Professional Documents
Culture Documents
Inward Inspection: Business Process Procedure
Inward Inspection: Business Process Procedure
Inward Inspection
Quality Process for Inward inspection will start after factory receipt.
Inspection Lot will be generated and material will be blocked Quality inspection.
Inward Inspection:
We will have selection menu to find specific Inspection lot as per plant, material, date etc.
Select Inspection Lot Origin 01 for inward inspection.
1. Change inspection lot : When our inspection lot have status as CRTD.
We will click on Change Inspection Lot and assign inspection plan to it as per shown in
screenshot.
Last Changed On Last Changed By Version Page Number
Page 3 of 20
17.01.2018 Abhijit Dusane 1
BUSINESS PROCESS PROCEDURE
Click on
INSPECTION
SPECIFICATION
Note: This activity will be done only when Inspection Lot have status as CRTD. If it REL just
process for next activity which is result recording.
2. RESULT RECORDING: In this process we maintain all entries for material about its
characteristics. We record results against material.
Click on for recording the result against material. Following screen will appear.
1 2 3
a. These are all characteristics for the material which we maintained in the inspection plan.
b. This box Show inspected sample i.e. inspection sample.
c. In this tab, we will record our result. Click on result box and press F4.
d. Select required result from appeared options.
For e.g. Okay or Not Okay or not as per drawing
e. Then press ENTER. Results will be saved and valuation of result will be done our
result.
f. In this manner, enter results for every characteristic.
Note:
MIC with name Visual insp., Dimension check and Functional check will be printed on
our MIIR report.
3. Defect Recording:
When we reject any characteristics, we need to create a defect for specific rejected
characteristics.
When you records result with red cross i.e. not okay.
1 2
d)
f) If you have pending MIC for result recording then ENTER it or click on and record results
for further MIC's.
After recording all results and defects; save the result recording window with CTRL+S.
a) Go to
c)
d) Select randomly any one defect. System will take all defects in the Notification tab.
e) Go to ACTIVATE Notification. Screen will appear. Select priority (Not mandatory) and ENTER.
m) Select Defect location from 1000 SKIND. Press F4 or click on drop down.
o) Select code for Cause from the drop down list and enter.
p) Click on Excel Word file will open. Write Root cause analysis in word file. You can write root
cause analysis for other defects also in the same Word file (Recommended).
Go back
r) Select TASK code from the drop down list. Select Task of codes 1000, 2000 and 3000 only.
t) Select Task Processor as VU User responsible if causes and corrective action taken by SEMIKRON
u) Select Task processor as VENDOR if and corrective action taken by SEMIKRON and corrective
w) Select corrective action from the activity code from the Group SKIND-CA (Strictly recommended)
and Press ENTER. Long text tab will appear. Click on , word file will open; write down the
corrective action taken by SEMIKRONs or VENDOR.
y) Select Role of user in function column and select user from PARTNER column.
To find out Notification No. go to change defect again and click on process notification. In the
From all our entries in notification will be fetched in the NCR report.
So to take print of NCR; Go to transaction ZNCR.
5. Usage Decision:
At this stage all quality inspection process finished. Now we will clear the material from
quality inspection and we give decision according to our inspection result.
In the Usage decision activity, we post material to its storage location and clear the
inspection lot by giving usage decision code.
a) Go to the transaction code QA32.
b) Select inspection lot and click on .
c) Usage decision screen will appear
e) Put accepted Qty in "To unrestricted use" and select desired storage location. Then
save it. You will return to QA32 transaction screen.
f) If you some rejected quantity also, then go to same option of "Usage decision"
g) Put your rejected qty in same "To unrestricted use". But this select storage location
as "ZRET"
i) Give your Usage Decision Code from the drop down list.
In this way we finished all SAP data entries for inward inspection.
6. Documentation:
Note:
1. You can't take generate MIIR if you haven't take Usage decision for any material in the
MIGO/Delivery Challan no.
2. If you forgot to record result for visual, functional, dimensional characteristics, then it won't
be reflect in MIIR.