Completion & Workover – DURI09857 – 5G-0302A

CHEVRON PACIFIC INDONESIA - SUMATERA OPERATION


COMPLETION & WORKOVER PROGRAM – DURI – DURI09857 – 5G-0302A

7/18/2019

PREPARED BY: ROHUL RAMADHAN X ROHU


COMPLETION ENGINEER Rohul Ramadhan
Completion Engineer
Signed by: Rohul Ramadhan
7/18/2019

SANTOSO BUDI UTOMO X sanbudi


REVIEWED BY: DC ENGINEERING TEAM LEAD Santoso Budi Utomo
D&C Engineering Team Lead
Signed by: Santoso Budi Utomo
7/18/2019

S. NURMANTHIAS X NSA
DC OPERATION TEAM LEAD Nurmanthias
D&C Operation Team Lead
Signed by: Nurmanthias Setiaw an

RIG : BN 11
AFE NUMBER : 2500CP7455
AFE AMOUNT : $48,805.00
PROGRAM NUMBER : DURI0985720190715RLN12
EST. TIME : 5 DAYS
Completion & Workover – DURI09857 – 5G-0302A

WELL COMPLETION & WORKOVER PROGRAM


5G-0302A - DURI09857

Table of Content
A. OBJECTIVES .................................................................................................................................................... 2

B. INFORMATION AND DETAILS ........................................................................................................................... 2

1. BASIC WELL DATA ......................................................................................................................................................2


A. BEFORE AND AFTER DIAGRAM - WELL SCHEMATIC ............................................................................................................ 3
B. CURRENT - WELL SCHEMATIC........................................................................................................................................ 4
2. AS BUILT DATA – CASING/LINER DATA............................................................................................................................5
3. COMPLETION INTERVAL – GEOLOGICAL DATA, WELL PRESSURE, WELL TEMPERATURE, AND CALCULATED MASP ..........................5
4. WORKOVER HISTORY ...................................................................................................................................................6
5. GENERAL DATA ..........................................................................................................................................................6
6. WELL CONTROL RISKS..................................................................................................................................................6
7. COMPLETIONS FLUID MANAGEMENT PLAN ......................................................................................................................7
8. CASING/TUBING TEST PRESSURES ..................................................................................................................................8
9. BARRIER....................................................................................................................................................................8
10. DISPLACEMENT PROCEDURE........................................................................................................................................9
11. RIG - BOP CONFIGURATION........................................................................................................................................9
12. CHOKE MANIFOLD CONFIGURATION ...........................................................................................................................11
13. SHEAR TABLE .........................................................................................................................................................11
14. BOP TEST PRESSURES AND FREQUENCY ......................................................................................................................12

C. JOB PROCEDURE – BASE PLAN ....................................................................................................................... 13

1
Completion & Workover – DURI09857 – 5G-0302A

A. Objectives
The program objectives are:
• Maintain Well Control at All Times
• Provide safe and reliable operations
• POH tubing pump, run CBL/ USIT, perform pressure test casing, RIH tubing pump with the same
size and pump depth

B. Information and Details


1. Basic Well Data
Well Name DURI09857
Well Grid 5G-0302A
Well Coordinate 1° 22' 33.891'' N, 101° 13' 48.934 '' E
Well Type Oil Producer - Vertical
Spud Date 2/13/2014 9:30:00 AM
RTE (feet) 59.8
GLE (feet) 42.3
MD/TVD (feet) 615 / 615
PBTD (feet) 614
Wellhead Picture: Note:
1. Sucker Rod Pump producer well tree type in
good condition.
2. Casing Head: CPO 13-3/8”– 2M buried
underground
3. Tubing Head: Flange type 9-5/8” – 2M
4. Well status is OFF
5. Well pad & Access road is in good Condition
6. WCT is on location and recent SICP/SITP 5/5
psi

2
Completion & Workover – DURI09857 – 5G-0302A

a. Before and After Diagram - Well Schematic

3
Completion & Workover – DURI09857 – 5G-0302A

b. Current - Well Schematic

4
Completion & Workover – DURI09857 – 5G-0302A

2. As Built Data – Casing/Liner Data


Type Surface
Size (Inch) 13.37 Burst Rating (psi) 1911 (70%)
OD (Inch) 13.37 Collapse Rating (psi) 791 (70%)
ID (Inch) 12.62 Tension Rating (klbs) 853
Weight (lb/ft) 54.5 Setting Depth (MD) 205
Grade K-55 Setting Depth (TVD) 205
Pressure Test No, based on Historical Data.
Type Production Casing
Size (Inch) 9.63 Burst Rating (psi) 2464 (70%)
OD (Inch) 9.63 Collapse Rating (psi) 1414 (70%)
ID (Inch) 8.92 Tension Rating (klbs) 564
Weight (lb/ft) 36 Setting Depth (MD) 379
Grade K-55 Setting Depth (TVD) 379
Pressure Test No, based on Historical Data.
Type Tubing
Size (Inch) 2.88 Burst Rating (psi) 5082 (70%)
OD (Inch) 2.88 Collapse Rating (psi) 5376 (70%)
ID (Inch) 2.44 Tension Rating (klbs) 72.58
Weight (lb/ft) 6.5 Setting Depth (MD) 583
Grade J-55 Setting Depth (TVD) 583
Pressure Test No, based on Historical Data.
As Built Data – Fluid Inside Casing
Fluid Type Water
Fluid Weight (ppg) 8.33 PPG

3. Completion Interval – Geological Data, Well Pressure, Well Temperature, and Calculated MASP
Pressure and temperature refer to: Fluids data Assumption:
Est. Maximum Formation Temp. at Rindu sand, (447' TVD): 152deg.F Oil Avg. API Duri: 22 deg. API
Est. Maximum Formation Pressure at Pertama sand, (610' TVD): Oil Fluid Gradient: 0.3992 psi/ft
243.9268 psi Gas Gradient: 0.1 psi/ft
Gas/Oil Mixture Gradient: 0.23
Estimate Fract. Gradient: 0.5408 psi/ft
psi/ft
Potential GOR: 0 MSCF/STB
MASP = 45.4psi
Maximum Bullheading or Injection pressure (below fract pressure) = 48.2psi, *use water
Calculated MASP:
Penetrated Top Reservoir Reservoir Reservoir Fluid
press. Hydrocarbon MASP
Reservoir Sand Status depth press. temp. (deg Gradient
(ppg) content (psig)
Sand TVD/MD (psig) F) (psi/ft)

Rindu Exposed 447/447 224 9.6 152 Oil 0.40 45


Pertama Not Exposed 610/610 244 7.7 152 Oil 0.40 1

5
Completion & Workover – DURI09857 – 5G-0302A

4. Workover History
- This well indicated has high casing and tubing pressure. Please do same procedure as well
5G0905A caused bubbling near well head during injected water thru annulus.
- Last Rig job was PMP05 (NPN) on 06-Mar-2015 by CPI-98. TOS @ 605 ft (10 ft Sand Fill), COS to
615 ft (PBTD). No well control issue.
- No other rig job or any workover job performed yet on well since drilled.
Date Comments
15/07/19 WCT- Cooling Down Well
WCT is on location to cooling down well. As update on 5 Jul 2019 the
pressure was 5/5 psi. Waiting on rig to execute the well.
07/01/19 BN 08 – LW – No Operation Issue – Pending well,
- Initial SITP/SICP 100/150 psi. Initial cooling down total 1080 bcw,
KCL water 9.6 ppg 360 bbls.
- Oil and hot water in return
- Final SITP/SICP 30/45 psi. Pending the well
5/3/2019 SET BDJ TRUCK PT. ACS - PJM. RUN PRESS 70/70 PSI. BUP W/10 STRKS.
PRESS 80/80-80/80 PSI. LOWERED PLGR 6 INCH. BUP W/10 STRKS. PRESS
300/300-300/300 PSI. FINAL PRESS 70/70 PSI.
2/26/2017 COMPLETED INJECTED STEAM1.5 BBTU @16:30 BY CYCLIC UNIT
11/21/2016 COMPLETED INJECTED STEAM 1.5 BBTU @15:00 BY CYCLIC UNIT
6/20/2016 COMPLETED CYCLIC STEAM INJECT1.5 BBTUs @ 12:30, MOVE CYCLIC
UNIT TO NEW LOCATION
5/24/2015 SET BDJ TRUCK PT. ACS - PJM. RUN PRESS 90/75 PSI. BUP W/3 STRKS.
PRESS 300/200-80/80 PSI. LOWERED PLGR 4 INCH,FISH,HIT AND RESET
STD VLV. BUP W/2 STRKS. PRESS 300/300-300/300 PSI. FINAL PRESS
105/95 PSI. THE WELL RE POP @ 22:15 HRS.

5. General Data
Mechanical Status • Last Tag at 605 ftMD
in Wellbore • No mechanical problem
Installed Wellhead • Casing Head: CPO 13-3/8” – 2M
• Tubing Head: SOW 9-5/8 x Flanged 11” – 2M
Bit History • Surface Section: 17.5” bit to 213’
• Production Section: 9.87” bit to 622’
Primary Cementing • Surface Casing: Full Circ. had 12 bbls cement return.
History • Production Casing: Had 10 bbls cement return to surface. Float held
No CBL Data

6. Well Control Risks


• No well control issue experienced.
Reservoir Pressure • Production from RINDU, MASP 45 psi
• Pressure may be higher than anticipated due to Steam
Potential Risk:
Reservoir Fluid • Uncontrolled flow of hydrocarbon or steam to surface
• Higher GOR causing high shut-in pressure and flammability

6
Completion & Workover – DURI09857 – 5G-0302A

• Presence of H2S causing personnel injury


• Hot water or crude oil causing personnel injury.
Potential Risk:
• Well is produced from Rindu
Fluid Losses
• In case need LCM, there's risk for shortage of LCM. However,
Service provider can deliver to location within 30 km
Potential Risk:
Mechanical Condition of • Plunger and rods left in hole unable to recover
• Tubing stuck, unable to pull with maximum capacity
Well Bore
• Tubing broken/ collapsed after pulling
• Sand/ clay fill up wellbore, blockage the annulus
Verified presence, Internal barriers
integrity, and suitability • (no verified existing barrier)
of existing barriers External barrier
including internal and • (no verified existing barrier)
annular cement.
High/Low Pressure • Only Rindu sands is opened. There is no chance of high / low
formations above/below pressure risk.
the interval to be
completed/isolation
Surrounding injector wells may have impact (i.e. cause well control
event) to the wellbore. Shut in active steam injector nearby below:
1. 5G0303A-R, 78 m (already shut in)
Offset Injector Wells 2. 5G0103A-R, 172 m (already shut in)
Management Plan Monitor steam injector below, shut in if experience initial killing
problem:
1. 5G0503A-R, 170 m
2. 4G0313A-R, 191m
Other No other significant risks were evaluated.

7. Completions Fluid Management Plan


• Initial Killing use Fresh or Formation water (8.33ppg). Fill up well to cool
down or/and maintain over balance.
• If water density is not enough to kill the well then completion fluid density
can be determined as following formula (ensure well’s annulus or string has
been filled up with fresh or formation water) :
KF ppg = 8.33 ppg + {(Shut-in Pressure*)/(0.052 x TVD)} + 0.5 ppg (SF)
Minimum
* If bullheading through tubing use SITP
Overbalance
If bullheading through annulus use SICP
• Completion Fluid Brine i.e. KCL, NaCl and combination of Sodium Formate
and Sodium Nitrate are commonly used for killing fluid within the area
operation which will be provided by a third-party Contractor
• Based on history, this well doesn’t have killing problem history. In case found
pressure, we will use safety factor 0.5 ppg

7
Completion & Workover – DURI09857 – 5G-0302A

• Maximum pore pressure is 8.61ppg, which is slightly high than water, but for
initial killing will use water at first then stabilized shut in pressure will be use
to calculate KF. Please prepare estimate 9 – 9.5ppg KF.
Expect low/high fluid losses from Rindu sand, up to 20 BPH
Mitigation for Fluid Loss:
- Refer to IBU SMO Loss circulation SOP section 2.2
- There are 2 tanks available in rig site with both have maximum 200 bbls
capacity or total for 2 tanks are 400 bbls. With average pump rate 2-5 bpm, 2
tanks could supply water for 80 – 200 minutes depends on the fluid loss and
supply water from killing line.
- Each of area has dedicated stand pipe or central gathering station (either
treated formation water or fresh water): Stand pipe 5U and 6L Brine and Mud
Fluid loss are provided by third party contractor (PT. Matra Unikatama).
control plan - With 1 load of vacuum or tanker capacity is 60 bbl., we need 7 load to full the
tank. We need the vacuum to re-fill up rig tank every 12 – 30 minutes to get
continues pumping (assuming no fluid in the tank).
- Based on assessment, the access road to location is good enough for vacuum
truck to reach the location. The availability of vacuum truck to be discussed
with operation team in Pre-Operation Meeting.
- If polymer is needed. Chemical for mixing polymer will be provided by service
company (Matra Unikatama) which base is located within 30 KM from the
field.

TCT/PCT N/A
Hydrates
N/A
Suppression

8. Casing/Tubing Test Pressures


Casing test is required in this program
Casing test value is defined as per DCM-BST-102002-A-IBU-SMO 500psi + MASP/MAWP. Casing
test variance is 5% and 15 minutes stabilized as per Well Barrier Design SOP revised as per MOC
Barrier Test or Well Barrier Design SOP Black language.

9. Barrier
No Operatio Procedure Internal Barrier External Barrier
n
1. Routine POH Plunger and 1) Kill Weight Fluid 1) Kill Weight Fluid
Sucker Rod 2) Rod BOP 2) Tubing hanger
2. Non- N/D or N/U Tree Kill Weight Fluid inside 1) Kill Weight Fluid
Routine wellbore 2) Tubing Hanger
3. Routine N/U or N/D BOPE 1) Kill Weight Fluid 1) Kill Weight Fluid
2) Stab-in FOSV/IBOP 2) Tubing hanger
4. Routine Tripping with OE, 1) Kill Weight Fluid 1) Kill Weight Fluid
or other DHT with 2) Stab-in FOSV/IBOP 2) BOP
definite diameter

8
Completion & Workover – DURI09857 – 5G-0302A

5. Routine Release / install 1) Kill Weight Fluid 1) Kill Weight Fluid


packer with 2) Stab-in FOSV/IBOP 2) BOP
Workstring
6. Routine Fishing operation 1) Kill Weight Fluid 1) Kill Weight Fluid
with DP (jar 2) Stab-in FOSV/IBOP 2) BOP
up/down) (Ready at rig
floor/wellhead)
3) Check valve pump
7. Non- Wells Unable to Continue operations while Continue operations while
Routine Hold a Column of pumping fluid into the well pumping fluid into the well
Fluid. regularly. If there is no regularly. If there is no bleeve
bleeve history & free gas, history & free gas, wellbore
wellbore will have static will have static fluid level at
fluid level at some point, some point, monitor and fill
monitor and fill up wellbore up wellbore as needed.
as needed.
8. Routine Perforation/ 1) Kill Weight Fluid 1) Kill Weight Fluid
Logging 2) PCE &BOPE 2) PCE &BOPE
9. Non- Non-Sealing Kill Weight Fluid Kill Weight Fluid
Routine Tubing hanger

10. Displacement Procedure


There is foaming job on this well.
Foaming job:
Internal barrier are hydrostatic, kelly cock/FOSV and IBOP. Meanwhile external barrier are
hydrostatic and BOP. BOP will be in open position during the displacement. Kelly Cock/FOSV and
IBOP will be installed at work string during execution to secure work string in case well control
incident happens. Detail procedure for Aerated/foaming job is available procedure.

9
Completion & Workover – DURI09857 – 5G-0302A

11. Rig - BOP Configuration


RIG: BN 08
BOP Specification & Configuration - The following information for the Blow Out Preventer (BOP) stack shall
be specified for the well or well program/grouping.
No Acceptance Criteria Data
1. Quantity, Bore ID & Pressure Rating of Annular Preventer(s) 1 Unit/Ready/11 Inch x 3000 Psi
1 Unit, 11 Inch, 3000 Psi, Shear Blind
2. Quantity, Bore ID and Pressure Rating of the Ram Preventers
Ram
Configuration of Ram Preventers to include position within
the stack and Ram Type (i.e. Fixed Pipe, Variable Bore,
3. See picture BOP configuration below
Casing, Blind Rams, Blind Shear Rams, Shear Rams, Casing
Shear Rams, etc.)
Available Single Ram, size 11in x 3000
For each Pipe Ram type preventer provide pipe size or size
4. Psi c/w Blind Shear Ram, See picture
range and hang off capacity
BOP configuration below
Location, bore ID and Pressure Rating of the Choke & Kill 3-1/8 Inch x 3000 Psi (Choke), 3 Inch x
5.
Valves & Lines 3000 Psi (pipe Line)
Reference point and distance from reference for each See BOP space out diagram section
6.
component in the stack below
Elastomer type is Nitrile (NBR) with
Temperature rating and fluid compatibility of BOP temperature range -20 to 190 deg. F.
7.
rubbers/elastomers Oil and water-based muds. Poor
Resistance to H2S
BOP Class 2
Component Dimension
Ram to WPF (A) 8.67 Ft.
Annular to WPF (B) 5.57 Ft.
Space to WPF (C) 0.72 Ft.
Drip Pan (D) 2.85 Ft.
Annular (E) 3.39 Ft.
Shear Blind Ram (F) 3.33 Ft.
Drilling Spool (G) 2.65 Ft.
Total BOP Stack (H) 16.55 Ft.

12. Choke Manifold Configuration

Heavy Oil Operation

10
Completion & Workover – DURI09857 – 5G-0302A

13. Shear Table

11
Completion & Workover – DURI09857 – 5G-0302A

14. BOP Test Pressures and Frequency


Allowable Pressure
Equipment Tested Pressure Test Requirement
Rating (psi)
BOP Class 2 – HO Operation
Low: 250 – 350 psi
Annular 2,100 (70%)
High: 1200 psi 5 minutes hold, with no
Low: 250 – 350 psi visible leakage
Shear Blind Ram 3,000
High: 1200 psi
Note:
• Ensure not to exceed 70% Casing Burst Pressure or 100% Wellhead RWP or 70% Annular RWP
or 100% Packer RWP
• All pressure tests must be recorded on a pressure recording chart (use Barton chart) and
BOP test form. The Chevron site representative shall witness and sign off on all BOP &
Choke manifold pressure tests.
The Frequency of the BOP tests
Annular, Ram BOP, Choke Manifold, IBOP (Ready at rig floor/wellhead) and FOSV must be pressure
tested as follows:
a. Not exceed interval of 21 day
b. Before the equipment is put into operational service on wellhead
c. In accordance with the equipment owners PM program
d. Following the disconnection or repair of any wellbore pressure seal in the BOP stack
assembly or choke manifold (limited to the affected components only)
Chamber pressure test shall be performed and charted as follow:
a. At least once yearly
b. When equipment is repaired or manufactured
c. In accordance with the equipment owners PM program

12
Completion & Workover – DURI09857 – 5G-0302A

C. Job Procedure – Base Plan

HO Completion
Engineering
Team -
Recommendation
DC Eng SMO
Rumbai - 2019.

GENERAL PROCEDURE FOR WORKOVER HOOU - IBU


SMO COMPLETION
WELL NAME / ID 5G0302A-01
JOB TYPE RLN12 - Light Workover, SLWO, Spc Killing Job
CURRENT WELL STATUS OFF || 6/25/2019 3:00:00 PM || PRESSURE
PROGRAM NUMBER DURI0985720190715RLN12
WELL PROFILE VERT
PROD CASING SHOE 379 ft
CURRENT TBA 332 ft
CURRENT/ PROPOSED 583 ft / 583 ft
PS
CURRENT PBTD 614 ft
DEVELOPED BY Fadhlan/Riko (16/07/2019)
Last Job History:
- This well was drilled on 16-Feb-2014 wih OHGP completion type and vertical well profile. Original target sand
is R.
- This well indicated has high casing and tubing pressure. Did the same procedure as well 5G0905A caused
bubbling near well head during injected water thru annulus.
- Last Rig job RLN07 (LW) on 01-Jul-2019 by BN-08 was suspended due to killing problem. LW Program + LOG14
suspended. Used ttl 1080 bbls water, ttl 520 bbls KCL water up to 9.6 ppg.
Initial Killing: SICP = 150 psi, Initial SITP = 100 psi, Cooling down well w/ 360 bbls water, with pump rate 4-5
bpm, pumping pressure 150 psi. Shut in well and observed for 1 hrs, bleed off pressure found well retun oil +
water. Shut in well found SICP = 70 psi / SITP = 30 psi.
Last Pressure before suspended: SICP : 45 psi, SITP :30. Bleed of Pressure , found oil hot water on return w/
rate 10.4 BPH w/ 8.5 ppg. Circulated 24% KCL water 40 Bbls 3 Bpm70 Psi and reverse circulation w/ 8.5 ppg
- NWW12 (WCT) tried to cool down well on 15-Jul-19. Initially bleed off pressure SITP : 130 Psi SICP : 130 Psi.
Last bleed off pressure SICP : 5 Psi SITP : 5 Psi.
- PMP05 (NPN) on 06-Mar-2015 by CPI-98. TOS @ 605 ft (10 ft Sand Fill), COS to 615 ft (PBTD). No well control
issue.
- Now asset propose to conduct LWK job to resolve killing problem on suspended RLN07 program, continue
LOG14 program (run CBL / USIT), conduct pressure test casing and then RIH TP.

Head Up List before moving into the well:


- Ensure to req to FOD (PMT) to shut off electric source and LOTO prior rig enter the location

NO PROCEDURE

13
Completion & Workover – DURI09857 – 5G-0302A

Time
(hrs)
1 MIRU RIG. 12
2 N/D PRODUCTION LINE. 2
3 CHECK SICP AND SITP, RECORD IN WELLVIEW. LINE UP LINES FROM CASING AND
TUBING TO TANK. BLEED OF CASING AND TUBING PRESSURE TO 0 PSI (OR AS
LOWEST AS POSSIBLE). CONTINUE TO KILL THE WELL.

Make sure to kill the well properly before commencing workover operation and
also maintain primary well Control at all time (WSEA 3A and 3B)

Last killing history: Used ttl 1080 bbls water 8.33 ppg and ttl 520 bbls KCL water up
to 9.6 ppg. SICP : 45 psi, SITP :30 (Unsuccessful killing)

If found clay problem in previous job, please use 2-8% KCl in killing fluid

STEP 1:
Pump water with 2-6 bpm every ~100 bbls. Shut in, check pressure and bleed off.
Maximum total volume to be pumped is 1500 bbls 36
STEP 2:
a. IF steam still in return, shut in another injector nearby or Suspect contributed
steam, continue cooling down for another 500 bbls with maximum pump rate
b. IF no steam in return, measure fluid return weight and calculate required KF using
below formula:
KF (ppg) = 8.33 (ppg) + 0.5 ppg (SF) + (Shut-in Pressure (psi)*)/(0.052 x TVD top of
perforation (ft))
Pump KF with maximum 2 times wellbore volume
STEP 3:
Pump polymer 40-80 smf with LCM 40-80 ppb, XX bbls maximum 2 times wellbore
volume
For any other issue or option during initial killing, please discuss with CE and TL Ops

IF well still flowing, discuss with CE and TL Ops for pending job option
4 DISCONNECT STUFFING BOX, RELEASE POLISH ROD, POH PLUNGER AND SUCKER
ROD STRING

History: 2-1/4" PLGR ON 21 JTS 3/4" S.ROD + 18' P.ROD (ALL S.ROD F/PIPE RACK -
BY USING 3/4" SHEAR COUPLING). INSTALLED 1-1/4" PLSH ROD

Fishing Tree Plan if found plunger stuck, 2


--> Option #1 : Apply over pull and reciprocate plunger or break shear coupling.
--> Option #2 : Blind backoff sucker rod.
--> Option #3 : Cut sucker rod using rod cutter.
--> Option #4 : Pull with tubing pump to recover the succer rod (stripping job)
Other options will be dictated based on the fish condition. Discuss with fisherman
and TL Operation.

14
Completion & Workover – DURI09857 – 5G-0302A

5 N/D X-MAS TREE, INSTALL FOSV, AND N/U BOP (ENSURE WELL SECURE). PERFORM
FUNCTION TEST AND PRESSURE TEST BOP.

Low pressure test BOP'S to 250 psi and high pressure test to 650 PSI or 500 + MASP
hold 5 minutes each. Record on Borton chart (WSEA 9B) 6

Inspect wellhead connection, valves, seals. replace if necessary.

6 POH EXISTING TUBING STRING

History: 2-1/4" TP (1052043) ON 17 JTS 2-7/8" NUE TBG. INSTALLED TBG D.NUT
AND SET TP @ 683'

Remaining Fish: N/A

Step of Fishing Plan for WPF Rig,


1. Please reciprocate and overpull stuck TP.
For 2-3/8" NUE tubing max overpull to 40 klbs, for 2-7/8" NUE tubing max overpull to
60 klbs and for 3-1/2" and 4-1/2" NUE tubing overpull to 80 klbs.
Please confirm with CE and TL Operation prior to conduct fishing job using wireline
(step 2-5) 12
2. R/U Wireline and RIH Jet Cutter. RIH FPI as necessary to determine stuck point - as
deep as possible.
If length of stuck tubing more than 1 jts then cut tubing above stuck point, pull out
tubing and TIH tubing with tubing pump set shallow then pending job.
If length of stuck tubing less than 1 jts then cut tubing and continue with next step
below
3. Continue with wash over using rotary shoe and circulate out
If loss circulation occur, please use foam for circulation
For size of rotary shoe please find in reference.
4. Redress top of fish using skirt mill.
5. Fish out remaining fish use Overshot or Spear.
For size of overshot and spear please find in reference

15
Completion & Workover – DURI09857 – 5G-0302A

Fishing Options for RT Rig,


To free the existing completion string:
--> Option #1 : Back off with Rotary Slip
--> Option #2 : Jarring Job with Surface Jar - If Doughnut Stuck
Follow SOP for Jarring Job then continue with Option#1. Back off as deep as possible,
recommended to backoff until below TBA to continue process with wash over job.
--> Option #3 : R/U Wireline and RIH Jet Cutter or Prima Cord (String Shot) - follow
SOP for Back off with wireline. RIH FPI as necessary to determine stuck point - as
deep as possible. If Stuck Point 200 ft above TBA, cut tubing at 2 spots (1st in the
middle of stucked fish, and 2nd above stuck point ).

Continue with fishing job as below,


1. Wash over using rotary shoe and circulate out (if loss use foam unit).
2. Fish out remaining fish (if thread in good condition, screw in tubing to TOF or use
die collar or tapper tap, if thread is not good RIH skirt mill and then use Overshot or
Spear).

Note,
1. If TOF is not clear please Run IB, next job will be decided based on IB result.
2. Do not conduct back off tubing for WPF Rig (if need to back off tubing, please
suspend job and move out rig)
3. Please do inspect pulled tubing string condition (every tubing, nozzles, mandrel
and cup packer). Report for any anomaly
4. Notes in the tour report if there is any anomaly such as fluid cut, sand fill, scale,
etc
5. Please discuss with Fisherman and TL Operation if any deviation.

In case Rig did not successful to pull out stuck tubing pump and have to pending
well, make sure to TIH tubing pump (instead of OE tubing) so Rig still able to
perform pressure test Xmas tree (all tree, connections, stuffing box, or sample cock
whichever applicable) to 500 psi + MASP as per stated in WSEA 10-L
Reference,
Fishing in Casing
Fishing in Liner
Fishing tool per hole size
7 ROUND TRIP WITH CASING SCRAPPER TO TBA AND LINER SCRAPPER TO PBTD

Run with 5-1/2" liner scrapper and 9-5/8" casing scrapper


TBA : 332 ft
PBTD : 614 ft
4
Do Not Rotate the String while running or scrapping the casing
If there is indication casing damage, please execute "Contingency Plan for Casing
Leaking/ Clay Problem" - Please call TL Operation and CE before conducting this plan

16
Completion & Workover – DURI09857 – 5G-0302A

9 CLEAN OUT SAND TO PBTD

RIH with mule shoe and clean out sand to PBTD.


Ensure water supply is enough during clean out

Option for clean out sand on a loss circulation condition,


1. Pump fluid into wellbore with max rigs pump rate
2. Pump using 40 smf polymer. If well is still experiencing loss circulation, increased 6
completion viscosity by 10 smf until max of 80 smf.
3. Aerated polymer
4. Use Foam whenever required if there is experience loss circulation

Reference,
Loss Circulation SOP page 11-12
10 CONDUCT PRESSURE TEST CASING

Before performing Pressure test please isolate lower zone by setting packer
(serco/DCS) or dump sand and cement cap if necessary. Pressure Test casing with
300 PSI and hold for 5 mnts.

IF test casing is OK - continue with the next original program.


IF there is any indication of casing leak, perform the following step: 8
1. Locate casing leak by adjusting packer depth setting or by using pressure washer
2. Perform injectivity test with low rate and record as a base line for Squeeze
Cementing Design
3. Prepare next step to do Squeeze Job.

Other options or detail information please discuss with TL Operation

11 RUN CEMENT BOND LOG USIT/URS FROM TBA TO SURFACE


Refer to on scheduled program : DURI0985720190523LOG14

Evaluate cement bond quality from TBA to Surface to identify cause of Bubbling.

Send CBL -USIT/URS result to PE and CE. If found bad bonding (CE will decide) 12
conduct Squeeze improve bonding. Please see improve bonding job contingency
plan. Conduct injectivity test before Improve Bonding.

17
Completion & Workover – DURI09857 – 5G-0302A

12 RIH WITH TUBING PUMP AS PER PROGRAM REQUIREMENT.

Install tubing hanger and pressure test to 650 psi or 500 psi + MASP hold 5 mnts as
per WSEA 10 H.
2
RIH with new tubing pump 2.25 inch and set pump at 583 ft

Please inform CE if get indication new sand fill in the wellbore

13 INSTALL FOSV, N/D BOP, NU X-MAS TREE 4


14 RIH PLUNGER, SUCKER ROD AND POLISH ROD. SET PLUNGER AS PER PUMP SET.

Perform pressure test Xmas tree (all tree, connections, stuffing box, or sample cock
whichever applicable) to 500 psi + MASP as per stated in WSEA 10-L.
1
Conduct test pumping 300 psi - 10 minutes to make sure pump can be normally
operated
If it is OK- Continue R/D Rig,
If leaking - Re POH Tubing Pump & check, change TP if needed
15 N/U PRODUCTION LINE. 1
16 RDMO
Ensure to do Proper Handover with PMT. 2
Note: Ensure to write down handover information in the tour report.

CONDUCT PRESSURE TEST CASING


Problem - Please call CE before conducting
Contingency Plan for Casing Leaking/ Clay

Before performing Pressure test please isolate lower zone by setting packer
(serco/DCS) or dump sand and cement cap if necessary. Pressure Test casing with
300 PSI and hold for 5 mnts.
this plan.

IF test casing is OK - continue with the next original program.


IF there is any indication of casing leak, perform the following step: 3
1. Locate casing leak by adjusting packer depth setting or by using pressure washer
2. Perform injectivity test with low rate and record as a base line for Squeeze
Cementing Design
3. Prepare next step to do Squeeze Job.

Other options or detail information please discuss with TL Operation

18
Completion & Workover – DURI09857 – 5G-0302A

ISOLATE OPEN ZONE WITH ONE OF BELOW METHOD DEPEND ON WELL


CONDITION.

1. Using packer-- Retrievable Packer + Dump 5 ft sand on top


a. RIH with Retrievable Packer
follow SOP for Running and Setting Packer complete with Setting/Releasing
Tools.
4
b. RIH with Mule Shoe and dump sand at least 20 ft above packer.
2. Dump sand above TBA and Cement cap 5 ft
a. RIH with Mole Shoe and dump sand above TBA/open interval or depend on
program.
b. Dump 5 - 10 ft Cement Cap with Class "G" Cement on top of the sand

Discuss with TL Operation if other isolation alternative need to be proposed.


PREPARE CEMENTING UNIT AND PERFORM SQUEEZE CASING LEAK JOB

Discuss with TL Operation, Completion Engineer, and or Cementing Engineer to 12


determine detail squeeze method (basic method is bullhead)

WOC
WOC as per design and monitor cement surface sample 6

DOC TO ORIGINAL TOP OF CEMENT. RETEST SQUEEZE CASING LEAK RESULT.


Pressure test casing and increase pressure gradually (per 100 psi) to get 300 psi - 5
mnts hold.
4
If still leaking, discuss with TL Operation and Completion Engineer if required
additional squeeze or other alternative will be taken.
ISOLATE OPEN ZONE WITH ONE OF BELOW METHOD DEPEND ON WELL
CONDITION:

1. Using packer-- Retrievable Packer + Dump 5 ft sand on top


Contingency Plan to Change Wellhead

a. RIH with Retrievable Packer


follow SOP for Running and Setting Packer complete with Setting/Releasing
Tools.
b. RIH with Mule Shoe and dump sand above packer.
2. Dump sand and/or Cement by Service company 8
a. RIH with Mole Shoe and dump sand above TBA/open interval or depend on
program.
b. Spot cement on top of the sand

Please make sure isolation (packer or cement) can be tested to 1000 psi for 15 min
5% decline or 30 mins 10% decline alloved as per WSEA 10D

Discuss with TL Operation if other isolation alternative need to be proposed.


CHANGE WELLHEAD INTO DOUGHNUT TYPE BY RIGLESS SURFACE TEAM
6

19
Completion & Workover – DURI09857 – 5G-0302A

POOH RETRIEVABLE PACKER :


1. Using packer-- Retrievable Packer + Dump 5 ft sand on top
a. RIH with releasing tool. clean out sand on top of the Packer and retrieve the
Packer. POOH.
2. Dump sand and Cement cap 5 ft 8
a. RIH with Rock bit, drill out cement and clean out sand.

BACK TO MAIN PROCEDURE


TOTAL TIME : P10
Assumption: No Test Casing, No Casing Leak, No Killing Problem, No Fishing Problem 104
TOTAL TIME : P50
Assumption: No Test Casing, No Casing Leak, No Killing Problem & Fishing Problem 110
TOTAL TIME : P90
Assumption: Test Casing,Casing Leak, with Fishing Problem & Killing Problem 139

20