Labor Production Estimate
Labor Production Estimate
2. Formworks
Materials No. of Use (per sq.m)
1 2 3 4 Lumber Bdft
Plywood (pcs) 0.336 0.605 0.857 1.076 2 x 2 x 12 4.0
Lumber 2x3x12 (pcs) 0.860 1.548 2.193 2.752 2 x 3 x 12 6.0
Lumber 2x4x12 (pcs) 1.610 2.898 4.106 5.152 2 x 4 x 12 8.0
Nails (kg) 0.173 0.311 0.440 0.552
Form Oil (lit) 0.161 0.291 0.412 0.516
3. Steel Works
Materials Wt of Reinforcing Stee
Oxygen 4.4 pcs.per ton steel Diameter
Accetylene 2.2 pcs.per ton steel 10
Welding Rod 0.025 of ton steel (20kg/ box) 4 inch/ rod 12
Paint 2 40 kg 16
Thinner 1 gal / ton steel (1 coat) 20
Equipment 0.4 percent of labor cost
4. Painting Works
4.1 Xyladecor
Wood Lite 0.25 L/ sq.m
Sand Paper 0.3 sq.m/ sq.m
Xyladecor 0.15 L/ sq.m/ coat
Stoppa Rugs 0.1 kgs/ sq.m
4.2 Acdytex
Acrytex Cast 0.225 L/ sq.m
Acrytex Primer 0.15 L/ sq.m
Acrytex Top Coat 0.15 L/ sq.m/ coat
Acrytex Reducer 0.15 L/ sq.m
4.5 Duco
Lacquer Flo 0.15 L/ sq.m/ coat
Lacquer Thinner 0.15 L/ sq.m/ coat
Lacquer Primer 0.05 L/ sq.m
Lacquer Primer Putty 0.1 L/ sq.m
Sand Paper 0.1 sq.m/ sq.m
Auto White 0.225 L/ sq.m
4.6 Varnish
Wood Lite 0.3 L/ sq.m
Wood Bleach 0.15 L/ sq.m
Wood Stain 0.15 L/ sq.m
Sanding Sealer 0.1 L/ sq.m
Dead Flat Lacquer 0.15 L/ sq.m/ coat
Sand Paper 0.1 sq.m/ sq.m
Architectural Estimates
1.Floor Finishes
1.1 Red Cement Floor Finish
Red Cement 0.0278 Bag/ sq.m
2. Wall Finishes
2.1 Plywood Paneling on 2"x2" frame @ 400mm O.C.
Joist 2"x2" 5.46 Bd. Ft/ sq.m
Nails 0.89 Kg/ sq.m
Plywood 4'x8'x1/4" 0.7 Pc/ sq.m (DW)
0.35 Pc/ sq.m (SW)
2.2 Plain Cement Plaster 19mm ave. 1:2 Quantity of cement and sand for plaster per sq.m
Cement 0.34 Bags/ sq.m Class 8mm 12mm
Sand 0.018 Cu.m/ sq.m A 0.144 0.216
B 0.096 0.144
2.3 Glazed Tiles C 0.072 0.108
Scratch Coat 12mm Thick 1:2 D 0.06 0.09
Cement 0.23 Bags/ sq.m Sand 0.008 0.012
Sand 0.12 Cu.m/ sq.m
Adhesive 0.083 Bags/ sq.m
Cement for grout 0.1 Bags/ sq.m
Tile 4"x4" 97 Pc/ sq.m
Muriatic Acid 0.005 Gal/ sq.m
2.4 Wallpaper
Wallpaper 1 sq.m/ sq.m
Wall paste 0.04 box/ sq.m
3. Ceiling Finishes
4. Miscellaneous
4.1 Wood Cabinet Hardware Accessories
2"x2" 20 Bd.ft/ cu.m Nails
1/2" Plywood 0.5 Pc/ cu.m Ceiling 0.105
1/4" Plywood 2 Pc/ cu.m Dry Wall 0.66
Hardware 400 Php/ cu.m
Assorted Nails 6.15 Kg/ cu.m
Steel Reinforcement for Concrete Hollow Block Mortar for filler and bloc
Vert'l. Reinforcement Horiz'l. Reinforcement Size of CHB
Spacing Lenth / sq.m Spacing Lenth / sq.m 10 x 20 x 40 - 4"
400 2.93 m 400 3.300 m 12.5 x 20 x 40 - 4"
600 2.13 m 600 2.150 m 15 x 20 x 40 - 4"
800 1.60 m 800 1.720 m 20 x 20 x 40 - 4"
Tie Wire for CHB Reinforcement
Kg per 100 CHB
V-Spacing H-Spacing 25cm Ties 30cm Ties 40cm Ties
400 400 0.0042 0.0051 0.086
600 0.0031 0.0038 0.063
800 0.0028 0.0033 0.039
600 400 0.0028 0.0034 0.057
600 0.0021 0.0025 0.042
800 0.0018 0.0022 0.032
800 400 0.0021 0.0025 0.044
600 0.0016 0.0019 0.032
800 0.0014 0.0017 0.024
6. Scaffoldings
Rentals 220 per cu.m
Installation 140 per cu.m
mobilization 70 per cu.m
demobilization 70 per cu.m
8. Rip rap
Quantity of Cement and sand on a stone rip-rap per cu. Meter
Stone Class Cement in bags Sand
Grout mixture cu.m
A B C
Class A 2.574 1.716 1.287 0.143
Class B 2.448 1.62 1.214 0.135
Class C 2.232 1.488 1.116 0.124
Class D 1.944 1.296 0.972 0.108
Gravel,
cu.m
1
1
1
1
Wt of Reinforcing Steel Number of Lateral Ties in one steel bar and quantity per m length of column
kg/m Lateral Ties Number of Length of Number of cut in one Steel Bar length
0.62 Spacing Lateral Ties Ties with
0.89 per m ht. hook and bend 5m 6m 7.5m 9m
1.58 150 6.7 60 0 10 0 15
2.47 70 7 0 0 0
200 5.15 80 6 0 0 11
85 0 7 0 0
250 4.13 90 0 0 8 10
95 5 0 0 0
300 3.43 100 5 6 0 9
105 0 0 7 0
350 3 110 0 0 0 8
115 0 5 0 0
400 2.64 120 4 5 0 0
125 4 0 6 0
450 2.36 130 0 0 0 0
135 0 0 0 0
500 2.14 140 0 4 0 0
145 0 4 5 6
550 1.96 150 0 4 5 6
160 3 0 0 0
600 1.81 170 0 0 0 5
180 0 0 4 5
190 0 3 0 0
200 0 3 0 0
Quantity of Reinforcing steel bars in a one-way concrete slab Quantity of Reinforcing Tie w
Bar Spacing Number of steel bars per square meter Bar Spacing
mm 6m 7.50 m 9.0m 12 m mm
100 3.764 2.937 2.421 1.769
125 3.062 2.381 1.934 1.427 100
150 2.584 2.004 1.636 1.197 125
175 2.232 1.726 1.407 1.033 150
200 1.98 1.528 1.258 0.914 175
225 1.786 1.369 1.109 0.81 200
250 1.627 1.25 1.014 0.736 225
300 250
300
Quantity of Reinforcing steel bars in a one-way concrete slab Quantity of Reinforcing Tie w
Bar Spacing Number of steel bars per square meter Bar Spacing
mm 6m 7.50 m 9.0m 12 m mm
100 4.369 3.337 2.772 2.022
125 3.603 2.662 2.245 1.635 100
150 3.221 2.296 1.921 1.382 125
175 2.647 2.025 1.65 1.196 150
200 2.36 1.775 1.461 1.056 175
225 2.168 1.601 1.312 0.907 200
250 1.977 1.466 1.217 0.862 225
300 250
300
pcs/ sq.m
pcs/ sq.m
pcs/ sq.m
pcs/ sq.m
Block Filler
sand gravel
0.150 0.300
B. Rebar Works
Difficulty Man Day/
Structure
Factor Kg
Foundation 1.00 0.0100
Beam 1.05 0.0105
Slab 1.03 0.0103
Column 1.08 0.0108
Shear Wall 1.06 0.0106
Stair 1.05 0.0105
D. Masonry
Sq.m/ Man
Day
4" CHB 4.44
5" CHB 4.00
6" CHB 3.64
E. Formworks
Man Hour Table per sq.m
F. Steel Works
Labor Man Hr./ kg
Fabrication 0.22 0.38
Erection 0.16
Delivery 0.04
Painting 0.02
G. Painting Works
Xyladecor 0.4 Man Hr/ sq.m
Acrytex 0.5 Man Hr/ sq.m
Masonry Paint 0.4 Man Hr/ sq.m
Flatwall Enamel 0.5 Man Hr/ sq.m
Duco 1.2 Man Hr/ sq.m
Varnish 1.2 Man Hr/ sq.m
Architectural Estimates
A. Floor Finishes
1.Red Cement Finish
1.1 Spreading 0.12 Man hr/ sq.m
1.2 Trowelling 0.25 Man hr/ sq.m
2. Vinyl Tiles
2.1 Surface Preparation 0.8 Man hr/ sq.m
2.2 Tile Installation 0.67 Man hr/ sq.m
4. Wood Parquet
4.1 Scratch Coat 1.34 Man Hr/ sq.m
4.2 Parquet Installation 2 Man Hr/ sq.m
4.3 Sanding 0.5 Man Hr/ sq.m
0.25 Eqpt. Hr/ sq.m (sanding machine)
5. Marble Slab
5.1 Scratch Coat 2 Man Hr/ sq.m
5.2 Marble Installation 2.67 Man Hr/ sq.m
5.3 Sanding 0.67 Man Hr/ sq.m
0.25 Eqpt. Hr/ sq.m (sanding machine)
B. Wall Finishes
1. Plywood Paneling on 2" x 2" frame @ 400mm O.C.
1.1 Frame Installation 0.67 Man Hr/ sq.m
1.2 Panel Installation 0.54 Man Hr/ sq.m
3. Glazed Tiles
3.1 Scratch Coat 1.77 Man Hr/ sq.m
3.2 Tile Installation 1.6 Man Hr/ sq.m
3.3 Cleaning 0.44 Man Hr/ sq.m
4. Wall Paper
4.1 Installation 1 Man Hr/ sq.m
5. Pebble Washout
5.1 Scratch Coat 1.77 Man Hr/ sq.m
5.2 Plaster Coat 1.33 Man Hr/ sq.m
5.3 Water Repellant 0.25 Man Hr/ sq.m
6. Marble Slab
6.1 Scratch Coat 2 Man Hr/ sq.m
6.2 Marble Installation 3.2 Man Hr/ sq.m
6.3 Sanding 0.89 Man Hr/ sq.m
8. Gypsum Board
8.1 Frame Installation 1.33 Man Hr/ sq.m
8.2 Board Installation 0.67 Man Hr/ sq.m
9. Miscellaneous
9.1 Wood Cabinet 0.24 Man Hr/ cu.m
9.2 G.I. Roofing 4 Man Hr/ sq.m
C. Scaffolding
Installation 72 Cu. m / crew day 1 Crew:
Dismantle 144 Cu.m / crew day 1 - Supervisor 465.95 465.95
2 - Skilled 315 630
Installation Cost 25.80 per cu.m 3 - Helper 254 762
Dismantle Cost 12.90 per cu.m 1857.95
Others