REPORTE AVANCE AL 23-05-17

Desc. Trab. AVANCE

Data
Nivel Labor Sum - Programa (mt) Sum - CANTIDADREAL
-580 RP_78 80 0
-550 XC_5021_550 80 0
-520 RP_4283 10 0
XC_4283_10 20 19
XC_4283_13 20
XC_4283_2 80 51
XC_4283_4 18
XC_4283_5 20
XC_4283_7 11.7
-490 XC_4313_35 17 21
XC_4313_36 6.4 5
XC_4313_37 6.8 5.5
XC_4313_4_1 15 17 18
XC_4313_4_2 8.3 8.2
XC_4313_40 12 6.8 6.8
XC_4953_3 8.3 5
XC_4986_1_490 25 8.3 7.2
XC_4986_490 70 68 64
XC_5009 50 54.4 54
XC_5604_1_490 17 0
-460 RP_4313_2 6.8 6.9
XC_4155_N 50 40.8 36
XC_4155_S 50 23.8 16
XC_4313_25_4 3.4 3.3
XC_4313_26 70 74.8 64
XC_4313_26_3 6 7.9 9
XC_4313_26_4 6 7.9 6.7
XC_4313_26_5 6 4.9 5.3
XC_4313_44 10 17
XC_4313_46_1 6.8
XC_4332 50 10.2
XC_4332_17 25
XC_4993_2 13.2
XC_5029_1 33.6
XC_5604 23 33.6
-440 XC_4929_3 3
XC_4929_4 3
-425 RP_4392_1 43 52.5
XC_4647_4 10 47.8
XC_4647_5 6.4
Total Result 866 680.4
REPORTE DE SOSTENIMINETO
Mes MAYO
Desc. Trab. SHOTCRETE
Fecha - all -

Data
Nivel Labor Espesor(pulg) Actividad Sum - CANTIDA Sum - M3 Observaciones
-460 XC_4332 2 SH 501 40 Falta avanzar para continuar shotcrete
3 SH 198 22 Falta completar shotcrete
20 XC_4054 3 SH 108 12 culmino
-95 XC_3927 3 SH 144 16 culmino
Total Result 951 90

Mes MAYO
Desc. Trab. Perno Helicoidal
Fecha - all -

Sum - CANTIDAD REPORTE TIPO DE TRABAJO


Nivel Labor Actividad Und CONVENCIONALMECANIZADO OBERVACIONES
-520 XC_4283_11 IPM Und 115 Culmino
XC_4283_2 IP Und 18 Culmino
IPM Und 127 Falta ajustar 15 pernos
XC_4283_8 IPM Und 65 Culmino
-490 XC_5009 IPM Und 47 Falta completar
XC_4313_29 IPM Und 33 Falta completar
-460 XC_4313_25 IPM Und 193 Falta ajustar
XC_4332 IP Und 82 Falta completar
XC_4332_5 IP Und 18 Falta completar
XC_5604 IPM Und 68 Culmino
XC_4339 IP Und 58 Falta completar
-425 XC_4460_5 IPM Und 10 Falta acsesar para medir
Total Result 10 824