COMPUTATION OF LABOR

(1 working day = 8 hours)

1ST FLOOR

Activity No. A
Site Clearing and Grubbing
Manual Clearing
2
Manhour Capability = 0.03 m
2
Total Area = 200 m
No. of Persons = 3
No. of Days = 0.25 day(s)
say = 1 day(s)

Activity No. B
Delivery of materials for Field Office and Construction
No. of Persons = 5
No. of Days = 5 day(s)

Activity No. C
Mobilization
No. of Persons = 3
No. of Days = 2 day(s)

Activity No. D
Delivery of materials
No. of Persons = 3
No. of Days = 3 day(s)

Activity No. E
Layout and batterboard
2
Manhour Capability = 0.02 hr/m
Total Area = 200.00 m2
No. of Persons = 3
No. of Days = 0.17 day(s)
say = 1 day(s)

Activity No. F
Fabrication of Rebars for Column, CF and WF (1st flr)
Manhour Capability = 10.00 kg/hr
Total No. of kg = 706.97 kg
No. of Persons = 3
No. of Days = 2.95 day(s)
say = 3 day(s)
Activity No. G
Excavating of column footing and wall footing
3
Manhour Capability = 1.35 m /m day
3
Total Volume = 26.64 m
No. of Persons = 4
No. of Days = 4.93 day(s)
say = 5 day(s)

Activity No. H
Fabrication of Forms, scaffolding for columns (1st flr)
2
Manhour Capability = 1.42 MH/m
Total Area = 296.19 m2
No. of Persons = 3
No. of Days = 8.67 day(s)
say = 9 day(s)

Activity No. I
Installation of rebars for column, CF and WF (1st flr)
Manhour Capability = 10.00 MH/kg
Total No. of kg = 706.97 kg
No. of Persons = 8
No. of Days = 1.10 day(s)
say = 2 day(s)

Activity No. J
Fabrication of Forms, scaffolding and staging for stairway
2
Manhour Capability = 1.42 m /hr
Total Area = 102.84 m2
No. of Persons = 3
No. of Days = 3.02 day(s)
say = 4 day(s)

Activity No. K
Soil poisoning and excavating of septic tank and catch basin
Soil poisoning
No. of Persons = 3
No. of Days = 2.00 day(s)
Excavation
3
Manhour Capability = 1.35 m /m day
3
Total Volume = 51.99 m
No. of Persons = 6
No. of Days = 6.42 day(s)
say = 7 day(s)
say = 9 day(s)
Activity No. L
Concreting of CF and WF
3
Equipment Capability (1 bagger conc. Mixer) = 6.80 m /day
3
Pouring = 5.00 m /hr
3
Total Volume = 49.10 m
No. of Persons = 14
No. of Days = 9.41 day(s)
say = 10 day(s)

Activity No. M
Concreting of footing of septic tank
3
Equipment Capability (1 bagger conc. Mixer) = 6.80 m /day
3
Pouring = 5.00 m /hr
3
Total Volume = 1.08 m
No. of Persons = 4
No. of Days = 0.18 day(s)
say = 1 day(s)

Activity No. N
Fabrication of rebars for stairway
Manhour Capability = 10.00 kg/hr
Total No. of kg = 33.19 kg
No. of Persons = 3
No. of Days = 0.14 day(s)
say = 1 day(s)

Activity No. O
Dummy
No. of Days = 0 day(s)

Activity No. P
Installation of Forms, scaffolding for columns (1st flr)
2
Manhour Capability = 0.85 m /hr
2
Total Area = 250.29 m
No. of Persons = 6
No. of Days = 8.86 day(s)
say = 9 day(s)

Activity No. Q
Dummy
No. of Days = 0 day(s)
Activity No. R
Laying of CHB for wall (1st flr)
2
Manhour Capability = 1.25 m /hr
2
Total Area = 444.09 m
No. of Persons = 10
No. of Days = 8.88 day(s)
say = 9 day(s)

Activity No. S
Concreting of column (1st flr)
3
Equipment Capability (1 bagger conc. Mixer) = 6.80 m /day
3
Pouring = 5.00 m /hr
3
Total Volume = 22.46 m
No. of Persons = 8
No. of Days = 3.37 day(s)
say = 4 day(s)

Activity No. T
Fabrication of rebars for slab (1st flr)
Manhour Capability = 10.00 kg/hr
Total No. of kg = 1203.28 kg
No. of Persons = 4
No. of Days = 3.76 day(s)
say = 4 day(s)

Activity No. U
Laying of CHB for septic tank and catch basin
2
Manhour Capability = 1.25 m /hr
2
Total Area = 27.00 m
No. of Persons = 3
No. of Days = 1.80 day(s)
say = 2 day(s)

Activity No. V
Dummy
No. of Days = 0 day(s)

Activity No. W
Stripping of forms & scaffolding of columns (1st flr)
2
Manhour Capability = 2.35 m /hr
Total Area = 250.29 m2
No. of Persons = 6
No. of Days = 4.44 day(s)
say = 5 day(s)
Activity No. X
Dummy
No. of Days = 0.00 day(s)
say = 0 day(s)

Activity No. Y
Earthfilling for slab
3
Manhour Capability = 1.22 m /m day
3
Total Volume = 146.12 m
No. of Persons = 4
No. of Days = 7.49 day(s)
say = 8 day(s)

Activity No. Z
Installation of rebars for slab (1st flr)
Manhour Capability = 10.00 kg/hr
Total No. of kg = 2431.32 kg
No. of Persons = 8
No. of Days = 7.60 day(s)
say = 8 day(s)

Activity No. A'


Installing of electrical conduits (1st flr)
2
Manhour Capability = 1.33 hr/m
2
Total Area = 131.25 m
No. of Persons = 6
No. of Days = 3.64 day(s)
say = 4 day(s)

Activity No. B'


Spreading, tamping and grading
3
Manhour Capability = 2.09 m /hr
3
Total Volume = 146.12 m
No. of Persons = 3
No. of Days = 2.91 day(s)
say = 3 day(s)
Activity No. C'
Roughing in plumbing and water pipe connections (1st flr)
Manhour Capability
Pipes = 1 hr/pc 81.00 pcs
Clean-outs = 2 hr/pc 15.00 pcs
No. of Persons = 6
No. of Days = 2.31 day(s)
say = 3 day(s)

Activity No. D'


Fabrication of forms, scaffolding for beams (1st flr)
2
Manhour Capability = 1.42 m /hr
2
Total Area = 15.94 m
No. of Persons = 4
No. of Days = 0.71 day(s)
say = 1 day(s)

Activity No. E'


Installation of rebars for beam (1st flr)
Manhour Capability = 10.00 kg/hr
Total No. of kg = 358.95 kg
No. of Persons = 8
No. of Days = 1.12 day(s)
say = 2 day(s)

Activity No. F'


Concreting of slab (1st flr)
3
Equipment Capability (1 bagger conc. Mixer) = 6.80 m /day
3
Pouring = 5.00 m /hr
2
Total Volume = 131.25 m
No. of Persons = 15
No. of Days = 0.38 day(s)
say = 1 day(s)

Activity No. G'


Installation of forms, scaffolding for beams (1st flr)
2
Manhour Capability = 0.65 m /hr
2
Total Area = 15.94 m
No. of Persons = 8
No. of Days = 0.77 day(s)
say = 1 day(s)
Activity No. H'
Fabrication of forms, scaffolding & staging for slab(2nd flr)
2
Manhour Capability = 1.42 m /hr
2
Total Area = 56.63 m
No. of Persons = 4
No. of Days = 2.51 day(s)
say = 3 day(s)

Activity No. I'


Installation of rebars for beam (1st flr)
Manhour Capability = 10.00 kg/hr
Total No. of kg = 358.95 kg
No. of Persons = 6
No. of Days = 1.50 day(s)
say = 2 day(s)

Activity No. J'


Fabrication of rebar for slab (2nd flr)
Manhour Capability = 10.00 kg/hr
Total No. of kg = 221.16 kg
No. of Persons = 3
No. of Days = 0.92 day(s)
say = 1 day(s)

Activity No. K'


Dummy
No. of Days = 0 day(s)

Activity No. L'


Installation of forms, scaffolding & staging for stairway
2
Manhour Capability = 0.65 m /hr
2
Total Area = 10.00 m
No. of Persons = 5
No. of Days = 0.77 day(s)
say = 1 day(s)

Activity No. M'


Concreting of beam (1st flr)
3
Equipment Capability (1 bagger conc. Mixer) = 6.80 m /day
3
Pouring = 5.00 hr/m
3
Total Volume = 3.21 m
No. of Persons = 4
No. of Days = 0.97 day(s)
say = 1 day(s)
Activity No. N'
Installation of forms, scaffolding & staging for slab (2nd flr)
2
Manhour Capability = 0.65 m /hr
2
Total Area = 56.63 m
No. of Persons = 4
No. of Days = 5.44 day(s)
say = 6 day(s)

Activity No. O'


Installing of electrical wirings (2nd flr)
2
Manhour Capability = 1.33 m /hr
2
THHN conduit = 56.625 m
No. of Persons = 4
No. of Days = 2.35 day(s)
say = 3 day(s)

Activity No. P'


Installation of rebars for slab(2nd flr)
Manhour Capability = 10.00 kg/hr
Total No. of kg = 221.16 kg
No. of Persons = 4
No. of Days = 1.38 day(s)
say = 2 day(s)

Activity No. Q'


Roughing in plumbing and water pipe connections (2nd flr)
Manhour Capability
Pipes = 1 hr/pc 40 pcs
Clean-outs = 2 hr/pc 15 pcs
No. of Persons = 4
No. of Days = 2.19 day(s)
say = 3 day(s)

Activity No. R'


Stripping of forms & scaffolding of beams (1st flr)
2
Manhour Capability = 1.95 m /hr
2
Total Area = 15.94 m
No. of Persons = 3
No. of Days = 2.59 day(s)
say = 3 day(s)
Activity No. S'
Installation of rebars for stairway
Manhour Capability = 10.00 kg/hr
Total No. of kg = 33.19 kg
No. of Persons = 10
No. of Days = 8.30 day(s)
say = 9 day(s)

Activity No. T'


Concreting of slab and beams (2nd flr)
3
Equipment Capability (1 bagger conc. Mixer) = 6.80 m /day
3
Pouring = 5.00 hr/m
2
Total Volume = 51.00 m
No. of Persons = 10
No. of Days = 0.22 day(s)
say = 1 day(s)

Activity No. U'


Concreting of stairway
3
Manhour Capability = 0.91 m /m day
3
Total Volume = 1.55 m
No. of Persons = 2
No. of Days = 0.85 day(s)
say = 1 day(s)

Activity No. V'


Laying of CHB for Wall (2nd flr)
2
Manhour Capability = 1.25 m /hr
2
Total Area = 344.12 m
No. of Persons = 5
No. of Days = 13.76 day(s)
say = 14 day(s)

Activity No. W'


Stripping of forms & scaffolding of stairway
2
Manhour Capability = 1.95 m /hr
2
Total Area = 102.84 m
No. of Persons = 4
No. of Days = 3.30 day(s)
say = 4 day(s)
Activity No. X'
Plastering of CHB Walls (1st flr)
2
Manhour Capability = 1.67 hr/m
2
Total Area = 888.17 m
No. of Persons = 5
No. of Days = 13.30 day(s)
say = 14 day(s)

Activity No. Y'


Fabrication of forms, scaffolding for columns (2nd flr)
2
Manhour Capability = 1.42 MH/m
2
Total Area = 116.48 m
No. of Persons = 3
No. of Days = 6.91 day(s)
say = 7 day(s)

Activity No. Z'


Stripping of Forms, scaffolding & staging for slab (2nd flr)
2
Manhour Capability = 1.86 m /hr
2
Total Area = 56.63 m
No. of Persons = 6
No. of Days = 1.27 day(s)
say = 2 day(s)

Activity No. A''


Fabrication of rebars for column (2nd flr)
Manhour Capability = 10.00 MH/kg
Total No. of kg = 1550.62 kg
No. of Persons = 6
No. of Days = 3.23 day(s)
say = 4 day(s)

Activity No. B''


Installation of forms, scaffolding for columns (2nd flr)
2
Manhour Capability = 0.85 m /hr
2
Total Area = 116.48 m
No. of Persons = 6
No. of Days = 5.71 day(s)
say = 6 day(s)

Activity No. C''


Dummy
No. of Days = 0 day(s)
Activity No. D''
Installation of rebars for column (2nd flr)
Manhour Capability = 10.00 kg/hr
Total No. of kg = 1550.62 kg
No. of Persons = 4
No. of Days = 4.85 day(s)
say = 5 day(s)

Activity No. E''


Dummy
No. of Days = 0.00 day(s)
say = 0 day(s)

Activity No. F''


Fabrication of Forms, scaffolding and staging for beams and slab (roof)
2
Manhour Capability = 1.42 m /hr
2
Total Area = 56.63 m
No. of Persons = 4
No. of Days = 2.51 day(s)
say = 3 day(s)

Activity No. G''


Fabrication of rebars for slab and beam (roof deck)
Manhour Capability = 10.00 kg/hr
Total No. of kg = 2542.15 kg
No. of Persons = 3
No. of Days = 10.59 day(s)
say = 11 day(s)

Activity No. H''


Concreting of Column (2nd flr)
3
Equipment Capability (1 bagger conc. Mixer) = 6.80 m /day
3
Pouring = 5.00 hr/m
3
Total Volume = 10.29 m
No. of Persons = 10
No. of Days = 2.16 day(s)
say = 3 day(s)

Activity No. I''


Installation of forms, scaffolding and staging for beams and slab (roof)
2
Manhour Capability = 0.65 m /hr
2
Total Area = 56.63 m
No. of Persons = 4
No. of Days = 5.44 day(s)
say = 6 day(s)
Activity No. J''
Roughing in plumbing and water pipe connections (roof)
Manhour Capability
Pipes = 1 hr/pc 76 pcs
Clean-outs = 2 hr/pc 9 pcs
No. of Persons = 3
No. of Days = 3.92 day(s)
say = 4 day(s)

Activity No. K''


Installation of rebars for slab and beam (roof deck)
Manhour Capability = 10.00 kg/hr
Total No. of kg = 2542.15 kg
No. of Persons = 5
No. of Days = 12.71 day(s)
say = 13 day(s)

Activity No. L''


Installing of electrical works
Manhour Capability
THHN conduit 0.267 hr/m
No. of Persons = 3
No. of Days = 5.35 day(s)
say = 6 day(s)

Activity No. M''


Stripping of forms & scaffolding of columns (2nd flr)
2
Manhour Capability = 2.35 m /hr
2
Total Area = 116.48 m
No. of Persons = 5
No. of Days = 2.48 day(s)
say = 3 day(s)

Activity No. N''


Concreting of beam (roof deck)
3
Equipment Capability (1 bagger conc. Mixer) = 6.80 m /day
3
Pouring = 5.00 hr/m
3
Total Volume = 12.54 m
No. of Persons = 10
No. of Days = 1.88 day(s)
say = 2 day(s)
Activity No. O''
Concreting of slab (roof deck)
3
Equipment Capability (1 bagger conc. Mixer) = 6.80 m /day
3
Pouring = 5.00 hr/m
2
Total Volume = 161.50 m
No. of Persons = 16
No. of Days = 0.44 day(s)
say = 1 day(s)

Activity No. P''


Installation of down spout
Manhour Capability
Pipes = 1 hr/pc
No. of Persons = 3
No. of Days = 1.21 day(s)
say = 2 day(s)

Activity No. Q''


Installation of fabricated door jamp
Manhour Capability = 40.00 bd.ft./day
Total Area = 80.00 bd.ft.
No. of Persons = 2
No. of Days = 1.00 day(s)
say = 1 day(s)

Activity No. R''


Dummy
No. of Days = 0 day(s)

Activity No. S''


Plastering of CHB Walls (2nd flr)
2
Manhour Capability = 1.67 hr/m
2
Total Area = 688.24 m
No. of Persons = 4
No. of Days = 12.88 day(s)
say = 13 day(s)

Activity No. T''


Dummy
No. of Days = 0 day(s)
Activity No. U''
Installation of fabricated doors & windows
Manhour Capability
Doors = 2 sets/day 19 sets
windows = 1.00 set/hr 23 sets
No. of Persons = 3
No. of Days = 4.13 day(s)
say = 5 day(s)

Activity No. V''


Stripping of forms, scaffolding and staging for beams and slab
2
Manhour Capability = 1.86 m /hr
2
Total Area = 56.63 m
No. of Persons = 8
No. of Days = 0.95 day(s)
say = 1 day(s)

Activity No. W''


Installation of ceiling frame and ceiling board
2
Manhour Capability = 1.00 hr/m
2
Total Area = 161.50 m
No. of Persons = 3
No. of Days = 6.73 day(s)
say = 7 day(s)

Activity No. X''


Installation of railings
Manhour Capability = 0.5 hr/m
No. of Persons = 3
No. of Days = 1.67 day(s)
say = 2 day(s)

Activity No. Y''


Installation of electrical fixtures
Manhour Capability
Lighting Fixtures = 1.25 hr/set 98 sets
Convenience Outlet = 1.25 hr/set 39 sets
Panel Board = 1.15 hr/set 1 sets
Utility Box = 0.19 hr/set 57 sets
Switches = 1.25 hr/set 18 sets
No. of Persons = 3
No. of Days = 17.70 day(s)
say = 18 day(s)
Activity No. Z''
Painting Works
2
Manhour Capability = 0.43 hr/m
2
Total Area = 1576.41 m
No. of Persons = 6
No. of Days = 14.12 day(s)
say = 15 day(s)

Activity No. A'''


Installation of tile works
Manhour Capability = 25.00 pcs/day
Total Area = 1340.00 pcs
No. of Persons = 3
No. of Days = 2.23 day(s)
say = 3 day(s)

Activity No. B'''


Dummy
No. of Days = 0 day(s)

Activity No. C'''


Installation of Plumbing fixtures
Manhour Capability
Lavatory = 8 hr/set 2 sets
Water closet = 8 hr/set 2 sets
Kitchen sink = 14 hr/set 0 sets
Kitchen faucet = 2 hr/set 0 sets
Gate valve = 8 hr/set 2 sets
Faucet = 2 hr/set 5 sets
Floor drain = 2 hr/set 4 sets
No. of Persons = 3
No. of Days = 2.75 day(s)
say = 3 day(s)

Activity No. D'''


Clearing of Site For Final Inspection & Transfers to the Owner
2
Manhour Capability = 0.30 hr/m
2
Total Area = 131.25 m
No. of Persons = 5
No. of Days = 10.94 day(s)
say = 11 day(s)