GUIDE LINES- Heavy Storm Water Handling Storm Water Team

Isolate SCARP drain line to avoid off specs water drainage as well as line rupture and take EP-I
in service.
(Coord.Engr. P-1)

2. Open 16”& 6” v/v at P-5201A/B/C discharge lines to attain maximum flow.


(Coord.Engr. P-2)

3. Take P-1219 in service near gate#5 to handle P-I open channel water.
(Coord.Engr. P-1)

4. Take P-5201 A/B/C in service as on requirement basis.


(Coord.Engr. P-2)

5. Maintain P-5201A/B/C discharge pressure @ 0.7 Kg/cm2 to attain maximum flow


through the Pump.
(Coord.Engr. P-2)

6. Take P-1207 A/B both pumps in service. to reduce level in sewer pits.
(Coord.Engr. P-1)

7. Ensure controlled opening of open channel gates near BAGGING UNIT to avoid open
chanel over flow near CCR. [However try to handle P-I open channel water through P-
1219 operation to avoid opening of open channel gate near E&I building]
(Coord.Engr. P-1 & P2)

8. Start Satellite Storm water pumps as per requirement.


(Coord.Engr. P-1 & P-2)

9. Ensure the diversion of Cooling towers CBDs towards ADAM SOHABA CANAL
instead of open channel.
(Coord.Engr. P-1 )

10. To avoid open channel overflow during rain , Clean/ Remove the screens from open
channel or any temporary blockages.
(Coord.Engr. P-1 & P-2)

11. Take P-1304A/B in service installed at Bagging open channels.


(Coord.Engr. P-2)

RAINY SEASON PREPARATION :

a. EP –I/II levels should be minimum possible.


b. EP – I Transfer pump is available.
c. Open channels and inter connecting pits are cleaned on monthly basis.
d. Storm water pumps are available in good condition.