Professional Documents
Culture Documents
A Methodology To Determine Transient Recovery Voltage in Short-Line Fault
A Methodology To Determine Transient Recovery Voltage in Short-Line Fault
A Methodology To Determine Transient Recovery Voltage in Short-Line Fault
net/publication/312965487
CITATIONS READS
0 159
2 authors, including:
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Daniel Perez Dorantes on 28 February 2019.
Abstract— This paper presents a methodology to determine Short-Lines Faults (SLF) appear with major percentage of
the appropriate parameters to establish the capability of faults occurrence. When the Short-Lines Faults are liberated
Transient Recovery Voltage (TRV) of a 145kV circuit breaker. by the circuit breaker, the TRV in the circuit breaker terminals
The methodology involves the combination of a simulation is characterized by a large raised change in the RRRV. If the
procedure in the Electromagnetic Transients Program (ATP)
and an analytical technique based on the IEEE C37.06 and IEC
capability of the circuit breaker to support high changes of
62271-100 standards to evaluate the effect of the source side voltage is not enough, it can provoke arc reignitions in the
voltage and line side voltage on the TRV in a short-line fault circuit breaker contacts provoking a fault in the thermal region
(SLF). The results obtained on TRV of the circuit breaker operation and dielectric capability to support the TRV.
capability by simulation and analytical calculatión, acording to Therefore, it is essential to know the correct TRV limits of the
the IEEE and IEC standards, are compared using the Matlab circuit breaker to use. In reference [4] the effect of the TRV is
program. evaluated in short-line faults, explains the procedure to
evaluate the TRV parameters based on the IEEE C37.04
Keywords—TRV, RRRV, Circuit Breaker, SLF, ATP, Matlab.
standard, and in the references [5] and [6] is presented a
I. INTRODUCTION methodology to evaluate the TRV envelope based on the IEC
62271-100 standard.
The circuit breaker is an electromechanical device whose IEEE C37.06.2009 and IEC 62271-100 international standards
function is to connect and disconnect electrical circuits under present a similar methodology for the calculation of the of
normal or failure operating conditions of the electrical power TRV capability parameters, they only differ on the mentioned
network. These devices should be selected according to the references, in the terms names to classify the TRV and in
electrical infrastructure used, as the generator type, line, voltage limits values. For the classification, exist a trend for
transformer, capacitor or reactor. Because of its important the homologation of the above-mentioned standards.
work and the large number of power switches used in electric
network, it is essential to have a methodology to determine the The present paper proposes a methodology to determine the
TRV correctly. For example, transmission network of the appropriate parameters to establish the capability of Transient
Federal Electricity Commission (CFE) in Mexico uses around Recovery Voltage based on a simulation procedure in ATP
of 7093 power switches, installed in 399 substations of 230 and an analytical technique that uses the IEEE and IEC
kV and 400 kV [1]. standards to evaluate the effect of the source side voltage and
line side on the TRV in a short-line fault. For the application
The increase and complexity of the electrical network of the of developed methodology, it is considered the release of a
CFE and the occurrence of faults derived from the reduced single-phase fault presented in an 115kV transmission line of
limits in some parameters in the circuit breaker selection, as CFE network, located in the State of Mexico. Results of the
the transient recovery voltage and the Rate of Rise of evaluation of the TRV parameters are presented, considering
Recovery Voltage (RRRV), makes it necessary to carry out, the IEEE and IEC procedure to determine the cause-root of the
for the circuit breaker diverse applications, an evaluation circuit breaker fault.
using digital simulation to check and to verify the safety
margins of the switches during the operation. In addition for II. METHODOLOGY TO DETERMINE TRV CAPABILITY OF THE
the cause-root faults analysis tool of power switches, digital CIRCUIT BREAKER FOR SHORT-LINE FAULTS
simulation methodology allows to calculate the typical Fig. 1 shows the single-line diagram of the circuit where is
parameters of the TRV and compare them with the established located the line of 115kV where the fault of the circuit breaker
parameters using the international procedure IEEE 73040 was presented. The specifications of the 73040 circuit
C37.06.2009 [2] and IEC 62271-100 [3]. breaker are: rated voltage = 145kV, rated current =2000A and
rated current of short circuit = 40kA. Using IEEE C37.04 [2]
According to the faults statistics of CFE, the faults index is and IEC 62271-100 [3] standards, the Table I shown the
major in circuit breakers installed in transmission lines. The parameters of the TRV for the 145kV circuit breaker.
( %) = ( 100) (1)
( %) = ( 100) (2)
( %) = ( 100) (3)
( %) = ( 100) (4)
Voltage (V)
tL Time to peak (µs) 1 U1, t1
d Amplitude factor is 1.6
M Ratio of the fault current to the rated short-circuit 0.5
current UT, tL
td Time delay of recovery voltage on the source side 0
0 0.5 1 1.5 2 2.5
(2µs) Time (s) -4
x 10
Ur Rated voltage (kV) Fig. 2. TRV capability envelope for a 145kV circuit breaker at 83.7% of its
Zeff Line surge impedance=450Ω rated fault current, for short-line faults.
The procedure for calculating initial TRV envelope for short- III. ANALYTICAL TRV CALCULATION TECHNIQUE FOR SHORT
line fault is presented below. LINE FAULT
The calculation of TRV parameters of the system DOG of 115
The contribution of side line voltage in TRV is calculated kV to a single-phase fault in a short line is carried out using
considering that the initial voltage at the power circuit breaker the IEEE C37.011-2011 Reference Guide [7].
terminals is:
The single-phase fault occurs at 4.6km from the DOG bus. For
= (1 − ) 2/3 transmission lines 73040 and 73190 of the 115kV system, Fig.
1, it is assumed normalized (3 x ACSR 795 kCM + 2 x AG9)
= =
.
= 0.837 individual circuits in H structure with a ground resistance of
100 Ω/m. The positive sequence and the zero sequence line
= (1 − 0.837) × × 145 = 19.29 inductances are L1=1.223mH/km and L0=3.81mH/km
respectively. The positive sequence reactance of the Bus DOG
115kV side and the zero sequence reactances are X1=1.815Ω
The voltage on the line side is, using (6): and X0=2.657Ω respectively.
= = 1.6 × 19.29 = 30.87 The single-phase fault current can be determined by:
=
The rate of rise of TRV of the line side voltage, by (8) is:
Fig. 2 shows the TRV capability envelope of the 145kV From (5), the rise of rate of line side TRV is:
circuit breaker for a single-phase fault established with the
2016 IEEE International Autumn Meeting on Power, Electronics and Computing (ROPEC 2016). Ixtapa, Mexico
The initial voltage at the circuit breaker terminals is: RRRV=113/34= 3.32 /μs
= 3.32 × √2 × 12.25 = 57.51 The rated RRRV that is calculated for the 145kV circuit
breaker is of 8.85 kV/µs for single-phase of short line fault.
Then the line side voltage is given for: Then, 8.85 kV/µs is the limit of the envelope, and the TRV
initial slope must not exceed this capability limits. The
= = 1.6 × 57.51 = 92 analysis and comparison of the TRV capability of Fig. 3 with
the TRV determined by simulation means, using ATP, is
The time when the peak voltage occurs is: presented in the following section.
92
= = 33.5μs IV. TRV DETERMINATION OF THE 145KV CIRCUIT BREAKER FOR
2.74 SHORT LINE FAUL BY SIMULATION WITH ATP
The line side voltage obtained at 33.5 µs is: For the study case in this work, the release maneuver of
transmission line SE-GD 73040 in the 115kV system, Fig. 1,
Up=57.51-92= -34.49kV. is analyzed when a single-phase fault occurs on phase C due
to dielectric failure at 4.6km from the DOG bus. The circuit
The source side voltage, assuming capacitance can be diagram where the line SE-GD 73040 is located is
neglected, is as follows: implemented with ATP, as shown in Figure 4.
SE DOG
= 1− + V
LCC
Where: 73190
73040
0.0055
= = = 39.28
140
Therefore:
Fig. 4. ATP model of the 145kV system, under study.
= 36.38 1 − . + 57.51
The load is assumed as constant RL impedance with floated
The source side voltage, line-side voltage and TRV are shown neutral, for it calculation is used the sum of the demands
in Fig. 3. Where the TRV is the sum of the terminal source registered in the 73040 and 73190 lines, as shown in Table IV.
side and line side voltages of the power circuit breaker:
TABLE IV. LOAD IN THE 73040 AND 73190 LINES.
0
According to fault information, the fault current was released
-2 when the differential protection bus operate, which opened all
switches associated with the bar 2 of bus 115kV of the SE
Voltage(V)
-4
-6
DOG. The registered fault parameters and sequence are.
-8
• Ratings voltage and currents from the beginning of
-10 X: 3.4e-05
Y: -1.131e+05 fault up to 3.5 cycles.
-12
0 0.5 1 1.5 2 2.5
Time(s)
3 3.5 4 4.5
-5
5 • Overcurrent and depression voltage in phase C from
x 10
Fig. 3. TRV of the 145kV circuit breaker for short-line fault. cycle 3.5.
2016 IEEE International Autumn Meeting on Power, Electronics and Computing (ROPEC 2016). Ixtapa, Mexico
0.2
Voltage(V)
Figures 5 to 10 show the obtained results when simulated 0
73040 at 4.6 km from the bus DOG, following the above -0.4
extinguish the fault current and kept leading up to total Fig. 7. Phase to ground voltages on line GD-73040.
disconnection of the 115kV bus. Fig. 5 shows the currents
abc and in Fig. 6 are observed the phase to ground The results of the simulation are consistent with those
voltages in the 115kV bus. recorded in the information of the fault, validating the model
used in ATP, and it only remains to evaluate the transient
recovery voltage appearing between circuit breaker terminals.
4
x 10
2
1.5
ia The voltages between the circuit breaker contacts are
ib
ic
displayed in Fig. 8 for abc phases.
1
5
0.5 x 10
1
Current(A)
TRV A
0 TRV B
TRV C
0.5
-0.5
-1
0
Voltage(V)
-1.5
-2 -0.5
-2.5
0 0.02 0.04 0.06 0.08 0.1 0.12 0.14 0.16 0.18 0.2
-1
Time(s)
Fig. 5. Currents across the circuit breaker 73040.
-1.5
0.03 0.035 0.04 0.045 0.05 0.055 0.06
5
Time(s)
x 10
1
Fig. 8. Voltage across circuit breaker terminals.
0.8
0.6
The comparison of TRV calculated according to the IEEE
0.4
standard C37.011-2011 and the envelope of rated capability is
implemented in Matlab and is shown in Fig. 9. As seen in
Voltage(V)
0.2
0
figure, the TRV which was obtained in the simulated single-
-0.2
line release fault in Phase C at a distance of 4.6km from the
-0.4
bus, is more severe than the 145kV circuit breaker must
-0.6
support, according to the envelope calculated for capability
operation of 83.7% of the short-circuit rated current of the
-0.8
circuit breaker.
-1
0 0.02 0.04 0.06 0.08 0.1 0.12 0.14 0.16 0.18 0.2
Time(s)
0
System TRV
Phase voltages to ground on the side of the DOG-73040 line TRV related capability envelope
-1
Voltage(V)
-1.5
-2
-2.5
0.0361 0.0362 0.0362 0.0363 0.0363 0.0364 0.0364 0.0365
Time(s)
Fig. 9. Comparison of the obtained TRV, by simulation and by IEEE Norm.
2016 IEEE International Autumn Meeting on Power, Electronics and Computing (ROPEC 2016). Ixtapa, Mexico
The start of the slope of the TRV does not exceed the limits of V. CONCLUSION
the envelope as expected according to the analytical
calculations, but the peak voltage TRV exceeds the nominal This paper presents a methodology to determine the TRV of
envelope, exceeding the limit of TRV capability slope. The circuit breakers, combining digital simulation in ATP and an
interruption in the thermal zone was unsuccessful and came up analytical method based on the IEEE and IEC standards,
with a restrike in the circuit breaker located in the 73040 line verifying and checking the safety margins during the
that led it to have the fault occurred in the electrical system. occurrence of short line faults. The comparison of the obtained
TRV is implemented in Matlab. In the case study it is
Fig.10 presents the voltages of line side, source side and the determined that the 145kV circuit breaker of CFE fails
TRV in the circuit breaker terminals and Table II presents the because the level of the slope of the rated capability is
values obtained by simulation and the calculated according to exceeded. The interruption in the thermal zone was
the reference Guide of the IEEE. unsuccessful and came up a restrike of the circuit breaker that
leads to have a dielectric failure. The fault is caused by a high
TABLE V. TRV PARAMETERS, CALCULATED AND OBTAINED BY RRRV that exceeded the capability of the circuit breaker and
SIMULATION it continues conducting a phase of the system.
Parameter Simulation ATP Calculation IEEE
U0 54.2 kV 57.51 kV REFERENCES
UL 88 kV 92 kV
tL 37 µs 33.5 µs [1] SUBDIRECCIÓN DE TRANSMISIÓN CFE, “SÍNTESIS DE FALLAS DE
INTERRUPTORES DE POTENCIA”, MÉXICO, D.F., 2014.
Uc 128 kV 113 kV
[2] Switchgear Committee of the IEEE Power Engineering Society, “IEEE
RRRV 3.4 kV/µs 3.35 kV/µs
Standard for AC High-Voltage Circuit Breaker Rated on a Symmetrical
Current Basis- Preferred Ratings and Related Required Capabilities for
Voltages Above 1000V”, 2009.
[3] IEC working committee, “High voltage circuit breaker standard: IEC
4
x 10
4
Source side voltage
Line side voltage
62271-100", 2008.
2
TRV C [4] Grazia Todeschini, “Analysis of the effect of distance on the TRV
0 waveform for a Short-Line Fault, Transmission and Distribution
-2
Conference and Exposition”, 2012 IEEE PES.
[5] J.G Jamnani, Mrs S.A Kanitkar, “Design and simulation of 2-parameters
Voltage(V)