DAILY REPORT
FROM : 7 AM - September 1, 2018 TO : 7 PM - September 1, 2018
Order No. Plant Function Location Activities Description Start date Finish date Progress Remarks
A- Inspection Activities
210000090832 HIPF Gas boot to close drain Visual inspection of prefabrication welds 18.05.2018 95% Remaining only two welds for 2” line
verbal HM Inspection of damaged spool and all lines of Water Injection Manifold at North Manifold Visual Inspection and random UT measurements for damaged area 01.09.2018 01.09.2018 100% see photos
210000102793 EMC Workshop S DGS / R DGS Flowline TRU CM_ CHECK AND REPAIR TRU FOR CATHODIC PROTECTION SYSTEM 06.08.2018 80% Main overhaul in Workshop WMTL
110000134649 HIPF fire water tank TRU check short circuit in C.P system 28.08.2018 70%
110000134505 R DGS CP System 12 “ between Safwan to Rafidya DGS CHECK CATHODIC PROTECTION system and transformer 25.08.2018 31.08.2018 100%
C- Corrosion Activities
110000135655 HM ZB-075 @ North Manifold Site visit to assess the internal corrosion of the deteriorated portion 31.08.2018 01.09.2018 100% see photos of uniform corrosion