Professional Documents
Culture Documents
Donner Company Caseanalysis
Donner Company Caseanalysis
On
“Donner Company”
1. Problem Analysis
Here we try and analyze the problems which could have led to fall in profit of the company:
1.1. Production bottleneck: Since Donner received different types of circuit board to be manufactured
from different clients, they faced bottlenecks at different points in the process flow. This was a regular
occurrence but didn’t have any pattern as such and hence no solution till now had been found of dealing
with such bottlenecks. Here are some reasons which led to development of bottlenecks:
a. Rush orders: Donner had promised delivery time for rush orders as 4 days and hence when
received, these orders were given priority and replaced existing orders which were in process; thus leading
to frequent bottlenecks at different stages. These rush orders had a frequency of three a week.
b. Modifications post order placement: Sometimes, the customer requested modifications in the
board design after the manufacturing process had started. This stalled the production and consumed a lot of
time as the modification needed to be worked upon into the design and approved which resulted in almost
two weeks delay. Such modification requests in the design of the boards ranged between 1-9 per week.
c. Cross training and constant resource shuffling: The idle resources were often relocated at a
different work station when they were idle. This resulted in piling up task in their original location as they
had no proper forecast of when they would be required back on their original task also resulted in
bottlenecks.
a. Wrong estimation of working time: It was found that the labor hours did not correctly denote
the additional time a resource spent on reworking on parts which failed inspection or were returned by
customer. Moreover, Movement of boards between operations was also not accounted for and method
improvements lead to bottlenecks at subsequent operations.
b. Interruption in task: Most of the operators had to move in between their task almost 6-12 times
per day to seek advice, ask for work from upstream sources and for the delivery of the completed work.
This further added to the time taken and denotes the lack of set process flow and communication between
different operations and their workers.
1.3. Lack of quality standards:
a. Return rework: The quality standards of each finished product ranged from client to client.
Some had a lot of margin of error and only an informal check was required whereas some had pretty
stringent set of standards. This resulted in almost 1 of 10 deliveries lacking in quality in terms of missed
parts or other quality constraints.
Like in most cases the major concerns was because of procrastinating work till the end of the month where
prior work needs to be dispatched by month end. This naturally affected the utilization in the earlier part of
the month and also results in more overhead during the month end.
In the manufacturing process of Donner’s company there are some bottlenecks which require modifications:
Equating the total time taken (setup time +run time) for both CNC Drill and manual drill:
240+2X = 15+40X
38X = 225
Thus,
2. Breakeven points to determine which one to use between CNC router and manual punch
press
Thus, by equating the total time taken (setup time +run time) for both CNC Router and Punch Press:
50+X = 150+0.5X
0.5X = 100
X = 200
Thus,
When the order size is more than 200, CNC Router should be used
When the order size is less than 200, Punch Press should be used
Order size
8 80 800
DFPR area
Panel Prep 738.4 5485.6 15360
Laminate & Expose 174.4 960 1744
Develop 190.08 1744.8 9600
Thus,
If order size is 8 boards, then to avoid bottleneck the orders should be of less than 174 boards per
day.
And, If order size is 80 boards, the maximum daily capacity of DFPR is 960 boards.
Based on the analysis we found out that laminate and expose of DFPR process is the bottleneck.
3. Recommendations
The donner company was facing difficulty in taking longer time to complete their different tasks and delay
in their delivery time. Following are some of the suggestions for the same:-
1.They can save time by setting up the artwork and the inspect & shear and punch tooling holes
simultaneously at the same time. Performing this task in large batch sizes can be possible:-
3. The flow time of the process can be reduced if the facility layout is enhanced. The assembly line is not
strategically placed which on some instances has cost them around 15% of the working hour to relocate
from one process to another.
4. They can separate the production line and produce the small and large quantities of simple technology
boards in two separate lines. As we can see from the exhibit 4 that 4531 orders out of the 5761 orders were
of sizes greater than or equal to 200 which is more than the 78% of the total orders they received. As the
CNC machine uses less time for higher batch sizes. It can be very beneficial to move the units in two
separate lines in many ways. Firstly it will resolve the problem of bottleneck. It can reduce the delay time
of large orders which is currently 9 days. Secondly, it will increase the workers efficiency which is currently
underutilized as they are working only 41.4 % of their time (1531/3696). Lastly the defects and repetitive
works will get reduced because now the resources will be channelized and the workers won’t have to shift
from one process to another.
5. The organizational structures should be improved so that it won’t cost more issue in handling the flow
of processes or in instructing and assisting workers, or in inspecting products or for the modifications in the
change of the customers. If these processes won’t be solved in time they might create bottleneck in the
process.
6. It has proved to be wastage of time by randomly assigning workers to the available process my moving
them from one task to another. The workers should be trained in their preferred specializations and should
be assigned to the task related to that