Power System Risk Assessment Method Based On Dynamic Power Flow

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

Power System Risk Assessment Method Based on

Dynamic Power Flow


YE Xiaohui, ZHONG Wuzhi, SONG Xinli CHENG Lin
Power System Department Electrical Engineering Department
China Electric Power Research Institute Tsinghua University
Haidian District, Beijing 100192, China Haidian District, Beijing 100084, China
yexiaohui@epri.sgcc.com.cn chenglin@mail.tsinghua.edu.cn

Abstract—Risk assessment theory is paid more and more analysis method is very important, the traditional approach
attention to consider the random characteristics of power uses DC power flow and linear programming or AC power
system, but traditional method could not consider the
flow based optimal power flow (OPF) to calculate the
operating factors as frequency response of generators and
loads, various emergency control measures. In this paper, a
minimal load shedding at each bus subject to a set of
dynamic contingency analysis method base on dynamic load constraints, the calculation speed ofthe former one is faster
flow is proposed considering the above factors. The dynamic than the latter one, while the latter one are more accurate.
contingency analysis is a less time-consuming approach, but On the other hand, a power system is deemed secure
could simulate as well the detailed load shedding relay model, according with its ability to withstand disturbances. Power
and the time-varying reliability model. So the proposed systems are designed to provide an adequate and secure
dynamic contingency analysis gives a good tool for cascading
service. Therefore, protection and control must guarantee
failure simulation.
service adequacy under normal operation conditions. In
Keywords-dynamic power flow, risk assessment method, case of disturbances, protection and control must stabilize
generator model, dynamic contingency analysis the system and minimize the impact ofthe disturbance.
The traditional reliability theory is wildly applied in
I. INTRODUCTION
power system planning, but there are still some drawbacks
Because ofthe volatile of user's load demand, accidental as follow:
failures of electric equipment, and fast-growing renewable 1) The power flow in contingency analysis could not
generating capacity, the power system has random consider the operating factors as frequency response of
characteristics and sometimes operates on highly stressed generators and loads, various emergency control measures.
and unpredictable conditions, which makes planning And the calculated load curtailment is the minimum
difficult. Deterministic approaches, such as N-1 criterion, possible value different from the real load curtailment
scanning subjective contingency set cannot satisfy the needs which is dependent upon power system dynamics [7].
of modern power system. On the other hand, power system 2) There are many different types of interactions by
risk assessment theory employs the stochastic methods to which failures can propagate during the course of a
quantify the ability of a power system to provide supply of blackout. For example, a transmission line tripping can
electrical energy [1], and it could consider the adequate and cause a transient, the overloading of other lines, the mal-
secure risk of power system failures [2][3], operation or mis-operation of relays, reactive power
In aspect of power system risk evaluation area, recently problems, or can contribute to system instabilities or
research advancements can be divided into two operator stress.
classifications: components risk model [4][5], and bulk 3) The failure rate is time-varying under different
power system risk evaluations. Then traditional bulk power condition. For example, a component is getting easier to fail
system risk theory is divided into two categories: adequacy with its increasing age; a component's failure rate changes
evaluation and security evaluation. Adequacy is the ability in different weather conditions, and it needs more time to be
of the system to meet the load demand, within component repaired under bad weather; transmission lines are easier to
ratings and voltage limits, taking into account planned and be tripped by protect relays when it is overloaded.
unplanned component outages. Security is the ability ofthe Therefore the assumption that reliability parameters are
system to withstand disturbances without losing system constant is unwarranted. A condition-dependent reliability
instability [6]. model is needed to be employed.
To consider the possibility thoroughly, the reliability In this paper, a dynamic contingency analysis method
theory analyze more contingencies than deterministic base on dynamic load flow is proposed considering the
method, which is time-consuming, so the contingency above factors. The dynamic power flow is a less time-
Supported by Youth Foundation of China Electric Power Research consuming approach, but could simulate as well the
Institute (XT84-15-001).
dynamic of generators, primary frequency control and

978-l-5090-1970-0/16/$31.00 ©2016 IEEE PMAPS 2016


automatic generation control system. III. DYNAMIC POWER FLOW EQUATION

II. TRADITIONAL CONTINGENCY ANALYSIS METHOD


The conventional power flow equations assume a
balanced situation, in which total generation satisfied total
In each contingency, the system should meet several load and losses in power system, and all of the unbalanced
constraints, for example, the total power of generators must power is beard by a special chose bus, slack bus. The
match the total load demand, power on transmission lines concept of slack bus is mathematical one, and does not exist
should be within its capacity limit, and abnormal voltage of in real power system. Moreover, after power system
each bus need to be cleared up. If the above constraints are operation process, open circuit, generator out of operation
not met, remedial actions provide means of correcting or considerable change in load, the unbalance power is
abnormal conditions, such as generator rescheduling and beard by all the generators according to their inertia
shunt switching, etc. In case of inadequacy, remedial constants, primary frequency regular property of governors,
actions will involve load shedding, which is recorded as a or secondary regular parameters.
system failure. Results of the contingency evaluations are
The paper builds dynamic power flow equations to
stored to calculate reliability indices.
consider above factors. The unbalance active power Pacc is
For reliability analysis, the contingency analysis is calculate as (1):
important to calculate load-shedding relative index, and the =
Pacc Σ ί = ι PGI — Σ ^ = ι PLJ ~ PLOSS (1)
process is much computation-consuming. To calculate
minimal load shedding, multiple solutions of power flow where
problem are required to obtain a feasible solution satisfying V=total number of bus
constrains in power system, sometime optimal power flow PGi=total active power of generators in bus i
(OPF) is carried out. PLj=total loads in busj
DC power flow is the most simplified method to P s
LoS total loss in power grid
=

approximate power flow problem, which can get one Then, the frequency deviation Af of system can be
solution even in incorrect condition, because DC power represented as:
flow reduces the problem down to a set of linear equations.
And the DC based OPF is a simplified linear optimization
where
problem which is often used in practice, especially for
KGt =total sum of the slope of the frequency response
analysis of very large systems. The drawback is that only
characteristic on bus i
angles and active power flows are calculated, so it ignores
the voltage problem raised in real power system. KLj =total sum of load frequency regulation control factor
AC power flow, with Gauss-Seidel or Newton-Raphson in bus j
method, deals with a set of nonlinear equations. If the Real active power of generators and loads are functions
system operates in abnormal state, corrective actions are of frequency deviation Af:
carried out in order to bring power system to meet the PGt = PGi0 + KGi • Af (3)
operating constrains. PL; = PLjo + KLj • Af (4)
AC based OPF is the best method to calculate the least where
load shedding as consequences of one contingency, but PGÍ0 =initial active power of generators in bus i under
non-linear optimization problem is a difficult task [8] , then normal frequency
more effective and least time-consuming methods are PLj0= initial loads in b u s j under normal frequency
proposed to calculate the minimum interruption of loads. KGi and KLj are the frequency response coefficient of
The load curtail strategy by near [9] and central relaxation generators and load. In general, KLJ=l~3, that is to say, PLj
based curtail strategy [10] are faster, but the results are not changes about 1 % ~ 3 % when frequency deviation Δ / = 1 % .
optimal. The regional power flow sensitivity is presented in KGi is difficult to calculate as shown in Fig. 1, for it is
[11] to calculate the load curtailment, and the improved dependent of generators' inertia constants M, primary
algorithm provides faster execution time without frequency control parameter R, and power order APAGC
compromising the quality of solutions obtained. from automatic generation control. The factors above have
The traditional contingency analysis method is suitable different response time, and this paper focus on second
for solving adequacy of system, and ignores the operational time-scale, so coefficient of primary frequency regulation is
modes. There are many special modes appearing in real chosen as KGi.
system. For example, not all of the generators are spinning
standby to bear the load immediately; some equipment
without failure is not available during its maintenance
process; construction of transmission line is stage by stage,
and its capacity will change by uprating project. So a novel
contingency analysis under special operational mode is
desired.
Figure 1. The generator simplified dynamic model
Assuming m is the number of PQ nodes, the dimension or/and overloaded, it will be tripped off by current-
of traditional power flow is (N+m-1). Adding a new state controlled overload relays.
value Δ/ the dynamic power flow problem can be presented In the practical statistic work of lines' reliability data, the
as (V+m)-dimensional system of non-linear equations as outage probabilities of lines are not classified according to
following: the transfer capacity. Therefore the relation between outage
ΙΔΡ =PG„ - PL„ +(KG + KL )Δ/ -V ¿ V (o^coss, + B, sins, ) probabilities and transfer capacity is not obtained.
- = (5) Assuming the following three conditions, F{L), the curve of
I AQ. = QG, -QL-ν,JV, (Gilsinl,il-BilcosSil) lines' outage probability changing with transfer capacity, is
obtained, as shown in figure 3.
The equations are similar with traditional ones, so it can
be solved using Newton method.

IV. RISK ANALYSIS MOTHOD

Dynamic power flow is a good tool to simulate dynamic


response of power system approximately in each F
contingency, and could be used in contingency analysis. L-omal L-ormal L l

Moreover, in cascading failure analysis, a transmission line Figure 3 Line's outage probability-transfer capacity curve
tripping can cause a transient, the overloading of other lines,
C. Contingency Analysis Process
the mal-operation or mis-operation of relays. For
components' failure rate is changing under different So as shown in Fig. 4, the simplified procedure of
operation condition [12] , a time-varying reliability model dynamic contingency analysis is summarized as follow:
should be used after calculation of each dynamic power Stepl: Analyze the initial contingency, and deal with the
flow. network islands. Calculate the unbalanced power Pacc
using (1);
A. Detailed Load Shedding Relay Model Step2: Determine the frequency deviation using (2);
Taking the advantages of dynamic power flow, more Step3: Use detailed low cycle load reduction relay model
detailed load shedding strategy could be employed to to determine whether the low-frequency load shedding acts.
calculate the load curtailment. If frequency is lower than the value of sequential rounds,
Under-frequency load shedding relay will cut off load load cut off one round, if frequency is lower than the value
when frequency is lower than the setting value to make sure of special rounds, it acts immediately, and then go back to
the stability of power system. Normally, there are stepl to recalculate unbalanced power Pacc and frequency
sequential rounds and special rounds as shown in Fig. 2: deviation;
sequential rounds act one by one, special rounds act under Step4: Calculate dynamic power flow using (5);
urge situation quicker than sequential rounds. Step5: Use detailed low-voltage and high-voltage load
Under-voltage load shedding relay cuts local loads, and it reduction relay model to determine whether the load
acts according to the voltage of local key bus. So there are shedding happens;
several rounds with different action threshold value. Over- Step6: Update the failure rate of abnormal components,
voltage relay is placed on generator to protect generator and simulate the cascading process by Monte-Carlo method,
from extreme heating, and generator will be cut off under if there is another device fail, go back to stepl;
over voltage condition. Step7: Summarize the total load curtailment, and use the
value as the result of contingency.
D. Operational Risk Assessment
f ä f,„ SeqRoundl j
Dynamic contingency analysis based risk evaluation
process is shown in Fig. 5.
-SeqRound*
1). Calculate the initial failure rate of each component
according to element's reliability models based on the real-
time operating conditions;
fä SpRound! ί 2). Simulate and give out possible contingency by means
ί
:
Special
Rounds
of Monte-Carlo simulation method;
f ä f,p2 • SpRound2 |
3). Consider each contingency, and calculate its load
curtailment results using dynamic contingency analysis
method;
4). Calculate reliability indices according to the
Figure 2. The under-frequency load shedding relay model definition of reliability index, the product of faults
probability and faults consequence.
B. Time-varying Reliability Model
When a transmission line or transformer is overheated
Network island analysis and calculate load curtailment is more accurate than traditional OPF
the unbalanced power Pacc using (1) based one by means of detailed load shedding relay model.
After applying dynamic contingency analysis method, the
operational risk evaluation method assesses the adequacy of
a power system to supply power to its customers under real-
time operating conditions.
Moreover, dynamic power flow based contingency
analysis method could also get the cascading routine, which
is important in cascading failure analysis. And cascading
failure process is also our future work.

REFERENCES
[1] R. Billinton, R.N. Allan, "Reliability evaluation of power systems",
Solve dynamic power flow using (5) 2nd ed., New York and London: Plenum Press, 1996.
i [2] R. Billinton, A. Sankarakrishnan, "A Comparison of Monte Carlo
Simulation Techniques for Composite Power System Reliability
If voltage is abnormal, calculate load
Assessment", IEEE WESCANEX '95 proceedings, pp. 145-150,
curtailment using abnormal-voltage 1995.
load shedding model
[3] V Vittal, J D McCalley, V Vanacker, et al, "Transient instability risk
assessment", IEEE Power Engineering Society Summer Meeting,
Edmonton, Alberta, Canada, pp. 206 -211, 1999.
Refresh the failure rate of the
components, and simulate cascading [4] J Zhang, J Pu, J D Mccalley, et al, "A bayesian approach for short-
failure of abnormal components term transmission line thermal overload risk assessment", IEEE
Trans, on Power Delivery, Vol. 17, No. 3, pp. 770-778, 2002
[5] W Η Fu, J D Mccalley, V Vittal, "Risk assessment for transformer
loading", IEEE Trans, on Power Systems, Vol. 16, No. 3, pp.
346-353, 2001.
[6] A. M. L. da Silva, J. Endrenyi, L. Wang, "Integrated treatment of
adequacy and security in bulk power system reliability evaluations,"
IEEE Trans. Power Syst., vol. 8, no. 1, pp. 275-285, Feb. 1993.
[7] Hongbin Sun, Qin Li, Mingye Zhange, et al, "Continuation Power
Figure 4. The diagram of dynamic contingency analysis Flow Method Based on Dynamic Power Flow Equation", Proceeding
o f t h e CSEE. Vol. 31,No.7, pp. 77-82, 2011.
[8] Yuan zhao, Jiaqi Zhou, Yang Liu, "Analysis on Optimal Load
Shedding Model in Reliability Evaluation of Composite Generation
and Transmission System", Power System Technology, Vol. 28, No.
10, pp. 34-37, 2004.
[9] Yang Liu, Jiaqi Zhou, "Optmal Load Curtailment in Bulk Power
System Reliability Evaluation", Journal of Chongqing Universisty,
Vol. 26, No. 10, pp. 52-55, 2003.
[10] Kai Xiao, Yongji Guo, Yongjian Xi, et al, "New Algorithm for Large
Power System Reliability Evaluation", J Tsinghua Univ (Sei & Tech),
Vol.39, No. 1, pp 12-15, 1999.
[11] Lin Cheng, Yuanzhang Sun, Wangqi Zheng, "Large-scale composite
generation and transmission system adequacy evaluation.
Automation of Electric Power Systems", Vol. 28, No. 11, pp. 75-78,
2004.
[12] Sun Y, Cheng L, Ye X, et al, "Overview of power system operational
reliability", Probabilistic Methods Applied to Power Systems (PMAPS),
2010 IEEE 11th International Conference on. IEEE, pp. 166-171, 2010.

Figure 5. The diagram of risk analysis process

V. CONCLUSION

In this paper, a dynamic power flow based contingency


analysis method is proposed. The analysis process can
simulate the dynamic of power system, and the calculated

You might also like