Tamper Switch 150 31-Oct-19 31-Mar-20 0% 210 Delivery at Site - Tamper Switch
Auto Air Vent 389 02-Jul-19 01-Aug-20 182 01-Aug-20, Auto Air Vent
T4-PRO-FF-2850 PO Placement - Auto Air Vent 14 02-Jul-19 16-Jul-19 0% 182 PO Placement - Auto Air Vent
T4-PRO-FF-2860 Manufacturing - Auto Air Vent 35 16-Jul-19 21-Aug-19 0% 182 Manufacturing - Auto Air Vent
T4-PRO-FF-2870 Delivery at Site - Auto Air Vent 340 21-Aug-19 01-Aug-20 0% 182 Delivery at Site - Auto Air Vent
Single / Double Hydrant Landing Valve 249 09-Sep-19 20-May-20 107 20-May-20, Single / Double Hydrant Land
T4-PRO-FF-2880 PO Placement - Single / Double Hydrant Landing Valve 14 09-Sep-19 23-Sep-19 0% 107 PO Placement - Single / Double Hydrant Landing Valve
T4-PRO-FF-2890 Manufacturing - Single / Double Hydrant Landing Valve 35 23-Sep-19 31-Oct-19 0% 107 Manufacturing - Single / Double Hydrant Landing Valve
T4-PRO-FF-2900 Delivery at Site - Single / Double Hydrant Landing Valve 200 31-Oct-19 20-May-20 0% 107 Delivery at Site - Single / Double Hydrant
4-way Breaching Inlet 249 24-Aug-19 05-May-20 122 05-May-20, 4-way Breaching Inlet
T4-PRO-FF-2910 PO Placement - 4- Way Breach Inlet 14 24-Aug-19 08-Sep-19 0% 122 PO Placement - 4- Way Breach Inlet
T4-PRO-FF-2920 Manufacturing - 4- Way Breach Inlet 35 08-Sep-19 15-Oct-19 0% 122 Manufacturing - 4- Way Breach Inlet
T4-PRO-FF-2930 Delivery at Site - 4- Way Breach Inlet 200 15-Oct-19 05-May-20 0% 122 Delivery at Site - 4- Way Breach Inlet
Orifice Plate 249 30-Aug-19 11-May-20 219 11-May-20, Orifice Plate
T4-PRO-FF-2940 PO Placement - Orifice Plate 14 30-Aug-19 14-Sep-19 0% 219 PO Placement - Orifice Plate
T4-PRO-FF-2950 Manufacturing - Orifice Plate 35 14-Sep-19 21-Oct-19 0% 219 Manufacturing - Orifice Plate
T4-PRO-FF-2960 Delivery at Site - Orifice Plate 200 21-Oct-19 11-May-20 0% 219 Delivery at Site - Orifice Plate
Deluge Valve 249 30-Jul-19 11-Apr-20 158 11-Apr-20, Deluge Valve
T4-PRO-FF-2970 PO Placement - Deluge Valve 14 30-Jul-19 13-Aug-19 0% 158 PO Placement - Deluge Valve
T4-PRO-FF-2980 Manufacturing - Deluge Valve 35 13-Aug-19 19-Sep-19 0% 158 Manufacturing - Deluge Valve
T4-PRO-FF-2990 Delivery at Site - Deluge Valve 200 19-Sep-19 11-Apr-20 0% 158 Delivery at Site - Deluge Valve
Water Curtain Nozzles 249 09-Aug-19 21-Apr-20 148 21-Apr-20, Water Curtain Nozzles
T4-PRO-FF-3000 PO Placement - Water Curtain Nozzles 14 09-Aug-19 24-Aug-19 0% 148 PO Placement - Water Curtain Nozzles
T4-PRO-FF-3010 Manufacturing - Water Curtain Nozzles 35 24-Aug-19 29-Sep-19 0% 148 Manufacturing - Water Curtain Nozzles
T4-PRO-FF-3020 Delivery at Site - Water Curtain Nozzles 200 29-Sep-19 21-Apr-20 0% 148 Delivery at Site - Water Curtain Nozzles
First Aid Hose Reel 299 28-Aug-19 28-Jun-20 216 28-Jun-20, First Aid Hose Reel
T4-PRO-FF-3030 PO Placement - First Aid Hose Reel 14 28-Aug-19 12-Sep-19 0% 216 PO Placement - First Aid Hose Reel
T4-PRO-FF-3040 Manufacturing - First Aid Hose Reel 35 12-Sep-19 19-Oct-19 0% 216 Manufacturing - First Aid Hose Reel
T4-PRO-FF-3050 Delivery at Site - First Aid Hose Reel 250 19-Oct-19 28-Jun-20 0% 216 Delivery at Site - First Aid Hose Reel
Branch Pipe and Nozzle 149 05-Jul-19 07-Dec-19 274 07-Dec-19, Branch Pipe and Nozzle

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 27 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul A Sep Oct N Dec Jan F Mar Apr May J Jul
Float A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-PRO-FF-3060 PO Placement - Branch Pipe & Nozzle 14 05-Jul-19 19-Jul-19 0% 274 PO Placement - Branch Pipe & Nozzle
T4-PRO-FF-3070 Manufacturing - Branch Pipe & Nozzle 35 19-Jul-19 24-Aug-19 0% 274 Manufacturing - Branch Pipe & Nozzle
T4-PRO-FF-3080 Delivery at Site - Branch Pipe & Nozzle 100 24-Aug-19 07-Dec-19 0% 274 Delivery at Site - Branch Pipe & Nozzle
Fire Hose Pipe 299 28-Aug-19 28-Jun-20 216 28-Jun-20, Fire Hose Pipe
T4-PRO-FF-3090 PO Placement - Fire Hose Pipe 14 28-Aug-19 12-Sep-19 0% 216 PO Placement - Fire Hose Pipe
T4-PRO-FF-3100 Manufacturing - Fire Hose Pipe 35 12-Sep-19 19-Oct-19 0% 216 Manufacturing - Fire Hose Pipe
T4-PRO-FF-3110 Delivery at Site - Fire Hose Pipe 250 19-Oct-19 28-Jun-20 0% 216 Delivery at Site - Fire Hose Pipe
Inline PRV 399 26-Sep-19 03-Nov-20 88 03-Nov-20, In
T4-PRO-FF-3120 PO Placement - Inline PRV 14 26-Sep-19 12-Oct-19 0% 88 PO Placement - Inline PRV
T4-PRO-FF-3130 Manufacturing - Inline PRV 35 12-Oct-19 18-Nov-19 0% 88 Manufacturing - Inline PRV
T4-PRO-FF-3140 Delivery at Site - Inline PRV 350 18-Nov-19 03-Nov-20 0% 88 Delivery at Si
Fire Hose Cabinet 299 07-Sep-19 07-Jul-20 207 07-Jul-20, Fire Hose Cabinet
T4-PRO-FF-3150 PO Placement - Fiire Hose Cabinet 14 07-Sep-19 21-Sep-19 0% 207 PO Placement - Fiire Hose Cabinet
T4-PRO-FF-3160 Manufacturing - Fiire Hose Cabinet 35 21-Sep-19 29-Oct-19 0% 207 Manufacturing - Fiire Hose Cabinet
T4-PRO-FF-3170 Delivery at Site - Fiire Hose Cabinet 250 29-Oct-19 07-Jul-20 0% 207 Delivery at Site - Fiire Hose Cabinet
Fire Extinguisher 149 15-Jul-19 17-Dec-19 291 17-Dec-19, Fire Extinguisher
T4-PRO-FF-3180 PO Placement - Fire Extinguisher 14 15-Jul-19 29-Jul-19 0% 291 PO Placement - Fire Extinguisher
T4-PRO-FF-3190 Manufacturing - Fire Extinguisher 35 29-Jul-19 04-Sep-19 0% 291 Manufacturing - Fire Extinguisher
T4-PRO-FF-3200 Delivery at Site - Fire Extinguisher 100 04-Sep-19 17-Dec-19 0% 291 Delivery at Site - Fire Extinguisher
Ball Valve 399 28-Jun-19 07-Aug-20 176 07-Aug-20, Ball Valve
T4-PRO-FF-3210 PO Placement - Ball Valve 14 28-Jun-19 12-Jul-19 0% 176 PO Placement - Ball Valve
T4-PRO-FF-3220 Manufacturing - Ball Valve 35 12-Jul-19 17-Aug-19 0% 176 Manufacturing - Ball Valve
T4-PRO-FF-3230 Delivery at Site - Ball Valve 350 17-Aug-19 07-Aug-20 0% 176 Delivery at Site - Ball Valve
Sprinklers 399 24-Aug-19 02-Oct-20 120 02-Oct-20, Sprinklers
T4-PRO-FF-3240 PO Placement - Sprinklers 14 24-Aug-19 08-Sep-19 0% 120 PO Placement - Sprinklers
T4-PRO-FF-3250 Manufacturing - Sprinklers 35 08-Sep-19 15-Oct-19 0% 120 Manufacturing - Sprinklers
T4-PRO-FF-3260 Delivery at Site - Sprinklers 350 15-Oct-19 02-Oct-20 0% 120 Delivery at Site - S
Flexible Sprinkler Connector 399 09-Jul-19 18-Aug-20 165 18-Aug-20, Flexible Sprink
T4-PRO-FF-3270 PO Placement - Flexible Sprinkler Connector 14 09-Jul-19 23-Jul-19 0% 165 PO Placement - Flexible Sprinkler Connector
T4-PRO-FF-3280 Manufacturing - Flexible Sprinkler Connector 35 23-Jul-19 28-Aug-19 0% 165 Manufacturing - Flexible Sprinkler Connector
T4-PRO-FF-3290 Delivery at Site - Flexible Sprinkler Connector 350 28-Aug-19 18-Aug-20 0% 165 Delivery at Site - Flexible S
Grooved Coupling (Flexible & Rigid) 399 25-Jul-19 03-Sep-20 144 03-Sep-20, Grooved C
T4-PRO-FF-3300 PO Placement - Grooved Coupling 14 25-Jul-19 08-Aug-19 0% 144 PO Placement - Grooved Coupling
T4-PRO-FF-3310 Manufacturing - Grooved Coupling 35 08-Aug-19 14-Sep-19 0% 144 Manufacturing - Grooved Coupling
T4-PRO-FF-3320 Delivery at Site - Grooved Coupling 350 14-Sep-19 03-Sep-20 0% 144 Delivery at Site - Groov
ELE 306 13-Jun-19 21-Apr-20 263 21-Apr-20, ELE
CLASS A 172 17-Jul-19 11-Jan-20 188 11-Jan-20, CLASS A
LT Panels 139 07-Aug-19 30-Dec-19 140 30-Dec-19, LT Panels
T4-PRO-ELE-2320 PO Placement - LT Panels 21 07-Aug-19 04-Sep-19 0% 103 PO Placement - LT Panels
T4-PRO-ELE-2570 Manufacturing - LT Panels 70 04-Sep-19 17-Nov-19 0% 140 Manufacturing - LT Panels
T4-PRO-ELE-2580 Delivery at Site - LT Panels 42 17-Nov-19 30-Dec-19 0% 140 Delivery at Site - LT Panels
Sub Main DB's 139 07-Aug-19 30-Dec-19 167 30-Dec-19, Sub Main DB's
T4-PRO-ELE-2590 PO Placement - Sub Main DB's 21 07-Aug-19 04-Sep-19 0% 122 PO Placement - Sub Main DB's
T4-PRO-ELE-2600 Manufacturing - Sub Main DB's 70 04-Sep-19 17-Nov-19 0% 167 Manufacturing - Sub Main DB's
T4-PRO-ELE-2610 Delivery at Site - Sub Main DB's 42 17-Nov-19 30-Dec-19 0% 167 Delivery at Site - Sub Main DB's
MCC Panel 140 19-Aug-19 11-Jan-20 152 11-Jan-20, MCC Panel
T4-PRO-ELE-2620 PO Placement - MCC Panel 21 19-Aug-19 16-Sep-19 0% 113 PO Placement - MCC Panel
T4-PRO-ELE-2630 Manufacturing - MCC Panel 70 16-Sep-19 29-Nov-19 0% 152 Manufacturing - MCC Panel
T4-PRO-ELE-2640 Delivery at Site - MCC Panel 42 29-Nov-19 11-Jan-20 0% 152 Delivery at Site - MCC Panel
Isolators 131 07-Aug-19 21-Dec-19 175 21-Dec-19, Isolators
T4-PRO-ELE-2650 PO Placement - Isolators 14 07-Aug-19 26-Aug-19 0% 129 PO Placement - Isolators
T4-PRO-ELE-2660 Manufacturing - Isolators 70 26-Aug-19 08-Nov-19 0% 175 Manufacturing - Isolators

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 28 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-PRO-ELE-2670 Delivery at Site - Isolators 42 08-Nov-19 21-Dec-19 0% 175 Delivery at Site - Isolators
Common DB's 125 17-Jul-19 24-Nov-19 214 24-Nov-19, Common DB's
T4-PRO-ELE-2680 PO Placement - Common DB's 14 17-Jul-19 05-Aug-19 0% 159 PO Placement - Common DB's
T4-PRO-ELE-2690 Manufacturing - Common DB's 70 05-Aug-19 18-Oct-19 0% 214 Manufacturing - Common DB's
T4-PRO-ELE-2700 Delivery at Site - Common DB's 35 18-Oct-19 24-Nov-19 0% 214 Delivery at Site - Common DB's
ATS 132 07-Aug-19 22-Dec-19 174 22-Dec-19, ATS
T4-PRO-ELE-2710 PO Placement - ATS 21 07-Aug-19 04-Sep-19 0% 127 PO Placement - ATS
T4-PRO-ELE-2720 Manufacturing - ATS 70 04-Sep-19 17-Nov-19 0% 174 Manufacturing - ATS
T4-PRO-ELE-2730 Delivery at Site - ATS 35 17-Nov-19 22-Dec-19 0% 174 Delivery at Site - ATS
Invertor 118 14-Aug-19 15-Dec-19 174 15-Dec-19, Invertor
T4-PRO-ELE-2740 PO Placement - Invertor 21 14-Aug-19 11-Sep-19 0% 127 PO Placement - Invertor
T4-PRO-ELE-2750 Manufacturing - Invertor 70 11-Sep-19 24-Nov-19 0% 174 Manufacturing - Invertor
T4-PRO-ELE-2760 Delivery at Site - Invertor 21 24-Nov-19 15-Dec-19 0% 174 Delivery at Site - Invertor
Invertor Batteries 118 14-Aug-19 15-Dec-19 184 15-Dec-19, Invertor Batteries
T4-PRO-ELE-2770 PO Placement - Invertor Batteries 21 14-Aug-19 11-Sep-19 0% 135 PO Placement - Invertor Batteries
T4-PRO-ELE-2780 Manufacturing - Invertor Batteries 70 11-Sep-19 24-Nov-19 0% 184 Manufacturing - Invertor Batteries
T4-PRO-ELE-2790 Delivery at Site - Invertor Batteries 21 24-Nov-19 15-Dec-19 0% 184 Delivery at Site - Invertor Batteries
Lightning Protection System 87 19-Aug-19 18-Nov-19 241 18-Nov-19, Lightning Protection System
T4-PRO-ELE-2800 PO Placement - Lightning Protection System 14 19-Aug-19 05-Sep-19 0% 176 PO Placement - Lightning Protection System
T4-PRO-ELE-2810 Manufacturing - Lightning Protection System 70 05-Sep-19 18-Nov-19 0% 241 Manufacturing - Lightning Protection System
T4-PRO-ELE-2820 Delivery at Site - Lightning Protection System 21 05-Sep-19 26-Sep-19 0% 241 Delivery at Site - Lightning Protection System
CLASS B 306 13-Jun-19 21-Apr-20 263 21-Apr-20, CLASS B
GI Conduit 249 25-Jun-19 07-Mar-20 251 07-Mar-20, GI Conduit
T4-PRO-ELE-2830 PO Placement - GI Conduit 14 25-Jun-19 09-Jul-19 0% 251 PO Placement - GI Conduit
T4-PRO-ELE-2840 Manufacturing - GI Conduit 35 09-Jul-19 13-Aug-19 0% 251 Manufacturing - GI Conduit
T4-PRO-ELE-2850 Delivery at Site - GI Conduit 200 13-Aug-19 07-Mar-20 0% 251 Delivery at Site - GI Conduit
PVC Conduit 249 26-Jun-19 08-Mar-20 250 08-Mar-20, PVC Conduit
T4-PRO-ELE-2860 PO Placement - PVC Conduit 14 26-Jun-19 10-Jul-19 0% 250 PO Placement - PVC Conduit
T4-PRO-ELE-2870 Manufacturing - PVC Conduit 35 10-Jul-19 14-Aug-19 0% 250 Manufacturing - PVC Conduit
T4-PRO-ELE-2880 Delivery at Site - PVC Conduit 200 14-Aug-19 08-Mar-20 0% 250 Delivery at Site - PVC Conduit
Switch Sockets 249 10-Jul-19 22-Mar-20 293 22-Mar-20, Switch Sockets
T4-PRO-ELE-2890 PO Placement - Switch Sockets 14 10-Jul-19 24-Jul-19 0% 293 PO Placement - Switch Sockets
T4-PRO-ELE-2900 Manufacturing - Switch Sockets 35 24-Jul-19 29-Aug-19 0% 293 Manufacturing - Switch Sockets
T4-PRO-ELE-2910 Delivery at Site - Switch Sockets 200 29-Aug-19 22-Mar-20 0% 293 Delivery at Site - Switch Sockets
HT Cable 70 04-Jul-19 14-Sep-19 275 14-Sep-19, HT Cable
T4-PRO-ELE-2920 PO Placement - HT Cable 14 04-Jul-19 18-Jul-19 0% 275 PO Placement - HT Cable
T4-PRO-ELE-2930 Manufacturing - HT Cable 35 18-Jul-19 23-Aug-19 0% 275 Manufacturing - HT Cable
T4-PRO-ELE-2940 Delivery at Site - HT Cable 21 23-Aug-19 14-Sep-19 0% 275 Delivery at Site - HT Cable
LT Cable - Power & Control 249 09-Aug-19 21-Apr-20 38 21-Apr-20, LT Cable - Power & Control
T4-PRO-ELE-2950 PO Placement - LT Cable 14 09-Aug-19 24-Aug-19 0% 38 PO Placement - LT Cable
T4-PRO-ELE-2960 Manufacturing - LT Cable 35 24-Aug-19 29-Sep-19 0% 38 Manufacturing - LT Cable
T4-PRO-ELE-2970 Delivery at Site - LT Cable 200 29-Sep-19 21-Apr-20 0% 38 Delivery at Site - LT Cable
FS Cable - Power & Control 249 09-Aug-19 21-Apr-20 38 21-Apr-20, FS Cable - Power & Control
T4-PRO-ELE-2980 PO Placement - FS Cable 14 09-Aug-19 24-Aug-19 0% 38 PO Placement - FS Cable
T4-PRO-ELE-2990 Manufacturing - FS Cable 35 24-Aug-19 29-Sep-19 0% 38 Manufacturing - FS Cable
T4-PRO-ELE-3000 Delivery at Site - FS Cable 200 29-Sep-19 21-Apr-20 0% 38 Delivery at Site - FS Cable
Cable Tray & Trunking 249 02-Jul-19 14-Mar-20 174 14-Mar-20, Cable Tray & Trunking
T4-PRO-ELE-3010 PO Placement - Cable Tray & Trunking 14 02-Jul-19 16-Jul-19 0% 174 PO Placement - Cable Tray & Trunking
T4-PRO-ELE-3020 Manufacturing - Cable Tray & Trunking 35 16-Jul-19 21-Aug-19 0% 174 Manufacturing - Cable Tray & Trunking
T4-PRO-ELE-3030 Delivery at Site - Cable Tray & Trunking 200 21-Aug-19 14-Mar-20 0% 174 Delivery at Site - Cable Tray & Trunking
Wires 249 02-Jul-19 14-Mar-20 80 14-Mar-20, Wires
T4-PRO-ELE-3040 PO Placement - Wires 14 02-Jul-19 16-Jul-19 0% 80 PO Placement - Wires
T4-PRO-ELE-3050 Manufacturing - Wires 35 16-Jul-19 21-Aug-19 0% 80 Manufacturing - Wires

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 29 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-PRO-ELE-3060 Delivery at Site - Wires 200 21-Aug-19 14-Mar-20 0% 80 Delivery at Site - Wires
Industrial Sockets 249 10-Jul-19 22-Mar-20 93 22-Mar-20, Industrial Sockets
T4-PRO-ELE-3070 PO Placement - Industrial Sockets 14 10-Jul-19 24-Jul-19 0% 93 PO Placement - Industrial Sockets
T4-PRO-ELE-3080 Manufacturing - Industrial Sockets 35 24-Jul-19 29-Aug-19 0% 93 Manufacturing - Industrial Sockets
T4-PRO-ELE-3090 Delivery at Site - Industrial Sockets 200 29-Aug-19 22-Mar-20 0% 93 Delivery at Site - Industrial Sockets
Glands & Lugs 70 13-Jun-19 23-Aug-19 274 23-Aug-19, Glands & Lugs
T4-PRO-ELE-3100 PO Placement - Glands & Lugs 14 13-Jun-19 27-Jun-19 0% 274 PO Placement - Glands & Lugs
T4-PRO-ELE-3110 Manufacturing - Glands & Lugs 35 27-Jun-19 01-Aug-19 0% 274 Manufacturing - Glands & Lugs
T4-PRO-ELE-3120 Delivery at Site - Glands & Lugs 21 01-Aug-19 23-Aug-19 0% 274 Delivery at Site - Glands & Lugs
Aviation Lights 249 12-Jul-19 24-Mar-20 272 24-Mar-20, Aviation Lights
T4-PRO-ELE-3130 PO Placement - Aviation Lights 14 12-Jul-19 26-Jul-19 0% 272 PO Placement - Aviation Lights
T4-PRO-ELE-3140 Manufacturing - Aviation Lights 35 26-Jul-19 31-Aug-19 0% 272 Manufacturing - Aviation Lights
T4-PRO-ELE-3150 Delivery at Site - Aviation Lights 200 31-Aug-19 24-Mar-20 0% 272 Delivery at Site - Aviation Lights
HT Termination Kit 249 04-Jul-19 16-Mar-20 96 16-Mar-20, HT Termination Kit
T4-PRO-ELE-3160 PO Placement - HT Termination Kit 14 04-Jul-19 18-Jul-19 0% 96 PO Placement - HT Termination Kit
T4-PRO-ELE-3170 Manufacturing - HT Termination Kit 35 18-Jul-19 23-Aug-19 0% 96 Manufacturing - HT Termination Kit
T4-PRO-ELE-3180 Delivery at Site - HT Termination Kit 200 23-Aug-19 16-Mar-20 0% 96 Delivery at Site - HT Termination Kit
Earthing & Copper Strip 249 06-Jul-19 18-Mar-20 197 18-Mar-20, Earthing & Copper Strip
T4-PRO-ELE-3190 PO Placement - Earthing & Copper Strip 14 06-Jul-19 20-Jul-19 0% 197 PO Placement - Earthing & Copper Strip
T4-PRO-ELE-3200 Manufacturing - Earthing & Copper Strip 35 20-Jul-19 25-Aug-19 0% 197 Manufacturing - Earthing & Copper Strip
T4-PRO-ELE-3210 Delivery at Site - Earthing & Copper Strip 200 25-Aug-19 18-Mar-20 0% 197 Delivery at Site - Earthing & Copper Strip
GI Strip 249 06-Jul-19 18-Mar-20 197 18-Mar-20, GI Strip
T4-PRO-ELE-3220 PO Placement - GI Strip 14 06-Jul-19 20-Jul-19 0% 197 PO Placement - GI Strip
T4-PRO-ELE-3230 Manufacturing - GI Strip 35 20-Jul-19 25-Aug-19 0% 197 Manufacturing - GI Strip
T4-PRO-ELE-3240 Delivery at Site - GI Strip 200 25-Aug-19 18-Mar-20 0% 197 Delivery at Site - GI Strip
MS Earth Strip 249 12-Jul-19 24-Mar-20 191 24-Mar-20, MS Earth Strip
T4-PRO-ELE-3250 PO Placement - MS Earth Strip 14 12-Jul-19 26-Jul-19 0% 191 PO Placement - MS Earth Strip
T4-PRO-ELE-3260 Manufacturing - MS Earth Strip 35 26-Jul-19 31-Aug-19 0% 191 Manufacturing - MS Earth Strip
T4-PRO-ELE-3270 Delivery at Site - MS Earth Strip 200 31-Aug-19 24-Mar-20 0% 191 Delivery at Site - MS Earth Strip
Maintenance Free Earthing 239 12-Jul-19 14-Mar-20 201 14-Mar-20, Maintenance Free Earthing
T4-PRO-ELE-3280 PO Placement - Maintenance Free Earthing 14 12-Jul-19 26-Jul-19 0% 201 PO Placement - Maintenance Free Earthing
T4-PRO-ELE-3290 Manufacturing - Maintenance Free Earthing 25 26-Jul-19 21-Aug-19 0% 201 Manufacturing - Maintenance Free Earthing
T4-PRO-ELE-3300 Delivery at Site - Maintenance Free Earthing 200 21-Aug-19 14-Mar-20 0% 201 Delivery at Site - Maintenance Free Earthing

MODULAR FABRICATION 150 15-Sep-19 16-Feb-20 120 16-Feb-20, MODULAR FABRICATION

MODULES FOR LEVEL 09 138 15-Sep-19 04-Feb-20 73 04-Feb-20, MODULES FOR LEVEL 09
PRE FABRICATION 125 15-Sep-19 22-Jan-20 86 22-Jan-20, PRE FABRICATION
T4-MD-FAB-PF-2005 Fabrication of Modular Frame (FL09) 10 15-Sep-19 24-Sep-19 0% 100 Fabrication of Modular Frame (FL09)
T4-MD-FAB-PF-2015 Fabrication of Chilled Water Pipes & Insulation as per module size (FL09) 60 22-Nov-19 22-Jan-20 0% 70 Fabrication of Chilled Water Pipes & Insulation as per module
T4-MD-FAB-PF-2025 Fabrication of Fire Fighting Pipes as per module size & painting / Nomenclature (FL09) 60 15-Sep-19 17-Nov-19 0% 144 Fabrication of Fire Fighting Pipes as per module size & painting / Nomen
T4-MD-FAB-PF-2045 Cutting of Cable Trays as per module size (FL09) 60 15-Sep-19 17-Nov-19 0% 151 Cutting of Cable Trays as per module size (FL09)
MODULE ASSEMBLY 134 19-Sep-19 04-Feb-20 70 04-Feb-20, MODULE ASSEMBLY
T4-MD-FAB-MA-2085 Assembly of Module Frame & Tagging (FL09) 14 19-Sep-19 03-Oct-19 0% 124 Assembly of Module Frame & Tagging (FL09)
T4-MD-FAB-MA-2095 Assembly of Factory Fabricated Ducts & Insulation (FL09) 60 26-Sep-19 28-Nov-19 0% 124 Assembly of Factory Fabricated Ducts & Insulation (FL09)
T4-MD-FAB-MA-2105 Assembly of Chilled Water Pipe (FL09) 60 29-Nov-19 29-Jan-20 0% 70 Assembly of Chilled Water Pipe (FL09)
T4-MD-FAB-MA-2115 Assembly of Fire Fighting (FL09) 55 01-Dec-19 26-Jan-20 0% 77 Assembly of Fire Fighting (FL09)
T4-MD-FAB-MA-2125 Assembly of Cable Trays (FL09) 50 08-Dec-19 28-Jan-20 0% 77 Assembly of Cable Trays (FL09)
T4-MD-FAB-MA-2135 Installation of FCU & Valve stations (FL09) 45 20-Dec-19 04-Feb-20 0% 70 Installation of FCU & Valve stations (FL09)
T4-MD-FAB-MA-2145 Installation of balance accessories for all services (FL09) 45 20-Dec-19 04-Feb-20 0% 70 Installation of balance accessories for all services (FL09)
MODULES FOR LEVEL 10 73 16-Oct-19 30-Dec-19 121 30-Dec-19, MODULES FOR LEVEL 10
PRE FABRICATION 60 16-Oct-19 16-Dec-19 134 16-Dec-19, PRE FABRICATION
T4-MD-FAB-PF-2055 Fabrication of Modular Frame (FL10) 10 16-Oct-19 25-Oct-19 0% 100 Fabrication of Modular Frame (FL10)
T4-MD-FAB-PF-2065 Fabrication of Chilled Water Pipes & Insulation as per module size (FL10) 60 16-Oct-19 16-Dec-19 0% 124 Fabrication of Chilled Water Pipes & Insulation as per module size (

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 30 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-MD-FAB-PF-2075 Fabrication of Fire Fighting Pipes as per module size & painting / Nomenclature (FL10) 60 16-Oct-19 16-Dec-19 0% 127 Fabrication of Fire Fighting Pipes as per module size & painting / No
T4-MD-FAB-PF-2085 Cutting of Cable Trays as per module size (FL10) 60 16-Oct-19 16-Dec-19 0% 134 Cutting of Cable Trays as per module size (FL10)
MODULE ASSEMBLY 69 20-Oct-19 30-Dec-19 113 30-Dec-19, MODULE ASSEMBLY
T4-MD-FAB-MA-2155 Assembly of Module Frame & Tagging (FL10) 14 20-Oct-19 03-Nov-19 0% 113 Assembly of Module Frame & Tagging (FL10)
T4-MD-FAB-MA-2165 Assembly of Factory Fabricated Ducts & Insulation (FL10) 45 27-Oct-19 12-Dec-19 0% 113 Assembly of Factory Fabricated Ducts & Insulation (FL10)
T4-MD-FAB-MA-2175 Assembly of Chilled Water Pipe (FL10) 45 04-Nov-19 19-Dec-19 0% 113 Assembly of Chilled Water Pipe (FL10)
T4-MD-FAB-MA-2185 Assembly of Fire Fighting (FL10) 45 04-Nov-19 19-Dec-19 0% 116 Assembly of Fire Fighting (FL10)
T4-MD-FAB-MA-2195 Assembly of Cable Trays (FL10) 45 11-Nov-19 27-Dec-19 0% 116 Assembly of Cable Trays (FL10)
T4-MD-FAB-MA-2205 Installation of FCU & Valve stations (FL10) 45 15-Nov-19 30-Dec-19 0% 113 Installation of FCU & Valve stations (FL10)
T4-MD-FAB-MA-2215 Installation of balance accessories for all services (FL10) 45 15-Nov-19 30-Dec-19 0% 113 Installation of balance accessories for all services (FL10)
MODULES FOR LEVEL 11 68 22-Oct-19 31-Dec-19 123 31-Dec-19, MODULES FOR LEVEL 11
PRE FABRICATION 55 22-Oct-19 17-Dec-19 136 17-Dec-19, PRE FABRICATION
T4-MD-FAB-PF-2095 Fabrication of Modular Frame (FL11) 10 22-Oct-19 01-Nov-19 0% 100 Fabrication of Modular Frame (FL11)
T4-MD-FAB-PF-2105 Fabrication of Chilled Water Pipes & Insulation as per module size (FL11) 55 22-Oct-19 17-Dec-19 0% 124 Fabrication of Chilled Water Pipes & Insulation as per module size (
T4-MD-FAB-PF-2115 Fabrication of Fire Fighting Pipes as per module size & painting / Nomenclature (FL11) 55 22-Oct-19 17-Dec-19 0% 129 Fabrication of Fire Fighting Pipes as per module size & painting / N
T4-MD-FAB-PF-2125 Cutting of Cable Trays as per module size (FL11) 55 22-Oct-19 17-Dec-19 0% 136 Cutting of Cable Trays as per module size (FL11)
MODULE ASSEMBLY 64 26-Oct-19 31-Dec-19 113 31-Dec-19, MODULE ASSEMBLY
T4-MD-FAB-MA-2225 Assembly of Module Frame & Tagging (FL11) 14 26-Oct-19 09-Nov-19 0% 113 Assembly of Module Frame & Tagging (FL11)
T4-MD-FAB-MA-2235 Assembly of Factory Fabricated Ducts & Insulation (FL11) 50 03-Nov-19 23-Dec-19 0% 113 Assembly of Factory Fabricated Ducts & Insulation (FL11)
T4-MD-FAB-MA-2245 Assembly of Chilled Water Pipe (FL11) 50 10-Nov-19 31-Dec-19 0% 113 Assembly of Chilled Water Pipe (FL11)
T4-MD-FAB-MA-2255 Assembly of Fire Fighting (FL11) 45 16-Nov-19 31-Dec-19 0% 113 Assembly of Fire Fighting (FL11)
T4-MD-FAB-MA-2265 Assembly of Cable Trays (FL11) 42 19-Nov-19 31-Dec-19 0% 113 Assembly of Cable Trays (FL11)
T4-MD-FAB-MA-2275 Installation of FCU & Valve stations (FL11) 45 10-Nov-19 26-Dec-19 0% 118 Installation of FCU & Valve stations (FL11)
T4-MD-FAB-MA-2285 Installation of balance accessories for all services (FL11) 40 21-Nov-19 31-Dec-19 0% 113 Installation of balance accessories for all services (FL11)
MODULES FOR LEVEL 12 84 22-Oct-19 16-Jan-20 151 16-Jan-20, MODULES FOR LEVEL 12
PRE FABRICATION 60 22-Oct-19 22-Dec-19 175 22-Dec-19, PRE FABRICATION
T4-MD-FAB-PF-2135 Fabrication of Modular Frame (FL12) 10 22-Oct-19 01-Nov-19 0% 100 Fabrication of Modular Frame (FL12)
T4-MD-FAB-PF-2145 Fabrication of Chilled Water Pipes & Insulation as per module size (FL12) 60 22-Oct-19 22-Dec-19 0% 154 Fabrication of Chilled Water Pipes & Insulation as per module size
T4-MD-FAB-PF-2155 Fabrication of Fire Fighting Pipes as per module size & painting / Nomenclature (FL12) 60 22-Oct-19 22-Dec-19 0% 168 Fabrication of Fire Fighting Pipes as per module size & painting / N
T4-MD-FAB-PF-2165 Cutting of Cable Trays as per module size (FL12) 60 22-Oct-19 22-Dec-19 0% 175 Cutting of Cable Trays as per module size (FL12)
MODULE ASSEMBLY 80 26-Oct-19 16-Jan-20 143 16-Jan-20, MODULE ASSEMBLY
T4-MD-FAB-MA-2295 Assembly of Module Frame & Tagging (FL12) 14 26-Oct-19 09-Nov-19 0% 143 Assembly of Module Frame & Tagging (FL12)
T4-MD-FAB-MA-2305 Assembly of Factory Fabricated Ducts & Insulation (FL12) 45 03-Nov-19 18-Dec-19 0% 143 Assembly of Factory Fabricated Ducts & Insulation (FL12)
T4-MD-FAB-MA-2315 Assembly of Chilled Water Pipe (FL12) 45 10-Nov-19 26-Dec-19 0% 143 Assembly of Chilled Water Pipe (FL12)
T4-MD-FAB-MA-2325 Assembly of Fire Fighting (FL12) 45 18-Nov-19 02-Jan-20 0% 150 Assembly of Fire Fighting (FL12)
T4-MD-FAB-MA-2335 Assembly of Cable Trays (FL12) 45 25-Nov-19 09-Jan-20 0% 150 Assembly of Cable Trays (FL12)
T4-MD-FAB-MA-2345 Installation of FCU & Valve stations (FL12) 45 02-Dec-19 16-Jan-20 0% 143 Installation of FCU & Valve stations (FL12)
T4-MD-FAB-MA-2355 Installation of balance accessories for all services (FL12) 45 02-Dec-19 16-Jan-20 0% 143 Installation of balance accessories for all services (FL12)
MODULES FOR LEVEL 14 75 29-Nov-19 12-Feb-20 113 12-Feb-20, MODULES FOR LEVEL 14
PRE FABRICATION 60 29-Nov-19 28-Jan-20 128 28-Jan-20, PRE FABRICATION
T4-MD-FAB-PF-2175 Fabrication of Modular Frame (FL14) 10 29-Nov-19 08-Dec-19 0% 100 Fabrication of Modular Frame (FL14)
T4-MD-FAB-PF-2185 Fabrication of Chilled Water Pipes & Insulation as per module size (FL14) 60 29-Nov-19 28-Jan-20 0% 116 Fabrication of Chilled Water Pipes & Insulation as per modu
T4-MD-FAB-PF-2195 Fabrication of Fire Fighting Pipes as per module size & painting / Nomenclature (FL14) 60 29-Nov-19 28-Jan-20 0% 121 Fabrication of Fire Fighting Pipes as per module size & paint
T4-MD-FAB-PF-2205 Cutting of Cable Trays as per module size (FL14) 60 29-Nov-19 28-Jan-20 0% 128 Cutting of Cable Trays as per module size (FL14)
MODULE ASSEMBLY 71 03-Dec-19 12-Feb-20 105 12-Feb-20, MODULE ASSEMBLY
T4-MD-FAB-MA-2365 Assembly of Module Frame & Tagging (FL14) 14 03-Dec-19 16-Dec-19 0% 105 Assembly of Module Frame & Tagging (FL14)
T4-MD-FAB-MA-2375 Assembly of Factory Fabricated Ducts & Insulation (FL14) 60 10-Dec-19 08-Feb-20 0% 105 Assembly of Factory Fabricated Ducts & Insulation (FL14)
T4-MD-FAB-MA-2385 Assembly of Chilled Water Pipe (FL14) 45 17-Dec-19 31-Jan-20 0% 105 Assembly of Chilled Water Pipe (FL14)
T4-MD-FAB-MA-2395 Assembly of Fire Fighting services (FL14) 45 22-Dec-19 05-Feb-20 0% 105 Assembly of Fire Fighting services (FL14)
T4-MD-FAB-MA-2405 Assembly of Cable Trays (FL14) 45 30-Dec-19 12-Feb-20 0% 105 Assembly of Cable Trays (FL14)
T4-MD-FAB-MA-2415 Installation of FCU & Valve stations (FL14) 45 28-Dec-19 10-Feb-20 0% 107 Installation of FCU & Valve stations (FL14)
T4-MD-FAB-MA-2425 Installation of balance accessories for all services (FL14) 43 01-Jan-20 12-Feb-20 0% 105 Installation of balance accessories for all services (FL14)

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 31 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
MODULES FOR LEVEL 15 75 01-Dec-19 14-Feb-20 116 14-Feb-20, MODULES FOR LEVEL 15
PRE FABRICATION 60 01-Dec-19 30-Jan-20 131 30-Jan-20, PRE FABRICATION
T4-MD-FAB-PF-2215 Fabrication of Modular Frame (FL15) 10 01-Dec-19 10-Dec-19 0% 100 Fabrication of Modular Frame (FL15)
T4-MD-FAB-PF-2225 Fabrication of Chilled Water Pipes & Insulation as per module size (FL15) 60 01-Dec-19 30-Jan-20 0% 119 Fabrication of Chilled Water Pipes & Insulation as per modu
T4-MD-FAB-PF-2235 Fabrication of Fire Fighting Pipes as per module size & painting / Nomenclature (FL15) 60 01-Dec-19 30-Jan-20 0% 126 Fabrication of Fire Fighting Pipes as per module size & pain
T4-MD-FAB-PF-2245 Cutting of Cable Trays as per module size (FL15) 60 01-Dec-19 30-Jan-20 0% 131 Cutting of Cable Trays as per module size (FL15)
MODULE ASSEMBLY 71 05-Dec-19 14-Feb-20 108 14-Feb-20, MODULE ASSEMBLY
T4-MD-FAB-MA-2435 Assembly of Module Frame & Tagging (FL15) 14 05-Dec-19 18-Dec-19 0% 108 Assembly of Module Frame & Tagging (FL15)
T4-MD-FAB-MA-2445 Assembly of Factory Fabricated Ducts & Insulation (FL15) 60 12-Dec-19 10-Feb-20 0% 108 Assembly of Factory Fabricated Ducts & Insulation (FL15)
T4-MD-FAB-MA-2455 Assembly of Chilled Water Pipe (FL15) 45 19-Dec-19 02-Feb-20 0% 108 Assembly of Chilled Water Pipe (FL15)
T4-MD-FAB-MA-2465 Assembly of Fire Fighting (FL15) 45 27-Dec-19 09-Feb-20 0% 108 Assembly of Fire Fighting (FL15)
T4-MD-FAB-MA-2475 Assembly of Cable Trays (FL15) 45 01-Jan-20 14-Feb-20 0% 108 Assembly of Cable Trays (FL15)
T4-MD-FAB-MA-2485 Installation of FCU & Valve stations (FL15) 45 30-Dec-19 12-Feb-20 0% 110 Installation of FCU & Valve stations (FL15)
T4-MD-FAB-MA-2495 Installation of balance accessories for all services (FL15) 45 01-Jan-20 14-Feb-20 0% 108 Installation of balance accessories for all services (FL15)
MODULES FOR LEVEL 16 75 03-Dec-19 16-Feb-20 108 16-Feb-20, MODULES FOR LEVEL 16
PRE FABRICATION 60 03-Dec-19 01-Feb-20 123 01-Feb-20, PRE FABRICATION
T4-MD-FAB-PF-2255 Fabrication of Modular Frame (FL16) 10 03-Dec-19 12-Dec-19 0% 100 Fabrication of Modular Frame (FL16)
T4-MD-FAB-PF-2265 Fabrication of Chilled Water Pipes & Insulation as per module size (FL16) 60 03-Dec-19 01-Feb-20 0% 100 Fabrication of Chilled Water Pipes & Insulation as per modu
T4-MD-FAB-PF-2275 Fabrication of Fire Fighting Pipes as per module size & painting / Nomenclature (FL16) 60 03-Dec-19 01-Feb-20 0% 121 Fabrication of Fire Fighting Pipes as per module size & pain
T4-MD-FAB-PF-2285 Cutting of Cable Trays as per module size (FL16) 60 03-Dec-19 01-Feb-20 0% 123 Cutting of Cable Trays as per module size (FL16)
MODULE ASSEMBLY 71 07-Dec-19 16-Feb-20 100 16-Feb-20, MODULE ASSEMBLY
T4-MD-FAB-MA-2505 Assembly of Module Frame & Tagging (FL16) 14 07-Dec-19 20-Dec-19 0% 104 Assembly of Module Frame & Tagging (FL16)
T4-MD-FAB-MA-2515 Assembly of Factory Fabricated Ducts & Insulation (FL16) 60 14-Dec-19 12-Feb-20 0% 104 Assembly of Factory Fabricated Ducts & Insulation (FL16)
T4-MD-FAB-MA-2525 Assembly of Chilled Water Pipe (FL16) 45 21-Dec-19 04-Feb-20 0% 100 Assembly of Chilled Water Pipe (FL16)
T4-MD-FAB-MA-2535 Assembly of Fire Fighting (FL16) 45 29-Dec-19 11-Feb-20 0% 103 Assembly of Fire Fighting (FL16)
T4-MD-FAB-MA-2545 Assembly of Cable Trays (FL16) 45 31-Dec-19 13-Feb-20 0% 103 Assembly of Cable Trays (FL16)
T4-MD-FAB-MA-2555 Installation of FCU & Valve stations (FL16) 45 01-Jan-20 14-Feb-20 0% 100 Installation of FCU & Valve stations (FL16)
T4-MD-FAB-MA-2565 Installation of balance accessories for all services (FL16) 45 03-Jan-20 16-Feb-20 0% 100 Installation of balance accessories for all services (FL16)

INSTALLATION 482 16-Aug-19 15-Dec-20 16 15-De

LOADING DECK 441 16-Aug-19 04-Nov-20 57 04-Nov-20, L


T4-IN-GEN-LD-0910 Requirement of Loading Deck at P2 90 16-Aug-19 18-Nov-19 0% 408 Requirement of Loading Deck at P2
T4-IN-GEN-LD-0920 Requirement of Loading Deck at P7, P8 411 16-Sep-19 04-Nov-20 0% 57 Requirement
T4-IN-GEN-LD-0930 Requirement of Loading Deck at S1 91 20-Dec-19 20-Mar-20 0% 286 Requirement of Loading Deck at S1
T4-IN-GEN-LD-0940 Requirement of Loading Deck at FL22 47 25-Mar-20 10-May-20 0% 235 Requirement of Loading Deck at FL22
T4-IN-GEN-LD-0950 Requirement of Loading Deck at FL26 32 15-May-20 15-Jun-20 0% 199 Requirement of Loading Deck at FL26
T4-IN-GEN-LD-0960 Requirement of Loading Deck at FL30 31 18-Jun-20 18-Jul-20 0% 166 Requirement of Loading Deck a
T4-IN-GEN-LD-0970 Requirement of Loading Deck at FL34 38 21-Jul-20 27-Aug-20 0% 126 Requirement of Loading
T4-IN-GEN-LD-0980 Requirement of Loading Deck at FL38 65 01-Sep-20 04-Nov-20 0% 57 Requirement
FIRST FIX 471 21-Aug-19 09-Dec-20 22 09-Dec
ACCESS FROM CLIENT FIRST FIX 371 21-Aug-19 01-Sep-20 39 01-Sep-20, ACCESS FR
T4-IN-PHE-FF-1000 Partial access required from client for FL B2 0 15-Dec-19 0% 64 Partial access required from client for FL B2
T4-IN-PHE-FF-1070 Partial access required from client for FL B1 0 22-Nov-19 0% 83 Partial access required from client for FL B1
T4-IN-PHE-FF-1150 Partial access required from client for FL P0 0 15-Oct-19 0% 172 Partial access required from client for FL P0
T4-IN-PHE-FF-1230 Partial access required from client for FL P1 0 30-Sep-19 0% 206 Partial access required from client for FL P1
T4-IN-PHE-FF-1310 Partial access required from client for FL P2 0 21-Aug-19 0% 41 Partial access required from client for FL P2
T4-IN-PHE-FF-1390 Partial access required from client for FL P3 0 14-Oct-19 0% 182 Partial access required from client for FL P3
T4-IN-PHE-FF-1470 Partial access required from client for FL P4 0 14-Oct-19 0% 182 Partial access required from client for FL P4
T4-IN-PHE-FF-1550 Partial access required from client for FL P5 0 14-Oct-19 0% 182 Partial access required from client for FL P5
T4-IN-PHE-FF-1630 Partial access required from client for FL P6 0 14-Oct-19 0% 182 Partial access required from client for FL P6
T4-IN-PHE-FF-1710 Partial access required from client for FL P7 0 15-Sep-19 0% 100 Partial access required from client for FL P7
T4-IN-PHE-FF-1790 Partial access required from client for FL P8 0 15-Sep-19 0% 154 Partial access required from client for FL P8

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 32 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-PHE-FF-1870 Partial access required from client for FL P9 0 05-Dec-19 0% 133 Partial access required from client for FL P9
T4-IN-PHE-FF-1875 Partial access required from client for FL P10 0 05-Dec-19 0% 133 Partial access required from client for FL P10
T4-IN-PHE-FF-1950 Partial access required from client for S1 0 22-Dec-19 0% 80 Partial access required from client for S1
T4-IN-PHE-FF-1951 Partial access required from client for FL09 0 23-Dec-19 0% 112 Partial access required from client for FL09
T4-IN-PHE-FF-1952 Partial access required from client for FL10 0 23-Dec-19 0% 118 Partial access required from client for FL10
T4-IN-PHE-FF-1953 Partial access required from client for FL11 0 23-Dec-19 0% 118 Partial access required from client for FL11
T4-IN-PHE-FF-1954 Partial access required from client for FL12 0 23-Dec-19 0% 113 Partial access required from client for FL12
T4-IN-PHE-FF-1955 Partial access required from client for FL14 0 01-Feb-20 0% 76 Partial access required from client for FL14
T4-IN-PHE-FF-1966 Partial access required from client for FL15 0 01-Feb-20 0% 73 Partial access required from client for FL15
T4-IN-PHE-FF-1977 Partial access required from client for FL16 0 01-Feb-20 0% 72 Partial access required from client for FL16
T4-IN-PHE-FF-2030 Partial access required from client for FL17 0 01-Feb-20 0% 34 Partial access required from client for FL17
T4-IN-PHE-FF-2110 Partial access required from client for FL18 0 11-Apr-20 0% 182 Partial access required from client for FL18
T4-IN-PHE-FF-2190 Partial access required from client for FL19 0 11-Apr-20 0% 182 Partial access required from client for FL19
T4-IN-PHE-FF-2270 Partial access required from client for FL20 0 11-Apr-20 0% 182 Partial access required from client for FL20
T4-IN-PHE-FF-2350 Partial access required from client for FL21 0 11-Apr-20 0% 182 Partial access required from client for FL21
T4-IN-PHE-FF-2430 Partial access required from client for FL22 0 27-Mar-20 0% 1 Partial access required from client for FL22
T4-IN-PHE-FF-2510 Partial access required from client for FL23 0 15-May-20 0% 148 Partial access required from client for FL23
T4-IN-PHE-FF-2590 Partial access required from client for FL24 0 15-May-20 0% 148 Partial access required from client for FL24
T4-IN-PHE-FF-2670 Partial access required from client for FL25 0 15-May-20 0% 148 Partial access required from client for FL25
T4-IN-PHE-FF-2750 Partial access required from client for FL26 0 15-May-20 0% 148 Partial access required from client for FL26
T4-IN-PHE-FF-2830 Partial access required from client for FL27 0 15-May-20 0% 148 Partial access required from client for FL27
T4-IN-PHE-FF-2910 Partial access required from client for FL28 0 18-Jun-20 0% 114 Partial access required from client fo
T4-IN-PHE-FF-2990 Partial access required from client for FL29 0 18-Jun-20 0% 114 Partial access required from client fo
T4-IN-PHE-FF-3070 Partial access required from client for FL30 0 18-Jun-20 0% 114 Partial access required from client fo
T4-IN-PHE-FF-3150 Partial access required from client for FL31 0 18-Jun-20 0% 114 Partial access required from client fo
T4-IN-PHE-FF-3230 Partial access required from client for FL32 0 23-Jul-20 0% 79 Partial access required from cli
T4-IN-PHE-FF-3310 Partial access required from client for FL33 0 23-Jul-20 0% 79 Partial access required from cli
T4-IN-PHE-FF-3390 Partial access required from client for FL34 0 23-Jul-20 0% 79 Partial access required from cli
T4-IN-PHE-FF-3470 Partial access required from client for FL35 0 23-Jul-20 0% 79 Partial access required from cli
T4-IN-PHE-FF-3550 Partial access required from client for FL36 0 01-Sep-20 0% 39 Partial access required f
T4-IN-PHE-FF-3630 Partial access required from client for FL37 0 01-Sep-20 0% 39 Partial access required f
T4-IN-PHE-FF-3710 Partial access required from client for FL38 0 01-Sep-20 0% 39 Partial access required f
T4-IN-PHE-FF-3790 Partial access required from client for FL39 0 01-Sep-20 0% 39 Partial access required f
T4-IN-PHE-FF-3870 Partial access required from client for Roof 0 01-Sep-20 0% 0 Partial access required f
PHE / FF 471 21-Aug-19 09-Dec-20 22 09-Dec
HORIZONTAL SERVICES 428 21-Aug-19 27-Oct-20 18 27-Oct-20, HO
LEVEL B2 75 15-Dec-19 28-Feb-20 64 28-Feb-20, LEVEL B2
PLUMBING 40 15-Dec-19 24-Jan-20 99 24-Jan-20, PLUMBING
T4-IN-PHE-FF-1010 Installation of Water Supply Piping with first coat painting (B2) 30 15-Dec-19 14-Jan-20 0% 99 Installation of Water Supply Piping with first coat painting (B2)
T4-IN-PHE-FF-1020 Installation of Drainage Piping with first coat painting (B2) 30 15-Dec-19 14-Jan-20 0% 99 Installation of Drainage Piping with first coat painting (B2)
T4-IN-PHE-FF-1030 Hydrotesting of Water Supply Piping (B2) 10 15-Jan-20 24-Jan-20 0% 99 Hydrotesting of Water Supply Piping (B2)
T4-IN-PHE-FF-1040 Hydrotesting of Drainage Piping (B2) 10 15-Jan-20 24-Jan-20 0% 99 Hydrotesting of Drainage Piping (B2)
FIRE FIGHTING 75 15-Dec-19 28-Feb-20 64 28-Feb-20, FIRE FIGHTING
T4-IN-PHE-FF-1050 Installation of Hydrant & Sprinkler Piping with first coat painting (B2) 65 15-Dec-19 18-Feb-20 0% 64 Installation of Hydrant & Sprinkler Piping with first coat pa
T4-IN-PHE-FF-1060 Hydrotesting of Hydrant & Sprinkler Piping (B2) 10 19-Feb-20 28-Feb-20 0% 64 Hydrotesting of Hydrant & Sprinkler Piping (B2)
LEVEL B1 70 22-Nov-19 31-Jan-20 83 31-Jan-20, LEVEL B1
PLUMBING 55 22-Nov-19 16-Jan-20 98 16-Jan-20, PLUMBING
T4-IN-PHE-FF-1080 Installation of Water Supply Piping with first coat painting (B1) 45 22-Nov-19 06-Jan-20 0% 98 Installation of Water Supply Piping with first coat painting (B1)
T4-IN-PHE-FF-1090 Installation of Drainage Piping with first coat painting (B1) 45 22-Nov-19 06-Jan-20 0% 98 Installation of Drainage Piping with first coat painting (B1)
T4-IN-PHE-FF-1100 Hydrotesting of Water Supply Piping (B1) 10 07-Jan-20 16-Jan-20 0% 98 Hydrotesting of Water Supply Piping (B1)
T4-IN-PHE-FF-1110 Hydrotesting of Drainage Piping (B1) 10 07-Jan-20 16-Jan-20 0% 98 Hydrotesting of Drainage Piping (B1)
FIRE FIGHTING 70 22-Nov-19 31-Jan-20 83 31-Jan-20, FIRE FIGHTING

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 33 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-PHE-FF-1120 Installation of Hydrant & Sprinkler Piping with first coat painting (B1) 60 22-Nov-19 21-Jan-20 0% 83 Installation of Hydrant & Sprinkler Piping with first coat paintin
T4-IN-PHE-FF-1130 Hydrotesting of Hydrant & Sprinkler Piping (B1) 10 22-Jan-20 31-Jan-20 0% 83 Hydrotesting of Hydrant & Sprinkler Piping (B1)
LEVEL P0 30 15-Oct-19 15-Nov-19 172 15-Nov-19, LEVEL P0
PLUMBING 24 15-Oct-19 08-Nov-19 178 08-Nov-19, PLUMBING
T4-IN-PHE-FF-1180 Installation of Water Supply Piping with first coat painting (P0) 20 15-Oct-19 04-Nov-19 0% 178 Installation of Water Supply Piping with first coat painting (P0)
T4-IN-PHE-FF-1190 Installation of Drainage Piping with first coat painting (P0) 20 15-Oct-19 04-Nov-19 0% 178 Installation of Drainage Piping with first coat painting (P0)
T4-IN-PHE-FF-1200 Hydrotesting of Water Supply Piping (P0) 4 05-Nov-19 08-Nov-19 0% 178 Hydrotesting of Water Supply Piping (P0)
T4-IN-PHE-FF-1210 Hydrotesting of Drainage Piping (P0) 4 05-Nov-19 08-Nov-19 0% 178 Hydrotesting of Drainage Piping (P0)
FIRE FIGHTING 30 15-Oct-19 15-Nov-19 172 15-Nov-19, FIRE FIGHTING
T4-IN-PHE-FF-1160 Installation of Hydrant & Sprinkler Piping with first coat painting (P0) 25 15-Oct-19 09-Nov-19 0% 172 Installation of Hydrant & Sprinkler Piping with first coat painting (P0)
T4-IN-PHE-FF-1170 Hydrotesting of Hydrant & Sprinkler Piping (P0) 5 10-Nov-19 15-Nov-19 0% 172 Hydrotesting of Hydrant & Sprinkler Piping (P0)
LEVEL P1 18 30-Sep-19 20-Oct-19 207 20-Oct-19, LEVEL P1
PLUMBING 16 30-Sep-19 18-Oct-19 209 18-Oct-19, PLUMBING
T4-IN-PHE-FF-1260 Installation of Water Supply Piping with first coat painting (P1) 13 30-Sep-19 14-Oct-19 0% 209 Installation of Water Supply Piping with first coat painting (P1)
T4-IN-PHE-FF-1270 Installation of Drainage Piping with first coat painting (P1) 13 30-Sep-19 14-Oct-19 0% 209 Installation of Drainage Piping with first coat painting (P1)
T4-IN-PHE-FF-1280 Hydrotesting of Water Supply Piping (P1) 3 15-Oct-19 18-Oct-19 0% 209 Hydrotesting of Water Supply Piping (P1)
T4-IN-PHE-FF-1290 Hydrotesting of Drainage Piping (P1) 3 15-Oct-19 18-Oct-19 0% 209 Hydrotesting of Drainage Piping (P1)
FIRE FIGHTING 18 30-Sep-19 20-Oct-19 207 20-Oct-19, FIRE FIGHTING
T4-IN-PHE-FF-1240 Installation of Hydrant & Sprinkler Piping with first coat painting (P1) 15 30-Sep-19 16-Oct-19 0% 207 Installation of Hydrant & Sprinkler Piping with first coat painting (P1)
T4-IN-PHE-FF-1250 Hydrotesting of Hydrant & Sprinkler Piping (P1) 3 17-Oct-19 20-Oct-19 0% 207 Hydrotesting of Hydrant & Sprinkler Piping (P1)
LEVEL P2 35 21-Aug-19 25-Sep-19 64 25-Sep-19, LEVEL P2
PLUMBING 18 21-Aug-19 09-Sep-19 81 09-Sep-19, PLUMBING
T4-IN-PHE-FF-1340 Installation of Water Supply Piping with first coat painting (P2) 15 21-Aug-19 05-Sep-19 0% 81 Installation of Water Supply Piping with first coat painting (P2)
T4-IN-PHE-FF-1350 Installation of Drainage Piping with first coat painting (P2) 15 21-Aug-19 05-Sep-19 0% 81 Installation of Drainage Piping with first coat painting (P2)
T4-IN-PHE-FF-1360 Hydrotesting of Water Supply Piping (P2) 3 06-Sep-19 09-Sep-19 0% 81 Hydrotesting of Water Supply Piping (P2)
T4-IN-PHE-FF-1370 Hydrotesting of Drainage Piping (P2) 3 06-Sep-19 09-Sep-19 0% 81 Hydrotesting of Drainage Piping (P2)
FIRE FIGHTING 35 21-Aug-19 25-Sep-19 64 25-Sep-19, FIRE FIGHTING
T4-IN-PHE-FF-1320 Installation of Hydrant & Sprinkler Piping with first coat painting (P2) 30 21-Aug-19 20-Sep-19 0% 64 Installation of Hydrant & Sprinkler Piping with first coat painting (P2)
T4-IN-PHE-FF-1330 Hydrotesting of Hydrant & Sprinkler Piping (P2) 5 21-Sep-19 25-Sep-19 0% 64 Hydrotesting of Hydrant & Sprinkler Piping (P2)
LEVEL P3 29 14-Oct-19 13-Nov-19 182 13-Nov-19, LEVEL P3
PLUMBING 14 14-Oct-19 27-Oct-19 197 27-Oct-19, PLUMBING
T4-IN-PHE-FF-1420 Installation of Water Supply Piping with first coat painting (P3) 10 14-Oct-19 23-Oct-19 0% 197 Installation of Water Supply Piping with first coat painting (P3)
T4-IN-PHE-FF-1430 Installation of Drainage Piping with first coat painting (P3) 10 14-Oct-19 23-Oct-19 0% 197 Installation of Drainage Piping with first coat painting (P3)
T4-IN-PHE-FF-1440 Hydrotesting of Water Supply Piping (P3) 4 24-Oct-19 27-Oct-19 0% 197 Hydrotesting of Water Supply Piping (P3)
T4-IN-PHE-FF-1450 Hydrotesting of Drainage Piping (P3) 4 24-Oct-19 27-Oct-19 0% 197 Hydrotesting of Drainage Piping (P3)
FIRE FIGHTING 29 14-Oct-19 13-Nov-19 182 13-Nov-19, FIRE FIGHTING
T4-IN-PHE-FF-1400 Installation of Hydrant & Sprinkler Piping with first coat painting (P3) 25 14-Oct-19 08-Nov-19 0% 182 Installation of Hydrant & Sprinkler Piping with first coat painting (P3)
T4-IN-PHE-FF-1410 Hydrotesting of Hydrant & Sprinkler Piping (P3) 4 09-Nov-19 13-Nov-19 0% 182 Hydrotesting of Hydrant & Sprinkler Piping (P3)
LEVEL P4 29 14-Oct-19 13-Nov-19 182 13-Nov-19, LEVEL P4
PLUMBING 13 14-Oct-19 27-Oct-19 198 27-Oct-19, PLUMBING
T4-IN-PHE-FF-1500 Installation of Water Supply Piping with first coat painting (P4) 10 14-Oct-19 23-Oct-19 0% 198 Installation of Water Supply Piping with first coat painting (P4)
T4-IN-PHE-FF-1510 Installation of Drainage Piping with first coat painting (P4) 10 14-Oct-19 23-Oct-19 0% 198 Installation of Drainage Piping with first coat painting (P4)
T4-IN-PHE-FF-1520 Hydrotesting of Water Supply Piping (P4) 3 24-Oct-19 27-Oct-19 0% 198 Hydrotesting of Water Supply Piping (P4)
T4-IN-PHE-FF-1530 Hydrotesting of Drainage Piping (P4) 3 24-Oct-19 27-Oct-19 0% 198 Hydrotesting of Drainage Piping (P4)
FIRE FIGHTING 29 14-Oct-19 13-Nov-19 182 13-Nov-19, FIRE FIGHTING
T4-IN-PHE-FF-1480 Installation of Hydrant & Sprinkler Piping with first coat painting (P4) 25 14-Oct-19 08-Nov-19 0% 182 Installation of Hydrant & Sprinkler Piping with first coat painting (P4)
T4-IN-PHE-FF-1490 Hydrotesting of Hydrant & Sprinkler Piping (P4) 4 09-Nov-19 13-Nov-19 0% 182 Hydrotesting of Hydrant & Sprinkler Piping (P4)
LEVEL P5 29 14-Oct-19 13-Nov-19 182 13-Nov-19, LEVEL P5
PLUMBING 13 14-Oct-19 27-Oct-19 198 27-Oct-19, PLUMBING
T4-IN-PHE-FF-1580 Installation of Water Supply Piping with first coat painting (P5) 10 14-Oct-19 23-Oct-19 0% 198 Installation of Water Supply Piping with first coat painting (P5)
T4-IN-PHE-FF-1590 Installation of Drainage Piping with first coat painting (P5) 10 14-Oct-19 23-Oct-19 0% 198 Installation of Drainage Piping with first coat painting (P5)
T4-IN-PHE-FF-1600 Hydrotesting of Water Supply Piping (P5) 3 24-Oct-19 27-Oct-19 0% 198 Hydrotesting of Water Supply Piping (P5)
T4-IN-PHE-FF-1610 Hydrotesting of Drainage Piping (P5) 3 24-Oct-19 27-Oct-19 0% 198 Hydrotesting of Drainage Piping (P5)

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 34 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
FIRE FIGHTING 29 14-Oct-19 13-Nov-19 182 13-Nov-19, FIRE FIGHTING
T4-IN-PHE-FF-1560 Installation of Hydrant & Sprinkler Piping with first coat painting (P5) 25 14-Oct-19 08-Nov-19 0% 182 Installation of Hydrant & Sprinkler Piping with first coat painting (P5)
T4-IN-PHE-FF-1570 Hydrotesting of Hydrant & Sprinkler Piping (P5) 4 09-Nov-19 13-Nov-19 0% 182 Hydrotesting of Hydrant & Sprinkler Piping (P5)
LEVEL P6 29 14-Oct-19 13-Nov-19 182 13-Nov-19, LEVEL P6
PLUMBING 13 14-Oct-19 27-Oct-19 198 27-Oct-19, PLUMBING
T4-IN-PHE-FF-1660 Installation of Water Supply Piping with first coat painting (P6) 10 14-Oct-19 23-Oct-19 0% 198 Installation of Water Supply Piping with first coat painting (P6)
T4-IN-PHE-FF-1670 Installation of Drainage Piping with first coat painting (P6) 10 14-Oct-19 23-Oct-19 0% 198 Installation of Drainage Piping with first coat painting (P6)
T4-IN-PHE-FF-1680 Hydrotesting of Water Supply Piping (P6) 3 24-Oct-19 27-Oct-19 0% 198 Hydrotesting of Water Supply Piping (P6)
T4-IN-PHE-FF-1690 Hydrotesting of Drainage Piping (P6) 3 24-Oct-19 27-Oct-19 0% 198 Hydrotesting of Drainage Piping (P6)
FIRE FIGHTING 29 14-Oct-19 13-Nov-19 182 13-Nov-19, FIRE FIGHTING
T4-IN-PHE-FF-1640 Installation of Hydrant & Sprinkler Piping with first coat painting (P6) 25 14-Oct-19 08-Nov-19 0% 182 Installation of Hydrant & Sprinkler Piping with first coat painting (P6)
T4-IN-PHE-FF-1650 Hydrotesting of Hydrant & Sprinkler Piping (P6) 4 09-Nov-19 13-Nov-19 0% 182 Hydrotesting of Hydrant & Sprinkler Piping (P6)
LEVEL P7 29 15-Sep-19 15-Oct-19 210 15-Oct-19, LEVEL P7
PLUMBING 13 15-Sep-19 28-Sep-19 226 28-Sep-19, PLUMBING
T4-IN-PHE-FF-1740 Installation of Water Supply Piping with first coat painting (P7) 10 15-Sep-19 24-Sep-19 0% 226 Installation of Water Supply Piping with first coat painting (P7)
T4-IN-PHE-FF-1750 Installation of Drainage Piping with first coat painting (P7) 10 15-Sep-19 24-Sep-19 0% 226 Installation of Drainage Piping with first coat painting (P7)
T4-IN-PHE-FF-1760 Hydrotesting of Water Supply Piping (P7) 3 25-Sep-19 28-Sep-19 0% 226 Hydrotesting of Water Supply Piping (P7)
T4-IN-PHE-FF-1770 Hydrotesting of Drainage Piping (P7) 3 25-Sep-19 28-Sep-19 0% 226 Hydrotesting of Drainage Piping (P7)
FIRE FIGHTING 29 15-Sep-19 15-Oct-19 210 15-Oct-19, FIRE FIGHTING
T4-IN-PHE-FF-1720 Installation of Hydrant & Sprinkler Piping with first coat painting (P7) 25 15-Sep-19 11-Oct-19 0% 210 Installation of Hydrant & Sprinkler Piping with first coat painting (P7)
T4-IN-PHE-FF-1730 Hydrotesting of Hydrant & Sprinkler Piping (P7) 4 12-Oct-19 15-Oct-19 0% 210 Hydrotesting of Hydrant & Sprinkler Piping (P7)
LEVEL P8 35 15-Sep-19 21-Oct-19 204 21-Oct-19, LEVEL P8
PLUMBING 13 15-Sep-19 28-Sep-19 226 28-Sep-19, PLUMBING
T4-IN-PHE-FF-1820 Installation of Water Supply Piping with first coat painting (P8) 10 15-Sep-19 24-Sep-19 0% 226 Installation of Water Supply Piping with first coat painting (P8)
T4-IN-PHE-FF-1830 Installation of Drainage Piping with first coat painting (P8) 10 15-Sep-19 24-Sep-19 0% 226 Installation of Drainage Piping with first coat painting (P8)
T4-IN-PHE-FF-1840 Hydrotesting of Water Supply Piping (P8) 3 25-Sep-19 28-Sep-19 0% 226 Hydrotesting of Water Supply Piping (P8)
T4-IN-PHE-FF-1850 Hydrotesting of Drainage Piping (P8) 3 25-Sep-19 28-Sep-19 0% 226 Hydrotesting of Drainage Piping (P8)
FIRE FIGHTING 35 15-Sep-19 21-Oct-19 204 21-Oct-19, FIRE FIGHTING
T4-IN-PHE-FF-1800 Installation of Hydrant & Sprinkler Piping with first coat painting (P8) 25 15-Sep-19 11-Oct-19 0% 204 Installation of Hydrant & Sprinkler Piping with first coat painting (P8)
T4-IN-PHE-FF-1810 Hydrotesting of Hydrant & Sprinkler Piping (P8) 10 12-Oct-19 21-Oct-19 0% 204 Hydrotesting of Hydrant & Sprinkler Piping (P8)
LEVEL P9 27 05-Dec-19 02-Jan-20 134 02-Jan-20, LEVEL P9
PLUMBING 13 05-Dec-19 18-Dec-19 148 18-Dec-19, PLUMBING
T4-IN-PHE-FF-1900 Installation of Water Supply Piping with first coat painting (P9) 10 05-Dec-19 14-Dec-19 0% 148 Installation of Water Supply Piping with first coat painting (P9)
T4-IN-PHE-FF-1910 Installation of Drainage Piping with first coat painting (P9) 10 05-Dec-19 14-Dec-19 0% 148 Installation of Drainage Piping with first coat painting (P9)
T4-IN-PHE-FF-1920 Hydrotesting of Water Supply Piping (P9) 3 15-Dec-19 18-Dec-19 0% 148 Hydrotesting of Water Supply Piping (P9)
T4-IN-PHE-FF-1930 Hydrotesting of Drainage Piping (P9) 3 15-Dec-19 18-Dec-19 0% 148 Hydrotesting of Drainage Piping (P9)
FIRE FIGHTING 27 05-Dec-19 02-Jan-20 134 02-Jan-20, FIRE FIGHTING
T4-IN-PHE-FF-1880 Installation of Hydrant & Sprinkler Piping with first coat painting (P9) 24 05-Dec-19 29-Dec-19 0% 134 Installation of Hydrant & Sprinkler Piping with first coat painting (P9)
T4-IN-PHE-FF-1890 Hydrotesting of Hydrant & Sprinkler Piping (P9) 3 30-Dec-19 02-Jan-20 0% 134 Hydrotesting of Hydrant & Sprinkler Piping (P9)
LEVEL P10 27 05-Dec-19 02-Jan-20 134 02-Jan-20, LEVEL P10
PLUMBING 13 05-Dec-19 18-Dec-19 148 18-Dec-19, PLUMBING
T4-IN-PHE-FF-1980 Installation of Water Supply Piping with first coat painting (P10) 10 05-Dec-19 14-Dec-19 0% 148 Installation of Water Supply Piping with first coat painting (P10)
T4-IN-PHE-FF-1990 Installation of Drainage Piping with first coat painting (P10) 10 05-Dec-19 14-Dec-19 0% 148 Installation of Drainage Piping with first coat painting (P10)
T4-IN-PHE-FF-2000 Hydrotesting of Water Supply Piping (P10) 3 15-Dec-19 18-Dec-19 0% 148 Hydrotesting of Water Supply Piping (P10)
T4-IN-PHE-FF-2010 Hydrotesting of Drainage Piping (P10) 3 15-Dec-19 18-Dec-19 0% 148 Hydrotesting of Drainage Piping (P10)
FIRE FIGHTING 27 05-Dec-19 02-Jan-20 134 02-Jan-20, FIRE FIGHTING
T4-IN-PHE-FF-1960 Installation of Hydrant & Sprinkler Piping with first coat painting (P10) 24 05-Dec-19 29-Dec-19 0% 134 Installation of Hydrant & Sprinkler Piping with first coat painting (P10)
T4-IN-PHE-FF-1970 Hydrotesting of Hydrant & Sprinkler Piping (P10) 3 30-Dec-19 02-Jan-20 0% 134 Hydrotesting of Hydrant & Sprinkler Piping (P10)
LEVEL S1 79 22-Dec-19 10-Mar-20 80 10-Mar-20, LEVEL S1
PLUMBING 79 22-Dec-19 10-Mar-20 80 10-Mar-20, PLUMBING
T4-IN-PHE-FF-6180 Installation of Water Supply Piping with first coat painting (S1) 45 22-Dec-19 05-Feb-20 0% 80 Installation of Water Supply Piping with first coat painting (S1)
T4-IN-PHE-FF-6190 Installation of Drainage Piping with first coat painting (S1) 55 06-Jan-20 29-Feb-20 0% 80 Installation of Drainage Piping with first coat painting (S1)
T4-IN-PHE-FF-6200 Hydrotesting of Water Supply Piping (S1) 5 06-Feb-20 10-Feb-20 0% 109 Hydrotesting of Water Supply Piping (S1)

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 35 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-PHE-FF-6210 Hydrotesting of Drainage Piping (S1) 10 01-Mar-20 10-Mar-20 0% 80 Hydrotesting of Drainage Piping (S1)
FIRE FIGHTING 57 22-Dec-19 17-Feb-20 102 17-Feb-20, FIRE FIGHTING
T4-IN-PHE-FF-6160 Installation of Hydrant & Sprinkler Piping with first coat painting (S1) 50 22-Dec-19 10-Feb-20 0% 102 Installation of Hydrant & Sprinkler Piping with first coat pain
T4-IN-PHE-FF-6170 Hydrotesting of Hydrant & Sprinkler Piping (S1) 7 11-Feb-20 17-Feb-20 0% 102 Hydrotesting of Hydrant & Sprinkler Piping (S1)
LEVEL 17 41 01-Feb-20 12-Mar-20 34 12-Mar-20, LEVEL 17
PLUMBING 30 01-Feb-20 01-Mar-20 45 01-Mar-20, PLUMBING
T4-IN-PHE-FF-2060 Installation of Water Supply Piping with first coat painting (FL17) 20 01-Feb-20 20-Feb-20 0% 50 Installation of Water Supply Piping with first coat painting
T4-IN-PHE-FF-2070 Installation of Drainage Piping with first coat painting (FL17) 20 06-Feb-20 25-Feb-20 0% 45 Installation of Drainage Piping with first coat painting (FL17)
T4-IN-PHE-FF-2080 Hydrotesting of Water Supply Piping (FL17) 5 21-Feb-20 25-Feb-20 0% 50 Hydrotesting of Water Supply Piping (FL17)
T4-IN-PHE-FF-2090 Hydrotesting of Drainage Piping (FL17) 5 26-Feb-20 01-Mar-20 0% 45 Hydrotesting of Drainage Piping (FL17)
FIRE FIGHTING 41 01-Feb-20 12-Mar-20 34 12-Mar-20, FIRE FIGHTING
T4-IN-PHE-FF-2040 Installation of Hydrant & Sprinkler Piping with first coat painting (FL17) 35 01-Feb-20 06-Mar-20 0% 34 Installation of Hydrant & Sprinkler Piping with first coat
T4-IN-PHE-FF-2050 Hydrotesting of Hydrant & Sprinkler Piping (FL17) 6 07-Mar-20 12-Mar-20 0% 34 Hydrotesting of Hydrant & Sprinkler Piping (FL17)
LEVEL 18 36 11-Apr-20 16-May-20 182 16-May-20, LEVEL 18
PLUMBING 30 11-Apr-20 10-May-20 188 10-May-20, PLUMBING
T4-IN-PHE-FF-2140 Installation of Water Supply Piping with first coat painting (FL18) 25 11-Apr-20 05-May-20 0% 188 Installation of Water Supply Piping with first
T4-IN-PHE-FF-2150 Installation of Drainage Piping with first coat painting (FL18) 25 11-Apr-20 05-May-20 0% 188 Installation of Drainage Piping with first coat
T4-IN-PHE-FF-2160 Hydrotesting of Water Supply Piping (FL18) 5 06-May-20 10-May-20 0% 188 Hydrotesting of Water Supply Piping (FL18)
T4-IN-PHE-FF-2170 Hydrotesting of Drainage Piping (FL18) 5 06-May-20 10-May-20 0% 188 Hydrotesting of Drainage Piping (FL18)
FIRE FIGHTING 36 11-Apr-20 16-May-20 182 16-May-20, FIRE FIGHTING
T4-IN-PHE-FF-2120 Installation of Hydrant & Sprinkler Piping with first coat painting (FL18) 31 11-Apr-20 11-May-20 0% 182 Installation of Hydrant & Sprinkler Piping w
T4-IN-PHE-FF-2130 Hydrotesting of Hydrant & Sprinkler Piping (FL18) 5 12-May-20 16-May-20 0% 182 Hydrotesting of Hydrant & Sprinkler Piping
LEVEL 19 36 11-Apr-20 16-May-20 182 16-May-20, LEVEL 19
PLUMBING 30 11-Apr-20 10-May-20 188 10-May-20, PLUMBING
T4-IN-PHE-FF-2220 Installation of Water Supply Piping with first coat painting (FL19) 25 11-Apr-20 05-May-20 0% 188 Installation of Water Supply Piping with first
T4-IN-PHE-FF-2230 Installation of Drainage Piping with first coat painting (FL19) 25 11-Apr-20 05-May-20 0% 188 Installation of Drainage Piping with first coat
T4-IN-PHE-FF-2240 Hydrotesting of Water Supply Piping (FL19) 5 06-May-20 10-May-20 0% 188 Hydrotesting of Water Supply Piping (FL19)
T4-IN-PHE-FF-2250 Hydrotesting of Drainage Piping (FL19) 5 06-May-20 10-May-20 0% 188 Hydrotesting of Drainage Piping (FL19)
FIRE FIGHTING 36 11-Apr-20 16-May-20 182 16-May-20, FIRE FIGHTING
T4-IN-PHE-FF-2200 Installation of Hydrant & Sprinkler Piping with first coat painting (FL19) 31 11-Apr-20 11-May-20 0% 182 Installation of Hydrant & Sprinkler Piping w
T4-IN-PHE-FF-2210 Hydrotesting of Hydrant & Sprinkler Piping (FL19) 5 12-May-20 16-May-20 0% 182 Hydrotesting of Hydrant & Sprinkler Piping
LEVEL 20 36 11-Apr-20 16-May-20 182 16-May-20, LEVEL 20
PLUMBING 30 11-Apr-20 10-May-20 188 10-May-20, PLUMBING
T4-IN-PHE-FF-2300 Installation of Water Supply Piping with first coat painting (FL20) 25 11-Apr-20 05-May-20 0% 188 Installation of Water Supply Piping with first
T4-IN-PHE-FF-2310 Installation of Drainage Piping with first coat painting (FL20) 25 11-Apr-20 05-May-20 0% 188 Installation of Drainage Piping with first coat
T4-IN-PHE-FF-2320 Hydrotesting of Water Supply Piping (FL20) 5 06-May-20 10-May-20 0% 188 Hydrotesting of Water Supply Piping (FL20)
T4-IN-PHE-FF-2330 Hydrotesting of Drainage Piping (FL20) 5 06-May-20 10-May-20 0% 188 Hydrotesting of Drainage Piping (FL20)
FIRE FIGHTING 36 11-Apr-20 16-May-20 182 16-May-20, FIRE FIGHTING
T4-IN-PHE-FF-2280 Installation of Hydrant & Sprinkler Piping with first coat painting (FL 20) 31 11-Apr-20 11-May-20 0% 182 Installation of Hydrant & Sprinkler Piping w
T4-IN-PHE-FF-2290 Hydrotesting of Hydrant & Sprinkler Piping (FL 20) 5 12-May-20 16-May-20 0% 182 Hydrotesting of Hydrant & Sprinkler Piping
LEVEL 21 36 11-Apr-20 16-May-20 182 16-May-20, LEVEL 21
PLUMBING 30 11-Apr-20 10-May-20 188 10-May-20, PLUMBING
T4-IN-PHE-FF-2380 Installation of Water Supply Piping with first coat painting (FL21) 25 11-Apr-20 05-May-20 0% 188 Installation of Water Supply Piping with first
T4-IN-PHE-FF-2390 Installation of Drainage Piping with first coat painting (FL21) 25 11-Apr-20 05-May-20 0% 188 Installation of Drainage Piping with first coat
T4-IN-PHE-FF-2400 Hydrotesting of Water Supply Piping (FL21) 5 06-May-20 10-May-20 0% 188 Hydrotesting of Water Supply Piping (FL21)
T4-IN-PHE-FF-2410 Hydrotesting of Drainage Piping (FL21) 5 06-May-20 10-May-20 0% 188 Hydrotesting of Drainage Piping (FL21)
FIRE FIGHTING 36 11-Apr-20 16-May-20 182 16-May-20, FIRE FIGHTING
T4-IN-PHE-FF-2360 Installation of Hydrant & Sprinkler Piping with first coat painting (FL21) 31 11-Apr-20 11-May-20 0% 182 Installation of Hydrant & Sprinkler Piping w
T4-IN-PHE-FF-2370 Hydrotesting of Hydrant & Sprinkler Piping (FL21) 5 12-May-20 16-May-20 0% 182 Hydrotesting of Hydrant & Sprinkler Piping
LEVEL 22 47 27-Mar-20 12-May-20 30 12-May-20, LEVEL 22
PLUMBING 47 27-Mar-20 12-May-20 30 12-May-20, PLUMBING
T4-IN-PHE-FF-2460 Installation of Water Supply Piping with first coat painting (FL22) 40 27-Mar-20 05-May-20 0% 30 Installation of Water Supply Piping with first
T4-IN-PHE-FF-2470 Installation of Drainage Piping with first coat painting (FL22) 40 27-Mar-20 05-May-20 0% 30 Installation of Drainage Piping with first coat

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 36 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-PHE-FF-2480 Hydrotesting of Water Supply Piping (FL22) 7 06-May-20 12-May-20 0% 30 Hydrotesting of Water Supply Piping (FL22)
T4-IN-PHE-FF-2490 Hydrotesting of Drainage Piping (FL22) 7 06-May-20 12-May-20 0% 30 Hydrotesting of Drainage Piping (FL22)
FIRE FIGHTING 46 27-Mar-20 11-May-20 31 11-May-20, FIRE FIGHTING
T4-IN-PHE-FF-2440 Installation of Hydrant & Sprinkler Piping with first coat painting (FL22) 40 27-Mar-20 05-May-20 0% 31 Installation of Hydrant & Sprinkler Piping wit
T4-IN-PHE-FF-2450 Hydrotesting of Hydrant & Sprinkler Piping (FL22) 6 06-May-20 11-May-20 0% 31 Hydrotesting of Hydrant & Sprinkler Piping
LEVEL 23 36 15-May-20 19-Jun-20 148 19-Jun-20, LEVEL 23
PLUMBING 30 15-May-20 13-Jun-20 154 13-Jun-20, PLUMBING
T4-IN-PHE-FF-2540 Installation of Water Supply Piping with first coat painting (FL23) 25 15-May-20 08-Jun-20 0% 154 Installation of Water Supply Piping with
T4-IN-PHE-FF-2550 Installation of Drainage Piping with first coat painting (FL23) 25 15-May-20 08-Jun-20 0% 154 Installation of Drainage Piping with firs
T4-IN-PHE-FF-2560 Hydrotesting of Water Supply Piping (FL23) 5 09-Jun-20 13-Jun-20 0% 154 Hydrotesting of Water Supply Piping
T4-IN-PHE-FF-2570 Hydrotesting of Drainage Piping (FL23) 5 09-Jun-20 13-Jun-20 0% 154 Hydrotesting of Drainage Piping (FL23)
FIRE FIGHTING 36 15-May-20 19-Jun-20 148 19-Jun-20, FIRE FIGHTING
T4-IN-PHE-FF-2520 Installation of Hydrant & Sprinkler Piping with first coat painting (FL23) 31 15-May-20 14-Jun-20 0% 148 Installation of Hydrant & Sprinkler Pip
T4-IN-PHE-FF-2530 Hydrotesting of Hydrant & Sprinkler Piping (FL23) 5 15-Jun-20 19-Jun-20 0% 148 Hydrotesting of Hydrant & Sprinkler
LEVEL 24 36 15-May-20 19-Jun-20 148 19-Jun-20, LEVEL 24
PLUMBING 30 15-May-20 13-Jun-20 154 13-Jun-20, PLUMBING
T4-IN-PHE-FF-2620 Installation of Water Supply Piping with first coat painting (FL24) 25 15-May-20 08-Jun-20 0% 154 Installation of Water Supply Piping with
T4-IN-PHE-FF-2630 Installation of Drainage Piping with first coat painting (FL24) 25 15-May-20 08-Jun-20 0% 154 Installation of Drainage Piping with firs
T4-IN-PHE-FF-2640 Hydrotesting of Water Supply Piping (FL24) 5 09-Jun-20 13-Jun-20 0% 154 Hydrotesting of Water Supply Piping
T4-IN-PHE-FF-2650 Hydrotesting of Drainage Piping (FL24) 5 09-Jun-20 13-Jun-20 0% 154 Hydrotesting of Drainage Piping (FL24)
FIRE FIGHTING 36 15-May-20 19-Jun-20 148 19-Jun-20, FIRE FIGHTING
T4-IN-PHE-FF-2600 Installation of Hydrant & Sprinkler Piping with first coat painting (FL24) 31 15-May-20 14-Jun-20 0% 148 Installation of Hydrant & Sprinkler Pip
T4-IN-PHE-FF-2610 Hydrotesting of Hydrant & Sprinkler Piping (FL24) 5 15-Jun-20 19-Jun-20 0% 148 Hydrotesting of Hydrant & Sprinkler
LEVEL 25 36 15-May-20 19-Jun-20 148 19-Jun-20, LEVEL 25
PLUMBING 30 15-May-20 13-Jun-20 154 13-Jun-20, PLUMBING
T4-IN-PHE-FF-2700 Installation of Water Supply Piping with first coat painting (FL25) 25 15-May-20 08-Jun-20 0% 154 Installation of Water Supply Piping with
T4-IN-PHE-FF-2710 Installation of Drainage Piping with first coat painting (FL25) 25 15-May-20 08-Jun-20 0% 154 Installation of Drainage Piping with firs
T4-IN-PHE-FF-2720 Hydrotesting of Water Supply Piping (FL25) 5 09-Jun-20 13-Jun-20 0% 154 Hydrotesting of Water Supply Piping
T4-IN-PHE-FF-2730 Hydrotesting of Drainage Piping (FL25) 5 09-Jun-20 13-Jun-20 0% 154 Hydrotesting of Drainage Piping (FL25)
FIRE FIGHTING 36 15-May-20 19-Jun-20 148 19-Jun-20, FIRE FIGHTING
T4-IN-PHE-FF-2680 Installation of Hydrant & Sprinkler Piping with first coat painting (FL25) 31 15-May-20 14-Jun-20 0% 148 Installation of Hydrant & Sprinkler Pip
T4-IN-PHE-FF-2690 Hydrotesting of Hydrant & Sprinkler Piping (FL25) 5 15-Jun-20 19-Jun-20 0% 148 Hydrotesting of Hydrant & Sprinkler
LEVEL 26 36 15-May-20 19-Jun-20 148 19-Jun-20, LEVEL 26
PLUMBING 30 15-May-20 13-Jun-20 154 13-Jun-20, PLUMBING
T4-IN-PHE-FF-2780 Installation of Water Supply Piping with first coat painting (FL26) 25 15-May-20 08-Jun-20 0% 154 Installation of Water Supply Piping with
T4-IN-PHE-FF-2790 Installation of Drainage Piping with first coat painting (FL26) 25 15-May-20 08-Jun-20 0% 154 Installation of Drainage Piping with firs
T4-IN-PHE-FF-2800 Hydrotesting of Water Supply Piping (FL26) 5 09-Jun-20 13-Jun-20 0% 154 Hydrotesting of Water Supply Piping
T4-IN-PHE-FF-2810 Hydrotesting of Drainage Piping (FL26) 5 09-Jun-20 13-Jun-20 0% 154 Hydrotesting of Drainage Piping (FL26)
FIRE FIGHTING 36 15-May-20 19-Jun-20 148 19-Jun-20, FIRE FIGHTING
T4-IN-PHE-FF-2760 Installation of Hydrant & Sprinkler Piping with first coat painting (FL26) 31 15-May-20 14-Jun-20 0% 148 Installation of Hydrant & Sprinkler Pip
T4-IN-PHE-FF-2770 Hydrotesting of Hydrant & Sprinkler Piping (FL26) 5 15-Jun-20 19-Jun-20 0% 148 Hydrotesting of Hydrant & Sprinkler
LEVEL 27 36 15-May-20 19-Jun-20 148 19-Jun-20, LEVEL 27
PLUMBING 30 15-May-20 13-Jun-20 154 13-Jun-20, PLUMBING
T4-IN-PHE-FF-2860 Installation of Water Supply Piping with first coat painting (FL27) 25 15-May-20 08-Jun-20 0% 154 Installation of Water Supply Piping with
T4-IN-PHE-FF-2870 Installation of Drainage Piping with first coat painting (FL27) 25 15-May-20 08-Jun-20 0% 154 Installation of Drainage Piping with firs
T4-IN-PHE-FF-2880 Hydrotesting of Water Supply Piping (FL27) 5 09-Jun-20 13-Jun-20 0% 154 Hydrotesting of Water Supply Piping
T4-IN-PHE-FF-2890 Hydrotesting of Drainage Piping (FL27) 5 09-Jun-20 13-Jun-20 0% 154 Hydrotesting of Drainage Piping (FL27)
FIRE FIGHTING 36 15-May-20 19-Jun-20 148 19-Jun-20, FIRE FIGHTING
T4-IN-PHE-FF-2840 Installation of Hydrant & Sprinkler Piping with first coat painting (FL27) 31 15-May-20 14-Jun-20 0% 148 Installation of Hydrant & Sprinkler Pip
T4-IN-PHE-FF-2850 Hydrotesting of Hydrant & Sprinkler Piping (FL27) 5 15-Jun-20 19-Jun-20 0% 148 Hydrotesting of Hydrant & Sprinkler
LEVEL 28 13 18-Jun-20 01-Jul-20 137 01-Jul-20, LEVEL 28
PLUMBING 13 18-Jun-20 01-Jul-20 137 01-Jul-20, PLUMBING
T4-IN-PHE-FF-2940 Installation of Water Supply Piping with first coat painting (FL28) 10 18-Jun-20 27-Jun-20 0% 137 Installation of Water Supply Piping

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 37 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-PHE-FF-2950 Installation of Drainage Piping with first coat painting (FL28) 10 18-Jun-20 27-Jun-20 0% 137 Installation of Drainage Piping with
T4-IN-PHE-FF-2960 Hydrotesting of Water Supply Piping (FL28) 3 28-Jun-20 01-Jul-20 0% 137 Hydrotesting of Water Supply Pipin
T4-IN-PHE-FF-2970 Hydrotesting of Drainage Piping (FL28) 3 28-Jun-20 01-Jul-20 0% 137 Hydrotesting of Drainage Piping (FL28)
FIRE FIGHTING 13 18-Jun-20 01-Jul-20 137 01-Jul-20, FIRE FIGHTING
T4-IN-PHE-FF-2920 Installation of Hydrant & Sprinkler Piping with first coat painting (FL28) 10 18-Jun-20 27-Jun-20 0% 137 Installation of Hydrant & Sprinkler P
T4-IN-PHE-FF-2930 Hydrotesting of Hydrant & Sprinkler Piping (FL28) 3 28-Jun-20 01-Jul-20 0% 137 Hydrotesting of Hydrant & Sprinkle
LEVEL 29 36 18-Jun-20 23-Jul-20 114 23-Jul-20, LEVEL 29
PLUMBING 30 18-Jun-20 17-Jul-20 120 17-Jul-20, PLUMBING
T4-IN-PHE-FF-3020 Installation of Water Supply Piping with first coat painting (FL29) 25 18-Jun-20 12-Jul-20 0% 120 Installation of Water Supply Pipin
T4-IN-PHE-FF-3030 Installation of Drainage Piping with first coat painting (FL29) 25 18-Jun-20 12-Jul-20 0% 120 Installation of Drainage Piping wi
T4-IN-PHE-FF-3040 Hydrotesting of Water Supply Piping (FL29) 5 13-Jul-20 17-Jul-20 0% 120 Hydrotesting of Water Supply P
T4-IN-PHE-FF-3050 Hydrotesting of Drainage Piping (FL29) 5 13-Jul-20 17-Jul-20 0% 120 Hydrotesting of Drainage Piping
FIRE FIGHTING 36 18-Jun-20 23-Jul-20 114 23-Jul-20, FIRE FIGHTING
T4-IN-PHE-FF-3000 Installation of Hydrant & Sprinkler Piping with first coat painting (FL29) 31 18-Jun-20 18-Jul-20 0% 114 Installation of Hydrant & Sprinkl
T4-IN-PHE-FF-3010 Hydrotesting of Hydrant & Sprinkler Piping (FL29) 5 19-Jul-20 23-Jul-20 0% 114 Hydrotesting of Hydrant & Spri
LEVEL 30 36 18-Jun-20 23-Jul-20 114 23-Jul-20, LEVEL 30
PLUMBING 30 18-Jun-20 17-Jul-20 120 17-Jul-20, PLUMBING
T4-IN-PHE-FF-3100 Installation of Water Supply Piping with first coat painting (FL30) 25 18-Jun-20 12-Jul-20 0% 120 Installation of Water Supply Pipin
T4-IN-PHE-FF-3110 Installation of Drainage Piping with first coat painting (FL30) 25 18-Jun-20 12-Jul-20 0% 120 Installation of Drainage Piping wi
T4-IN-PHE-FF-3120 Hydrotesting of Water Supply Piping (FL30) 5 13-Jul-20 17-Jul-20 0% 120 Hydrotesting of Water Supply P
T4-IN-PHE-FF-3130 Hydrotesting of Drainage Piping (FL30) 5 13-Jul-20 17-Jul-20 0% 120 Hydrotesting of Drainage Piping
FIRE FIGHTING 36 18-Jun-20 23-Jul-20 114 23-Jul-20, FIRE FIGHTING
T4-IN-PHE-FF-3080 Installation of Hydrant & Sprinkler Piping with first coat painting (FL30) 31 18-Jun-20 18-Jul-20 0% 114 Installation of Hydrant & Sprinkl
T4-IN-PHE-FF-3090 Hydrotesting of Hydrant & Sprinkler Piping (FL30) 5 19-Jul-20 23-Jul-20 0% 114 Hydrotesting of Hydrant & Spri
LEVEL 31 36 18-Jun-20 23-Jul-20 114 23-Jul-20, LEVEL 31
PLUMBING 30 18-Jun-20 17-Jul-20 120 17-Jul-20, PLUMBING
T4-IN-PHE-FF-3180 Installation of Water Supply Piping with first coat painting (FL31) 25 18-Jun-20 12-Jul-20 0% 120 Installation of Water Supply Pipin
T4-IN-PHE-FF-3190 Installation of Drainage Piping with first coat painting (FL31) 25 18-Jun-20 12-Jul-20 0% 120 Installation of Drainage Piping wi
T4-IN-PHE-FF-3200 Hydrotesting of Water Supply Piping (FL31) 5 13-Jul-20 17-Jul-20 0% 120 Hydrotesting of Water Supply P
T4-IN-PHE-FF-3210 Hydrotesting of Drainage Piping (FL31) 5 13-Jul-20 17-Jul-20 0% 120 Hydrotesting of Drainage Piping
FIRE FIGHTING 36 18-Jun-20 23-Jul-20 114 23-Jul-20, FIRE FIGHTING
T4-IN-PHE-FF-3160 Installation of Hydrant & Sprinkler Piping with first coat painting (FL31) 31 18-Jun-20 18-Jul-20 0% 114 Installation of Hydrant & Sprinkl
T4-IN-PHE-FF-3170 Hydrotesting of Hydrant & Sprinkler Piping (FL31) 5 19-Jul-20 23-Jul-20 0% 114 Hydrotesting of Hydrant & Spri
LEVEL 32 36 23-Jul-20 27-Aug-20 79 27-Aug-20, LEVEL 32
PLUMBING 30 23-Jul-20 21-Aug-20 85 21-Aug-20, PLUMBING
T4-IN-PHE-FF-3260 Installation of Water Supply Piping with first coat painting (FL32) 25 23-Jul-20 16-Aug-20 0% 85 Installation of Water Suppl
T4-IN-PHE-FF-3270 Installation of Drainage Piping with first coat painting (FL32) 25 23-Jul-20 16-Aug-20 0% 85 Installation of Drainage Pip
T4-IN-PHE-FF-3280 Hydrotesting of Water Supply Piping (FL32) 5 17-Aug-20 21-Aug-20 0% 85 Hydrotesting of Water Su
T4-IN-PHE-FF-3290 Hydrotesting of Drainage Piping (FL32) 5 17-Aug-20 21-Aug-20 0% 85 Hydrotesting of Drainage
FIRE FIGHTING 36 23-Jul-20 27-Aug-20 79 27-Aug-20, FIRE FIGHTING
T4-IN-PHE-FF-3240 Installation of Hydrant & Sprinkler Piping with first coat painting (FL32) 31 23-Jul-20 22-Aug-20 0% 79 Installation of Hydrant & S
T4-IN-PHE-FF-3250 Hydrotesting of Hydrant & Sprinkler Piping (FL32) 5 23-Aug-20 27-Aug-20 0% 79 Hydrotesting of Hydrant
LEVEL 33 36 23-Jul-20 27-Aug-20 79 27-Aug-20, LEVEL 33
PLUMBING 30 23-Jul-20 21-Aug-20 85 21-Aug-20, PLUMBING
T4-IN-PHE-FF-3340 Installation of Water Supply Piping with first coat painting (FL33) 25 23-Jul-20 16-Aug-20 0% 85 Installation of Water Suppl
T4-IN-PHE-FF-3350 Installation of Drainage Piping with first coat painting (FL33) 25 23-Jul-20 16-Aug-20 0% 85 Installation of Drainage Pip
T4-IN-PHE-FF-3360 Hydrotesting of Water Supply Piping (FL33) 5 17-Aug-20 21-Aug-20 0% 85 Hydrotesting of Water Su
T4-IN-PHE-FF-3370 Hydrotesting of Drainage Piping (FL33) 5 17-Aug-20 21-Aug-20 0% 85 Hydrotesting of Drainage
FIRE FIGHTING 36 23-Jul-20 27-Aug-20 79 27-Aug-20, FIRE FIGHTING
T4-IN-PHE-FF-3320 Installation of Hydrant & Sprinkler Piping with first coat painting (FL33) 31 23-Jul-20 22-Aug-20 0% 79 Installation of Hydrant & S
T4-IN-PHE-FF-3330 Hydrotesting of Hydrant & Sprinkler Piping (FL33) 5 23-Aug-20 27-Aug-20 0% 79 Hydrotesting of Hydrant
LEVEL 34 36 23-Jul-20 27-Aug-20 79 27-Aug-20, LEVEL 34
PLUMBING 30 23-Jul-20 21-Aug-20 85 21-Aug-20, PLUMBING

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 38 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-PHE-FF-3420 Installation of Water Supply Piping with first coat painting (FL34) 25 23-Jul-20 16-Aug-20 0% 85 Installation of Water Suppl
T4-IN-PHE-FF-3430 Installation of Drainage Piping with first coat painting (FL34) 25 23-Jul-20 16-Aug-20 0% 85 Installation of Drainage Pip
T4-IN-PHE-FF-3440 Hydrotesting of Water Supply Piping (FL34) 5 17-Aug-20 21-Aug-20 0% 85 Hydrotesting of Water Su
T4-IN-PHE-FF-3450 Hydrotesting of Drainage Piping (FL34) 5 17-Aug-20 21-Aug-20 0% 85 Hydrotesting of Drainage
FIRE FIGHTING 36 23-Jul-20 27-Aug-20 79 27-Aug-20, FIRE FIGHTING
T4-IN-PHE-FF-3400 Installation of Hydrant & Sprinkler Piping with first coat painting (FL34) 31 23-Jul-20 22-Aug-20 0% 79 Installation of Hydrant & S
T4-IN-PHE-FF-3410 Hydrotesting of Hydrant & Sprinkler Piping (FL34) 5 23-Aug-20 27-Aug-20 0% 79 Hydrotesting of Hydrant
LEVEL 35 36 23-Jul-20 27-Aug-20 79 27-Aug-20, LEVEL 35
PLUMBING 30 23-Jul-20 21-Aug-20 85 21-Aug-20, PLUMBING
T4-IN-PHE-FF-3500 Installation of Water Supply Piping with first coat painting (FL35) 25 23-Jul-20 16-Aug-20 0% 85 Installation of Water Suppl
T4-IN-PHE-FF-3510 Installation of Drainage Piping with first coat painting (FL35) 25 23-Jul-20 16-Aug-20 0% 85 Installation of Drainage Pip
T4-IN-PHE-FF-3520 Hydrotesting of Water Supply Piping (FL35) 5 17-Aug-20 21-Aug-20 0% 85 Hydrotesting of Water Su
T4-IN-PHE-FF-3530 Hydrotesting of Drainage Piping (FL35) 5 17-Aug-20 21-Aug-20 0% 85 Hydrotesting of Drainage
FIRE FIGHTING 36 23-Jul-20 27-Aug-20 79 27-Aug-20, FIRE FIGHTING
T4-IN-PHE-FF-3480 Installation of Hydrant & Sprinkler Piping with first coat painting (FL35) 31 23-Jul-20 22-Aug-20 0% 79 Installation of Hydrant & S
T4-IN-PHE-FF-3490 Hydrotesting of Hydrant & Sprinkler Piping (FL35) 5 23-Aug-20 27-Aug-20 0% 79 Hydrotesting of Hydrant
LEVEL 36 36 01-Sep-20 06-Oct-20 39 06-Oct-20, LEVEL 36
PLUMBING 30 01-Sep-20 30-Sep-20 45 30-Sep-20, PLUMBING
T4-IN-PHE-FF-3580 Installation of Water Supply Piping with first coat painting (FL36) 25 01-Sep-20 25-Sep-20 0% 45 Installation of Water
T4-IN-PHE-FF-3590 Installation of Drainage Piping with first coat painting (FL36) 25 01-Sep-20 25-Sep-20 0% 45 Installation of Draina
T4-IN-PHE-FF-3600 Hydrotesting of Water Supply Piping (FL36) 5 26-Sep-20 30-Sep-20 0% 45 Hydrotesting of Wa
T4-IN-PHE-FF-3610 Hydrotesting of Drainage Piping (FL36) 5 26-Sep-20 30-Sep-20 0% 45 Hydrotesting of Dra
FIRE FIGHTING 36 01-Sep-20 06-Oct-20 39 06-Oct-20, FIRE F
T4-IN-PHE-FF-3560 Installation of Hydrant & Sprinkler Piping with first coat painting (FL36) 31 01-Sep-20 01-Oct-20 0% 39 Installation of Hydra
T4-IN-PHE-FF-3570 Hydrotesting of Hydrant & Sprinkler Piping (FL36) 5 02-Oct-20 06-Oct-20 0% 39 Hydrotesting of Hy
LEVEL 37 36 01-Sep-20 06-Oct-20 39 06-Oct-20, LEVEL 37
PLUMBING 30 01-Sep-20 30-Sep-20 45 30-Sep-20, PLUMBING
T4-IN-PHE-FF-3660 Installation of Water Supply Piping with first coat painting (FL37) 25 01-Sep-20 25-Sep-20 0% 45 Installation of Water
T4-IN-PHE-FF-3670 Installation of Drainage Piping with first coat painting (FL37) 25 01-Sep-20 25-Sep-20 0% 45 Installation of Draina
T4-IN-PHE-FF-3680 Hydrotesting of Water Supply Piping (FL37) 5 26-Sep-20 30-Sep-20 0% 45 Hydrotesting of Wa
T4-IN-PHE-FF-3690 Hydrotesting of Drainage Piping (FL37) 5 26-Sep-20 30-Sep-20 0% 45 Hydrotesting of Dra
FIRE FIGHTING 36 01-Sep-20 06-Oct-20 39 06-Oct-20, FIRE F
T4-IN-PHE-FF-3640 Installation of Hydrant & Sprinkler Piping with first coat painting (FL37) 31 01-Sep-20 01-Oct-20 0% 39 Installation of Hydra
T4-IN-PHE-FF-3650 Hydrotesting of Hydrant & Sprinkler Piping (FL37) 5 02-Oct-20 06-Oct-20 0% 39 Hydrotesting of Hy
LEVEL 38 36 01-Sep-20 06-Oct-20 39 06-Oct-20, LEVEL 38
PLUMBING 30 01-Sep-20 30-Sep-20 45 30-Sep-20, PLUMBING
T4-IN-PHE-FF-3740 Installation of Water Supply Piping with first coat painting (FL38) 25 01-Sep-20 25-Sep-20 0% 45 Installation of Water
T4-IN-PHE-FF-3750 Installation of Drainage Piping with first coat painting (FL38) 25 01-Sep-20 25-Sep-20 0% 45 Installation of Draina
T4-IN-PHE-FF-3760 Hydrotesting of Water Supply Piping (FL38) 5 26-Sep-20 30-Sep-20 0% 45 Hydrotesting of Wa
T4-IN-PHE-FF-3770 Hydrotesting of Drainage Piping (FL38) 5 26-Sep-20 30-Sep-20 0% 45 Hydrotesting of Dra
FIRE FIGHTING 36 01-Sep-20 06-Oct-20 39 06-Oct-20, FIRE F
T4-IN-PHE-FF-3720 Installation of Hydrant & Sprinkler Piping with first coat painting (FL38) 31 01-Sep-20 01-Oct-20 0% 39 Installation of Hydra
T4-IN-PHE-FF-3730 Hydrotesting of Hydrant & Sprinkler Piping (FL38) 5 02-Oct-20 06-Oct-20 0% 39 Hydrotesting of Hy
LEVEL 39 36 01-Sep-20 06-Oct-20 39 06-Oct-20, LEVEL 39
PLUMBING 30 01-Sep-20 30-Sep-20 45 30-Sep-20, PLUMBING
T4-IN-PHE-FF-3820 Installation of Water Supply Piping with first coat painting (FL39) 25 01-Sep-20 25-Sep-20 0% 45 Installation of Water
T4-IN-PHE-FF-3830 Installation of Drainage Piping with first coat painting (FL39) 25 01-Sep-20 25-Sep-20 0% 45 Installation of Draina
T4-IN-PHE-FF-3840 Hydrotesting of Water Supply Piping (FL39) 5 26-Sep-20 30-Sep-20 0% 45 Hydrotesting of Wa
T4-IN-PHE-FF-3850 Hydrotesting of Drainage Piping (FL39) 5 26-Sep-20 30-Sep-20 0% 45 Hydrotesting of Dra
FIRE FIGHTING 36 01-Sep-20 06-Oct-20 39 06-Oct-20, FIRE F
T4-IN-PHE-FF-3800 Installation of Hydrant & Sprinkler Piping with first coat painting (FL39) 31 01-Sep-20 01-Oct-20 0% 39 Installation of Hydra
T4-IN-PHE-FF-3810 Hydrotesting of Hydrant & Sprinkler Piping (FL39) 5 02-Oct-20 06-Oct-20 0% 39 Hydrotesting of Hy
LEVEL ROOF 57 01-Sep-20 27-Oct-20 0 27-Oct-20, LE

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 39 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
PLUMBING 50 01-Sep-20 20-Oct-20 7 20-Oct-20, PLU
T4-IN-PHE-FF-3900 Installation of Water Supply Piping with first coat painting (Roof) 45 01-Sep-20 15-Oct-20 0% 7 Installation of Wa
T4-IN-PHE-FF-3910 Installation of Drainage Piping with first coat painting (Roof) 45 01-Sep-20 15-Oct-20 0% 7 Installation of Dra
T4-IN-PHE-FF-3920 Hydrotesting of Water Supply Piping (Roof) 5 16-Oct-20 20-Oct-20 0% 7 Hydrotesting of
T4-IN-PHE-FF-3930 Hydrotesting of Drainage Piping (Roof) 5 16-Oct-20 20-Oct-20 0% 7 Hydrotesting of
FIRE FIGHTING 57 01-Sep-20 27-Oct-20 0 27-Oct-20, FIR
T4-IN-PHE-FF-3880 Installation of Hydrant & Sprinkler Piping with first coat painting (Roof) 50 01-Sep-20 20-Oct-20 0% 0 Installation of Hy
T4-IN-PHE-FF-3890 Hydrotesting of Hydrant & Sprinkler Piping (Roof) 7 21-Oct-20 27-Oct-20 0% 0 Hydrotesting o
VERTICAL SERVICES 370 05-Dec-19 09-Dec-20 22 09-Dec
PLUMBING SHAFTS 345 05-Dec-19 14-Nov-20 47 14-Nov-20,
LEVEL B2 TO LEVEL P10 100 05-Dec-19 14-Mar-20 108 14-Mar-20, LEVEL B2 TO LEVEL P10
T4-IN-PHE-SFT-1005 Access from Client for Plumbing Riser Works (B1- P10) 0 05-Dec-19 0% 108 Access from Client for Plumbing Riser Works (B1- P10)
T4-IN-PHE-SFT-1015 Support Installation (B1- P10) 20 05-Dec-19 24-Dec-19 0% 108 Support Installation (B1- P10)
T4-IN-PHE-SFT-1025 Installation of Riser Pipes & Fittings (B1- P10) 55 26-Dec-19 18-Feb-20 0% 108 Installation of Riser Pipes & Fittings (B1- P10)
T4-IN-PHE-SFT-1035 Accessories Installation (B1- P10) 25 19-Feb-20 14-Mar-20 0% 108 Accessories Installation (B1- P10)
LEVEL S1 TO LEVEL 17 100 01-Feb-20 10-May-20 51 10-May-20, LEVEL S1 TO LEVEL 17
T4-IN-PHE-SFT-1045 Access from Client for Plumbing Riser Works (S1 - FL17) 0 01-Feb-20 0% 51 Access from Client for Plumbing Riser Works (S1 - FL17)
T4-IN-PHE-SFT-1055 Support Installation (S1 - FL17) 20 01-Feb-20 20-Feb-20 0% 51 Support Installation (S1 - FL17)
T4-IN-PHE-SFT-1065 Installation of Riser Pipes & Fittings (S1 - FL17) 55 21-Feb-20 15-Apr-20 0% 51 Installation of Riser Pipes & Fittings (S1 - FL17)
T4-IN-PHE-SFT-1075 Accessories Installation (S1 - FL17) 25 16-Apr-20 10-May-20 0% 51 Accessories Installation (S1 - FL17)
LEVEL 18 TO LEVEL 27 100 15-May-20 22-Aug-20 131 22-Aug-20, LEVEL 18 TO
T4-IN-PHE-SFT-1085 Access from Client for Plumbing Riser Works (FL18 - FL27) 0 15-May-20 0% 131 Access from Client for Plumbing Riser Wo
T4-IN-PHE-SFT-1095 Support Installation (FL18 - FL27) 20 15-May-20 03-Jun-20 0% 131 Support Installation (FL18 - FL27)
T4-IN-PHE-SFT-1105 Installation of Riser Pipes & Fittings (FL18 - FL27) 55 04-Jun-20 28-Jul-20 0% 131 Installation of Riser Pipes & Fi
T4-IN-PHE-SFT-1115 Accessories Installation (FL18 - FL27) 25 29-Jul-20 22-Aug-20 0% 131 Accessories Installation (F
LEVEL 28 TO LEVEL 35 100 23-Jul-20 30-Oct-20 62 30-Oct-20, LE
T4-IN-PHE-SFT-1125 Access from Client for Plumbing Riser Works (FL28 - FL35) 0 23-Jul-20 0% 62 Access from Client for Plumbin
T4-IN-PHE-SFT-1135 Support Installation (FL28 - FL35) 20 23-Jul-20 11-Aug-20 0% 62 Support Installation (FL28 -
T4-IN-PHE-SFT-1145 Installation of Riser Pipes & Fittings (FL28 - FL35) 55 12-Aug-20 05-Oct-20 0% 62 Installation of Rise
T4-IN-PHE-SFT-1155 Accessories Installation (FL28 - FL35) 25 06-Oct-20 30-Oct-20 0% 62 Accessories In
LEVEL 36 TO LEVEL ROOF 75 01-Sep-20 14-Nov-20 47 14-Nov-20,
T4-IN-PHE-SFT-1165 Access from Client for Plumbing Riser Works (FL36 - ROOF) 0 01-Sep-20 0% 47 Access from Client for P
T4-IN-PHE-SFT-1175 Support Installation (FL36 - ROOF) 15 01-Sep-20 15-Sep-20 0% 47 Support Installation (F
T4-IN-PHE-SFT-1185 Installation of Riser Pipes & Fittings (FL36 - ROOF) 40 16-Sep-20 25-Oct-20 0% 47 Installation of R
T4-IN-PHE-SFT-1195 Accessories Installation (FL36 - ROOF) 20 26-Oct-20 14-Nov-20 0% 47 Accessories
FIREFIGHTING SHAFTS 370 05-Dec-19 09-Dec-20 22 09-Dec
LEVEL B2 TO LEVEL P10 100 05-Dec-19 14-Mar-20 108 14-Mar-20, LEVEL B2 TO LEVEL P10
T4-IN-FF-SFT-1205 Access from Client for Firefighting Riser Works (B2- P10) 0 05-Dec-19 0% 108 Access from Client for Firefighting Riser Works (B2- P10)
T4-IN-FF-SFT-1215 Support Installation (B2- P10) 20 05-Dec-19 24-Dec-19 0% 108 Support Installation (B2- P10)
T4-IN-FF-SFT-1225 Installation of Riser Pipes & Fittings (B2- P10) 55 26-Dec-19 18-Feb-20 0% 108 Installation of Riser Pipes & Fittings (B2- P10)
T4-IN-FF-SFT-1235 Accessories Installation (B2- P10) 25 19-Feb-20 14-Mar-20 0% 108 Accessories Installation (B2- P10)
LEVEL S1 TO LEVEL 17 100 01-Feb-20 10-May-20 51 10-May-20, LEVEL S1 TO LEVEL 17
T4-IN-FF-SFT-1245 Access from Client for Firefighting Riser Works (S1 - FL17) 0 01-Feb-20 0% 51 Access from Client for Firefighting Riser Works (S1 - FL17)
T4-IN-FF-SFT-1255 Support Installation (S1 - FL17) 20 01-Feb-20 20-Feb-20 0% 51 Support Installation (S1 - FL17)
T4-IN-FF-SFT-1265 Installation of Riser Pipes & Fittings (S1 - FL17) 55 21-Feb-20 15-Apr-20 0% 51 Installation of Riser Pipes & Fittings (S1 - FL17)
T4-IN-FF-SFT-1275 Accessories Installation (S1 - FL17) 25 16-Apr-20 10-May-20 0% 51 Accessories Installation (S1 - FL17)
LEVEL 18 TO LEVEL 27 100 15-May-20 22-Aug-20 131 22-Aug-20, LEVEL 18 TO
T4-IN-FF-SFT-1285 Access from Client for Firefighting Riser Works (FL18 - FL27) 0 15-May-20 0% 131 Access from Client for Firefighting Riser W
T4-IN-FF-SFT-1295 Support Installation (FL18 - FL27) 20 15-May-20 03-Jun-20 0% 131 Support Installation (FL18 - FL27)
T4-IN-FF-SFT-1305 Installation of Riser Pipes & Fittings (FL18 - FL27) 55 04-Jun-20 28-Jul-20 0% 131 Installation of Riser Pipes & Fi
T4-IN-FF-SFT-1315 Accessories Installation (FL18 - FL27) 25 29-Jul-20 22-Aug-20 0% 131 Accessories Installation (F
LEVEL 28 TO LEVEL 35 100 23-Jul-20 30-Oct-20 62 30-Oct-20, LE
T4-IN-FF-SFT-1325 Access from Client for Firefighting Riser Works (FL28 - FL35) 0 23-Jul-20 0% 62 Access from Client for Firefight

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 40 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-FF-SFT-1335 Support Installation (FL28 - FL35) 20 23-Jul-20 11-Aug-20 0% 62 Support Installation (FL28 -
T4-IN-FF-SFT-1345 Installation of Riser Pipes & Fittings (FL28 - FL35) 55 12-Aug-20 05-Oct-20 0% 62 Installation of Rise
T4-IN-FF-SFT-1355 Accessories Installation (FL28 - FL35) 25 06-Oct-20 30-Oct-20 0% 62 Accessories In
LEVEL 36 TO LEVEL ROOF 100 01-Sep-20 09-Dec-20 22 09-Dec
T4-IN-FF-SFT-1365 Access from Client for Firefighting Riser Works (FL36 - ROOF) 0 01-Sep-20 0% 22 Access from Client for F
T4-IN-FF-SFT-1375 Support Installation (FL36 - ROOF) 20 01-Sep-20 20-Sep-20 0% 22 Support Installation (
T4-IN-FF-SFT-1385 Installation of Riser Pipes & Fittings (FL36 - ROOF) 55 21-Sep-20 14-Nov-20 0% 22 Installation o
T4-IN-FF-SFT-1395 Accessories Installation (FL36 - ROOF) 25 15-Nov-20 09-Dec-20 0% 22 Accesso
HVAC 441 21-Aug-19 09-Nov-20 52 09-Nov-20, HVAC
HORIZONTAL SERVICE 428 21-Aug-19 27-Oct-20 18 27-Oct-20, HO
LEVEL B2 67 15-Dec-19 20-Feb-20 72 20-Feb-20, LEVEL B2
T4-IN-HVC-FF-6170 Installation of TFA & Supply / Return Air Ducting with Insulation (B2) 55 15-Dec-19 08-Feb-20 0% 72 Installation of TFA & Supply / Return Air Ducting with Insula
T4-IN-HVC-FF-6180 Installation of Chilled Water Piping with Insulation (B2) 50 15-Dec-19 03-Feb-20 0% 79 Installation of Chilled Water Piping with Insulation (B2)
T4-IN-HVC-FF-6190 Installation of VCD/ Smoke / Fire Dampers (B2) 20 22-Jan-20 10-Feb-20 0% 72 Installation of VCD/ Smoke / Fire Dampers (B2)
T4-IN-HVC-FF-6200 Ducting Light Testing (B2) 10 11-Feb-20 20-Feb-20 0% 72 Ducting Light Testing (B2)
T4-IN-HVC-FF-6210 Chilled Water Piping Hydrotesting (B2) 10 04-Feb-20 13-Feb-20 0% 79 Chilled Water Piping Hydrotesting (B2)
LEVEL B1 70 22-Nov-19 31-Jan-20 83 31-Jan-20, LEVEL B1
T4-IN-HVC-FF-6220 Installation of TFA & Supply / Return Air Ducting with Insulation (B1) 55 22-Nov-19 16-Jan-20 0% 83 Installation of TFA & Supply / Return Air Ducting with Insulation
T4-IN-HVC-FF-6230 Installation of VCD/ Smoke / Fire Dampers (B1) 15 09-Jan-20 23-Jan-20 0% 83 Installation of VCD/ Smoke / Fire Dampers (B1)
T4-IN-HVC-FF-6240 Installation of Chilled Water Piping with Insulation (B1) 50 22-Nov-19 11-Jan-20 0% 93 Installation of Chilled Water Piping with Insulation (B1)
T4-IN-HVC-FF-6250 Ducting Light Testing (B1) 8 24-Jan-20 31-Jan-20 0% 83 Ducting Light Testing (B1)
T4-IN-HVC-FF-6260 Chilled Water Piping Hydrotesting (B1) 10 12-Jan-20 21-Jan-20 0% 93 Chilled Water Piping Hydrotesting (B1)
LEVEL P0 30 15-Oct-19 15-Nov-19 172 15-Nov-19, LEVEL P0
T4-IN-HVC-FF-6270 Installation of TFA & Supply / Return Air Ducting with Insulation (P0) 25 15-Oct-19 09-Nov-19 0% 172 Installation of TFA & Supply / Return Air Ducting with Insulation (P0)
T4-IN-HVC-FF-6280 Installation of VCD/ Smoke / Fire Dampers (P0) 15 27-Oct-19 11-Nov-19 0% 172 Installation of VCD/ Smoke / Fire Dampers (P0)
T4-IN-HVC-FF-6290 Installation of Chilled Water Piping with Insulation (P0) 25 15-Oct-19 09-Nov-19 0% 172 Installation of Chilled Water Piping with Insulation (P0)
T4-IN-HVC-FF-6300 Ducting Light Testing (P0) 3 13-Nov-19 15-Nov-19 0% 172 Ducting Light Testing (P0)
T4-IN-HVC-FF-6310 Chilled Water Piping Hydrotesting (P0) 5 10-Nov-19 15-Nov-19 0% 172 Chilled Water Piping Hydrotesting (P0)
LEVEL P1 19 30-Sep-19 20-Oct-19 206 20-Oct-19, LEVEL P1
T4-IN-HVC-FF-6320 Installation of TFA & Supply / Return Air Ducting with Insulation (P1) 12 30-Sep-19 13-Oct-19 0% 208 Installation of TFA & Supply / Return Air Ducting with Insulation (P1)
T4-IN-HVC-FF-6330 Installation of VCD/ Smoke / Fire Dampers (P1) 12 03-Oct-19 15-Oct-19 0% 208 Installation of VCD/ Smoke / Fire Dampers (P1)
T4-IN-HVC-FF-6340 Installation of Chilled Water Piping with Insulation (P1) 15 30-Sep-19 16-Oct-19 0% 206 Installation of Chilled Water Piping with Insulation (P1)
T4-IN-HVC-FF-6350 Ducting Light Testing (P1) 3 16-Oct-19 18-Oct-19 0% 208 Ducting Light Testing (P1)
T4-IN-HVC-FF-6360 Chilled Water Piping Hydrotesting (P1) 4 17-Oct-19 20-Oct-19 0% 206 Chilled Water Piping Hydrotesting (P1)
LEVEL P2 58 21-Aug-19 20-Oct-19 41 20-Oct-19, LEVEL P2
T4-IN-HVC-FF-6370 Installation of TFA & Supply / Return Air Ducting with Insulation (P2) 45 21-Aug-19 06-Oct-19 0% 41 Installation of TFA & Supply / Return Air Ducting with Insulation (P2)
T4-IN-HVC-FF-6380 Installation of VCD/ Smoke / Fire Dampers (P2) 20 24-Sep-19 15-Oct-19 0% 41 Installation of VCD/ Smoke / Fire Dampers (P2)
T4-IN-HVC-FF-6390 Installation of Chilled Water Piping with Insulation (P2) 45 21-Aug-19 06-Oct-19 0% 47 Installation of Chilled Water Piping with Insulation (P2)
T4-IN-HVC-FF-6400 Ducting Light Testing (P2) 5 16-Oct-19 20-Oct-19 0% 41 Ducting Light Testing (P2)
T4-IN-HVC-FF-6410 Chilled Water Piping Hydrotesting (P2) 7 07-Oct-19 14-Oct-19 0% 47 Chilled Water Piping Hydrotesting (P2)
LEVEL P3 29 14-Oct-19 13-Nov-19 182 13-Nov-19, LEVEL P3
T4-IN-HVC-FF-6420 Installation of TFA & Supply / Return Air Ducting with Insulation (P3) 25 14-Oct-19 08-Nov-19 0% 182 Installation of TFA & Supply / Return Air Ducting with Insulation (P3)
T4-IN-HVC-FF-6430 Installation of VCD/ Smoke / Fire Dampers (P3) 10 31-Oct-19 09-Nov-19 0% 182 Installation of VCD/ Smoke / Fire Dampers (P3)
T4-IN-HVC-FF-6440 Installation of Chilled Water Piping with Insulation (P3) 25 14-Oct-19 08-Nov-19 0% 182 Installation of Chilled Water Piping with Insulation (P3)
T4-IN-HVC-FF-6450 Ducting Light Testing (P3) 3 10-Nov-19 13-Nov-19 0% 182 Ducting Light Testing (P3)
T4-IN-HVC-FF-6460 Chilled Water Piping Hydrotesting (P3) 4 09-Nov-19 13-Nov-19 0% 182 Chilled Water Piping Hydrotesting (P3)
LEVEL P4 29 14-Oct-19 13-Nov-19 182 13-Nov-19, LEVEL P4
T4-IN-HVC-FF-6470 Installation of TFA & Supply / Return Air Ducting with Insulation (P4) 25 14-Oct-19 08-Nov-19 0% 182 Installation of TFA & Supply / Return Air Ducting with Insulation (P4)
T4-IN-HVC-FF-6480 Installation of VCD/ Smoke / Fire Dampers (P4) 10 31-Oct-19 09-Nov-19 0% 182 Installation of VCD/ Smoke / Fire Dampers (P4)
T4-IN-HVC-FF-6490 Installation of Chilled Water Piping with Insulation (P4) 25 14-Oct-19 08-Nov-19 0% 182 Installation of Chilled Water Piping with Insulation (P4)
T4-IN-HVC-FF-6500 Ducting Light Testing (P4) 3 10-Nov-19 13-Nov-19 0% 182 Ducting Light Testing (P4)
T4-IN-HVC-FF-6510 Chilled Water Piping Hydrotesting (P4) 4 09-Nov-19 13-Nov-19 0% 182 Chilled Water Piping Hydrotesting (P4)

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 41 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
LEVEL P5 29 14-Oct-19 13-Nov-19 182 13-Nov-19, LEVEL P5
T4-IN-HVC-FF-6520 Installation of TFA & Supply / Return Air Ducting with Insulation (P5) 25 14-Oct-19 08-Nov-19 0% 182 Installation of TFA & Supply / Return Air Ducting with Insulation (P5)
T4-IN-HVC-FF-6530 Installation of VCD/ Smoke / Fire Dampers (P5) 10 31-Oct-19 09-Nov-19 0% 182 Installation of VCD/ Smoke / Fire Dampers (P5)
T4-IN-HVC-FF-6540 Installation of Chilled Water Piping with Insulation (P5) 25 14-Oct-19 08-Nov-19 0% 182 Installation of Chilled Water Piping with Insulation (P5)
T4-IN-HVC-FF-6550 Ducting Light Testing (P5) 3 10-Nov-19 13-Nov-19 0% 182 Ducting Light Testing (P5)
T4-IN-HVC-FF-6560 Chilled Water Piping Hydrotesting (P5) 4 09-Nov-19 13-Nov-19 0% 182 Chilled Water Piping Hydrotesting (P5)
LEVEL P6 29 14-Oct-19 13-Nov-19 182 13-Nov-19, LEVEL P6
T4-IN-HVC-FF-6570 Installation of TFA & Supply / Return Air Ducting with Insulation (P5) 25 14-Oct-19 08-Nov-19 0% 182 Installation of TFA & Supply / Return Air Ducting with Insulation (P5)
T4-IN-HVC-FF-6580 Installation of VCD/ Smoke / Fire Dampers (P6) 10 31-Oct-19 09-Nov-19 0% 182 Installation of VCD/ Smoke / Fire Dampers (P6)
T4-IN-HVC-FF-6590 Installation of Chilled Water Piping with Insulation (P6) 25 14-Oct-19 08-Nov-19 0% 182 Installation of Chilled Water Piping with Insulation (P6)
T4-IN-HVC-FF-6600 Ducting Light Testing (P6) 3 10-Nov-19 13-Nov-19 0% 182 Ducting Light Testing (P6)
T4-IN-HVC-FF-6610 Chilled Water Piping Hydrotesting (P6) 4 09-Nov-19 13-Nov-19 0% 182 Chilled Water Piping Hydrotesting (P6)
LEVEL P7 40 02-Nov-19 12-Dec-19 154 12-Dec-19, LEVEL P7
T4-IN-HVC-FF-6620 Installation of TFA & Supply / Return Air Ducting with Insulation (P7) 35 02-Nov-19 07-Dec-19 0% 154 Installation of TFA & Supply / Return Air Ducting with Insulation (P7)
T4-IN-HVC-FF-6630 Installation of VCD/ Smoke / Fire Dampers (P7) 15 25-Nov-19 09-Dec-19 0% 154 Installation of VCD/ Smoke / Fire Dampers (P7)
T4-IN-HVC-FF-6640 Installation of Chilled Water Piping with Insulation (P7) 35 02-Nov-19 07-Dec-19 0% 154 Installation of Chilled Water Piping with Insulation (P7)
T4-IN-HVC-FF-6650 Ducting Light Testing (P7) 3 10-Dec-19 12-Dec-19 0% 154 Ducting Light Testing (P7)
T4-IN-HVC-FF-6660 Chilled Water Piping Hydrotesting (P7) 5 08-Dec-19 12-Dec-19 0% 154 Chilled Water Piping Hydrotesting (P7)
LEVEL P8 40 02-Nov-19 12-Dec-19 154 12-Dec-19, LEVEL P8
T4-IN-HVC-FF-6670 Installation of TFA & Supply / Return Air Ducting with Insulation (P8) 35 02-Nov-19 07-Dec-19 0% 154 Installation of TFA & Supply / Return Air Ducting with Insulation (P8)
T4-IN-HVC-FF-6680 Installation of VCD/ Smoke / Fire Dampers (P8) 15 25-Nov-19 09-Dec-19 0% 154 Installation of VCD/ Smoke / Fire Dampers (P8)
T4-IN-HVC-FF-6690 Installation of Chilled Water Piping with Insulation (P8) 35 02-Nov-19 07-Dec-19 0% 154 Installation of Chilled Water Piping with Insulation (P8)
T4-IN-HVC-FF-6700 Ducting Light Testing (P8) 3 10-Dec-19 12-Dec-19 0% 154 Ducting Light Testing (P8)
T4-IN-HVC-FF-6710 Chilled Water Piping Hydrotesting (P8) 5 08-Dec-19 12-Dec-19 0% 154 Chilled Water Piping Hydrotesting (P8)
LEVEL P9 28 05-Dec-19 02-Jan-20 133 02-Jan-20, LEVEL P9
T4-IN-HVC-FF-6720 Installation of TFA & Supply / Return Air Ducting with Insulation (P9) 21 05-Dec-19 26-Dec-19 0% 134 Installation of TFA & Supply / Return Air Ducting with Insulation (P9)
T4-IN-HVC-FF-6730 Installation of VCD/ Smoke / Fire Dampers (P9) 15 14-Dec-19 29-Dec-19 0% 134 Installation of VCD/ Smoke / Fire Dampers (P9)
T4-IN-HVC-FF-6740 Installation of Chilled Water Piping with Insulation (P9) 25 05-Dec-19 30-Dec-19 0% 133 Installation of Chilled Water Piping with Insulation (P9)
T4-IN-HVC-FF-6750 Ducting Light Testing (P9) 3 30-Dec-19 01-Jan-20 0% 134 Ducting Light Testing (P9)
T4-IN-HVC-FF-6760 Chilled Water Piping Hydrotesting (P9) 3 31-Dec-19 02-Jan-20 0% 133 Chilled Water Piping Hydrotesting (P9)
LEVEL P10 28 05-Dec-19 02-Jan-20 133 02-Jan-20, LEVEL P10
T4-IN-HVC-FF-6770 Installation of TFA & Supply / Return Air Ducting with Insulation (P10) 21 05-Dec-19 26-Dec-19 0% 134 Installation of TFA & Supply / Return Air Ducting with Insulation (P10)
T4-IN-HVC-FF-6780 Installation of VCD/ Smoke / Fire Dampers (P10) 15 14-Dec-19 29-Dec-19 0% 134 Installation of VCD/ Smoke / Fire Dampers (P10)
T4-IN-HVC-FF-6790 Installation of Chilled Water Piping with Insulation (P10) 25 05-Dec-19 30-Dec-19 0% 133 Installation of Chilled Water Piping with Insulation (P10)
T4-IN-HVC-FF-6800 Ducting Light Testing (P10) 3 30-Dec-19 01-Jan-20 0% 134 Ducting Light Testing (P10)
T4-IN-HVC-FF-6810 Chilled Water Piping Hydrotesting (P10) 3 31-Dec-19 02-Jan-20 0% 133 Chilled Water Piping Hydrotesting (P10)
LEVEL S1 57 22-Dec-19 17-Feb-20 102 17-Feb-20, LEVEL S1
T4-IN-HVC-FF-9540 Installation of TFA & Supply / Return Air Ducting with Insulation (S1) 40 22-Dec-19 31-Jan-20 0% 102 Installation of TFA & Supply / Return Air Ducting with Insulat
T4-IN-HVC-FF-9550 Installation of VCD/ Smoke / Fire Dampers (S1) 15 22-Jan-20 05-Feb-20 0% 109 Installation of VCD/ Smoke / Fire Dampers (S1)
T4-IN-HVC-FF-9560 Installation of Chilled Water Piping with Insulation (S1) 50 22-Dec-19 10-Feb-20 0% 102 Installation of Chilled Water Piping with Insulation (S1)
T4-IN-HVC-FF-9570 Ducting Light Testing (S1) 5 06-Feb-20 10-Feb-20 0% 109 Ducting Light Testing (S1)
T4-IN-HVC-FF-9580 Chilled Water Piping Hydrotesting (S1) 7 11-Feb-20 17-Feb-20 0% 102 Chilled Water Piping Hydrotesting (S1)
LEVEL 17 41 01-Feb-20 12-Mar-20 34 12-Mar-20, LEVEL 17
T4-IN-HVC-FF-6820 Installation of TFA & Supply / Return Air Ducting with Insulation (FL17) 35 01-Feb-20 06-Mar-20 0% 34 Installation of TFA & Supply / Return Air Ducting with I
T4-IN-HVC-FF-6830 Installation of VCD/ Smoke / Fire Dampers (FL17) 15 23-Feb-20 08-Mar-20 0% 34 Installation of VCD/ Smoke / Fire Dampers (FL17)
T4-IN-HVC-FF-6840 Installation of Chilled Water Piping with Insulation (FL17) 35 01-Feb-20 06-Mar-20 0% 35 Installation of Chilled Water Piping with Insulation (FL17)
T4-IN-HVC-FF-6850 Ducting Light Testing (FL17) 4 09-Mar-20 12-Mar-20 0% 34 Ducting Light Testing (FL17)
T4-IN-HVC-FF-6860 Chilled Water Piping Hydrotesting (FL17) 5 07-Mar-20 11-Mar-20 0% 35 Chilled Water Piping Hydrotesting (FL17)
LEVEL 18 36 11-Apr-20 16-May-20 182 16-May-20, LEVEL 18
T4-IN-HVC-FF-6870 Installation of TFA & Supply / Return Air Ducting with Insulation (FL18) 30 11-Apr-20 10-May-20 0% 182 Installation of TFA & Supply / Return Air Du
T4-IN-HVC-FF-6880 Installation of VCD/ Smoke / Fire Dampers (FL18) 15 28-Apr-20 12-May-20 0% 182 Installation of VCD/ Smoke / Fire Dampers
T4-IN-HVC-FF-6890 Installation of Chilled Water Piping with Insulation (FL18) 30 11-Apr-20 10-May-20 0% 183 Installation of Chilled Water Piping with Insu

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 42 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-HVC-FF-6900 Ducting Light Testing (FL18) 4 13-May-20 16-May-20 0% 182 Ducting Light Testing (FL18)
T4-IN-HVC-FF-6910 Chilled Water Piping Hydrotesting (FL18) 5 11-May-20 15-May-20 0% 183 Chilled Water Piping Hydrotesting (FL18)
LEVEL 19 36 11-Apr-20 16-May-20 182 16-May-20, LEVEL 19
T4-IN-HVC-FF-6920 Installation of TFA & Supply / Return Air Ducting with Insulation (FL19) 30 11-Apr-20 10-May-20 0% 182 Installation of TFA & Supply / Return Air Du
T4-IN-HVC-FF-6930 Installation of VCD/ Smoke / Fire Dampers (FL19) 15 28-Apr-20 12-May-20 0% 182 Installation of VCD/ Smoke / Fire Dampers
T4-IN-HVC-FF-6940 Installation of Chilled Water Piping with Insulation (FL19) 30 11-Apr-20 10-May-20 0% 183 Installation of Chilled Water Piping with Insu
T4-IN-HVC-FF-6950 Ducting Light Testing (FL19) 4 13-May-20 16-May-20 0% 182 Ducting Light Testing (FL19)
T4-IN-HVC-FF-6960 Chilled Water Piping Hydrotesting (FL19) 5 11-May-20 15-May-20 0% 183 Chilled Water Piping Hydrotesting (FL19)
LEVEL 20 36 11-Apr-20 16-May-20 182 16-May-20, LEVEL 20
T4-IN-HVC-FF-6970 Installation of TFA & Supply / Return Air Ducting with Insulation (FL20) 30 11-Apr-20 10-May-20 0% 182 Installation of TFA & Supply / Return Air Du
T4-IN-HVC-FF-6980 Installation of VCD/ Smoke / Fire Dampers (FL20) 15 28-Apr-20 12-May-20 0% 182 Installation of VCD/ Smoke / Fire Dampers
T4-IN-HVC-FF-6990 Installation of Chilled Water Piping with Insulation (FL20) 30 11-Apr-20 10-May-20 0% 183 Installation of Chilled Water Piping with Insu
T4-IN-HVC-FF-7000 Ducting Light Testing (FL20) 4 13-May-20 16-May-20 0% 182 Ducting Light Testing (FL20)
T4-IN-HVC-FF-7010 Chilled Water Piping Hydrotesting (FL20) 5 11-May-20 15-May-20 0% 183 Chilled Water Piping Hydrotesting (FL20)
LEVEL 21 36 11-Apr-20 16-May-20 182 16-May-20, LEVEL 21
T4-IN-HVC-FF-7020 Installation of TFA & Supply / Return Air Ducting with Insulation (FL21) 30 11-Apr-20 10-May-20 0% 182 Installation of TFA & Supply / Return Air Du
T4-IN-HVC-FF-7030 Installation of VCD/ Smoke / Fire Dampers (FL21) 15 28-Apr-20 12-May-20 0% 182 Installation of VCD/ Smoke / Fire Dampers
T4-IN-HVC-FF-7040 Installation of Chilled Water Piping with Insulation (FL21) 30 11-Apr-20 10-May-20 0% 183 Installation of Chilled Water Piping with Insu
T4-IN-HVC-FF-7050 Ducting Light Testing (FL21) 4 13-May-20 16-May-20 0% 182 Ducting Light Testing (FL21)
T4-IN-HVC-FF-7060 Chilled Water Piping Hydrotesting (FL21) 5 11-May-20 15-May-20 0% 183 Chilled Water Piping Hydrotesting (FL21)
LEVEL 22 46 27-Mar-20 11-May-20 31 11-May-20, LEVEL 22
T4-IN-HVC-FF-7070 Installation of TFA & Supply / Return Air Ducting with Insulation (FL22) 20 16-Apr-20 05-May-20 0% 31 Installation of TFA & Supply / Return Air Duc
T4-IN-HVC-FF-7080 Installation of VCD/ Smoke / Fire Dampers (FL22) 15 23-Apr-20 07-May-20 0% 31 Installation of VCD/ Smoke / Fire Dampers
T4-IN-HVC-FF-7090 Installation of Chilled Water Piping with Insulation (FL22) 36 27-Mar-20 01-May-20 0% 36 Installation of Chilled Water Piping with Insul
T4-IN-HVC-FF-7100 Ducting Light Testing (FL22) 4 08-May-20 11-May-20 0% 31 Ducting Light Testing (FL22)
T4-IN-HVC-FF-7110 Chilled Water Piping Hydrotesting (FL22) 5 02-May-20 06-May-20 0% 36 Chilled Water Piping Hydrotesting (FL22)
LEVEL 23 36 15-May-20 19-Jun-20 148 19-Jun-20, LEVEL 23
T4-IN-HVC-FF-7120 Installation of TFA & Supply / Return Air Ducting with Insulation (FL23) 30 15-May-20 13-Jun-20 0% 148 Installation of TFA & Supply / Return A
T4-IN-HVC-FF-7130 Installation of VCD/ Smoke / Fire Dampers (FL23) 15 01-Jun-20 15-Jun-20 0% 148 Installation of VCD/ Smoke / Fire Dam
T4-IN-HVC-FF-7140 Installation of Chilled Water Piping with Insulation (FL23) 30 15-May-20 13-Jun-20 0% 149 Installation of Chilled Water Piping wi
T4-IN-HVC-FF-7150 Ducting Light Testing (FL23) 4 16-Jun-20 19-Jun-20 0% 148 Ducting Light Testing (FL23)
T4-IN-HVC-FF-7160 Chilled Water Piping Hydrotesting (FL23) 5 14-Jun-20 18-Jun-20 0% 149 Chilled Water Piping Hydrotesting (FL23)
LEVEL 24 36 15-May-20 19-Jun-20 148 19-Jun-20, LEVEL 24
T4-IN-HVC-FF-7170 Installation of TFA & Supply / Return Air Ducting with Insulation (FL24) 30 15-May-20 13-Jun-20 0% 148 Installation of TFA & Supply / Return A
T4-IN-HVC-FF-7180 Installation of VCD/ Smoke / Fire Dampers (FL24) 15 01-Jun-20 15-Jun-20 0% 148 Installation of VCD/ Smoke / Fire Dam
T4-IN-HVC-FF-7190 Installation of Chilled Water Piping with Insulation (FL24) 30 15-May-20 13-Jun-20 0% 149 Installation of Chilled Water Piping wi
T4-IN-HVC-FF-7200 Ducting Light Testing (FL24) 4 16-Jun-20 19-Jun-20 0% 148 Ducting Light Testing (FL24)
T4-IN-HVC-FF-7210 Chilled Water Piping Hydrotesting (FL24) 5 14-Jun-20 18-Jun-20 0% 149 Chilled Water Piping Hydrotesting (FL24)
LEVEL 25 36 15-May-20 19-Jun-20 148 19-Jun-20, LEVEL 25
T4-IN-HVC-FF-7220 Installation of TFA & Supply / Return Air Ducting with Insulation (FL25) 30 15-May-20 13-Jun-20 0% 148 Installation of TFA & Supply / Return A
T4-IN-HVC-FF-7230 Installation of VCD/ Smoke / Fire Dampers (FL25) 15 01-Jun-20 15-Jun-20 0% 148 Installation of VCD/ Smoke / Fire Dam
T4-IN-HVC-FF-7240 Installation of Chilled Water Piping with Insulation (FL25) 30 15-May-20 13-Jun-20 0% 149 Installation of Chilled Water Piping wi
T4-IN-HVC-FF-7250 Ducting Light Testing (FL25) 4 16-Jun-20 19-Jun-20 0% 148 Ducting Light Testing (FL25)
T4-IN-HVC-FF-7260 Chilled Water Piping Hydrotesting (FL25) 5 14-Jun-20 18-Jun-20 0% 149 Chilled Water Piping Hydrotesting (FL25)
LEVEL 26 36 15-May-20 19-Jun-20 148 19-Jun-20, LEVEL 26
T4-IN-HVC-FF-7270 Installation of TFA & Supply / Return Air Ducting with Insulation (FL26) 30 15-May-20 13-Jun-20 0% 148 Installation of TFA & Supply / Return A
T4-IN-HVC-FF-7280 Installation of VCD/ Smoke / Fire Dampers (FL26) 15 01-Jun-20 15-Jun-20 0% 148 Installation of VCD/ Smoke / Fire Dam
T4-IN-HVC-FF-7290 Installation of Chilled Water Piping with Insulation (FL26) 30 15-May-20 13-Jun-20 0% 149 Installation of Chilled Water Piping wi
T4-IN-HVC-FF-7300 Ducting Light Testing (FL26) 4 16-Jun-20 19-Jun-20 0% 148 Ducting Light Testing (FL26)
T4-IN-HVC-FF-7310 Chilled Water Piping Hydrotesting (FL26) 5 14-Jun-20 18-Jun-20 0% 149 Chilled Water Piping Hydrotesting (FL26)
LEVEL 27 36 15-May-20 19-Jun-20 148 19-Jun-20, LEVEL 27
T4-IN-HVC-FF-7320 Installation of TFA & Supply / Return Air Ducting with Insulation (FL27) 30 15-May-20 13-Jun-20 0% 148 Installation of TFA & Supply / Return A

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 43 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-HVC-FF-7330 Installation of VCD/ Smoke / Fire Dampers (FL27) 15 01-Jun-20 15-Jun-20 0% 148 Installation of VCD/ Smoke / Fire Dam
T4-IN-HVC-FF-7340 Installation of Chilled Water Piping with Insulation (FL27) 30 15-May-20 13-Jun-20 0% 149 Installation of Chilled Water Piping wi
T4-IN-HVC-FF-7350 Ducting Light Testing (FL27) 4 16-Jun-20 19-Jun-20 0% 148 Ducting Light Testing (FL27)
T4-IN-HVC-FF-7360 Chilled Water Piping Hydrotesting (FL27) 5 14-Jun-20 18-Jun-20 0% 149 Chilled Water Piping Hydrotesting (FL27)
LEVEL 28 36 18-Jun-20 23-Jul-20 114 23-Jul-20, LEVEL 28
T4-IN-HVC-FF-7370 Installation of TFA & Supply / Return Air Ducting with Insulation (FL28) 30 18-Jun-20 17-Jul-20 0% 114 Installation of TFA & Supply / Re
T4-IN-HVC-FF-7380 Installation of VCD/ Smoke / Fire Dampers (FL28) 15 05-Jul-20 19-Jul-20 0% 114 Installation of VCD/ Smoke / Fir
T4-IN-HVC-FF-7390 Installation of Chilled Water Piping with Insulation (FL28) 30 18-Jun-20 17-Jul-20 0% 115 Installation of Chilled Water Pipi
T4-IN-HVC-FF-7400 Ducting Light Testing (FL28) 4 20-Jul-20 23-Jul-20 0% 114 Ducting Light Testing (FL28)
T4-IN-HVC-FF-7410 Chilled Water Piping Hydrotesting (FL28) 5 18-Jul-20 22-Jul-20 0% 115 Chilled Water Piping Hydrotest
LEVEL 29 36 18-Jun-20 23-Jul-20 114 23-Jul-20, LEVEL 29
T4-IN-HVC-FF-7420 Installation of TFA & Supply / Return Air Ducting with Insulation (FL29) 30 18-Jun-20 17-Jul-20 0% 114 Installation of TFA & Supply / Re
T4-IN-HVC-FF-7430 Installation of VCD/ Smoke / Fire Dampers (FL29) 15 05-Jul-20 19-Jul-20 0% 114 Installation of VCD/ Smoke / Fir
T4-IN-HVC-FF-7440 Installation of Chilled Water Piping with Insulation (FL29) 30 18-Jun-20 17-Jul-20 0% 115 Installation of Chilled Water Pipi
T4-IN-HVC-FF-7450 Ducting Light Testing (FL29) 4 20-Jul-20 23-Jul-20 0% 114 Ducting Light Testing (FL29)
T4-IN-HVC-FF-7460 Chilled Water Piping Hydrotesting (FL29) 5 18-Jul-20 22-Jul-20 0% 115 Chilled Water Piping Hydrotest
LEVEL 30 36 18-Jun-20 23-Jul-20 114 23-Jul-20, LEVEL 30
T4-IN-HVC-FF-7470 Installation of TFA & Supply / Return Air Ducting with Insulation (FL30) 30 18-Jun-20 17-Jul-20 0% 114 Installation of TFA & Supply / Re
T4-IN-HVC-FF-7480 Installation of VCD/ Smoke / Fire Dampers (FL30) 15 05-Jul-20 19-Jul-20 0% 114 Installation of VCD/ Smoke / Fir
T4-IN-HVC-FF-7490 Installation of Chilled Water Piping with Insulation (FL30) 30 18-Jun-20 17-Jul-20 0% 115 Installation of Chilled Water Pipi
T4-IN-HVC-FF-7500 Ducting Light Testing (FL30) 4 20-Jul-20 23-Jul-20 0% 114 Ducting Light Testing (FL30)
T4-IN-HVC-FF-7510 Chilled Water Piping Hydrotesting (FL30) 5 18-Jul-20 22-Jul-20 0% 115 Chilled Water Piping Hydrotest
LEVEL 31 36 18-Jun-20 23-Jul-20 114 23-Jul-20, LEVEL 31
T4-IN-HVC-FF-7520 Installation of TFA & Supply / Return Air Ducting with Insulation (FL31) 30 18-Jun-20 17-Jul-20 0% 114 Installation of TFA & Supply / Re
T4-IN-HVC-FF-7530 Installation of VCD/ Smoke / Fire Dampers (FL31) 15 05-Jul-20 19-Jul-20 0% 114 Installation of VCD/ Smoke / Fir
T4-IN-HVC-FF-7540 Installation of Chilled Water Piping with Insulation (FL31) 30 18-Jun-20 17-Jul-20 0% 115 Installation of Chilled Water Pipi
T4-IN-HVC-FF-7550 Ducting Light Testing (FL31) 4 20-Jul-20 23-Jul-20 0% 114 Ducting Light Testing (FL31)
T4-IN-HVC-FF-7560 Chilled Water Piping Hydrotesting (FL31) 5 18-Jul-20 22-Jul-20 0% 115 Chilled Water Piping Hydrotest
LEVEL 32 36 23-Jul-20 27-Aug-20 79 27-Aug-20, LEVEL 32
T4-IN-HVC-FF-7570 Installation of TFA & Supply / Return Air Ducting with Insulation (FL32) 30 23-Jul-20 21-Aug-20 0% 79 Installation of TFA & Supp
T4-IN-HVC-FF-7580 Installation of VCD/ Smoke / Fire Dampers (FL32) 15 09-Aug-20 23-Aug-20 0% 79 Installation of VCD/ Smok
T4-IN-HVC-FF-7590 Installation of Chilled Water Piping with Insulation (FL32) 30 23-Jul-20 21-Aug-20 0% 80 Installation of Chilled Wate
T4-IN-HVC-FF-7600 Ducting Light Testing (FL32) 4 24-Aug-20 27-Aug-20 0% 79 Ducting Light Testing (FL32)
T4-IN-HVC-FF-7610 Chilled Water Piping Hydrotesting (FL32) 5 22-Aug-20 26-Aug-20 0% 80 Chilled Water Piping Hyd
LEVEL 33 36 23-Jul-20 27-Aug-20 79 27-Aug-20, LEVEL 33
T4-IN-HVC-FF-7620 Installation of TFA & Supply / Return Air Ducting with Insulation (FL33) 30 23-Jul-20 21-Aug-20 0% 79 Installation of TFA & Supp
T4-IN-HVC-FF-7630 Installation of VCD/ Smoke / Fire Dampers (FL33) 15 09-Aug-20 23-Aug-20 0% 79 Installation of VCD/ Smok
T4-IN-HVC-FF-7640 Installation of Chilled Water Piping with Insulation (FL33) 30 23-Jul-20 21-Aug-20 0% 80 Installation of Chilled Wate
T4-IN-HVC-FF-7650 Ducting Light Testing (FL33) 4 24-Aug-20 27-Aug-20 0% 79 Ducting Light Testing (FL33)
T4-IN-HVC-FF-7660 Chilled Water Piping Hydrotesting (FL33) 5 22-Aug-20 26-Aug-20 0% 80 Chilled Water Piping Hyd
LEVEL 34 36 23-Jul-20 27-Aug-20 79 27-Aug-20, LEVEL 34
T4-IN-HVC-FF-7670 Installation of TFA & Supply / Return Air Ducting with Insulation (FL34) 30 23-Jul-20 21-Aug-20 0% 79 Installation of TFA & Supp
T4-IN-HVC-FF-7680 Installation of VCD/ Smoke / Fire Dampers (FL34) 15 09-Aug-20 23-Aug-20 0% 79 Installation of VCD/ Smok
T4-IN-HVC-FF-7690 Installation of Chilled Water Piping with Insulation (FL34) 30 23-Jul-20 21-Aug-20 0% 80 Installation of Chilled Wate
T4-IN-HVC-FF-7700 Ducting Light Testing (FL34) 4 24-Aug-20 27-Aug-20 0% 79 Ducting Light Testing (FL34)
T4-IN-HVC-FF-7710 Chilled Water Piping Hydrotesting (FL34) 5 22-Aug-20 26-Aug-20 0% 80 Chilled Water Piping Hyd
LEVEL 35 36 23-Jul-20 27-Aug-20 79 27-Aug-20, LEVEL 35
T4-IN-HVC-FF-7720 Installation of TFA & Supply / Return Air Ducting with Insulation (FL35) 30 23-Jul-20 21-Aug-20 0% 79 Installation of TFA & Supp
T4-IN-HVC-FF-7730 Installation of VCD/ Smoke / Fire Dampers (FL35) 15 09-Aug-20 23-Aug-20 0% 79 Installation of VCD/ Smok
T4-IN-HVC-FF-7740 Installation of Chilled Water Piping with Insulation (FL35) 30 23-Jul-20 21-Aug-20 0% 80 Installation of Chilled Wate
T4-IN-HVC-FF-7750 Ducting Light Testing (FL35) 4 24-Aug-20 27-Aug-20 0% 79 Ducting Light Testing (FL35)
T4-IN-HVC-FF-7760 Chilled Water Piping Hydrotesting (FL35) 5 22-Aug-20 26-Aug-20 0% 80 Chilled Water Piping Hyd

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 44 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
LEVEL 36 36 01-Sep-20 06-Oct-20 39 06-Oct-20, LEVEL 36
T4-IN-HVC-FF-7770 Installation of TFA & Supply / Return Air Ducting with Insulation (FL36) 30 01-Sep-20 30-Sep-20 0% 39 Installation of TFA &
T4-IN-HVC-FF-7780 Installation of VCD/ Smoke / Fire Dampers (FL36) 15 18-Sep-20 02-Oct-20 0% 39 Installation of VCD
T4-IN-HVC-FF-7790 Installation of Chilled Water Piping with Insulation (FL36) 30 01-Sep-20 30-Sep-20 0% 40 Installation of Chille
T4-IN-HVC-FF-7800 Ducting Light Testing (FL36) 4 03-Oct-20 06-Oct-20 0% 39 Ducting Light Test
T4-IN-HVC-FF-7810 Chilled Water Piping Hydrotesting (FL36) 5 01-Oct-20 05-Oct-20 0% 40 Chilled Water Pipin
LEVEL 37 36 01-Sep-20 06-Oct-20 39 06-Oct-20, LEVEL 37
T4-IN-HVC-FF-7820 Installation of TFA & Supply / Return Air Ducting with Insulation (FL37) 30 01-Sep-20 30-Sep-20 0% 39 Installation of TFA &
T4-IN-HVC-FF-7830 Installation of VCD/ Smoke / Fire Dampers (FL37) 15 18-Sep-20 02-Oct-20 0% 39 Installation of VCD
T4-IN-HVC-FF-7840 Installation of Chilled Water Piping with Insulation (FL37) 30 01-Sep-20 30-Sep-20 0% 40 Installation of Chille
T4-IN-HVC-FF-7850 Ducting Light Testing (FL37) 4 03-Oct-20 06-Oct-20 0% 39 Ducting Light Test
T4-IN-HVC-FF-7860 Chilled Water Piping Hydrotesting (FL37) 5 01-Oct-20 05-Oct-20 0% 40 Chilled Water Pipin
LEVEL 38 36 01-Sep-20 06-Oct-20 39 06-Oct-20, LEVEL 38
T4-IN-HVC-FF-7870 Installation of TFA & Supply / Return Air Ducting with Insulation (FL38) 30 01-Sep-20 30-Sep-20 0% 39 Installation of TFA &
T4-IN-HVC-FF-7880 Installation of VCD/ Smoke / Fire Dampers (FL38) 15 18-Sep-20 02-Oct-20 0% 39 Installation of VCD
T4-IN-HVC-FF-7890 Installation of Chilled Water Piping with Insulation (FL38) 30 01-Sep-20 30-Sep-20 0% 40 Installation of Chille
T4-IN-HVC-FF-7900 Ducting Light Testing (FL38) 4 03-Oct-20 06-Oct-20 0% 39 Ducting Light Test
T4-IN-HVC-FF-7910 Chilled Water Piping Hydrotesting (FL38) 5 01-Oct-20 05-Oct-20 0% 40 Chilled Water Pipin
LEVEL 39 36 01-Sep-20 06-Oct-20 39 06-Oct-20, LEVEL 39
T4-IN-HVC-FF-7920 Installation of TFA & Supply / Return Air Ducting with Insulation (FL39) 30 01-Sep-20 30-Sep-20 0% 39 Installation of TFA &
T4-IN-HVC-FF-7930 Installation of VCD/ Smoke / Fire Dampers (FL39) 15 18-Sep-20 02-Oct-20 0% 39 Installation of VCD
T4-IN-HVC-FF-7940 Installation of Chilled Water Piping with Insulation (FL39) 30 01-Sep-20 30-Sep-20 0% 40 Installation of Chille
T4-IN-HVC-FF-7950 Ducting Light Testing (FL39) 4 03-Oct-20 06-Oct-20 0% 39 Ducting Light Test
T4-IN-HVC-FF-7960 Chilled Water Piping Hydrotesting (FL39) 5 01-Oct-20 05-Oct-20 0% 40 Chilled Water Pipin
LEVEL ROOF 57 01-Sep-20 27-Oct-20 0 27-Oct-20, LE
T4-IN-HVC-FF-7970 Installation of TFA & Supply / Return Air Ducting with Insulation (ROOF) 40 01-Sep-20 10-Oct-20 0% 7 Installation of TFA
T4-IN-HVC-FF-7980 Installation of VCD/ Smoke / Fire Dampers (ROOF) 15 01-Oct-20 15-Oct-20 0% 7 Installation of VC
T4-IN-HVC-FF-7990 Installation of Chilled Water Piping with Insulation (ROOF) 50 01-Sep-20 20-Oct-20 0% 0 Installation of Ch
T4-IN-HVC-FF-8000 Ducting Light Testing (ROOF) 5 16-Oct-20 20-Oct-20 0% 7 Ducting Light Te
T4-IN-HVC-FF-8010 Chilled Water Piping Hydrotesting (ROOF) 7 21-Oct-20 27-Oct-20 0% 0 Chilled Water
VERTICAL SERVICES 340 05-Dec-19 09-Nov-20 52 09-Nov-20,
CHILLED WATER SHAFTS 340 05-Dec-19 09-Nov-20 52 09-Nov-20,
LEVEL B2 TO LEVEL P10 100 05-Dec-19 14-Mar-20 108 14-Mar-20, LEVEL B2 TO LEVEL P10
T4-IN-CHW-SFT-1210Access from Client for Chilled Water Riser Works (B2- P10) 0 05-Dec-19 0% 108 Access from Client for Chilled Water Riser Works (B2- P10)
T4-IN-CHW-SFT-1220Support Installation for Chilled Water Riser Shaft (B2- P10) 20 05-Dec-19 24-Dec-19 0% 108 Support Installation for Chilled Water Riser Shaft (B2- P10)
T4-IN-CHW-SFT-1230Installation of Chiled Water Riser Pipes & Fittings with Insulation (B2- P10) 55 26-Dec-19 18-Feb-20 0% 108 Installation of Chiled Water Riser Pipes & Fittings with Ins
T4-IN-CHW-SFT-1240Accessories Installation for Chilled Water Riser (B2- P10) 25 19-Feb-20 14-Mar-20 0% 108 Accessories Installation for Chilled Water Riser (B2- P10)
LEVEL S1 TO LEVEL 17 100 01-Feb-20 10-May-20 51 10-May-20, LEVEL S1 TO LEVEL 17
T4-IN-CHW-SFT-1255Access from Client for Chilled Water Riser Works (S1- FL17) 0 01-Feb-20 0% 51 Access from Client for Chilled Water Riser Works (S1- FL17)
T4-IN-CHW-SFT-1265Support Installation for Chilled Water Riser Shaft (S1- FL17) 20 01-Feb-20 20-Feb-20 0% 51 Support Installation for Chilled Water Riser Shaft (S1- FL17)
T4-IN-CHW-SFT-1275Installation of Chiled Water Riser Pipes & Fittings with Insulation (S1- FL17) 55 21-Feb-20 15-Apr-20 0% 51 Installation of Chiled Water Riser Pipes & Fitting
T4-IN-CHW-SFT-1285Accessories Installation for Chilled Water Riser (S1- FL17) 25 16-Apr-20 10-May-20 0% 51 Accessories Installation for Chilled Water R
LEVEL 18 TO LEVEL 27 100 15-May-20 22-Aug-20 131 22-Aug-20, LEVEL 18 TO
T4-IN-CHW-SFT-1295Access from Client for Chilled Water Riser Works (FL18 - FL27) 0 15-May-20 0% 131 Access from Client for Chilled Water Riser
T4-IN-CHW-SFT-1305Support Installation for Chilled Water Riser Shaft (FL18 - FL27) 20 15-May-20 03-Jun-20 0% 131 Support Installation for Chilled Water R
T4-IN-CHW-SFT-1315Installation of Chiled Water Riser Pipes & Fittings with Insulation (FL18 - FL27) 55 04-Jun-20 28-Jul-20 0% 131 Installation of Chiled Water Ri
T4-IN-CHW-SFT-1325Accessories Installation for Chilled Water Riser (FL18 - FL27) 25 29-Jul-20 22-Aug-20 0% 131 Accessories Installation fo
LEVEL 28 TO LEVEL 35 100 23-Jul-20 30-Oct-20 62 30-Oct-20, LE
T4-IN-CHW-SFT-1335Access from Client for Chilled Water Riser Works (FL28 - FL35) 0 23-Jul-20 0% 62 Access from Client for Chilled W
T4-IN-CHW-SFT-1345Support Installation for Chilled Water Riser Shaft (FL28 - FL35) 20 23-Jul-20 11-Aug-20 0% 62 Support Installation for Chi
T4-IN-CHW-SFT-1355Installation of Chiled Water Riser Pipes & Fittings with Insulation (FL28 - FL35) 55 12-Aug-20 05-Oct-20 0% 62 Installation of Chile
T4-IN-CHW-SFT-1365Accessories Installation for Chilled Water Riser (FL28 - FL35) 25 06-Oct-20 30-Oct-20 0% 62 Accessories In

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 45 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
LEVEL 36 TO LEVEL ROOF 70 01-Sep-20 09-Nov-20 52 09-Nov-20,
T4-IN-CHW-SFT-1375Access from Client for Chilled Water Riser Works (FL36 - ROOF) 0 01-Sep-20 0% 52 Access from Client for C
T4-IN-CHW-SFT-1385Support Installation for Chilled Water Riser Shaft (FL36 - ROOF) 15 01-Sep-20 15-Sep-20 0% 52 Support Installation fo
T4-IN-CHW-SFT-1395Installation of Chiled Water Riser Pipes & Fittings with Insulation (FL36 - ROOF) 40 16-Sep-20 25-Oct-20 0% 52 Installation of C
T4-IN-CHW-SFT-1405Accessories Installation for Chilled Water Riser (FL36 - ROOF) 15 26-Oct-20 09-Nov-20 0% 52 Accessories
DUCTING SHAFTS 340 05-Dec-19 09-Nov-20 52 09-Nov-20,
LEVEL B2 TO LEVEL P10 100 05-Dec-19 14-Mar-20 108 14-Mar-20, LEVEL B2 TO LEVEL P10
T4-IN-DCT-SFT-1410 Access from Client for Ducting Riser Works (B2- P10) 0 05-Dec-19 0% 108 Access from Client for Ducting Riser Works (B2- P10)
T4-IN-DCT-SFT-1420 Support Installation for Ducting Riser (B2- P10) 20 05-Dec-19 24-Dec-19 0% 108 Support Installation for Ducting Riser (B2- P10)
T4-IN-DCT-SFT-1430 Installation of Supply & Return Air Ducts with Insulation (B2- P10) 55 26-Dec-19 18-Feb-20 0% 108 Installation of Supply & Return Air Ducts with Insulation (B
T4-IN-DCT-SFT-1440 Accessories Installation for Ducting Riser (B2- P10) 25 19-Feb-20 14-Mar-20 0% 108 Accessories Installation for Ducting Riser (B2- P10)
LEVEL S1 TO LEVEL 17 100 01-Feb-20 10-May-20 51 10-May-20, LEVEL S1 TO LEVEL 17
T4-IN-DCT-SFT-1450 Access from Client for Ducting Riser Works (S1- FL17) 0 01-Feb-20 0% 51 Access from Client for Ducting Riser Works (S1- FL17)
T4-IN-DCT-SFT-1460 Support Installation for Ducting Riser (S1- FL17) 20 01-Feb-20 20-Feb-20 0% 51 Support Installation for Ducting Riser (S1- FL17)
T4-IN-DCT-SFT-1470 Installation of Supply & Return Air Ducts with Insulation (S1- FL17) 55 21-Feb-20 15-Apr-20 0% 51 Installation of Supply & Return Air Ducts with In
T4-IN-DCT-SFT-1480 Accessories Installation for Ducting Riser (S1- FL17) 25 16-Apr-20 10-May-20 0% 51 Accessories Installation for Ducting Riser (S
LEVEL 18 TO LEVEL 27 100 15-May-20 22-Aug-20 131 22-Aug-20, LEVEL 18 TO
T4-IN-DCT-SFT-1490 Access from Client for Ducting Riser Works (FL18 - FL27) 0 15-May-20 0% 131 Access from Client for Ducting Riser Work
T4-IN-DCT-SFT-1500 Support Installation for Ducting Riser (FL18 - FL27) 20 15-May-20 03-Jun-20 0% 131 Support Installation for Ducting Riser
T4-IN-DCT-SFT-1510 Installation of Supply & Return Air Ducts with Insulation (FL18 - FL27) 55 04-Jun-20 28-Jul-20 0% 131 Installation of Supply & Return
T4-IN-DCT-SFT-1520 Accessories Installation for Ducting Riser (FL18 - FL27) 25 29-Jul-20 22-Aug-20 0% 131 Accessories Installation fo
LEVEL 28 TO LEVEL 35 100 23-Jul-20 30-Oct-20 62 30-Oct-20, LE
T4-IN-DCT-SFT-1530 Access from Client for Ducting Riser Works (FL28 - FL35) 0 23-Jul-20 0% 62 Access from Client for Ducting
T4-IN-DCT-SFT-1540 Support Installation for Ducting Riser (FL28 - FL35) 20 23-Jul-20 11-Aug-20 0% 62 Support Installation for Duc
T4-IN-DCT-SFT-1550 Installation of Supply & Return Air Ducts with Insulation (FL28 - FL35) 55 12-Aug-20 05-Oct-20 0% 62 Installation of Supp
T4-IN-DCT-SFT-1560 Accessories Installation for Ducting Riser (FL28 - FL35) 25 06-Oct-20 30-Oct-20 0% 62 Accessories In
LEVEL 36 TO LEVEL ROOF 70 01-Sep-20 09-Nov-20 52 09-Nov-20,
T4-IN-DCT-SFT-1570 Access from Client for Ducting Riser Works (FL36 - ROOF) 0 01-Sep-20 0% 52 Access from Client for D
T4-IN-DCT-SFT-1580 Support Installation for Ducting Riser (FL36 - ROOF) 15 01-Sep-20 15-Sep-20 0% 52 Support Installation fo
T4-IN-DCT-SFT-1590 Installation of Supply & Return Air Ducts with Insulation (FL36 - ROOF) 40 16-Sep-20 25-Oct-20 0% 52 Installation of S
T4-IN-DCT-SFT-1600 Accessories Installation for Ducting Riser (FL36 - ROOF) 15 26-Oct-20 09-Nov-20 0% 52 Accessories
EQUIPMENT INSTALLATION 386 15-Oct-19 06-Nov-20 55 06-Nov-20, E
JET / PROPELLER / AXIAL FANS 298 13-Jan-20 06-Nov-20 55 06-Nov-20, J
T4-IN-HVC-FF-9130 Installation of Jet Fans/ Vane Axial / Propeller Fans at B2 45 14-Feb-20 29-Mar-20 0% 93 Installation of Jet Fans/ Vane Axial / Propeller Fan
T4-IN-HVC-FF-9140 Installation of Jet Fans/ Vane Axial / Propeller Fans at B1 45 15-Feb-20 31-Mar-20 0% 91 Installation of Jet Fans/ Vane Axial / Propeller Fan
T4-IN-HVC-FF-9150 Installation of Jet Fans/ Vane Axial / Propeller Fans at P0 5 13-Jan-20 18-Jan-20 0% 164 Installation of Jet Fans/ Vane Axial / Propeller Fans at P0
T4-IN-HVC-FF-9160 Installation of Jet Fans/ Vane Axial / Propeller Fans at P3 5 13-Jan-20 18-Jan-20 0% 164 Installation of Jet Fans/ Vane Axial / Propeller Fans at P3
T4-IN-HVC-FF-9170 Installation of Jet Fans/ Vane Axial / Propeller Fans at S1 35 15-Feb-20 21-Mar-20 0% 101 Installation of Jet Fans/ Vane Axial / Propeller Fans at S1
T4-IN-HVC-FF-9180 Installation of Jet Fans/ Vane Axial / Propeller Fans at FL22 10 07-May-20 16-May-20 0% 45 Installation of Jet Fans/ Vane Axial / Prope
T4-IN-HVC-FF-9190 Installation of Jet Fans/ Vane Axial / Propeller Fans at ROOF 10 28-Oct-20 06-Nov-20 0% 55 Installation of
AHU & CSU 380 15-Oct-19 31-Oct-20 27 31-Oct-20, AH
T4-IN-HVC-FF-9195 Installation & allignment of AHU's & associated Piping at P2 4 04-Nov-19 08-Nov-19 0% 31 Installation & allignment of AHU's & associated Piping at P2
T4-IN-HVC-FF-9200 Installation & allignment of AHU's & associated Piping at FL17 4 10-May-20 14-May-20 0% 0 Installation & allignment of AHU's & associ
T4-IN-HVC-FF-9210 Installation & allignment of AHU's & associated Piping at FL18 4 16-May-20 19-May-20 0% 191 Installation & allignment of AHU's & assoc
T4-IN-HVC-FF-9220 Installation & allignment of AHU's & associated Piping at FL19 4 16-May-20 19-May-20 0% 191 Installation & allignment of AHU's & assoc
T4-IN-HVC-FF-9230 Installation & allignment of AHU's & associated Piping at FL20 4 16-May-20 19-May-20 0% 191 Installation & allignment of AHU's & assoc
T4-IN-HVC-FF-9240 Installation & allignment of AHU's & associated Piping at FL21 4 16-May-20 19-May-20 0% 191 Installation & allignment of AHU's & assoc
T4-IN-HVC-FF-9250 Installation & allignment of AHU's & associated Piping at FL22 4 07-May-20 10-May-20 0% 191 Installation & allignment of AHU's & associa
T4-IN-HVC-FF-9260 Installation & allignment of AHU's & associated Piping at FL23 4 19-Jun-20 22-Jun-20 0% 158 Installation & allignment of AHU's &
T4-IN-HVC-FF-9270 Installation & allignment of AHU's & associated Piping at FL24 4 19-Jun-20 22-Jun-20 0% 150 Installation & allignment of AHU's &
T4-IN-HVC-FF-9280 Installation & allignment of AHU's & associated Piping at FL25 4 19-Jun-20 22-Jun-20 0% 158 Installation & allignment of AHU's &
T4-IN-HVC-FF-9290 Installation & allignment of AHU's & associated Piping at FL26 4 19-Jun-20 22-Jun-20 0% 158 Installation & allignment of AHU's &

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 46 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-HVC-FF-9300 Installation & allignment of AHU's & associated Piping at FL27 4 19-Jun-20 22-Jun-20 0% 158 Installation & allignment of AHU's &
T4-IN-HVC-FF-9310 Installation & allignment of AHU's & associated Piping at FL28 4 23-Jul-20 26-Jul-20 0% 124 Installation & allignment of AH
T4-IN-HVC-FF-9320 Installation & allignment of AHU's & associated Piping at FL29 4 23-Jul-20 26-Jul-20 0% 124 Installation & allignment of AH
T4-IN-HVC-FF-9330 Installation & allignment of AHU's & associated Piping at FL30 4 23-Jul-20 26-Jul-20 0% 124 Installation & allignment of AH
T4-IN-HVC-FF-9340 Installation & allignment of AHU's & associated Piping at FL31 4 23-Jul-20 26-Jul-20 0% 119 Installation & allignment of AH
T4-IN-HVC-FF-9350 Installation & allignment of AHU's & associated Piping at FL32 4 27-Aug-20 30-Aug-20 0% 84 Installation & allignment
T4-IN-HVC-FF-9360 Installation & allignment of AHU's & associated Piping at FL33 4 27-Aug-20 30-Aug-20 0% 89 Installation & allignment
T4-IN-HVC-FF-9370 Installation & allignment of AHU's & associated Piping at FL34 4 27-Aug-20 30-Aug-20 0% 89 Installation & allignment
T4-IN-HVC-FF-9380 Installation & allignment of AHU's & associated Piping at FL35 4 27-Aug-20 30-Aug-20 0% 89 Installation & allignment
T4-IN-HVC-FF-9390 Installation & allignment of AHU's & associated Piping at FL36 4 06-Oct-20 09-Oct-20 0% 44 Installation & allign
T4-IN-HVC-FF-9400 Installation & allignment of AHU's & associated Piping at FL37 4 06-Oct-20 09-Oct-20 0% 49 Installation & allign
T4-IN-HVC-FF-9410 Installation & allignment of AHU's & associated Piping at FL38 4 06-Oct-20 09-Oct-20 0% 44 Installation & allign
T4-IN-HVC-FF-9420 Installation & allignment of AHU's & associated Piping at FL39 4 06-Oct-20 09-Oct-20 0% 49 Installation & allign
T4-IN-HVC-FF-9430 Installation & allignment of CSU's & associated Piping at B1 4 22-Jan-20 25-Jan-20 0% 118 Installation & allignment of CSU's & associated Piping at B1
T4-IN-HVC-FF-9440 Installation & allignment of CSU's & associated Piping at P2 4 15-Oct-19 18-Oct-19 0% 55 Installation & allignment of CSU's & associated Piping at P2
T4-IN-HVC-FF-9450 Installation & allignment of CSU's & associated Piping at FL09 4 07-Jan-20 11-Jan-20 0% 140 Installation & allignment of CSU's & associated Piping at FL09
T4-IN-HVC-FF-9460 Installation & allignment of CSU's & associated Piping at FL17 4 12-Mar-20 15-Mar-20 0% 60 Installation & allignment of CSU's & associated Pipin
T4-IN-HVC-FF-9470 Installation & allignment of CSU's & associated Piping at FL22 4 07-May-20 10-May-20 0% 201 Installation & allignment of CSU's & associa
T4-IN-HVC-FF-9480 Installation & allignment of CSU's & associated Piping at FL24 4 19-Jun-20 22-Jun-20 0% 155 Installation & allignment of CSU's &
T4-IN-HVC-FF-9490 Installation & allignment of CSU's & associated Piping at FL31 4 23-Jul-20 26-Jul-20 0% 124 Installation & allignment of CS
T4-IN-HVC-FF-9500 Installation & allignment of CSU's & associated Piping at FL32 4 27-Aug-20 30-Aug-20 0% 89 Installation & allignment
T4-IN-HVC-FF-9510 Installation & allignment of CSU's & associated Piping at FL36 4 06-Oct-20 09-Oct-20 0% 49 Installation & allign
T4-IN-HVC-FF-9520 Installation & allignment of CSU's & associated Piping at FL38 4 06-Oct-20 09-Oct-20 0% 49 Installation & allign
T4-IN-HVC-FF-9530 Installation & allignment of CSU's & associated Piping at ROOF 4 28-Oct-20 31-Oct-20 0% 10 Installation & a
ELECTRICAL 425 23-Aug-19 27-Oct-20 65 27-Oct-20, EL
HORIZONTAL SERVICES 425 23-Aug-19 27-Oct-20 18 27-Oct-20, HO
LEVEL B2 62 15-Dec-19 15-Feb-20 77 15-Feb-20, LEVEL B2
T4-IN-ELE-FF-8020 Installation of PVC/GI Conduit & Backbox (B2) 30 15-Dec-19 14-Jan-20 0% 77 Installation of PVC/GI Conduit & Backbox (B2)
T4-IN-ELE-FF-8030 Installation of GI/ MS Earthing Strip & Earthing Wire (B2) 30 30-Dec-19 28-Jan-20 0% 77 Installation of GI/ MS Earthing Strip & Earthing Wire (B2)
T4-IN-ELE-FF-8040 Installation of Cable Trays & Trunking (B2) 45 02-Jan-20 15-Feb-20 0% 77 Installation of Cable Trays & Trunking (B2)
LEVEL B1 64 22-Nov-19 25-Jan-20 89 25-Jan-20, LEVEL B1
T4-IN-ELE-FF-8050 Installation of PVC/GI Conduit & Backbox (B1) 35 22-Nov-19 27-Dec-19 0% 89 Installation of PVC/GI Conduit & Backbox (B1)
T4-IN-ELE-FF-8060 Installation of GI/ MS Earthing Strip & Earthing Wire (B1) 35 07-Dec-19 11-Jan-20 0% 89 Installation of GI/ MS Earthing Strip & Earthing Wire (B1)
T4-IN-ELE-FF-8070 Installation of Cable Trays & Trunking (B1) 45 11-Dec-19 25-Jan-20 0% 89 Installation of Cable Trays & Trunking (B1)
LEVEL P0 30 15-Oct-19 15-Nov-19 172 15-Nov-19, LEVEL P0
T4-IN-ELE-FF-8080 Installation of PVC/GI Conduit & Backbox (P0) 20 15-Oct-19 04-Nov-19 0% 172 Installation of PVC/GI Conduit & Backbox (P0)
T4-IN-ELE-FF-8090 Installation of GI/ MS Earthing Strip & Earthing Wire (P0) 14 22-Oct-19 05-Nov-19 0% 172 Installation of GI/ MS Earthing Strip & Earthing Wire (P0)
T4-IN-ELE-FF-8100 Installation of Cable Trays & Trunking (P0) 20 25-Oct-19 15-Nov-19 0% 172 Installation of Cable Trays & Trunking (P0)
LEVEL P1 19 30-Sep-19 20-Oct-19 206 20-Oct-19, LEVEL P1
T4-IN-ELE-FF-8110 Installation of PVC/GI Conduit & Backbox (P1) 15 30-Sep-19 16-Oct-19 0% 206 Installation of PVC/GI Conduit & Backbox (P1)
T4-IN-ELE-FF-8120 Installation of GI/ MS Earthing Strip & Earthing Wire (P1) 14 30-Sep-19 15-Oct-19 0% 206 Installation of GI/ MS Earthing Strip & Earthing Wire (P1)
T4-IN-ELE-FF-8130 Installation of Cable Trays & Trunking (P1) 15 05-Oct-19 20-Oct-19 0% 206 Installation of Cable Trays & Trunking (P1)
LEVEL P2 48 31-Aug-19 20-Oct-19 41 20-Oct-19, LEVEL P2
T4-IN-ELE-FF-8140 Installation of PVC/GI Conduit & Backbox (P2) 30 31-Aug-19 30-Sep-19 0% 41 Installation of PVC/GI Conduit & Backbox (P2)
T4-IN-ELE-FF-8150 Installation of GI/ MS Earthing Strip & Earthing Wire (P2) 21 08-Sep-19 28-Sep-19 0% 41 Installation of GI/ MS Earthing Strip & Earthing Wire (P2)
T4-IN-ELE-FF-8160 Installation of Cable Trays & Trunking (P2) 30 19-Sep-19 20-Oct-19 0% 41 Installation of Cable Trays & Trunking (P2)
LEVEL P3 29 14-Oct-19 13-Nov-19 182 13-Nov-19, LEVEL P3
T4-IN-ELE-FF-8170 Installation of PVC/GI Conduit & Backbox (P3) 20 14-Oct-19 03-Nov-19 0% 182 Installation of PVC/GI Conduit & Backbox (P3)
T4-IN-ELE-FF-8180 Installation of GI/ MS Earthing Strip & Earthing Wire (P3) 14 21-Oct-19 04-Nov-19 0% 182 Installation of GI/ MS Earthing Strip & Earthing Wire (P3)
T4-IN-ELE-FF-8190 Installation of Cable Trays & Trunking (P3) 14 30-Oct-19 13-Nov-19 0% 182 Installation of Cable Trays & Trunking (P3)
LEVEL P4 29 14-Oct-19 13-Nov-19 182 13-Nov-19, LEVEL P4
T4-IN-ELE-FF-8200 Installation of PVC/GI Conduit & Backbox (P4) 20 14-Oct-19 03-Nov-19 0% 182 Installation of PVC/GI Conduit & Backbox (P4)

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 47 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-ELE-FF-8210 Installation of GI/ MS Earthing Strip & Earthing Wire (P4) 14 21-Oct-19 04-Nov-19 0% 182 Installation of GI/ MS Earthing Strip & Earthing Wire (P4)
T4-IN-ELE-FF-8220 Installation of Cable Trays & Trunking (P4) 14 30-Oct-19 13-Nov-19 0% 182 Installation of Cable Trays & Trunking (P4)
LEVEL P5 29 14-Oct-19 13-Nov-19 182 13-Nov-19, LEVEL P5
T4-IN-ELE-FF-8230 Installation of PVC/GI Conduit & Backbox (P5) 20 14-Oct-19 03-Nov-19 0% 182 Installation of PVC/GI Conduit & Backbox (P5)
T4-IN-ELE-FF-8240 Installation of GI/ MS Earthing Strip & Earthing Wire (P5) 14 21-Oct-19 04-Nov-19 0% 182 Installation of GI/ MS Earthing Strip & Earthing Wire (P5)
T4-IN-ELE-FF-8250 Installation of Cable Trays & Trunking (P5) 14 30-Oct-19 13-Nov-19 0% 182 Installation of Cable Trays & Trunking (P5)
LEVEL P6 29 14-Oct-19 13-Nov-19 182 13-Nov-19, LEVEL P6
T4-IN-ELE-FF-8260 Installation of PVC/GI Conduit & Backbox (P6) 20 14-Oct-19 03-Nov-19 0% 182 Installation of PVC/GI Conduit & Backbox (P6)
T4-IN-ELE-FF-8270 Installation of GI/ MS Earthing Strip & Earthing Wire (P6) 14 21-Oct-19 04-Nov-19 0% 182 Installation of GI/ MS Earthing Strip & Earthing Wire (P6)
T4-IN-ELE-FF-8280 Installation of Cable Trays & Trunking (P6) 14 30-Oct-19 13-Nov-19 0% 182 Installation of Cable Trays & Trunking (P6)
LEVEL P7 35 07-Nov-19 12-Dec-19 154 12-Dec-19, LEVEL P7
T4-IN-ELE-FF-8290 Installation of PVC/GI Conduit & Backbox (P7) 20 07-Nov-19 27-Nov-19 0% 154 Installation of PVC/GI Conduit & Backbox (P7)
T4-IN-ELE-FF-8300 Installation of GI/ MS Earthing Strip & Earthing Wire (P7) 14 15-Nov-19 28-Nov-19 0% 154 Installation of GI/ MS Earthing Strip & Earthing Wire (P7)
T4-IN-ELE-FF-8310 Installation of Cable Trays & Trunking (P7) 14 29-Nov-19 12-Dec-19 0% 154 Installation of Cable Trays & Trunking (P7)
LEVEL P8 35 07-Nov-19 12-Dec-19 154 12-Dec-19, LEVEL P8
T4-IN-ELE-FF-8320 Installation of PVC/GI Conduit & Backbox (P8) 20 07-Nov-19 27-Nov-19 0% 154 Installation of PVC/GI Conduit & Backbox (P8)
T4-IN-ELE-FF-8330 Installation of GI/ MS Earthing Strip & Earthing Wire (P8) 14 15-Nov-19 28-Nov-19 0% 154 Installation of GI/ MS Earthing Strip & Earthing Wire (P8)
T4-IN-ELE-FF-8340 Installation of Cable Trays & Trunking (P8) 14 29-Nov-19 12-Dec-19 0% 154 Installation of Cable Trays & Trunking (P8)
LEVEL P9 28 05-Dec-19 02-Jan-20 133 02-Jan-20, LEVEL P9
T4-IN-ELE-FF-8350 Installation of PVC/GI Conduit & Backbox (P9) 20 05-Dec-19 24-Dec-19 0% 133 Installation of PVC/GI Conduit & Backbox (P9)
T4-IN-ELE-FF-8360 Installation of GI/ MS Earthing Strip & Earthing Wire (P9) 14 12-Dec-19 26-Dec-19 0% 133 Installation of GI/ MS Earthing Strip & Earthing Wire (P9)
T4-IN-ELE-FF-8370 Installation of Cable Trays & Trunking (P9) 14 19-Dec-19 02-Jan-20 0% 133 Installation of Cable Trays & Trunking (P9)
LEVEL P10 28 05-Dec-19 02-Jan-20 133 02-Jan-20, LEVEL P10
T4-IN-ELE-FF-8380 Installation of PVC/GI Conduit & Backbox (P10) 20 05-Dec-19 24-Dec-19 0% 133 Installation of PVC/GI Conduit & Backbox (P10)
T4-IN-ELE-FF-8390 Installation of GI/ MS Earthing Strip & Earthing Wire (P10) 14 12-Dec-19 26-Dec-19 0% 133 Installation of GI/ MS Earthing Strip & Earthing Wire (P10)
T4-IN-ELE-FF-8400 Installation of Cable Trays & Trunking (P10) 14 19-Dec-19 02-Jan-20 0% 133 Installation of Cable Trays & Trunking (P10)
LEVEL S1 57 23-Aug-19 22-Oct-19 217 22-Oct-19, LEVEL S1
T4-IN-ELE-FF-9130 Installation of PVC/GI Conduit & Backbox (S1) 45 23-Aug-19 10-Oct-19 0% 217 Installation of PVC/GI Conduit & Backbox (S1)
T4-IN-ELE-FF-9140 Installation of GI/ MS Earthing Strip & Earthing Wire (S1) 35 30-Aug-19 06-Oct-19 0% 217 Installation of GI/ MS Earthing Strip & Earthing Wire (S1)
T4-IN-ELE-FF-9150 Installation of Cable Trays & Trunking (S1) 45 05-Sep-19 22-Oct-19 0% 217 Installation of Cable Trays & Trunking (S1)
LEVEL 17 41 01-Feb-20 12-Mar-20 34 12-Mar-20, LEVEL 17
T4-IN-ELE-FF-8410 Installation of PVC/GI Conduit & Backbox (FL17) 21 01-Feb-20 21-Feb-20 0% 34 Installation of PVC/GI Conduit & Backbox (FL17)
T4-IN-ELE-FF-8420 Installation of GI/ MS Earthing Strip & Earthing Wire (FL17) 14 08-Feb-20 21-Feb-20 0% 34 Installation of GI/ MS Earthing Strip & Earthing Wire (FL17)
T4-IN-ELE-FF-8430 Installation of Cable Trays & Trunking (FL17) 21 21-Feb-20 12-Mar-20 0% 34 Installation of Cable Trays & Trunking (FL17)
LEVEL 18 36 11-Apr-20 16-May-20 182 16-May-20, LEVEL 18
T4-IN-ELE-FF-8440 Installation of PVC/GI Conduit & Backbox (FL18) 20 11-Apr-20 30-Apr-20 0% 182 Installation of PVC/GI Conduit & Backbox (FL18)
T4-IN-ELE-FF-8450 Installation of GI/ MS Earthing Strip & Earthing Wire (FL18) 14 18-Apr-20 01-May-20 0% 182 Installation of GI/ MS Earthing Strip & Earthin
T4-IN-ELE-FF-8460 Installation of Cable Trays & Trunking (FL18) 14 03-May-20 16-May-20 0% 182 Installation of Cable Trays & Trunking (FL18)
LEVEL 19 36 11-Apr-20 16-May-20 182 16-May-20, LEVEL 19
T4-IN-ELE-FF-8470 Installation of PVC/GI Conduit & Backbox (FL19) 20 11-Apr-20 30-Apr-20 0% 182 Installation of PVC/GI Conduit & Backbox (FL19)
T4-IN-ELE-FF-8480 Installation of GI/ MS Earthing Strip & Earthing Wire (FL19) 14 18-Apr-20 01-May-20 0% 182 Installation of GI/ MS Earthing Strip & Earthin
T4-IN-ELE-FF-8490 Installation of Cable Trays & Trunking (FL19) 14 03-May-20 16-May-20 0% 182 Installation of Cable Trays & Trunking (FL19)
LEVEL 20 36 11-Apr-20 16-May-20 182 16-May-20, LEVEL 20
T4-IN-ELE-FF-8500 Installation of PVC/GI Conduit & Backbox (FL20) 20 11-Apr-20 30-Apr-20 0% 182 Installation of PVC/GI Conduit & Backbox (FL20)
T4-IN-ELE-FF-8510 Installation of GI/ MS Earthing Strip & Earthing Wire (FL20) 14 18-Apr-20 01-May-20 0% 182 Installation of GI/ MS Earthing Strip & Earthin
T4-IN-ELE-FF-8520 Installation of Cable Trays & Trunking (FL20) 20 27-Apr-20 16-May-20 0% 182 Installation of Cable Trays & Trunking (FL20)
LEVEL 21 36 11-Apr-20 16-May-20 182 16-May-20, LEVEL 21
T4-IN-ELE-FF-8530 Installation of PVC/GI Conduit & Backbox (FL21) 20 11-Apr-20 30-Apr-20 0% 182 Installation of PVC/GI Conduit & Backbox (FL21)
T4-IN-ELE-FF-8540 Installation of GI/ MS Earthing Strip & Earthing Wire (FL21) 14 18-Apr-20 01-May-20 0% 182 Installation of GI/ MS Earthing Strip & Earthin
T4-IN-ELE-FF-8550 Installation of Cable Trays & Trunking (FL21) 20 27-Apr-20 16-May-20 0% 182 Installation of Cable Trays & Trunking (FL21)
LEVEL 22 52 27-Mar-20 17-May-20 25 17-May-20, LEVEL 22
T4-IN-ELE-FF-8560 Installation of PVC/GI Conduit & Backbox (FL22) 35 27-Mar-20 30-Apr-20 0% 25 Installation of PVC/GI Conduit & Backbox (FL22)

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 48 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-ELE-FF-8570 Installation of GI/ MS Earthing Strip & Earthing Wire (FL22) 30 03-Apr-20 02-May-20 0% 25 Installation of GI/ MS Earthing Strip & Earthi
T4-IN-ELE-FF-8580 Installation of Cable Trays & Trunking (FL22) 35 13-Apr-20 17-May-20 0% 25 Installation of Cable Trays & Trunking (FL22)
LEVEL 23 36 15-May-20 19-Jun-20 148 19-Jun-20, LEVEL 23
T4-IN-ELE-FF-8590 Installation of PVC/GI Conduit & Backbox (FL23) 20 15-May-20 03-Jun-20 0% 148 Installation of PVC/GI Conduit & Backb
T4-IN-ELE-FF-8600 Installation of GI/ MS Earthing Strip & Earthing Wire (FL23) 14 22-May-20 04-Jun-20 0% 148 Installation of GI/ MS Earthing Strip & E
T4-IN-ELE-FF-8610 Installation of Cable Trays & Trunking (FL23) 20 31-May-20 19-Jun-20 0% 148 Installation of Cable Trays & Trunkin
LEVEL 24 36 15-May-20 19-Jun-20 148 19-Jun-20, LEVEL 24
T4-IN-ELE-FF-8620 Installation of PVC/GI Conduit & Backbox (FL24) 20 15-May-20 03-Jun-20 0% 148 Installation of PVC/GI Conduit & Backb
T4-IN-ELE-FF-8630 Installation of GI/ MS Earthing Strip & Earthing Wire (FL24) 14 22-May-20 04-Jun-20 0% 148 Installation of GI/ MS Earthing Strip & E
T4-IN-ELE-FF-8640 Installation of Cable Trays & Trunking (FL24) 20 31-May-20 19-Jun-20 0% 148 Installation of Cable Trays & Trunkin
LEVEL 25 36 15-May-20 19-Jun-20 148 19-Jun-20, LEVEL 25
T4-IN-ELE-FF-8650 Installation of PVC/GI Conduit & Backbox (FL25) 20 15-May-20 03-Jun-20 0% 148 Installation of PVC/GI Conduit & Backb
T4-IN-ELE-FF-8660 Installation of GI/ MS Earthing Strip & Earthing Wire (FL25) 14 22-May-20 04-Jun-20 0% 148 Installation of GI/ MS Earthing Strip & E
T4-IN-ELE-FF-8670 Installation of Cable Trays & Trunking (FL25) 20 31-May-20 19-Jun-20 0% 148 Installation of Cable Trays & Trunkin
LEVEL 26 36 15-May-20 19-Jun-20 148 19-Jun-20, LEVEL 26
T4-IN-ELE-FF-8680 Installation of PVC/GI Conduit & Backbox (FL26) 20 15-May-20 03-Jun-20 0% 148 Installation of PVC/GI Conduit & Backb
T4-IN-ELE-FF-8690 Installation of GI/ MS Earthing Strip & Earthing Wire (FL26) 14 22-May-20 04-Jun-20 0% 148 Installation of GI/ MS Earthing Strip & E
T4-IN-ELE-FF-8700 Installation of Cable Trays & Trunking (FL26) 20 31-May-20 19-Jun-20 0% 148 Installation of Cable Trays & Trunkin
LEVEL 27 36 15-May-20 19-Jun-20 148 19-Jun-20, LEVEL 27
T4-IN-ELE-FF-8710 Installation of PVC/GI Conduit & Backbox (FL27) 20 15-May-20 03-Jun-20 0% 148 Installation of PVC/GI Conduit & Backb
T4-IN-ELE-FF-8720 Installation of GI/ MS Earthing Strip & Earthing Wire (FL27) 14 22-May-20 04-Jun-20 0% 148 Installation of GI/ MS Earthing Strip & E
T4-IN-ELE-FF-8730 Installation of Cable Trays & Trunking (FL27) 20 31-May-20 19-Jun-20 0% 148 Installation of Cable Trays & Trunkin
LEVEL 28 36 18-Jun-20 23-Jul-20 114 23-Jul-20, LEVEL 28
T4-IN-ELE-FF-8740 Installation of PVC/GI Conduit & Backbox (FL28) 20 18-Jun-20 07-Jul-20 0% 114 Installation of PVC/GI Conduit & B
T4-IN-ELE-FF-8750 Installation of GI/ MS Earthing Strip & Earthing Wire (FL28) 14 25-Jun-20 08-Jul-20 0% 114 Installation of GI/ MS Earthing Str
T4-IN-ELE-FF-8760 Installation of Cable Trays & Trunking (FL28) 20 04-Jul-20 23-Jul-20 0% 114 Installation of Cable Trays & Tr
LEVEL 29 36 18-Jun-20 23-Jul-20 114 23-Jul-20, LEVEL 29
T4-IN-ELE-FF-8770 Installation of PVC/GI Conduit & Backbox (FL29) 20 18-Jun-20 07-Jul-20 0% 114 Installation of PVC/GI Conduit & B
T4-IN-ELE-FF-8780 Installation of GI/ MS Earthing Strip & Earthing Wire (FL29) 14 25-Jun-20 08-Jul-20 0% 114 Installation of GI/ MS Earthing Str
T4-IN-ELE-FF-8790 Installation of Cable Trays & Trunking (FL29) 20 04-Jul-20 23-Jul-20 0% 114 Installation of Cable Trays & Tr
LEVEL 30 36 18-Jun-20 23-Jul-20 114 23-Jul-20, LEVEL 30
T4-IN-ELE-FF-8800 Installation of PVC/GI Conduit & Backbox (FL30) 20 18-Jun-20 07-Jul-20 0% 114 Installation of PVC/GI Conduit & B
T4-IN-ELE-FF-8810 Installation of GI/ MS Earthing Strip & Earthing Wire (FL30) 14 25-Jun-20 08-Jul-20 0% 114 Installation of GI/ MS Earthing Str
T4-IN-ELE-FF-8820 Installation of Cable Trays & Trunking (FL30) 20 04-Jul-20 23-Jul-20 0% 114 Installation of Cable Trays & Tr
LEVEL 31 36 18-Jun-20 23-Jul-20 114 23-Jul-20, LEVEL 31
T4-IN-ELE-FF-8830 Installation of PVC/GI Conduit & Backbox (FL31) 20 18-Jun-20 07-Jul-20 0% 114 Installation of PVC/GI Conduit & B
T4-IN-ELE-FF-8840 Installation of GI/ MS Earthing Strip & Earthing Wire (FL31) 14 25-Jun-20 08-Jul-20 0% 114 Installation of GI/ MS Earthing Str
T4-IN-ELE-FF-8850 Installation of Cable Trays & Trunking (FL31) 20 04-Jul-20 23-Jul-20 0% 114 Installation of Cable Trays & Tr
LEVEL 32 36 23-Jul-20 27-Aug-20 79 27-Aug-20, LEVEL 32
T4-IN-ELE-FF-8860 Installation of PVC/GI Conduit & Backbox (FL32) 20 23-Jul-20 11-Aug-20 0% 79 Installation of PVC/GI Cond
T4-IN-ELE-FF-8870 Installation of GI/ MS Earthing Strip & Earthing Wire (FL32) 14 30-Jul-20 12-Aug-20 0% 79 Installation of GI/ MS Earth
T4-IN-ELE-FF-8880 Installation of Cable Trays & Trunking (FL32) 20 08-Aug-20 27-Aug-20 0% 79 Installation of Cable Tray
LEVEL 33 36 23-Jul-20 27-Aug-20 79 27-Aug-20, LEVEL 33
T4-IN-ELE-FF-8890 Installation of PVC/GI Conduit & Backbox (FL33) 20 23-Jul-20 11-Aug-20 0% 79 Installation of PVC/GI Cond
T4-IN-ELE-FF-8900 Installation of GI/ MS Earthing Strip & Earthing Wire (FL33) 14 30-Jul-20 12-Aug-20 0% 79 Installation of GI/ MS Earth
T4-IN-ELE-FF-8910 Installation of Cable Trays & Trunking (FL33) 20 08-Aug-20 27-Aug-20 0% 79 Installation of Cable Tray
LEVEL 34 36 23-Jul-20 27-Aug-20 79 27-Aug-20, LEVEL 34
T4-IN-ELE-FF-8920 Installation of PVC/GI Conduit & Backbox (FL34) 20 23-Jul-20 11-Aug-20 0% 79 Installation of PVC/GI Cond
T4-IN-ELE-FF-8930 Installation of GI/ MS Earthing Strip & Earthing Wire (FL34) 14 30-Jul-20 12-Aug-20 0% 79 Installation of GI/ MS Earth
T4-IN-ELE-FF-8940 Installation of Cable Trays & Trunking (FL34) 20 08-Aug-20 27-Aug-20 0% 79 Installation of Cable Tray
LEVEL 35 36 23-Jul-20 27-Aug-20 79 27-Aug-20, LEVEL 35
T4-IN-ELE-FF-8950 Installation of PVC/GI Conduit & Backbox (FL35) 20 23-Jul-20 11-Aug-20 0% 79 Installation of PVC/GI Cond

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 49 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-ELE-FF-8960 Installation of GI/ MS Earthing Strip & Earthing Wire (FL35) 14 30-Jul-20 12-Aug-20 0% 79 Installation of GI/ MS Earth
T4-IN-ELE-FF-8970 Installation of Cable Trays & Trunking (FL35) 20 08-Aug-20 27-Aug-20 0% 79 Installation of Cable Tray
LEVEL 36 36 01-Sep-20 06-Oct-20 39 06-Oct-20, LEVEL 36
T4-IN-ELE-FF-8980 Installation of PVC/GI Conduit & Backbox (FL36) 20 01-Sep-20 20-Sep-20 0% 39 Installation of PVC/G
T4-IN-ELE-FF-8990 Installation of GI/ MS Earthing Strip & Earthing Wire (FL36) 14 08-Sep-20 21-Sep-20 0% 39 Installation of GI/ MS
T4-IN-ELE-FF-9000 Installation of Cable Trays & Trunking (FL36) 20 17-Sep-20 06-Oct-20 0% 39 Installation of Cab
LEVEL 37 36 01-Sep-20 06-Oct-20 39 06-Oct-20, LEVEL 37
T4-IN-ELE-FF-9010 Installation of PVC/GI Conduit & Backbox (FL37) 20 01-Sep-20 20-Sep-20 0% 39 Installation of PVC/G
T4-IN-ELE-FF-9020 Installation of GI/ MS Earthing Strip & Earthing Wire (FL37) 14 08-Sep-20 21-Sep-20 0% 39 Installation of GI/ MS
T4-IN-ELE-FF-9030 Installation of Cable Trays & Trunking (FL37) 20 17-Sep-20 06-Oct-20 0% 39 Installation of Cab
LEVEL 38 36 01-Sep-20 06-Oct-20 39 06-Oct-20, LEVEL 38
T4-IN-ELE-FF-9040 Installation of PVC/GI Conduit & Backbox (FL38) 20 01-Sep-20 20-Sep-20 0% 39 Installation of PVC/G
T4-IN-ELE-FF-9050 Installation of GI/ MS Earthing Strip & Earthing Wire (FL38) 14 08-Sep-20 21-Sep-20 0% 39 Installation of GI/ MS
T4-IN-ELE-FF-9060 Installation of Cable Trays & Trunking (FL38) 20 17-Sep-20 06-Oct-20 0% 39 Installation of Cab
LEVEL 39 36 01-Sep-20 06-Oct-20 39 06-Oct-20, LEVEL 39
T4-IN-ELE-FF-9070 Installation of PVC/GI Conduit & Backbox (FL39) 20 01-Sep-20 20-Sep-20 0% 39 Installation of PVC/G
T4-IN-ELE-FF-9080 Installation of GI/ MS Earthing Strip & Earthing Wire (FL39) 14 08-Sep-20 21-Sep-20 0% 39 Installation of GI/ MS
T4-IN-ELE-FF-9090 Installation of Cable Trays & Trunking (FL39) 20 17-Sep-20 06-Oct-20 0% 39 Installation of Cab
LEVEL ROOF 57 01-Sep-20 27-Oct-20 0 27-Oct-20, LE
T4-IN-ELE-FF-9100 Installation of PVC/GI Conduit & Backbox (ROOF) 45 01-Sep-20 15-Oct-20 0% 0 Installation of PV
T4-IN-ELE-FF-9110 Installation of GI/ MS Earthing Strip & Earthing Wire (ROOF) 35 08-Sep-20 12-Oct-20 0% 0 Installation of GI/
T4-IN-ELE-FF-9120 Installation of Cable Trays & Trunking (ROOF) 45 13-Sep-20 27-Oct-20 0% 0 Installation of C
VERTICAL SERVICES 325 05-Dec-19 25-Oct-20 67 25-Oct-20, VER
LEVEL B2 TO LEVEL P10 55 05-Dec-19 29-Jan-20 153 29-Jan-20, LEVEL B2 TO LEVEL P10
T4-IN-ELE-SFT-1610 Access from Client for Electrical Shaft Works (B2 - P10) 0 05-Dec-19 0% 153 Access from Client for Electrical Shaft Works (B2 - P10)
T4-IN-ELE-SFT-1620 Installation of Supports (B2 - P10) 15 05-Dec-19 19-Dec-19 0% 153 Installation of Supports (B2 - P10)
T4-IN-ELE-SFT-1630 Install Cable Trays & Ladders (B2 - P10) 25 20-Dec-19 14-Jan-20 0% 153 Install Cable Trays & Ladders (B2 - P10)
T4-IN-ELE-SFT-1640 Installation of Earthing Strips (B2 - P10) 15 15-Jan-20 29-Jan-20 0% 153 Installation of Earthing Strips (B2 - P10)
LEVEL S1 TO LEVEL 17 55 01-Feb-20 26-Mar-20 96 26-Mar-20, LEVEL S1 TO LEVEL 17
T4-IN-ELE-SFT-1650 Access from Client for Electrical Shaft Works (S1 - FL17) 0 01-Feb-20 0% 96 Access from Client for Electrical Shaft Works (S1 - FL17)
T4-IN-ELE-SFT-1660 Installation of Supports (S1 - FL17) 15 01-Feb-20 15-Feb-20 0% 96 Installation of Supports (S1 - FL17)
T4-IN-ELE-SFT-1670 Install Cable Trays & Ladders (S1 - FL17) 25 16-Feb-20 11-Mar-20 0% 96 Install Cable Trays & Ladders (S1 - FL17)
T4-IN-ELE-SFT-1680 Installation of Earthing Strips (S1 - FL17) 15 12-Mar-20 26-Mar-20 0% 96 Installation of Earthing Strips (S1 - FL17)
LEVEL 18 TO LEVEL 27 55 15-May-20 08-Jul-20 176 08-Jul-20, LEVEL 18 TO LEVEL 27
T4-IN-ELE-SFT-1690 Access from Client for Electrical Shaft Works (FL18 - FL27) 0 15-May-20 0% 176 Access from Client for Electrical Shaft Wor
T4-IN-ELE-SFT-1700 Installation of Supports (FL18 - FL27) 15 15-May-20 29-May-20 0% 176 Installation of Supports (FL18 - FL27)
T4-IN-ELE-SFT-1710 Install Cable Trays & Ladders (FL18 - FL27) 25 30-May-20 23-Jun-20 0% 176 Install Cable Trays & Ladders (FL18
T4-IN-ELE-SFT-1720 Installation of Earthing Strips (FL18 - FL27) 15 24-Jun-20 08-Jul-20 0% 176 Installation of Earthing Strips (FL1
LEVEL 28 TO LEVEL 35 55 23-Jul-20 15-Sep-20 107 15-Sep-20, LEVEL 28
T4-IN-ELE-SFT-1730 Access from Client for Electrical Shaft Works (FL28 - FL35) 0 23-Jul-20 0% 107 Access from Client for Electrica
T4-IN-ELE-SFT-1740 Installation of Supports (FL28 - FL35) 15 23-Jul-20 06-Aug-20 0% 107 Installation of Supports (FL2
T4-IN-ELE-SFT-1750 Install Cable Trays & Ladders (FL28 - FL35) 25 07-Aug-20 31-Aug-20 0% 107 Install Cable Trays & Lad
T4-IN-ELE-SFT-1760 Installation of Earthing Strips (FL28 - FL35) 15 01-Sep-20 15-Sep-20 0% 107 Installation of Earthing
LEVEL 36 TO LEVEL ROOF 55 01-Sep-20 25-Oct-20 67 25-Oct-20, LEV
T4-IN-ELE-SFT-1770 Access from Client for Electrical Shaft Works (FL36 - ROOF) 0 01-Sep-20 0% 67 Access from Client for E
T4-IN-ELE-SFT-1780 Installation of Supports (FL36 - ROOF) 15 01-Sep-20 15-Sep-20 0% 67 Installation of Support
T4-IN-ELE-SFT-1790 Install Cable Trays & Ladders (FL36 - ROOF) 25 16-Sep-20 10-Oct-20 0% 67 Install Cable Tray
T4-IN-ELE-SFT-1800 Installation of Earthing Strips (FL36 - ROOF) 15 11-Oct-20 25-Oct-20 0% 67 Installation of E
MODULAR FOR SUPREMUS FLOORS 82 23-Dec-19 14-Mar-20 71 14-Mar-20, MODULAR FOR SUPREMUS FLOORS
LEVEL 09 82 23-Dec-19 14-Mar-20 70 14-Mar-20, LEVEL 09
T4-IN-MOD-FF-3100 Fixing of supports on Deck Slab (FL09) 4 23-Dec-19 27-Dec-19 0% 112 Fixing of supports on Deck Slab (FL09)
T4-IN-MOD-FF-3110 Shifting & Installation of Modules (FL09) 28 04-Feb-20 03-Mar-20 0% 70 Shifting & Installation of Modules (FL09)

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 50 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-MOD-FF-3120 Joint Connection of Modules (FL09) 28 06-Feb-20 05-Mar-20 0% 70 Joint Connection of Modules (FL09)
T4-IN-MOD-FF-3130 Ducting- Light Test (FL09) 2 05-Mar-20 07-Mar-20 0% 71 Ducting- Light Test (FL09)
T4-IN-MOD-FF-3140 Chilled Water Piping- Hydrotest (FL09) 3 05-Mar-20 08-Mar-20 0% 71 Chilled Water Piping- Hydrotest (FL09)
T4-IN-MOD-FF-3150 Fire Fighting Pipes - Hydrotest (FL09) 4 05-Mar-20 09-Mar-20 0% 70 Fire Fighting Pipes - Hydrotest (FL09)
T4-IN-MOD-FF-3160 Joint Insulation of Ducting / Chilled water pipes (FL09) 5 09-Mar-20 14-Mar-20 0% 70 Joint Insulation of Ducting / Chilled water pipes (FL09)
LEVEL 10 40 23-Dec-19 01-Feb-20 113 01-Feb-20, LEVEL 10
T4-IN-MOD-FF-3170 Fixing of supports on Deck Slab (FL10) 4 23-Dec-19 27-Dec-19 0% 118 Fixing of supports on Deck Slab (FL10)
T4-IN-MOD-FF-3180 Shifting & Installation of Modules (FL10) 25 31-Dec-19 24-Jan-20 0% 113 Shifting & Installation of Modules (FL10)
T4-IN-MOD-FF-3190 Joint Connection of Modules (FL10) 25 02-Jan-20 26-Jan-20 0% 113 Joint Connection of Modules (FL10)
T4-IN-MOD-FF-3200 Ducting- Light Test (FL10) 2 27-Jan-20 28-Jan-20 0% 113 Ducting- Light Test (FL10)
T4-IN-MOD-FF-3210 Chilled Water Piping- Hydrotest (FL10) 2 28-Jan-20 29-Jan-20 0% 113 Chilled Water Piping- Hydrotest (FL10)
T4-IN-MOD-FF-3220 Fire Fighting Pipes - Hydrotest (FL10) 4 27-Jan-20 30-Jan-20 0% 115 Fire Fighting Pipes - Hydrotest (FL10)
T4-IN-MOD-FF-3230 Joint Insulation of Ducting / Chilled water pipes (FL10) 2 31-Jan-20 01-Feb-20 0% 113 Joint Insulation of Ducting / Chilled water pipes (FL10)
LEVEL 11 40 23-Dec-19 01-Feb-20 113 01-Feb-20, LEVEL 11
T4-IN-MOD-FF-3240 Fixing of supports on Deck Slab (FL11) 4 23-Dec-19 27-Dec-19 0% 118 Fixing of supports on Deck Slab (FL11)
T4-IN-MOD-FF-3250 Shifting & Installation of Modules (FL11) 24 01-Jan-20 24-Jan-20 0% 113 Shifting & Installation of Modules (FL11)
T4-IN-MOD-FF-3260 Joint Connection of Modules (FL11) 24 04-Jan-20 27-Jan-20 0% 113 Joint Connection of Modules (FL11)
T4-IN-MOD-FF-3270 Ducting- Light Test (FL11) 2 28-Jan-20 29-Jan-20 0% 113 Ducting- Light Test (FL11)
T4-IN-MOD-FF-3280 Chilled Water Piping- Hydrotest (FL11) 3 28-Jan-20 30-Jan-20 0% 113 Chilled Water Piping- Hydrotest (FL11)
T4-IN-MOD-FF-3290 Fire Fighting Pipes - Hydrotest (FL11) 2 28-Jan-20 29-Jan-20 0% 114 Fire Fighting Pipes - Hydrotest (FL11)
T4-IN-MOD-FF-3300 Joint Insulation of Ducting / Chilled water pipes (FL11) 2 31-Jan-20 01-Feb-20 0% 113 Joint Insulation of Ducting / Chilled water pipes (FL11)
LEVEL 12 36 28-Dec-19 01-Feb-20 113 01-Feb-20, LEVEL 12
T4-IN-MOD-FF-3310 Fixing of supports on Deck Slab (FL12) 4 28-Dec-19 31-Dec-19 0% 113 Fixing of supports on Deck Slab (FL12)
T4-IN-MOD-FF-3320 Shifting & Installation of Modules (FL12) 22 02-Jan-20 23-Jan-20 0% 113 Shifting & Installation of Modules (FL12)
T4-IN-MOD-FF-3330 Joint Connection of Modules (FL12) 22 05-Jan-20 26-Jan-20 0% 113 Joint Connection of Modules (FL12)
T4-IN-MOD-FF-3340 Ducting- Light Test (FL12) 2 27-Jan-20 28-Jan-20 0% 114 Ducting- Light Test (FL12)
T4-IN-MOD-FF-3350 Chilled Water Piping- Hydrotest (FL12) 3 27-Jan-20 29-Jan-20 0% 114 Chilled Water Piping- Hydrotest (FL12)
T4-IN-MOD-FF-3360 Fire Fighting Pipes - Hydrotest (FL12) 4 27-Jan-20 30-Jan-20 0% 113 Fire Fighting Pipes - Hydrotest (FL12)
T4-IN-MOD-FF-3370 Joint Insulation of Ducting / Chilled water pipes (FL12) 2 31-Jan-20 01-Feb-20 0% 113 Joint Insulation of Ducting / Chilled water pipes (FL12)
LEVEL 14 38 01-Feb-20 10-Mar-20 76 10-Mar-20, LEVEL 14
T4-IN-MOD-FF-3380 Fixing of supports on Deck Slab (FL14) 4 01-Feb-20 04-Feb-20 0% 76 Fixing of supports on Deck Slab (FL14)
T4-IN-MOD-FF-3390 Shifting & Installation of Modules (FL14) 28 02-Feb-20 29-Feb-20 0% 76 Shifting & Installation of Modules (FL14)
T4-IN-MOD-FF-3400 Joint Connection of Modules (FL14) 28 04-Feb-20 02-Mar-20 0% 76 Joint Connection of Modules (FL14)
T4-IN-MOD-FF-3410 Ducting- Light Test (FL14) 2 03-Mar-20 04-Mar-20 0% 77 Ducting- Light Test (FL14)
T4-IN-MOD-FF-3420 Chilled Water Piping- Hydrotest (FL14) 3 03-Mar-20 05-Mar-20 0% 77 Chilled Water Piping- Hydrotest (FL14)
T4-IN-MOD-FF-3430 Fire Fighting Pipes - Hydrotest (FL14) 4 03-Mar-20 06-Mar-20 0% 76 Fire Fighting Pipes - Hydrotest (FL14)
T4-IN-MOD-FF-3440 Joint Insulation of Ducting / Chilled water pipes (FL14) 3 07-Mar-20 10-Mar-20 0% 76 Joint Insulation of Ducting / Chilled water pipes (FL14)
LEVEL 15 41 01-Feb-20 13-Mar-20 73 13-Mar-20, LEVEL 15
T4-IN-MOD-FF-3450 Fixing of supports on Deck Slab (FL15) 4 01-Feb-20 04-Feb-20 0% 73 Fixing of supports on Deck Slab (FL15)
T4-IN-MOD-FF-3460 Shifting & Installation of Modules (FL15) 28 05-Feb-20 03-Mar-20 0% 73 Shifting & Installation of Modules (FL15)
T4-IN-MOD-FF-3470 Joint Connection of Modules (FL15) 28 07-Feb-20 05-Mar-20 0% 73 Joint Connection of Modules (FL15)
T4-IN-MOD-FF-3480 Ducting- Light Test (FL15) 2 06-Mar-20 07-Mar-20 0% 74 Ducting- Light Test (FL15)
T4-IN-MOD-FF-3490 Chilled Water Piping- Hydrotest (FL15) 3 06-Mar-20 08-Mar-20 0% 74 Chilled Water Piping- Hydrotest (FL15)
T4-IN-MOD-FF-3500 Fire Fighting Pipes - Hydrotest (FL15) 4 06-Mar-20 09-Mar-20 0% 73 Fire Fighting Pipes - Hydrotest (FL15)
T4-IN-MOD-FF-3510 Joint Insulation of Ducting / Chilled water pipes (FL15) 3 10-Mar-20 13-Mar-20 0% 73 Joint Insulation of Ducting / Chilled water pipes (FL15)
LEVEL 16 42 01-Feb-20 14-Mar-20 72 14-Mar-20, LEVEL 16
T4-IN-MOD-FF-3520 Fixing of supports on Deck Slab (FL16) 4 01-Feb-20 04-Feb-20 0% 72 Fixing of supports on Deck Slab (FL16)
T4-IN-MOD-FF-3530 Shifting & Installation of Modules (FL16) 28 06-Feb-20 04-Mar-20 0% 72 Shifting & Installation of Modules (FL16)
T4-IN-MOD-FF-3540 Joint Connection of Modules (FL16) 28 08-Feb-20 06-Mar-20 0% 72 Joint Connection of Modules (FL16)
T4-IN-MOD-FF-3550 Ducting- Light Test (FL16) 2 07-Mar-20 08-Mar-20 0% 73 Ducting- Light Test (FL16)
T4-IN-MOD-FF-3560 Chilled Water Piping- Hydrotest (FL16) 3 07-Mar-20 09-Mar-20 0% 73 Chilled Water Piping- Hydrotest (FL16)
T4-IN-MOD-FF-3570 Fire Fighting Pipes - Hydrotest (FL16) 4 07-Mar-20 10-Mar-20 0% 72 Fire Fighting Pipes - Hydrotest (FL16)

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 51 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-MOD-FF-3580 Joint Insulation of Ducting / Chilled water pipes (FL16) 3 11-Mar-20 14-Mar-20 0% 72 Joint Insulation of Ducting / Chilled water pipes (FL16)
HANDOVER TO CLIENT 370 20-Oct-19 27-Oct-20 18 27-Oct-20, HA
T4-IN-PHE-FF-1065 1st Fix Handover to Civil from MEP (B2) 0 28-Feb-20 0% 64 1st Fix Handover to Civil from MEP (B2)
T4-IN-PHE-FF-1140 1st Fix Handover to Civil from MEP (B1) 0 31-Jan-20 0% 83 1st Fix Handover to Civil from MEP (B1)
T4-IN-PHE-FF-1220 1st Fix Handover to Civil from MEP (P0) 0 15-Nov-19 0% 172 1st Fix Handover to Civil from MEP (P0)
T4-IN-PHE-FF-1300 1st Fix Handover to Civil from MEP (P1) 0 20-Oct-19 0% 206 1st Fix Handover to Civil from MEP (P1)
T4-IN-PHE-FF-1380 1st Fix Handover to Civil from MEP (P2) 0 20-Oct-19 0% 41 1st Fix Handover to Civil from MEP (P2)
T4-IN-PHE-FF-1460 1st Fix Handover to Civil from MEP (P3) 0 13-Nov-19 0% 182 1st Fix Handover to Civil from MEP (P3)
T4-IN-PHE-FF-1540 1st Fix Handover to Civil from MEP (P4) 0 13-Nov-19 0% 182 1st Fix Handover to Civil from MEP (P4)
T4-IN-PHE-FF-1620 1st Fix Handover to Civil from MEP (P5) 0 13-Nov-19 0% 182 1st Fix Handover to Civil from MEP (P5)
T4-IN-PHE-FF-1700 1st Fix Handover to Civil from MEP (P6) 0 13-Nov-19 0% 182 1st Fix Handover to Civil from MEP (P6)
T4-IN-PHE-FF-1780 1st Fix Handover to Civil from MEP (P7) 0 12-Dec-19 0% 154 1st Fix Handover to Civil from MEP (P7)
T4-IN-PHE-FF-1860 1st Fix Handover to Civil from MEP (P8) 0 12-Dec-19 0% 154 1st Fix Handover to Civil from MEP (P8)
T4-IN-PHE-FF-1940 1st Fix Handover to Civil from MEP (P9) 0 02-Jan-20 0% 133 1st Fix Handover to Civil from MEP (P9)
T4-IN-PHE-FF-1945 1st Fix Handover to Civil from MEP (P10) 0 02-Jan-20 0% 133 1st Fix Handover to Civil from MEP (P10)
T4-IN-PHE-FF-1946 1st Fix Handover to Civil from MEP (S1) 0 10-Mar-20 0% 80 1st Fix Handover to Civil from MEP (S1)
T4-IN-PHE-FF-2021 1st Fix Handover to Civil from MEP (FL09) 0 14-Mar-20 0% 70 1st Fix Handover to Civil from MEP (FL09)
T4-IN-PHE-FF-2022 1st Fix Handover to Civil from MEP (FL10) 0 01-Feb-20 0% 113 1st Fix Handover to Civil from MEP (FL10)
T4-IN-PHE-FF-2023 1st Fix Handover to Civil from MEP (FL11) 0 01-Feb-20 0% 113 1st Fix Handover to Civil from MEP (FL11)
T4-IN-PHE-FF-2024 1st Fix Handover to Civil from MEP (FL12) 0 01-Feb-20 0% 113 1st Fix Handover to Civil from MEP (FL12)
T4-IN-PHE-FF-2025 1st Fix Handover to Civil from MEP (FL14) 0 10-Mar-20 0% 76 1st Fix Handover to Civil from MEP (FL14)
T4-IN-PHE-FF-2026 1st Fix Handover to Civil from MEP (FL15) 0 13-Mar-20 0% 73 1st Fix Handover to Civil from MEP (FL15)
T4-IN-PHE-FF-2027 1st Fix Handover to Civil from MEP (FL16) 0 14-Mar-20 0% 72 1st Fix Handover to Civil from MEP (FL16)
T4-IN-PHE-FF-2100 1st Fix Handover to Civil from MEP (FL17) 0 12-Mar-20 0% 34 1st Fix Handover to Civil from MEP (FL17)
T4-IN-PHE-FF-2180 1st Fix Handover to Civil from MEP (FL18) 0 16-May-20 0% 182 1st Fix Handover to Civil from MEP (FL18)
T4-IN-PHE-FF-2260 1st Fix Handover to Civil from MEP (FL19) 0 16-May-20 0% 182 1st Fix Handover to Civil from MEP (FL19)
T4-IN-PHE-FF-2340 1st Fix Handover to Civil from MEP (FL 20) 0 16-May-20 0% 182 1st Fix Handover to Civil from MEP (FL 20)
T4-IN-PHE-FF-2420 1st Fix Handover to Civil from MEP (FL21) 0 16-May-20 0% 182 1st Fix Handover to Civil from MEP (FL21)
T4-IN-PHE-FF-2500 1st Fix Handover to Civil from MEP (FL22) 0 17-May-20 0% 25 1st Fix Handover to Civil from MEP (FL22)
T4-IN-PHE-FF-2580 1st Fix Handover to Civil from MEP (FL23) 0 19-Jun-20 0% 148 1st Fix Handover to Civil from MEP
T4-IN-PHE-FF-2660 1st Fix Handover to Civil from MEP (FL24) 0 19-Jun-20 0% 148 1st Fix Handover to Civil from MEP
T4-IN-PHE-FF-2740 1st Fix Handover to Civil from MEP (FL25) 0 19-Jun-20 0% 148 1st Fix Handover to Civil from MEP
T4-IN-PHE-FF-2820 1st Fix Handover to Civil from MEP (FL26) 0 19-Jun-20 0% 148 1st Fix Handover to Civil from MEP
T4-IN-PHE-FF-2900 1st Fix Handover to Civil from MEP (FL27) 0 19-Jun-20 0% 148 1st Fix Handover to Civil from MEP
T4-IN-PHE-FF-2980 1st Fix Handover to Civil from MEP (FL28) 0 23-Jul-20 0% 114 1st Fix Handover to Civil from
T4-IN-PHE-FF-3060 1st Fix Handover to Civil from MEP (FL29) 0 23-Jul-20 0% 114 1st Fix Handover to Civil from
T4-IN-PHE-FF-3140 1st Fix Handover to Civil from MEP (FL30) 0 23-Jul-20 0% 114 1st Fix Handover to Civil from
T4-IN-PHE-FF-3220 1st Fix Handover to Civil from MEP (FL31) 0 23-Jul-20 0% 114 1st Fix Handover to Civil from
T4-IN-PHE-FF-3300 1st Fix Handover to Civil from MEP (FL32) 0 27-Aug-20 0% 79 1st Fix Handover to Civil
T4-IN-PHE-FF-3380 1st Fix Handover to Civil from MEP (FL33) 0 27-Aug-20 0% 79 1st Fix Handover to Civil
T4-IN-PHE-FF-3460 1st Fix Handover to Civil from MEP (FL34) 0 27-Aug-20 0% 79 1st Fix Handover to Civil
T4-IN-PHE-FF-3540 1st Fix Handover to Civil from MEP (FL35) 0 27-Aug-20 0% 79 1st Fix Handover to Civil
T4-IN-PHE-FF-3620 1st Fix Handover to Civil from MEP (FL36) 0 06-Oct-20 0% 39 1st Fix Handover
T4-IN-PHE-FF-3700 1st Fix Handover to Civil from MEP (FL37) 0 06-Oct-20 0% 39 1st Fix Handover
T4-IN-PHE-FF-3780 1st Fix Handover to Civil from MEP (FL38) 0 06-Oct-20 0% 39 1st Fix Handover
T4-IN-PHE-FF-3860 1st Fix Handover to Civil from MEP (FL39) 0 06-Oct-20 0% 39 1st Fix Handover
T4-IN-PHE-FF-3940 1st Fix Handover to Civil from MEP (Roof) 0 27-Oct-20 0% 0 1st Fix Handov
SECOND FIX 394 29-Oct-19 27-Nov-20 34 27-Nov-2
ACCESS FROM CLIENT SECOND FIX 363 29-Oct-19 28-Oct-20 18 28-Oct-20, AC
T4-IN-ACC-SF-3950 Access from Client for Second Fix at B2 0 29-Mar-20 0% 35 Access from Client for Second Fix at B2
T4-IN-ACC-SF-4010 Access from Client for Second Fix at B1 0 01-Mar-20 0% 54 Access from Client for Second Fix at B1

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 52 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-ACC-SF-4070 Access from Client for Second Fix at P0 0 15-Dec-19 0% 143 Access from Client for Second Fix at P0
T4-IN-ACC-SF-4130 Access from Client for Second Fix at P1 0 29-Oct-19 0% 199 Access from Client for Second Fix at P1
T4-IN-ACC-SF-4190 Access from Client for Second Fix at P2 0 29-Oct-19 0% 34 Access from Client for Second Fix at P2
T4-IN-ACC-SF-4250 Access from Client for Second Fix at P3 0 21-Nov-19 0% 175 Access from Client for Second Fix at P3
T4-IN-ACC-SF-4310 Access from Client for Second Fix at P4 0 21-Nov-19 0% 175 Access from Client for Second Fix at P4
T4-IN-ACC-SF-4370 Access from Client for Second Fix at P5 0 21-Nov-19 0% 175 Access from Client for Second Fix at P5
T4-IN-ACC-SF-4430 Access from Client for Second Fix at P6 0 21-Nov-19 0% 175 Access from Client for Second Fix at P6
T4-IN-ACC-SF-4490 Access from Client for Second Fix at P7 0 20-Dec-19 0% 147 Access from Client for Second Fix at P7
T4-IN-ACC-SF-4550 Access from Client for Second Fix at P8 0 20-Dec-19 0% 147 Access from Client for Second Fix at P8
T4-IN-ACC-SF-4610 Access from Client for Second Fix at P9 0 10-Jan-20 0% 126 Access from Client for Second Fix at P9
T4-IN-ACC-SF-4615 Access from Client for Second Fix at P10 0 10-Jan-20 0% 126 Access from Client for Second Fix at P10
T4-IN-ACC-SF-4620 Access from Client for Second Fix at FL09 0 14-Mar-20 0% 70 Access from Client for Second Fix at FL09
T4-IN-ACC-SF-4630 Access from Client for Second Fix at FL10 0 09-Feb-20 0% 106 Access from Client for Second Fix at FL10
T4-IN-ACC-SF-4635 Access from Client for Second Fix at S1 0 15-Apr-20 0% 45 Access from Client for Second Fix at S1
T4-IN-ACC-SF-4640 Access from Client for Second Fix at FL11 0 09-Feb-20 0% 106 Access from Client for Second Fix at FL11
T4-IN-ACC-SF-4650 Access from Client for Second Fix at FL12 0 09-Feb-20 0% 106 Access from Client for Second Fix at FL12
T4-IN-ACC-SF-4655 Access from Client for Second Fix at FL14 0 10-Mar-20 0% 76 Access from Client for Second Fix at FL14
T4-IN-ACC-SF-4660 Access from Client for Second Fix at FL15 0 13-Mar-20 0% 73 Access from Client for Second Fix at FL15
T4-IN-ACC-SF-4665 Access from Client for Second Fix at FL16 0 14-Mar-20 0% 72 Access from Client for Second Fix at FL16
T4-IN-ACC-SF-4730 Access from Client for Second Fix at FL17 0 13-Mar-20 0% 34 Access from Client for Second Fix at FL17
T4-IN-ACC-SF-4790 Access from Client for Second Fix at FL18 0 24-May-20 0% 175 Access from Client for Second Fix at FL18
T4-IN-ACC-SF-4850 Access from Client for Second Fix at FL19 0 24-May-20 0% 175 Access from Client for Second Fix at FL19
T4-IN-ACC-SF-4910 Access from Client for Second Fix at FL20 0 24-May-20 0% 175 Access from Client for Second Fix at FL20
T4-IN-ACC-SF-4970 Access from Client for Second Fix at FL21 0 24-May-20 0% 175 Access from Client for Second Fix at FL21
T4-IN-ACC-SF-5030 Access from Client for Second Fix at FL22 0 18-May-20 0% 25 Access from Client for Second Fix at FL22
T4-IN-ACC-SF-5090 Access from Client for Second Fix at FL23 0 27-Jun-20 0% 141 Access from Client for Second Fix
T4-IN-ACC-SF-5150 Access from Client for Second Fix at FL24 0 27-Jun-20 0% 141 Access from Client for Second Fix
T4-IN-ACC-SF-5210 Access from Client for Second Fix at FL25 0 27-Jun-20 0% 141 Access from Client for Second Fix
T4-IN-ACC-SF-5270 Access from Client for Second Fix at FL26 0 27-Jun-20 0% 141 Access from Client for Second Fix
T4-IN-ACC-SF-5330 Access from Client for Second Fix at FL27 0 27-Jun-20 0% 141 Access from Client for Second Fix
T4-IN-ACC-SF-5390 Access from Client for Second Fix at FL28 0 31-Jul-20 0% 107 Access from Client for Second
T4-IN-ACC-SF-5450 Access from Client for Second Fix at FL29 0 31-Jul-20 0% 107 Access from Client for Second
T4-IN-ACC-SF-5510 Access from Client for Second Fix at FL30 0 31-Jul-20 0% 107 Access from Client for Second
T4-IN-ACC-SF-5570 Access from Client for Second Fix at FL31 0 31-Jul-20 0% 107 Access from Client for Second
T4-IN-ACC-SF-5630 Access from Client for Second Fix at FL32 0 04-Sep-20 0% 72 Access from Client for S
T4-IN-ACC-SF-5690 Access from Client for Second Fix at FL33 0 04-Sep-20 0% 72 Access from Client for S
T4-IN-ACC-SF-5750 Access from Client for Second Fix at FL34 0 04-Sep-20 0% 72 Access from Client for S
T4-IN-ACC-SF-5810 Access from Client for Second Fix at FL35 0 04-Sep-20 0% 72 Access from Client for S
T4-IN-ACC-SF-5870 Access from Client for Second Fix at FL36 0 14-Oct-20 0% 32 Access from Clie
T4-IN-ACC-SF-5930 Access from Client for Second Fix at FL37 0 14-Oct-20 0% 32 Access from Clie
T4-IN-ACC-SF-5990 Access from Client for Second Fix at FL38 0 14-Oct-20 0% 32 Access from Clie
T4-IN-ACC-SF-6050 Access from Client for Second Fix at FL39 0 14-Oct-20 0% 32 Access from Clie
T4-IN-ACC-SF-6110 Access from Client for Second Fix at ROOF 0 28-Oct-20 0% 0 Access from C
PHE / FF 394 29-Oct-19 27-Nov-20 9 27-Nov-2
LEVEL B2 31 29-Mar-20 28-Apr-20 35 28-Apr-20, LEVEL B2
PLUMBING 14 29-Mar-20 11-Apr-20 52 11-Apr-20, PLUMBING
T4-IN-PHE-FF-4020 Installation of Floor Drains/ Canpoy (B2) 4 29-Mar-20 01-Apr-20 0% 52 Installation of Floor Drains/ Canpoy (B2)
T4-IN-PHE-FF-4030 Installation of Sanitory Fixtures (B2) 10 02-Apr-20 11-Apr-20 0% 52 Installation of Sanitory Fixtures (B2)
FIRE FIGHTING 31 29-Mar-20 28-Apr-20 35 28-Apr-20, FIRE FIGHTING
T4-IN-PHE-FF-4040 Installation of Valves & accessories (B2) 15 29-Mar-20 12-Apr-20 0% 35 Installation of Valves & accessories (B2)
T4-IN-PHE-FF-4050 Installation of Sprinkler Hose & Upright Sprinklers (B2) 16 13-Apr-20 28-Apr-20 0% 35 Installation of Sprinkler Hose & Upright Sprink
LEVEL B1 30 01-Mar-20 30-Mar-20 67 30-Mar-20, LEVEL B1

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 53 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
PLUMBING 14 01-Mar-20 14-Mar-20 83 14-Mar-20, PLUMBING
T4-IN-PHE-FF-3960 Installation of Floor Drains/ Canpoy (B1) 4 01-Mar-20 04-Mar-20 0% 83 Installation of Floor Drains/ Canpoy (B1)
T4-IN-PHE-FF-3970 Installation of Sanitory Fixtures (B1) 10 05-Mar-20 14-Mar-20 0% 83 Installation of Sanitory Fixtures (B1)
FIRE FIGHTING 30 01-Mar-20 30-Mar-20 67 30-Mar-20, FIRE FIGHTING
T4-IN-PHE-FF-3980 Installation of Valves & accessories (B1) 14 01-Mar-20 14-Mar-20 0% 67 Installation of Valves & accessories (B1)
T4-IN-PHE-FF-3990 Installation of Sprinkler Hose & Upright Sprinklers (B1) 16 15-Mar-20 30-Mar-20 0% 67 Installation of Sprinkler Hose & Upright Sprinklers (B1)
LEVEL P0 30 15-Dec-19 14-Jan-20 143 14-Jan-20, LEVEL P0
PLUMBING 14 15-Dec-19 29-Dec-19 159 29-Dec-19, PLUMBING
T4-IN-PHE-FF-4080 Installation of Floor Drains/ Canpoy (P0) 4 15-Dec-19 18-Dec-19 0% 159 Installation of Floor Drains/ Canpoy (P0)
T4-IN-PHE-FF-4090 Installation of Sanitory Fixtures (P0) 10 19-Dec-19 29-Dec-19 0% 159 Installation of Sanitory Fixtures (P0)
FIRE FIGHTING 30 15-Dec-19 14-Jan-20 143 14-Jan-20, FIRE FIGHTING
T4-IN-PHE-FF-4100 Installation of Valves & accessories (P0) 14 15-Dec-19 29-Dec-19 0% 143 Installation of Valves & accessories (P0)
T4-IN-PHE-FF-4110 Installation of Sprinkler Hose & Upright Sprinklers (P0) 16 30-Dec-19 14-Jan-20 0% 143 Installation of Sprinkler Hose & Upright Sprinklers (P0)
LEVEL P1 20 29-Oct-19 18-Nov-19 199 18-Nov-19, LEVEL P1
PLUMBING 14 29-Oct-19 11-Nov-19 205 11-Nov-19, PLUMBING
T4-IN-PHE-FF-4140 Installation of Floor Drains/ Canpoy (P1) 4 29-Oct-19 01-Nov-19 0% 205 Installation of Floor Drains/ Canpoy (P1)
T4-IN-PHE-FF-4150 Installation of Sanitory Fixtures (P1) 10 02-Nov-19 11-Nov-19 0% 205 Installation of Sanitory Fixtures (P1)
FIRE FIGHTING 20 29-Oct-19 18-Nov-19 199 18-Nov-19, FIRE FIGHTING
T4-IN-PHE-FF-4160 Installation of Valves & accessories (P1) 6 29-Oct-19 03-Nov-19 0% 199 Installation of Valves & accessories (P1)
T4-IN-PHE-FF-4170 Installation of Sprinkler Hose & Upright Sprinklers (P1) 14 04-Nov-19 18-Nov-19 0% 199 Installation of Sprinkler Hose & Upright Sprinklers (P1)
LEVEL P2 20 29-Oct-19 18-Nov-19 34 18-Nov-19, LEVEL P2
PLUMBING 14 29-Oct-19 11-Nov-19 40 11-Nov-19, PLUMBING
T4-IN-PHE-FF-4200 Installation of Floor Drains/ Canpoy (P2) 4 29-Oct-19 01-Nov-19 0% 40 Installation of Floor Drains/ Canpoy (P2)
T4-IN-PHE-FF-4210 Installation of Sanitory Fixtures (P2) 10 02-Nov-19 11-Nov-19 0% 40 Installation of Sanitory Fixtures (P2)
FIRE FIGHTING 20 29-Oct-19 18-Nov-19 34 18-Nov-19, FIRE FIGHTING
T4-IN-PHE-FF-4220 Installation of Valves & accessories (P2) 6 29-Oct-19 03-Nov-19 0% 34 Installation of Valves & accessories (P2)
T4-IN-PHE-FF-4230 Installation of Sprinkler Hose & Upright Sprinklers (P2) 14 04-Nov-19 18-Nov-19 0% 34 Installation of Sprinkler Hose & Upright Sprinklers (P2)
LEVEL P3 22 21-Nov-19 12-Dec-19 175 12-Dec-19, LEVEL P3
PLUMBING 14 21-Nov-19 04-Dec-19 183 04-Dec-19, PLUMBING
T4-IN-PHE-FF-4260 Installation of Floor Drains/ Canpoy (P3) 4 21-Nov-19 24-Nov-19 0% 183 Installation of Floor Drains/ Canpoy (P3)
T4-IN-PHE-FF-4270 Installation of Sanitory Fixtures (P3) 10 25-Nov-19 04-Dec-19 0% 183 Installation of Sanitory Fixtures (P3)
FIRE FIGHTING 22 21-Nov-19 12-Dec-19 175 12-Dec-19, FIRE FIGHTING
T4-IN-PHE-FF-4280 Installation of Valves & accessories (P3) 8 21-Nov-19 28-Nov-19 0% 175 Installation of Valves & accessories (P3)
T4-IN-PHE-FF-4290 Installation of Sprinkler Hose & Upright Sprinklers (P3) 14 29-Nov-19 12-Dec-19 0% 175 Installation of Sprinkler Hose & Upright Sprinklers (P3)
LEVEL P4 22 21-Nov-19 12-Dec-19 175 12-Dec-19, LEVEL P4
PLUMBING 14 21-Nov-19 04-Dec-19 183 04-Dec-19, PLUMBING
T4-IN-PHE-FF-4320 Installation of Floor Drains/ Canpoy (P4) 4 21-Nov-19 24-Nov-19 0% 183 Installation of Floor Drains/ Canpoy (P4)
T4-IN-PHE-FF-4330 Installation of Sanitory Fixtures (P4) 10 25-Nov-19 04-Dec-19 0% 183 Installation of Sanitory Fixtures (P4)
FIRE FIGHTING 22 21-Nov-19 12-Dec-19 175 12-Dec-19, FIRE FIGHTING
T4-IN-PHE-FF-4340 Installation of Valves & accessories (P4) 8 21-Nov-19 28-Nov-19 0% 175 Installation of Valves & accessories (P4)
T4-IN-PHE-FF-4350 Installation of Sprinkler Hose & Upright Sprinklers (P4) 14 29-Nov-19 12-Dec-19 0% 175 Installation of Sprinkler Hose & Upright Sprinklers (P4)
LEVEL P5 22 21-Nov-19 12-Dec-19 175 12-Dec-19, LEVEL P5
PLUMBING 14 21-Nov-19 04-Dec-19 183 04-Dec-19, PLUMBING
T4-IN-PHE-FF-4380 Installation of Floor Drains/ Canpoy (P5) 4 21-Nov-19 24-Nov-19 0% 183 Installation of Floor Drains/ Canpoy (P5)
T4-IN-PHE-FF-4390 Installation of Sanitory Fixtures (P5) 10 25-Nov-19 04-Dec-19 0% 183 Installation of Sanitory Fixtures (P5)
FIRE FIGHTING 22 21-Nov-19 12-Dec-19 175 12-Dec-19, FIRE FIGHTING
T4-IN-PHE-FF-4400 Installation of Valves & accessories (P5) 8 21-Nov-19 28-Nov-19 0% 175 Installation of Valves & accessories (P5)
T4-IN-PHE-FF-4410 Installation of Sprinkler Hose & Upright Sprinklers (P5) 14 29-Nov-19 12-Dec-19 0% 175 Installation of Sprinkler Hose & Upright Sprinklers (P5)
LEVEL P6 22 21-Nov-19 12-Dec-19 175 12-Dec-19, LEVEL P6
PLUMBING 14 21-Nov-19 04-Dec-19 183 04-Dec-19, PLUMBING
T4-IN-PHE-FF-4440 Installation of Floor Drains/ Canpoy (P6) 4 21-Nov-19 24-Nov-19 0% 183 Installation of Floor Drains/ Canpoy (P6)
T4-IN-PHE-FF-4450 Installation of Sanitory Fixtures (P6) 10 25-Nov-19 04-Dec-19 0% 183 Installation of Sanitory Fixtures (P6)
FIRE FIGHTING 22 21-Nov-19 12-Dec-19 175 12-Dec-19, FIRE FIGHTING
T4-IN-PHE-FF-4460 Installation of Valves & accessories (P6) 8 21-Nov-19 28-Nov-19 0% 175 Installation of Valves & accessories (P6)

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 54 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-PHE-FF-4470 Installation of Sprinkler Hose & Upright Sprinklers (P6) 14 29-Nov-19 12-Dec-19 0% 175 Installation of Sprinkler Hose & Upright Sprinklers (P6)
LEVEL P7 21 20-Dec-19 10-Jan-20 147 10-Jan-20, LEVEL P7
PLUMBING 14 20-Dec-19 03-Jan-20 154 03-Jan-20, PLUMBING
T4-IN-PHE-FF-4500 Installation of Floor Drains/ Canpoy (P7) 4 20-Dec-19 23-Dec-19 0% 154 Installation of Floor Drains/ Canpoy (P7)
T4-IN-PHE-FF-4510 Installation of Sanitory Fixtures (P7) (P7) 10 24-Dec-19 03-Jan-20 0% 154 Installation of Sanitory Fixtures (P7) (P7)
FIRE FIGHTING 21 20-Dec-19 10-Jan-20 147 10-Jan-20, FIRE FIGHTING
T4-IN-PHE-FF-4520 Installation of Valves & accessories (P7) 7 20-Dec-19 27-Dec-19 0% 147 Installation of Valves & accessories (P7)
T4-IN-PHE-FF-4530 Installation of Sprinkler Hose & Upright Sprinklers (P7) 14 28-Dec-19 10-Jan-20 0% 147 Installation of Sprinkler Hose & Upright Sprinklers (P7)
LEVEL P8 21 20-Dec-19 10-Jan-20 147 10-Jan-20, LEVEL P8
PLUMBING 14 20-Dec-19 03-Jan-20 154 03-Jan-20, PLUMBING
T4-IN-PHE-FF-4560 Installation of Floor Drains/ Canpoy (P8) 4 20-Dec-19 23-Dec-19 0% 154 Installation of Floor Drains/ Canpoy (P8)
T4-IN-PHE-FF-4570 Installation of Sanitory Fixtures (P8) 10 24-Dec-19 03-Jan-20 0% 154 Installation of Sanitory Fixtures (P8)
FIRE FIGHTING 21 20-Dec-19 10-Jan-20 147 10-Jan-20, FIRE FIGHTING
T4-IN-PHE-FF-4580 Installation of Valves & accessories (P8) 7 20-Dec-19 27-Dec-19 0% 147 Installation of Valves & accessories (P8)
T4-IN-PHE-FF-4590 Installation of Sprinkler Hose & Upright Sprinklers (P8) 14 28-Dec-19 10-Jan-20 0% 147 Installation of Sprinkler Hose & Upright Sprinklers (P8)
LEVEL P9 22 10-Jan-20 31-Jan-20 126 31-Jan-20, LEVEL P9
PLUMBING 14 10-Jan-20 23-Jan-20 134 23-Jan-20, PLUMBING
T4-IN-PHE-FF-4620 Installation of Floor Drains/ Canpoy (P9) 4 10-Jan-20 13-Jan-20 0% 134 Installation of Floor Drains/ Canpoy (P9)
T4-IN-PHE-FF-4630 Installation of Sanitory Fixtures (P9) 10 14-Jan-20 23-Jan-20 0% 134 Installation of Sanitory Fixtures (P9)
FIRE FIGHTING 22 10-Jan-20 31-Jan-20 126 31-Jan-20, FIRE FIGHTING
T4-IN-PHE-FF-4640 Installation of Valves & accessories (P9) 8 10-Jan-20 17-Jan-20 0% 126 Installation of Valves & accessories (P9)
T4-IN-PHE-FF-4650 Installation of Sprinkler Hose & Upright Sprinklers (P9) 14 18-Jan-20 31-Jan-20 0% 126 Installation of Sprinkler Hose & Upright Sprinklers (P9)
LEVEL P10 22 10-Jan-20 31-Jan-20 126 31-Jan-20, LEVEL P10
PLUMBING 14 10-Jan-20 23-Jan-20 134 23-Jan-20, PLUMBING
T4-IN-PHE-FF-4680 Installation of Floor Drains/ Canpoy (P10) 4 10-Jan-20 13-Jan-20 0% 134 Installation of Floor Drains/ Canpoy (P10)
T4-IN-PHE-FF-4690 Installation of Sanitory Fixtures (P10) 10 14-Jan-20 23-Jan-20 0% 134 Installation of Sanitory Fixtures (P10)
FIRE FIGHTING 22 10-Jan-20 31-Jan-20 126 31-Jan-20, FIRE FIGHTING
T4-IN-PHE-FF-4700 Installation of Valves & accessories (P10) 8 10-Jan-20 17-Jan-20 0% 126 Installation of Valves & accessories (P10)
T4-IN-PHE-FF-4710 Installation of Sprinkler Hose & Upright Sprinklers (P10) 14 18-Jan-20 31-Jan-20 0% 126 Installation of Sprinkler Hose & Upright Sprinklers (P10)
LEVEL FL17 24 13-Mar-20 05-Apr-20 49 05-Apr-20, LEVEL FL17
PLUMBING 14 13-Mar-20 26-Mar-20 59 26-Mar-20, PLUMBING
T4-IN-PHE-FF-4740 Installation of Floor Drains/ Canpoy (FL17) 4 13-Mar-20 16-Mar-20 0% 59 Installation of Floor Drains/ Canpoy (FL17)
T4-IN-PHE-FF-4750 Installation of Sanitory Fixtures (FL17) 10 17-Mar-20 26-Mar-20 0% 59 Installation of Sanitory Fixtures (FL17)
FIRE FIGHTING 24 13-Mar-20 05-Apr-20 49 05-Apr-20, FIRE FIGHTING
T4-IN-PHE-FF-4760 Installation of Valves & accessories (FL17) 10 13-Mar-20 22-Mar-20 0% 49 Installation of Valves & accessories (FL17)
T4-IN-PHE-FF-4770 Installation of Sprinkler Hose & Upright Sprinklers (FL17) 14 23-Mar-20 05-Apr-20 0% 49 Installation of Sprinkler Hose & Upright Sprinklers
LEVEL FL18 22 24-May-20 14-Jun-20 175 14-Jun-20, LEVEL FL18
PLUMBING 14 24-May-20 06-Jun-20 183 06-Jun-20, PLUMBING
T4-IN-PHE-FF-4800 Installation of Floor Drains/ Canpoy (FL18) 4 24-May-20 27-May-20 0% 183 Installation of Floor Drains/ Canpoy (FL18)
T4-IN-PHE-FF-4810 Installation of Sanitory Fixtures (FL18) 10 28-May-20 06-Jun-20 0% 183 Installation of Sanitory Fixtures (FL18)
FIRE FIGHTING 22 24-May-20 14-Jun-20 175 14-Jun-20, FIRE FIGHTING
T4-IN-PHE-FF-4820 Installation of Valves & accessories (FL18) 8 24-May-20 31-May-20 0% 175 Installation of Valves & accessories (FL18)
T4-IN-PHE-FF-4830 Installation of Sprinkler Hose & Upright Sprinklers (FL18) 14 01-Jun-20 14-Jun-20 0% 175 Installation of Sprinkler Hose & Uprigh
LEVEL FL19 22 24-May-20 14-Jun-20 175 14-Jun-20, LEVEL FL19
PLUMBING 14 24-May-20 06-Jun-20 183 06-Jun-20, PLUMBING
T4-IN-PHE-FF-4860 Installation of Floor Drains/ Canpoy (FL19) 4 24-May-20 27-May-20 0% 183 Installation of Floor Drains/ Canpoy (FL19)
T4-IN-PHE-FF-4870 Installation of Sanitory Fixtures (FL19) 10 28-May-20 06-Jun-20 0% 183 Installation of Sanitory Fixtures (FL19)
FIRE FIGHTING 22 24-May-20 14-Jun-20 175 14-Jun-20, FIRE FIGHTING
T4-IN-PHE-FF-4880 Installation of Valves & accessories (FL19) 8 24-May-20 31-May-20 0% 175 Installation of Valves & accessories (FL19)
T4-IN-PHE-FF-4890 Installation of Sprinkler Hose & Upright Sprinklers (FL19) 14 01-Jun-20 14-Jun-20 0% 175 Installation of Sprinkler Hose & Uprigh
LEVEL FL20 22 24-May-20 14-Jun-20 175 14-Jun-20, LEVEL FL20
PLUMBING 14 24-May-20 06-Jun-20 183 06-Jun-20, PLUMBING
T4-IN-PHE-FF-4920 Installation of Floor Drains/ Canpoy (FL20) 4 24-May-20 27-May-20 0% 183 Installation of Floor Drains/ Canpoy (FL20)
T4-IN-PHE-FF-4930 Installation of Sanitory Fixtures (FL20) 10 28-May-20 06-Jun-20 0% 183 Installation of Sanitory Fixtures (FL20)

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 55 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
FIRE FIGHTING 22 24-May-20 14-Jun-20 175 14-Jun-20, FIRE FIGHTING
T4-IN-PHE-FF-4940 Installation of Valves & accessories (FL20) 8 24-May-20 31-May-20 0% 175 Installation of Valves & accessories (FL20)
T4-IN-PHE-FF-4950 Installation of Sprinkler Hose & Upright Sprinklers (FL20) 14 01-Jun-20 14-Jun-20 0% 175 Installation of Sprinkler Hose & Uprigh
LEVEL FL21 22 24-May-20 14-Jun-20 175 14-Jun-20, LEVEL FL21
PLUMBING 14 24-May-20 06-Jun-20 183 06-Jun-20, PLUMBING
T4-IN-PHE-FF-4980 Installation of Floor Drains/ Canpoy (FL21) 4 24-May-20 27-May-20 0% 183 Installation of Floor Drains/ Canpoy (FL21)
T4-IN-PHE-FF-4990 Installation of Sanitory Fixtures (FL21) 10 28-May-20 06-Jun-20 0% 183 Installation of Sanitory Fixtures (FL21)
FIRE FIGHTING 22 24-May-20 14-Jun-20 175 14-Jun-20, FIRE FIGHTING
T4-IN-PHE-FF-5000 Installation of Valves & accessories (FL21) 8 24-May-20 31-May-20 0% 175 Installation of Valves & accessories (FL21)
T4-IN-PHE-FF-5010 Installation of Sprinkler Hose & Upright Sprinklers (FL21) 14 01-Jun-20 14-Jun-20 0% 175 Installation of Sprinkler Hose & Uprigh
LEVEL FL22 31 18-May-20 17-Jun-20 172 17-Jun-20, LEVEL FL22
PLUMBING 28 18-May-20 14-Jun-20 175 14-Jun-20, PLUMBING
T4-IN-PHE-FF-5040 Installation of Floor Drains/ Canpoy (FL22) 8 18-May-20 25-May-20 0% 175 Installation of Floor Drains/ Canpoy (FL22)
T4-IN-PHE-FF-5050 Installation of Sanitory Fixtures (FL22) 20 26-May-20 14-Jun-20 0% 175 Installation of Sanitory Fixtures (FL22)
FIRE FIGHTING 31 18-May-20 17-Jun-20 172 17-Jun-20, FIRE FIGHTING
T4-IN-PHE-FF-5060 Installation of Valves & accessories (FL22) 13 18-May-20 30-May-20 0% 172 Installation of Valves & accessories (FL22)
T4-IN-PHE-FF-5070 Installation of Sprinkler Hose & Upright Sprinklers (FL22) 18 31-May-20 17-Jun-20 0% 172 Installation of Sprinkler Hose & Uprig
LEVEL FL23 22 27-Jun-20 18-Jul-20 141 18-Jul-20, LEVEL FL23
PLUMBING 14 27-Jun-20 10-Jul-20 149 10-Jul-20, PLUMBING
T4-IN-PHE-FF-5100 Installation of Floor Drains/ Canpoy (FL23) 4 27-Jun-20 30-Jun-20 0% 149 Installation of Floor Drains/ Canpo
T4-IN-PHE-FF-5110 Installation of Sanitory Fixtures (FL23) 10 01-Jul-20 10-Jul-20 0% 149 Installation of Sanitory Fixtures (F
FIRE FIGHTING 22 27-Jun-20 18-Jul-20 141 18-Jul-20, FIRE FIGHTING
T4-IN-PHE-FF-5120 Installation of Valves & accessories (FL23) 8 27-Jun-20 04-Jul-20 0% 141 Installation of Valves & accessorie
T4-IN-PHE-FF-5130 Installation of Sprinkler Hose & Upright Sprinklers (FL23) 14 05-Jul-20 18-Jul-20 0% 141 Installation of Sprinkler Hose &
LEVEL FL24 22 27-Jun-20 18-Jul-20 141 18-Jul-20, LEVEL FL24
PLUMBING 14 27-Jun-20 10-Jul-20 149 10-Jul-20, PLUMBING
T4-IN-PHE-FF-5160 Installation of Floor Drains/ Canpoy (FL24) 4 27-Jun-20 30-Jun-20 0% 149 Installation of Floor Drains/ Canpo
T4-IN-PHE-FF-5170 Installation of Sanitory Fixtures (FL24) 10 01-Jul-20 10-Jul-20 0% 149 Installation of Sanitory Fixtures (F
FIRE FIGHTING 22 27-Jun-20 18-Jul-20 141 18-Jul-20, FIRE FIGHTING
T4-IN-PHE-FF-5180 Installation of Valves & accessories (FL24) 8 27-Jun-20 04-Jul-20 0% 141 Installation of Valves & accessorie
T4-IN-PHE-FF-5190 Installation of Sprinkler Hose & Upright Sprinklers (FL24) 14 05-Jul-20 18-Jul-20 0% 141 Installation of Sprinkler Hose &
LEVEL FL25 22 27-Jun-20 18-Jul-20 141 18-Jul-20, LEVEL FL25
PLUMBING 14 27-Jun-20 10-Jul-20 149 10-Jul-20, PLUMBING
T4-IN-PHE-FF-5220 Installation of Floor Drains/ Canpoy (FL25) 4 27-Jun-20 30-Jun-20 0% 149 Installation of Floor Drains/ Canpo
T4-IN-PHE-FF-5230 Installation of Sanitory Fixtures (FL25) 10 01-Jul-20 10-Jul-20 0% 149 Installation of Sanitory Fixtures (F
FIRE FIGHTING 22 27-Jun-20 18-Jul-20 141 18-Jul-20, FIRE FIGHTING
T4-IN-PHE-FF-5240 Installation of Valves & accessories (FL25) 8 27-Jun-20 04-Jul-20 0% 141 Installation of Valves & accessorie
T4-IN-PHE-FF-5250 Installation of Sprinkler Hose & Upright Sprinklers (FL25) 14 05-Jul-20 18-Jul-20 0% 141 Installation of Sprinkler Hose &
LEVEL FL26 22 27-Jun-20 18-Jul-20 141 18-Jul-20, LEVEL FL26
PLUMBING 14 27-Jun-20 10-Jul-20 149 10-Jul-20, PLUMBING
T4-IN-PHE-FF-5280 Installation of Floor Drains/ Canpoy (FL26) 4 27-Jun-20 30-Jun-20 0% 149 Installation of Floor Drains/ Canpo
T4-IN-PHE-FF-5290 Installation of Sanitory Fixtures (FL26) 10 01-Jul-20 10-Jul-20 0% 149 Installation of Sanitory Fixtures (F
FIRE FIGHTING 22 27-Jun-20 18-Jul-20 141 18-Jul-20, FIRE FIGHTING
T4-IN-PHE-FF-5300 Installation of Valves & accessories (FL26) 8 27-Jun-20 04-Jul-20 0% 141 Installation of Valves & accessorie
T4-IN-PHE-FF-5310 Installation of Sprinkler Hose & Upright Sprinklers (FL26) 14 05-Jul-20 18-Jul-20 0% 141 Installation of Sprinkler Hose &
LEVEL FL27 22 27-Jun-20 18-Jul-20 141 18-Jul-20, LEVEL FL27
PLUMBING 14 27-Jun-20 10-Jul-20 149 10-Jul-20, PLUMBING
T4-IN-PHE-FF-5340 Installation of Floor Drains/ Canpoy (FL27) 4 27-Jun-20 30-Jun-20 0% 149 Installation of Floor Drains/ Canpo
T4-IN-PHE-FF-5350 Installation of Sanitory Fixtures (FL27) 10 01-Jul-20 10-Jul-20 0% 149 Installation of Sanitory Fixtures (F
FIRE FIGHTING 22 27-Jun-20 18-Jul-20 141 18-Jul-20, FIRE FIGHTING
T4-IN-PHE-FF-5360 Installation of Valves & accessories (FL27) 8 27-Jun-20 04-Jul-20 0% 141 Installation of Valves & accessorie
T4-IN-PHE-FF-5370 Installation of Sprinkler Hose & Upright Sprinklers (FL27) 14 05-Jul-20 18-Jul-20 0% 141 Installation of Sprinkler Hose &
LEVEL FL28 22 31-Jul-20 21-Aug-20 107 21-Aug-20, LEVEL FL28
PLUMBING 14 31-Jul-20 13-Aug-20 115 13-Aug-20, PLUMBING

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 56 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-PHE-FF-5400 Installation of Floor Drains/ Canpoy (FL28) 4 31-Jul-20 03-Aug-20 0% 115 Installation of Floor Drains/ C
T4-IN-PHE-FF-5410 Installation of Sanitory Fixtures (FL28) 10 04-Aug-20 13-Aug-20 0% 115 Installation of Sanitory Fixtu
FIRE FIGHTING 22 31-Jul-20 21-Aug-20 107 21-Aug-20, FIRE FIGHTING
T4-IN-PHE-FF-5420 Installation of Valves & accessories (FL28) 8 31-Jul-20 07-Aug-20 0% 107 Installation of Valves & acces
T4-IN-PHE-FF-5430 Installation of Sprinkler Hose & Upright Sprinklers (FL28) 14 08-Aug-20 21-Aug-20 0% 107 Installation of Sprinkler Ho
LEVEL FL29 22 31-Jul-20 21-Aug-20 107 21-Aug-20, LEVEL FL29
PLUMBING 14 31-Jul-20 13-Aug-20 115 13-Aug-20, PLUMBING
T4-IN-PHE-FF-5460 Installation of Floor Drains/ Canpoy (FL29) 4 31-Jul-20 03-Aug-20 0% 115 Installation of Floor Drains/ C
T4-IN-PHE-FF-5470 Installation of Sanitory Fixtures (FL29) 10 04-Aug-20 13-Aug-20 0% 115 Installation of Sanitory Fixtu
FIRE FIGHTING 22 31-Jul-20 21-Aug-20 107 21-Aug-20, FIRE FIGHTING
T4-IN-PHE-FF-5480 Installation of Valves & accessories (FL29) 8 31-Jul-20 07-Aug-20 0% 107 Installation of Valves & acces
T4-IN-PHE-FF-5490 Installation of Sprinkler Hose & Upright Sprinklers (FL29) 14 08-Aug-20 21-Aug-20 0% 107 Installation of Sprinkler Ho
LEVEL FL30 22 31-Jul-20 21-Aug-20 107 21-Aug-20, LEVEL FL30
PLUMBING 14 31-Jul-20 13-Aug-20 115 13-Aug-20, PLUMBING
T4-IN-PHE-FF-5520 Installation of Floor Drains/ Canpoy (FL30) 4 31-Jul-20 03-Aug-20 0% 115 Installation of Floor Drains/ C
T4-IN-PHE-FF-5530 Installation of Sanitory Fixtures (FL30) 10 04-Aug-20 13-Aug-20 0% 115 Installation of Sanitory Fixtu
FIRE FIGHTING 22 31-Jul-20 21-Aug-20 107 21-Aug-20, FIRE FIGHTING
T4-IN-PHE-FF-5540 Installation of Valves & accessories (FL30) 8 31-Jul-20 07-Aug-20 0% 107 Installation of Valves & acces
T4-IN-PHE-FF-5550 Installation of Sprinkler Hose & Upright Sprinklers (FL30) 14 08-Aug-20 21-Aug-20 0% 107 Installation of Sprinkler Ho
LEVEL FL31 22 31-Jul-20 21-Aug-20 107 21-Aug-20, LEVEL FL31
PLUMBING 14 31-Jul-20 13-Aug-20 115 13-Aug-20, PLUMBING
T4-IN-PHE-FF-5580 Installation of Floor Drains/ Canpoy (FL31) 4 31-Jul-20 03-Aug-20 0% 115 Installation of Floor Drains/ C
T4-IN-PHE-FF-5590 Installation of Sanitory Fixtures (FL31) 10 04-Aug-20 13-Aug-20 0% 115 Installation of Sanitory Fixtu
FIRE FIGHTING 22 31-Jul-20 21-Aug-20 107 21-Aug-20, FIRE FIGHTING
T4-IN-PHE-FF-5600 Installation of Valves & accessories (FL31) 8 31-Jul-20 07-Aug-20 0% 107 Installation of Valves & acces
T4-IN-PHE-FF-5610 Installation of Sprinkler Hose & Upright Sprinklers (FL31) 14 08-Aug-20 21-Aug-20 0% 107 Installation of Sprinkler Ho
LEVEL FL32 22 04-Sep-20 25-Sep-20 72 25-Sep-20, LEVEL FL32
PLUMBING 14 04-Sep-20 17-Sep-20 80 17-Sep-20, PLUMBING
T4-IN-PHE-FF-5640 Installation of Floor Drains/ Canpoy (FL32) 4 04-Sep-20 07-Sep-20 0% 80 Installation of Floor Dra
T4-IN-PHE-FF-5650 Installation of Sanitory Fixtures (FL32) 10 08-Sep-20 17-Sep-20 0% 80 Installation of Sanitory
FIRE FIGHTING 22 04-Sep-20 25-Sep-20 72 25-Sep-20, FIRE FI
T4-IN-PHE-FF-5660 Installation of Valves & accessories (FL32) 8 04-Sep-20 11-Sep-20 0% 72 Installation of Valves &
T4-IN-PHE-FF-5670 Installation of Sprinkler Hose & Upright Sprinklers (FL32) 14 12-Sep-20 25-Sep-20 0% 72 Installation of Sprink
LEVEL FL33 22 04-Sep-20 25-Sep-20 72 25-Sep-20, LEVEL FL33
PLUMBING 14 04-Sep-20 17-Sep-20 80 17-Sep-20, PLUMBING
T4-IN-PHE-FF-5700 Installation of Floor Drains/ Canpoy (FL33) 4 04-Sep-20 07-Sep-20 0% 80 Installation of Floor Dra
T4-IN-PHE-FF-5710 Installation of Sanitory Fixtures (FL33) 10 08-Sep-20 17-Sep-20 0% 80 Installation of Sanitory
FIRE FIGHTING 22 04-Sep-20 25-Sep-20 72 25-Sep-20, FIRE FI
T4-IN-PHE-FF-5720 Installation of Valves & accessories (FL33) 8 04-Sep-20 11-Sep-20 0% 72 Installation of Valves &
T4-IN-PHE-FF-5730 Installation of Sprinkler Hose & Upright Sprinklers (FL33) 14 12-Sep-20 25-Sep-20 0% 72 Installation of Sprink
LEVEL FL34 22 04-Sep-20 25-Sep-20 72 25-Sep-20, LEVEL FL34
PLUMBING 14 04-Sep-20 17-Sep-20 80 17-Sep-20, PLUMBING
T4-IN-PHE-FF-5760 Installation of Floor Drains/ Canpoy (FL34) 4 04-Sep-20 07-Sep-20 0% 80 Installation of Floor Dra
T4-IN-PHE-FF-5770 Installation of Sanitory Fixtures (FL34) 10 08-Sep-20 17-Sep-20 0% 80 Installation of Sanitory
FIRE FIGHTING 22 04-Sep-20 25-Sep-20 72 25-Sep-20, FIRE FI
T4-IN-PHE-FF-5780 Installation of Valves & accessories (FL34) 8 04-Sep-20 11-Sep-20 0% 72 Installation of Valves &
T4-IN-PHE-FF-5790 Installation of Sprinkler Hose & Upright Sprinklers (FL34) 14 12-Sep-20 25-Sep-20 0% 72 Installation of Sprink
LEVEL FL35 22 04-Sep-20 25-Sep-20 72 25-Sep-20, LEVEL FL35
PLUMBING 14 04-Sep-20 17-Sep-20 80 17-Sep-20, PLUMBING
T4-IN-PHE-FF-5820 Installation of Floor Drains/ Canpoy (FL35) 4 04-Sep-20 07-Sep-20 0% 80 Installation of Floor Dra
T4-IN-PHE-FF-5830 Installation of Sanitory Fixtures (FL35) 10 08-Sep-20 17-Sep-20 0% 80 Installation of Sanitory
FIRE FIGHTING 22 04-Sep-20 25-Sep-20 72 25-Sep-20, FIRE FI
T4-IN-PHE-FF-5840 Installation of Valves & accessories (FL35) 8 04-Sep-20 11-Sep-20 0% 72 Installation of Valves &

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 57 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-PHE-FF-5850 Installation of Sprinkler Hose & Upright Sprinklers (FL35) 14 12-Sep-20 25-Sep-20 0% 72 Installation of Sprink
LEVEL FL36 22 14-Oct-20 04-Nov-20 32 04-Nov-20, L
PLUMBING 14 14-Oct-20 27-Oct-20 40 27-Oct-20, PL
T4-IN-PHE-FF-5880 Installation of Floor Drains/ Canpoy (FL36) 4 14-Oct-20 17-Oct-20 0% 40 Installation of Flo
T4-IN-PHE-FF-5890 Installation of Sanitory Fixtures (FL36) 10 18-Oct-20 27-Oct-20 0% 40 Installation of S
FIRE FIGHTING 22 14-Oct-20 04-Nov-20 32 04-Nov-20, F
T4-IN-PHE-FF-5900 Installation of Valves & accessories (FL36) 8 14-Oct-20 21-Oct-20 0% 32 Installation of Va
T4-IN-PHE-FF-5910 Installation of Sprinkler Hose & Upright Sprinklers (FL36) 14 22-Oct-20 04-Nov-20 0% 32 Installation of
LEVEL FL37 22 14-Oct-20 04-Nov-20 32 04-Nov-20, L
PLUMBING 14 14-Oct-20 27-Oct-20 40 27-Oct-20, PL
T4-IN-PHE-FF-5940 Installation of Floor Drains/ Canpoy (FL37) 4 14-Oct-20 17-Oct-20 0% 40 Installation of Flo
T4-IN-PHE-FF-5950 Installation of Sanitory Fixtures (FL37) 10 18-Oct-20 27-Oct-20 0% 40 Installation of S
FIRE FIGHTING 22 14-Oct-20 04-Nov-20 32 04-Nov-20, F
T4-IN-PHE-FF-5960 Installation of Valves & accessories (FL37) 8 14-Oct-20 21-Oct-20 0% 32 Installation of Va
T4-IN-PHE-FF-5970 Installation of Sprinkler Hose & Upright Sprinklers (FL37) 14 22-Oct-20 04-Nov-20 0% 32 Installation of
LEVEL FL38 22 14-Oct-20 04-Nov-20 32 04-Nov-20, L
PLUMBING 14 14-Oct-20 27-Oct-20 40 27-Oct-20, PL
T4-IN-PHE-FF-6000 Installation of Floor Drains/ Canpoy (FL38) 4 14-Oct-20 17-Oct-20 0% 40 Installation of Flo
T4-IN-PHE-FF-6010 Installation of Sanitory Fixtures (FL38) 10 18-Oct-20 27-Oct-20 0% 40 Installation of S
FIRE FIGHTING 22 14-Oct-20 04-Nov-20 32 04-Nov-20, F
T4-IN-PHE-FF-6020 Installation of Valves & accessories (FL38) 8 14-Oct-20 21-Oct-20 0% 32 Installation of Va
T4-IN-PHE-FF-6030 Installation of Sprinkler Hose & Upright Sprinklers (FL38) 14 22-Oct-20 04-Nov-20 0% 32 Installation of
LEVEL FL39 22 14-Oct-20 04-Nov-20 32 04-Nov-20, L
PLUMBING 14 14-Oct-20 27-Oct-20 40 27-Oct-20, PL
T4-IN-PHE-FF-6060 Installation of Floor Drains/ Canpoy (FL39) 4 14-Oct-20 17-Oct-20 0% 40 Installation of Flo
T4-IN-PHE-FF-6070 Installation of Sanitory Fixtures (FL39) 10 18-Oct-20 27-Oct-20 0% 40 Installation of S
FIRE FIGHTING 22 14-Oct-20 04-Nov-20 32 04-Nov-20, F
T4-IN-PHE-FF-6080 Installation of Valves & accessories (FL39) 8 14-Oct-20 21-Oct-20 0% 32 Installation of Va
T4-IN-PHE-FF-6090 Installation of Sprinkler Hose & Upright Sprinklers (FL39) 14 22-Oct-20 04-Nov-20 0% 32 Installation of
LEVEL ROOF 31 28-Oct-20 27-Nov-20 0 27-Nov-2
PLUMBING 14 28-Oct-20 10-Nov-20 17 10-Nov-20,
T4-IN-PHE-FF-6120 Installation of Floor Drains/ Canpoy (ROOF) 4 28-Oct-20 31-Oct-20 0% 17 Installation of
T4-IN-PHE-FF-6130 Installation of Sanitory Fixtures (ROOF) 10 01-Nov-20 10-Nov-20 0% 17 Installation o
FIRE FIGHTING 31 28-Oct-20 27-Nov-20 0 27-Nov-2
T4-IN-PHE-FF-6140 Installation of Valves & accessories (ROOF) 14 28-Oct-20 10-Nov-20 0% 0 Installation o
T4-IN-PHE-FF-6150 Installation of Sprinkler Hose & Upright Sprinklers (ROOF) 17 11-Nov-20 27-Nov-20 0% 0 Installatio
HVAC 390 29-Oct-19 23-Nov-20 13 23-Nov-20
LEVEL B1 25 01-Mar-20 25-Mar-20 72 25-Mar-20, LEVEL B1
T4-IN-HVC-SF-9775 Ducting & CHW piping Joint Insulation (B1) 20 01-Mar-20 20-Mar-20 0% 72 Ducting & CHW piping Joint Insulation (B1)
T4-IN-HVC-SF-9780 Installation & allignment of CSU Panel (B1) 10 01-Mar-20 10-Mar-20 0% 83 Installation & allignment of CSU Panel (B1)
T4-IN-HVC-SF-9900 Cable Pulling & Termination for CSU Panel (B1) 4 11-Mar-20 14-Mar-20 0% 83 Cable Pulling & Termination for CSU Panel (B1)
T4-IN-HVC-SF-9910 AHU room acoustic Insulation (B1) 5 21-Mar-20 25-Mar-20 0% 72 AHU room acoustic Insulation (B1)
LEVEL P2 23 29-Oct-19 21-Nov-19 31 21-Nov-19, LEVEL P2
T4-IN-HVC-SF-9535 Ducting & CHW piping Joint Insulation (P2) 15 29-Oct-19 13-Nov-19 0% 34 Ducting & CHW piping Joint Insulation (P2)
T4-IN-HVC-SF-9540 Installation & allignment of AHU Panel (P2) 4 08-Nov-19 13-Nov-19 0% 31 Installation & allignment of AHU Panel (P2)
T4-IN-HVC-SF-9790 Installation & allignment of CSU Panel (P2) 4 13-Nov-19 17-Nov-19 0% 31 Installation & allignment of CSU Panel (P2)
T4-IN-HVC-SF-9930 Cable Pulling & Termination for AHU & CSU Panel (P2) 4 17-Nov-19 21-Nov-19 0% 31 Cable Pulling & Termination for AHU & CSU Panel (P2)
T4-IN-HVC-SF-9940 AHU room acoustic Insulation (P2) 5 14-Nov-19 18-Nov-19 0% 34 AHU room acoustic Insulation (P2)
LEVEL 09 13 14-Mar-20 27-Mar-20 70 27-Mar-20, LEVEL 09
T4-IN-HVC-SF-9795 Ducting & CHW piping Joint Insulation (FL09) 7 14-Mar-20 21-Mar-20 0% 70 Ducting & CHW piping Joint Insulation (FL09)
T4-IN-HVC-SF-9800 Installation & allignment of CSU Panel (FL09) 2 21-Mar-20 23-Mar-20 0% 70 Installation & allignment of CSU Panel (FL09)
T4-IN-HVC-SF-9950 Cable Pulling & Termination for CSU Panel (FL09) 4 23-Mar-20 27-Mar-20 0% 70 Cable Pulling & Termination for CSU Panel (FL09)
T4-IN-HVC-SF-9960 CSU room acoustic Insulation (FL09) 5 21-Mar-20 26-Mar-20 0% 71 CSU room acoustic Insulation (FL09)

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 58 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
LEVEL 17 73 13-Mar-20 24-May-20 0 24-May-20, LEVEL 17
T4-IN-HVC-SF-9545 Ducting & CHW piping Joint Insulation (FL17) 15 01-Apr-20 15-Apr-20 0% 34 Ducting & CHW piping Joint Insulation (FL17)
T4-IN-HVC-SF-9550 Installation & allignment of AHU Panel (FL17) 5 13-Mar-20 17-Mar-20 0% 58 Installation & allignment of AHU Panel (FL17)
T4-IN-HVC-SF-9810 Installation & allignment of CSU Panel (FL17) 5 14-May-20 19-May-20 0% 0 Installation & allignment of CSU Panel (FL17)
T4-IN-HVC-SF-9920 Cable Pulling & Termination for AHU & CSU Panel (FL17) 5 19-May-20 24-May-20 0% 0 Cable Pulling & Termination for AHU & C
T4-IN-HVC-SF-9970 AHU room acoustic Insulation (FL17) 5 16-Apr-20 20-Apr-20 0% 34 AHU room acoustic Insulation (FL17)
LEVEL 18 22 24-May-20 14-Jun-20 175 14-Jun-20, LEVEL 18
T4-IN-HVC-SF-9555 Ducting & CHW piping Joint Insulation (FL18) 15 24-May-20 07-Jun-20 0% 175 Ducting & CHW piping Joint Insulation
T4-IN-HVC-SF-9560 Installation & allignment of AHU Panel (FL18) 5 24-May-20 28-May-20 0% 187 Installation & allignment of AHU Panel (
T4-IN-HVC-SF-9990 Cable Pulling & Termination for AHU Panel (FL18) 5 29-May-20 02-Jun-20 0% 187 Cable Pulling & Termination for AHU Pa
T4-IN-HVC-SF-9995 AHU room acoustic Insulation (FL18) 7 08-Jun-20 14-Jun-20 0% 175 AHU room acoustic Insulation (FL18)
LEVEL 19 22 24-May-20 14-Jun-20 175 14-Jun-20, LEVEL 19
T4-IN-HVC-SF-10005 Ducting & CHW piping Joint Insulation (FL19) 15 24-May-20 07-Jun-20 0% 175 Ducting & CHW piping Joint Insulation
T4-IN-HVC-SF-10015 Installation & allignment of AHU Panel (FL19) 5 24-May-20 28-May-20 0% 187 Installation & allignment of AHU Panel (
T4-IN-HVC-SF-10025 Cable Pulling & Termination for AHU Panel (FL19) 5 29-May-20 02-Jun-20 0% 187 Cable Pulling & Termination for AHU Pa
T4-IN-HVC-SF-10035 AHU room acoustic Insulation (FL19) 7 08-Jun-20 14-Jun-20 0% 175 AHU room acoustic Insulation (FL19)
LEVEL 20 22 24-May-20 14-Jun-20 175 14-Jun-20, LEVEL 20
T4-IN-HVC-SF-10045 Ducting & CHW piping Joint Insulation (FL20) 15 24-May-20 07-Jun-20 0% 175 Ducting & CHW piping Joint Insulation
T4-IN-HVC-SF-10055 Installation & allignment of AHU Panel (FL20) 5 24-May-20 28-May-20 0% 187 Installation & allignment of AHU Panel (
T4-IN-HVC-SF-10065 Cable Pulling & Termination for AHU Panel (FL20) 5 29-May-20 02-Jun-20 0% 187 Cable Pulling & Termination for AHU Pa
T4-IN-HVC-SF-10075 AHU room acoustic Insulation (FL20) 7 08-Jun-20 14-Jun-20 0% 175 AHU room acoustic Insulation (FL20)
LEVEL 21 22 24-May-20 14-Jun-20 175 14-Jun-20, LEVEL 21
T4-IN-HVC-SF-10085 Ducting & CHW piping Joint Insulation (FL21) 15 24-May-20 07-Jun-20 0% 175 Ducting & CHW piping Joint Insulation
T4-IN-HVC-SF-10095 Installation & allignment of AHU Panel (FL21) 5 24-May-20 28-May-20 0% 187 Installation & allignment of AHU Panel (
T4-IN-HVC-SF-10105 Cable Pulling & Termination for AHU Panel (FL21) 5 29-May-20 02-Jun-20 0% 187 Cable Pulling & Termination for AHU Pa
T4-IN-HVC-SF-10115 AHU room acoustic Insulation (FL21) 7 08-Jun-20 14-Jun-20 0% 175 AHU room acoustic Insulation (FL21)
LEVEL 22 27 18-May-20 13-Jun-20 176 13-Jun-20, LEVEL 22
T4-IN-HVC-SF-10125 Ducting & CHW piping Joint Insulation (FL22) 20 18-May-20 06-Jun-20 0% 176 Ducting & CHW piping Joint Insulation
T4-IN-HVC-SF-10135 Installation & allignment of AHU Panel (FL22) 10 18-May-20 27-May-20 0% 184 Installation & allignment of AHU Panel (
T4-IN-HVC-SF-10145 Installation & allignment of CSU Panel (FL22) 5 28-May-20 01-Jun-20 0% 184 Installation & allignment of CSU Panel
T4-IN-HVC-SF-10155 Cable Pulling & Termination for AHU & CSU Panel (FL22) 4 02-Jun-20 05-Jun-20 0% 184 Cable Pulling & Termination for AHU &
T4-IN-HVC-SF-10165 AHU room acoustic Insulation (FL22) 7 07-Jun-20 13-Jun-20 0% 176 AHU room acoustic Insulation (FL22)
LEVEL 23 21 27-Jun-20 17-Jul-20 142 17-Jul-20, LEVEL 23
T4-IN-HVC-SF-10175 Ducting & CHW piping Joint Insulation (FL23) 14 27-Jun-20 10-Jul-20 0% 142 Ducting & CHW piping Joint Insu
T4-IN-HVC-SF-10185 Installation & allignment of AHU Panel (FL23) 5 27-Jun-20 01-Jul-20 0% 154 Installation & allignment of AHU P
T4-IN-HVC-SF-10195 Cable Pulling & Termination for AHU Panel (FL23) 4 02-Jul-20 05-Jul-20 0% 154 Cable Pulling & Termination for AH
T4-IN-HVC-SF-10205 AHU room acoustic Insulation (FL23) 7 11-Jul-20 17-Jul-20 0% 142 AHU room acoustic Insulation (F
LEVEL 24 22 27-Jun-20 18-Jul-20 141 18-Jul-20, LEVEL 24
T4-IN-HVC-SF-10215 Ducting & CHW piping Joint Insulation (FL24) 15 27-Jun-20 11-Jul-20 0% 141 Ducting & CHW piping Joint Insu
T4-IN-HVC-SF-10225 Installation & allignment of AHU Panel (FL24) 5 27-Jun-20 01-Jul-20 0% 146 Installation & allignment of AHU P
T4-IN-HVC-SF-10235 Installation & allignment of CSU Panel (FL24) 5 02-Jul-20 06-Jul-20 0% 146 Installation & allignment of CSU P
T4-IN-HVC-SF-10245 Cable Pulling & Termination for AHU & CSU Panel (FL24) 7 07-Jul-20 13-Jul-20 0% 146 Cable Pulling & Termination for A
T4-IN-HVC-SF-10255 AHU room acoustic Insulation (FL24) 7 12-Jul-20 18-Jul-20 0% 141 AHU room acoustic Insulation (F
LEVEL 25 21 27-Jun-20 17-Jul-20 142 17-Jul-20, LEVEL 25
T4-IN-HVC-SF-10265 Ducting & CHW piping Joint Insulation (FL25) 14 27-Jun-20 10-Jul-20 0% 142 Ducting & CHW piping Joint Insu
T4-IN-HVC-SF-10275 Installation & allignment of AHU Panel (FL25) 5 27-Jun-20 01-Jul-20 0% 154 Installation & allignment of AHU P
T4-IN-HVC-SF-10285 Cable Pulling & Termination for AHU Panel (FL25) 4 02-Jul-20 05-Jul-20 0% 154 Cable Pulling & Termination for AH
T4-IN-HVC-SF-10295 AHU room acoustic Insulation (FL25) 7 11-Jul-20 17-Jul-20 0% 142 AHU room acoustic Insulation (F
LEVEL 26 21 27-Jun-20 17-Jul-20 142 17-Jul-20, LEVEL 26
T4-IN-HVC-SF-10305 Ducting & CHW piping Joint Insulation (FL26) 14 27-Jun-20 10-Jul-20 0% 142 Ducting & CHW piping Joint Insu
T4-IN-HVC-SF-10315 Installation & allignment of AHU Panel (FL26) 5 27-Jun-20 01-Jul-20 0% 154 Installation & allignment of AHU P
T4-IN-HVC-SF-10325 Cable Pulling & Termination for AHU Panel (FL26) 4 02-Jul-20 05-Jul-20 0% 154 Cable Pulling & Termination for AH

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 59 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-HVC-SF-10335 AHU room acoustic Insulation (FL26) 7 11-Jul-20 17-Jul-20 0% 142 AHU room acoustic Insulation (F
LEVEL 27 21 27-Jun-20 17-Jul-20 142 17-Jul-20, LEVEL 27
T4-IN-HVC-SF-10345 Ducting & CHW piping Joint Insulation (FL27) 14 27-Jun-20 10-Jul-20 0% 142 Ducting & CHW piping Joint Insu
T4-IN-HVC-SF-10355 Installation & allignment of AHU Panel (FL27) 5 27-Jun-20 01-Jul-20 0% 154 Installation & allignment of AHU P
T4-IN-HVC-SF-10365 Cable Pulling & Termination for AHU Panel (FL27) 4 02-Jul-20 05-Jul-20 0% 154 Cable Pulling & Termination for AH
T4-IN-HVC-SF-10375 AHU room acoustic Insulation (FL27) 7 11-Jul-20 17-Jul-20 0% 142 AHU room acoustic Insulation (F
LEVEL 28 22 31-Jul-20 21-Aug-20 107 21-Aug-20, LEVEL 28
T4-IN-HVC-SF-10385 Ducting & CHW piping Joint Insulation (FL28) 15 31-Jul-20 14-Aug-20 0% 107 Ducting & CHW piping Join
T4-IN-HVC-SF-10395 Installation & allignment of AHU Panel (FL28) 5 31-Jul-20 04-Aug-20 0% 120 Installation & allignment of A
T4-IN-HVC-SF-10405 Cable Pulling & Termination for AHU Panel (FL28) 4 05-Aug-20 08-Aug-20 0% 120 Cable Pulling & Termination
T4-IN-HVC-SF-10415 AHU room acoustic Insulation (FL28) 7 15-Aug-20 21-Aug-20 0% 107 AHU room acoustic Insula
LEVEL 29 22 31-Jul-20 21-Aug-20 107 21-Aug-20, LEVEL 29
T4-IN-HVC-SF-10425 Ducting & CHW piping Joint Insulation (FL29) 15 31-Jul-20 14-Aug-20 0% 107 Ducting & CHW piping Join
T4-IN-HVC-SF-10435 Installation & allignment of AHU Panel (FL29) 5 31-Jul-20 04-Aug-20 0% 120 Installation & allignment of A
T4-IN-HVC-SF-10445 Cable Pulling & Termination for AHU Panel (FL29) 4 05-Aug-20 08-Aug-20 0% 120 Cable Pulling & Termination
T4-IN-HVC-SF-10455 AHU room acoustic Insulation (FL29) 7 15-Aug-20 21-Aug-20 0% 107 AHU room acoustic Insula
LEVEL 30 22 31-Jul-20 21-Aug-20 107 21-Aug-20, LEVEL 30
T4-IN-HVC-SF-10465 Ducting & CHW piping Joint Insulation (FL30) 15 31-Jul-20 14-Aug-20 0% 107 Ducting & CHW piping Join
T4-IN-HVC-SF-10475 Installation & allignment of AHU Panel (FL30) 5 31-Jul-20 04-Aug-20 0% 120 Installation & allignment of A
T4-IN-HVC-SF-10485 Cable Pulling & Termination for AHU Panel (FL30) 4 05-Aug-20 08-Aug-20 0% 120 Cable Pulling & Termination
T4-IN-HVC-SF-10495 AHU room acoustic Insulation (FL30) 7 15-Aug-20 21-Aug-20 0% 107 AHU room acoustic Insula
LEVEL 31 22 31-Jul-20 21-Aug-20 107 21-Aug-20, LEVEL 31
T4-IN-HVC-SF-10505 Ducting & CHW piping Joint Insulation (FL31) 15 31-Jul-20 14-Aug-20 0% 107 Ducting & CHW piping Join
T4-IN-HVC-SF-10515 Installation & allignment of AHU Panel (FL31) 5 31-Jul-20 04-Aug-20 0% 115 Installation & allignment of A
T4-IN-HVC-SF-10525 Installation & allignment of CSU Panel (FL31) 5 05-Aug-20 09-Aug-20 0% 115 Installation & allignment of C
T4-IN-HVC-SF-10535 Cable Pulling & Termination for AHU & CSU Panel (FL31) 4 10-Aug-20 13-Aug-20 0% 115 Cable Pulling & Termination
T4-IN-HVC-SF-10545 AHU room acoustic Insulation (FL31) 7 15-Aug-20 21-Aug-20 0% 107 AHU room acoustic Insula
LEVEL 32 22 04-Sep-20 25-Sep-20 72 25-Sep-20, LEVEL 32
T4-IN-HVC-SF-10555 Ducting & CHW piping Joint Insulation (FL32) 15 04-Sep-20 18-Sep-20 0% 72 Ducting & CHW pipin
T4-IN-HVC-SF-10565 Installation & allignment of AHU Panel (FL32) 5 04-Sep-20 08-Sep-20 0% 80 Installation & allignmen
T4-IN-HVC-SF-10575 Installation & allignment of CSU Panel (FL32) 5 09-Sep-20 13-Sep-20 0% 80 Installation & allignmen
T4-IN-HVC-SF-10585 Cable Pulling & Termination for AHU & CSU Panel (FL32) 4 14-Sep-20 17-Sep-20 0% 80 Cable Pulling & Term
T4-IN-HVC-SF-10595 AHU room acoustic Insulation (FL32) 7 19-Sep-20 25-Sep-20 0% 72 AHU room acoustic
LEVEL 33 22 04-Sep-20 25-Sep-20 72 25-Sep-20, LEVEL 33
T4-IN-HVC-SF-10605 Ducting & CHW piping Joint Insulation (FL33) 15 04-Sep-20 18-Sep-20 0% 72 Ducting & CHW pipin
T4-IN-HVC-SF-10615 Installation & allignment of AHU Panel (FL33) 5 04-Sep-20 08-Sep-20 0% 85 Installation & allignmen
T4-IN-HVC-SF-10625 Cable Pulling & Termination for AHU Panel (FL33) 4 09-Sep-20 12-Sep-20 0% 85 Cable Pulling & Termin
T4-IN-HVC-SF-10635 AHU room acoustic Insulation (FL33) 7 19-Sep-20 25-Sep-20 0% 72 AHU room acoustic
LEVEL 34 22 04-Sep-20 25-Sep-20 72 25-Sep-20, LEVEL 34
T4-IN-HVC-SF-10645 Ducting & CHW piping Joint Insulation (FL34) 15 04-Sep-20 18-Sep-20 0% 72 Ducting & CHW pipin
T4-IN-HVC-SF-10655 Installation & allignment of AHU Panel (FL34) 5 04-Sep-20 08-Sep-20 0% 85 Installation & allignmen
T4-IN-HVC-SF-10665 Cable Pulling & Termination for AHU Panel (FL34) 4 09-Sep-20 12-Sep-20 0% 85 Cable Pulling & Termin
T4-IN-HVC-SF-10675 AHU room acoustic Insulation (FL34) 7 19-Sep-20 25-Sep-20 0% 72 AHU room acoustic
LEVEL 35 22 04-Sep-20 25-Sep-20 72 25-Sep-20, LEVEL 35
T4-IN-HVC-SF-10685 Ducting & CHW piping Joint Insulation (FL35) 15 04-Sep-20 18-Sep-20 0% 72 Ducting & CHW pipin
T4-IN-HVC-SF-10695 Installation & allignment of AHU Panel (FL35) 5 04-Sep-20 08-Sep-20 0% 85 Installation & allignmen
T4-IN-HVC-SF-10705 Cable Pulling & Termination for AHU Panel (FL35) 4 09-Sep-20 12-Sep-20 0% 85 Cable Pulling & Termin
T4-IN-HVC-SF-10715 AHU room acoustic Insulation (FL35) 7 19-Sep-20 25-Sep-20 0% 72 AHU room acoustic
LEVEL 36 22 14-Oct-20 04-Nov-20 32 04-Nov-20, L
T4-IN-HVC-SF-10725 Ducting & CHW piping Joint Insulation (FL36) 15 14-Oct-20 28-Oct-20 0% 32 Ducting & CHW
T4-IN-HVC-SF-10735 Installation & allignment of AHU Panel (FL36) 5 14-Oct-20 18-Oct-20 0% 40 Installation & alli
T4-IN-HVC-SF-10745 Installation & allignment of CSU Panel (FL36) 5 19-Oct-20 23-Oct-20 0% 40 Installation & al

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 60 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-HVC-SF-10755 Cable Pulling & Termination for AHU & CSU Panel (FL36) 4 24-Oct-20 27-Oct-20 0% 40 Cable Pulling &
T4-IN-HVC-SF-10765 AHU room acoustic Insulation (FL36) 7 29-Oct-20 04-Nov-20 0% 32 AHU room ac
LEVEL 37 22 14-Oct-20 04-Nov-20 32 04-Nov-20, L
T4-IN-HVC-SF-10775 Ducting & CHW piping Joint Insulation (FL37) 15 14-Oct-20 28-Oct-20 0% 32 Ducting & CHW
T4-IN-HVC-SF-10785 Installation & allignment of AHU Panel (FL37) 5 14-Oct-20 18-Oct-20 0% 45 Installation & alli
T4-IN-HVC-SF-10795 Cable Pulling & Termination for AHU Panel (FL37) 4 19-Oct-20 22-Oct-20 0% 45 Cable Pulling &
T4-IN-HVC-SF-10805 AHU room acoustic Insulation (FL37) 7 29-Oct-20 04-Nov-20 0% 32 AHU room ac
LEVEL 38 22 14-Oct-20 04-Nov-20 32 04-Nov-20, L
T4-IN-HVC-SF-10815 Ducting & CHW piping Joint Insulation (FL38) 15 14-Oct-20 28-Oct-20 0% 32 Ducting & CHW
T4-IN-HVC-SF-10825 Installation & allignment of AHU Panel (FL38) 5 14-Oct-20 18-Oct-20 0% 40 Installation & alli
T4-IN-HVC-SF-10835 Installation & allignment of CSU Panel (FL38) 5 19-Oct-20 23-Oct-20 0% 40 Installation & al
T4-IN-HVC-SF-10845 Cable Pulling & Termination for AHU & CSU Panel (FL38) 4 24-Oct-20 27-Oct-20 0% 40 Cable Pulling &
T4-IN-HVC-SF-10855 AHU room acoustic Insulation (FL38) 7 29-Oct-20 04-Nov-20 0% 32 AHU room ac
LEVEL 39 20 14-Oct-20 02-Nov-20 34 02-Nov-20, L
T4-IN-HVC-SF-10865 Ducting & CHW piping Joint Insulation (FL39) 15 14-Oct-20 28-Oct-20 0% 34 Ducting & CHW
T4-IN-HVC-SF-10875 Installation & allignment of AHU Panel (FL39) 5 14-Oct-20 18-Oct-20 0% 45 Installation & alli
T4-IN-HVC-SF-10885 Cable Pulling & Termination for AHU Panel (FL39) 4 19-Oct-20 22-Oct-20 0% 45 Cable Pulling &
T4-IN-HVC-SF-10895 AHU room acoustic Insulation (FL39) 5 29-Oct-20 02-Nov-20 0% 34 AHU room ac
LEVEL ROOF 27 28-Oct-20 23-Nov-20 4 23-Nov-20
T4-IN-HVC-SF-10905 Ducting & CHW piping Joint Insulation (ROOF) 20 28-Oct-20 16-Nov-20 0% 4 Ducting & C
T4-IN-HVC-SF-10915 Installation & allignment of CSU Panel (ROOF) 10 01-Nov-20 10-Nov-20 0% 10 Installation &
T4-IN-HVC-SF-10925 Cable Pulling & Termination for CSU Panel (ROOF) 7 11-Nov-20 17-Nov-20 0% 10 Cable Pullin
T4-IN-HVC-SF-10935 CSU room acoustic Insulation (ROOF) 7 17-Nov-20 23-Nov-20 0% 4 CSU room
ELECTRICAL 382 29-Oct-19 15-Nov-20 46 15-Nov-20,
CABLE PULLING & WIRING 370 29-Oct-19 04-Nov-20 33 04-Nov-20, C
LEVEL B2 7 29-Mar-20 05-Apr-20 59 05-Apr-20, LEVEL B2
A2070 LV Cable Pulling (B2) 4 29-Mar-20 01-Apr-20 0% 59 LV Cable Pulling (B2)
A2080 Wire Pulling & DB Installation (B2) 3 02-Apr-20 05-Apr-20 0% 59 Wire Pulling & DB Installation (B2)
LEVEL B1 7 01-Mar-20 08-Mar-20 90 08-Mar-20, LEVEL B1
A2090 LV Cable Pulling (B1) 4 01-Mar-20 04-Mar-20 0% 90 LV Cable Pulling (B1)
A2100 Wire Pulling & DB Installation (B1) 3 05-Mar-20 08-Mar-20 0% 90 Wire Pulling & DB Installation (B1)
LEVEL P0 93 15-Dec-19 18-Mar-20 80 18-Mar-20, LEVEL P0
A2110 LV Cable Pulling (P0) 4 15-Dec-19 18-Dec-19 0% 166 LV Cable Pulling (P0)
A2120 Wire Pulling & DB Installation (P0) 3 14-Mar-20 18-Mar-20 0% 80 Wire Pulling & DB Installation (P0)
LEVEL P1 7 29-Oct-19 05-Nov-19 212 05-Nov-19, LEVEL P1
A2130 LV Cable Pulling (P1) 4 29-Oct-19 01-Nov-19 0% 212 LV Cable Pulling (P1)
A2140 Wire Pulling & DB Installation (P1) 3 02-Nov-19 05-Nov-19 0% 212 Wire Pulling & DB Installation (P1)
LEVEL P2 7 29-Oct-19 05-Nov-19 47 05-Nov-19, LEVEL P2
A2150 LV Cable Pulling (P2) 4 29-Oct-19 01-Nov-19 0% 47 LV Cable Pulling (P2)
A2160 Wire Pulling & DB Installation (P2) 3 02-Nov-19 05-Nov-19 0% 47 Wire Pulling & DB Installation (P2)
LEVEL P3 7 21-Nov-19 28-Nov-19 190 28-Nov-19, LEVEL P3
A2170 LV Cable Pulling (P3) 4 21-Nov-19 24-Nov-19 0% 190 LV Cable Pulling (P3)
A2180 Wire Pulling & DB Installation (P3) 3 25-Nov-19 28-Nov-19 0% 190 Wire Pulling & DB Installation (P3)
LEVEL P4 7 21-Nov-19 28-Nov-19 190 28-Nov-19, LEVEL P4
A2190 LV Cable Pulling (P4) 4 21-Nov-19 24-Nov-19 0% 190 LV Cable Pulling (P4)
A2200 Wire Pulling & DB Installation (P4) 3 25-Nov-19 28-Nov-19 0% 190 Wire Pulling & DB Installation (P4)
LEVEL P5 7 21-Nov-19 28-Nov-19 190 28-Nov-19, LEVEL P5
A2210 LV Cable Pulling (P5) 4 21-Nov-19 24-Nov-19 0% 190 LV Cable Pulling (P5)
A2220 Wire Pulling & DB Installation (P5) 3 25-Nov-19 28-Nov-19 0% 190 Wire Pulling & DB Installation (P5)
LEVEL P6 7 21-Nov-19 28-Nov-19 190 28-Nov-19, LEVEL P6
A2230 LV Cable Pulling (P6) 4 21-Nov-19 24-Nov-19 0% 190 LV Cable Pulling (P6)
A2240 Wire Pulling & DB Installation (P6) 3 25-Nov-19 28-Nov-19 0% 190 Wire Pulling & DB Installation (P6)
LEVEL P7 7 20-Dec-19 28-Dec-19 161 28-Dec-19, LEVEL P7

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 61 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
A2250 LV Cable Pulling (P7) 4 20-Dec-19 23-Dec-19 0% 161 LV Cable Pulling (P7)
A2260 Wire Pulling & DB Installation (P7) 3 24-Dec-19 28-Dec-19 0% 161 Wire Pulling & DB Installation (P7)
LEVEL P8 7 20-Dec-19 28-Dec-19 161 28-Dec-19, LEVEL P8
A2270 LV Cable Pulling (P8) 4 20-Dec-19 23-Dec-19 0% 161 LV Cable Pulling (P8)
A2280 Wire Pulling & DB Installation (P8) 3 24-Dec-19 28-Dec-19 0% 161 Wire Pulling & DB Installation (P8)
LEVEL P9 14 15-Apr-20 29-Apr-20 38 29-Apr-20, LEVEL P9
A2290 LV Cable Pulling (P9) 4 21-Apr-20 25-Apr-20 0% 38 LV Cable Pulling (P9)
A2300 Wire Pulling & DB Installation (P9) 3 25-Apr-20 29-Apr-20 0% 38 Wire Pulling & DB Installation (P9)
LEVEL S1 7 15-Apr-20 22-Apr-20 45 22-Apr-20, LEVEL S1
A2350 LV Cable Pulling (P10) 4 15-Apr-20 18-Apr-20 0% 45 LV Cable Pulling (P10)
A2360 Wire Pulling & DB Installation (P10) 3 19-Apr-20 22-Apr-20 0% 45 Wire Pulling & DB Installation (P10)
LEVEL FL17 7 13-Mar-20 20-Mar-20 66 20-Mar-20, LEVEL FL17
A2310 LV Cable Pulling (FL17) 4 13-Mar-20 16-Mar-20 0% 66 LV Cable Pulling (FL17)
A2320 Wire Pulling & DB Installation (FL17) 3 17-Mar-20 20-Mar-20 0% 66 Wire Pulling & DB Installation (FL17)
LEVEL FL18 7 24-May-20 31-May-20 190 31-May-20, LEVEL FL18
A2330 LV Cable Pulling (FL18) 4 24-May-20 27-May-20 0% 190 LV Cable Pulling (FL18)
A2340 Wire Pulling & DB Installation (FL18) 3 28-May-20 31-May-20 0% 190 Wire Pulling & DB Installation (FL18)
LEVEL FL19 7 24-May-20 31-May-20 190 31-May-20, LEVEL FL19
A2370 LV Cable Pulling (FL19) 4 24-May-20 27-May-20 0% 190 LV Cable Pulling (FL19)
A2380 Wire Pulling & DB Installation (FL19) 3 28-May-20 31-May-20 0% 190 Wire Pulling & DB Installation (FL19)
LEVEL FL20 7 24-May-20 31-May-20 190 31-May-20, LEVEL FL20
A2390 LV Cable Pulling (FL20) 4 24-May-20 27-May-20 0% 190 LV Cable Pulling (FL20)
A2400 Wire Pulling & DB Installation (FL20) 3 28-May-20 31-May-20 0% 190 Wire Pulling & DB Installation (FL20)
LEVEL FL21 7 24-May-20 31-May-20 190 31-May-20, LEVEL FL21
A2410 LV Cable Pulling (FL21) 4 24-May-20 27-May-20 0% 190 LV Cable Pulling (FL21)
A2420 Wire Pulling & DB Installation (FL21) 3 28-May-20 31-May-20 0% 190 Wire Pulling & DB Installation (FL21)
LEVEL FL22 7 18-May-20 25-May-20 196 25-May-20, LEVEL FL22
A2430 LV Cable Pulling (FL22) 4 18-May-20 21-May-20 0% 196 LV Cable Pulling (FL22)
A2440 Wire Pulling & DB Installation (FL22) 3 22-May-20 25-May-20 0% 196 Wire Pulling & DB Installation (FL22)
LEVEL FL23 7 27-Jun-20 04-Jul-20 156 04-Jul-20, LEVEL FL23
A2450 LV Cable Pulling (FL23) 4 27-Jun-20 30-Jun-20 0% 156 LV Cable Pulling (FL23)
A2460 Wire Pulling & DB Installation (FL23) 3 01-Jul-20 04-Jul-20 0% 156 Wire Pulling & DB Installation (FL23)
LEVEL FL24 7 27-Jun-20 04-Jul-20 156 04-Jul-20, LEVEL FL24
A2470 LV Cable Pulling (FL24) 4 27-Jun-20 30-Jun-20 0% 156 LV Cable Pulling (FL24)
A2480 Wire Pulling & DB Installation (FL24) 3 01-Jul-20 04-Jul-20 0% 156 Wire Pulling & DB Installation (FL24)
LEVEL FL25 7 27-Jun-20 04-Jul-20 156 04-Jul-20, LEVEL FL25
A2490 LV Cable Pulling (FL25) 4 27-Jun-20 30-Jun-20 0% 156 LV Cable Pulling (FL25)
A2500 Wire Pulling & DB Installation (FL25) 3 01-Jul-20 04-Jul-20 0% 156 Wire Pulling & DB Installation (FL25)
LEVEL FL26 7 27-Jun-20 04-Jul-20 156 04-Jul-20, LEVEL FL26
A2510 LV Cable Pulling (FL26) 4 27-Jun-20 30-Jun-20 0% 156 LV Cable Pulling (FL26)
A2520 Wire Pulling & DB Installation (FL26) 3 01-Jul-20 04-Jul-20 0% 156 Wire Pulling & DB Installation (FL26)
LEVEL FL27 7 27-Jun-20 04-Jul-20 156 04-Jul-20, LEVEL FL27
A2530 LV Cable Pulling (FL27) 4 27-Jun-20 30-Jun-20 0% 156 LV Cable Pulling (FL27)
A2540 Wire Pulling & DB Installation (FL27) 3 01-Jul-20 04-Jul-20 0% 156 Wire Pulling & DB Installation (FL27)
LEVEL FL28 7 31-Jul-20 07-Aug-20 122 07-Aug-20, LEVEL FL28
A2550 LV Cable Pulling (FL28) 4 31-Jul-20 03-Aug-20 0% 122 LV Cable Pulling (FL28)
A2560 Wire Pulling & DB Installation (FL28) 3 04-Aug-20 07-Aug-20 0% 122 Wire Pulling & DB Installatio
LEVEL FL29 7 31-Jul-20 07-Aug-20 122 07-Aug-20, LEVEL FL29
A2570 LV Cable Pulling (FL29) 4 31-Jul-20 03-Aug-20 0% 122 LV Cable Pulling (FL29)
A2580 Wire Pulling & DB Installation (FL29) 3 04-Aug-20 07-Aug-20 0% 122 Wire Pulling & DB Installatio
LEVEL FL30 7 31-Jul-20 07-Aug-20 122 07-Aug-20, LEVEL FL30
A2590 LV Cable Pulling (FL30) 4 31-Jul-20 03-Aug-20 0% 122 LV Cable Pulling (FL30)
A2600 Wire Pulling & DB Installation (FL30) 3 04-Aug-20 07-Aug-20 0% 122 Wire Pulling & DB Installatio

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 62 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
LEVEL FL31 7 31-Jul-20 07-Aug-20 122 07-Aug-20, LEVEL FL31
A2610 LV Cable Pulling (FL31) 4 31-Jul-20 03-Aug-20 0% 122 LV Cable Pulling (FL31)
A2620 Wire Pulling & DB Installation (FL31) 3 04-Aug-20 07-Aug-20 0% 122 Wire Pulling & DB Installatio
LEVEL FL32 7 04-Sep-20 11-Sep-20 87 11-Sep-20, LEVEL FL32
A2630 LV Cable Pulling (FL32) 4 04-Sep-20 07-Sep-20 0% 87 LV Cable Pulling (FL32)
A2640 Wire Pulling & DB Installation (FL32) 3 08-Sep-20 11-Sep-20 0% 87 Wire Pulling & DB Inst
LEVEL FL33 7 04-Sep-20 11-Sep-20 87 11-Sep-20, LEVEL FL33
A2650 LV Cable Pulling (FL33) 4 04-Sep-20 07-Sep-20 0% 87 LV Cable Pulling (FL33)
A2660 Wire Pulling & DB Installation (FL33) 3 08-Sep-20 11-Sep-20 0% 87 Wire Pulling & DB Inst
LEVEL FL34 7 04-Sep-20 11-Sep-20 87 11-Sep-20, LEVEL FL34
A2670 LV Cable Pulling (FL34) 4 04-Sep-20 07-Sep-20 0% 87 LV Cable Pulling (FL34)
A2680 Wire Pulling & DB Installation (FL34) 3 08-Sep-20 11-Sep-20 0% 87 Wire Pulling & DB Inst
LEVEL FL35 7 04-Sep-20 11-Sep-20 87 11-Sep-20, LEVEL FL35
A2690 LV Cable Pulling (FL35) 4 04-Sep-20 07-Sep-20 0% 87 LV Cable Pulling (FL35)
A2700 Wire Pulling & DB Installation (FL35) 3 08-Sep-20 11-Sep-20 0% 87 Wire Pulling & DB Inst
LEVEL FL36 7 14-Oct-20 21-Oct-20 47 21-Oct-20, LEV
A2710 LV Cable Pulling (FL36) 4 14-Oct-20 17-Oct-20 0% 47 LV Cable Pulling
A2720 Wire Pulling & DB Installation (FL36) 3 18-Oct-20 21-Oct-20 0% 47 Wire Pulling & D
LEVEL FL37 7 14-Oct-20 21-Oct-20 47 21-Oct-20, LEV
A2730 LV Cable Pulling (FL37) 4 14-Oct-20 17-Oct-20 0% 47 LV Cable Pulling
A2740 Wire Pulling & DB Installation (FL37) 3 18-Oct-20 21-Oct-20 0% 47 Wire Pulling & D
LEVEL FL38 7 14-Oct-20 21-Oct-20 47 21-Oct-20, LEV
A2750 LV Cable Pulling (FL38) 4 14-Oct-20 17-Oct-20 0% 47 LV Cable Pulling
A2760 Wire Pulling & DB Installation (FL38) 3 18-Oct-20 21-Oct-20 0% 47 Wire Pulling & D
LEVEL FL39 7 14-Oct-20 21-Oct-20 47 21-Oct-20, LEV
A2770 LV Cable Pulling (FL39) 4 14-Oct-20 17-Oct-20 0% 47 LV Cable Pulling
A2780 Wire Pulling & DB Installation (FL39) 3 18-Oct-20 21-Oct-20 0% 47 Wire Pulling & D
LEVEL ROOF 7 28-Oct-20 04-Nov-20 24 04-Nov-20, L
A2790 LV Cable Pulling (ROOF) 4 28-Oct-20 31-Oct-20 0% 24 LV Cable Pulli
A2800 Wire Pulling & DB Installation (ROOF) 3 01-Nov-20 04-Nov-20 0% 24 Wire Pulling &
PANEL INSTALLATION 356 24-Nov-19 15-Nov-20 46 15-Nov-20,
SMDB'S/ METERING PANELS / MCC PANELS 260 01-Mar-20 15-Nov-20 46 15-Nov-20,
LEVEL B2 16 29-Mar-20 13-Apr-20 78 13-Apr-20, LEVEL B2
SMDB'S / MDB PANELS 16 29-Mar-20 13-Apr-20 78 13-Apr-20, SMDB'S / MDB PANELS
T4-IN-ELE-SF-3105 Installation & allignment of SMDB / MDB Panel (B2) 7 29-Mar-20 04-Apr-20 0% 78 Installation & allignment of SMDB / MDB Panel (B2)
T4-IN-ELE-SF-3115 Cable Tray installation upto alley (B2) 2 05-Apr-20 06-Apr-20 0% 78 Cable Tray installation upto alley (B2)
T4-IN-ELE-SF-3125 Horizontal cable laying (B2) 3 07-Apr-20 10-Apr-20 0% 78 Horizontal cable laying (B2)
T4-IN-ELE-SF-3135 Cable termination (B2) 3 10-Apr-20 13-Apr-20 0% 78 Cable termination (B2)
MCC PANELS 16 29-Mar-20 13-Apr-20 78 13-Apr-20, MCC PANELS
T4-IN-ELE-SF-3145 Installation & allignment of MCC Panel (B2) 7 29-Mar-20 04-Apr-20 0% 78 Installation & allignment of MCC Panel (B2)
T4-IN-ELE-SF-3155 Cable Tray installation upto alley (B2) 2 05-Apr-20 06-Apr-20 0% 78 Cable Tray installation upto alley (B2)
T4-IN-ELE-SF-3165 Horizontal cable laying (B2) 3 07-Apr-20 10-Apr-20 0% 78 Horizontal cable laying (B2)
T4-IN-ELE-SF-3175 Cable termination (B2) 3 10-Apr-20 13-Apr-20 0% 78 Cable termination (B2)
LEVEL B1 19 01-Mar-20 19-Mar-20 103 19-Mar-20, LEVEL B1
SMDB PANELS 19 01-Mar-20 19-Mar-20 103 19-Mar-20, SMDB PANELS
T4-IN-ELE-SF-3185 Installation & allignment of SMDB Panels (B1) 9 01-Mar-20 09-Mar-20 0% 103 Installation & allignment of SMDB Panels (B1)
T4-IN-ELE-SF-3195 Cable Tray installation upto alley (B1) 2 11-Mar-20 12-Mar-20 0% 103 Cable Tray installation upto alley (B1)
T4-IN-ELE-SF-3205 Horizontal cable laying (B1) 3 13-Mar-20 16-Mar-20 0% 103 Horizontal cable laying (B1)
T4-IN-ELE-SF-3215 Cable termination (B1) 3 16-Mar-20 19-Mar-20 0% 103 Cable termination (B1)
MCC / FIRE PANELS 19 01-Mar-20 19-Mar-20 103 19-Mar-20, MCC / FIRE PANELS
T4-IN-ELE-SF-3645 Installation & allignment of MCC / FP Panels (B1) 9 01-Mar-20 09-Mar-20 0% 103 Installation & allignment of MCC / FP Panels (B1)
T4-IN-ELE-SF-3655 Cable Tray installation upto alley (B1) 2 11-Mar-20 12-Mar-20 0% 103 Cable Tray installation upto alley (B1)
T4-IN-ELE-SF-3665 Horizontal cable laying (B1) 3 13-Mar-20 16-Mar-20 0% 103 Horizontal cable laying (B1)

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 63 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-ELE-SF-3675 Cable termination (B1) 3 16-Mar-20 19-Mar-20 0% 103 Cable termination (B1)
LEVEL S1 19 15-Apr-20 03-May-20 58 03-May-20, LEVEL S1
MCC PANELS 19 15-Apr-20 03-May-20 58 03-May-20, MCC PANELS
T4-IN-ELE-SF-3225 Installation & allignment of MCC Panels (S1) 9 15-Apr-20 23-Apr-20 0% 58 Installation & allignment of MCC Panels (S1)
T4-IN-ELE-SF-3235 Cable Tray installation upto alley (S1) 2 25-Apr-20 26-Apr-20 0% 58 Cable Tray installation upto alley (S1)
T4-IN-ELE-SF-3245 Horizontal cable laying (S1) 3 27-Apr-20 30-Apr-20 0% 58 Horizontal cable laying (S1)
T4-IN-ELE-SF-3255 Cable termination (S1) 3 30-Apr-20 03-May-20 0% 58 Cable termination (S1)
LEVEL 22 19 18-May-20 05-Jun-20 25 05-Jun-20, LEVEL 22
MCC PANELS 19 18-May-20 05-Jun-20 25 05-Jun-20, MCC PANELS
T4-IN-ELE-SF-3265 Installation & allignment of MCC Panels (FL22) 9 18-May-20 26-May-20 0% 25 Installation & allignment of MCC Panels
T4-IN-ELE-SF-3275 Cable Tray installation upto alley (FL22) 2 28-May-20 29-May-20 0% 25 Cable Tray installation upto alley (FL22)
T4-IN-ELE-SF-3285 Horizontal cable laying (FL22) 3 30-May-20 02-Jun-20 0% 25 Horizontal cable laying (FL22)
T4-IN-ELE-SF-3295 Cable termination (FL22) 3 02-Jun-20 05-Jun-20 0% 25 Cable termination (FL22)
SMDB PANELS 16 18-May-20 02-Jun-20 28 02-Jun-20, SMDB PANELS
T4-IN-ELE-SF-3305 Installation & allignment of SMDB Panel (FL22) 7 18-May-20 24-May-20 0% 28 Installation & allignment of SMDB Panel (
T4-IN-ELE-SF-3315 Cable Tray installation upto alley (FL22) 2 25-May-20 26-May-20 0% 28 Cable Tray installation upto alley (FL22)
T4-IN-ELE-SF-3325 Horizontal cable laying (FL22) 3 27-May-20 30-May-20 0% 28 Horizontal cable laying (FL22)
T4-IN-ELE-SF-3335 Cable termination (FL22) 3 30-May-20 02-Jun-20 0% 28 Cable termination (FL22)
LEVEL ROOF 19 28-Oct-20 15-Nov-20 46 15-Nov-20,
MCC PANELS 19 28-Oct-20 15-Nov-20 46 15-Nov-20,
T4-IN-ELE-SF-3345 Installation & allignment of MCC Panels (ROOF) 9 28-Oct-20 05-Nov-20 0% 46 Installation &
T4-IN-ELE-SF-3355 Cable Tray installation upto alley (ROOF) 2 07-Nov-20 08-Nov-20 0% 46 Cable Tray in
T4-IN-ELE-SF-3365 Horizontal cable laying (ROOF) 3 09-Nov-20 12-Nov-20 0% 46 Horizontal c
T4-IN-ELE-SF-3375 Cable termination (ROOF) 3 12-Nov-20 15-Nov-20 0% 46 Cable term
COMMON DISTRIBUTION BOARDS 341 24-Nov-19 31-Oct-20 61 31-Oct-20, CO
LEVEL B2 4 29-Mar-20 01-Apr-20 90 01-Apr-20, LEVEL B2
T4-IN-ELE-SF-3385 Installation of LDB's & PDB's (B2) 2 29-Mar-20 30-Mar-20 0% 90 Installation of LDB's & PDB's (B2)
T4-IN-ELE-SF-3395 DB Dressing (B2) 2 31-Mar-20 01-Apr-20 0% 90 DB Dressing (B2)
LEVEL B1 4 01-Mar-20 04-Mar-20 118 04-Mar-20, LEVEL B1
T4-IN-ELE-SF-3405 Installation of LDB's & PDB's (B1) 2 01-Mar-20 02-Mar-20 0% 118 Installation of LDB's & PDB's (B1)
T4-IN-ELE-SF-3415 DB Dressing (B1) 2 03-Mar-20 04-Mar-20 0% 118 DB Dressing (B1)
LEVEL P0 4 15-Dec-19 18-Dec-19 194 18-Dec-19, LEVEL P0
T4-IN-ELE-SF-3425 Installation of LDB's & PDB's (P0) 2 15-Dec-19 16-Dec-19 0% 194 Installation of LDB's & PDB's (P0)
T4-IN-ELE-SF-3435 DB Dressing (P0) 2 17-Dec-19 18-Dec-19 0% 194 DB Dressing (P0)
LEVEL P2 4 24-Nov-19 28-Nov-19 214 28-Nov-19, LEVEL P2
T4-IN-ELE-SF-3445 Installation of LDB's & PDB's (P2) 2 24-Nov-19 26-Nov-19 0% 214 Installation of LDB's & PDB's (P2)
T4-IN-ELE-SF-3455 DB Dressing (P2) 2 26-Nov-19 28-Nov-19 0% 214 DB Dressing (P2)
LEVEL P4 4 24-Nov-19 28-Nov-19 214 28-Nov-19, LEVEL P4
T4-IN-ELE-SF-3465 Installation of LDB's & PDB's (P4) 2 24-Nov-19 26-Nov-19 0% 214 Installation of LDB's & PDB's (P4)
T4-IN-ELE-SF-3475 DB Dressing (P4) 2 26-Nov-19 28-Nov-19 0% 214 DB Dressing (P4)
LEVEL S1 4 24-Nov-19 28-Nov-19 214 28-Nov-19, LEVEL S1
T4-IN-ELE-SF-3485 Installation of LDB's & PDB's (S1) 2 24-Nov-19 26-Nov-19 0% 214 Installation of LDB's & PDB's (S1)
T4-IN-ELE-SF-3495 DB Dressing (S1) 2 26-Nov-19 28-Nov-19 0% 214 DB Dressing (S1)
LEVEL 14 4 10-Mar-20 14-Mar-20 108 14-Mar-20, LEVEL 14
T4-IN-ELE-SF-3505 Installation of LDB's & PDB's (FL14) 2 10-Mar-20 12-Mar-20 0% 108 Installation of LDB's & PDB's (FL14)
T4-IN-ELE-SF-3515 DB Dressing (FL14) 2 12-Mar-20 14-Mar-20 0% 108 DB Dressing (FL14)
LEVEL 18 4 24-May-20 27-May-20 218 27-May-20, LEVEL 18
T4-IN-ELE-SF-3525 Installation of LDB's & PDB's (FL18) 2 24-May-20 25-May-20 0% 218 Installation of LDB's & PDB's (FL18)
T4-IN-ELE-SF-3535 DB Dressing (FL18) 2 26-May-20 27-May-20 0% 218 DB Dressing (FL18)
LEVEL 22 4 18-May-20 21-May-20 40 21-May-20, LEVEL 22
T4-IN-ELE-SF-3545 Installation of LDB's & PDB's (FL22) 2 18-May-20 19-May-20 0% 40 Installation of LDB's & PDB's (FL22)
T4-IN-ELE-SF-3555 DB Dressing (FL22) 2 20-May-20 21-May-20 0% 40 DB Dressing (FL22)
LEVEL 27 4 27-Jun-20 30-Jun-20 184 30-Jun-20, LEVEL 27

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 64 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-ELE-SF-3565 Installation of LDB's & PDB's (FL27) 2 27-Jun-20 28-Jun-20 0% 184 Installation of LDB's & PDB's (FL27)
T4-IN-ELE-SF-3575 DB Dressing (FL27) 2 29-Jun-20 30-Jun-20 0% 184 DB Dressing (FL27)
LEVEL 32 4 04-Sep-20 07-Sep-20 115 07-Sep-20, LEVEL 32
T4-IN-ELE-SF-3585 Installation of LDB's & PDB's (FL32) 2 04-Sep-20 05-Sep-20 0% 115 Installation of LDB's & P
T4-IN-ELE-SF-3595 DB Dressing (FL32) 2 06-Sep-20 07-Sep-20 0% 115 DB Dressing (FL32)
LEVEL 36 4 14-Oct-20 17-Oct-20 75 17-Oct-20, LEVEL 36
T4-IN-ELE-SF-3605 Installation of LDB's & PDB's (FL36) 2 14-Oct-20 15-Oct-20 0% 75 Installation of LD
T4-IN-ELE-SF-3615 DB Dressing (FL36) 2 16-Oct-20 17-Oct-20 0% 75 DB Dressing (FL36)
LEVEL ROOF 4 28-Oct-20 31-Oct-20 61 31-Oct-20, LE
T4-IN-ELE-SF-3625 Installation of LDB's & PDB's (ROOF) 2 28-Oct-20 29-Oct-20 0% 61 Installation of L
T4-IN-ELE-SF-3635 DB Dressing (ROOF) 2 30-Oct-20 31-Oct-20 0% 61 DB Dressing (
INVERTOR INSTALLATION 35 01-Mar-20 04-Apr-20 87 04-Apr-20, INVERTOR INSTALLATION
T4-IN-ELE- SF-3695 Access to Commence Invertor Installation Works (UPS) 0 01-Mar-20 0% 87 Access to Commence Invertor Installation Works (UPS)
T4-IN-ELE- SF-3700 Installation of Cable Trays/ Trunking (UPS) 7 01-Mar-20 07-Mar-20 0% 87 Installation of Cable Trays/ Trunking (UPS)
T4-IN-ELE- SF-3702 Instalation of Earthing (UPS) 5 08-Mar-20 12-Mar-20 0% 87 Instalation of Earthing (UPS)
T4-IN-ELE- SF-3705 Installation of Invertor Panels (UPS) 10 13-Mar-20 22-Mar-20 0% 87 Installation of Invertor Panels (UPS)
T4-IN-ELE- SF-3715 Installation of Batteries (UPS) 3 23-Mar-20 25-Mar-20 0% 87 Installation of Batteries (UPS)
T4-IN-ELE- SF-3725 Installation of LV Cable & Gland Termination (UPS) 5 26-Mar-20 30-Mar-20 0% 87 Installation of LV Cable & Gland Termination (UPS)
T4-IN-ELE- SF-3735 Testing & Commissioning 5 31-Mar-20 04-Apr-20 0% 87 Testing & Commissioning
AVIATION LIGHTS 13 28-Oct-20 10-Nov-20 51 10-Nov-20, A
T4-IN-ELE- SF-3645 Access to Commence Aviation Light Works (Roof) 0 28-Oct-20 0% 51 Access to Com
T4-IN-ELE- SF-3655 Installation of Supports (Roof) 3 28-Oct-20 31-Oct-20 0% 51 Installation of
T4-IN-ELE- SF-3665 Installation of Aviation Lights (Roof) 3 31-Oct-20 03-Nov-20 0% 51 Installation of
T4-IN-ELE- SF-3670 Installation of Control Panel (Roof) 3 03-Nov-20 06-Nov-20 0% 51 Installation of
T4-IN-ELE- SF-3675 Cable Laying & Termination Work (Roof) 3 07-Nov-20 10-Nov-20 0% 51 Cable Laying
MODULAR FOR SUPREMUS FLOORS 47 09-Feb-20 26-Mar-20 71 26-Mar-20, MODULAR FOR SUPREMUS FLOORS
LEVEL 09 12 14-Mar-20 26-Mar-20 71 26-Mar-20, LEVEL 09
T4-MOD-ALL-SF-3590 Cable Pulling through Modules (FL09) 10 14-Mar-20 24-Mar-20 0% 71 Cable Pulling through Modules (FL09)
T4-MOD-ALL-SF-3600 Cable Testing (FL09) 2 24-Mar-20 26-Mar-20 0% 71 Cable Testing (FL09)
LEVEL 10 12 09-Feb-20 20-Feb-20 106 20-Feb-20, LEVEL 10
T4-MOD-ALL-SF-3610 Cable Pulling through Modules (FL10) 10 09-Feb-20 18-Feb-20 0% 106 Cable Pulling through Modules (FL10)
T4-MOD-ALL-SF-3620 Cable Testing (FL10) 2 19-Feb-20 20-Feb-20 0% 106 Cable Testing (FL10)
LEVEL 11 12 09-Feb-20 20-Feb-20 106 20-Feb-20, LEVEL 11
T4-MOD-ALL-SF-3630 Cable Pulling through Modules (FL11) 10 09-Feb-20 18-Feb-20 0% 106 Cable Pulling through Modules (FL11)
T4-MOD-ALL-SF-3640 Cable Testing (FL11) 2 19-Feb-20 20-Feb-20 0% 106 Cable Testing (FL11)
LEVEL 12 12 09-Feb-20 20-Feb-20 106 20-Feb-20, LEVEL 12
T4-MOD-ALL-SF-3650 Cable Pulling through Modules (FL12) 10 09-Feb-20 18-Feb-20 0% 106 Cable Pulling through Modules (FL12)
T4-MOD-ALL-SF-3660 Cable Testing (FL12) 2 19-Feb-20 20-Feb-20 0% 106 Cable Testing (FL12)
LEVEL 14 12 10-Mar-20 22-Mar-20 76 22-Mar-20, LEVEL 14
T4-MOD-ALL-SF-3670 Cable Pulling through Modules (FL14) 10 10-Mar-20 20-Mar-20 0% 76 Cable Pulling through Modules (FL14)
T4-MOD-ALL-SF-3680 Cable Testing (FL14) 2 20-Mar-20 22-Mar-20 0% 76 Cable Testing (FL14)
LEVEL 15 12 13-Mar-20 25-Mar-20 73 25-Mar-20, LEVEL 15
T4-MOD-ALL-SF-3690 Cable Pulling through Modules (FL15) 10 13-Mar-20 23-Mar-20 0% 73 Cable Pulling through Modules (FL15)
T4-MOD-ALL-SF-3700 Cable Testing (FL15) 2 23-Mar-20 25-Mar-20 0% 73 Cable Testing (FL15)
LEVEL 16 12 14-Mar-20 26-Mar-20 72 26-Mar-20, LEVEL 16
T4-MOD-ALL-SF-3710 Cable Pulling through Modules (FL16) 10 14-Mar-20 24-Mar-20 0% 72 Cable Pulling through Modules (FL16)
T4-MOD-ALL-SF-3720 Cable Testing (FL16) 2 24-Mar-20 26-Mar-20 0% 72 Cable Testing (FL16)
HANDOVER TO CLIENT 374 18-Nov-19 27-Nov-20 9 27-Nov-2
T4-IN-HAN-SF-4000 2nd Fix Handover to Civil from MEP (B2) 0 28-Apr-20 0% 35 2nd Fix Handover to Civil from MEP (B2)
T4-IN-HAN-SF-4060 2nd Fix Handover to Civil from MEP (B1) 0 30-Mar-20 0% 67 2nd Fix Handover to Civil from MEP (B1)
T4-IN-HAN-SF-4120 2nd Fix Handover to Civil from MEP (P0) 0 18-Mar-20 0% 80 2nd Fix Handover to Civil from MEP (P0)
T4-IN-HAN-SF-4180 2nd Fix Handover to Civil from MEP (P1) 0 18-Nov-19 0% 199 2nd Fix Handover to Civil from MEP (P1)
T4-IN-HAN-SF-4240 2nd Fix Handover to Civil from MEP (P2) 0 21-Nov-19 0% 31 2nd Fix Handover to Civil from MEP (P2)

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 65 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-HAN-SF-4300 2nd Fix Handover to Civil from MEP (P3) 0 12-Dec-19 0% 175 2nd Fix Handover to Civil from MEP (P3)
T4-IN-HAN-SF-4360 2nd Fix Handover to Civil from MEP (P4) 0 12-Dec-19 0% 175 2nd Fix Handover to Civil from MEP (P4)
T4-IN-HAN-SF-4420 2nd Fix Handover to Civil from MEP (P5) 0 12-Dec-19 0% 175 2nd Fix Handover to Civil from MEP (P5)
T4-IN-HAN-SF-4480 2nd Fix Handover to Civil from MEP (P6) 0 12-Dec-19 0% 175 2nd Fix Handover to Civil from MEP (P6)
T4-IN-HAN-SF-4540 2nd Fix Handover to Civil from MEP (P7) 0 10-Jan-20 0% 147 2nd Fix Handover to Civil from MEP (P7)
T4-IN-HAN-SF-4600 2nd Fix Handover to Civil from MEP (P8) 0 10-Jan-20 0% 147 2nd Fix Handover to Civil from MEP (P8)
T4-IN-HAN-SF-4660 2nd Fix Handover to Civil from MEP (P9) 0 29-Apr-20 0% 38 2nd Fix Handover to Civil from MEP (P9)
T4-IN-HAN-SF-4720 2nd Fix Handover to Civil from MEP (P10) 0 22-Apr-20 0% 45 2nd Fix Handover to Civil from MEP (P10)
T4-IN-HAN-SF-4730 2nd Fix Handover to Civil from MEP (FL09) 0 27-Mar-20 0% 70 2nd Fix Handover to Civil from MEP (FL09)
T4-IN-HAN-SF-4740 2nd Fix Handover to Civil from MEP (FL10) 0 20-Feb-20 0% 106 2nd Fix Handover to Civil from MEP (FL10)
T4-IN-HAN-SF-4750 2nd Fix Handover to Civil from MEP (FL11) 0 20-Feb-20 0% 106 2nd Fix Handover to Civil from MEP (FL11)
T4-IN-HAN-SF-4760 2nd Fix Handover to Civil from MEP (FL12) 0 20-Feb-20 0% 106 2nd Fix Handover to Civil from MEP (FL12)
T4-IN-HAN-SF-4765 2nd Fix Handover to Civil from MEP (FL14) 0 22-Mar-20 0% 76 2nd Fix Handover to Civil from MEP (FL14)
T4-IN-HAN-SF-4770 2nd Fix Handover to Civil from MEP (FL15) 0 25-Mar-20 0% 73 2nd Fix Handover to Civil from MEP (FL15)
T4-IN-HAN-SF-4775 2nd Fix Handover to Civil from MEP (FL16) 0 26-Mar-20 0% 72 2nd Fix Handover to Civil from MEP (FL16)
T4-IN-HAN-SF-4780 2nd Fix Handover to Civil from MEP (FL17) 0 24-May-20 0% 0 2nd Fix Handover to Civil from MEP (FL17)
T4-IN-HAN-SF-4840 2nd Fix Handover to Civil from MEP (FL18) 0 14-Jun-20 0% 175 2nd Fix Handover to Civil from MEP
T4-IN-HAN-SF-4900 2nd Fix Handover to Civil from MEP (FL19) 0 14-Jun-20 0% 175 2nd Fix Handover to Civil from MEP
T4-IN-HAN-SF-4960 2nd Fix Handover to Civil from MEP (FL20) 0 14-Jun-20 0% 175 2nd Fix Handover to Civil from MEP
T4-IN-HAN-SF-5020 2nd Fix Handover to Civil from MEP (FL21) 0 14-Jun-20 0% 175 2nd Fix Handover to Civil from MEP
T4-IN-HAN-SF-5080 2nd Fix Handover to Civil from MEP (FL22) 0 17-Jun-20 0% 172 2nd Fix Handover to Civil from MEP
T4-IN-HAN-SF-5140 2nd Fix Handover to Civil from MEP (FL23) 0 18-Jul-20 0% 141 2nd Fix Handover to Civil from
T4-IN-HAN-SF-5200 2nd Fix Handover to Civil from MEP (FL24) 0 18-Jul-20 0% 141 2nd Fix Handover to Civil from
T4-IN-HAN-SF-5260 2nd Fix Handover to Civil from MEP (FL25) 0 18-Jul-20 0% 141 2nd Fix Handover to Civil from
T4-IN-HAN-SF-5320 2nd Fix Handover to Civil from MEP (FL26) 0 18-Jul-20 0% 141 2nd Fix Handover to Civil from
T4-IN-HAN-SF-5380 2nd Fix Handover to Civil from MEP (FL27) 0 18-Jul-20 0% 141 2nd Fix Handover to Civil from
T4-IN-HAN-SF-5440 2nd Fix Handover to Civil from MEP (FL28) 0 21-Aug-20 0% 107 2nd Fix Handover to Civil
T4-IN-HAN-SF-5500 2nd Fix Handover to Civil from MEP (FL29) 0 21-Aug-20 0% 107 2nd Fix Handover to Civil
T4-IN-HAN-SF-5560 2nd Fix Handover to Civil from MEP (FL30) 0 21-Aug-20 0% 107 2nd Fix Handover to Civil
T4-IN-HAN-SF-5620 2nd Fix Handover to Civil from MEP (FL31) 0 21-Aug-20 0% 107 2nd Fix Handover to Civil
T4-IN-HAN-SF-5680 2nd Fix Handover to Civil from MEP (FL32) 0 25-Sep-20 0% 72 2nd Fix Handover to
T4-IN-HAN-SF-5740 2nd Fix Handover to Civil from MEP (FL33) 0 25-Sep-20 0% 72 2nd Fix Handover to
T4-IN-HAN-SF-5800 2nd Fix Handover to Civil from MEP (FL34) 0 25-Sep-20 0% 72 2nd Fix Handover to
T4-IN-HAN-SF-5860 2nd Fix Handover to Civil from MEP (FL35) 0 25-Sep-20 0% 72 2nd Fix Handover to
T4-IN-HAN-SF-5920 2nd Fix Handover to Civil from MEP (FL36) 0 04-Nov-20 0% 32 2nd Fix Hand
T4-IN-HAN-SF-5980 2nd Fix Handover to Civil from MEP (FL37) 0 04-Nov-20 0% 32 2nd Fix Hand
T4-IN-HAN-SF-6040 2nd Fix Handover to Civil from MEP (FL38) 0 04-Nov-20 0% 32 2nd Fix Hand
T4-IN-HAN-SF-6100 2nd Fix Handover to Civil from MEP (FL39) 0 04-Nov-20 0% 32 2nd Fix Hand
T4-IN-HAN-SF-6160 2nd Fix Handover to Civil from MEP (ROOF) 0 27-Nov-20 0% 0 2nd Fix H
FINAL FIX 378 03-Dec-19 15-Dec-20 16 15-De
ACCESS FROM CLIENT FINAL FIX 370 03-Dec-19 08-Dec-20 16 08-Dec
T4-IN-ACC-FNF-1010 Access required from Client for Final Fix at B2 3 13-May-20 16-May-20 0% 35 Access required from Client for Final Fix at B2
T4-IN-ACC-FNF-1020 Access required from Client for Final Fix at B1 3 14-Apr-20 17-Apr-20 0% 67 Access required from Client for Final Fix at B1
T4-IN-ACC-FNF-1030 Access required from Client for Final Fix at P0 3 01-Apr-20 04-Apr-20 0% 80 Access required from Client for Final Fix at P0
T4-IN-ACC-FNF-1040 Access required from Client for Final Fix at P1 3 03-Dec-19 06-Dec-19 0% 199 Access required from Client for Final Fix at P1
T4-IN-ACC-FNF-1050 Access required from Client for Final Fix at P2 3 05-Dec-19 09-Dec-19 0% 196 Access required from Client for Final Fix at P2
T4-IN-ACC-FNF-1060 Access required from Client for Final Fix at P3 3 28-Dec-19 31-Dec-19 0% 175 Access required from Client for Final Fix at P3
T4-IN-ACC-FNF-1070 Access required from Client for Final Fix at P4 3 28-Dec-19 31-Dec-19 0% 175 Access required from Client for Final Fix at P4
T4-IN-ACC-FNF-1080 Access required from Client for Final Fix at P5 3 28-Dec-19 31-Dec-19 0% 175 Access required from Client for Final Fix at P5
T4-IN-ACC-FNF-1090 Access required from Client for Final Fix at P6 3 28-Dec-19 31-Dec-19 0% 175 Access required from Client for Final Fix at P6
T4-IN-ACC-FNF-1100 Access required from Client for Final Fix at P7 3 25-Jan-20 28-Jan-20 0% 147 Access required from Client for Final Fix at P7

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 66 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-ACC-FNF-1110 Access required from Client for Final Fix at P8 3 25-Jan-20 28-Jan-20 0% 147 Access required from Client for Final Fix at P8
T4-IN-ACC-FNF-1120 Access required from Client for Final Fix at P9 3 13-May-20 16-May-20 0% 38 Access required from Client for Final Fix at P9
T4-IN-ACC-FNF-1130 Access required from Client for Final Fix at P10 3 06-May-20 09-May-20 0% 45 Access required from Client for Final Fix at P10
T4-IN-ACC-FNF-1140 Access required from Client for Final Fix at FL09 3 10-Apr-20 14-Apr-20 0% 70 Access required from Client for Final Fix at FL09
T4-IN-ACC-FNF-1150 Access required from Client for Final Fix at FL10 3 06-Mar-20 09-Mar-20 0% 106 Access required from Client for Final Fix at FL10
T4-IN-ACC-FNF-1160 Access required from Client for Final Fix at FL11 3 06-Mar-20 09-Mar-20 0% 106 Access required from Client for Final Fix at FL11
T4-IN-ACC-FNF-1170 Access required from Client for Final Fix at FL12 3 06-Mar-20 09-Mar-20 0% 106 Access required from Client for Final Fix at FL12
T4-IN-ACC-FNF-1180 Access required from Client for Final Fix at FL14 3 05-Apr-20 08-Apr-20 0% 76 Access required from Client for Final Fix at FL14
T4-IN-ACC-FNF-1190 Access required from Client for Final Fix at FL15 3 08-Apr-20 11-Apr-20 0% 73 Access required from Client for Final Fix at FL15
T4-IN-ACC-FNF-1200 Access required from Client for Final Fix at FL16 3 09-Apr-20 12-Apr-20 0% 72 Access required from Client for Final Fix at FL16
T4-IN-ACC-FNF-1210 Access required from Client for Final Fix at FL17 3 07-Jun-20 11-Jun-20 0% 0 Access required from Client for Final F
T4-IN-ACC-FNF-1220 Access required from Client for Final Fix at FL18 3 29-Jun-20 02-Jul-20 0% 175 Access required from Client for Fin
T4-IN-ACC-FNF-1230 Access required from Client for Final Fix at FL19 3 29-Jun-20 02-Jul-20 0% 175 Access required from Client for Fin
T4-IN-ACC-FNF-1240 Access required from Client for Final Fix at FL20 3 29-Jun-20 02-Jul-20 0% 175 Access required from Client for Fin
T4-IN-ACC-FNF-1250 Access required from Client for Final Fix at FL21 3 29-Jun-20 02-Jul-20 0% 175 Access required from Client for Fin
T4-IN-ACC-FNF-1260 Access required from Client for Final Fix at FL22 3 02-Jul-20 05-Jul-20 0% 172 Access required from Client for Fi
T4-IN-ACC-FNF-1270 Access required from Client for Final Fix at FL23 3 02-Aug-20 05-Aug-20 0% 141 Access required from Client
T4-IN-ACC-FNF-1280 Access required from Client for Final Fix at FL24 3 02-Aug-20 05-Aug-20 0% 141 Access required from Client
T4-IN-ACC-FNF-1290 Access required from Client for Final Fix at FL25 3 02-Aug-20 05-Aug-20 0% 141 Access required from Client
T4-IN-ACC-FNF-1300 Access required from Client for Final Fix at FL26 3 02-Aug-20 05-Aug-20 0% 141 Access required from Client
T4-IN-ACC-FNF-1310 Access required from Client for Final Fix at FL27 3 02-Aug-20 05-Aug-20 0% 141 Access required from Client
T4-IN-ACC-FNF-1320 Access required from Client for Final Fix at FL28 3 05-Sep-20 08-Sep-20 0% 107 Access required from C
T4-IN-ACC-FNF-1330 Access required from Client for Final Fix at FL29 3 05-Sep-20 08-Sep-20 0% 107 Access required from C
T4-IN-ACC-FNF-1340 Access required from Client for Final Fix at FL30 3 05-Sep-20 08-Sep-20 0% 107 Access required from C
T4-IN-ACC-FNF-1350 Access required from Client for Final Fix at FL31 3 05-Sep-20 08-Sep-20 0% 107 Access required from C
T4-IN-ACC-FNF-1360 Access required from Client for Final Fix at FL32 3 10-Oct-20 13-Oct-20 0% 72 Access required f
T4-IN-ACC-FNF-1370 Access required from Client for Final Fix at FL33 3 10-Oct-20 13-Oct-20 0% 72 Access required f
T4-IN-ACC-FNF-1380 Access required from Client for Final Fix at FL34 3 10-Oct-20 13-Oct-20 0% 72 Access required f
T4-IN-ACC-FNF-1390 Access required from Client for Final Fix at FL35 3 10-Oct-20 13-Oct-20 0% 72 Access required f
T4-IN-ACC-FNF-1400 Access required from Client for Final Fix at FL36 3 19-Nov-20 22-Nov-20 0% 32 Access req
T4-IN-ACC-FNF-1410 Access required from Client for Final Fix at FL37 3 19-Nov-20 22-Nov-20 0% 32 Access req
T4-IN-ACC-FNF-1420 Access required from Client for Final Fix at FL38 3 19-Nov-20 22-Nov-20 0% 32 Access req
T4-IN-ACC-FNF-1430 Access required from Client for Final Fix at FL39 3 19-Nov-20 22-Nov-20 0% 32 Access req
T4-IN-ACC-FNF-1440 Access required from Client for Final Fix at ROOF 3 05-Dec-20 08-Dec-20 0% 0 Access
PHE/ FF 374 06-Dec-19 15-Dec-20 16 15-De
LEVEL B2 10 16-May-20 26-May-20 35 26-May-20, LEVEL B2
T4-IN-PHE-FNF-1450 Installation of Plumbing / CP Fittings (B2) 3 16-May-20 19-May-20 0% 35 Installation of Plumbing / CP Fittings (B2)
T4-IN-PHE-FNF-1460 Installation of Fire Hydrant Accessories & Signages (B2) 3 19-May-20 22-May-20 0% 35 Installation of Fire Hydrant Accessories &
T4-IN-PHE-FNF-1470 Installation of Pendant Sprinklers & Final Painting (B2) 4 22-May-20 26-May-20 0% 35 Installation of Pendant Sprinklers & Final
LEVEL B1 7 17-Apr-20 24-Apr-20 67 24-Apr-20, LEVEL B1
T4-IN-PHE-FNF-1480 Installation of Plumbing / CP Fittings (B1) 3 17-Apr-20 20-Apr-20 0% 67 Installation of Plumbing / CP Fittings (B1)
T4-IN-PHE-FNF-1490 Installation of Fire Hydrant Accessories & Signages (B1) 3 20-Apr-20 23-Apr-20 0% 67 Installation of Fire Hydrant Accessories & Sign
T4-IN-PHE-FNF-1500 Installation of Pendant Sprinklers & Final Painting (B1) 4 20-Apr-20 24-Apr-20 0% 67 Installation of Pendant Sprinklers & Final Pain
LEVEL P0 7 04-Apr-20 11-Apr-20 80 11-Apr-20, LEVEL P0
T4-IN-PHE-FNF-1510 Installation of Plumbing / CP Fittings (P0) 3 04-Apr-20 07-Apr-20 0% 80 Installation of Plumbing / CP Fittings (P0)
T4-IN-PHE-FNF-1520 Installation of Fire Hydrant Accessories & Signages (P0) 3 07-Apr-20 10-Apr-20 0% 80 Installation of Fire Hydrant Accessories & Signag
T4-IN-PHE-FNF-1530 Installation of Pendant Sprinklers & Final Painting (P0) 4 07-Apr-20 11-Apr-20 0% 80 Installation of Pendant Sprinklers & Final Paintin
LEVEL P1 7 06-Dec-19 13-Dec-19 199 13-Dec-19, LEVEL P1
T4-IN-PHE-FNF-1540 Installation of Plumbing / CP Fittings (P1) 3 06-Dec-19 09-Dec-19 0% 199 Installation of Plumbing / CP Fittings (P1)
T4-IN-PHE-FNF-1550 Installation of Fire Hydrant Accessories & Signages (P1) 3 09-Dec-19 12-Dec-19 0% 199 Installation of Fire Hydrant Accessories & Signages (P1)
T4-IN-PHE-FNF-1560 Installation of Pendant Sprinklers & Final Painting (P1) 4 09-Dec-19 13-Dec-19 0% 199 Installation of Pendant Sprinklers & Final Painting (P1)
LEVEL P2 7 09-Dec-19 16-Dec-19 196 16-Dec-19, LEVEL P2

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 67 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-PHE-FNF-1570 Installation of Plumbing / CP Fittings (P2) 3 09-Dec-19 12-Dec-19 0% 196 Installation of Plumbing / CP Fittings (P2)
T4-IN-PHE-FNF-1580 Installation of Fire Hydrant Accessories & Signages (P2) 3 12-Dec-19 15-Dec-19 0% 196 Installation of Fire Hydrant Accessories & Signages (P2)
T4-IN-PHE-FNF-1590 Installation of Pendant Sprinklers & Final Painting (P2) 4 12-Dec-19 16-Dec-19 0% 196 Installation of Pendant Sprinklers & Final Painting (P2)
LEVEL P3 7 31-Dec-19 07-Jan-20 175 07-Jan-20, LEVEL P3
T4-IN-PHE-FNF-1600 Installation of Plumbing / CP Fittings (P3) 3 31-Dec-19 03-Jan-20 0% 175 Installation of Plumbing / CP Fittings (P3)
T4-IN-PHE-FNF-1610 Installation of Fire Hydrant Accessories & Signages (P3) 3 03-Jan-20 06-Jan-20 0% 175 Installation of Fire Hydrant Accessories & Signages (P3)
T4-IN-PHE-FNF-1620 Installation of Pendant Sprinklers & Final Painting (P3) 4 03-Jan-20 07-Jan-20 0% 175 Installation of Pendant Sprinklers & Final Painting (P3)
LEVEL P4 7 31-Dec-19 07-Jan-20 175 07-Jan-20, LEVEL P4
T4-IN-PHE-FNF-1630 Installation of Plumbing / CP Fittings (P4) 3 31-Dec-19 03-Jan-20 0% 175 Installation of Plumbing / CP Fittings (P4)
T4-IN-PHE-FNF-1640 Installation of Fire Hydrant Accessories & Signages (P4) 3 03-Jan-20 06-Jan-20 0% 175 Installation of Fire Hydrant Accessories & Signages (P4)
T4-IN-PHE-FNF-1650 Installation of Pendant Sprinklers & Final Painting (P4) 4 03-Jan-20 07-Jan-20 0% 175 Installation of Pendant Sprinklers & Final Painting (P4)
LEVEL P5 7 31-Dec-19 07-Jan-20 175 07-Jan-20, LEVEL P5
T4-IN-PHE-FNF-1660 Installation of Plumbing / CP Fittings (P5) 3 31-Dec-19 03-Jan-20 0% 175 Installation of Plumbing / CP Fittings (P5)
T4-IN-PHE-FNF-1670 Installation of Fire Hydrant Accessories & Signages (P5) 3 03-Jan-20 06-Jan-20 0% 175 Installation of Fire Hydrant Accessories & Signages (P5)
T4-IN-PHE-FNF-1680 Installation of Pendant Sprinklers & Final Painting (P5) 4 03-Jan-20 07-Jan-20 0% 175 Installation of Pendant Sprinklers & Final Painting (P5)
LEVEL P6 7 31-Dec-19 07-Jan-20 175 07-Jan-20, LEVEL P6
T4-IN-PHE-FNF-1690 Installation of Plumbing / CP Fittings (P6) 3 31-Dec-19 03-Jan-20 0% 175 Installation of Plumbing / CP Fittings (P6)
T4-IN-PHE-FNF-1700 Installation of Fire Hydrant Accessories & Signages (P6) 3 03-Jan-20 06-Jan-20 0% 175 Installation of Fire Hydrant Accessories & Signages (P6)
T4-IN-PHE-FNF-1710 Installation of Pendant Sprinklers & Final Painting (P6) 4 03-Jan-20 07-Jan-20 0% 175 Installation of Pendant Sprinklers & Final Painting (P6)
LEVEL P7 7 28-Jan-20 04-Feb-20 147 04-Feb-20, LEVEL P7
T4-IN-PHE-FNF-1720 Installation of Plumbing / CP Fittings (P7) 3 28-Jan-20 31-Jan-20 0% 147 Installation of Plumbing / CP Fittings (P7)
T4-IN-PHE-FNF-1730 Installation of Fire Hydrant Accessories & Signages (P7) 3 31-Jan-20 03-Feb-20 0% 147 Installation of Fire Hydrant Accessories & Signages (P7)
T4-IN-PHE-FNF-1740 Installation of Pendant Sprinklers & Final Painting (P7) 4 31-Jan-20 04-Feb-20 0% 147 Installation of Pendant Sprinklers & Final Painting (P7)
LEVEL P8 7 28-Jan-20 04-Feb-20 147 04-Feb-20, LEVEL P8
T4-IN-PHE-FNF-1750 Installation of Plumbing / CP Fittings (P8) 3 28-Jan-20 31-Jan-20 0% 147 Installation of Plumbing / CP Fittings (P8)
T4-IN-PHE-FNF-1760 Installation of Fire Hydrant Accessories & Signages (P8) 3 31-Jan-20 03-Feb-20 0% 147 Installation of Fire Hydrant Accessories & Signages (P8)
T4-IN-PHE-FNF-1770 Installation of Pendant Sprinklers & Final Painting (P8) 4 31-Jan-20 04-Feb-20 0% 147 Installation of Pendant Sprinklers & Final Painting (P8)
LEVEL P9 7 16-May-20 23-May-20 38 23-May-20, LEVEL P9
T4-IN-PHE-FNF-1780 Installation of Plumbing / CP Fittings (P9) 3 16-May-20 19-May-20 0% 38 Installation of Plumbing / CP Fittings (P9)
T4-IN-PHE-FNF-1790 Installation of Fire Hydrant Accessories & Signages (P9) 3 19-May-20 22-May-20 0% 38 Installation of Fire Hydrant Accessories &
T4-IN-PHE-FNF-1800 Installation of Pendant Sprinklers & Final Painting (P9) 4 19-May-20 23-May-20 0% 38 Installation of Pendant Sprinklers & Final
LEVEL P10 7 09-May-20 16-May-20 45 16-May-20, LEVEL P10
T4-IN-PHE-FNF-1810 Installation of Plumbing / CP Fittings (P10) 3 09-May-20 12-May-20 0% 45 Installation of Plumbing / CP Fittings (P10)
T4-IN-PHE-FNF-1820 Installation of Fire Hydrant Accessories & Signages (P10) 3 13-May-20 15-May-20 0% 45 Installation of Fire Hydrant Accessories & S
T4-IN-PHE-FNF-1830 Installation of Pendant Sprinklers & Final Painting (P10) 4 13-May-20 16-May-20 0% 45 Installation of Pendant Sprinklers & Final P
LEVEL 09 7 14-Apr-20 21-Apr-20 70 21-Apr-20, LEVEL 09
T4-IN-PHE-FNF-1840 Installation of Plumbing / CP Fittings (FL09) 3 14-Apr-20 17-Apr-20 0% 70 Installation of Plumbing / CP Fittings (FL09)
T4-IN-PHE-FNF-1850 Installation of Fire Hydrant Accessories & Signages (FL09) 3 17-Apr-20 20-Apr-20 0% 70 Installation of Fire Hydrant Accessories & Signa
T4-IN-PHE-FNF-1860 Installation of Pendant Sprinklers & Final Painting (FL09) 4 17-Apr-20 21-Apr-20 0% 70 Installation of Pendant Sprinklers & Final Paint
LEVEL 10 7 09-Mar-20 16-Mar-20 106 16-Mar-20, LEVEL 10
T4-IN-PHE-FNF-1870 Installation of Plumbing / CP Fittings (FL10) 3 09-Mar-20 12-Mar-20 0% 106 Installation of Plumbing / CP Fittings (FL10)
T4-IN-PHE-FNF-1880 Installation of Fire Hydrant Accessories & Signages (FL10) 3 12-Mar-20 15-Mar-20 0% 106 Installation of Fire Hydrant Accessories & Signages (
T4-IN-PHE-FNF-1890 Installation of Pendant Sprinklers & Final Painting (FL10) 4 12-Mar-20 16-Mar-20 0% 106 Installation of Pendant Sprinklers & Final Painting (FL10)
LEVEL 11 7 09-Mar-20 16-Mar-20 106 16-Mar-20, LEVEL 11
T4-IN-PHE-FNF-1900 Installation of Plumbing / CP Fittings (FL11) 3 09-Mar-20 12-Mar-20 0% 106 Installation of Plumbing / CP Fittings (FL11)
T4-IN-PHE-FNF-1910 Installation of Fire Hydrant Accessories & Signages (FL11) 3 12-Mar-20 15-Mar-20 0% 106 Installation of Fire Hydrant Accessories & Signages (
T4-IN-PHE-FNF-1920 Installation of Pendant Sprinklers & Final Painting (FL11) 4 12-Mar-20 16-Mar-20 0% 106 Installation of Pendant Sprinklers & Final Painting (FL11)
LEVEL 12 7 09-Mar-20 16-Mar-20 106 16-Mar-20, LEVEL 12
T4-IN-PHE-FNF-1930 Installation of Plumbing / CP Fittings (FL12) 3 09-Mar-20 12-Mar-20 0% 106 Installation of Plumbing / CP Fittings (FL12)
T4-IN-PHE-FNF-1940 Installation of Fire Hydrant Accessories & Signages (FL12) 3 12-Mar-20 15-Mar-20 0% 106 Installation of Fire Hydrant Accessories & Signages (
T4-IN-PHE-FNF-1950 Installation of Pendant Sprinklers & Final Painting (FL12) 4 12-Mar-20 16-Mar-20 0% 106 Installation of Pendant Sprinklers & Final Painting (FL12)
LEVEL 14 7 08-Apr-20 15-Apr-20 76 15-Apr-20, LEVEL 14

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 68 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-PHE-FNF-1960 Installation of Plumbing / CP Fittings (FL14) 3 08-Apr-20 11-Apr-20 0% 76 Installation of Plumbing / CP Fittings (FL14)
T4-IN-PHE-FNF-1970 Installation of Fire Hydrant Accessories & Signages (FL14) 3 12-Apr-20 14-Apr-20 0% 76 Installation of Fire Hydrant Accessories & Signa
T4-IN-PHE-FNF-1980 Installation of Pendant Sprinklers & Final Painting (FL14) 4 12-Apr-20 15-Apr-20 0% 76 Installation of Pendant Sprinklers & Final Paintin
LEVEL 15 7 11-Apr-20 18-Apr-20 73 18-Apr-20, LEVEL 15
T4-IN-PHE-FNF-1990 Installation of Plumbing / CP Fittings (FL15) 3 11-Apr-20 14-Apr-20 0% 73 Installation of Plumbing / CP Fittings (FL15)
T4-IN-PHE-FNF-2000 Installation of Fire Hydrant Accessories & Signages (FL15) 3 15-Apr-20 17-Apr-20 0% 73 Installation of Fire Hydrant Accessories & Signa
T4-IN-PHE-FNF-2010 Installation of Pendant Sprinklers & Final Painting (FL15) 4 15-Apr-20 18-Apr-20 0% 73 Installation of Pendant Sprinklers & Final Painti
LEVEL 16 7 12-Apr-20 19-Apr-20 72 19-Apr-20, LEVEL 16
T4-IN-PHE-FNF-2020 Installation of Plumbing / CP Fittings (FL16) 3 12-Apr-20 15-Apr-20 0% 72 Installation of Plumbing / CP Fittings (FL16)
T4-IN-PHE-FNF-2030 Installation of Fire Hydrant Accessories & Signages (FL16) 3 16-Apr-20 18-Apr-20 0% 72 Installation of Fire Hydrant Accessories & Signa
T4-IN-PHE-FNF-2040 Installation of Pendant Sprinklers & Final Painting (FL16) 4 16-Apr-20 19-Apr-20 0% 72 Installation of Pendant Sprinklers & Final Painti
LEVEL 17 7 11-Jun-20 18-Jun-20 0 18-Jun-20, LEVEL 17
T4-IN-PHE-FNF-2050 Installation of Plumbing / CP Fittings (FL17) 3 11-Jun-20 14-Jun-20 0% 0 Installation of Plumbing / CP Fittings (
T4-IN-PHE-FNF-2060 Installation of Fire Hydrant Accessories & Signages (FL17) 3 14-Jun-20 17-Jun-20 0% 0 Installation of Fire Hydrant Accessori
T4-IN-PHE-FNF-2070 Installation of Pendant Sprinklers & Final Painting (FL17) 4 14-Jun-20 18-Jun-20 0% 0 Installation of Pendant Sprinklers & F
LEVEL 18 7 02-Jul-20 09-Jul-20 175 09-Jul-20, LEVEL 18
T4-IN-PHE-FNF-2080 Installation of Plumbing / CP Fittings (FL18) 3 02-Jul-20 05-Jul-20 0% 175 Installation of Plumbing / CP Fittin
T4-IN-PHE-FNF-2090 Installation of Fire Hydrant Accessories & Signages (FL18) 3 05-Jul-20 08-Jul-20 0% 175 Installation of Fire Hydrant Access
T4-IN-PHE-FNF-2100 Installation of Pendant Sprinklers & Final Painting (FL18) 4 05-Jul-20 09-Jul-20 0% 175 Installation of Pendant Sprinklers
LEVEL 19 7 02-Jul-20 09-Jul-20 175 09-Jul-20, LEVEL 19
T4-IN-PHE-FNF-2110 Installation of Plumbing / CP Fittings (FL19) 3 02-Jul-20 05-Jul-20 0% 175 Installation of Plumbing / CP Fittin
T4-IN-PHE-FNF-2120 Installation of Fire Hydrant Accessories & Signages (FL19) 3 05-Jul-20 08-Jul-20 0% 175 Installation of Fire Hydrant Access
T4-IN-PHE-FNF-2130 Installation of Pendant Sprinklers & Final Painting (FL19) 4 05-Jul-20 09-Jul-20 0% 175 Installation of Pendant Sprinklers
LEVEL 20 7 02-Jul-20 09-Jul-20 175 09-Jul-20, LEVEL 20
T4-IN-PHE-FNF-2140 Installation of Plumbing / CP Fittings (FL20) 3 02-Jul-20 05-Jul-20 0% 175 Installation of Plumbing / CP Fittin
T4-IN-PHE-FNF-2150 Installation of Fire Hydrant Accessories & Signages (FL20) 3 05-Jul-20 08-Jul-20 0% 175 Installation of Fire Hydrant Access
T4-IN-PHE-FNF-2160 Installation of Pendant Sprinklers & Final Painting (FL20) 4 05-Jul-20 09-Jul-20 0% 175 Installation of Pendant Sprinklers
LEVEL 21 7 02-Jul-20 09-Jul-20 175 09-Jul-20, LEVEL 21
T4-IN-PHE-FNF-2170 Installation of Plumbing / CP Fittings (FL21) 3 02-Jul-20 05-Jul-20 0% 175 Installation of Plumbing / CP Fittin
T4-IN-PHE-FNF-2180 Installation of Fire Hydrant Accessories & Signages (FL21) 3 05-Jul-20 08-Jul-20 0% 175 Installation of Fire Hydrant Access
T4-IN-PHE-FNF-2190 Installation of Pendant Sprinklers & Final Painting (FL21) 4 05-Jul-20 09-Jul-20 0% 175 Installation of Pendant Sprinklers
LEVEL 22 7 05-Jul-20 12-Jul-20 172 12-Jul-20, LEVEL 22
T4-IN-PHE-FNF-2200 Installation of Plumbing / CP Fittings (FL22) 3 05-Jul-20 08-Jul-20 0% 172 Installation of Plumbing / CP Fittin
T4-IN-PHE-FNF-2210 Installation of Fire Hydrant Accessories & Signages (FL22) 3 08-Jul-20 11-Jul-20 0% 172 Installation of Fire Hydrant Acces
T4-IN-PHE-FNF-2220 Installation of Pendant Sprinklers & Final Painting (FL22) 4 08-Jul-20 12-Jul-20 0% 172 Installation of Pendant Sprinklers
LEVEL 23 7 05-Aug-20 12-Aug-20 141 12-Aug-20, LEVEL 23
T4-IN-PHE-FNF-2230 Installation of Plumbing / CP Fittings (FL23) 3 05-Aug-20 08-Aug-20 0% 141 Installation of Plumbing / CP
T4-IN-PHE-FNF-2240 Installation of Fire Hydrant Accessories & Signages (FL23) 3 08-Aug-20 11-Aug-20 0% 141 Installation of Fire Hydrant A
T4-IN-PHE-FNF-2250 Installation of Pendant Sprinklers & Final Painting (FL23) 4 08-Aug-20 12-Aug-20 0% 141 Installation of Pendant Sprin
LEVEL 24 7 05-Aug-20 12-Aug-20 141 12-Aug-20, LEVEL 24
T4-IN-PHE-FNF-2260 Installation of Plumbing / CP Fittings (FL24) 3 05-Aug-20 08-Aug-20 0% 141 Installation of Plumbing / CP
T4-IN-PHE-FNF-2270 Installation of Fire Hydrant Accessories & Signages (FL24) 3 08-Aug-20 11-Aug-20 0% 141 Installation of Fire Hydrant A
T4-IN-PHE-FNF-2280 Installation of Pendant Sprinklers & Final Painting (FL24) 4 08-Aug-20 12-Aug-20 0% 141 Installation of Pendant Sprin
LEVEL 25 7 05-Aug-20 12-Aug-20 141 12-Aug-20, LEVEL 25
T4-IN-PHE-FNF-2290 Installation of Plumbing / CP Fittings (FL25) 3 05-Aug-20 08-Aug-20 0% 141 Installation of Plumbing / CP
T4-IN-PHE-FNF-2300 Installation of Fire Hydrant Accessories & Signages (FL25) 3 08-Aug-20 11-Aug-20 0% 141 Installation of Fire Hydrant A
T4-IN-PHE-FNF-2310 Installation of Pendant Sprinklers & Final Painting (FL25) 4 08-Aug-20 12-Aug-20 0% 141 Installation of Pendant Sprin
LEVEL 26 7 05-Aug-20 12-Aug-20 141 12-Aug-20, LEVEL 26
T4-IN-PHE-FNF-2320 Installation of Plumbing / CP Fittings (FL26) 3 05-Aug-20 08-Aug-20 0% 141 Installation of Plumbing / CP
T4-IN-PHE-FNF-2330 Installation of Fire Hydrant Accessories & Signages (FL26) 3 08-Aug-20 11-Aug-20 0% 141 Installation of Fire Hydrant A
T4-IN-PHE-FNF-2340 Installation of Pendant Sprinklers & Final Painting (FL26) 4 08-Aug-20 12-Aug-20 0% 141 Installation of Pendant Sprin
LEVEL 27 7 05-Aug-20 12-Aug-20 141 12-Aug-20, LEVEL 27

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 69 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-PHE-FNF-2350 Installation of Plumbing / CP Fittings (FL27) 3 05-Aug-20 08-Aug-20 0% 141 Installation of Plumbing / CP
T4-IN-PHE-FNF-2360 Installation of Fire Hydrant Accessories & Signages (FL27) 3 08-Aug-20 11-Aug-20 0% 141 Installation of Fire Hydrant A
T4-IN-PHE-FNF-2370 Installation of Pendant Sprinklers & Final Painting (FL27) 4 08-Aug-20 12-Aug-20 0% 141 Installation of Pendant Sprin
LEVEL 28 7 08-Sep-20 15-Sep-20 107 15-Sep-20, LEVEL 28
T4-IN-PHE-FNF-2380 Installation of Plumbing / CP Fittings (FL28) 3 08-Sep-20 11-Sep-20 0% 107 Installation of Plumbing
T4-IN-PHE-FNF-2390 Installation of Fire Hydrant Accessories & Signages (FL28) 3 11-Sep-20 14-Sep-20 0% 107 Installation of Fire Hyd
T4-IN-PHE-FNF-2400 Installation of Pendant Sprinklers & Final Painting (FL28) 4 11-Sep-20 15-Sep-20 0% 107 Installation of Pendan
LEVEL 29 7 08-Sep-20 15-Sep-20 107 15-Sep-20, LEVEL 29
T4-IN-PHE-FNF-2410 Installation of Plumbing / CP Fittings (FL29) 3 08-Sep-20 11-Sep-20 0% 107 Installation of Plumbing
T4-IN-PHE-FNF-2420 Installation of Fire Hydrant Accessories & Signages (FL29) 3 11-Sep-20 14-Sep-20 0% 107 Installation of Fire Hyd
T4-IN-PHE-FNF-2430 Installation of Pendant Sprinklers & Final Painting (FL29) 4 11-Sep-20 15-Sep-20 0% 107 Installation of Pendan
LEVEL 30 7 08-Sep-20 15-Sep-20 107 15-Sep-20, LEVEL 30
T4-IN-PHE-FNF-2440 Installation of Plumbing / CP Fittings (FL30) 3 08-Sep-20 11-Sep-20 0% 107 Installation of Plumbing
T4-IN-PHE-FNF-2450 Installation of Fire Hydrant Accessories & Signages (FL30) 3 11-Sep-20 14-Sep-20 0% 107 Installation of Fire Hyd
T4-IN-PHE-FNF-2460 Installation of Pendant Sprinklers & Final Painting (FL30) 4 11-Sep-20 15-Sep-20 0% 107 Installation of Pendan
LEVEL 31 7 08-Sep-20 15-Sep-20 107 15-Sep-20, LEVEL 31
T4-IN-PHE-FNF-2470 Installation of Plumbing / CP Fittings (FL31) 3 08-Sep-20 11-Sep-20 0% 107 Installation of Plumbing
T4-IN-PHE-FNF-2480 Installation of Fire Hydrant Accessories & Signages (FL31) 3 11-Sep-20 14-Sep-20 0% 107 Installation of Fire Hyd
T4-IN-PHE-FNF-2490 Installation of Pendant Sprinklers & Final Painting (FL31) 4 11-Sep-20 15-Sep-20 0% 107 Installation of Pendan
LEVEL 32 7 13-Oct-20 20-Oct-20 72 20-Oct-20, LEV
T4-IN-PHE-FNF-2500 Installation of Plumbing / CP Fittings (FL32) 3 13-Oct-20 16-Oct-20 0% 72 Installation of Plu
T4-IN-PHE-FNF-2510 Installation of Fire Hydrant Accessories & Signages (FL32) 3 16-Oct-20 19-Oct-20 0% 72 Installation of Fir
T4-IN-PHE-FNF-2520 Installation of Pendant Sprinklers & Final Painting (FL32) 4 16-Oct-20 20-Oct-20 0% 72 Installation of Pe
LEVEL 33 7 13-Oct-20 20-Oct-20 72 20-Oct-20, LEV
T4-IN-PHE-FNF-2530 Installation of Plumbing / CP Fittings (FL33) 3 13-Oct-20 16-Oct-20 0% 72 Installation of Plu
T4-IN-PHE-FNF-2540 Installation of Fire Hydrant Accessories & Signages (FL33) 3 16-Oct-20 19-Oct-20 0% 72 Installation of Fir
T4-IN-PHE-FNF-2550 Installation of Pendant Sprinklers & Final Painting (FL33) 4 16-Oct-20 20-Oct-20 0% 72 Installation of Pe
LEVEL 34 7 13-Oct-20 20-Oct-20 72 20-Oct-20, LEV
T4-IN-PHE-FNF-2560 Installation of Plumbing / CP Fittings (FL34) 3 13-Oct-20 16-Oct-20 0% 72 Installation of Plu
T4-IN-PHE-FNF-2570 Installation of Fire Hydrant Accessories & Signages (FL34) 3 16-Oct-20 19-Oct-20 0% 72 Installation of Fir
T4-IN-PHE-FNF-2580 Installation of Pendant Sprinklers & Final Painting (FL34) 4 16-Oct-20 20-Oct-20 0% 72 Installation of Pe
LEVEL 35 7 13-Oct-20 20-Oct-20 72 20-Oct-20, LEV
T4-IN-PHE-FNF-2590 Installation of Plumbing / CP Fittings (FL35) 3 13-Oct-20 16-Oct-20 0% 72 Installation of Plu
T4-IN-PHE-FNF-2600 Installation of Fire Hydrant Accessories & Signages (FL35) 3 16-Oct-20 19-Oct-20 0% 72 Installation of Fir
T4-IN-PHE-FNF-2610 Installation of Pendant Sprinklers & Final Painting (FL35) 4 16-Oct-20 20-Oct-20 0% 72 Installation of Pe
LEVEL 36 7 22-Nov-20 29-Nov-20 32 29-Nov-2
T4-IN-PHE-FNF-2620 Installation of Plumbing / CP Fittings (FL36) 3 22-Nov-20 25-Nov-20 0% 32 Installation
T4-IN-PHE-FNF-2630 Installation of Fire Hydrant Accessories & Signages (FL36) 3 25-Nov-20 28-Nov-20 0% 32 Installatio
T4-IN-PHE-FNF-2640 Installation of Pendant Sprinklers & Final Painting (FL36) 4 25-Nov-20 29-Nov-20 0% 32 Installatio
LEVEL 37 7 22-Nov-20 29-Nov-20 32 29-Nov-2
T4-IN-PHE-FNF-2650 Installation of Plumbing / CP Fittings (FL37) 3 22-Nov-20 25-Nov-20 0% 32 Installation
T4-IN-PHE-FNF-2660 Installation of Fire Hydrant Accessories & Signages (FL37) 3 25-Nov-20 28-Nov-20 0% 32 Installatio
T4-IN-PHE-FNF-2670 Installation of Pendant Sprinklers & Final Painting (FL37) 4 25-Nov-20 29-Nov-20 0% 32 Installatio
LEVEL 38 7 22-Nov-20 29-Nov-20 32 29-Nov-2
T4-IN-PHE-FNF-2680 Installation of Plumbing / CP Fittings (FL38) 3 22-Nov-20 25-Nov-20 0% 32 Installation
T4-IN-PHE-FNF-2690 Installation of Fire Hydrant Accessories & Signages (FL38) 3 25-Nov-20 28-Nov-20 0% 32 Installatio
T4-IN-PHE-FNF-2700 Installation of Pendant Sprinklers & Final Painting (FL38) 4 25-Nov-20 29-Nov-20 0% 32 Installatio
LEVEL 39 7 22-Nov-20 29-Nov-20 32 29-Nov-2
T4-IN-PHE-FNF-2710 Installation of Plumbing / CP Fittings (FL39) 3 22-Nov-20 25-Nov-20 0% 32 Installation
T4-IN-PHE-FNF-2720 Installation of Fire Hydrant Accessories & Signages (FL39) 3 25-Nov-20 28-Nov-20 0% 32 Installatio
T4-IN-PHE-FNF-2730 Installation of Pendant Sprinklers & Final Painting (FL39) 4 25-Nov-20 29-Nov-20 0% 32 Installatio
LEVEL ROOF 7 08-Dec-20 15-Dec-20 0 15-De

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 70 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-PHE-FNF-2740 Installation of Plumbing / CP Fittings (ROOF) 3 08-Dec-20 11-Dec-20 0% 0 Installa
T4-IN-PHE-FNF-2750 Installation of Fire Hydrant Accessories & Signages (ROOF) 3 11-Dec-20 14-Dec-20 0% 0 Installa
T4-IN-PHE-FNF-2760 Installation of Pendant Sprinklers & Final Painting (ROOF) 4 11-Dec-20 15-Dec-20 0% 0 Installa
HVAC 369 09-Dec-19 12-Dec-20 19 12-Dec
LEVEL B2 4 16-May-20 20-May-20 41 20-May-20, LEVEL B2
T4-IN-HVC-FNF-2780 Installation of Grills & Diffusers (B2) 3 16-May-20 19-May-20 0% 41 Installation of Grills & Diffusers (B2)
T4-IN-HVC-FNF-2790 Air balancing (B2) 1 19-May-20 20-May-20 0% 41 Air balancing (B2)
LEVEL B1 4 17-Apr-20 21-Apr-20 70 21-Apr-20, LEVEL B1
T4-IN-HVC-FNF-2800 Installation of Grills & Diffusers (B1) 3 17-Apr-20 20-Apr-20 0% 70 Installation of Grills & Diffusers (B1)
T4-IN-HVC-FNF-2810 Air balancing (B1) 1 20-Apr-20 21-Apr-20 0% 70 Air balancing (B1)
LEVEL P2 4 09-Dec-19 13-Dec-19 199 13-Dec-19, LEVEL P2
T4-IN-HVC-FNF-2860 Installation of Grills & Diffusers (P2) 3 09-Dec-19 12-Dec-19 0% 199 Installation of Grills & Diffusers (P2)
T4-IN-HVC-FNF-2870 Air balancing (P2) 1 12-Dec-19 13-Dec-19 0% 199 Air balancing (P2)
LEVEL P4 4 31-Dec-19 04-Jan-20 178 04-Jan-20, LEVEL P4
T4-IN-HVC-FNF-2880 Installation of Grills & Diffusers (P4) 3 31-Dec-19 03-Jan-20 0% 178 Installation of Grills & Diffusers (P4)
T4-IN-HVC-FNF-2890 Air balancing (P4) 1 03-Jan-20 04-Jan-20 0% 178 Air balancing (P4)
LEVEL 09 4 14-Apr-20 18-Apr-20 73 18-Apr-20, LEVEL 09
T4-IN-HVC-FNF-2900 Installation of Grills & Diffusers (FL09) 3 14-Apr-20 17-Apr-20 0% 73 Installation of Grills & Diffusers (FL09)
T4-IN-HVC-FNF-2910 Air balancing (FL09) 1 17-Apr-20 18-Apr-20 0% 73 Air balancing (FL09)
LEVEL 10 4 09-Mar-20 13-Mar-20 109 13-Mar-20, LEVEL 10
T4-IN-HVC-FNF-2920 Installation of Grills & Diffusers (FL10) 3 09-Mar-20 12-Mar-20 0% 109 Installation of Grills & Diffusers (FL10)
T4-IN-HVC-FNF-2930 Air balancing (FL10) 1 12-Mar-20 13-Mar-20 0% 109 Air balancing (FL10)
LEVEL 11 4 09-Mar-20 13-Mar-20 109 13-Mar-20, LEVEL 11
T4-IN-HVC-FNF-2940 Installation of Grills & Diffusers (FL11) 3 09-Mar-20 12-Mar-20 0% 109 Installation of Grills & Diffusers (FL11)
T4-IN-HVC-FNF-2950 Air balancing (FL11) 1 12-Mar-20 13-Mar-20 0% 109 Air balancing (FL11)
LEVEL 12 4 09-Mar-20 13-Mar-20 109 13-Mar-20, LEVEL 12
T4-IN-HVC-FNF-2960 Installation of Grills & Diffusers (FL12) 3 09-Mar-20 12-Mar-20 0% 109 Installation of Grills & Diffusers (FL12)
T4-IN-HVC-FNF-2970 Air balancing (FL12) 1 12-Mar-20 13-Mar-20 0% 109 Air balancing (FL12)
LEVEL 14 4 08-Apr-20 12-Apr-20 79 12-Apr-20, LEVEL 14
T4-IN-HVC-FNF-2980 Installation of Grills & Diffusers (FL14) 3 08-Apr-20 11-Apr-20 0% 79 Installation of Grills & Diffusers (FL14)
T4-IN-HVC-FNF-2990 Air balancing (FL14) 1 12-Apr-20 12-Apr-20 0% 79 Air balancing (FL14)
LEVEL 15 4 11-Apr-20 15-Apr-20 76 15-Apr-20, LEVEL 15
T4-IN-HVC-FNF-3000 Installation of Grills & Diffusers (FL15) 3 11-Apr-20 14-Apr-20 0% 76 Installation of Grills & Diffusers (FL15)
T4-IN-HVC-FNF-3010 Air balancing (FL15) 1 15-Apr-20 15-Apr-20 0% 76 Air balancing (FL15)
LEVEL 16 4 12-Apr-20 16-Apr-20 75 16-Apr-20, LEVEL 16
T4-IN-HVC-FNF-3020 Installation of Grills & Diffusers (FL16) 3 12-Apr-20 15-Apr-20 0% 75 Installation of Grills & Diffusers (FL16)
T4-IN-HVC-FNF-3030 Air balancing (FL16) 1 16-Apr-20 16-Apr-20 0% 75 Air balancing (FL16)
LEVEL 17 4 11-Jun-20 15-Jun-20 15 15-Jun-20, LEVEL 17
T4-IN-HVC-FNF-3040 Installation of Grills & Diffusers (FL17) 3 11-Jun-20 14-Jun-20 0% 15 Installation of Grills & Diffusers (FL17)
T4-IN-HVC-FNF-3050 Air balancing (FL17) 1 14-Jun-20 15-Jun-20 0% 15 Air balancing (FL17)
LEVEL 18 4 02-Jul-20 06-Jul-20 178 06-Jul-20, LEVEL 18
T4-IN-HVC-FNF-3060 Installation of Grills & Diffusers (FL18) 3 02-Jul-20 05-Jul-20 0% 178 Installation of Grills & Diffusers (FL18)
T4-IN-HVC-FNF-3070 Air balancing (FL18) 1 05-Jul-20 06-Jul-20 0% 178 Air balancing (FL18)
LEVEL 19 4 02-Jul-20 06-Jul-20 178 06-Jul-20, LEVEL 19
T4-IN-HVC-FNF-3080 Installation of Grills & Diffusers (FL19) 3 02-Jul-20 05-Jul-20 0% 178 Installation of Grills & Diffusers (FL19)
T4-IN-HVC-FNF-3090 Air balancing (FL19) 1 05-Jul-20 06-Jul-20 0% 178 Air balancing (FL19)
LEVEL 20 4 02-Jul-20 06-Jul-20 178 06-Jul-20, LEVEL 20
T4-IN-HVC-FNF-3100 Installation of Grills & Diffusers (FL20) 3 02-Jul-20 05-Jul-20 0% 178 Installation of Grills & Diffusers (FL20)
T4-IN-HVC-FNF-3110 Air balancing (FL20) 1 05-Jul-20 06-Jul-20 0% 178 Air balancing (FL20)
LEVEL 21 4 02-Jul-20 06-Jul-20 178 06-Jul-20, LEVEL 21
T4-IN-HVC-FNF-3120 Installation of Grills & Diffusers (FL21) 3 02-Jul-20 05-Jul-20 0% 178 Installation of Grills & Diffusers (FL21)
T4-IN-HVC-FNF-3130 Air balancing (FL21) 1 05-Jul-20 06-Jul-20 0% 178 Air balancing (FL21)
LEVEL 22 4 05-Jul-20 09-Jul-20 175 09-Jul-20, LEVEL 22

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 71 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-HVC-FNF-3140 Installation of Grills & Diffusers (FL22) 3 05-Jul-20 08-Jul-20 0% 175 Installation of Grills & Diffusers (FL22)
T4-IN-HVC-FNF-3150 Air balancing (FL22) 1 08-Jul-20 09-Jul-20 0% 175 Air balancing (FL22)
LEVEL 23 4 05-Aug-20 09-Aug-20 144 09-Aug-20, LEVEL 23
T4-IN-HVC-FNF-3160 Installation of Grills & Diffusers (FL23) 3 05-Aug-20 08-Aug-20 0% 144 Installation of Grills & Diffuse
T4-IN-HVC-FNF-3170 Air balancing (FL23) 1 08-Aug-20 09-Aug-20 0% 144 Air balancing (FL23)
LEVEL 24 4 05-Aug-20 09-Aug-20 144 09-Aug-20, LEVEL 24
T4-IN-HVC-FNF-3180 Installation of Grills & Diffusers (FL24) 3 05-Aug-20 08-Aug-20 0% 144 Installation of Grills & Diffuse
T4-IN-HVC-FNF-3190 Air balancing (FL24) 1 08-Aug-20 09-Aug-20 0% 144 Air balancing (FL24)
LEVEL 25 4 05-Aug-20 09-Aug-20 144 09-Aug-20, LEVEL 25
T4-IN-HVC-FNF-3200 Installation of Grills & Diffusers (FL25) 3 05-Aug-20 08-Aug-20 0% 144 Installation of Grills & Diffuse
T4-IN-HVC-FNF-3210 Air balancing (FL25) 1 08-Aug-20 09-Aug-20 0% 144 Air balancing (FL25)
LEVEL 26 4 05-Aug-20 09-Aug-20 144 09-Aug-20, LEVEL 26
T4-IN-HVC-FNF-3220 Installation of Grills & Diffusers (FL26) 3 05-Aug-20 08-Aug-20 0% 144 Installation of Grills & Diffuse
T4-IN-HVC-FNF-3230 Air balancing (FL26) 1 08-Aug-20 09-Aug-20 0% 144 Air balancing (FL26)
LEVEL 27 4 05-Aug-20 09-Aug-20 144 09-Aug-20, LEVEL 27
T4-IN-HVC-FNF-3240 Installation of Grills & Diffusers (FL27) 3 05-Aug-20 08-Aug-20 0% 144 Installation of Grills & Diffuse
T4-IN-HVC-FNF-3250 Air balancing (FL27) 1 08-Aug-20 09-Aug-20 0% 144 Air balancing (FL27)
LEVEL 28 4 08-Sep-20 12-Sep-20 110 12-Sep-20, LEVEL 28
T4-IN-HVC-FNF-3260 Installation of Grills & Diffusers (FL28) 3 08-Sep-20 11-Sep-20 0% 110 Installation of Grills & D
T4-IN-HVC-FNF-3270 Air balancing (FL28) 1 11-Sep-20 12-Sep-20 0% 110 Air balancing (FL28)
LEVEL 29 4 08-Sep-20 12-Sep-20 110 12-Sep-20, LEVEL 29
T4-IN-HVC-FNF-3280 Installation of Grills & Diffusers (FL29) 3 08-Sep-20 11-Sep-20 0% 110 Installation of Grills & D
T4-IN-HVC-FNF-3290 Air balancing (FL29) 1 11-Sep-20 12-Sep-20 0% 110 Air balancing (FL29)
LEVEL 30 4 08-Sep-20 12-Sep-20 110 12-Sep-20, LEVEL 30
T4-IN-HVC-FNF-3300 Installation of Grills & Diffusers (FL30) 3 08-Sep-20 11-Sep-20 0% 110 Installation of Grills & D
T4-IN-HVC-FNF-3310 Air balancing (FL30) 1 11-Sep-20 12-Sep-20 0% 110 Air balancing (FL30)
LEVEL 31 4 08-Sep-20 12-Sep-20 110 12-Sep-20, LEVEL 31
T4-IN-HVC-FNF-3320 Installation of Grills & Diffusers (FL31) 3 08-Sep-20 11-Sep-20 0% 110 Installation of Grills & D
T4-IN-HVC-FNF-3330 Air balancing (FL31) 1 11-Sep-20 12-Sep-20 0% 110 Air balancing (FL31)
LEVEL 32 4 13-Oct-20 17-Oct-20 75 17-Oct-20, LEVEL 32
T4-IN-HVC-FNF-3340 Installation of Grills & Diffusers (FL32) 3 13-Oct-20 16-Oct-20 0% 75 Installation of Gr
T4-IN-HVC-FNF-3350 Air balancing (FL32) 1 16-Oct-20 17-Oct-20 0% 75 Air balancing (FL32)
LEVEL 33 4 13-Oct-20 17-Oct-20 75 17-Oct-20, LEVEL 33
T4-IN-HVC-FNF-3360 Installation of Grills & Diffusers (FL33) 3 13-Oct-20 16-Oct-20 0% 75 Installation of Gr
T4-IN-HVC-FNF-3370 Air balancing (FL33) 1 16-Oct-20 17-Oct-20 0% 75 Air balancing (FL33)
LEVEL 34 4 13-Oct-20 17-Oct-20 75 17-Oct-20, LEVEL 34
T4-IN-HVC-FNF-3380 Installation of Grills & Diffusers (FL34) 3 13-Oct-20 16-Oct-20 0% 75 Installation of Gr
T4-IN-HVC-FNF-3390 Air balancing (FL34) 1 16-Oct-20 17-Oct-20 0% 75 Air balancing (FL34)
LEVEL 35 4 13-Oct-20 17-Oct-20 75 17-Oct-20, LEVEL 35
T4-IN-HVC-FNF-3400 Installation of Grills & Diffusers (FL35) 3 13-Oct-20 16-Oct-20 0% 75 Installation of Gr
T4-IN-HVC-FNF-3410 Air balancing (FL35) 1 16-Oct-20 17-Oct-20 0% 75 Air balancing (FL35)
LEVEL 36 4 22-Nov-20 26-Nov-20 35 26-Nov-2
T4-IN-HVC-FNF-3420 Installation of Grills & Diffusers (FL36) 3 22-Nov-20 25-Nov-20 0% 35 Installation
T4-IN-HVC-FNF-3430 Air balancing (FL36) 1 25-Nov-20 26-Nov-20 0% 35 Air balanc
LEVEL 37 4 22-Nov-20 26-Nov-20 35 26-Nov-2
T4-IN-HVC-FNF-3440 Installation of Grills & Diffusers (FL37) 3 22-Nov-20 25-Nov-20 0% 35 Installation
T4-IN-HVC-FNF-3450 Air balancing (FL37) 1 25-Nov-20 26-Nov-20 0% 35 Air balanc
LEVEL 38 4 22-Nov-20 26-Nov-20 35 26-Nov-2
T4-IN-HVC-FNF-3460 Installation of Grills & Diffusers (FL38) 3 22-Nov-20 25-Nov-20 0% 35 Installation
T4-IN-HVC-FNF-3470 Air balancing (FL38) 1 25-Nov-20 26-Nov-20 0% 35 Air balanc
LEVEL 39 4 22-Nov-20 26-Nov-20 35 26-Nov-2
T4-IN-HVC-FNF-3480 Installation of Grills & Diffusers (FL39) 3 22-Nov-20 25-Nov-20 0% 35 Installation
T4-IN-HVC-FNF-3490 Air balancing (FL39) 1 25-Nov-20 26-Nov-20 0% 35 Air balanc

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 72 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
LEVEL ROOF 4 08-Dec-20 12-Dec-20 19 12-Dec
T4-IN-HVC-FNF-3500 Installation of Grills & Diffusers (ROOF) 3 08-Dec-20 11-Dec-20 0% 19 Installa
T4-IN-HVC-FNF-3510 Air balancing (ROOF) 1 11-Dec-20 12-Dec-20 0% 19 Air bala
ELECTRICAL 374 06-Dec-19 14-Dec-20 17 14-Dec
LEVEL B2 7 16-May-20 22-May-20 39 22-May-20, LEVEL B2
T4-IN-ELE-FNF-3530 Installation of Switch Sockets (B2) 3 16-May-20 19-May-20 0% 39 Installation of Switch Sockets (B2)
T4-IN-ELE-FNF-3540 Installation of Light Fixtures (B2) 3 19-May-20 22-May-20 0% 39 Installation of Light Fixtures (B2)
LEVEL B1 7 17-Apr-20 23-Apr-20 68 23-Apr-20, LEVEL B1
T4-IN-ELE-FNF-3550 Installation of Switch Sockets (B1) 3 17-Apr-20 20-Apr-20 0% 68 Installation of Switch Sockets (B1)
T4-IN-ELE-FNF-3560 Installation of Light Fixtures (B1) 3 20-Apr-20 23-Apr-20 0% 68 Installation of Light Fixtures (B1)
LEVEL P0 7 04-Apr-20 11-Apr-20 80 11-Apr-20, LEVEL P0
T4-IN-ELE-FNF-3570 Installation of Switch Sockets (P0) 3 04-Apr-20 07-Apr-20 0% 80 Installation of Switch Sockets (P0)
T4-IN-ELE-FNF-3580 Installation of Light Fixtures (P0) 3 07-Apr-20 11-Apr-20 0% 80 Installation of Light Fixtures (P0)
LEVEL P1 7 06-Dec-19 12-Dec-19 200 12-Dec-19, LEVEL P1
T4-IN-ELE-FNF-3590 Installation of Switch Sockets (P1) 3 06-Dec-19 09-Dec-19 0% 200 Installation of Switch Sockets (P1)
T4-IN-ELE-FNF-3600 Installation of Light Fixtures (P1) 3 09-Dec-19 12-Dec-19 0% 200 Installation of Light Fixtures (P1)
LEVEL P2 7 09-Dec-19 15-Dec-19 197 15-Dec-19, LEVEL P2
T4-IN-ELE-FNF-3610 Installation of Switch Sockets (P2) 3 09-Dec-19 12-Dec-19 0% 197 Installation of Switch Sockets (P2)
T4-IN-ELE-FNF-3620 Installation of Light Fixtures (P2) 3 12-Dec-19 15-Dec-19 0% 197 Installation of Light Fixtures (P2)
LEVEL P3 7 31-Dec-19 06-Jan-20 176 06-Jan-20, LEVEL P3
T4-IN-ELE-FNF-3630 Installation of Switch Sockets (P3) 3 31-Dec-19 03-Jan-20 0% 176 Installation of Switch Sockets (P3)
T4-IN-ELE-FNF-3640 Installation of Light Fixtures (P3) 3 03-Jan-20 06-Jan-20 0% 176 Installation of Light Fixtures (P3)
LEVEL P4 7 31-Dec-19 06-Jan-20 176 06-Jan-20, LEVEL P4
T4-IN-ELE-FNF-3650 Installation of Switch Sockets (P4) 3 31-Dec-19 03-Jan-20 0% 176 Installation of Switch Sockets (P4)
T4-IN-ELE-FNF-3660 Installation of Light Fixtures (P4) 3 03-Jan-20 06-Jan-20 0% 176 Installation of Light Fixtures (P4)
LEVEL P5 7 31-Dec-19 06-Jan-20 176 06-Jan-20, LEVEL P5
T4-IN-ELE-FNF-3670 Installation of Switch Sockets (P5) 3 31-Dec-19 03-Jan-20 0% 176 Installation of Switch Sockets (P5)
T4-IN-ELE-FNF-3680 Installation of Light Fixtures (P5) 3 03-Jan-20 06-Jan-20 0% 176 Installation of Light Fixtures (P5)
LEVEL P6 7 31-Dec-19 06-Jan-20 176 06-Jan-20, LEVEL P6
T4-IN-ELE-FNF-3690 Installation of Switch Sockets (P6) 3 31-Dec-19 03-Jan-20 0% 176 Installation of Switch Sockets (P6)
T4-IN-ELE-FNF-3700 Installation of Light Fixtures (P6) 3 03-Jan-20 06-Jan-20 0% 176 Installation of Light Fixtures (P6)
LEVEL P7 7 28-Jan-20 03-Feb-20 148 03-Feb-20, LEVEL P7
T4-IN-ELE-FNF-3710 Installation of Switch Sockets (P7) 3 28-Jan-20 31-Jan-20 0% 148 Installation of Switch Sockets (P7)
T4-IN-ELE-FNF-3720 Installation of Light Fixtures (P7) 3 31-Jan-20 03-Feb-20 0% 148 Installation of Light Fixtures (P7)
LEVEL P8 7 28-Jan-20 03-Feb-20 148 03-Feb-20, LEVEL P8
T4-IN-ELE-FNF-3730 Installation of Switch Sockets (P8) 3 28-Jan-20 31-Jan-20 0% 148 Installation of Switch Sockets (P8)
T4-IN-ELE-FNF-3740 Installation of Light Fixtures (P8) 3 31-Jan-20 03-Feb-20 0% 148 Installation of Light Fixtures (P8)
LEVEL P9 7 16-May-20 23-May-20 38 23-May-20, LEVEL P9
T4-IN-ELE-FNF-3750 Installation of Switch Sockets (P9) 3 16-May-20 19-May-20 0% 38 Installation of Switch Sockets (P9)
T4-IN-ELE-FNF-3760 Installation of Light Fixtures (P9) 3 19-May-20 23-May-20 0% 38 Installation of Light Fixtures (P9)
LEVEL P10 7 09-May-20 16-May-20 45 16-May-20, LEVEL P10
T4-IN-ELE-FNF-3770 Installation of Switch Sockets (P10) 3 09-May-20 12-May-20 0% 45 Installation of Switch Sockets (P10)
T4-IN-ELE-FNF-3780 Installation of Light Fixtures (P10) 3 13-May-20 16-May-20 0% 45 Installation of Light Fixtures (P10)
LEVEL S1 7 09-May-20 16-May-20 45 16-May-20, LEVEL S1
T4-IN-ELE-FNF-3790 Installation of Switch Sockets (S1) 3 09-May-20 12-May-20 0% 45 Installation of Switch Sockets (S1)
T4-IN-ELE-FNF-3800 Installation of Light Fixtures (S1) 3 13-May-20 16-May-20 0% 45 Installation of Light Fixtures (S1)
LEVEL 09 7 14-Apr-20 20-Apr-20 71 20-Apr-20, LEVEL 09
T4-IN-ELE-FNF-3810 Installation of Switch Sockets (FL09) 3 14-Apr-20 17-Apr-20 0% 71 Installation of Switch Sockets (FL09)
T4-IN-ELE-FNF-3820 Installation of Light Fixtures (FL09) 3 17-Apr-20 20-Apr-20 0% 71 Installation of Light Fixtures (FL09)
LEVEL 10 7 09-Mar-20 15-Mar-20 107 15-Mar-20, LEVEL 10
T4-IN-ELE-FNF-3830 Installation of Switch Sockets (FL10) 3 09-Mar-20 12-Mar-20 0% 107 Installation of Switch Sockets (FL10)
T4-IN-ELE-FNF-3840 Installation of Light Fixtures (FL10) 3 12-Mar-20 15-Mar-20 0% 107 Installation of Light Fixtures (FL10)
LEVEL 11 7 09-Mar-20 15-Mar-20 107 15-Mar-20, LEVEL 11

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 73 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-ELE-FNF-3850 Installation of Switch Sockets (FL11) 3 09-Mar-20 12-Mar-20 0% 107 Installation of Switch Sockets (FL11)
T4-IN-ELE-FNF-3860 Installation of Light Fixtures (FL11) 3 12-Mar-20 15-Mar-20 0% 107 Installation of Light Fixtures (FL11)
LEVEL 12 7 09-Mar-20 15-Mar-20 107 15-Mar-20, LEVEL 12
T4-IN-ELE-FNF-3870 Installation of Switch Sockets (FL12) 3 09-Mar-20 12-Mar-20 0% 107 Installation of Switch Sockets (FL12)
T4-IN-ELE-FNF-3880 Installation of Light Fixtures (FL12) 3 12-Mar-20 15-Mar-20 0% 107 Installation of Light Fixtures (FL12)
LEVEL 14 7 08-Apr-20 15-Apr-20 76 15-Apr-20, LEVEL 14
T4-IN-ELE-FNF-3890 Installation of Switch Sockets (FL14) 3 08-Apr-20 11-Apr-20 0% 76 Installation of Switch Sockets (FL14)
T4-IN-ELE-FNF-3900 Installation of Light Fixtures (FL14) 3 12-Apr-20 15-Apr-20 0% 76 Installation of Light Fixtures (FL14)
LEVEL 15 7 11-Apr-20 18-Apr-20 73 18-Apr-20, LEVEL 15
T4-IN-ELE-FNF-3910 Installation of Switch Sockets (FL15) 3 11-Apr-20 14-Apr-20 0% 73 Installation of Switch Sockets (FL15)
T4-IN-ELE-FNF-3920 Installation of Light Fixtures (FL15) 3 15-Apr-20 18-Apr-20 0% 73 Installation of Light Fixtures (FL15)
LEVEL 16 7 12-Apr-20 19-Apr-20 72 19-Apr-20, LEVEL 16
T4-IN-ELE-FNF-3930 Installation of Switch Sockets (FL16) 3 12-Apr-20 15-Apr-20 0% 72 Installation of Switch Sockets (FL16)
T4-IN-ELE-FNF-3940 Installation of Light Fixtures (FL16) 3 16-Apr-20 19-Apr-20 0% 72 Installation of Light Fixtures (FL16)
LEVEL 17 7 11-Jun-20 17-Jun-20 13 17-Jun-20, LEVEL 17
T4-IN-ELE-FNF-3950 Installation of Switch Sockets (FL17) 3 11-Jun-20 14-Jun-20 0% 13 Installation of Switch Sockets (FL17)
T4-IN-ELE-FNF-3960 Installation of Light Fixtures (FL17) 3 14-Jun-20 17-Jun-20 0% 13 Installation of Light Fixtures (FL17)
LEVEL 18 7 02-Jul-20 08-Jul-20 176 08-Jul-20, LEVEL 18
T4-IN-ELE-FNF-3970 Installation of Switch Sockets (FL18) 3 02-Jul-20 05-Jul-20 0% 176 Installation of Switch Sockets (FL18)
T4-IN-ELE-FNF-3980 Installation of Light Fixtures (FL18) 3 05-Jul-20 08-Jul-20 0% 176 Installation of Light Fixtures (FL18)
LEVEL 19 7 02-Jul-20 08-Jul-20 176 08-Jul-20, LEVEL 19
T4-IN-ELE-FNF-3990 Installation of Switch Sockets (FL19) 3 02-Jul-20 05-Jul-20 0% 176 Installation of Switch Sockets (FL19)
T4-IN-ELE-FNF-4000 Installation of Light Fixtures (FL19) 3 05-Jul-20 08-Jul-20 0% 176 Installation of Light Fixtures (FL19)
LEVEL 20 7 02-Jul-20 08-Jul-20 176 08-Jul-20, LEVEL 20
T4-IN-ELE-FNF-4010 Installation of Switch Sockets (FL20) 3 02-Jul-20 05-Jul-20 0% 176 Installation of Switch Sockets (FL20)
T4-IN-ELE-FNF-4020 Installation of Light Fixtures (FL20) 3 05-Jul-20 08-Jul-20 0% 176 Installation of Light Fixtures (FL20)
LEVEL 21 7 02-Jul-20 08-Jul-20 176 08-Jul-20, LEVEL 21
T4-IN-ELE-FNF-4030 Installation of Switch Sockets (FL21) 3 02-Jul-20 05-Jul-20 0% 176 Installation of Switch Sockets (FL21)
T4-IN-ELE-FNF-4040 Installation of Light Fixtures (FL21) 3 05-Jul-20 08-Jul-20 0% 176 Installation of Light Fixtures (FL21)
LEVEL 22 7 05-Jul-20 11-Jul-20 173 11-Jul-20, LEVEL 22
T4-IN-ELE-FNF-4050 Installation of Switch Sockets (FL22) 3 05-Jul-20 08-Jul-20 0% 173 Installation of Switch Sockets (FL22)
T4-IN-ELE-FNF-4060 Installation of Light Fixtures (FL22) 3 08-Jul-20 11-Jul-20 0% 173 Installation of Light Fixtures (FL22)
LEVEL 23 7 05-Aug-20 11-Aug-20 142 11-Aug-20, LEVEL 23
T4-IN-ELE-FNF-4070 Installation of Switch Sockets (FL23) 3 05-Aug-20 08-Aug-20 0% 142 Installation of Switch Socket
T4-IN-ELE-FNF-4080 Installation of Light Fixtures (FL23) 3 08-Aug-20 11-Aug-20 0% 142 Installation of Light Fixtures
LEVEL 24 7 05-Aug-20 11-Aug-20 142 11-Aug-20, LEVEL 24
T4-IN-ELE-FNF-4090 Installation of Switch Sockets (FL24) 3 05-Aug-20 08-Aug-20 0% 142 Installation of Switch Socket
T4-IN-ELE-FNF-4100 Installation of Light Fixtures (FL24) 3 08-Aug-20 11-Aug-20 0% 142 Installation of Light Fixtures
LEVEL 25 7 05-Aug-20 11-Aug-20 142 11-Aug-20, LEVEL 25
T4-IN-ELE-FNF-4110 Installation of Switch Sockets (FL25) 3 05-Aug-20 08-Aug-20 0% 142 Installation of Switch Socket
T4-IN-ELE-FNF-4120 Installation of Light Fixtures (FL25) 3 08-Aug-20 11-Aug-20 0% 142 Installation of Light Fixtures
LEVEL 26 7 05-Aug-20 11-Aug-20 142 11-Aug-20, LEVEL 26
T4-IN-ELE-FNF-4130 Installation of Switch Sockets (FL26) 3 05-Aug-20 08-Aug-20 0% 142 Installation of Switch Socket
T4-IN-ELE-FNF-4140 Installation of Light Fixtures (FL26) 3 08-Aug-20 11-Aug-20 0% 142 Installation of Light Fixtures
LEVEL 27 7 05-Aug-20 11-Aug-20 142 11-Aug-20, LEVEL 27
T4-IN-ELE-FNF-4150 Installation of Switch Sockets (FL27) 3 05-Aug-20 08-Aug-20 0% 142 Installation of Switch Socket
T4-IN-ELE-FNF-4160 Installation of Light Fixtures (FL27) 3 08-Aug-20 11-Aug-20 0% 142 Installation of Light Fixtures
LEVEL 28 7 08-Sep-20 14-Sep-20 108 14-Sep-20, LEVEL 28
T4-IN-ELE-FNF-4170 Installation of Switch Sockets (FL28) 3 08-Sep-20 11-Sep-20 0% 108 Installation of Switch S
T4-IN-ELE-FNF-4180 Installation of Light Fixtures (FL28) 3 11-Sep-20 14-Sep-20 0% 108 Installation of Light Fix
LEVEL 29 7 08-Sep-20 14-Sep-20 108 14-Sep-20, LEVEL 29
T4-IN-ELE-FNF-4190 Installation of Switch Sockets (FL29) 3 08-Sep-20 11-Sep-20 0% 108 Installation of Switch S
T4-IN-ELE-FNF-4200 Installation of Light Fixtures (FL29) 3 11-Sep-20 14-Sep-20 0% 108 Installation of Light Fix

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 74 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
LEVEL 30 7 08-Sep-20 14-Sep-20 108 14-Sep-20, LEVEL 30
T4-IN-ELE-FNF-4210 Installation of Switch Sockets (FL30) 3 08-Sep-20 11-Sep-20 0% 108 Installation of Switch S
T4-IN-ELE-FNF-4220 Installation of Light Fixtures (FL30) 3 11-Sep-20 14-Sep-20 0% 108 Installation of Light Fix
LEVEL 31 7 08-Sep-20 14-Sep-20 108 14-Sep-20, LEVEL 31
T4-IN-ELE-FNF-4230 Installation of Switch Sockets (FL31) 3 08-Sep-20 11-Sep-20 0% 108 Installation of Switch S
T4-IN-ELE-FNF-4240 Installation of Light Fixtures (FL31) 3 11-Sep-20 14-Sep-20 0% 108 Installation of Light Fix
LEVEL 32 7 13-Oct-20 19-Oct-20 73 19-Oct-20, LEVEL 32
T4-IN-ELE-FNF-4250 Installation of Switch Sockets (FL32) 3 13-Oct-20 16-Oct-20 0% 73 Installation of Sw
T4-IN-ELE-FNF-4260 Installation of Light Fixtures (FL32) 3 16-Oct-20 19-Oct-20 0% 73 Installation of Lig
LEVEL 33 7 13-Oct-20 19-Oct-20 73 19-Oct-20, LEVEL 33
T4-IN-ELE-FNF-4270 Installation of Switch Sockets (FL33) 3 13-Oct-20 16-Oct-20 0% 73 Installation of Sw
T4-IN-ELE-FNF-4280 Installation of Light Fixtures (FL33) 3 16-Oct-20 19-Oct-20 0% 73 Installation of Lig
LEVEL 34 7 13-Oct-20 19-Oct-20 73 19-Oct-20, LEVEL 34
T4-IN-ELE-FNF-4290 Installation of Switch Sockets (FL34) 3 13-Oct-20 16-Oct-20 0% 73 Installation of Sw
T4-IN-ELE-FNF-4300 Installation of Light Fixtures (FL34) 3 16-Oct-20 19-Oct-20 0% 73 Installation of Lig
LEVEL 35 7 13-Oct-20 19-Oct-20 73 19-Oct-20, LEVEL 35
T4-IN-ELE-FNF-4310 Installation of Switch Sockets (FL35) 3 13-Oct-20 16-Oct-20 0% 73 Installation of Sw
T4-IN-ELE-FNF-4320 Installation of Light Fixtures (FL35) 3 16-Oct-20 19-Oct-20 0% 73 Installation of Lig
LEVEL 36 7 22-Nov-20 28-Nov-20 33 28-Nov-2
T4-IN-ELE-FNF-4330 Installation of Switch Sockets (FL36) 3 22-Nov-20 25-Nov-20 0% 33 Installation
T4-IN-ELE-FNF-4340 Installation of Light Fixtures (FL36) 3 25-Nov-20 28-Nov-20 0% 33 Installatio
LEVEL 37 7 22-Nov-20 28-Nov-20 33 28-Nov-2
T4-IN-ELE-FNF-4350 Installation of Switch Sockets (FL37) 3 22-Nov-20 25-Nov-20 0% 33 Installation
T4-IN-ELE-FNF-4360 Installation of Light Fixtures (FL37) 3 25-Nov-20 28-Nov-20 0% 33 Installatio
LEVEL 38 7 22-Nov-20 28-Nov-20 33 28-Nov-2
T4-IN-ELE-FNF-4370 Installation of Switch Sockets (FL38) 3 22-Nov-20 25-Nov-20 0% 33 Installation
T4-IN-ELE-FNF-4380 Installation of Light Fixtures (FL38) 3 25-Nov-20 28-Nov-20 0% 33 Installatio
LEVEL 39 7 22-Nov-20 28-Nov-20 33 28-Nov-2
T4-IN-ELE-FNF-4390 Installation of Switch Sockets (FL39) 3 22-Nov-20 25-Nov-20 0% 33 Installation
T4-IN-ELE-FNF-4400 Installation of Light Fixtures (FL39) 3 25-Nov-20 28-Nov-20 0% 33 Installatio
LEVEL ROOF 7 08-Dec-20 14-Dec-20 17 14-Dec
T4-IN-ELE-FNF-4410 Installation of Switch Sockets (ROOF) 3 08-Dec-20 11-Dec-20 0% 17 Installa
T4-IN-ELE-FNF-4420 Installation of Light Fixtures (ROOF) 3 11-Dec-20 14-Dec-20 0% 17 Installa
PLANT ROOMS 353 15-Dec-19 03-Dec-20 8 03-Dec-
B2 PUMP ROOM 103 15-Dec-19 27-Mar-20 95 27-Mar-20, B2 PUMP ROOM
T4-IN-PLR-PHE-6160 Partial access from Client (B2) 0 15-Dec-19 0% 94 Partial access from Client (B2)
PLUMBING PUMP ROOM 103 15-Dec-19 27-Mar-20 95 27-Mar-20, PLUMBING PUMP ROOM
T4-IN-PLR-PHE-6170 Installation of Support / Bracket & Rungs for piping (B2 - PL Plant Room) 7 15-Dec-19 21-Dec-19 0% 94 Installation of Support / Bracket & Rungs for piping (B2 - PL Plant
T4-IN-PLR-PHE-6180 Installation of Piping & Valves (B2 - PL Plant Room) 30 21-Dec-19 21-Jan-20 0% 94 Installation of Piping & Valves (B2 - PL Plant Room)
T4-IN-PLR-PHE-6190 Installation of Domestic Water Transfer Pumps & Panels on foundation and levelling (B2 - PL Plant Room) 7 02-Feb-20 09-Feb-20 0% 82 Installation of Domestic Water Transfer Pumps & Panels o
T4-IN-PLR-PHE-6200 Installation of Grey Water transfer Pumps & Panels on foundation and levelling (B2 - PL Plant Room) 4 09-Feb-20 13-Feb-20 0% 82 Installation of Grey Water transfer Pumps & Panels on fou
T4-IN-PLR-PHE-6210 Installation of Grey Water Booster Pumps & Panels on foundation and levelling (B2 - PL Plant Room) 4 13-Feb-20 17-Feb-20 0% 82 Installation of Grey Water Booster Pumps & Panels on fo
T4-IN-PLR-PHE-6220 Installation of Rain Water Transfer Pumps & Panels on foundation and levelling (B2 - PL Plant Room) 4 23-Feb-20 27-Feb-20 0% 75 Installation of Rain Water Transfer Pumps & Panels on
T4-IN-PLR-PHE-6230 Installation of Oil Interceptor Sump Pumps & Panels on foundation and levelling (B2 - PL Plant Room) 4 27-Feb-20 02-Mar-20 0% 75 Installation of Oil Interceptor Sump Pumps & Panels on
T4-IN-PLR-PHE-6240 Installation of Plant Room Sump Pumps & Panels on foundation and levelling (B2 - PL Plant Room) 4 02-Mar-20 06-Mar-20 0% 75 Installation of Plant Room Sump Pumps & Panels on f
T4-IN-PLR-PHE-6250 Installation of Sewage Ejection Pumps & Panels on foundation and levelling (B2 - PL Plant Room) 4 06-Mar-20 10-Mar-20 0% 75 Installation of Sewage Ejection Pumps & Panels on fo
T4-IN-PLR-PHE-6260 Installation of Precharged Air Vessels on foundation and levelling (B2 - PL Plant Room) 3 17-Feb-20 20-Feb-20 0% 95 Installation of Precharged Air Vessels on foundation and
T4-IN-PLR-PHE-6270 Inlet & Outlet Pump connections & Electrical Works (B2 - PL Plant Room) 7 10-Mar-20 17-Mar-20 0% 75 Inlet & Outlet Pump connections & Electrical Works (
T4-IN-PLR-PHE-6290 Hydrotesting (B2 - PL Plant Room) 7 17-Mar-20 24-Mar-20 0% 75 Hydrotesting (B2 - PL Plant Room)
T4-IN-PLR-PHE-6300 Painting & Nomenclature (B2 - PL Plant Room) 3 24-Mar-20 27-Mar-20 0% 95 Painting & Nomenclature (B2 - PL Plant Room)
T4-IN-PLR-PHE-6305 Attending Snag & Desnag (B2 - PL Plant Room) 3 24-Mar-20 27-Mar-20 0% 95 Attending Snag & Desnag (B2 - PL Plant Room)
FIRE FIGHTING PUMP ROOM 60 15-Dec-19 13-Feb-20 138 13-Feb-20, FIRE FIGHTING PUMP ROOM
T4-IN-PLR-FF-6340 Installation of Support / Bracket & Rungs for piping (B2 - FF Plant Room) 7 15-Dec-19 21-Dec-19 0% 120 Installation of Support / Bracket & Rungs for piping (B2 - FF Plant

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 75 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-PLR-FF-6350 Installation of Piping & Valves (B2 - FF Plant Room) 20 21-Dec-19 11-Jan-20 0% 120 Installation of Piping & Valves (B2 - FF Plant Room)
T4-IN-PLR-FF-6360 Installation of Fire Hydrant Pumps & Panels on foundation and levelling (B2 - FF Plant Room) 7 11-Jan-20 18-Jan-20 0% 120 Installation of Fire Hydrant Pumps & Panels on foundation and
T4-IN-PLR-FF-6370 Installation of Fire Sprinkler Pumps & Panels on foundation and levelling (B2 - FF Plant Room) 3 18-Jan-20 21-Jan-20 0% 120 Installation of Fire Sprinkler Pumps & Panels on foundation an
T4-IN-PLR-FF-6380 Installation of Fire Standby Pumps & Panels on foundation and levelling (B2 - FF Plant Room) 3 21-Jan-20 24-Jan-20 0% 120 Installation of Fire Standby Pumps & Panels on foundation an
T4-IN-PLR-FF-6390 Installation of Fire Hydrant Jockey Pumps & Panels on foundation and levelling (B2 - FF Plant Room) 3 25-Jan-20 28-Jan-20 0% 120 Installation of Fire Hydrant Jockey Pumps & Panels on found
T4-IN-PLR-FF-6400 Installation of Fire Sprinker Jockey Pumps & Panels on foundation and levelling (B2 - FF Plant Room) 3 28-Jan-20 31-Jan-20 0% 120 Installation of Fire Sprinker Jockey Pumps & Panels on foun
T4-IN-PLR-FF-6410 Inlet & Outlet Pump connections & Electrical Works (B2 - FF Plant Room) 3 31-Jan-20 03-Feb-20 0% 120 Inlet & Outlet Pump connections & Electrical Works (B2 - F
T4-IN-PLR-FF-6420 Hydrotesting (B2 - FF Plant Room) 7 04-Feb-20 10-Feb-20 0% 120 Hydrotesting (B2 - FF Plant Room)
T4-IN-PLR-FF-6430 Painting & Nomenclature (B2 - FF Plant Room) 3 10-Feb-20 13-Feb-20 0% 138 Painting & Nomenclature (B2 - FF Plant Room)
T4-IN-PLR-FF-6440 Attending Snag & Desnag (B2 - FF Plant Room) 3 10-Feb-20 13-Feb-20 0% 120 Attending Snag & Desnag (B2 - FF Plant Room)
B1 ELECTRICAL ROOM / TRANSFORMER ROOM 68 01-Mar-20 07-May-20 54 07-May-20, B1 ELECTRICAL ROOM / TRA
T4-IN-PLR-ELE-7405 Installation of Cable Trays (B1- Electrical Room) 25 01-Mar-20 25-Mar-20 0% 54 Installation of Cable Trays (B1- Electrical Room)
T4-IN-PLR-ELE-7410 Installation Earth Strip & Wire (B1- Electrical Room) 25 01-Mar-20 25-Mar-20 0% 54 Installation Earth Strip & Wire (B1- Electrical Room)
T4-IN-PLR-ELE-7415 Installation of Main Ring Unit Panel 7 26-Mar-20 01-Apr-20 0% 80 Installation of Main Ring Unit Panel
T4-IN-PLR-ELE-7420 Installation of MDB-1 (B1- Electrical Room) 5 26-Mar-20 30-Mar-20 0% 54 Installation of MDB-1 (B1- Electrical Room)
T4-IN-PLR-ELE-7430 Installation of MDB-2 (B1- Electrical Room) 5 31-Mar-20 04-Apr-20 0% 54 Installation of MDB-2 (B1- Electrical Room)
T4-IN-PLR-ELE-7440 Installation of MDB-3 (B1- Electrical Room) 5 05-Apr-20 09-Apr-20 0% 54 Installation of MDB-3 (B1- Electrical Room)
T4-IN-PLR-ELE-7450 Installation of MDB-4 (B1- Electrical Room) 5 10-Apr-20 14-Apr-20 0% 54 Installation of MDB-4 (B1- Electrical Room)
T4-IN-PLR-ELE-7460 Installation of APFC Panels (B1- Electrical Room) 5 15-Apr-20 19-Apr-20 0% 54 Installation of APFC Panels (B1- Electrical Room)
T4-IN-PLR-ELE-7470 Installation of Transformers 8 20-Apr-20 27-Apr-20 0% 54 Installation of Transformers
T4-IN-PLR-ELE-7480 HT Cable Laying & Termination 10 28-Apr-20 07-May-20 0% 54 HT Cable Laying & Termination
T4-IN-PLR-ELE-7490 LT Cable Laying & Termination 18 20-Apr-20 07-May-20 0% 54 LT Cable Laying & Termination
COOLING TOWER - TEMPORARY (P0) 54 18-Apr-20 11-Jun-20 19 11-Jun-20, COOLING TOWER - TEM
T4-IN-PLR-HVC-7390 Installation of Support / Bracket & Rungs for piping (P0 - Cooling Tower) 15 18-Apr-20 02-May-20 0% 19 Installation of Support / Bracket & Rungs for
T4-IN-PLR-HVC-7400 Assembly of Cooling Towers (P0 - Cooling Tower) 25 18-Apr-20 12-May-20 0% 19 Assembly of Cooling Towers (P0 - Cooling
T4-IN-PLR-HVC-7410 Installation of Cooling Tower-01 (P0 - Cooling Tower) 10 13-May-20 22-May-20 0% 19 Installation of Cooling Tower-01 (P0 - Co
T4-IN-PLR-HVC-7420 Installation of Cooling Tower-02 (P0 - Cooling Tower) 7 13-May-20 19-May-20 0% 19 Installation of Cooling Tower-02 (P0 - Coo
T4-IN-PLR-HVC-7450 Installation of Piping & Valves alongwith Insualation (P0 - Cooling Tower) 10 18-Apr-20 27-Apr-20 0% 46 Installation of Piping & Valves alongwith Insu
T4-IN-PLR-HVC-7460 Installation of Make Up Water Pumps (P0 - Cooling Tower) 5 28-Apr-20 02-May-20 0% 46 Installation of Make Up Water Pumps (P0 - C
T4-IN-PLR-HVC-7470 Installation of Make Up Water Transfer Pumps (P0 - Cooling Tower) 5 28-Apr-20 02-May-20 0% 46 Installation of Make Up Water Transfer Pum
T4-IN-PLR-HVC-7480 Installation of Sand Pressure Filter for Cooling Tower (P0 - Cooling Tower) 7 20-May-20 26-May-20 0% 19 Installation of Sand Pressure Filter for C
T4-IN-PLR-HVC-7490 Installation of Water Softening Plant (P0 - Cooling Tower) 10 20-May-20 29-May-20 0% 19 Installation of Water Softening Plant (P0
T4-IN-PLR-HVC-7500 Inlet & Outlet Pump connections & Electrical Works (P0 - Cooling Tower) 7 30-May-20 05-Jun-20 0% 19 Inlet & Outlet Pump connections & Elec
T4-IN-PLR-HVC-7510 Hydrotesting (P0 - Cooling Tower) 3 06-Jun-20 09-Jun-20 0% 19 Hydrotesting (P0 - Cooling Tower)
T4-IN-PLR-HVC-7520 Attending Snag & Desnag (P0 - Cooling Tower) 2 09-Jun-20 11-Jun-20 0% 19 Attending Snag & Desnag (P0 - Cooli
P2 HVAC ROOM 87 15-Feb-20 12-May-20 31 12-May-20, P2 HVAC ROOM
T4-IN-PLR-HVC-7010 Partial access from Client (P2-HVAC Room) 0 15-Feb-20 0% 31 Partial access from Client (P2-HVAC Room)
T4-IN-PLR-HVC-7020 Installation of Support / Bracket & Rungs for piping (P2 - HVAC Room) 25 15-Feb-20 11-Mar-20 0% 31 Installation of Support / Bracket & Rungs for piping (
T4-IN-PLR-HVC-7030 Installation of Piping & Valves with Insulation (FL22 - PL Plant Room) 30 19-Feb-20 20-Mar-20 0% 31 Installation of Piping & Valves with Insulation (FL22
T4-IN-PLR-HVC-7040 Installation of Filter Feed Pumps & Panels on foundation and levelling (P2 - HVAC Room) 7 20-Mar-20 27-Mar-20 0% 31 Installation of Filter Feed Pumps & Panels on foun
T4-IN-PLR-HVC-7050 Installation of Condenser Pumps & Panels on foundation and levelling (P2 - HVAC Room) 7 27-Mar-20 03-Apr-20 0% 31 Installation of Condenser Pumps & Panels on fou
T4-IN-PLR-HVC-7060 Installation of Primary Chilled Water Pumps & Panels on foundation and levelling (P2 - HVAC Room) 10 03-Apr-20 13-Apr-20 0% 31 Installation of Primary Chilled Water Pumps & P
T4-IN-PLR-HVC-7070 Installation of Air Separator on foundation and levelling (P2 - HVAC Room) 5 13-Apr-20 18-Apr-20 0% 31 Installation of Air Separator on foundation and
T4-IN-PLR-HVC-7080 Installation of Chilled Water Expansion Tank on foundation and levelling (P2 - HVAC Room) 5 18-Apr-20 23-Apr-20 0% 31 Installation of Chilled Water Expansion Tank o
T4-IN-PLR-HVC-7090 Inlet & Outlet Pump connections & Electrical Works (P2 - HVAC Room) 7 23-Apr-20 30-Apr-20 0% 31 Inlet & Outlet Pump connections & Electrical
T4-IN-PLR-HVC-7100 Hydrotesting (P2 - HVAC Room) 7 30-Apr-20 07-May-20 0% 31 Hydrotesting (P2 - HVAC Room)
T4-IN-PLR-HVC-7110 Joint Insulation (P2 - HVAC Room) 5 07-May-20 12-May-20 0% 31 Joint Insulation (P2 - HVAC Room)
FL 22 PLANT ROOM 62 27-Mar-20 28-May-20 9 28-May-20, FL 22 PLANT ROOM
T4-IN-PLR-PHE-6460 Partial access from Client (FL22) 0 27-Mar-20 0% 1 Partial access from Client (FL22)
PLUMBING PUMP ROOM 62 27-Mar-20 28-May-20 1 28-May-20, PLUMBING PUMP ROOM
T4-IN-PLR-FF-6470 Installation of Support / Bracket & Rungs for piping (FL22 - PL Plant Room) 7 27-Mar-20 02-Apr-20 0% 1 Installation of Support / Bracket & Rungs for pipin
T4-IN-PLR-FF-6480 Installation of Piping & Valves (FL22 - PL Plant Room) 20 02-Apr-20 22-Apr-20 0% 1 Installation of Piping & Valves (FL22 - PL Plan

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 76 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-PLR-FF-6490 Installation of Domestic Water Transer Pumps & Panels on foundation and levelling (FL22 - PL Plant Room) 7 22-Apr-20 29-Apr-20 0% 1 Installation of Domestic Water Transer Pump
T4-IN-PLR-FF-6500 Installation of Grey Water Transfer Pumps & Panels on foundation and levelling (FL22 - PL Plant Room) 7 29-Apr-20 06-May-20 0% 1 Installation of Grey Water Transfer Pumps &
T4-IN-PLR-FF-6510 Installation of Pre Charged Air Vessel on foundation and levelling (FL22 - PL Plant Room) 3 06-May-20 09-May-20 0% 1 Installation of Pre Charged Air Vessel on fo
T4-IN-PLR-FF-6520 Inlet & Outlet Pump connections & Electrical Works (FL22 - PL Plant Room) 7 09-May-20 16-May-20 0% 1 Inlet & Outlet Pump connections & Electric
T4-IN-PLR-FF-6530 Hydrotesting (FL22 - PL Plant Room) 5 16-May-20 21-May-20 0% 1 Hydrotesting (FL22 - PL Plant Room)
T4-IN-PLR-FF-6540 Painting & Nomenclature (FL22 - PL Plant Room) 3 21-May-20 24-May-20 0% 1 Painting & Nomenclature (FL22 - PL Pla
T4-IN-PLR-FF-6550 Attending Snag & Desnag (FL22 - PL Plant Room) 3 25-May-20 28-May-20 0% 1 Attending Snag & Desnag (FL22 - PL P
HVAC / HEAT EXCHANGER ROOM 61 27-Mar-20 26-May-20 10 26-May-20, HVAC / HEAT EXCHANGER
T4-IN-PLR-HVC-7140 Partial access from Client (FL22) 0 27-Mar-20 0% 10 Partial access from Client (FL22)
T4-IN-PLR-HVC-7150 Installation of Support / Bracket & Rungs for piping (FL22 - HVAC Room) 10 27-Mar-20 05-Apr-20 0% 10 Installation of Support / Bracket & Rungs for pipi
T4-IN-PLR-HVC-7160 Installation of Piping & Valves (FL22 - HVAC Room) 25 03-Apr-20 27-Apr-20 0% 10 Installation of Piping & Valves (FL22 - HVAC
T4-IN-PLR-HVC-7170 Installation of Condensor Water Pumps (FL22 - HVAC Room) 7 13-Apr-20 19-Apr-20 0% 14 Installation of Condensor Water Pumps (FL22
T4-IN-PLR-HVC-7180 Installation of Secondary Chilled Water Pumps (FL22 - HVAC Room) 14 20-Apr-20 03-May-20 0% 14 Installation of Secondary Chilled Water Pum
T4-IN-PLR-HVC-7190 Installation of Heat Recovery Units (FL22 - HVAC Room) 10 28-Apr-20 07-May-20 0% 10 Installation of Heat Recovery Units (FL22 -
T4-IN-PLR-HVC-7195 Installation of Plate Type Heat Exchanger (FL22 - HVAC Room) 10 28-Apr-20 07-May-20 0% 10 Installation of Plate Type Heat Exchanger (F
T4-IN-PLR-HVC-7200 Inlet & Outlet Pump connections & Electrical Works (FL22 - HVAC Room) 7 08-May-20 14-May-20 0% 10 Inlet & Outlet Pump connections & Electric
T4-IN-PLR-HVC-7210 Hydrotesting (FL22 - HVAC Room) 7 15-May-20 21-May-20 0% 10 Hydrotesting (FL22 - HVAC Room)
T4-IN-PLR-HVC-7220 Joint Insulation (FL22 - HVAC Room) 5 22-May-20 26-May-20 0% 10 Joint Insulation (FL22 - HVAC Room)
ROOF PUMP ROOM / COOLING TOWER 93 01-Sep-20 03-Dec-20 8 03-Dec-
T4-IN-PLR-PHE-6580 Partial access from Client (ROOF) 0 01-Sep-20 0% 0 Partial access from Clien
PLUMBING PUMP ROOM 74 01-Sep-20 13-Nov-20 27 13-Nov-20,
T4-IN-PLR-PHE-6590 Installation of Support / Bracket & Rungs for piping (ROOF- PL Plant Room) 7 01-Sep-20 07-Sep-20 0% 27 Installation of Support /
T4-IN-PLR-PHE-6600 Installation of Piping & Valves (ROOF- PL Plant Room) 25 07-Sep-20 02-Oct-20 0% 27 Installation of Pipin
T4-IN-PLR-PHE-6610 Installation of Domestic Water Booster Pumps & Panels on foundation and levelling (ROOF - PL Plant Room) 7 02-Oct-20 09-Oct-20 0% 27 Installation of Dom
T4-IN-PLR-PHE-6620 Installation of Grey Water Booster Pumps & Panels on foundation and levelling (ROOF - PL Plant Room) 7 09-Oct-20 16-Oct-20 0% 27 Installation of Gr
T4-IN-PLR-PHE-6630 Installation of Pre Charged Air Vessel on foundation and levelling (ROOF - PL Plant Room) 5 16-Oct-20 21-Oct-20 0% 27 Installation of Pr
T4-IN-PLR-PHE-6640 Inlet & Outlet Pump connections & Electrical Works (ROOF - PL Plant Room) 7 21-Oct-20 28-Oct-20 0% 27 Inlet & Outlet P
T4-IN-PLR-PHE-6650 Hydrotesting (ROOF - PL Plant Room) 7 28-Oct-20 03-Nov-20 0% 27 Hydrotesting
T4-IN-PLR-PHE-6660 Painting & Nomenclature (ROOF - PL Plant Room) 5 04-Nov-20 08-Nov-20 0% 27 Painting & N
T4-IN-PLR-PHE-6670 Attending Snag & Desnag (ROOF - PL Plant Room) 5 09-Nov-20 13-Nov-20 0% 27 Attending S
FIRE FIGHTING PUMP ROOM 93 01-Sep-20 03-Dec-20 8 03-Dec-
T4-IN-PLR-FF-6890 Installation of Support / Bracket & Rungs for piping (ROOF - FF Plant Room) 7 01-Sep-20 07-Sep-20 0% 8 Installation of Support /
T4-IN-PLR-FF-6900 Installation of Piping & Valves (ROOF- FF Plant Room) 25 07-Sep-20 02-Oct-20 0% 8 Installation of Pipin
T4-IN-PLR-FF-6910 Installation of Fire Hydrant Pumps & Panels on foundation and levelling (ROOF - FF Plant Room) 10 02-Oct-20 12-Oct-20 0% 8 Installation of Fire
T4-IN-PLR-FF-6920 Installation of Fire Sprinkler Pumps & Panels on foundation and levelling (ROOF - FF Plant Room) 10 12-Oct-20 22-Oct-20 0% 8 Installation of F
T4-IN-PLR-FF-6930 Installation of Fire Standby Pumps & Panels on foundation and levelling (ROOF - FF Plant Room) 7 22-Oct-20 29-Oct-20 0% 8 Installation of F
T4-IN-PLR-FF-6940 Installation of Fire Hydrant Jockey Pumps & Panels on foundation and levelling (ROOF - FF Plant Room) 7 29-Oct-20 05-Nov-20 0% 8 Installation of
T4-IN-PLR-FF-6950 Installation of Fire Sprinkler Jockey Pumps & Panels on foundation and levelling (ROOF - FF Plant Room) 7 05-Nov-20 12-Nov-20 0% 8 Installation o
T4-IN-PLR-FF-6960 Inlet & Outlet Pump connections & Electrical Works (ROOF - FF Plant Room) 5 12-Nov-20 17-Nov-20 0% 8 Inlet & Outl
T4-IN-PLR-FF-6970 Hydrotesting (ROOF - FF Plant Room) 7 17-Nov-20 24-Nov-20 0% 8 Hydrotesti
T4-IN-PLR-FF-6980 Painting & Nomenclature (ROOF- FF Plant Room) 5 24-Nov-20 29-Nov-20 0% 8 Painting &
T4-IN-PLR-FF-6990 Attending Snag & Desnag (ROOF- FF Plant Room) 4 29-Nov-20 03-Dec-20 0% 8 Attendin
HVAC PLANT ROOM / COOLING TOWER 81 01-Sep-20 21-Nov-20 0 21-Nov-20
T4-IN-PLR-HVC-7250 Installation of Support / Bracket & Rungs for piping (ROOF - Cooling Tower) 15 01-Sep-20 15-Sep-20 0% 0 Installation of Support
T4-IN-PLR-HVC-7260 Assembly of Cooling Towers (ROOF - Cooling Tower) 25 16-Sep-20 10-Oct-20 0% 0 Assembly of Cool
T4-IN-PLR-HVC-7270 Installation of Cooling Tower-01 (ROOF - Cooling Tower) 10 11-Oct-20 20-Oct-20 0% 0 Installation of Co
T4-IN-PLR-HVC-7280 Installation of Cooling Tower-02 (ROOF - Cooling Tower) 7 11-Oct-20 17-Oct-20 0% 0 Installation of Co
T4-IN-PLR-HVC-7290 Installation of Cooling Tower-03 (ROOF - Cooling Tower) 7 18-Oct-20 24-Oct-20 0% 10 Installation of C
T4-IN-PLR-HVC-7300 Installation of Cooling Tower-04 (ROOF - Cooling Tower) 7 18-Oct-20 24-Oct-20 0% 10 Installation of C
T4-IN-PLR-HVC-7310 Installation of Piping & Valves alongwith Insualation (ROOF - Cooling Tower) 10 11-Oct-20 20-Oct-20 0% 9 Installation of Pi
T4-IN-PLR-HVC-7320 Installation of Make Up Water Pumps (ROOF - Cooling Tower) 5 21-Oct-20 25-Oct-20 0% 9 Installation of M
T4-IN-PLR-HVC-7330 Installation of Make Up Water Transfer Pumps (ROOF - Cooling Tower) 5 26-Oct-20 30-Oct-20 0% 9 Installation of M

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 77 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
T4-IN-PLR-HVC-7340 Installation of Sand Pressure Filter for Cooling Tower (ROOF - Cooling Tower) 7 18-Oct-20 24-Oct-20 0% 0 Installation of S
T4-IN-PLR-HVC-7350 Installation of Water Softening Plant (ROOF - Cooling Tower) 15 25-Oct-20 08-Nov-20 0% 0 Installation o
T4-IN-PLR-HVC-7360 Inlet & Outlet Pump connections & Electrical Works (ROOF - Cooling Tower) 7 09-Nov-20 15-Nov-20 0% 0 Inlet & Outl
T4-IN-PLR-HVC-7370 Hydrotesting (ROOF - Cooling Tower) 3 16-Nov-20 19-Nov-20 0% 0 Hydrotestin
T4-IN-PLR-HVC-7380 Attending Snag & Desnag (ROOF - Cooling Tower) 2 19-Nov-20 21-Nov-20 0% 0 Attending S

TESTING & COMMISSIONING 268 07-May-20 31-Jan-21 0

SYSTEMWISE TESTING & COMMISSIONING 237 07-May-20 31-Dec-20 0 31-D


PHASE- I 52 07-May-20 28-Jun-20 33 28-Jun-20, PHASE- I
STATUATORY INSPECTION- FIRE FIGHTING 10 18-Jun-20 28-Jun-20 0 28-Jun-20, STATUATORY INSPEC
A2810 CFO Site Inspection & Approval 10 18-Jun-20 28-Jun-20 0% 0 CFO Site Inspection & Approval
HVAC 36 08-May-20 12-Jun-20 10 12-Jun-20, HVAC
T4-TC-HVAC-P1-7035 Commissioning of Pressurisation System 10 08-May-20 17-May-20 0% 36 Commissioning of Pressurisation System
T4-TC-HVAC-P1-7045 Commissioning of Ventilation System 10 08-May-20 17-May-20 0% 36 Commissioning of Ventilation System
LEVEL P2- HVAC ROOM 10 12-May-20 22-May-20 31 22-May-20, LEVEL P2- HVAC ROOM
T4-TC-HVAC-P1-7055 Commissioning of Chilled Water System (P2) 10 12-May-20 22-May-20 0% 31 Commissioning of Chilled Water System (P2)
LEVEL S1- HVAC ROOM 10 08-May-20 17-May-20 36 17-May-20, LEVEL S1- HVAC ROOM
T4-TC-HVAC-P1-7065 Commissioning of Heat Recovery Unit (S1) 10 08-May-20 17-May-20 0% 36 Commissioning of Heat Recovery Unit (S1)
LEVEL 22- HVAC ROOM 17 27-May-20 12-Jun-20 10 12-Jun-20, LEVEL 22- HVAC ROOM
T4-TC-HVAC-P1-7075 Commissioning of Heat Exchanger System - (FL22) 10 27-May-20 05-Jun-20 0% 10 Commissioning of Heat Exchanger Sys
T4-TC-HVAC-P1-7085 Commissioning of Heat Recovery Unit - (FL22) 7 06-Jun-20 12-Jun-20 0% 10 Commissioning of Heat Recovery Un
T4-TC-HVAC-P1-7095 Commissioning of Chilled Water System - (FL22) 10 27-May-20 05-Jun-20 0% 17 Commissioning of Chilled Water System
PHE / FF 45 08-May-20 22-Jun-20 1 22-Jun-20, PHE / FF
LEVEL B2 - PLANT ROOM 15 08-May-20 22-May-20 31 22-May-20, LEVEL B2 - PLANT ROOM
T4-TC-PHE-P1-7045 Commissioning of Domestic Water Supply System (B2) 5 08-May-20 12-May-20 0% 31 Commissioning of Domestic Water Supply
T4-TC-PHE-P1-7055 Commissioning of Grey Water Supply System (B2) 5 13-May-20 17-May-20 0% 31 Commissioning of Grey Water Supply Sys
T4-TC-PHE-P1-7060 Commissioning of Sump Pump System (B2) 5 18-May-20 22-May-20 0% 31 Commissioning of Sump Pump System (B2)
T4-TC-PHE-P1-7065 Commiosioning of Fire Fighting System (B2) 10 08-May-20 17-May-20 0% 36 Commiosioning of Fire Fighting System (B2)
LEVEL 22 - PLANT ROOM 25 28-May-20 22-Jun-20 1 22-Jun-20, LEVEL 22 - PLANT ROOM
T4-TC-PHE-P1-7075 Commissioning of Domestic Water Supply System (FL22) 10 28-May-20 07-Jun-20 0% 1 Commissioning of Domestic Water Su
T4-TC-PHE-P1-7085 Commissioning of Grey Water Supply System (FL22) 10 07-Jun-20 17-Jun-20 0% 1 Commissioning of Grey Water Supp
T4-TC-PHE-P1-7095 Commissioning of Sump Pump System (FL22) 5 17-Jun-20 22-Jun-20 0% 1 Commissioning of Sump Pump Syst
ELECTRICAL 39 07-May-20 15-Jun-20 46 15-Jun-20, ELECTRICAL
TESTING & COMMISSIONING WITH PERMANENT POWER 39 07-May-20 15-Jun-20 46 15-Jun-20, TESTING & COMMISSIO
T4-TC-ELE-P1-8005 Availability of Permanent Power 0 07-May-20 0% 21 Availability of Permanent Power
T4-TC-ELE-P1-8015 Testing & Commissioning of Electrical Room at B1 25 08-May-20 01-Jun-20 0% 46 Testing & Commissioning of Electrical R
T4-TC-ELE-P1-8025 Commissioning of DG Sets 0 01-Jun-20 0% 46 Commissioning of DG Sets
T4-TC-ELE-P1-8035 Power On MDB's at B1 Level 14 02-Jun-20 15-Jun-20 0% 46 Power On MDB's at B1 Level
PHASE- II 47 14-Nov-20 31-Dec-20 0 31-D
PHE / FF 39 14-Nov-20 23-Dec-20 8 23-D
LEVEL ROOF - PHE / FF PLANT ROOM 39 14-Nov-20 23-Dec-20 8 23-D
T4-TC-PHE-P2-7105 Commissioning of Domestic Water Supply System (ROOF) 10 14-Nov-20 23-Nov-20 0% 27 Commissio
T4-TC-PHE-P2-7115 Commissioning of Grey Water Supply System (ROOF) 10 24-Nov-20 03-Dec-20 0% 27 Commis
T4-TC-PHE-P2-7125 Commiosioning of Fire Fighting - Hydrant System (ROOF) 10 03-Dec-20 13-Dec-20 0% 8 Comm
T4-TC-PHE-P2-7135 Commiosioning of Fire Fighting - Sprinkler System (ROOF) 10 13-Dec-20 23-Dec-20 0% 8 Comm
HVAC 40 21-Nov-20 31-Dec-20 0 31-D
LEVEL ROOF- COOLING TOWER 40 21-Nov-20 31-Dec-20 0 31-D
T4-TC-HVAC-P2-7145 Commissioning of Cooling Tower System 20 21-Nov-20 11-Dec-20 0% 0 Commi
T4-TC-HVAC-P2-7155 Commissioning of Chilled Water System 10 11-Dec-20 21-Dec-20 0% 0 Comm
T4-TC-HVAC-P2-7165 Commissionig of Ventilation System 10 21-Dec-20 31-Dec-20 0% 0 Com
INTEGRATED TESTING & COMMISSIONING 223 22-Jun-20 31-Jan-21 0
PHASE- I 39 22-Jun-20 31-Jul-20 1 31-Jul-20, PHASE- I
A2830 Intergrated Testing & Commissioning of Supremus Floors 39 22-Jun-20 31-Jul-20 0% 1 Intergrated Testing & Commis
PHASE- II 31 31-Dec-20 31-Jan-21 0

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 78 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work
Activity ID Activity Name Ori Start Finish % Comp Total 2019 2020 2021
Dur May J Jul
Float A Sep Oct N Dec Jan F Mar Apr May J Jul A Sep Oct N Dec Jan
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
A2870 Integrated Testing & Commissioning of Entire Building / Excelus Floors 31 31-Dec-20 31-Jan-21 0% 0

Remaining Level of Effort Milestone Initial Works Programme- Revision Log Data Date: 21-Sep-19
Page 79 of 79
Date Revision Checked Approved Layout/Filtter Name: General
Actual Work Summary
30-Jan-19 0 Layout IWP
Remaining Work
Critical Remaining Work

You might also like