Final Project Title: TNTS PTA Cash System

Project Organization:

Mr. Paulino Tado


PR2 Head

Ms. Allyn Joy


Calcaben
PR2 Adviser

Shanley Ylanan
Project Manager

Jenny Mae Tocmo Alexis Broey Tito Daniel RJ Dioso


Front-end Full-stack Back-end
Developer Developer Developer

Main Functionality Distribution

Software Methodologies to Apply

The software methodologies to be used are the Agile Model and the Spiral Model. As per
definition of both the methodologies, both are commonly used when the system to be implemented is
complex and implementing TNTS PTA Cash System is a complex work to deal with. The purpose into
using the Agile Model is that it can be helpful as a guide for the breakdown of works to be done as to
implanting the system whereas to the Spiral Model, it can be helpful into tracking some possible system
errors when testing the system.

Gantt Chart for Breakdown of Works

Task Description Duration Predecessor


(days) Task
A Planning -
B Designing A
C System Testing D
D Code Implementation B
E Deployment F
F Debugging C

Task
Name
Planning
Designing
System Testing
Code
Implementation
Deployment
Debugging

Risk Management Plan