Professional Documents
Culture Documents
Questionnaire On The Contractual Matters
Questionnaire On The Contractual Matters
1
Question 3: Is the contractor required to keep an allowance in the
Preliminary Items in his tender bid for the Provisional Sums inserted in the
tender by the Employer?
Question 4: What FIDIC says about the Contractor’s entitlement against his
Claims, if he failed to notify the claims in a timely manner.
The FIDIC has different provision for Time Claims and the Cost Claims.
For Time Claims, FIDIC says that the Engineer is not bound to make a
determination for an Extension of Time in case the Contractor failed to
fulfill his obligation of timely notification. RTA conditions say that the
Engineer shall not make a determination in case the contractor failed to
fulfill his obligation of timely notification.
For Cost Claims, the Clause 53.4 states that if the Contractor fails to
comply with the notice requirement, the Engineer shall still assess his
entitlement or the Arbitrator based on the contemporary awards.
2
Out of all the above, the courts and the Arbitrators internationally have
shown their preference to use Window Analysis method for delay claims.
The clause 49.2 (b) requires the Contractor to execute all such work of
amendment, reconstruction as the Engineer may instruct.
3
Question no. 7: What is a collateral warranty.
The collateral warranty is an agreement, which exists along side the main
contract between the parties which otherwise have no contractual links.
For example, if the Employer wants to have a separate contract with the
nominate subcontractor, he can have it by way of having a collateral
warranty.
But for the prolonged project, he could have reduced some of his
head office resources,
That his head office overheads increased to deal with the prolonged
project.