Professional Documents
Culture Documents
aaac32c291cb346be27f496586018bd7
aaac32c291cb346be27f496586018bd7
aaac32c291cb346be27f496586018bd7
NEWS
Summer 2007
Overview
Dear Business colleagues,
It's my pleasure to introduce to you the 6th edition of
Fagioli Group Newsletter.
z Transport for the Nuclear Industry Also, in this issue we will take a deep look into Middle East activities
(Yanbu) with a 1,300 tonne column transport; an interesting substitution of
z Heavy Transport for the Shipyard 4 huge crane dischargers; load in and load out operations of modules for
Industries the off-shore industry; rail and sea transportation with group-owned
equipment, project logistics performances..…in few words a "juicy"
z Project Logistics summer EDITION !!!
z Fagioli Engineering Take a look inside and …. enjoy this 16-page edition!!!
z Breakbulk Conference, Antwerp
Rudy Corbetta,
z All Change for PSC Marketing & Publicity
Heavy Lifting and Transportation
2
Heavy Lifting and Transportation
TANKS
Fagioli team unloaded 6 Tanks sections
Above photo: Tank transport inside GBS weighing up to 1,600 tons each, from
marine vessel moored at site new quay.
PROJECT NUMBERS EQUIPMENT Then, Fagioli successfully performed
Total Tonnage to be moved: z Up to 200 SPMT axle lines the site transport from quay area to the
abt.16,000 tonne z 2 X 750 ton crawler crane intermediate storage area and
Heaviest Module: ORV - 4,400 ton subsequent transport from storage area
z Auxiliary cranes
inside GBS.
Biggest Module: ORV 75 x 31.5 x 28.4m z Beam and skid tracks for skidding
Engineering hours (Phase 1): operation for an overall capacity up to Installation of 60 Strand Jacks and
planned more than 14,000 7,200 tonne assembling structures onto GBS roof;
Operational hours (Phase 2): z Tower Lifting/ Strand Jacks for Lifting Installation of n. 6 Tanks sections by
planned more than 53,000 Operation / Steel plates for unloading means of 60 Strand Jacks;
Duration: operations of the Modules from
Phase 1: Jan - Oct 2006 Barges / PPU’S / Semi-Trailers / Lifting with Strand Jacks from SPMT
Phase 2: Oct 2006 - Dec 2007 Floating Platform / Fork-Lifts. and removal of SPMT’s.
3
Heavy Lifting and Transportation
The lift required four L100 jacks Fagioli recently performed a challenging transport in Saudi Arabia (Yanbu) for the
& one L12/8E power pack, the Yansab plant. Two 98m long splitters weighing 1,300 tonne and approximately 10m
installation required two L15 diameter.
jacks & a Hillman roller. Fagioli performed the transport of the two vessels using 72 axle lines of SPMTs (2x36).
The vessel was unloaded onto SPMTs in Yanbu and than positioned onto temporary
After lifting the Gas Turbine into
stools. The second vessel was performed in the same way.
the steel structure, the whole
thing was then manouvered by After a long trip of 14km from jetty to site the vessels were positioned onto stools. The
gantry to its foundation. Fagioli team also carried out the transportation of all the accessory parts. This is a
typical job performed in the Middle East area, with group-owned equipment.
4
Heavy Lifting and Transportation
Fagioli PSC Korea carried out the lift and installation of Chimney
Steel Can sections weighing a total of 322Ton for Young Hung #4 in
Korea. The lift required four L100 jacks & one L4/14E power pack.
The transport was successfully performed with a 2 x Transport to Vasto San Salvo
7 axles of modular trailers with turntables. One of the
most challenging points was an underpass in
Saronno (north west of Milan). 5.2m meters of
available height with a convoy that reached 5.35m.
The flexibility of the modular trailers allowed the
whole convoy to be lowered 15cm necessary to pass
without scratching or touching the concrete. The
column will be loaded and transported by means of
group-owned barge to Venice.
Fagioli performed the transport of a 210 tonne transformer from
Legnano to Chieti with final destination Termoli. Fagioli loaded the
heavy item and supports specially made for rail transport onto a 22
axles road convoy (11 + 11) and transported to Busto Arsizio.
5
Heavy Lifting and Transportation
Quayside Crane
Loadout at Marina Di Ravenna Port
Ravenna port , Italy.
On week 24 Fagioli
transported a 646 tonne
deck module onto a barge
by means of 2 x 18 SPMT
axles. After this operation
a peculiar jacket (1,172
tonne) was "escorted" on
the same barge by 42
SPMT axle lines using 3
lines of 14 axles as the
module was a huge
January 2007, Fagioli successfully performed the "tripod".
load-out, sea transport and final load-in operations of On week 25 Fagioli
a new quayside crane (700ton) from Vado Ligure performed the heaviest
(SV) to Genoa. load out, a 3,112 tonne
Fagioli provided all heavy transport equipment, living quarter by means of
Fagioli recently performed the load 136 axles lines and 4
operation engineering as well as the supply of sea-
out of 3 gigantic modules for the power packs.
fastening and grillage devices.
Offshore activities at Marina di
6
Heavy Lifting and Transportation
7
Heavy Lifting and Transportation
The delivery of the heavy plant, via barges which received the
heavy plant from the ocean-going ship, is hindered by the low
height / clearance of some bridges enroute to the off-loading
jetty near Ratchaburi job-site. It become necessary to transfer
the heavy plant directly onto the deck of the barge, gaining more
than a metre in height tolerance in comparison with having the
plant being supported on steel stools. Upon arrival at the off-
loading jetty, the plant was lifted to enable the transportation
trailer to take them away.
The M/V then sailed to Brindisi to load a dismantled crane which consisted
of a crawler and tower section, weighing 217 tonne, a jib (in 2 sections), 3
counterweights, 7 ancillary parts.
The total journey started in Marghera, then went onto Brindisi, Al Jubail and
final destination. Fagioli’s shipping department has been very active in the
Mediterranean, Gulf area and Indian Ocean this year.
8
Heavy Lifting and Transportation
9
Heavy Lifting and Transportation
10
Transport For The Nuclear Industry
Transport of Four 350 Tonne Steam Generators from France to New Jersey
It looks as if summer 2007 will be a very challenging and "hot" The different types of transport used during the project were:
season for the Fagioli Nuclear Department, with the transport
z Barges for internal navigation in France
of 4 Steam Generators from France to Salem (see below) and
z Heavy Lift Ship to USA
the transport of 2 RGS's from France to USA (see article
above). Fagioli are also preparing for the execution of z Barge in USA
generators to be transported from Mexico to Arizona which will z Land transporters to the temporary storage facility inside
be documented in the next issue!! the Plant
11
Heavy Transportation for the Shipyard Industry
12
Project Logistics
In the last issue of the News letter we mentioned that Fagioli is the only Project Logistics company with a full range of group
owned equipment (ships, barges, SPMTs, strand jacks, tower lift etc….) for heavy transport and lifting activities. Fagioli also
own equipment dedicated to Freight Forwarding projects such as containers, normal trucks and trailers, small and medium
range cranes as well as storage facilities at main ports. With a complete range of equipment Fagioli are able to cover every
possible kind of transport, lifting and logistical requirement with a high level of professionalism!!
During the construction of a plant, whether you are transporting by normal trailers, air transportation, ocean going vessels, carrying
out container deliveries or large reactors, every single activity involving the movement of any single item has its relevant importance!!
Fagioli know that the delay of an item, no matter what size could stop the entire plant development!! And this is the key we use
for supplying old Customers and acquiring new names competing with an
indefinite number of Competitors formed by the small Freight forwarder just
situated next door to the Customer as well as the international world wide Group
established everywhere on the territory. Most of them are dedicated to specific
trades and commodities while certain well known Companies handle huge
volumes of cargoes and attack the market from a strong position.
It doesn't make any difference if we are handling spare parts for automotive
production, components for the aerospace industry (which involves a complete
range of worldwide road, air, sea services) projects to/from the Maghreb area
using our ro/ro service or humanitarian / military cargo where we delivery
international aid to critical areas. "No difference, same target: safe and Above: A road and air transport of a
professional performances, timing and competitive rates". Satellite from Rome to USA
13
Fagioli Engineering - The New Concept
14
Fagioli Engineering - The New Concept
The input data furnished by the Client (also during Bid phase) Recently, for the ADRIATIC LNG project in Spain, Fagioli
can be crucial for the awarding of the project and for the safe specially built 4 box girders comprising of modular
execution of it. Just to give a recent example, a customer components hinged and jointed together. Each of the box
asked us to study the assembly of a huge unit, consisting of girders is 40m long and can be hoisted up to 1,500 tonne.
5 different pieces weighing 500 tons each, to be pre- These box girders will be the main structure of the lifting
fabricated, to be separately transported and at the end, system that will be used to position large modules on top of
joined together on its foundations. Fagioli, after a careful and the GBS concrete structure.
detailed analysis of the project, suggested to build the
In-house engineering means also risk reduction. To achieve
complete unit in one piece (on a base frame designed by
this Fagioli uses the most sophisticated computer programs
Fagioli) in order to directly transport and install the whole
to perform accurate engineering studies in order to complete
piece by means of SPMTs. This technical solution avoided
safe transport and lifting thanks to the latest generation of
the problem of having other special equipment on site (e.g.
technical drawing software and 3d movie simulation
cranes, towers etc…) and the hook-up operations between
technology used to calculate all possible risks and replicate
the modules. This plan turned a win win situation for both the
the movement of the whole transport and lifting operation.
client and Fagioli. The structure in question was a Cold Box
weighing 2,600 tons, and a height of 60m. During the execution stage, the Engineering Department
supports the Operations Division, by issuing all the
During the bid stage, Fagioli Engineering Department
necessary documents for the preparation and the execution
supports the Commercial department to identify the most
of the job on site:
suitable means of equipment for the execution of the jobs,
issues method Statements and drawings, analyses the
z Equipment list
technical specifications of the Client and the technical
aspects of the offer/tender. Moreover, the Engineering z Transport and lifting drawings showing details of the all
Department prepares the technical specifications for the the equipment for the operation.
procurement and the construction of the equipment, z Calculations statement (stability, structural, ballasting…)
providing the fabrication and control plans. For instance, our
z Operational procedures explaining the safest way to
team supervised all the operations for the fabrication of two
execute the jobs; organisation charts; check list for the
80m high Towerlift System (with capacity up to 1.000 tonne
preparation and control of the equipment; step by step
each), checking the materials used for the fabrication and the
description of the operations; operational methods
welding, tolerances, painting, laboratory tests and final third
(tolerances, maximum speed, wind speed limitations,
party certification.
maximum reactions…) for safe execution.
15
Other News
Breakbulk Conference in Antwerp All Change for PSC - New Name, New Offices
In April 2007 it was decided to drop the PSC from Fagioli PSC
Limited and become Fagioli Limited, as such a new company
logo has been produced to coincide with our Group Company
Fagioli SpA.
Between the 22nd and the 24th of May the 2nd edition of
the European Breakbulk conference took place in
Antwerp with some of the most relevant ship-owners of
the global market. The trade fair has clearly grown-up in
terms of exhibitors, meetings and attendees.
www.fagioligroup.com www.fagioli-lifting.com