Professional Documents
Culture Documents
A Novel Technique For Congestion Management in Transmission System by Real Power Flow Control
A Novel Technique For Congestion Management in Transmission System by Real Power Flow Control
Abstract— As the demand on power system increases the smooth line reactance control with much quicker response
transmission system is forced to operate beyond its transfer compared to other control devices [5-6].
capability resulting in congestion. It may cause cascaded outages, Optimal Placement of FACTS device plays a significant role
voltage instability etc which in turn affect the system security and in congestion management which is based on dynamic-static
reliability. So congestion management becomes crucial for the performance of the today’s power system. In [7] and [8]
efficient power transfer in the power system. This paper deals
genetic algorithm and differential algorithm based
with a method for congestion management by real power flow
control using TCSC.The power injection required to relieve optimization method is used for optimal position identification
congestion is calculated based on DC power flow equations. of the TCSC. Sensitivity based methods are generally adopted
Optimal location of TCSC is obtained by sensitivity based for the identification of optimal position of FACT devices
approach. A control algorithm is developed for congestion which in turn enhance the operation of the power system. In
management by real power flow control using reactance [9] and [10] real power flow sensitivity index and total system
compensation and is tested on a 5 bus system. reactive power loss sensitivity index is used for the
identification of optimal position for TCPAR. In [11] single
contingency criterion based approach has been used for the
Keywords—Congestionmanagement;TCSC;Optimal placement;DC
static security enhancement of the transmission system.
power flow equations.
Congestion management in a deregulated electricity market by
optimizing FACTS device location using sensitivity factor
I. INTRODUCTION method has been proposed in [12].
The transmission lines in power system are forced to operate So far attempt has not been made by the researchers to remove
near to its limit due to the day to day increase in power congestion using sensitivity matrix .This paper deals with
demand resulting in congestion. The transmission line congestion management using reactance compensation. The
congestion leads to cascade outages, voltage instability etc amount of reactance compensation for removing congestion is
which will adversely affect the power system security and calculated using sensitivity matrix. The power injection
reliability. Available transfer capability needs to be utilized in equivalent of this reactance compensation is calculated using
a better way so that congestion doesn’t occur in any of the DC power flow equations. Reactance compensation is
transmission line. So congestion management plays an implemented using TCSC. Optimal location for TCSC has
important role for the safe and reliable operation of today’s been found based on sensitivity analysis. A real power flow
transmission system. The different techniques used for control algorithm using reactance compensation has been
congestion management include cost-free techniques and non developed for congestion management.
cost-free techniques. Changing the network structure, use of Section 2 describes the method of congestion management by
transformer and series FACT devices are the cost-free reactance compensation. Section 3 illustrates the algorithm
methods adopted for congestion management. The Non cost- developed for congestion management. Section 4 details the
free techniques adopted for congestion management are implementation of proposed algorithm in the 5 bus system and
generation rescheduling, load curtailment options[1].Among the section 5 details the conclusion.
these methods FACT devices has an added advantage of
improving the loadability of the transmission line by series II. CONGESTION MANAGEMENT BY REAL POWER FLOW
compensation[2-4].Usage of FACT device such as Thyristor- CONTROL
controlled series capacitor (TCSC) helps to attain flexible and The real power flow control plays a significant role in
relieving congestion in order to ensure reliable and secure d
power supply .Power flow between two buses shown in fig .1 B.INJECTION MODEL FOR TCSC
of a lossless transmission line is given by equation (1)[11]. Fig 3 shows a transmission line model with TCSC attached
between i and bus j .The TCSC is depicted as a static
reactance during steady state which is represented as –jxc.So
the effective impedance of the line becomes
Zij1 rij j ( xij xc )
i j sin G ij
VV
Pij (1)
Fig.3.Transmission line model with TCSC
X net
Pij represents real power flow between bus i and bus j The net admittance of the branch with TCSC is calculated as:
respectively, Vi∟δi represent the complex voltage at bus i and 1
Yij1 Gij1 jBij1 (5)
Vj∟δj represents the complex voltage at bus j, Xnet represents Zij1
net effective line reactance offered by line 1 and 2 and δij
represents the bus angle difference. From (1) it is clear that rij xij xc
Where, Gij1 , Bij1
the power flow in a line can be managed by changing bus
rij 2 xij xc rij 2 xij xc
2 2
'Gij Gij Gij1 (10) maximum limit by TCSC and Plm (max) represents the
maximum power flow limit of the congested line.
'Bij Bij Bij1 (11)
E.COMPUTATION OF REACTANCE COMPENSATION
The power injection due to TCSC calculated in the section C
C.OPTIMAL PLACEMENT OF TCSC is converted into equivalent reactance(xc) using equations (7)
The optimal position for TCSC placement is found out by real and (8).For a lossless transmission line r ij=0, substituting the
power flow reduction method [10].This method is based on value of rij in equations (10) and (11)
real power flow sensitivity with respect to the xc. uij represents
real power flow sensitivity with respect to xc .The uij is 'Gij 0 (16)
computed using equation (12). xc
'Bij (17)
( x xij xc )
2
ij
The entries of the branch node incidence matrix (A) will be 1 , These power flow values are then compared with the
-1 and 0 depending upon the power flow direction. If the maximum loading limit of each line given in table 1 and it was
direction of the power flow in a branch is towards the node found that the line 1(Pl1)power flow is exceeding its maximum
the entry will be -1, if it is away from the node the entry will loading limit indicating congestion in the line 1.This
be 1 and if the branch is not connected to the node the entry congestion in line 1 is relived by optimal placement of TCSC
will be 0.The A matrix for 5 bus system sis given by The location for TCSC is found out by calculating uij value
equation(22). each line using equation(12). The uij values for 5 bus system
ª1 1 0 0 0 º are as given below:
«0 »
« 1 1 0 0 » ªu12 º ª -.94 º
«0 0 0 1 1 » (22) «u » «-.166 »
« »
A «0 0 1 1 0 » « 23 » « »
«1 0 0 0 1 » «u54 » «-.1419» (26)
« » «u »
«0 1 0 0 1 » «-.008 »
«0 0 1 0 1 » « 34 » «-.220 »
¬ ¼
«u15 » « »
The B1 matrix is a diagonal matrix composing of line
«u » «-.146 »
admittances. The B1 matrix for 5 bus system is given by
« 52 » «¬-.174 »¼
equation (23) «¬u53 »¼
ªY12 0 0 0 0 0 0 º
« » From equation (26) line 1 has the highest negative uij value so
«0 Y23 0 0 0 0 0 » TCSC has to be placed in line 1[10].
«0 0 Y 0 0 0 0 » The power injections due to TCSC are calculated using
« 54 »
B1 «0 0 0 Y34 0 0 0 » equation (27) which are as follows:
«0 0 0 0 Y 0 0 » ª100 º
« 15 » ª.5136 .2911 .1538 .0941 .0254 º
«0 0 0 0 0 Y52 0 » (23) «Pl 2 » «.2326 .3013 .3691 .2257 .0609 » ª125.9 P1s º
« » «Pl 3 » «.1017 .0778 .0368 .3041 .1614 » «105 P1s »
«¬0 0 0 0 0 0 Y53 »¼ «Pl 4 » «.0983 .1222 .2368 .4959 .0386 » u «35 » (27)
ª10 0 0 0 0 0 0 º «Pl 5 » «.2864 .0911 .0462 .1059 .2254
» «16 »
« 0 5 0 0 0 0 0 » «P » «.0810 .2076 .0153 .0683 .2355 «
» ¬ 24 »¼
« »
« 0 0 2 0 0 0 0 » «Pl 6 » ¬.0657 .0209 .1941 .0702 .1777 ¼
« 0 0 0 4 0 0 0 »
¬ l7 ¼
« 0 0 0 0 4 0 0 »
« » Where P1s and –P1s represents the power injection due to
« 0 0 0 0 0 4 0 »
TCSC at buses 1 and 2 respectively. By solving equation (27)
«¬ 0 0 0 0 0 0 2.5»
¼ P1s is equal to -2.83.Equivalent reactance (xc) is calculated
The Smn matrix for 5 bus system is calculated using equation from power injection using equations (17) and (18). The
(14) ,i.e by multiplying equation(22),equation(23) and inverse equivalent reactance is .011pu.With this equivalent reactance
of equation (21). line data is updated and Smn new matrix is calculated .
ª.5136 .2911 .1538 .0941 .0254 º ª.5009 .2839 .1500 .0917 .0248 º
«.2326 .3013 .3691 .2257 .0609 » «.2281 .3038
« » .3677 .2249 .0607 »
«.1017 .0778 .0368 .3041 .1614 » « »
(24) «.1033 .0769 .0373 .3044 .1615 »
S mn «.0983 .1222 .2368 .4959 .0386 »
«.2864 .0911 .0462 .1059 .2254 » S
mn ( new)
«.0963 .1231 .2373 .4956 .0385 » (28)
« » «.2991 .0839 .0500 .1083 .2248 »
«.0810 .2076 .0153 .0683 .2355 » « »
«¬.0657 .0209 .1941 .0702 .1777 ¼» «.0727 .2123 .0178 .0668 .2359 »
DC load flow analysis is performed with this S mn matrix and «¬.0686 .0192 .1950 .0707 .1778 »¼
the flow of power through each line (Plm) is found to be as Updated sensitivity matrix is then used for performing DC
given below: load flow analysis. The power flow through each branch is
ª Pl1 º ª 102.7256º represented by equation (29)
«P » « » ª Pl1 º ª100.00 º
« l 2 » « 15.6414» «P » «14.7470 »
« Pl 3 » « 14.6630» . « l2 » « »
« P » « 0.1170 » (25) « Pl 3 » «14.9741 »
«P » «0.1941 »
« l4 » « » « l4 » (29)
« Pl 5 » « 24.3944» «26.9377 »
« Pl 5 » « »
« P » « 16.6958» «P » «18.3447 »
« l6 » « « l6 » «¬18.8389 »¼
»
«¬ Pl 7 »¼ ¬ 18.2556¼ «¬ Pl 7 »¼
From this power flow values it is found that the power flow is [12] Naresh Acharya and N. Mithulananthan, “Locating series FACTS
reduced to 100MW in line 1. Thus the congestion in the line 1 devices for congestion management in deregulated electricity markets,”
Electric power Systems Research, vol.77, pp. 352-360, March 2007
has been relieved.
[13] Xi-Fan Wang ,Yonghua Song , Malcolm Irving, “Modern power system
analysis”volume:1,issue:2
V. CONCLUSION
[14] S. Balamurugan, N. Janarthanan and K. R. M. V. Chandrakala,
"Laboratory model to teach Surge Impedance Loading," 2016 Biennial
This paper presents a real power flow control method for International Conference on Power and Energy Systems: Towards
congestion management in transmission lines. The real power Sustainable Energy (PESTSE), Bangalore, 2016, pp. 1-4.
flow control is realized by reactance compensation using
TCSC. In this paper reactance compensation of the TCSC is
modeled as a power injection equivalent. This power injection
by TCSC is calculated based on DC power flow calculations.
The optimal position for TCSC is calculated based on real
power flow reduction method. A real power flow control
algorithm using reactance compensation for congestion
management is developed .This algorithm is implemented on a
5 bus system and is found to be effective in removing
congestion.
REFERENCES
[1] J. Hazra, A. K. Sinha and Y. Phulpin, "Congestion management using
generation rescheduling and/or load shedding of sensitive buses," 2009
International Conference on Power Systems, Kharagpur, 2009, pp. 1-5.
[2] L.Rajalakshmi, M.V.Suganyadevi, and S.Parameswari “Congestion
Management in Deregulated Power System by Locating Series FACTS
Devices”, International Journal of Computer Applications (0975 – 8887)
Volume 13– No.8, January 2011.
[3] Narain.G.Hingroni,Laszlo Gyugyi, “Understanding FACTS”, 11th
Edition Wiley, New Delhi, 2013, pp. 209-210.
[4] N. Kirthika and Balamurugan. S, “A new dynamic control strategy for
power transmission congestion management using series compensation”,
Elsevier - International Journal of Electrical Power and Energy Systems,
vol. 77, pp. 271 - 279, 2016.
[5] J P. Preedavichit and S. C. Srivastava, "Optimal reactive power dispatch
considering FACTS devices," 1997 Fourth International Conference on
Advances in Power System Control, Operation and Management,
APSCOM-97. (Conf. Publ. No. 450), 1997, pp. 620-625 vol.2.
[6] K. Manjusha, S. Balamurugan and N. Kirthika, "Real power flow
control in transmission system using TCSC," 2016 Biennial
International Conference on Power and Energy Systems: Towards
Sustainable Energy (PESTSE), Bangalore, 2016, pp. 1-5.
[7] E. Ghahremani and I. Kamwa, "Optimal placement of multiple-type
FACTS devices to maximize power system loadability using a generic
graphical user interface," in IEEE Transactions on Power Systems, vol.
28, no. 2, pp. 764-778, May 2013
[8] G. I. Rashed, Y. Sun and H. I. Shaheen, "Optimal TCSC placement in a
power system by means of Differential Evolution Algorithm considering
loss minimization," 2011 6th IEEE Conference on Industrial Electronics
and Applications, Beijing, 2011, pp. 2209-2215
[9] S. N. Singh and A. K. David, "Congestion management by optimising
FACTS device location," DRPT2000. International Conference on
Electric Utility Deregulation and Restructuring and Power Technologies.
Proceedings (Cat. No.00EX382), London, 2000, pp. 23-28.
[10] P. P. Kulkarni and N. D. Ghawghawe, "Optimal placement and
parameter setting of TCSC in power transmission system to increase the
power transfer capability," 2015 International Conference on Energy
Systems and Applications, Pune, 2015, pp. 735-739.
[11] Yunqiang Lu and A. Abur, "Closure on "Static security enhancement via
optimal utilization of thyristor controlled series capacitors"," in IEEE
Transactions on Power Systems, vol. 18, no. 2, pp. 955-956, ssMay
2003.