Review & Approval of Cea Form
Review & Approval of Cea Form
*There should be at least 3 quotations and if it doesn’t meet this requirement, a waiver
for approval must be signed first by the General Manager (GM) subject to the following
rule:
Asset Group refers to the asset category of the item (ex. Engineering Plant and
Equipment, Computer Equipment, AT & E – A320, etc.)
Control Number refers to asset/tag number assigned to the item (refer to number)
Once this portion is filled out by the FA team, the CEA form is now subject for the approval of
SFM & FM.
Problems:
1. When the requested items are tools, the aircraft type in which the tools are intended for or to be
used in is sometimes not indicated in the PR form. And as such, finance will have to ask the
purchasing personnel responsible about the mentioned concern through email.
2. The department are raising a purchase request form (PR) without knowing the listed items in the
approved CAPEX and their remaining budget.
3. CEAs are often forwarded directly to SFM & FM offices without being reviewed first by the FA
team.